1 Pressure Testing Procedures for Building Services Piping Document Number Revision 0 Approved By Ric Morris McMurdo, Palmer, and South Pole February 25, 2005 Active Divisions/Departments FEMC Raytheon Polar Services Company HARD COPY NOT CONTROLLED-CONTROLLED COPY AVAILABLE ONLINE
2 Table of Contents Table of Contents...i Purpose...1 Responsibility...1 Plumbing Foreman, Construction Coordinator, Project Engineer, and Field Engineer, FEMC...1 Personnel...1 Discussion...1 Requirements...2 Tools and Equipment...2 Ensuring Safety of Work Site...2 Conducting the Pressure Test...3 References...6 Records...6 i
3 Purpose This procedure outlines the necessary actions and safety practices for hydrostatic pressure testing or air pressure testing all building services piping within heated structures at McMurdo, Palmer, and South Pole. Responsibility Plumbing Foreman, Construction Coordinator, Project Engineer, and Field Engineer, FEMC Personnel Plumbing Foreman (project or Work Center), FEMC Construction Coordinator, Project Engineer, Field Engineer, NSF Station Manager, NSF Representative Discussion In order to ensure the integrity of any building services pipe upon which work has been performed within a heated structure, RPSC will perform pressure testing. For piping that will contain water, brine, seawater, glycol heating solution or CO 2 (due to the high pressure of the test) a hydrostatic test will be used. For piping that will contain air or fuel, RPSC will uses pneumatic (air) testing. The pressure testing procedures adopted by RPSC follow API and ASME recommended standards and practices. The procedures also outline proper safety practices that must be followed in order to minimize risks. Page 1 of 6 pages
4 Requirements Tools and Equipment All personnel within test area shall be required to wear eye and hearing Personnel Protection Equipment (PPE). Air tests will be performed with Chicago quick couplings and an air compressor (currently using Sul-Air Type compressor, exact equipment type may vary). Hydrostatic tests will be performed with a high-pressure hydraulic pump and isolation valves that are rated for the pressure and service of the system being tested. Ensuring Safety of Work Site Pneumatic and Hydrostatic testing can be dangerous and should be performed with caution and careful attention to all safety procedures. To ensure the safety of all workers and residents, the following safety precautions must be completed prior to conducting the pressure testing: 1. Notify station personnel of area to be avoided due to potential risks during pressure testing. 2. Ensure that no high pressure testing occur in the work centers. 3. Ensure personnel conducting the test stand behind a barrier during pressurization. 4. Mark off the area as a dangerous site, and ensure only individuals associated with the testing activities are in the area. This information should be provided if the test occurs in normally occupied work area. Occupants must be advised to avoid the area. Results After following the above prerequisites, the necessary steps to ensure safety will be complete. Proceed to conduct the pressure test. Page 2 of 6 pages
5 Conducting the Pressure Test To conduct a pressure test of building services piping systems in all Station buildings, complete the following steps: 1. Identify the maximum test pressure to be used, as determined by the Project Engineer or Field Engineer. 2. Identify the type of pipe system to be tested. The maximum aggregate length of pipe to be tested at one time is 400 feet. 3. Examine all connections prior to the test to ensure proper tightness. 4. Determine the pressure rating for all connected fittings and devices to ensure they are rated for the maximum test pressure. 5. Isolate any equipment that may be damaged by the test and indicate this isolation on the test form. 6. Secure a blind flange or cap suitable for the system s rated pressure on all openings that are not closed off by valves. 7. Plug all test, drain, and vent ports that are not required for the test. 8. If the section of pipe being tested is isolated from other sections by in-line valves, ensure the portion not being tested is open to the atmosphere. For Pneumatic Testing follow steps 9 through 15: 9. Apply a preliminary test pressure of 25 psig, or as directed by the Project Engineer. Note This pressure should be held for a minimum of 10 minutes to allow for the location of any major leaks. If leaks are detected during this step, or at any time during the test, relieve the pressure and take appropriate action to correct the leak. If necessary, consult the Project Engineer for instruction. 10. Apply the test pressure in increments of 25 psig, or as directed by the Project Engineer, until the maximum test pressure is reached. Hold pressure for 5 minutes at each 25 psig increment and inspect for leaks before adding more pressure. Page 3 of 6 pages
6 Note The maximum test pressure shall be 150% of the maximum system operating pressure. For systems that derive their pressure from hydrostatic pressure, the required test pressure will be verified prior to testing by the Project Engineer or the Field Engineer. 11. Hold the maximum test pressure for 10 minutes. The NSF Station Manager or other appropriate NSF representative must observe this step. 12. After the required 10 minutes, reduce the pressure to 100 psi or predetermined pressure. 13. Hold this pressure for 24 hours. 14. Obtain confirmation of a successful test by the NSF representative after the 24 hour time period. 15. Remove the pressure, with caution to avoid escaping air stream, debris, and high decibel noise level. For Hydrostatic Testing follow steps 16 through 23: 16. For McMurdo Station: if water consumption for the hydrostatic test is anticipated to exceed 1000 gallons, notify the Water Plant Supervisor of the pending water consumption. For Palmer Station or South Pole Station: if water consumption for the hydrostatic test is anticipated to exceed 100 gallons, notify the Facility Engineer of the pending water consumption. 17. Fill the piping system with water and apply a preliminary test pressure of 25 psig, or as directed by the Project Engineer. While holding this pressure, purge all remaining air from the piping system and continue to fill with water as necessary to maintain a 25 psig initial fill pressure. Note This pressure should be held for a minimum of 10 minutes to allow for the location of any major leaks. If leaks are detected during this step, or at any time during the test, relieve the pressure and take appropriate action to correct the leak. If necessary, consult the Project Engineer for instruction. 18. Remove pressure and verify that all air bleed ports are appropriately secured with valves, caps or plugs. Page 4 of 6 pages
7 19. Apply the hydrostatic test pressure in increments of 25 psig, or as directed by the Project Engineer, until the maximum test pressure is reached. Hold pressure for 5 minutes at each 25 psig increment and inspect for leaks before adding more pressure. Note Minimum and Maximum Test Pressures The minimum test pressure is 1.5x the design pressure or 100 psig, whichever is greater. The maximum test pressure is less than any system component under test. CO 2 fire protection system piping test pressure per NFPA Establish that the required test pressure has been achieved. The NSF Station Manager or other appropriate NSF representative must observe this step. 21. Hold the required pressure for 24 hours or for special projects that are following NSF provided specifications; hold the test pressure for the specified duration of the type of system being tested. 22. Obtain confirmation of a successful test by the NSF representative after the required time period. 23. Remove the pressure, with caution to avoid escaping fluid and debris. Consult waste management for determination of potential hazard of the test fluid before disposal. At McMurdo Station, if appropriate to discharge to waste treatment system, notify the Waste Water Treatment Plant operator prior to release, include contaminants in fluid. If capture of the waste test fluid is appropriate, contact waste management for proper disposal. For all tests: 24. Complete the appropriate following forms Pressure/Leak Testing Sheet (EN-MPS-706a) and/or the Pressure and Temperature Log (EN-MPS- 706b) and place them in the appropriate engineering files as specified by the Project Engineer. Page 5 of 6 pages
8 Results After completing these steps, pressure testing is completed. Once the test is successfully completed, then the piping system is ready for service. References ASME B31.9 Building Services Piping; 937 Leak Testing, 1996 Edition NFPA 12- Carbon Dioxide Extinguishing Systems Pressure/Leak Testing Sheet (EN-MPS-706a) Pressure and Temperature Log (EN-MPS-706b) Records See the Pressure/Leak Testing Sheet and the Pressure and Temperature Log, under the FEMC-MPS tab of the FEMC Records Management Table (EN-D- 226a). (All forms are located on Common drive I:/Perm/Procedures/Master List/FEMC forms) Page 6 of 6 pages
Pressure Testing Procedures for Pipelines
Pressure Testing Procedures for Pipelines Document Number Revision 2 Approved By Ric Morris McMurdo, Palmer, and South Pole November 11, 2004 Active Divisions/Departments FEMC Raytheon Polar Services Company
Facilities Maintenance Work Order Procedures
Facilities Maintenance Work Order Procedures Document Number Revision 2 Approved by Ric Morris 09/14/05 Active Divisions/Departments FEMC Raytheon Polar Services Company Facilities, Engineering, Maintenance,
Standard Hydraulic Piping Flushing Procedure
Page 1 of 6 1.0 Scope This procedure covers the minimum technical requirements for cleaning and flushing of Hydraulic and Piping, and related accessories. 2.0 Introduction In hydraulic fluid power systems,
Pressure Testing (Hydrostatic / Pneumatic) Safety Guidelines
The INGAA Foundation, Inc. 1.0 ACTIVITY DESCRIPTION 1.1 This document provides basic safety guidelines for the safety of all personnel and the general public during pressure (e.g., hydrostatic, pneumatic)
Water System Disinfection
Water System Disinfection Document Number Revision 1 Approved By Ric Morris All 6/2/04 Active Divisions/Departments FEMC Raytheon Polar Services Company HARD COPY NOT CONTROLLED-CONTROLLED COPY AVAILABLE
Project Scheduling and Control Procedures
Project Scheduling and Control Procedures Document Number Revision 0 Approved By Ric Morris (Acting Director) DHQ, Stations August 30, 2001 Active Divisions/Departments FEMC Raytheon Polar Services Company
PBX Series Quick Fit Connector Bimetallic Steam Traps
6262100/6 IM-P626-01 ST Issue 6 PBX Series Quick Fit Connector Bimetallic Steam Traps Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4. Commissioning
SAFETY - LIFE SAVING RULES MECHANICAL ISOLATION CAT A-1 SOP #3
SUNCOR ENERGY PRODUCTS DISTRIBUTION TERMINAL OPERATING MANUAL STANDARD OPERATING PROCEDURE SAFETY - LIFE SAVING RULES Verify isolations of hazardous energy before any work begins. Date Issued: February
The following definitions apply with regard to requirements specified in this document:
GUIDELINES FOR INSTALLATION OF TEMPORARY AND PERMANENT ABOVEGROUND DIESEL FUEL TANKS FOR EMERGENCY AND STANDBY POWER SYSTEMS LOCATED OUTSIDE OF BUILDINGS For Use by Unidocs Member Agencies or where approved
OPERATIONS & MAINTENANCE (O&M) FOR PROPANE STORAGE FACILITIES
OPERATIONS & MAINTENANCE (O&M) FOR PROPANE STORAGE FACILITIES Reference: National Fire Protection Association (NFPA) Pamphlet No. 58 Liquefied Petroleum Gas Code, 2001, Chapter 11 Type of Facility: Petroleum
COMPRESSED GASES. 1.2 The contents of each cylinder and container must be clearly identified (by tag or stamp) on the cylinder.
Page 1 of 5 COMPRESSED GASES A compressed gas is defined as any mixture of gases in a container with a pressure exceeding 40 psi. at 70 o F, or 104 psi. at 130 o F; or any flammable liquid with an absolute
Lockout - Tagout. Control of Hazardous Energy OSHA Standard 1910.147
Lockout - Tagout Control of Hazardous Energy OSHA Standard 1910.147 You will learn Purpose of Lockout-Tagout Requirements for LOTO Types of Hazardous Energy Procedures for LOTO Types of Energy Electrical
Element D Services Plumbing
Medical Vacuum and Gas PART 1 - GENERAL 1.01 OVERVIEW A. This section addresses medical vacuum, waste anesthetic gas disposal, compressed air, oxygen, nitrous oxide, nitrogen and carbon dioxide systems.
Occupational Health Program Safety Training Series. Lockout/Tagout Safety Awareness Training
Occupational Health Program Safety Training Series Lockout/Tagout Safety Awareness Training 1 Lock out/tag out Lock out: the placement of a lockout device (lock) on an energy isolating device in accordance
Confined Space Training. Developed and Presented by: Scott Cole, CSP (440) 520-9499 [email protected]
Confined Space Training Developed and Presented by: Scott Cole, CSP (440) 520-9499 [email protected] Objectives To understand and recognize a confined space, To understand the difference in a permit required
PC1130 Electric Air Compressor
Senco Products Inc. 8485 Broadwell Road Cincinnati, Ohio 45244 PC1130 Electric Air Compressor Operating Instructions 2006 by Senco Products, Inc. Warnings for the safe use of this tool are included in
WORKING IN CONFINED SPACES GUIDELINES
WORKING IN CONFINED SPACES GUIDELINES Contents 1 Introduction... 2 2 Scope... 2 3 Definitions... 2 4 Responsibilities... 3 4.1 Permit Authoriser... 3 4.2 Permit Receiver... 3 4.3 Responsible UOW Officer...
Installing a Probe. Typical Installation
for hazardous locations. Prior to any installation in a Classified Hazardous Location, verify installation methods by the Control Drawing referenced on the product s name tag 2. The Feed Through Assembly
Standard Pneumatic Test Procedure Requirements for Piping Systems
the pressure equipment safety authority Standard Pneumatic Test Procedure Requirements for Piping Systems AB-522 Edition 2, Rev. 0 Issued 2012-06-28 Table of Contents FOREWORD... 3 1.0 INTRODUCTION...
Select the Right Relief Valve - Part 1 Saeid Rahimi
Select the Right Relief Valve - Part 1 Saeid Rahimi 8-Apr-01 Introduction Selecting a proper type of relief valve is an essential part of an overpressure protection system design. The selection process
Course Title: Safety Issues in Electronics Engineering Technology Number of Credits: 3 B.A. B.S. B.A.S A.A. A.S. Degree Type
GENERAL INFORMATION Name: Diane King Phone #: 77021 Course Prefix/Number: ETI3704 Course Title: Safety Issues in Electronics Engineering Technology Number of Credits: 3 B.A. B.S. B.A.S A.A. A.S. Degree
PC1131 Electric Air Compressor
Senco Products Inc. 8485 Broadwell Road Cincinnati, Ohio 45244 PC1131 Electric Air Compressor Operating Instructions 2006 by Senco Products, Inc. Warnings for the safe use of this tool are included in
Farm Fuel Tank Safety Guide
Farm Fuel Tank Safety Guide This brochure is provided by North Dakota Department of Emergency Services, your Local Emergency Planning Committee, and the State Emergency Response Commission along with assistance
WHAT YOU DON T KNOW ABOUT ACCUMULATORS CAN KILL YOU!
WHAT YOU DON T KNOW ABOUT ACCUMULATORS CAN KILL YOU! Atlanta (Monroe) GA 770-267-3787 [email protected] www.gpmhydraulic.com What You Don t Know About Hydraulic Accumulators Can Kill You TABLE OF CONTENTS
IMPORTANT SAFETY NOTICE
IMPORTANT SAFETY NOTICE To: Our Valued Customers User safety is a major focus in the design of our products. Following the precautions outlined in this manual will minimize your risk of injury. ITT Goulds
Technical Note 802 Leak Testing of Polyethylene Pipe For Municipal and Industrial Applications Part 1 Pre-Test Considerations
Technical Note 802 Leak Testing of Polyethylene Pipe For Municipal and Industrial Applications Part 1 Pre-Test Considerations Leak testing may be used to find leaks in a newly constructed or newly modified
Safety and Health Resource Manual. Sample Permit-Required Confined Space Written Program
Sample Permit-Required Confined Space Written Program Purpose The purpose of this document is to communicate Employer s compliance with MIOSHA s requirements for a permit-required confined space entry
GUIDANCE FOR DEVELOPMENT OF SPILL AND SLUG PREVENTION CONTROL PLANS AND FACILITIES FOR THE CITY OF ATTLEBORO SEWER USERS
Company Name: Address: The City of Attleboro s Rules and Regulations for the use of Wastewater Facilities require each user to provide protection from accidental discharge of prohibited materials and substances
BLADDER SURGE CONTROL SYSTEM
PART I GENERAL 1.01 Description BLADDER SURGE CONTROL SYSTEM This specification describes the requirements for a Bladder Surge Control System. The purpose of the system is to minimize transient pressures
Industrial Process Pump Safety Manual IMPORTANT SAFETY NOTICE
Industrial Process Pump Safety Manual IMPORTANT SAFETY NOTICE To: Our Valued Customers User safety is a major focus in the design of our products. Following the precautions outlined in this manual will
BPW32 DN15, DN20 and DN25 Balanced Pressure Wafer Steam Trap
1263050/6 IM-P126-07 ST Issue 6 BPW32 DN15, DN20 and DN25 Balanced Pressure Wafer Steam Trap Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation
OREGON FIRE CODE Interpretations and Technical Advisories
OREGON FIRE CODE Interpretations and Technical Advisories A collaborative service by local and state fire professionals, along with our stakeholders and customers, to provide consistent and concise application
Notes. Material 1. Appropriate Flammable Liquids
29 CFR 1910.106 Flammable Materials Flammable Liquids Preparation 1. Read Applicable Background information and related Company Policy Chapter. 2. Make Copies of this Lesson Plan for Personnel 3. Make
The following definitions apply with regard to requirements specified in this document:
GUIDELINES FOR INSTALLATION OF TEMPORARY AND PERMANENT ABOVEGROUND DIESEL FUEL TANKS FOR EMERGENCY AND STANDBY POWER SYSTEMS LOCATED OUTSIDE OF BUILDINGS For Use by Unidocs Member Agencies or where approved
Float and Thermostatic Traps Series H, C and X
Hoffman Specialty Installation & Maintenance Instructions HS-(E) and Thermostatic Traps Series H, C and X Series C & NPT Series C NPT Series X NPT Series C NPT Series H Ratings Maximum Max. Operating NPT
Fire Sprinkler System Maintenance and Testing Page 1 MAINTENANCE AND TESTING OF FIRE SPRINKLER SYSTEMS
Page 1 MAINTENANCE AND TESTING OF FIRE SPRINKLER SYSTEMS Introduction When properly installed and maintained, automatic fire sprinkler systems have proven to be the most effective means for protecting
ALVERNIA UNIVERSITY OSHA REGULATION: 29 CFR 1910.252 WELDING, CUTTING, AND BRAZING ( HOT WORK ) SECTION: 3600
OSHA REGULATION: 9 CFR 90.5 WELDING, CUTTING, AND BRAZING ( HOT WORK ) A. POLICY. This procedure follows requirements set forth in 9 CFR 90.5.. This policy applies to all Hot Work operations being done
Title: Aircraft Parking
Environmental Standard Operating Procedure Originating Office: Revision: Prepared By: Approved By: MCAS Miramar Environmental Original Environmental Management Department William Moog Management Department
FLAMMABLE AND COMBUSTIBLE LIQUIDS. n OSHA Changes
FLAMMABLE AND COMBUSTIBLE LIQUIDS OSHA Changes Introduction This module covers the two primary hazards associated with flammable and combustible liquids: explosion and fire. In order to prevent these hazards,
HSE information sheet. Fire and explosion hazards in offshore gas turbines. Offshore Information Sheet No. 10/2008
HSE information sheet Fire and explosion hazards in offshore gas turbines Offshore Information Sheet No. 10/2008 Contents Introduction.. 2 Background of gas turbine incidents in the UK offshore sector...2
Druck PV 62x pneumatic/hydraulic pressure stations
GE Sensing & Inspection Technologies Druck PV 6x pneumatic/hydraulic pressure stations safety and quick reference guide - K08 A. PV 6: Pneumatic pressure station (Figure A.) -90 mbar to 0 bar (-3. to 300
COMPETENCY ANALYSIS PROFILE Refrigeration and Air Conditioning Systems Mechanic - Branch 1 313A
COMPETENCY ANALYSIS PROFILE Refrigeration and Air Conditioning Systems Mechanic - Branch 1 313A (All unshaded skill sets must be demonstrated/completed) PROTECT SELF AND OTHERS Identify, interpret, and
ELECTRIC/DIESEL FIRE PUMP CHECK LIST
BUILDING NAME: DESIGNER: SCO REPRESENTATIVE: PUMP MANUF.: LOCATION: INSTALLER: DATE: OWNER NAME: INSTALLATION Certificate for flushing and hydrostatic test furnished Piping been hydrostatically tested
I. Introduction. 10 minutes
I. Introduction 10 minutes Introduction (1 of 2) An uninterrupted water supply is: The primary weapon for extinguishment Essential for fire fighter safety Ensuring a dependable water supply is a critical
Topics of the Presentation
Drill Rig Safety Topics of the Presentation Personnel safety and monitoring PPE Health (Drugs and Alcohol) Drill Rig operation Safe set up procedures Safe operation of machine Safety related accidents
Transformer Deluge Systems
Transformer Deluge Systems How Do Transformer Fires Ignite? Common causes of transformer failure: Weather-related events such as lightning Short circuits in electrical equipment The most common cause is
CONFINED SPACE ENTRY NON-MARINE FACILITES
CONFINED SPACE SAFETY CONFINED SPACE ENTRY NON-MARINE FACILITES EM-385 Chapter 34 CONFINED SPACE ENTRY NON- MARINE FACILITIES UFGS 013526 OSHA 29 CFR 1910.146 A space that: What is a Confined Space? Is
BOP PRESSURE TESTING PROCEDURE
0 Discuss Operator BOP requirements WITH RIG MANAGER. Insure that all Romfor's BOP equipment is tested consistent with Romfor's policy. This may require Nabors to incur the cost for the testing subcontractor
Control of Hazardous Energy LOCKOUT/TAGOUT 29 CFR 1910.147
Control of Hazardous Energy LOCKOUT/TAGOUT 29 CFR 1910.147 Contents I. Introduction II. Scope and Application III. Definitions IV. Lockout/Tagout Manual V. Energy Control Procedures 1. Applying Energy
System Saver 318 Air Compressor for Mack E-Tech and ASET Engines
Maintenance Manual 31 System Saver 318 Air Compressor for Mack E-Tech and ASET Engines Revised 08-05 NON-THROUGH DRIVE THROUGH DRIVE Service Notes About This Manual This manual provides service and repair
Northern Region. Underground Storage Tank
California CUPA Northern Region Presents Underground Storage Tank Designated Operators Workshop Workshop Agenda Definitions Tank Construction Corrosion Protection Spill Prevention Overfill Prevention Piping
GUIDELINES FOR LOGBOOKS COMPLIANCE TO BOILER REGULATIONS N.J.A.C. 12:90
GUIDELINES FOR LOGBOOKS COMPLIANCE TO BOILER REGULATIONS N.J.A.C. 12:90 Department of Labor and Workforce Development Labor Standards & Safety Enforcement Division of Public Safety and Occupational Safety
NFPA31FuelOilPiping 1 Revised 3-1-11
NFPA 31 Fuel Oil Piping, Installation and Testing Chapter 8 Fuel Piping Systems and Components 8.1 Scope. This chapter shall apply to piping systems and their components used to transfer fuel oil from
P O B o x 3 11 5 4 S t. L o u i s, M O 6 3 1 3 1-0 1 5 4 P h o n e : ( 3 1 4 ) 9 6 6-8 9 1 9 ~ E m a i l : w m h u I t t @ a o l.
P O B o x 3 11 5 4 S t. L o u i s, M O 6 3 1 3 1-0 1 5 4 P h o n e : ( 3 1 4 ) 9 6 6-8 9 1 9 ~ E m a i l : w m h u I t t @ a o l. c o m Determining Code Compliance and Pipe System Leak ing by William M.
RHODE ISLAND. Downloaded 01.15.11
Housekeeping/Laundry/Maintenance Section 35.0 Housekeeping RHODE ISLAND Downloaded 01.15.11 35.1 A full time employee of the facility shall be designated responsible for housekeeping services, supervision
Job Description. Water Plant Treatment Operator. Water Treatment Plant Operator 5/30/2005 Page 1
Job Description Water Plant Treatment Operator 5/30/2005 Page 1 PURPOSE OF THE POSITION (The main reason for the position, in what context and what is the overall end result) The is responsible for of
FILLING AND PURGING THE SYSTEM
FILLING INSTRUCTIONS FOR WATER HEATER OR CONDENSING BOILER (City Water) Safety tip: Before beginning, turn off power to boiler and circulator. FILLING AND PURGING Step 1: Close Return Manifold Isolation
Air Conditioner Water Heater - A Product of HotSpot Energy LLC
Air Conditioner Water Heater - A Product of HotSpot Energy LLC PLEASE READ THIS BEFORE YOU INSTALL THE UNIT 1. This air conditioner must be installed and/or repaired by a qualified technician. If you perform
1. A belt pulley is 3 ft. in diameter and rotates at 250 rpm. The belt which is 5 ins. wide makes an angle of contact of 190 over the pulley.
Sample Questions REVISED FIRST CLASS PARTS A1, A2, AND A3 (NOTE: these questions are intended as representations of the style of questions that may appear on examinations. They are not intended as study
BUILDING A WORLD OF DIFFERENCE. Safe work in confined spaces
Health & Safety Training Safe work in confined spaces Agenda Introduction What is a confined space? What are the hazards? Safe system of work Emergency arrangements Summary of pre-entry checks Questions
PIPES AND TUBES FOR HVAC PIPING AND EQUIPMENT
PIPES AND TUBES FOR HVAC PIPING AND EQUIPMENT GENERAL INFORMATION 1.1 This section applies to piping systems for chilled water, hot water, condenser water, steam, condensate return, fuel oil, refrigerant
EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT. BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309
EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309 FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT FOUR 1.0 SCOPE OF
A Safe Workplace A Workplace Safety and Health Manual for Your Community Section: III-C Subject: G-9
Page 1 of 7 The following procedure provides the requirements for. Refer to part 15 Confined Spaces, part 6 Personal Protective Equipment, part 14 Fall Protection, of The Manitoba Workplace Safety and
www.klmtechgroup.com TABLE OF CONTENT
Page : 1 of 19 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia TABLE OF CONTENT SCOPE 2 REFERENCES
FIBERGLASS UNDERGROUND STORAGE TANKS Special Installation Instructions for New York City Gasoline and Diesel Motor Fuels
INTRODUCTION The purpose of this manual is to provide speci c, detailed supplemental instruction regarding the installation of special Fiberglass Double-Wall Underground Storage Tanks (including compartment
Facility Operations Physical Safety Guidance Document
Facility Operations Physical Safety Guidance Document Title: Guide on Pipe Identification Standards (ASME A13.1-1996) Original Date: December 18, 2000 Section: 4.0 Facility Operations Revised Date: Number:
Civil Engineering Sector Labour-Management Health and Safety Committee
PROCEDURE FOR THE STORAGE AND HANDLING OF FUEL ON CONSTRUCTION SITES Civil Engineering Sector Labour-Management Health and Safety Committee July 2008 PROCEDURE FOR THE STORAGE AND HANDLING OF FUEL ON CONSTRUCTION
Engineering Documents in Expedition
Engineering Documents in Expedition Document Number Revision 0 Approved By Wayne L. Cornell, PE January 10, 2006 Active Divisions/Departments Raytheon Polar Services Company Facilities, Engineering, Maintenance,
Failure to comply with the following cautions and warnings could cause equipment damage and personal injury.
1.0 IMPORTANT RECEIVING INSTRUCTIONS Visually inspect all components for shipping damage. Shipping Damage is not covered by warranty. If shipping damage is found, notify carrier at once. The carrier is
Notes. Material 1. Personal Protective Equipment 2.
29CFR 1926.20(b)-Accident Reduction, 29CFR 1926.21- Safety Training & Education 29CFR 1926.20(a)-Unsafe Working Conditions 29 CFR 1910.132-138, the "Personal Protection Equipment" standard. & 20 CFR 1910.134
1.0 Purpose... 4. 2.0 Definitions...4. 3.0 Hot Work Operations. 5
HOT WORK PROGRAM Introduction The University of Kentucky recognizes a potential for fire from hot work operations. For that reason this program should be implemented in all departments at the University
APPENDIX O. Spill Prevention and Emergency Response Plan. G3 Terminal Vancouver Port Metro Vancouver Project Permit Application APPENDIX O
APPENDIX O Spill Prevention and Emergency Response Plan APPENDIX O G3 Terminal Vancouver Port Metro Vancouver Project Permit Application G3 TERMINAL VANCOUVER: PORT METRO VANCOUVER SPILL PREVENTION AND
CHEMICAL CLEANING UNIT Product number: 737189
CHEMICAL CLEANING UNIT Product number: 737189-1 - v.05/16 Content Page Intro 3 Specifications 4 Installation 5 Safety precautions 7 Maintenance 8 Spares and Accessories 8 Unitor Chemicals 9 Notes 10-2
Operating instructions
6302 6959 02/2006 GB For the user Operating instructions Logano G215 WS Oil and gas-fired boilers Please read thoroughly before use. Overview Regulations and directives Installation: 90/396/EEC gas appliance
Ontario Fire Code SECTION 5.13 DIP TANKS. Illustrated Commentary. Office of the Ontario Fire Marshal
Ontario Fire Code SECTION 5.13 DIP TANKS Illustrated Commentary Office of the Ontario Fire Marshal Dip Tanks Illustrated Commentary 1 5.13.1. Location 5.13.1.1. Dip tank operations involving flammable
Waste Oil Collection / Storage
ENVIRONMENTAL & REGULATORY SERVICES Storage Tank Regulation Section P. O. Box 7837 Madison, Wisconsin 53707-7837 TDD #: (608) 264-8777 http://www.commerce.state.wi.us http://www.wisconsin.gov Jim Doyle,
Pollution Incident Response Management Plan
Pollution Incident Response Management Plan POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN 1. Introduction This Pollution Incident Response Management Plan (PIRMP) has been prepared to describe the processes
SMALL GAS OPERATOR OPERATION AND MAINTENANCE PLAN
SMALL GAS OPERATOR OPERATION AND MAINTENANCE PLAN Facility Name: Address: QUALIFIED PERSONNEL All tasks shall be completed by a person that is qualified to that task (see operators qualification of individuals
TRAINING AND EQUIPMENT MANUAL HOSE PRACTICES EFFECTIVE: OCTOBER 2007
TRAINING AND EQUIPMENT MANUAL HOSE PRACTICES 301.010 ANNUAL SERVICE TEST FOR FIRE HOSE EFFECTIVE: OCTOBER 2007 The Department will test all fire hose annually. The testing of fire hose determines its serviceability.
Flushing and Cleaning the A/C System
Flushing and Cleaning the A/C System Once an AC system has been contaminated or has suffered a failure, the most important part of the AC service to restore the cooling performance to the system = FLUSHING
DIRECTIVE 055: STORAGE REQUIREMENTS FOR THE UPSTREAM PETROLEUM INDUSTRY. August 2012
DIRECTIVE 055: STORAGE REQUIREMENTS FOR THE UPSTREAM PETROLEUM INDUSTRY August 2012 SECTION 2 The storage requirements in Directive 055 apply to upstream petroleum facilities, well sites, and pipelines
Process Safety Management of Highly Hazardous & Explosive Chemicals. Operating Procedures
Process Safety Management of Highly Hazardous & Explosive Chemicals Operating Procedures Now that the PHA s Are Competed or Underway Operating Procedures & Safety Programs Must Be Developed PHA Information
Installation Manual DIAPHRAGM WELL TANK
Installation Manual DIAPHRAGM WELL TANK IN-LINE SERIES: 2-5 & 7 GALLON VERTICAL SERIES: 14-20-25-32-36-52-65-86-96-119 GALLON HORIZONTAL SERIES: 7-14 & 20 GALLON NO LEAD NO LEAD: The weighted average of
PROCEDURES PREVENTION OF ACCIDENTAL IGNITION
Page No: 1 of 7 6.0 PURPOSE (192.751) All possible precautions shall be exercised to prevent the accidental escape and ignition of gas. Whenever possible, potential sources of ignition should be eliminated
Competency Framework for Marine Engineer Class 6. Competency Framework for Marine Engineer Class 6
Table of Contents (MEC 6)... 1 Function: Operate Vessel Machinery and Systems... 1 Diesel engines.... 1 Operational procedures.... 3 Operate and monitor a vessel s engines and auxiliary equipment.... 4
CONFINED SPACE PROGRAM
California Institute of Technology CONFINED SPACE PROGRAM Caltech Environment, Health, and Safety Office 1200 E. California Blvd., M/C 25-6 Pasadena, CA 91125 Phone: 626.395.6727 Fax: 626.577.6028 Email:
Element D Services Plumbing
PART 1 - GENERAL 1.01 OVERVIEW A. This section addresses domestic cold, hot and hot water return distribution systems within and to five feet beyond building perimeter. PART 2 - DESIGN CRITERIA 2.01 GENERAL
Arapahoe County Residential Water Heater Installation and Inspection Guide
Arapahoe County Residential Water Heater Installation and Inspection Guide The attached handout is designed to be a general permit submittal and inspection guide covering most installation instances, however
MAINE DEPARTMENT OF ENVIRONMENTAL PROTECTION
Oxford Hills Bus Garage 36 Brown St, Norway, ME Oil Storage Inspection 2/20/14 CONDITIONS OBSERVED Underground Oil Storage: 12,000 gallon underground oil storage tank (split 10,000 gallon diesel/2,000
ACTIVITY NAME. Training Requirements for Spill Prevention Control and Countermeasures (SPCC) 40 CFR Part 112 Naval Air Station Corpus Christi Texas
ACTIVITY NAME Training Requirements for Spill Prevention Control and Countermeasures (SPCC) 40 CFR Part 112 Naval Air Station Corpus Christi Texas CY 2014 BOTTOM LINE UP FRONT To prevent oil discharges
Spill Prevention, Control and Countermeasure (SPCC) Training
Spill Prevention, Control and Countermeasure (SPCC) Training Fort Jackson 2015 Origins of SPCC Regulatory History 1972 Clean Water Act Oil Pollution Act of 1990 Spill Prevention Control and Countermeasures
THE UNIVERSITY OF MAINE COMPRESSED GAS CYLINDERS FOR SCUBA DIVING
THE UNIVERSITY OF MAINE COMPRESSED GAS CYLINDERS FOR SCUBA DIVING Department: The University of Maine Safety and Environmental Management Department Page i TABLE OF CONTENTS Section Title Page 1.0 Purpose
INSTALLATION INSTRUCTIONS GEO-BOOSTER TM
Table of Contents General Description 1 Parts list 1 Installation 2 New Ground Loop 2 Retrofit 4 Temporary 6 Troubleshooting 8 INSTALLATION INSTRUCTIONS GEO-BOOSTER TM General Description The Geo-Booster
Voltmaster Trash Pumps Model TSP2, TSP3 and TSP4
Model TSP2, TSP3 and TSP4 Owner s Manual July 2010 Table of Contents 1 Introduction...................................................... 1 1.1 Read before using..............................................
Flammable and Combustible Liquids. Slide 1 (of 23)
Flammable and Combustible Liquids Slide 1 (of 23) Introduction The two primary hazards associated with flammable and combustible liquids are explosion and fire Safe handling and storage of flammable liquids
Water Efficiency. Water Management Options. Boilers. for Commercial, Industrial and Institutional Facilities. Boiler Water Impurities
Water Efficiency Water Management Options Boilers for Commercial, Industrial and Institutional Facilities Boiler Water Impurities All boiler make-up water contains impurities. As clean steam is released
ABC CIRCUITS 10 Circuit Drive Circuit Town, IN 12345 SLUG CONTROL PLAN
ABC CIRCUITS 10 Circuit Drive Circuit Town, IN 12345 SLUG CONTROL PLAN The purpose of this plan is to provide detailed instructions for slug prevention and control. A complete copy of this plan is maintained
INSTRUCTION MANUAL. Boil-Out TABLE OF CONTENTS SAFETY WARNINGS 2-3 RESPONSIBILITY 3 INTRODUCTION 3 PRE-BOIL OUT PROCEDURES 3-5 BOIL OUT PROCESS 5-9
TABLE OF CONTENTS Description Page Number SAFETY WARNINGS 2-3 RESPONSIBILITY 3 INTRODUCTION 3 PRE-BOIL OUT PROCEDURES 3-5 BOIL OUT PROCESS 5-9 Indeck Keystone Energy, LLC. 5451 Merwin Lane, Suite 100 Erie,