Project Scheduling and Control Procedures
|
|
|
- Lillian Goodman
- 10 years ago
- Views:
Transcription
1 Project Scheduling and Control Procedures Document Number Revision 0 Approved By Ric Morris (Acting Director) DHQ, Stations August 30, 2001 Active Divisions/Departments FEMC Raytheon Polar Services Company HARD COPY NOT CONTROLLED-CONTROLLED COPY AVAILABLE ONLINE
2 Table of Contents Table of Contents... i Purpose... 1 Scope/Applicability...1 Responsibilities... 1 Director, FEMC... 1 Manager, Planning and Controls... 2 Manager, FEMC... 2 Construction Coordinator... 2 Manager, Engineering... 3 Project Engineer... 3 Scheduler... 4 FEMC Assistant Manager, Materials... 4 Procedures... 4 Master Schedule... 4 Engineering and Procurement Schedule (EP)... 5 Construction Schedule... 5 Distribution/Use... 5 References... 5 Records... 5 i
3 Purpose To create, maintain, and publish an integrated system of schedules that coordinate engineering, procurement, shipping, and construction activities or tasks. Scope/Applicability This procedure applies to all projects assigned and undertaken by the Facilities Engineering, Maintenance and Construction Division (FEMC), Raytheon Polar Services Company (RPSC). Responsibilities Director, FEMC Assures that this procedure is implemented for all engineering and construction projects. Reviews and approves all schedules prior to release to the NSF or other organizations. Reviews and approves all resource and cost loading in schedules prior to use. Reviews all schedules and approves options to minimize the impact of schedule deviations on planned cost and performance. Interfaces with the National Science Foundation (NSF) on all scheduling matters. Page 1 of 5 pages
4 Manager, Planning and Controls Supervises the establishment of standard procedures for creating and maintaining schedules. Supervises the creation of schedules. Reviews all schedules for accuracy and consistency. Develops and supervises the implementation and execution of the cost and performance reporting systems. Reviews the reporting systems for accuracy and reasonableness. Manager, FEMC Reviews construction schedules for completeness and accuracy. Establishes manpower allocations and activity duration for all construction schedules. Approves projected deviations from Engineered Standards. Establishes the format and frequency of construction schedules. Approves selected options to reduce the impact of deviations from the schedule. Provides actual performance data to the Project Control Office through schedule updates. Construction Coordinator Assists the scheduler with the creation of construction schedules. Performs a detailed review of the schedule for construction logic and reasonableness. Reviews manpower allocations and activity duration for all construction activities. Supervises project execution to ensure adherence to the schedule to the extent possible. Reports deviations from or additions to the schedule to the Manager, FEMC, and the Project Scheduler. Page 2 of 5 pages
5 Utilizes construction schedules to determine deviations from planned cost or performance and evaluates options to minimize impacts. Provides actual performance data to the Project Controls Office. Manager, Engineering Coordinates the gathering of project information prior to schedule preparation, including the Engineering Project Definitions (EPD), design drawings, and resources. Reviews Engineering and Procurement (EP) schedules for accuracy and reasonableness. Assigns resource allocations and activity duration for engineering and design schedules. Establishes the format and frequency of engineering and design schedules. Coordinates and reports deviations from the schedule to the Project Controls Office. Reports actual cost and performance data to the Project Control Office. Project Engineer Provides engineering requirements to the Engineering Manager and Scheduler. Assists the Construction Coordinator/Supervisor and the Scheduler by identifying relevant engineering standards and evaluating the need for planned deviations from those standards. Reviews the construction schedule for integration of logic. Provides accurate schedule updates to the Master and Engineering, Construction, and Procurement schedules for engineering and design activities. Utilizes the published schedules to detect deviations from planned performance of engineering design that affect procurement and construction activities, and to recommend options to reduce impacts. Assists the scheduler to interpret the plans and specifications. Page 3 of 5 pages
6 Scheduler Creates cost and resource schedules with input from the Estimator, Engineering Manager, and Construction Management. Maintains compatible baseline and as-built schedules to provide comparative data between planned and actual costs and between schedules and productivity performance. Provides projected resource requirements from the scheduling system to the Manager, FEMC, and the Engineering Manager. Provides schedules as required by the Manager, FEMC, and the Engineering Manager, to ensure early warning of deviations from planned performance. FEMC Assistant Manager, Materials Assists the scheduler by identifying needed procurement and logistics activities and estimating the activity duration. Provides continuous tracking of procurement and logistics activities for schedules and immediately notifies the scheduler of deviations from planned cost or performance. Procedures This procedure will be used to produce 3 types of schedules: Master Schedule, Engineering, Procurement (EP) Schedules and Construction Schedules. Master Schedule The Master Schedules are used for total project planning of SPSE and SPSM and to summarize detailed engineering, procurement, and construction. The Master Schedule is resource and cost loaded based upon the package summary of the detailed Final estimate. It outlines the start, execution, and completion of a project. Milestone activities are shown as well as engineering, design, procurement, logistics, and construction activities. The Master Schedule summarizes the EP and Construction Schedules to facilitate management review. Updates and reporting to the client occurs as required by the client. Page 4 of 5 pages
7 Engineering and Procurement Schedule (EP) An EP Schedule is prepared immediately upon authorized inclusion of a project in the Annual Program Plan. This schedule defines the activities necessary for timely commencement of the detail engineering and design functions. This schedule details in weeks the production of engineering reports, design drawings, material procurements, and construction efforts. The ECP is updated and statused weekly. Construction Schedule The Construction Schedule is developed from the detailed estimate. The estimate work packages are incorporated into construction activities based upon logical criteria not necessarily comparable with Engineered Standards. It is resource and cost loaded using mandays, and can be summarized using hammock and milestone activities. The Construction Schedule is updated and statused weekly and functions as a basis for the Program Plan development. Distribution/Use The schedules are intended as planning and control schedules for use internally by RPSC. The schedules will not normally be distributed outside RPSC. The Director of FEMC, the Manager of Engineering, or the Manager of SPSM may provide copies of schedules to the National Science Foundation as required. References Engineering Project Definitions (EPD) (EN-D-200) Records This procedure generates no records. Page 5 of 5 pages
Engineering Documents in Expedition
Engineering Documents in Expedition Document Number Revision 0 Approved By Wayne L. Cornell, PE January 10, 2006 Active Divisions/Departments Raytheon Polar Services Company Facilities, Engineering, Maintenance,
Pressure Testing Procedures for Pipelines
Pressure Testing Procedures for Pipelines Document Number Revision 2 Approved By Ric Morris McMurdo, Palmer, and South Pole November 11, 2004 Active Divisions/Departments FEMC Raytheon Polar Services Company
FEMC Document Control
FEMC Document Control Document Number Revision 7 Approved by Wayne L. Cornell, PE Posting Date- April 10, 2006 Active Divisions/Departments FEMC Raytheon Polar Services Company Owning Division or organizational
Pressure Testing Procedures for Building Services Piping
Pressure Testing Procedures for Building Services Piping Document Number Revision 0 Approved By Ric Morris McMurdo, Palmer, and South Pole February 25, 2005 Active Divisions/Departments FEMC Raytheon Polar
Facilities Maintenance Work Order Procedures
Facilities Maintenance Work Order Procedures Document Number Revision 2 Approved by Ric Morris 09/14/05 Active Divisions/Departments FEMC Raytheon Polar Services Company Facilities, Engineering, Maintenance,
Water System Disinfection
Water System Disinfection Document Number Revision 1 Approved By Ric Morris All 6/2/04 Active Divisions/Departments FEMC Raytheon Polar Services Company HARD COPY NOT CONTROLLED-CONTROLLED COPY AVAILABLE
PROJECT CONTROL PROCEDURE (PROJECT STANDARDS AND SPECIFICATIONS)
TABLE OF CONTENTS Page 1 of 18 PURPOSE 2 SCOPE 2 DEFINITION 2 ORGANIZATION AND RESPONSIBILITIES 2 Organization and Function 2 Integration of Control Functions 5 7 Introduction 7 Planning and Scheduling
HAPE Treatment Guidelines
HAPE Treatment Guidelines Approved by Version Number 0 16 December 2006 Active Divisions/Departments (McMurdo, South Pole) Raytheon Polar Services Company Medical Department Hard Copy Not Controlled Controlled
Project Control System Manual. Jefferson Science Associates, LLC. 600 Progress Status. Project Control System Manual Revision 7 - 44 -
Jefferson Science Associates, LLC 600 Progress Status Project Control System Manual Revision 7-44 - 600 Progress Status This chapter of the JSA Project Control System Manual explains how the status of
Table 2-1: Elements of the Project Management Plan
2 PROJECT MANAGEMENT [NTA: DB Project Management requirements drop off at Project Opening and the O&M management requirements start. In Book 2A address projects that have periods of no DB or O&M Phase
ACE PROJECT M&E CONSULTANCY
ASSOCIATION OF AFRICAN UNIVERSITIES ASSOCIATION DES UNIVERSITÉS AFRICAINES ACE PROJECT M&E CONSULTANCY BACKGROUND The Association of African Universities has received financing from the World Bank toward
Best Practices for Print Service Management. Best Practices in Open Print Management
Best Practices for Print Service Management Best Practices in Open Print Management Best Practices for Print Service Management Plan Design Measure Analyze Improve Control 1. Develop and maintain a print
Project Management Guidelines
Project Management Guidelines Overview Section 86-1506 (5) directs the NITC to adopt guidelines regarding project planning and management. The goal of project management is to achieve the objectives of
IT1T Integrated Recruitment Systems 2015
UCD IT Services IT1T Integrated Recruitment Systems 2015 Project Initiation Document Version 1.0 2 December 2014 Version History Version Date Summary of Changes Changed by 1.0 02/12/2014 Initial Draft
Software Quality Subcontractor Survey Questionnaire INSTRUCTIONS FOR PURCHASE ORDER ATTACHMENT Q-201
PURCHASE ORDER ATTACHMENT Q-201A Software Quality Subcontractor Survey Questionnaire INSTRUCTIONS FOR PURCHASE ORDER ATTACHMENT Q-201 1. A qualified employee shall be selected by the Software Quality Manager
Project Management Fact Sheet:
Project Management Fact Sheet: Steering Committee nuts and bolts Version: 1.2, November 2008 DISCLAIMER This material has been prepared for use by Tasmanian Government agencies and Instrumentalities. It
Scheduling Process Maturity Level Self Assessment Questionnaire
Scheduling Process Maturity Level Self Assessment Questionnaire Process improvement usually begins with an analysis of the current state. The purpose of this document is to provide a means to undertake
TECHNIQUES FOR MANAGING COMPLEX PROJECTS WITH PLANNING AND SCHEDULING SOFTWARE PAUL E HARRIS EASTWOOD HARRIS
P.O. Box 4032 EASTWOOD HARRIS PTY LTD Tel 61 (0)4 1118 7701 Doncaster Heights ACN 085 065 872 Fax 61 (0)3 9846 7700 Victoria 3109 Project Management Systems Email: [email protected] Australia Software
Template K Implementation Requirements Instructions for RFP Response RFP #
Template K Implementation Requirements Instructions for RFP Response Table of Contents 1.0 Project Management Approach... 3 1.1 Program and Project Management... 3 1.2 Change Management Plan... 3 1.3 Relationship
Chapter 5. Planning the Audit Engagement
Chapter 5 Planning the Audit Engagement A. Purpose for Planning the Engagement Engagement planning is performed to provide a means for developing an understanding of the business objectives of the auditee,
Section 100 Contractor Quality Control Program
7/21/2014 AC 150/5370-10G Section 100 Contractor Quality Control Program 100-01 General. When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and
Schedule analytics tool
Schedule analytics tool As capital project spend increases and aggressive deadlines are built into project schedules, the reliance on accurate, transparent and meaningful schedule practices is growing.
Construction Management Standards of Practice
Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388
10 Best Practices in Printer Fleet Management
10 Best Practices in Printer Fleet Management Corporations recognize that they need to address out of control costs associated with network printing. How do they get there? Many are looking to solve it
INTERIM SITE MONITORING PROCEDURE
INTERIM SITE MONITORING PROCEDURE 1. PURPOSE The purpose of this SOP is to describe the interim monitoring procedures conducted at Institution, according to GCP and other applicable local regulations.
1. Interpretation of this Schedule
Schedule 6 Programming Requirements 1. Interpretation of this Schedule 1.1 Primavera The following capitalised terms used in this Schedule 6 have the meanings given to them in the proprietary computer
Commonwealth of Massachusetts CommonWay Schedule Management Guidelines. Common Values - Common Goals Common Way. Schedule Management.
Schedule Management Values - Goals Schedule Management Schedule Management v1.0 1 of 6 10/27/2010 Schedule Management Values - Goals Table of Contents 1 Schedule Management Guideline... 3 1.1 Determine
Terms of Reference. Egypt Post - Several position: Architects, Interior Design, Structure Design, Site Engineer and Electromechanical Design.
Terms of Reference Duty Station: Type of contract: Title: Duration of the contract: Egypt Service Contract (Only Egyptians) Egypt Post - Several position: Architects, Interior Design, Structure Design,
Infrastructure Planning and Management. Phases of an Infrastructure Project
Infrastructure Planning and Management Phases of an Infrastructure Project Agenda Talking about the various phases in an infrastructure project Introduction to the Infrastructure Process Infrastructure
Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices
: A CDOT Guide to Better Project Management Practices Project Management practices have been a part of the CDOT culture for many years. However, with a transitioning workforce and increasing demands, it
PROJECT MANAGEMENT PLAN <PROJECT NAME>
PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
The Program Managers Guide to the Integrated Baseline Review Process
The Program Managers Guide to the Integrated Baseline Review Process April 2003 Table of Contents Foreword... 1 Executive Summary... 2 Benefits... 2 Key Elements... 3 Introduction... 4 IBR Process Overview...
Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 2014
for Inspecting and Certifying Buildings and Works Building Control Regulations 2014 February, 2014 Table of Contents 1. Introduction 1 1.1 Status and Purpose of Code 1 1.2 Overview of Code 1 1.3 Application
Consultancy Services Proposal
Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847
CATHOLIC UNIVERSITY OF HEALTH AND ALLIED SCIENCES - GUIDELINES FOR JOINT PHD PROGRAMMES
2014 CATHOLIC UNIVERSITY OF HEALTH AND ALLIED SCIENCES - GUIDELINES FOR JOINT PHD PROGRAMMES School of Graduate Studies 1/8/2014 Contents 1.0 Introduction... 3 2.0 Guidelines for Joint PhD Programs...
EMS Example Example EMS Audit Procedure
EMS Example Example EMS Audit Procedure EMS Audit Procedures must be developed and documented with goals which: Ensure that the procedures incorporated into the EMS are being followed; Determine if the
Project Management Competency Standards
BSB01 Business Services Training Package Project Management Competency Standards CONTENTS BSBPM401A Apply scope management techniques...3 BSBPM402A Apply time management techniques...8 BSBPM403A Apply
JOB ANALYSIS AND DESCRIPTION
JOB ANALYSIS AND DESCRIPTION 1. Importance of Job Analysis and Description Job analysis and job description are closely interrelated. The information gathered on each job through job analysis is subsequently
CCE-TRK-SPN-010 Specification for Movement Monitoring of Railway Track
Reference No. CCE-TRK-SPN-010 Version 1.0 Operative Date 02/08/2011 Status LIVE Prepared by Nick West, Colin Hedderly Checked by Cathal Mangan Approved by Éamonn Ballance CCE DEPARTMENT TECHNICAL SPECIFICATION
700 Analysis and Reporting
Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) Copyright: Australian Institute of Project Management Document Information Document
IT Asset Management. ProPath. Office of Information and Technology
IT Asset Management ProPath Office of Information and Technology Table of Contents IT Asset Management Process Maps... 1 Process: IT Asset Management... 19 IT Asset Management and Goals... 22... 22 Goals...
Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344
Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344 Table of Contents SERIES DEFINITION... 2 EXCLUSIONS... 2 OCCUPATIONAL INFORMATION... 3 TITLES... 6 EVALUATING
Release: 1. BSBPMG510A Manage projects
Release: 1 BSBPMG510A Manage projects BSBPMG510A Manage projects Modification History Not applicable. Unit Descriptor Unit descriptor This unit describes the performance outcomes, skills and knowledge
DATA PROTECTION POLICY
DATA PROTECTION POLICY DATA PROTECTION POLICY Document Control Information Title Data Protection Policy Version V1.0 Author Diana Watt Date Approved 21 February 2013 Review Date Annually, on the anniversary
Project Management Tools
Project Management Tools 1 Name: Subject: Professor: Date: Project Management Tools Project Management Tools 2 1. Introduction Project Management is a method of organizing and managing resources in strategic
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES. Level III Content Outline
Fire Alarm Systems Level III Content Outline The skills and knowledge listed under each task are suggestive of those involved in that task, but are not intended to constitute an exhaustive listing. 3.1
SCHEDULE AND BUDGETING
PROJECT CONTROLS The right combination of software management tools, proper initial project set-up, timely and accurate data input, continuous tracking of progress, a meaningful reporting structure, strong
DOCUMENT HISTORY LOG. Description
Effective Date: 02/26/2013 Page 2 of 16 DOCUMENT HISTORY LOG Status (Baseline/ Revision/ Canceled) Document Revision Effective Date Baseline 1.0 02/19/2003 Revision 1.1 03/12/2003 Description Revision
CRITICAL PATH METHOD (CPM) SCHEDULES
96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without
Contract / Construction Management. November 2006
Contract / Construction Management November 2006 Presentation Outline I. Introduction Project Management II. Contract/Construction Management Stage 1: Construction Period Stage 2: Defects Liability Period
Salmabad, Kingdom of Bahrain. COLLEGE OF ADMINISTRATIVE AND FINANCIAL SCIENCES (CAFS) Bachelor of Science in Business Informatics (BSBI)
Salmabad, Kingdom of Bahrain COLLEGE OF ADMINISTRATIVE AND FINANCIAL SCIENCES (CAFS) Bachelor of Science in Business Informatics (BSBI) Alumni Survey SY 2013-2014 Introduction AMA International University-Bahrain
2.0 OBJECTIVES OF THE CONSULTANCY SERVICE
TERMS OF REFERENCE FOR AN INDEPENDENT DATA BASE MANAGEMENT AND IT CONSULTANT TO PROVIDE PREPARATION AND IMPLEMENTATION SUPPORT FOR THE NEITI INDUSTRY AUDIT DATA MANAGEMENT SYSTEM (NIADMS) 1.0 BACKGROUND
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
Information Technology Engineers Examination. Network Specialist Examination. (Level 4) Syllabus. Details of Knowledge and Skills Required for
Information Technology Engineers Examination Network Specialist Examination (Level 4) Syllabus Details of Knowledge and Skills Required for the Information Technology Engineers Examination Version 2.0
Digital Archiving Survey
Digital Archiving Survey Background information Under the Public Records Act 2002 (the Act), public authorities have a responsibility to ensure that digital records under their control remain accessible
OFFICE OF PERSONNEL MANAGEMENT ATLANTA OVERSIGHT DIVISION ATLANTA, GEORGIA
OFFICE OF PERSONNEL MANAGEMENT ATLANTA OVERSIGHT DIVISION ATLANTA, GEORGIA CLASSIFICATION APPEAL DECISION Under section 5112(b) of title 5, United States Code Appellant: [the appellant] Position: Engineering
Pre Bid Notice. Rajeev Keskar G.M. (R.O.) MPPMCL, Bhopal 9425303923. Notice: GM/RO/314 Date 03/09/2015
Pre Bid Notice Subject: Outsourcing of selected Metering and Billing related activities for MPPoKVVCL, Jabalpur, MPMKVVCL, Bhopal and MPPaKVVCL, Indore. Notice: GM/RO/314 Date 03/09/2015 This notice is
CHAPTER 7: QUALITY CONTROL/QUALITY ASSURANCE ***DRAFT***
CHAPTER 7: QUALITY CONTROL/QUALITY ASSURANCE ***DRAFT*** CHAPTER 7: QUALITY CONTROL/QUALITY ASSURANCE... 1 SECTION 7.1 INTRODUCTION... 2 Subsection 7.1.1 Purpose... 2 Subsection 7.1.2 Scope... 2 Subsection
How To Manage Assets
INSTITUTE OF CERTIFIED PUBLIC ACCOUNTANTS OF KENYA ASSET MANAGEMENT SEMINAR SEPTEMBER 9 TH -11 TH, 2015 Asset Information Credibility. Professionalism. AccountAbility 1 Asset Information 2 Content 1. Stakeholders
ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution
A GUIDE TO THE PROJECT MANAGEMENT BODY OF KNOWLEDGE
A GUIDE TO THE PROJECT MANAGEMENT BODY OF KNOWLEDGE PMI Standards Committee William R. Duncan, Director of Standards Project Management Institute 130 South State Road Upper Darby, PA 19082 USA Library
Classification Appeal Decision Under Section 5112 of Title 5, United States Code
U.S. Office of Personnel Management Office of Merit Systems Oversight and Effectiveness Classification Appeals and FLSA Programs Atlanta Oversight Division 75 Spring Street, SW., Suite 972 Atlanta, GA
POLICY STATEMENT Commonwealth of Pennsylvania Department of Corrections
POLICY STATEMENT Commonwealth of Pennsylvania Department of Corrections Policy Subject: Policy Number: Project Management 1.1.5 Date of Issue: Authority: Effective Date: May 29, 2009 Signature on File
Fundamentals of Measurements
Objective Software Project Measurements Slide 1 Fundamentals of Measurements Educational Objective: To review the fundamentals of software measurement, to illustrate that measurement plays a central role
THE CITY OF NORTH LAS VEGAS REQUEST FOR INFORMATION FOR ASSET TRACKING & INVENTORY MANAGEMENT RFI# 06-30-09-01 RELEASE DATE: JUNE 30, 2009
THE CITY OF NORTH LAS VEGAS REQUEST FOR INFORMATION FOR ASSET TRACKING & INVENTORY MANAGEMENT RFI# 06-30-09-01 RELEASE DATE: JUNE 30, 2009 RESPONSES TO BE RECEIVED BY JULY 21, 2009 2:00 P.M. RETURN TO
MASSEY UNIVERSITY COLLEGE RESEARCH CENTRE AGREEMENT
MASSEY UNIVERSITY COLLEGE RESEARCH CENTRE AGREEMENT Agreement effective from: PARTIES: Between the Vice-Chancellor and the Pro Vice-Chancellor of the College of College of Sciences concerning the operation
Commercialization of Transport and Logistics Storage Logistics Supply Logistics Administrative Management of International Trade
EUROPASS DIPLOMA SUPPLEMENT TITLE OF THE DIPLOMA (ES) Técnico Superior en Transporte y Logística TRANSLATED TITLE OF THE DIPLOMA (EN) (1) Higher Technician in Transports and Logistics ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Project Manager (Renewable Energy) Terms of Reference
I. Position Information Project Manager (Renewable Energy) Terms of Reference Organization: Office of the Quartet (OQ) Title: Project Manager (Renewable Energy) Reports to: Energy Adviser Duty Station:
Timor- Leste. United Nations Development Programme. Vacancy Announcement
United Nations Development Programme Timor- Leste Vacancy Announcement Project Title: Strengthening Capacities for Disaster Risk Management in Timor Leste Post Title: National Administration and Finance
(UNOFFICIAL TRANSLATION)
Readers should be aware that only the original Thai text has legal force and that this English translation is strictly for reference. The Stock Exchange of Thailand cannot undertake any responsibility
Interim Terms of Reference for Consultancy Services
Interim Terms of Reference for Consultancy Services Design for the Centre of Excellence in Biomedical Engineering at the University of Rwanda, College of Medicine and Health Sciences, Nyarugenge Campus
Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A
Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A Programme Description: Dedicated one full day training module in a structured and professional manner to
Papua New Guinea LNG Project Environmental and Social Management Plan Appendix 21: Procurement and Supply Management Plan PGGP-EH-SPENV-000018-025
Esso Highlands Limited Papua New Guinea LNG Project Environmental and Social Management Plan Appendix 21: Procurement and Supply Management Plan PGGP-EH-SPENV-000018-025 LNG Project Page i of ii CONTENTS
Supporting Effective Evaluations: A Guide to Developing Performance Measurement Strategies
Home > Centre of Excellence for Evaluation Supporting Effective Evaluations: A Guide to Developing Performance Measurement Strategies 6.0 Performance Measurement Strategy Framework 6.1 Overview of the
SA Tool Kit release life cycle
Release management Release management process is a software engineering process intended to oversee the development, testing, deployment and support of software releases. A release is usually a named collection
Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive
Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86
D R A F T. Resource Ordering and Status System (ROSS) Software Configuration Management Guidelines
TO #GA81 Resource Ordering and Status System (ROSS) D R A F T Resource Ordering and Status System (ROSS) Software Configuration Management Guidelines June 28, 2000 Version 1.1 Contract: GS-35F-4863G Delivery
Operations. Group Standard. Business Operations process forms the core of all our business activities
Standard Operations Business Operations process forms the core of all our business activities SMS-GS-O1 Operations December 2014 v1.1 Serco Public Document Details Document Details erence SMS GS-O1: Operations
EXHIBIT 2-2-C PROGRESS SCHEDULES
EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,
EQR PROTOCOL 1: ASSESSMENT OF COMPLIANCE WITH MEDICAID MANAGED CARE REGULATIONS
OMB Approval No. 0938-0786 EQR PROTOCOL 1: ASSESSMENT OF COMPLIANCE WITH MEDICAID MANAGED CARE REGULATIONS A Mandatory Protocol for External Quality Review (EQR) Protocol 1: Protocol 2: Validation of Measures
Project Management Manual Update 2006. Transportation Department City of Edmonton
Project Management Manual Update 2006 Transportation Department City of Edmonton Project Management Manual for Transportation Projects EXECUTIVE SUMMARY This document has been updated to fulfill the requirements
Sound Transit Internal Audit Report - No. 2014-3
Sound Transit Internal Audit Report - No. 2014-3 IT Project Management Report Date: Dec. 26, 2014 Table of Contents Page Background 2 Audit Approach and Methodology 2 Summary of Results 4 Findings & Management