MSP MOROCCO S CONTRIBUTION Presented by Mr. ABDERRAHIM EL HAFIDI DIRECTOR OF ELECTRICITY AND RENEWABLE ENERGIES
OUTLINE I ENERGY SECTOR IN MOROCCO II NEW MOROCCO S ENERGY STRATEGY III MOROCCO: A R E G IO N A L O P P O R T U N IT Y FO R R EN EW ABLE EN ERG Y IV MSP: MOROCCO S PILOT PROJECTS
I ENERGY SECTOR IN MOROCCO
ENER G Y S EC TOR IN MOR OC C O CHARACTERISTICS Limited domestic Energy ressources: imports 97% Energy consumption in constant growth Total Consumption soared from 4.6 Mtoe in 1980 to 13.7 Mtoe in 2007 (5% /year; 2003-2007)) Electrical consumption boomed from 4 460 GWH in 1980 to 22 600 GWH in 2007 (8%/year; 2003-2007) Energy bill (2007) : 5.8 billion US$
Electricity cons umption 8,8% 9,0% 8,1% 8,0% 8,0% 7,0% 6,5% 6,5% 6,2% 7,1% 7,0% 6,0% 8% 5,8% 5,0% 5,1% 5,0% 4,0% 3,0% 3,2% 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007
II NEW ENERGY STRATEGY
NEW C HALLENG ES Growing energy demand : Economic and social development Growth of population with better revenues Steady high Energy prices Needs for huge investments to meet future demand Infrastructures Capacities Competitiveness of Moroccan economy in opened international markets Environmental issues.
. ÉVOLUTION DE LA C ONS OMMATION ET Unit of measure DE LA PUIS S ANC E APPELÉE Consommation (En TWH) Prise en compte de 10% de pertes réseau * ELEC TR IQUE 2008-2030 * Scenario de Base Scénario disruptif 133 140 120 100 95 80 61 60 40 34 31 24 20 0 2002 2004 2006 2008 2010 2012 La consommation nationale multipliée par à minima 4 et à maxima 6 entre 2007 et 2030 52 2014 2016 2018 2020 2022 2024 2026 2028 2030 Puissance appelée (En MW) 20 000 04/12/2008 La puissance maximale appelée estimée entre 12 000 et 20 000 MW La production multipliée par 3,5 04/12/2008 10 000 12 000 04/12/2008 6.000 04/12/2008 5.500 04/12/2008 2002 * 2004 2006 Footnote Source : Analyse de l équipe Source: Source 2008 2010 2012 2014 8 500 2016 2018 2020 2022 2024 2026 2028 2030
NEW ENER G Y S TR ATE G Y Security of supply by diversification of energy sources and resources Accessibility of energy for all at the best cost Sustainable development Regional integration
INS TITUTIONAL R E FOR MS Self Production Encouragement : new limit at 50 MW Energy Efficiency and Renewable Energies Law Project (regulation, Open access, exportation Labeling, Energy Audits, fiscal and finance incentives) RE & EE Support Fund, leverage mechanism Evolvement of CDER toward National Agency for EE & RE Promotion in charge of Programs Implementation New Electricity law in study
III MOROCCO A R E G IO N A L O P P O R T U N IT Y F O R R EN EW ABLE EN ER G Y
S T R O N G R E G IO N A L IN T E R C O N N E X IO N ESPAGNE Morocco Spain : 700 MW (97) to 1400 MW (06) Morocco Algeria : 400 MW (88/92) to 1200 MW PINAR DEL REY TARIFA MEDITERRANNEE FARDIOUA TANGER PARC EOLIEN 140 MW MELLOUSSA TETOUAN 1 er CC TAHADDART 400 MW LOUKKOS IMZOURNEN ATLANTIQUE SELOUANE + SONASID + GHAZAOUAT + TELEMCEN + FOUARAT OUJDA BOURDIM + + + OUALILI A.FASSI JERADA DOUYET RIAD ALGERIE + AL WAHDA Cle KENITRA + H.AMEUR TOULAL EL OUALI ZAER TAZA SEHOUL Founding member of the COMELEC Fourth player on the OMEL since 1999 The sole southern Mediterranean interface to the UCTE (Union for the Co-ordination of Transmission of Electricity ) IME2
AS S ES TS FOR R ENEWAB LE ENER G IE S Wind Potential 10000 MW Solar Potential 5KWH/m2/day Biomass Potential
W IN D P O T E N T IA L : O V E R 1 0,0 0 0 M W 300 300 300 150 300 500 1000 500 1000 1500 500 400 10 0
S OLAR POTENTIAL MAP OF MOR OC C O Potential 5 kwh/m2/day Feasible Potential 2020 PV 1 080 MWc CES 1 700 000 M² CSP 400 MW 3 Millions TCO2/year avoided 925 Thousand Tep/an saved
B IOMAS S POTENTIAL Biomass : Unknown Potential Feasible Potential 2020 950 MW electric 2 Billions Euro Investis. 4.8 Millions T/year CO2 avoided 16
R enewable Energ ies : Hig h priority 10% in the energy balance 20% in the power generation KINGDOM OF MOROCCO -
IMPLEMENTED WIND FAR M POWER INSTALLED 123,5 MW Wind Farm Power implemented speed CED-Tetouan 50 MW Aug 2000 11 m/s Koudia El Badia 3.5 MW March 2001 11 m/s Lafarge-Tetouan 10 MW sept 2005 11 m/s Essaouira 60 MW April 2007 9.5 m/s
G R ID C ONNEC TED R NE PR OJEC TS IN DEVELOPMENT 2012 Projects Power Expected Tanger 140 MW 2009 Tarfaya 300 MW 2010 AUTOPRODUCERS 1000 MW 2012 Total Wind 1440 MW Ain Beni Mathar 20 MW WIND SOLAR 2009
OFF-G R ID DEC ENTR ALIS ED R ENEWAB LE ENER G IES PR OG R AMS Solar photovoltaic 150 000 Homes electrified PERG Solar Thermic (PROMASOL) 200 000 m² solar collectors installed
IV M O R O C C O S P IL O T P R O J E C T S
MOR OC C O S PILOTS PR OJEC TS : 450 MW Projects Power Technology OUJDA.ABM 125 MW CSP OUARZAZATE 100 MW CSP TAN TAN 15 MW CSP FIGUIG 10 MW PV BOUJDOUR 10 MW PV City Eco 50 MW PV NAREVA 2x10 MW PV/CSP WIND TOUAHAR.TAZA 100 MW BIOMASS CDER 20 MW SOLAR
WIND FARM TOUAHAR de 100 MW Tanger Solar Power Plant 125 MW CSP A ECO CITY 50 MW PV Lkhyayta Ouarzazate 15 MW CSP: Desalination TanTa Solar Power Plant 10 MW PV TAZA n 100 MW CSP/PV OUJD ABM Solar Power Plant 10 MW PV g Figui 20 MW biomass Boujdour MSP M O R O C C O S P IL O T P R O JE C TS
M S P : M o r o c c o 's c o n tr ib u tio n T h in k M o r o c c o, T h in k R e g io n a l www.mem.gov.ma Onhym.com mem.gov.ma 24