The Future in Fire Protection and Life Safety Cx. David J. LeBlanc, PE, FSFPE



Similar documents
Commissioning of Fire Protection and Life Safety Systems. Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA

Electrical Systems Commissioning

NFPA 3 and 4 Commissioning and Integrated Testing of Fire Protection and Life Safety Systems. Matt Klaus Senior Fire Protection Engineer NFPA

CAN/ULC S Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning

Guide Specification SECTION COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY

NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES. Level III Content Outline

REAL OPERATING COST SAVINGS FROM RETRO- COMMISSIONING OPPORTUNITIES FOR SAVINGS IN ACADEMIC MEDICAL CENTERS

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.

NFPA Edition Fire dampers shall be permitted to be installed in exhaust systems in the following situations:

Energy Design Resources Commissioning Plan Outline Template

Rhode Island State Fire Marshal Fire Protection Systems Narrative Reports. What is a Narrative Report?

Commissioning and Maintenance: Two Sides of the Same Coin? Kristin Heinemeier, PE, PhD Principal Engineer UC Davis WCEC

SUPPLEMENTAL TERMS AND CONDITIONS TO STATE FORM SC-5.1TC ARCHITECT/ENGINEER AGREEMENT TERMS AND CONDITIONS DESIGN/BID/BUILD

Data Center Commissioning: What you need to know

Amendments to the 2012 INTERNATIONAL FIRE CODE

SECTION TESTING, ADJUSTING, AND BALANCING

SECTION FIRE ALARM AND DETECTION SYSTEM

FLORIDA ATLANTIC UNIVERSITY FIRE ALARM SYSTEM INSTALLATION MANUAL

ARE YOU READY FOR THIS RISK ASSESSMENT IN THE CODES?

COMMISSIONING OF FIRE ALARM SYSTEMS

Sample Company SECTION GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES

Commissioning of Mission Critical Facilities

Building Codes Update: The 2009 International Fire Code and the Apartment Industry

Understanding Fire Alarm Requirements & Inspections. Presented By Bill Conroy Technical Sales For Briscoe Protective Systems Inc

Sam Docknevich, PSP, Security Service Portfolio Manager. Are You Prepared? The impending impact of Code on Servicing Security Systems

CLARK COUNTY FIRE DEPARTMENT Fire Hazard & Prevention Services

FIRE ALARM SYSTEM RECORD OF COMPLETION

FIRE ALARM SYSTEM RECORD OF COMPLETION

Denver International Airport Data Center Commissioning Plan

Fire Alarm and Protection Impairment Policy and Procedures

The Mission Critical Fire Protection Experts

Winnipeg Fire Department Fire Prevention Branch

POSITION STATEMENT THE ENGINEER AND THE ENGINEERING TECHNICIAN DESIGNING FIRE PROTECTION SYSTEMS. July 28, 2008

Chilled Water System Commissioning: Variable Primary Flow. John D. Villani, P.E. Associate Grumman/Butkus Associates

Module 4, Lesson 12 Fire Alarm Systems

COMMONWEALTH OF MASSACHUSETTS STATE BUILDING CODE 780 CMR, 6 th Edition FIRE PROTECTION SYSTEMS CHAPTER 9

Overview of Hotel Fire Safety Requirements

INSPECTION, TESTING AND MAINTENANCE OF FIRE PROTECTION SYSTEMS AND EQUIPMENT

NEW YORK CITY FIRE DEPARTMENT

FIRE ALARM AND EMERGENCY COMMUNICATION SYSTEM INSPECTION AND TESTING FORM

Cx Contracts: Liability, Indemnity, Insurance. Bruce Pitts, CPMP, CSBA, LEED AP Ujjval Vyas, PhD, JD

NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES Fire Alarm Systems

FIRE ALARM /FIRE PROTECTION OUTAGE/IMPAIRMENT RESPONSE GUIDELINE

CITY OF PHILADELPHIA DEPARTMENT OF LICENSES AND INSPECTIONS ANNUAL CERTIFICATION FOR FIRE ALARM SYSTEMS

DELAWARE STATE FIRE MARSHAL FIRE ALARM SYSTEM CERTIFICATE OF INSTALLATION

Life Safety Code Enabling References

TAMARAC FIRE RESCUE INSTRUCTIONS FOR FIRE ALARM PRE-SUBMITTAL CHECKLIST

A Guide to Renovation and Repair Contract Warranties

INSTRUCTIONS FOR BUILDINGS WITH FIRE PROTECTION EQUIPMENT

908.7 (New) [IBC [F] (New)], (New), Chapter 47 (IBC Chapter 35)

Inspection, Testing and Maintenance

The Life-Cycle of Commissioning for New Construction

AETNA FIRE ALARM SERVICE CO., INC.

Program No Section Heading

The Building Commissioning Association

Global Leaders in Fire Engineering. Company Overview. Finding simple solutions to complex problems.

Design Options (Tradeoffs) Allowed by the 2012 Building Codes for Properties with Sprinkler Systems. April 2013

2.4 Protected Elevators For Egress And Access During Fires In Tall Buildings

1. The objective of this guideline is to provide minimum standards for design and installation of fire alarm systems for the University of Missouri.

ALBERTA FIRE CODE SAFETY EQUIPMENT MAINTENANCE REQUIREMENTS

Fire Alarm and Detection Systems And Central Station Monitoring Plan Submittal Guidelines

1.0 General. Inspection, Testing, and Maintenance 1 of 8

Design Guidelines for Facilities Construction:

New York City Department of Buildings

Requirements for Fire Protection of Light Weight Floor Systems **Act 1 Revisited**

Certification. Kitchen Exhaust Cleaning and Certification Manual 2 ~ Certification. Table of Contents

Cx for the Forgotten Resource: Water. Daniel Forino, PE, LEED AP BD+C

NFPA 72. Exception No. 1: Where ambient conditions prohibit installation of automatic smoke detection, automatic heat detection shall be permitted.

Miami Beach Building Department

Health Chapter ALABAMA STATE BOARD OF HEALTH ALABAMA DEPARTMENT OF PUBLIC HEALTH ADMINISTRATIVE CODE

BUILDING INSPECTORS INSPECTION FORM FOR CHILD CARE CENTERS

to Commissioning The Strategic Guide Report from the ASHRAE Presidential Ad-Hoc Committee Building Performance Alliance on Commissioning

FIRE-FIGHTING DESIGN BRIEF REPORT

HVAC INSTALLATION SUCCESS WITH 2012 IECC DELAWARE. for Builders & Trades. Recommended Practices for Optimized Energy Savings

LIFE SAFETY UPDATE. FULL SPRINKLERING OF ALL NURSING FACILITIES ADDITIONAL CLARIFICATIONS Prepared by Eric Rosenbaum, P.E. Hughes Associates, Inc.

Fire Alarm System Plans Submittal Guidelines For New and Existing Systems

EXHIBIT A SCOPE OF WORK

Code Requirements for Existing Buildings

Fire-Rated Glass and Glazing START

FIRE SPRINKLER SYSTEM DESIGN, ENGINEERING EXEMPTION POLICY FOR (Effective April 1, 2006)

Fighting Fire in Sprinklered Buildings. Student Guide

HERNANDO COUNTY FIRE ALARM GUIDELINES

NATIONAL FIRE ALARM AND SIGNALING CODE

SARATOGA FIRE DISTRICT EARLY WARNING FIRE ALARM SYSTEM STANDARDS AND REQUIRMENTS CONTENTS

Jeff Sloan, P.E., McKinstry Co. Wednesday, April 29

City of Columbus Department of Building and Zoning Services

Transcription:

The Future in Fire Protection and Life Safety Cx David J. LeBlanc, PE, FSFPE

AIA Quality Assurance The Building Commissioning Association is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES for AIA members. Certificates of the Completion for both AIA members and non-aia members are available upon request. This program is registered with AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation. 2

Learning Objectives 1. Understand the NFPA 3 Cx process for Fire Protection and Life Safety Systems. 2. Understand the critical difference between Commissioning and acceptance testing for Fire Protection and Life Safety Systems. 3. Identify the role of the Fire Commissioning Agent (FCxA) and how they integrate with the full building commissioning team and Commissioning Authority (CxA). 4. Understand the difference between Commissioning (NFPA3) and Integrated Testing (NFPA 4) for Fire Protection and Life Safety Systems. SPEAKERS: Learning Objectives must indicate what attendees will do (not simply understand or learn ) with your information. Read About Learning Objectives Required for AIA Continuing Education Credit: www.aia.org/education/providers/aiab040189?dvid=&recspec=aiab040189 3

Overview Commissioning - NFPA 3 Terminology Integrated Testing - NFPA 4 ICC Commissioning Standard Importance of Cx F&LS Case Studies Lessons learned Re-Cx vs. Retro-Cx review Wrap-Up/Questions 4

NFPA 3 Commissioning and Integrated Testing of Fire Protection Systems Commissioning A systematic process that provides documented confirmation that building systems function according to the intended design criteria set forth in the project documents and satisfy the owner s operational needs, including compliance with applicable laws, regulations, codes, and standards. 5

Terminology Fire Protection Industry-term Commissioning utilized incorrectly. Acceptance Testing with Engineer or local Building/Fire Department is often incorrectly termed Commissioning. Commissioning is a systematic process not just a test. NFPA3 should help with Terminology. ACCEPTANCE TESTING COMMISSIONING Integrated Testing Agent (ITA) NFPA 4 new term 6

NFPA 3 & 4 Updates 2012 Edition NFPA 3 is Recommended Practice 2012 Edition NFPA 3 contains both Commissioning & Integrated Testing of Fire Protection and Life Safety Systems 2015 Edition of NFPA 3 only contains Commissioning New NFPA 4 (2015 Edition) is a Standard and only deals with Integrated Testing Future NFPA 3 moving to Standard 7

Key Stakeholders Owner Architect / Engineer Commissioning Agent (CxA) if overall building commissioning Fire Commissioning Agent (FCxA) Integrated Testing Agent (ITa) Contractor Subcontractors Registered Design Professionals (RDP) Authorities Having Jurisdiction (AHJ) 8

Key Documents Owner s Project Requirements (OPR) Basis of Design (BOD) Commissioning Plan Integrated Testing Plan Commissioning Record Document 9

NFPA 3 & 4 Qualifications Qualified FCxA and ITa required Advanced knowledge & experience in installation and operation of systems Advanced knowledge & experience in installation, operation, and interfaces between the various systems 10

NFPA 3 New and Existing Buildings Commissioning is done on new buildings or new systems. Re-commissioning (RE-Cx) is commissioning of existing systems that were previously commissioned. Retro-commissioning is commissioning of existing systems that were not previously 11

ICC Update ICC publishes the set of International Codes IBC & IMC ICC Draft ANSI Commissioning Standard ICC 1000 Public Comment Period Ended April 30, 2015 Current form ICC 1000 is vague, but covers all systems NFPA submitted Public Comment 12

Large F& LS Commissioning Projects 13

Importance of Commissioning Fire Protection and Life Safety Systems Many fire protection systems sit dormant until emergency conditions Life safety systems are essential in protecting occupants, contents of, and the building itself and notifying occupants during emergency conditions Owners are legally obligated to have properly functioning fire protection systems and to maintain and test these systems. The complex integration of fire protection systems is at an all time high Non-commissioned or improperly commissioned fire protection systems are a liability for owners and commissioning firms. 14

Case Study Existing High Rise Building with an Atrium Smoke Control System and Stair Pressurization System. Building occupied for years with areas of the building were getting renovated. Lack of documentation and no evidence it was commissioned resulted in a thorough test of the system to verify installation, operation, and performance. One test scenario was to simulate a transfer to emergency power for entire building during heavy load, including smoke control systems, fire pumps, and fire alarm systems all running under normal power to verify it continued to perform and that the transfer to emergency generator worked. 15

Result Under normal power systems activated properly, but on emergency power transfer all of the dampers closed, even though some were suppose to be open. Smoke control fans were on emergency power, but all the dampers were on normal power and failed safe close upon loss of power. 16 21 st NCBC Conference

Lessons Learned 1. Emergency/Standby power critical for fire protection and life safety systems. 2. Showcased importance of proper Commissioning and Retro- Commissioning 3. Highlighted importance of integrated test plans 4. Systems need to properly function in various conditions, not only ideal normal conditions. 5. Existing fire protection and life safety systems are many times not properly configured, coordinated, integrated, or commissioned. 17 21 st NCBC Conference

Case Study Relatively new Low-rise large building with Atrium smoke control system. Actual fire outside of Atrium activated non-atrium sprinkler water flow in a remote area of building Atrium smoke control system activated in real life (not suppose to per basis of design and project/owner objective). 18 21 st NCBC Conference

Result Smoke from remote area of building was dragged through the building causing extensive damage and clean-up. Improperly configured smoke control sequence did much more harm 19 21 st NCBC Conference

Lessons 1. Improperly configured systems not only not helpful, can cause more problems. 2. Need comprehensive test scenarios and when systems should activate, but also when they should not activate. 3. Proper Commissioning of fire protection and life safety systems critical for proper orientation. 4. Non-Commissioned systems have significantly increased rate of not properly functioning and possibly doing more harm putting occupants, property, and the building at risk from fire and life safety. 20 21 st NCBC Conference

Case Study New High-Rise Hotel with Pressurized Stairs, Fire Pump, Fire Alarm System, Emergency Lighting, and other Systems on the Emergency Generator Emergency generator was tested prior to all the systems were completed and connected to the emergency generator and signed off. Generator was properly sized to accommodate load As part of life safety systems test a full load on emergency generator was done with the smoke control system, fire pump, fire alarm system, emergency lighting, and other systems running. 21 21 st NCBC Conference

Result During life safety test transfer to emergency generator the generator tripped out. All systems in the building went down with no power and dark no lighting (night test) Generator had capacity but not properly balanced and configured as other systems were added to the emergency generator load. 22 21 st NCBC Conference

Lessons Learned 1. Need to commission systems when they are first brought online, but also after other systems are finished. 2. Importance of Commissioning to identify and resolve problems. 23 21 st NCBC Conference

Importance of Commissioning Team Brought In Early New Construction Mixed-Use High Rise Project with A Smoke Control System Fire Protection Life Safety Commissioning Team brought in late to the project after much of the system were installed. Systems and smoke control shafts were constructed, sealed, and painted. Required duct leakage test was never conducted prior to sealing shafts. 24 21 st NCBC Conference

Results Smoke control system could not meet performance of.10 inch water gauge pressure differential. Leaky duct was the culprit, which would have been identified if the duct test was conducted. Had to take down the drywall shaft for entire building to fix the duct work, conduct duct test, and replace shaft and paint. Additional cost and schedule impact. 25 21 st NCBC Conference

Lessons Learned 1. Best to bring in Commissioning Team during the design phase. 2. Need to conduct commissioning testing and component verification at the proper installation point during construction. 3. Skipping Commissioning or improperly delaying steps most likely will cost you significantly more financially and impact schedule. 26 21 st NCBC Conference

David LeBlanc, PE, SFPE Vice President JENSEN HUGHES dleblanc@jensenhughes.com www.jensenhughes.com 508-620-8900 Thank You!