T2S PROGRAMME OFFICE Connecting to T2S Technical Session June 25 th, 2014 2010 Colt Telecom Group Limited. All rights reserved.
Agenda Connecting to T2S Overview Onboarding Phase NSP Support User Testing Weekends for Testing (Pre)-Migration Phase Technical Session Page 2
Connecting to T2S Overview Delivery Onboarding User Testing Migration Go Live Dedicated Project Manager Project Team NSP appoints a dedicated Project Manager for the T2S Actor NSP Project Manager and the project team provide support to T2S Actor from Delivery to Go-Live Ad-hoc documentation and manuals available to support activities Onboarding phase envisages: 1.Entity and Users registration 2.Certificate enrolment 3. T2S Registration 4. Set-up readiness Technical Session Page 3
Connecting to T2S Onboarding Phase (1/2) Entity and Users registration 1.Entity and Users registration 2.Certificate enrolment 3. T2S Registration 4. Set-up readiness Registration of the T2S Actor entity in the NSP systems Definition of Technical Address(es) Appointment of the roles through the NSP web portal Client Administrator (CA) responsible for registering users and assigning their relevant role Client Security Officer (CSO): responsible of all security aspects (e.g. CGU subscription, certificates request..) Certificate enrolment 1.Entity and Users registration 2.Certificate enrolment 3. T2S Registration 4. Set-up readiness Appointment of relevant roles to establish the certificates chain of trust Enrolment process for U2A End Users and A2A Application certificate based on electronic workflow on NSP PKI portal Technical Session Page 4
Connecting to T2S Onboarding Phase (2/2) T2S Registration 1.Entity and Users registration 2.Certificate enrolment 3. T2S Registration 4. Set-up readiness Registration to T2S User Testing environment by submitting the specific form to T2S Service Desk Subscription to the Closed Group of Users (CGU) through the NSP web portal workflow A2A Provisioning: implementation of the A2A addressing configuration U2A End Users appointment: authorization procedure for T2S Actor users to access the required CGU Set-up readiness 1.Entity and Users registration 2.Certificates enrolment 3. T2S Registration 4. Set-up readiness Activation of the configuration on the Messaging Interface and Network Gateway to enable the exchange of messages Technical Session Page 5
Agenda Connecting to T2S Overview Onboarding Phase NSP Support User Testing Weekends for Testing (Pre)-Migration Phase Technical Session Page 6
NSP Support User Testing SIA-Colt Help Desk is available to collect requests for support/issues Communication channels: web portal, telephone or email Service Desk available on 24x7 basis Dedicated Project Manager as additional contact point for T2S Actor Project Team to support issue investigation and resolution User Testing Weekend for Testing Project Manager Project Team Migration Phase L2 and L3 extended support Help Desk Technical Session Page 7
NSP Support Weekend for Testing NSP infrastructure is available for testing activities for the following: dress rehearsal migration weekends (DRMW) end-to-end volume test weekends Normal maintenance windows (Sat 5pm to Sun 8am) are cancelled for DRMW User Testing Weekend for Testing Migration Phase Special support with Level-2 and Level-3 specialists available Level-3 on call support Level-2 on site support from NSP premises during an agreed timeframe Project Manager Help Desk Project Team L2 and L3 extended support Technical Session Page 8
NSP Support (Pre)-Migration Phase Tailored support for production environment set-up migration from test environment to production environment final configuration and tuning on-site support for the first days after the initial Go-Live Infrastructure readiness checks Support during Migration Weekend User Testing Weekend for Testing Migration Phase Special support with Level-2 and Level-3 specialists available Level-3 h24 on call support Level-2 on site support from NSP premises during an agreed timeframe Project Manager Help Desk Project Team L2 and L3 extended support Technical Session Page 9
The End Thank you! Contact: Paolo Piangerelli T2S Project Manager paolo.piangerelli@sia.eu Technical Session Page 10
Q&A Question & Answer Technical Session Page 11