1 UCD IT Services IT1T Integrated Recruitment Systems 2015 Project Initiation Document Version December 2014 Version History Version Date Summary of Changes Changed by /12/2014 Initial Draft Bronwyn O Callaghan
2 Contents 1 Objectives & Scope Project Objective Project Scope Change Control 4 2 Project Plan Project Approach Milestone Plan 5 3 Project Structure Roles & Responsibilities Project Team Meetings 7 4 Risks & Issues Initial Risk & Issue Log Ongoing Management of Risks and Issues 8 5 Stakeholder Plan 9 IT15 Integrated Recruitment Systems Project Initiation Document Page 2 of 10
3 1 Objectives & Scope This Project Initiation Document (PID) defines a programme of work entitled Integrated Recruitment Systems 2015 and outlines its objectives, scope, approach, deliverables, timescale and structure so that it can be understood and agreed by all stakeholders. 1.1 Objective The objective of this programme of work is to provide support for the recruitment of students both undergraduate and postgraduate building upon the work completed in 2014 in support of the recruitment of non-eu students. 1.2 Scope This programme of work will cover the delivery of a series of projects including: Enhancement of the CRM capabilities implemented in 2014 in support of the recruitment of non-eu students as part of the Global Engagement Initiative. Enhancement of support for Recruitment Activities in the Graduate Space (in particular looking at how enquiries and leads for graduate programmes are managed) Onboarding of Graduate Students i.e. the time between when a graduate accepts in Mar/Apr/May and when they start to register in Aug/Sept. In particular, we are looking at the provision of an Onboarding Portal. Redevelopment of the Course Finder within the Graduate Studies Website working with Graduate Studies 1.3 Benefits The benefits of undertaking this programme of work include: Supporting more effective recruitment by providing systems support such as CRM etc. Optimising the conversion of prospective students from offer stage through to a registered student in UCD. Promotion of a more effective web presence for prospective students by providing highquality course information online. IT15 Integrated Recruitment Systems Project Initiation Document Page 3 of 10
4 1.4 Change Control The Project Initiation Document will be approved on commencement of the programme of work by the IT Services Management Team. Following this, an ongoing Project Plan will be maintained and updated to accommodate any minor changes that occur. Once the scope is agreed herein, any further changes to scope or major deviation from the proposed timeframes will be the subject of a change control procedure. IT15 Integrated Recruitment Systems Project Initiation Document Page 4 of 10
5 2 Project Plan 2.1 Project Approach The approach to this programme of work involves delivering independently a number of selfstanding projects which when combined will achieve the overall programme objectives. The exact details of each project and the timing of each will be subject to regular review throughout the year to ensure that the projects implemented reflect ongoing priorities and availability of staff in IT Services and each of the customer areas covered by the proposed projects. Each individual project will be managed based on the principles contained in our Project Management Methodology. 2.2 Milestone Plan Milestones, deliverables and target delivery dates for each of the constituent projects will be agreed with the relevant stakeholders. The typical milestones are outlined below. Milestone Deliverable Responsibility Reviewers/ Approvers 1 Project Initiation Document Approved 2 Requirements completed 3 Delivery of prototype 4 Completion of testing Project Initiation Document Summary Statement of Requirements Project Team Registry Liaison Group Due Date TBD Project Team Registry team TBD Working prototype Project Team Registry team TBD Test results document 5 Version 2 delivery Working prototype version 2 6 Completion of final testing Final test results document sign off 7 Go live System live, communications complete Project Team Registry team TBD Project Team Registry team TBD Project Team Registry team TBD Project Team Registry team TBD 2.3 Project Plan A project plan for each of the constituent projects will be developed prior to the commencement of the project. IT15 Integrated Recruitment Systems Project Initiation Document Page 5 of 10
6 3 Project Structure The programme comprises of a set of project teams with oversight by the one or more Steering (or existing Liaison) Groups to be defined. These Steering Groups will agree project schedules, approve major deliverables and resolve any critical issues that arise during the lifetime of this work programme. Project teams will be created to deliver each project and a project manager appointed to manage the project on a daily basis and will report regularly to the Steering Group. 3.1 Roles & Responsibilities Role Responsibilities Names Steering Group(s) Ensure that the project direction is appropriate to the achievement of the ultimate objectives Review progress reports from the Project Manager and determine actions needed to address deviations Provide guidance to the Project Team on high level principles to be complied with Review and approve deliverables Monitor and proactively manage risks as they arise. tbd Project Sponsor Ensure that resources are provided as required for the project tbd Take action on any issues escalated by the Project Team Project Manager Prepare the Project Plans Determine resource requirements and ensure that appropriate resources are allocated Bronwyn O Callaghan Manage the project to ensure that the desired results are achieved within agreed time-scales Monitor progress and report on a regular basis to the Steering Committee Prepare project deliverables and their presentation for approval Project Conduct the tasks and activities of the Various (dependent on IT15 Integrated Recruitment Systems Project Initiation Document Page 6 of 10
7 Role Responsibilities Names Team project in accordance with the Project Plan Prepare the project deliverables by the agreed due dates Report progress to the project) 3.2 Project Team Meetings The following are the scheduled project governance meetings: Team Attendees Frequency Steering Groups (s) Project Team tbd Project Team Members Monthly At least weekly for the duration of each individual project IT15 Integrated Recruitment Systems Project Initiation Document Page 7 of 10
8 4 Risks & Issues 4.1 Initial Risk & Issue Log The following project risks or issues have been identified on commencement of the project. These initial tasks to address these risks or issues are outlined. Risk / Issue Lack of clear responsibility for recruitment in the university Probability H M L Impact H M L Actions to Mitigate Y Y Y Consult all interested parties and try to build consensus Responsibility 4.2 Ongoing Management of Risks and Issues Any additional risks and issues identified will be maintained on an ongoing basis by the in separate Risks and Issues logs. IT15 Integrated Recruitment Systems Project Initiation Document Page 8 of 10
9 5 Communication Plan As part of the detailed planning for each of the constituent projects, key stakeholders will be identified and plans for interaction and communication with them will be detailed. The following table highlights the communication and interaction activities planned for each stakeholder group: Stakeholder Actions Responsibility Dean of Graduate Studies Graduate Studies Arrange meeting to discuss scope of project and possible Steering Group Include in Project Team so that this project is seen as a joint initiative Schools & Colleges Identify pilot areas to work with whilst communicating on a wider basis UCD Registry - Admissions Include in Project Team so that this project is seen as a joint initiative UCD Registry Meet to discuss approach and inclusion on the project Communications Office Meet to discuss approach and inclusion on the project IT15 Integrated Recruitment Systems Project Initiation Document Page 9 of 10
10 6 Costs 6.1 Initial Budget It is not expected that individual projects within this programme will incur costs beyond the staff time involved. The one exception will be the procurement of some web design expertise to ensure a very high quality look and feel to the project. 6.2 Ongoing Costs It is not expected that individual projects within this programme will incur ongoing costs other than ongoing staff time. IT15 Integrated Recruitment Systems Project Initiation Document Page 10 of 10
It0x Enhanced data storage services Sharepoint Teamsites
UCD IT Services It0x Enhanced data storage services Sharepoint Teamsites Project Initiation Document Version 1.0 2, December 2014 Version History Version Date Summary of Changes Changed by 1 2/12/2014
More informationIT11 - Cloud Services for Off-Site Resilience
UCD IT Services IT11 - Cloud Services for Off-Site Resilience Project Initiation Document Version 1.0 December 2 nd 2014 Version History Version Date Summary of Changes Changed by 1.0 02/12/2014 Initial
More informationUCD International UCD IT Services. IT12 - Device Security & Encryption Strategy. Project Initiation Document. Version 1.0 2 nd December 2014
UCD International UCD IT Services IT12 - Device Security & Encryption Strategy Project Initiation Document Version 1.0 2 nd December 2014 Version History Version Date Summary of Changes Changed by 1.0
More informationUCD IT Services. Research Data. Project Initiation Document. Version 1.0 03 rd December 2014. Version History
UCD IT Services Research Data Project Initiation Document Version 1.0 03 rd December 2014 Version History Version Date Summary of Changes Changed by 1.0 03/12/2014 Initial Document 1.1 09/12/2014 Minor
More informationIT Services Website Redevelopment
UCD IT Services IT01 IT Services Website Redevelopment Project Initiation Document Version 1.0 1, December 2014 Version History Version Date Summary of Changes Changed by 1 1/12/2014 Brian Morrissey IT
More informationUCD IT Services. IT13 - Wireless Expansion. Project Initiation Document. Version 1.0 02 December 2014. Version History
UCD IT Services IT13 - Wireless Expansion Project Initiation Document Version 1.0 02 December 2014 Version History Version Date Summary of Changes Changed by 1.0 02/12/2014 Initial Draft Anthony Grenham
More informationOE PROJECT CHARTER TEMPLATE
PROJECT : PREPARED BY: DATE (MM/DD/YYYY): Project Name Typically the Project Manager Project Charter Last Modified Date PROJECT CHARTER VERSION HISTORY VERSION DATE (MM/DD/YYYY) COMMENTS (DRAFT, SIGNED,
More informationDepartment of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000
Project Management Project Management Public Private Partnership Guidance Note 7 14 April 2000 Guidance Note 7 14 April 2000 Project Management Contents Section Page I INTRODUCTION...1 SCOPE AND PURPOSE
More informationSenior Project Manager (Web Content Management)
Senior Project Manager (Web Content Management) IT Services Portfolio & Project Management Office Salary Grade 8-40,046 to 45,053 per annum Fixed term contract for 2 years (** see below for contract information)
More informationIBAPro Project Management Methodology
IBAPro Project Management Methodology A description of the IBApps Project Management Methodology and Implementation Process Version 2.2, June 2013 Contents 1. Project Management... 3 2. Phases... 3 2.1.
More informationLONDON CYCLE HIRE SCHEME AGREEMENT. Schedule 10 Contract Management and Reporting. Schedule 10 Contract Management and Reporting REDACTED VERSION
LONDON CYCLE HIRE SCHEME AGREEMENT Schedule 10 Contract Management and Reporting Transport for London - Version Final CCS0000151079 SCHEDULE 10 Contract Management and Reporting Procedure 1. Introduction
More informationProject Roles and Responsibilities
Project s and This template can be used to define roles and responsibilities Below is a few typical examples of the different types of roles involved in delivering a project and their respective responsibilities.
More informationUoD IT Job Description
UoD IT Job Description Role: Projects Portfolio Manager HERA Grade: 8 Responsible to: Director of IT Accountable for: Day to day leadership of team members and assigned workload Key Relationships: Management
More informationSenior Project Manager
Senior Project Manager IT Services Portfolio & Project Management Office Salary Grade 8-40,046 to 45,053 per annum Open Ended Contract Ref: CSE00868 At Leicester we re going places. Ranked in the top-12
More informationProject Team Roles Adapted for PAAMCO
Project Team Roles Adapted for PAAMCO Project Roles, Authority & Responsibilities Role a defined funciton assumed by or assigned to a person in the project Authority the right to apply project resources,
More informationOperations. Group Standard. Business Operations process forms the core of all our business activities
Standard Operations Business Operations process forms the core of all our business activities SMS-GS-O1 Operations December 2014 v1.1 Serco Public Document Details Document Details erence SMS GS-O1: Operations
More informationPROCUREMENT PROGRAMME PROCUREMENT OF CONSULTANTS HEAD OF WASTE STRATEGY AND CONTRACTS
NORTH LONDON WASTE AUTHORITY Agenda Item No: REPORT TITLE: PROCUREMENT PROGRAMME PROCUREMENT OF CONSULTANTS REPORT OF: HEAD OF WASTE STRATEGY AND CONTRACTS FOR SUBMISSION TO: DATE: AUTHORITY MEETING 11
More informationWorks closely with all members of the Training and Consultancy team, and the wider Operations, Fundraising and Marketing directorate.
Job description Training Officer Main purpose of job The main purpose of this role is to co-ordinate the department s training and marketing activities provide market intelligence to the Training team
More informationPost Title and Post Number Postgraduate Recruitment Officer - 48194. External Relations
Job Description Post Title and Post Number Postgraduate Recruitment Officer - 48194 Organisation Advertising Description External Relations Post Number 48194 Full Time/Part Time Duration Post is open to:
More informationCASE STUDY 6 SECTOR: NHS DELIVERABLE: NEW MULTIFUNCTION SERVICE DESK THE CLIENT:
CASE STUDY 6 SECTOR: NHS DELIVERABLE: NEW MULTIFUNCTION SERVICE DESK THE CLIENT: The Queen Elizabeth Hospital King s Lynn NHS Foundation Trust (QEH) is a 514 bed general hospital providing services to
More informationCONFIGURATION COMMITTEE. Terms of Reference
SWBTB (8/13) 166 (g) CONFIGURATION COMMITTEE Terms of Reference 1. CONSTITUTION 1.1 The Board hereby resolves to establish a Committee of the Board to be known as the Configuration Committee (The Committee).
More information3. OPERATING COMPANY'S ANNUAL ROAD SAFETY REVIEW 1
SCOTTISH MINISTERS' REQUIREMENTS 1. SCHEDULE 8 PART 3 ROAD SAFETY AND ACCIDENT INVESTIGATION AND PREVENTION CONTENTS Page No. 1. GENERAL 1 1.1 Introduction 1 2. ROUTE SAFETY FILES 1 3. OPERATING COMPANY'S
More informationPROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
More informationMinnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
More informationProgramme Governance and Management Plan Version 2
PROCESS FOR CHANGE - Detailed Design Programme Governance and Management Plan Version 2 1 INTRODUCTION In October 2008, the Council approved the selection of seven opportunity themes to take forward from
More informationProject Audit & Review Checklist. The following provides a detailed checklist to assist the PPO with reviewing the health of a project:
Project Audit & Review Checklist The following provides a detailed checklist to assist the PPO with reviewing the health of a project: Relevance (at this time) Theory & Practice (How relevant is this attribute
More informationJob Description- SF09775
Visual Identity Team Human Resources Section name Job Description- SF09775 Post Title: Grade: Faculty/Department: Reports to: Responsible for: Telemarketing Recruitment Executive Grade 5-23,386 to 26,274
More informationLGS Project Management Methodology
Page: 32 LGS Project Management Methodoy The LGS project management methodoy is integral to our overall delivery methodoy. Based on inpro, one of the LGS inspiration series documents, our methodoy is compliant
More informationRetained Fire Fighters Union. Introduction to PRINCE2 Project Management
Retained Fire Fighters Union Introduction to PRINCE2 Project Management PRINCE2 PRINCE stands for: PRojects IN Controlled Environments and is a structured method which can be applied to any size or type
More informationQuality Assurance Manual
Office of Quality, Standards and Partnerships Quality Assurance Manual Section 05 3 Periodic Academic Review Panel Member Guidance and Report Template This document sets out guidance for members of Periodic
More informationProject Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee
Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Page 1 2 Contents 1. Introduction... 3 1.1 Definition of a... 3 1.2 Why have
More informationMaturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce
Maturity Model March 2006 Version 1.0 P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value Added product which is outside the scope of the HMSO
More informationAdmissions CRM Project Charter
PMO Anne Milkovich 1/26/2015 Page 1 of 5 Student enrollment among traditional undergraduate Freshmen has declined by about 10% over the last six years, a source of concern for institutional leadership.
More informationJOB DESCRIPTION. 1. JOB TITLE: Administrative Assistant (Student Liaison) 4. DEPARTMENT: University Centre Shrewsbury
JOB DESCRIPTION 1. JOB TITLE: Administrative Assistant (Student Liaison) 2: HR REFERENCE NUMBER: HR15037 3. ROLE CODE: FINADMIN01 4. DEPARTMENT: University Centre Shrewsbury 5. JOB PURPOSE: To provide
More informationROLE DESCRIPTION. Role of TEC
ROLE DESCRIPTION Role Title: Manager Corporate Support Projects and Services Number and Title of Direct Reports: 7 Directorate: Corporate Services Budget: tbc Reports to: Chief Financial Officer Location:
More informationHR & EXECUTIVE SUPPORT MANAGER ROLE PROFILE
HR & EXECUTIVE SUPPORT MANAGER ROLE PROFILE 1 JOB PURPOSE Promote a consistent people centred approach to employee management which supports the values and develops the culture of LYHA. Champion HR practices
More informationJOB DESCRIPTION. 1. JOB TITLE: Receptionist/Clerical Assistant. 4. DEPARTMENT: Chester Business School
JOB DESCRIPTION 1. JOB TITLE: Receptionist/Clerical Assistant 2: HRMS REFERENCE NUMBER: HR14017 3. ROLE CODE: FINCA 4. DEPARTMENT: Chester Business School 5. ORGANISATION CHART: Head of Department Receptionist/
More informationProject Management Guidebook
METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple
More informationDirector of Development and External Affairs (DDEA)
JOB DESCRIPTION Post Digital Development Manager Job Family Specialist, Professional and Administrative Grade 6 Role code DDM001 Status Full-time Contract Type Permanent Reporting to Director of Development
More informationDigital Signature Application
Department of Science and Technology Republic of South Africa Specification Digital Signature Application 1. INTRODUCTION The Department of Science and Technology (DST) has 100 employees in Pretoria and
More informationSCHEDULE 8 Generalist Project Services Framework 2015
SCHEDULE 8 Generalist Project Services Framework 2015 Nominal Insurer And Schedule 8 (Project Services Framework) Page: 1 of 6 Schedule 8 Generalist Project Services Framework Contents Overview... 3 1.
More informationIT Re procurement 2013 project governance
ICO IT Re procurement 2013 project governance A summary of the recommended project governance that will be required to deliver the IT re procurement project Bill Ritchie Version 1.0 26 Apr 2012 Contents
More informationPOSITION DESCRIPTION
POSITION DESCRIPTION POSITION TITLE: Future Student Officer SCHOOL/OFFICE: Office of Future Students CLASSIFICATION LEVEL: Bond Level 3 DATE POSITION CLASSIFIED/UPDATED: September 2014 This position is
More informationResponsibilities of Associate Deans and School Directors of Teaching and Learning
Guide to policy and procedures for teaching and learning Section 2: Introduction to quality management process/structure in the University Responsibilities of Associate Deans and School Directors of Teaching
More information2: HRMS REFERENCE NUMBER:
JOB DESCRIPTION 1. JOB TITLE: Helpdesk Supervisor 2: HRMS REFERENCE NUMBER: HRMS/HRMS13310 3. ROLE CODE: FINDACO 4. DEPARTMENT: Facilities Management 5. ORGANISATION CHART: Post will report to the Head
More informationPROJECT SCOPE STATEMENT
PROJECT SCOPE STATEMENT Note: Any work not explicitly included in the Project Scope Statement is implicitly excluded from the project. Project Name: Prepared by: BI - IT Governance Amy Winkel Date: 12/20/2010
More informationThe roles of Graduate Studies Committees and the operation of progress reviews for research students
Approved by Academic Council 26th November 2010 The roles of Graduate Studies Committees and the operation of progress reviews for research students The roles of Graduate Studies Committees and the operation
More informationPOSITION INFORMATION DOCUMENT
POSITION INFORMATION DOCUMENT Position Title: Senior Manager, ICT Contracts Classification Code: ASO8 Division: ICT Services Directorate: ICT Contracts & Performance Management Type of Appointment: Branch:
More informationIn each and every appointment for employment at Tai Poutini Polytechnic, the employer is the Chief Executive of the institution.
Position Description and Person Specification HR Advisor In each and every appointment for employment at Tai Poutini Polytechnic, the employer is the Chief Executive of the institution. Conditions of Service:
More informationUniversity of Cambridge Information Services Committee Governance of ISC Projects Originated January 2009 (updated December 2011; awaiting further
University of Cambridge Information Services Committee Governance of ISC Projects Originated January 2009 (updated December 2011; awaiting further revision June 2014) 1. Introduction This paper defines
More informationJOB DESCRIPTION. 5. ORGANISATION CHART: Reports to the Institute of Medicine Administrator. Institute of Medicine Directors
JOB DESCRIPTION 1. JOB TITLE: Administrative Assistant 2. HRMS REFERENCE NUMBER: HR14132 3. ROLE CODE: FINADMIN01 4. DEPARTMENT: Institute of Medicine (IoM) 5. ORGANISATION CHART: Reports to the Institute
More informationTerms of Reference. Project Management Advisor for the Development of a Public Debt Management System (PDMS)
Terms of Reference Project Management Advisor for the Development of a Public Debt Management System (PDMS) (A) Background The Commonwealth is a voluntary association of 53 countries that support each
More informationPage 7. Area Served: Borough Wide Chair of the Committee: Cllr Tim Crowley
Report to: Date: Report of: Audit Committee Page 7 27 th September Executive Head Policy and Customer Services Agenda Item 4 Ward Location: Not Applicable Author(s) and Contact Phone Number(s): Gill Bull,
More informationProject Management Guidelines
Project Management Guidelines Overview Section 86-1506 (5) directs the NITC to adopt guidelines regarding project planning and management. The goal of project management is to achieve the objectives of
More informationResource Management. Determining and managing the people resources on projects can be complex as:
Baseline Resource Management RESOURCE MANAGEMENT Purpose To provide a procedure and associated guidelines to facilitate the management of project people resources. Overview This Phase is used to establish
More informationHow To Write A Project Management Plan
Enter Project Name Project Management Plan (PMP) Kickoff Month, Day, Year 1 Purpose The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents
More informationMNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
More informationTeaching Excellence Framework & Quality Assurance Administrator
University Offices Teaching Excellence Framework & Quality Assurance Administrator Academic Division (Educational and Student Policy) 1 Educational and Student Policy Educational and Student Policy (ESP)
More informationCompliance. Group Standard
Group Standard Compliance Serco is committed to good governance practices and the management of risks supported by a robust business compliance process SMS-GS-G2 Compliance July 2014 v1.0 Serco Public
More informationGUIDELINE NO. 22 REGULATORY AUDITS OF ENERGY BUSINESSES
Level 37, 2 Lonsdale Street Melbourne 3000, Australia Telephone.+61 3 9302 1300 +61 1300 664 969 Facsimile +61 3 9302 1303 GUIDELINE NO. 22 REGULATORY AUDITS OF ENERGY BUSINESSES ENERGY INDUSTRIES JANUARY
More informationAccess What are the HIT requirements to support recommendations of the Equity & Access Council to guard against under-service or patient selection?
HEALTH INFORMATION TECHNOLOGY (HIT) COUNCIL Charter This work group will develop for recommendation to the Healthcare Innovation Steering Committee, a proposal for HIT requirements 1 and technology components
More informationTelstra Service Management Framework. Your assurance of first-class network support
Telstra Service Framework Your assurance of first-class network support The Service Framework delivers comprehensive, integrated support Service Frame work SERVICE IMPROVEMENT & REPORTING Performance &
More informatione-tourism Marketing Specialist
! Role Profile for e-tourism Marketing Specialist e-jobs-observatory.eu European Profiles in e-tourism Functions e-tourism Marketing Specialist 1 e-tourism Marketing Specialist 1. Role Profile Role title
More informationJob Title: Subject Leader Animation (Senior Lecturer Teaching and Research)
JOB DESCRIPTION Job Title: Subject Leader Animation (Senior Lecturer Teaching and Research) Post No: Department: Location: Grade: Salary: Tenure: Hours: Accountable to: Accountable for: NA101 Cardiff School
More informationPROJECT AGREEMENT FOR INDEPENDENT PUBLIC SCHOOLS INITIATIVE
PROJECT AGREEMENT FOR INDEPENDENT PUBLIC SCHOOLS INITIATIVE An agreement between: - the Commonwealth of Australia; and - the State of South Australia. This project will increase the autonomy of government
More informationPage 5. The Adult Social Services and Health Committee. The Strategic Director of Adult Social Services, Housing and Health
Page 5 Agenda Item 5 Report to: The Adult Social Services and Health Committee Date: 20 th November 2012 Report of: The Strategic Director of Adult Social Services, Housing and Health Ward Location: All
More informationNewcastle University. Educational Partnerships. Framework for Joint and Dual PhDs
Newcastle University Educational Partnerships Framework for Joint and Dual PhDs These principles are provided as a guide for the development of joint or dual PhD programmes and should be read in conjunction
More informationTRANSITION PLAN TEMPLATE
TRANSITION PLAN TEMPLATE In this template, instructions are included in italics. When you have completed the template and no longer need the instructions, delete them. Provide a brief overview of the transition
More informationUNIVERSITY OF LINCOLN JOB DESCRIPTION
UNIVERSITY OF LINCOLN JOB DESCRIPTION JOB TITLE DEPARTMENT LOCATION College Marketing, Intelligence & Recruitment Officer College of Arts Brayford Campus JOB NUMBER MHT001 GRADE 6 DATE December 2015 REPORTS
More informationUNIVERSITY OF SUSSEX. 1. Advertisement Ref: 482
UNIVERSITY OF SUSSE 1. Advertisement Ref: 482 Student Recruitment Services Marketing Manager Permanent, full time Salary range: starting at 30,728 and rising to 36,661 per annum. It is normal to appoint
More informationThe overall aim for this project is To improve the way that the University currently manages its research publications data
Project Plan Overview of Project 1. Background The I-WIRE project will develop a workflow and toolset, integrated into a portal environment, for the submission, indexing, and re-purposing of research outputs
More informationNSW Government ICT Benefits Realisation and Project Management Guidance
NSW Government ICT Benefits Realisation and Project Management Guidance November 2014 CONTENTS 1. Introduction 1 2. Document purpose 1 3. Benefits realisation 1 4. Project management 4 5. Document control
More informationJOB DESCRIPTION. 1. JOB TITLE: Senior Lecturer in Business and Management. 4. DEPARTMENT: Business Strategy, Finance and Entrepreneurship
JOB DESCRIPTION 1. JOB TITLE: Senior Lecturer in Business and Management 2. HRMS REFERENCE: HR/15117 3. ROLE CODE: FINSLTSR5 4. DEPARTMENT: Business Strategy, Finance and Entrepreneurship 5. ORGANISATION
More informationJOB DESCRIPTION. Design, Exhibitions and Future Plan. Department/Section: Projects. Pay band: 3. Background
JOB DESCRIPTION Job Title: Client Project Manager Division: Design, Exhibitions and Future Plan Department/Section: Projects Pay band: 3 Reporting to: Head of Projects Background The work of the Projects
More informationWHITE PAPER Business Process Services: A Successful Transition Is the Foundation of World- Class Outsourcing cgi.com
WHITE PAPER Business Process Services: A Successful Transition Is the Foundation of World- Class Outsourcing A summary of the key transition questions asked by our clients In this paper, we examine five
More informationProgramme Manager Relationship Management System
Programme Manager Relationship Management System Russam Ref 4573 Job Profile This document is a generic description for the role. Any specific requirements in the published advert should also be taken
More informationManager for Social Sciences - 42897. External Relations. Full time. Permanent. External and internal candidates
Job Description Post Title and Post Number Organisation Advertising Description College Marketing and Communications Manager for Social Sciences - 42897 External Relations Post Number 42897 Full Time/Part
More informationSCHEDULE 10. Contract Management and Reporting. the Management Information and reporting requirements,
SCHEDULE 10 Contract Management and Reporting 1. Scope 1.1 This schedule sets out: contract management procedures; and the Management Information and reporting requirements, with which the Service Provider
More informationICT Service Desk Creation
ICT Service Desk Creation Project Initiation Document Document: ICT Service desk Creation: PID Issue Date: 26 th November 2010 Version: 0.1 Draft Version Number: 1.0 Change Control Quality Assurance Document:
More informationUNIVERSITY OF DUBLIN TRINITY COLLEGE HUMAN RESOURCES COMMITTEE
UNIVERSITY OF DUBLIN TRINITY COLLEGE HUMAN RESOURCES COMMITTEE The Human Resources Committee met on Wednesday 26 th November 2014 at 11am in the Board Room, House 1. PRESENT: APOLOGIES: Mr Dermot Frost
More informationSustaining Progress Fourth Progress Report
Sustaining Progress Fourth Progress Report Name of Institution DUBLIN CITY UNIVERSITY I confirm that I have assessed and verified the extent of progress and co-operation which has been achieved to date
More informationPROJECT AUDIENCE REQUEST FOR PROPOSAL: Business Plan
CONTENTS Introduction Proposal Submission deadline Background Summary of Goals Project Details o Business Plan Participants Financial Planning o Business structure/leadership model Framework Board governance/structure
More informationPOSITION DETAILS. Centre for Higher Education Development (CHED)
JOB DESCRIPTION NOTES Forms must be downloaded from the UCT website: http://www.uct.ac.za/depts/sapweb/forms/forms.htm This form serves as a template for the writing of job descriptions. A copy of this
More informationLMI Aerospace PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012
PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012 TABLE OF CONTENTS INTRODUCTION... 2 PROJECT MANAGEMENT APPROACH... 2 PROJECT SCOPE... 2 MILESTONE LIST... 2 SCHEDULE BASELINE
More informationSmart Meters Programme Schedule 2.5. (Security Management Plan) (CSP South version)
Smart Meters Programme Schedule 2.5 (Security Management Plan) (CSP South version) Schedule 2.5 (Security Management Plan) (CSP South version) Amendment History Version Date Author Status v.1 Signature
More informationDraft Document STATE OF MICHIGAN. SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing
STATE OF MICHIGAN SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing Executive Summary The State of Michigan has dedicated integrated team of resources for the
More informationProgramme Manager (Finance) Programme Manager - Finance (Contract Management
JOB DESCRIPTION Programme Manager (Finance) Job Responsibilities: Team) Programme Manager - Finance (Contract Management The Alliance comprises a UK Secretariat and national, independent intermediary organisations
More informationUNIVERSITY COLLEGE DUBLIN. Policy on Accreditation of Prior Learning: Certificated Learning
UNIVERSITY COLLEGE DUBLIN Policy on Accreditation of Prior Learning: Certificated Learning POLICY DOCUMENT Approved by Academic Council 13 April 2006 Amendments to Policy Approved by Academic Council Executive
More informationStudent Attendance Policy
Student Attendance Policy Introduction Providing a student experience of the highest possible quality is a priority for Queen Margaret University. Promoting and encouraging student engagement with all
More informationContract Management Guideline
www.spb.sa.gov.au Contract Management Guideline Version 3.2 Date Issued January 2014 Review Date January 2014 Principal Contact State Procurement Board Telephone 8226 5001 Contents Overview... 3 Contract
More informationSecuring and using additional external resources to support Health Inequalities Strategy delivery
REQUEST FOR DIRECTOR DECISION DD537 Title: Securing and using additional external resources to support Health Inequalities Strategy delivery Executive Summary: The Greater London Authority Act 1999 requires
More informationCOMMUNICATIONS MANAGEMENT PLAN <PROJECT NAME>
COMMUNICATIONS MANAGEMENT PLAN TEMPLATE This Project Communications Management Template is free for you to copy and use on your project and within your organization. We hope that you find this template
More informationHealth Information Management Module. Annual Review. Internal Audit Branch 378-1-233. Approved by Audit Committee
Health Information Management Module Annual Review Internal Audit Branch 378-1-233 Approved by Audit Committee September 25 th, 2007 Table of Contents Executive Summary... i 1.0 Background...1 2.0 Objective
More informationST ANDREWS COMMUNITY HOSPITAL AND HEALTH CENTRE PROJECT MANAGEMENT AND MONITORING THE BOARD S OBLIGATIONS
ST ANDREWS COMMUNITY HOSPITAL AND HEALTH CENTRE PROJECT MANAGEMENT AND MONITORING THE BOARD S OBLIGATIONS GENERAL LEAD RESPONSIBILITY OBLIGATIONS UNDER THE PROJECT AGREEMENT Deliver to Project Co the Completion
More informationBefore starting it is worth considering what we mean by the term project - basically it can be defined as:
Delivering Successful Projects, Tom Moriarty, MDR Consulting This paper outlines the critical requirements of success in managing projects of all types from the definition of a business need to the delivery
More informationFixed Scope Offering for Oracle Fusion HCM. Slide 1
Fixed Scope Offering for Oracle Fusion HCM Slide 1 Today s Business Challenges Adopt leading Global HCM practices. Streamline the HCM processes and achieve measurable efficiencies. Achieve HR excellence
More informationDistance Learning PhD
APRC.12.05.02 Appendix 1 Annex 1 Distance Learning PhD 1. Background 1.1 The University of Birmingham (UoB) permits postgraduate researchers (PGRs) to read for the degree of PhD on a full-time and part-time
More informationQAA Quality Code of Higher Education Mapping
QAA Quality Code of Higher Education Mapping Chapter B11: Research degrees Quality Code Document: Chapter B11: Research degrees Expectation Research degrees are awarded in a research environment that provides
More informationInformation Commissioner's Office
Information Commissioner's Office IT Procurement Review Ian Falconer Partner T: 0161 953 6480 E: ian.falconer@uk.gt.com Last updated 18 June 2012 Will Simpson Senior Manager T: 0161 953 6486 E: will.g.simpson@uk.gt.com
More informationIntegrated Assurance & Approval Strategy and Integrated Assurance & Approval Plans
Integrated Assurance & Approval Strategy and Integrated Assurance & Approval Plans A guide to implementing integrated assurance and approvals Version 1.0 - May 2011 Contents Introduction 03 Integrated
More information