Full-scale reconstruction and upgrade of the Budapest Research Reactor
|
|
|
- Jemima Patterson
- 10 years ago
- Views:
Transcription
1 Full-scale reconstruction and upgrade of the Budapest Research Reactor S. Tızsér Hungarian Academy of Sciences, KFKI Atomic Energy Research Institute, Budapest, Hungary Abstract. The BRR is a tank-type research reactor (RR), moderated and cooled by light water. The reactor, which went critical in 1959, is of Soviet origin. The initial thermal power was 2 MW. The first upgrade took place in 1967 when the power was increased from 2 MW to 5 MW, using a new type of fuel and a beryllium reflector. A full-scale reactor reconstruction and upgrade began in The upgraded 10 MW reactor received the operation license in November Since that time the reactor has been operating on average 3500 hours/year without any significant problem. In the early nineteen-eighties, about 8-10 years before the 30-year service life elapsed, discussion began to decide whether to extend the life of the reactor or start the preparation for final shut-down. Due to the general consensus of necessity for further reactor operation, in 1983 the government made the decision to go ahead with reconstruction and upgrading. The design work started in 1984 while the reconstruction project began in According to the modernization plan a partial decommissioning preceded the modernization, during which, with the exception of the civil engineering construction, all equipment was replaced. The reconstruction was finished in the technical sense by the end of 1990, but due to the political changes in the country, the institute could only apply for a license for reactor start up in In 1992 a consortium, namely Budapest Neutron Centre (BNC), was founded by four academic institutes to coordinate the reactor utilization and ensure a scientific background for managing the utilization strategy. With guidance from the BNC the experimental facilities around the beam ports were put into operation continuously in the first 2-3 years after the reactor start up, but investment in several facilities was postponed for several years. One of the postponed utilizations was the cold neutron source (CNS), which was eventually commissioned in The installation of a multi-frame time-of-flight (TOF) diffractometer was completed in Currently 12 research facilities are operating. Reviewing the last year period with respect to the reactor reconstruction milestones, including the preparation phases for restarting regular operation and the lunch of utilization, highlights many experiences. These experiences and lessons learned may prove useful to members of the RR community if faced with the dilemma of choosing between renewal or irreversible degradation. 1. Facility Background The Budapest Research Reactor (BRR) has been operated by the Hungarian Academy of Sciences KFKI Atomic Energy Institute (AEKI). The BRR was built in to a standard VVR-S design. It is a tank type reactor with light water moderation and cooling. The reactor went critical in March In 1967 the original power of 2 MW was increased to 5 MW with a change of fuel type from EK-10 to VVR-SM. The core was also modified by the installation of a solid beryllium reflector surrounding the core. After this first upgrade the reactor remained in operation until 1986 when it was a shut down for second upgrade. During its initial 27-year operation period the reactor was used as a basic facility for neutron scattering, radiochemistry, shielding investigation and radio-isotope production. More than this however, its mission was to establish and afterwards maintain the culture of nuclear research in the country. The main data and operational record Reactor type:... Light-water cooled and moderated tank-type reactor with beryllium reflector (the beryllium has been used since the time of 1 st upgrade) Physical start up:... March 25, Fuel assembly:... EK-10 then VVR-SM after the 1 st upgrade 1
2 Thermal power:... 2 MW then 5 MW after the 1 st upgrade Shut down for upgrade:... March 29, st upgrade:... Partial upgrade Physical start up after 1 st upgrade:... September 4, Shut down for reconstruction:... May 9, 1986 Operation record Average annual operation: on 2 MW; 3230 on 5 MW Total operation time: hours Total MW-days: MWday Shut down for upgrade:... May 9, Reconstruction and Upgrade Scope The first study of the development goals of the BRR was completed in 1974 by the Hungarian Academy of Sciences. Following this, several feasibility studies were also conducted by different organizations from the Hungarian and foreign scientific communities, including industrial representatives and the Kurtsatov Institute in Moscow. In these studies, the utilization demands were primarily considered from the perspective of fundamental and applied research but also stressed the importance of education, training and even industrial applications. Although these studies were mostly undertaken from a scientific perspective, the technical possibilities were also considered. 2.1.Strategic arguments for reconstruction and upgrade As a result of the preliminary studies mentioned above a general consensus had shaped for further reactor operation and even a demand for increasing flux density started to form. The strategic arguments for the necessity of further reactor operation and upgrade were grouped around four issues as follows: Radioisotope production: the reactor should ensure further isotope production for medical and industrial application. The importance of the production of short-lifetime isotopes was emphasized. Basic and applied research: research activities in the field of condensed matters, materials science, activation analysis, radiochemistry, nuclear gamma spectroscopy, reactor safety, health physics, etc. would be highly desirable to continue and/or extend or in some cases start. Technological and commercial applications: demands for investigations relating to nuclear reactions based on neutron, neutron induced embrittlement study, and the surveillance of the power plant's pressure vessels can only be met through the using of a research reactor. In addition to these are industrial and commercial applications: silicon doping, development of nuclear instrumentation, tests and certification for industry by neutron and gamma radiography etc. These promote prosperous service applications for reactor. Education and training: contribution to university and postgraduate education, training for nuclear engineering, and hosting international training courses (e.g. at the behest and with the participation of the IAEA) are all duties of the reactor and an essential source of political interest. 2.2.Decision for reconstruction and upgrade The first development conception [1] was elaborated in 1981 by the leading Hungarian power plant design company (ERİTERV). The conception was elaborated according to the new trends in nuclear research and applications, as well as modern reactor safety requirements including IAEA s recommendations (e.g. as defence-in-depth). The conception took into account all feasible and available possibilities such as: fuel questions, core configuration with increased irradiation places, technical capabilities including utilization issues, as well as future operation and maintenance questions. The 2
3 conception made a real cost-benefit analysis (comparable to a modern day SWOT analysis) and defined the design basis and design requirements including safety issues. Finally, on the basis of the considerations listed above, the reconstruction and upgrade project was drafted including the outline project schedule and resources needed including financial and human demands. Due to the general consensus and the well-founded strategic arguments for the necessity of further reactor operation, in 1983 the government made the decision to go ahead with the reconstruction and upgrade of the BRR. 3. Reconstruction and Upgrade Project After the political decision the budget calculations and project scheduling started immediately. The technical design (conceptual, technical and workshop design) and licensing work were started in The project implementation itself began in 1986, following 27 years of operation since initial reactor criticality. 3.1.Budget and project schedule A significant part of the investment grant was secured from governmental sources as the project was afforded so called capital state investment. To obtain this nomination, which ensured a high priority for the project, in many respects was due mostly to the strong support of the IAEA. However, domestic and foreign scientific public opinions also helped the project get a green light. Although the greatest part of the investment costs were covered by the governmental budget, the IAEA, in addition to the continued moral support, contributed financially with direct procurement of beryllium elements, primary pumps, valves built in the primary loop and hot cell facilities (manipulators and their accessories). The financial resources covered the reactor reconstruction and reactor upgrade costs in all respects. The reactor technically was made according to the design. All reactor systems and auxiliary units were implemented. However it become obvious at the very beginning that the investment of some utilization facilities should be postponed to avoid delaying the project start or (more likely) the reactor restart. Due to the careful preparation and financial planning the project was performed according to the reconstruction conception from the design stage right through to the implementation. Originally the shutdown was estimated to take place by the middle of However the design and licensing was delayed by one year, thus the partial shut down was performed in May The project implementation together with partial decommissioning was scheduled for 24-month period. The reconstruction was finished (in the technical sense) by the end of 1990 but due to the political changes in the country, the reorganization of the institute and other non-technical considerations, the AEKI could only apply for a license for reactor start up in 1992, after a two-year period of uncertainty. During these two years of indecision, the reactor was essentially ownerless and the reactor came very close to being dismounted (this possibility was considered as a real alternative). 3.2.Project management and human factor It should be mentioned that good management is a key factor in a successful project. This was the roll of the reactor staff during the reconstruction. Although the reconstruction had a general contractor for design and implementation, the project was supervised and guided by the close cooperation of the institute director and reactor manager. The reactor specific design (core design, thermo-hydraulic calculations, etc.) and safety assessments were also made by the nuclear physicist and engineers of the institute and these calculations were validated by the experts of the Kurtchatov Institute. The panel reviews of the technical designs were also fulfilled by the reactor experts of the institute. Regarding the effective job, the partial decommissioning work was entirely carried out by the reactor staff. Whereas the implementation was the task of the contactors. Nevertheless the quality controls, factory tests, the assembling and testing of subsystems, general functional tests, verification and validation 3
4 procedures, as well as the setting the baseline data (BLD: initial parameters as 0 -status) were done with the active participation of reactor staff too. It should be mentioned that all tasks concerning the reactor staff could be managed with the standard human sources available at the reactor. There was no needed for any additional temporary employment of workers. It should be mentioned also that during the two-year period of uncertainty, several well-trained experts were head-hunted by multinational companies coming into the country, and left the reactor. In some cases it was many years before their replacements could be found. 3.3.Technical and safety features of the reconstructed reactor In our case it was very important that the calculations and the foreign experience (Rossendorf, St. Petersburg) proved the biological shield of the reactor to be of sufficient strength with the increased power. In order to satisfy the safety criteria essential technical measures were made during the reconstruction. These steps resulted in the safety of the facility having been increased significantly. However, a lot of further technical measures have been made in consequence of reactor technique development. On the basis of the PSAR [2] these features can be summarized as follows: Core. The core furthermore is built of VVR-SM fuel assemblies. The number of fuel is increased in order to increase the power, but to increase the flux further the power produced by one element is increased as well. This fact necessitates that the cooling of assemblies be more intensive. It is ensured by the adequate design of the primary cooling system (pipes, pumps, heat exchangers, etc.) Safety and control rods. The increased number of irradiation places, where the neutron flux is relatively high, resulted in a rather complicated core. To ensure a suitably long refuelling cycle, that the number of control rods also had to be increased. Whereas before two safety rods were sufficient, now three rods are built in to guarantee a safe shut down. Measuring and control system. As the core became more sophisticated, control of the operational parameters became more important. Therefore the measuring and control system was required to be more reliable. The measurements are generally redundant (triplicate) and the safety and warning signals of the nuclear instrumentation are evaluated using a majority vote (two out of the three). Material of vessel and primary loop. One of the most important safety criteria is to avoid loss of coolant accident (LOCA) failures. Thus the materials of the primary loop were very carefully designed. The material of the vessel and grid is an aluminium alloy named R-AlMg2.5 (this is a modified version of the alloy 5052; the material composition is the same but the aluminium base material is purer). Material of the pipes is 18/8 type stabilised austenitic steel with nuclear grade certification. Safety systems. Two battery stations and two diesel generators were installed to ensure UPS for the emergency system. The safety logic is up-to-date and highly reliable. Fail-safe principle is realized in the actuation of the safety rods. Regarding emergency cooling a passive cooling system (gravity tank) was constructed which provides core cooling for one minute after the loss of electric power. In addition to the make-up water system, which was also improved, an emergency water feedback system was constructed to collect and feed back the water from the reactor well and pump room in case of LOCA type incidents. In addition a sprinkler system has been installed to cool the core in the case of extensive LOCA failure. Secondary cooling system. The previous open secondary circuit was replaced by a new, closed system, which contains two cooling towers. The secondary circuit is designed for 20 MW. Systems and measures to avoid radioactive release. The sealing of the reactor hall was strengthened to form a quasi-containment area. In addition a recirculation ventilation system was commissioned which could be activated if the limit of radioactive release would be violated. 4
5 Nuclear spent fuel (NSF) storage. A new AR-pool was installed with high-density grid with boron carbide absorbers. Also new storage pipes were installed in the AFR-pool, which could be hermetically sealed. Waste management. Two new storage tanks with 150 m 3 capacity each were installed with a renewed drainage network. The existing four storage wells were also renewed to ensure safe temporary storage for the gathered solid waste. 3.4.Licensing related analyses and obligatory documentations Due to the three-level design procedure (conceptual-, technical- and working designs) and the applied quality management and control system the project has been well documented and the certificates and records for demonstrating compliance with the requirements are settled and retained. The test records of commissioning procedures, as well as setting the so-called 0 -status of the systems are also retained. Prior to investment SAR (for licensing the shut-down and reconstruction), preliminary SAR (prior to reactor start-up for licensing the physical start-up) then final SAR (for operation licensing after physical and energetic start-up) were elaborated according to the status of the reconstruction project. According to nuclear safety regulations the most important documents for reactor start-up and continued operation were also elaborated. Of course the set of documents that served the licensing procedure on the basis of operational experiences were reviewed. In terms of the results of the periodic safety review (PSR), which was conducted in , it can be stated that the obligatory documents exist, that they are generally upto-date and have been improved by experience. 3.5.Utilization In 1992, during the period of uncertainty, a consortium, the Budapest Neutron Centre (BNC), was founded by four academic institutes to coordinate the reactor utilization and ensure a scientific background for managing the utilization strategy. With guidance from the BNC the experimental facilities around the beam ports were put into operation continuously in the first 2-3 years after the reactor start up. Later on, as the budget was available and/or ensured, the postponed utilization facilities were also put into operation. One of the postponed utilizations was the cold neutron source (CNS), which was eventually commissioned in 2001 with the strong financial support of IAEA and EC. In the framework of the utilization program in 2003 a hot cell rehabilitation project was completed with the financial support of a Hungarian Government grant. The installation of a multi-frame time-of-flight (TOF) diffractometer was completed in 2004 with the sponsorship of the Hahn-Meitner Institute Berlin and the institutes of BNC. 4. BRR after the reconstruction The newly independent AEKI applied for licensing in After having got the license for the first period, the start-up procedure of the reactor was begun in The reactor reached first criticality on 12 December The licensing and testing period took nearly a year (physical start-up, measurements at zero power, approaching nominal power, and at nominal power). The license for regular operation at nominal power was issued on 25 November 1993, without any restrictions. The regular operation started immediately on 26 November An aerial view of the site, Rector Hall and Control Room can bee seen in the attached photos (see Photos 1-3). Main technical data Vessel:... Aluminium alloy (height: 5685 mm; 2300 mm) Fuel:... VVR-SM(-M2); initial enrichment: 36 % 235U; Average burn-up: % Core geometry:... Hexagonal (height: 600 mm; 1000 mm) Equilibrium core: fuel assemblies (in single equivalent) Control:... 3 safety rods (B4C); 14 shim rods (B4C); 1 automatic (fine) rod (SS) 5
6 Nominal thermal power: MW Mean power density in the core: kw/litre Neutron flux density in the core:... 2,5 * n/cm 2 s (thermal in the flux trap) 1 * n/cm 2 s (approx. max. fast flux in the fast channel) Cooling system:...two closed loops (primary and secondary loop) Primary loop:... Q nominal : 1650 m 3 /h T inlet : 45 o C; T outlet : 50 o C Secondary loop:... Q nominal : 1850 m 3 /h Ventilation system:... Stack air flow rate: m 3 /h Pressure in technological rooms: gradually decreasing (-5-25 mm wh) Experimental channels:... Vertical irradiation places: 40 channels Horizontal irradiation beam ports: 8 radial & 2 tangential : Reactor Building with the Control Room being on the 2 nd floor 2: Reactor Hall 3: Engine room with air filters of the Air Ventilation System 4. Secondary Pump Room 5. Cooling Towers 6. Auxiliary Building accommodating the Diesel Generators and Compressed Air System 7. Building of the Liquid waste storage facilities (under the foreground area two storage tanks are accommodated 8. AFR-pool (with solid waste storage wells in the foreground area) 9. CNS s Measuring Hall 10. Cryo-system of CNS 11. TOF s Measuring Hall Photo 1 Aerial view of the BRR site 6
7 Photo 2 Panorama view of reactor hall Photo 3 Control Room 4.1.Operation record of the BRR From the time of start-up the upgraded reactor has been operating on average 3500 hours/year without any significant problem. The operation time record (scheduled and performed) is displayed in Fig. 1, while the operation cycles performed in 2005 are shown in Fig. 2. Fig. 1 Operation time record Fig. 2 Operation cycles in 2005 Upon comparing the yearly operation data (see Fig. 1) it can be seen that the actual operation was close to the scheduled plan (coincidence>93 %). From the restart in 1993 the BRR fulfilled 22 refuelling cycles (campaigns), as indicated on the graphs of Fig. 2 (the numbering on the graphs means: No. of campaign/no. of operation cycle). It can be seen from the figure that the length of a typical operation cycle is 234 hours at 10 MW nominal power and a campaign consists of 9 operation cycles. 4.2.Periodic Safety Review (PSR) in In line with Hungarian safety regulations [3] a periodic safety review (PSR) was conducted in , as a result of which the operation licence was renewed in November 2003 and is now valid until further notice. In the course of the PSR, validation test procedures carried out during the reactor upgrade were repeated. These were the most important parts of the validation test procedures of the reactor systems carried out during the system installation and commissioning in the period of the reactor upgrade. The latest results were compared with the BLD recorded years ago during the same validation test procedures. Based on the results of these comparisons and the operation data and event-audit the most important statements were taken as follows [4]: 7
8 There are no significant ageing problems, no unexpected degradation, and no abnormal phenomena appeared on any safety-critical system or component. The degradation is in accordance with the service life of the reactor. The 10-year service life of the reactor was safe, the operation passed without any OLC s violation. The assumptions of the PSAR are confirmed and its extreme conservatism justified by the experiences of operation and the reassessments of the FSAR. The operational environments including human factors and safety culture appearing in the everyday practices promote safe and reliable reactor operation. 4.3.Utilization The BRR is used for various purposes. This includes, amongst other things, for irradiation and neutron research, the latter being the main utilization (to serve as a neutron source). Irradiations are performed in vertical channels (the reactor has more than 40 channels, including six flux traps that can be used for isotope production and material testing; in one of the channels there is a pneumatic rabbit system that serves for neutron activation analysis). In contrast, experiments are carried out at the horizontal neutron beam ports. The reactor has ten beam ports (eight radial and two tangential) and now nearly all of them are in use. Currently 12 research facilities are operating around the beam ports of BRR. The present layout of the horizontal neutron beam facilities is shown in Fig. 3. Fig. 3 Layout of the horizontal neutron beam facilities at the BRR The utilisation of the reactor for basic- and applied research is considered to be the primary application of the reactor. In particular this includes the research fields of: condensed matter, radiochemistry, biological irradiations, reactor physics and technology (with the commissioning the CNS the material research 8
9 possibilities of the reactor were significantly increased). The reactor is used for isotope production also and, as an industrial application, for neutron radiography and activation analyses. The BRR s research facilities have been offered to the entire international user community, and in particular, for EU and associated countries of the European Union in the Access to Research Infrastructures action of the 6th Framework Programme (FP6). The BRR is foreseen to provide university and postgraduate education opportunities. In addition it should be used to fulfil training for specialists in the nuclear industry and those on international training courses. 5. Lessons learned Reviewing the last year period with respect to the reactor reconstruction milestones, including the preparation phases for restarting regular operation and the lunch of utilization, highlights many experiences. These experiences and lessons learned may prove useful to members of the RR community if faced with the dilemma of renewal or irreversible degradation. The most important conclusions (with lessons learned) can be summarized as follows: Conclusion No. 1. Looking back at the discussions to settle the future of the reactor; the final shutdown and decommission, as an alternative solution, was really not considered. It could not have happened because the leader representatives of the institute (former KFKI) had an enthusiastic and realistic vision for further reactor operation and utilization. They viewed the reactor operation both from the user and operator perspectives, took the initiative in time and led the discussions throughout the preparation period, Lesson learned: if the operators and users know what they want (they have a realistic vision) the unconvinced public can be persuaded. Conclusion No. 2. The preliminary discussion was begun halfway through the service life of the reactor. The real preparation began with the first official feasibility study, made about 8-10 years before the 30-year service life elapsed. Due to this long preparation time a general consensus was gained and well-founded strategic goals were elaborated. Lesson learned: The preparation of the M&R project has to start early to give sufficient time for elaborating good strategic goals with a general consensus of the scientific and industrial public. Conclusion No. 3. On the basis of the general consensus and the well-founded utilization arguments, not only the Hungarian decision makers were persuaded to opt for the reconstruction but the IAEA also. Thus the IAEA strongly sponsored the reconstruction with continued moral and financial support. In the preparation phase the moral support of the IAEA was considerable and sufficient to obtain the capital state investment status for the project. During the period of indecisiveness the moral support of the Agency that was based on the review of PSAR, helped to win public opinion for reactor start up. Lesson learned. The financial support of the Agency could be significant, but the moral support absolutely necessary. The moral sponsorship of the Agency can be considerable and it could strongly maintain the M&R project up to the commissioning in any respect. Conclusion No. 4. In spite of some budgetary deficiencies the project could start more or less according to the scheduled time and was completed in timely manner without any technical reduction. In the case of some utilization facilities, this was due, in part, to decisions taken during the beginning phase to postpone investments. Lesson learned. The method of postponed investment (or in other words sequential investment at utilization) can be applied. But it should be highlighted that this method can be applied for the utilization only! 9
10 Conclusion No. 5. The reactor management supervised the project from the beginning to the final stage. The management acted as a real owner of the project. The partial decommissioning (that effectively achieved IAEA Stage 3 decommission level) was carried out and comprehensively documented by the staff while the on-site job of the reconstruction (in spite of turnkey investment) was made also with their active participation. The experiences gained from this job form a stand-alone database and opinion base for further reactor operation (the everyday practice has already proved this statement). Lesson learned. The reactor management has to be the owner of the M&R project while the staff should participate in the M&R project. They together may personalize a proactive (foreseen and anticipated) sense of ownership. Conclusion No. 6. Although the BNC was founded to manage the utilization but during the period of uncertainty it could double the amount of public influence for reactor start up. Also, later on when this consortium put into operation the facilities around the reactor and started to manage the utilization strategy, it became obvious that the BNC could successfully represent the user interests, leaving the reactor management to focus on the safe reactor operation. Thus, a decision was made to separate the reactor operation matters from the utilization ones. Due to this management system, almost from the time of reactor start up the reactor manager was responsible for the safe reactor operation only, leaving the utilization issues to be managed by the BNC. Now this management system is highlighted as being one of the best operational practices. Lesson learned. Separating the reactor operation issues from the utilization ones can increase the capability to enforce the reactor s interest (two parties could lobby for the same goal). On the other this management solution, can also promote a safe reactor operation. 6. Future Plans The factors determining the future operation of the BRR and likely to provide the M&R with tasks in the forthcoming years are as follows: BRR s lifetime. Due to the overall reconstruction and upgrade the reactor lifetime was reset and is calculated from The lifetime of the deterministic elements (including the reactor vessel itself) is 30 years. This defines the service deadline of the reactor. Assuming that there will be no technical modernization to extend the lifetime 1, the deadline is the year Utilization factor. Considering the short and long-term research programs, international obligations and contract obligations for irradiation services (isotope production), users calculate a 40% annual availability factor ( 3500 operation hours in a year). Regarding the strategic issues of the research programs it is estimated that the reactor will work out its remaining service life (until 2023). Technical and human factors. The PSR certified that there are no significant ageing problems, no unexpected degradation and that no abnormal phenomena was detected in any safety-critical system or component of the reactor. However few technical renewals as safety increasing measures were prescribed by the LA s resolution closing the PSR (about 90% of which have already been completed). Regarding the human factor, a few years ago the aging of the personnel was a real problem but due to a systematic program effected after the PSR we have already employed six young colleagues in the last few years and this program is envisaged to continue. Fuel factors. As a result of a trilateral discussion between the U.S., RF and the IAEA, a project for repatriate the Russian origin RR fuel was lunched in The project, namely Russian Research Reactor Fuel Return Program (RRRFRP) is supported and coordinated by the U.S. Department of 1 Apart form the continued safety increasing measures and modernisation, no life extension plans are currently proposed. 10
11 Energy. The AEKI signed a contract for site preparation at the end of After signing this contract, two projects were started in this year. The first one is the site preparation for the transfer of Russian origin highly enriched uranium (HEU) SNF from the reactor, while the second one is the preliminary calculation for core conversion form HEU to LEU. Both projects provide tasks for the next 3-5 years. Licence factor. Although the operation licence renewed in 2003 is valid until further notice, the Hungarian legal system obliges operators of a nuclear facility to prepare a safety review every ten years. This means in practice the licence validity has to be confirmed by a repeated PSR in Financial factor. The basic annual operation costs are covered by the governmental budget. Other costs are paid for through grants and sponsorships, as well as income from industrial services. These sources together ensure: sustainable safe reactor operation including waste management resulting from the normal operation; investment in improved safety; and some modernization. The cost of core conversion and the procurement of fresh fuel incur extra charges. ACKNOWLEDGEMENTS During the full-scale reconstruction and upgrade, from the preparation phase to the licensing phase, the institute management and staff members of the BRR played a key role. The author is grateful to all those who actively participated or who supported the fulfilment of this project. The author is especially grateful to L. Gácsi, J. Gadó and T. Hargitai for their faithful managerial activities. In addition, the author would like to commend the contributions made by the late L. Frankl, Z. Gimesi, F. Szabó and G. Vizdos for their outstanding effort in support of the project. REFERENCES [1] Development Scope of Reactor Reconstruction. ERİTERV, Budapest, [2] Budapest Research Reactor, Safety Report, Volume 4: Safety Criteria and Analysis of the Possible Accident Situation. AEKI, Budapest, [3] Nuclear Safety Regulation No. 5 (Research Reactors). Hungarian Regulatory Body, [4] S. Tızsér, J. Gadó, K. Késmárky I. Vidovszky. Periodic Safety Review of the Budapest Research Reactor. International Conference on Topical Issues in Nuclear Installation Safety: Continuous Improvement of Nuclear Safety in a Changing World (IAEA-CN-120/4), pp Beijing, China, October IAEA, Reproduced with permission. 11
Published in the Official State Gazette (BOE) number 166 of July 10th 2009 [1]
Nuclear Safety Council Instruction number IS-22, of July 1st 2009, on safety requirements for the management of ageing and long-term operation of nuclear power plants Published in the Official State Gazette
PROPOSALS FOR UNIVERSITY REACTORS OF A NEW GENERATION
PROPOSALS FOR UNIVERSITY REACTORS OF A NEW GENERATION Introduction R.P. Kuatbekov, O.A. Kravtsova, K.A. Nikel, N.V. Romanova, S.A. Sokolov, I.T. Tretiyakov, V.I. Trushkin (NIKIET, Moscow, Russia) Worldwide,
V K Raina. Reactor Group, BARC
Critical facility for AHWR and PHWRs V K Raina Reactor Group, BARC India has large reserves of Thorium Critical facility Utilisation of Thorium for power production is a thrust area of the Indian Nuclear
Improving reactor safety systems using component redundancy allocation technique
NUKLEONIKA 2005;50(3):105 112 ORIGINAL PAPER Improving reactor safety systems using component redundancy allocation technique Aziz Shafik Habib, Hoda Abd-el Monem Ashry, Amgad Mohamed Shokr, Azza Ibrahim
NUCLEARINSTALLATIONSAFETYTRAININGSUPPORTGROUP DISCLAIMER
NUCLEARINSTALLATIONSAFETYTRAININGSUPPORTGROUP DISCLAIMER Theinformationcontainedinthisdocumentcannotbechangedormodifiedinanywayand shouldserveonlythepurposeofpromotingexchangeofexperience,knowledgedissemination
DEMONSTRATION ACCELERATOR DRIVEN COMPLEX FOR EFFECTIVE INCINERATION OF 99 Tc AND 129 I
DEMONSTRATION ACCELERATOR DRIVEN COMPLEX FOR EFFECTIVE INCINERATION OF 99 Tc AND 129 I A.S. Gerasimov, G.V. Kiselev, L.A. Myrtsymova State Scientific Centre of the Russian Federation Institute of Theoretical
Government Degree on the Safety of Nuclear Power Plants 717/2013
Translation from Finnish. Legally binding only in Finnish and Swedish. Ministry of Employment and the Economy, Finland Government Degree on the Safety of Nuclear Power Plants 717/2013 Chapter 1 Scope and
Fire Protection Program Of Chashma Nuclear Power Generating Station Pakistan Atomic Energy Commission 5/28/2015 1
Fire Protection Program Of Chashma Nuclear Power Generating Station Pakistan Atomic Energy Commission 5/28/2015 1 Nuclear Power in Pakistan Nuclear Power Plants Capacity (MWe) Year of Commissioning In
IMPLEMENTATION OF A MANAGEMENT SYSTEM FOR OPERATING ORGANIZATIONS OF RESEARCH REACTORS
IMPLEMENTATION OF A MANAGEMENT SYSTEM FOR OPERATING ORGANIZATIONS OF RESEARCH REACTORS Eduardo Kibrit 1, Afonso Rodrigues de Aquino 2 and Désirée Moraes Zouain 3 1 Centro Tecnológico da Marinha em São
Boiling Water Reactor Systems
Boiling Water (BWR) s This chapter will discuss the purposes of some of the major systems and components associated with a boiling water reactor (BWR) in the generation of electrical power. USNRC Technical
ANTEP 2015 Needs from China (NNSA)
ANTEP 2015 Needs from China (NNSA) 1 Content of training/education that Decommissioning plan and technologies 2 Background of above need 1. Design life of Qinshan NPP is 30 years, and it has been put into
Safety Analysis for Nuclear Power Plants
Regulatory Document Safety Analysis for Nuclear Power Plants February 2008 CNSC REGULATORY DOCUMENTS The Canadian Nuclear Safety Commission (CNSC) develops regulatory documents under the authority of paragraphs
REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL
EUROPEAN COMMISSION Brussels, 3.3.2015 COM(2015) 78 final REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL on the implementation of the work under the nuclear decommissioning assistance
How To Clean Up A Reactor Water Cleanup
General Electric Systems Technology Manual Chapter 2.8 Reactor Water Cleanup System TABLE OF CONTENTS 2.8 REACTOR CLEANUP SYSTEM... 1 2.8.1 Introduction... 2 2.8.2 System Description... 2 2.8.3 Component
Nuclear Energy of Ukraine - History
Nuclear Energy of Ukraine - History 1950-s Uranium Industry was started 1962 Ministry of Energy and Electrification of Ukraine was established(ukraine a Republic of Soviet Union) 1965 Unique Energy System
Public SUMMARY OF EU STRESS TEST FOR LOVIISA NUCLEAR POWER PLANT
1 (8) SUMMARY OF EU STRESS TEST FOR LOVIISA NUCLEAR POWER PLANT 1 LOVIISA NUCLEAR POWER PLANT Loviisa town is located approximately 90 km eastwards from Helsinki at the coast of Gulf of Finland. Loviisa
Cyber Security Design Methodology for Nuclear Power Control & Protection Systems. By Majed Al Breiki Senior Instrumentation & Control Manager (ENEC)
Cyber Security Design Methodology for Nuclear Power Control & Protection Systems By Majed Al Breiki Senior Instrumentation & Control Manager (ENEC) 1. INTRODUCTION In today s world, cyber security is one
Nuclear Power Plant Electrical Power Supply System Requirements
1 Nuclear Power Plant Electrical Power Supply System Requirements Željko Jurković, Krško NPP, [email protected] Abstract Various regulations and standards require from electrical power system of the
Technical Meeting on the Implications of the Fukushima Daiichi Accident on the Safety of Fuel Cycle Facilities. IAEA Headquarters Vienna, Austria
1 J7-TM-44883 Technical Meeting on the Implications of the Fukushima Daiichi Accident on the Safety of Fuel Cycle Facilities IAEA Headquarters Vienna, Austria 1 5 July 2013 INFORMATION SHEET 1. Background
HOW DOES A NUCLEAR POWER PLANT WORK?
HOW DOES A NUCLEAR POWER PLANT WORK? O n t a r i o P o w e r G e n e r a t i o n P U T T I N G O U R E N E R G Y T O U S G O O D E O N T A R I O P O W E R G E N E R A T I O N What a Nuclear Reactor Does
Nuclear Energy: Nuclear Energy
Introduction Nuclear : Nuclear As we discussed in the last activity, energy is released when isotopes decay. This energy can either be in the form of electromagnetic radiation or the kinetic energy of
Introductions: Dr. Stephen P. Schultz
Introductions: Dr. Stephen P. Schultz Vienna, Austria 1 3 September 2015 Work Experience Current Member Advisory Committee on Reactor Safeguards, U.S. Nuclear Regulatory Commission, 12/2011 Chair, Fukushima
Technical Challenges for Conversion of U.S. High-Performance Research Reactors (USHPRR)
Technical Challenges for Conversion of U.S. High-Performance Research Reactors (USHPRR) John G. Stevens, Ph.D. Argonne National Laboratory Technical Lead of Reactor Conversion GTRI USHPRR Conversion Program
Determination of the Comsumption Rate in the Core of the Nigeria Research Reactor-1 (NIRR-1) Fuelled with 19.75% UO 2 Material
Journal of Nuclear and Particle Physics 2016, 6(1): 1-5 DOI: 10.5923/j.jnpp.20160601.01 Determination of the Comsumption Rate in the Core of the Nigeria Research Reactor-1 (NIRR-1) Fuelled with 19.75%
Long Term Operation R&D to Investigate the Technical Basis for Life Extension and License Renewal Decisions
Long Term Operation R&D to Investigate the Technical Basis for Life Extension and License Renewal Decisions John Gaertner Technical Executive Electric Power Research Institute Charlotte, North Carolina,
Fission fragments or daughters that have a substantial neutron absorption cross section and are not fissionable are called...
KNOWLEDGE: K1.01 [2.7/2.8] B558 Fission fragments or daughters that have a substantial neutron absorption cross section and are not fissionable are called... A. fissile materials. B. fission product poisons.
ORC TURBOGENERATOR TYPE CHP - Organic Rankine Cycle Turbogenerator fed by thermal oil, for the combined production of electric energy and heat -
Doc. : 08C00031_e Date : 10.02.2009 Page : 1 / 9 ORC TURBOGENERATOR TYPE CHP - Organic Rankine Cycle Turbogenerator fed by thermal oil, for the combined production of electric - (Preliminary) Doc. : 08C00031_e
February 19, 2014. Senior Fellow, Nuclear Energy Systems & Services Division Power Systems Company
JAPAN-U.S. DECOMISSIONING AND REMEDIATION FUKUSHIMA RECOVERY FORUM February 19, 2014 Senior Fellow, Nuclear Energy Systems & Services Division Power Systems Company Toshiba global formation Information
Dynamic Behavior of BWR
Massachusetts Institute of Technology Department of Nuclear Science and Engineering 22.06 Engineering of Nuclear Systems Dynamic Behavior of BWR 1 The control system of the BWR controls the reactor pressure,
Nuclear power plant systems, structures and components and their safety classification. 1 General 3. 2 Safety classes 3. 3 Classification criteria 3
GUIDE 26 June 2000 YVL 2.1 Nuclear power plant systems, structures and components and their safety classification 1 General 3 2 Safety classes 3 3 Classification criteria 3 4 Assigning systems to safety
ADDITIONAL INFORMATION ON MODERN VVER GEN III TECHNOLOGY. Mikhail Maltsev Head of Department JSC Atomenergoproekt
ADDITIONAL INFORMATION ON MODERN VVER GEN III TECHNOLOGY Mikhail Maltsev Head of Department JSC Atomenergoproekt February 12, 2015 Introduction The main intention of this presentation is to provide: -
PROBABILISTIC RISK ASSESSMENT AND RISK MANAGEMENT OF A NUCLEAR POWER PLANT
PROBABILISTIC RISK ASSESSMENT AND RISK MANAGEMENT OF A NUCLEAR POWER PLANT 1 Introduction 3 2 Scope of application 3 3 Development and use of the PRA 4 3.1 General requirements 4 3.2 PRA during the design
IAEA Research Reactor Operations & Maintenance Support 2014 TRTR Meeting August 3rd-7th, 2014 Benson Hotel Portland Oregon
IAEA Research Reactor Operations & Maintenance Support 2014 TRTR Meeting August 3rd-7th, 2014 Benson Hotel Portland Oregon By Charles R Morris Personal Nuclear History Contents 1. Introduction 2. Digital
Generation IV Fast Reactors. Dr Richard Stainsby AMEC [email protected]
Generation IV Fast Reactors Dr Richard Stainsby AMEC [email protected] Contents The Generation IV international research programme on advanced reactors The case for fast reactors The technology:
Nuclear Safety Council Instruction number IS- 23 on in-service inspection at nuclear power plants
Nuclear Safety Council Instruction number IS- 23 on in-service inspection at nuclear power plants Published in the Official State Gazette (BOE) No 283 of November 24 th 2009 Nuclear Safety Council Instruction
Nuclear Consultancy & Engineering Services
Insert a caption to go with the photograph in here ITER, France Wednesday, 14 December 2011 Nuclear Consultancy & Engineering Services T H E N U C L E A R A T K I N S A S S Y S T E M A L L I A N C E CONSTRUCTION
Report WENRA Safety Reference Levels for Existing Reactors - UPDATE IN RELATION TO LESSONS LEARNED FROM TEPCO FUKUSHIMA DAI-ICHI ACCIDENT
Report WENRA Safety Reference Levels for Existing Reactors - UPDATE IN RELATION TO LESSONS LEARNED FROM TEPCO FUKUSHIMA DAI-ICHI ACCIDENT 24 th September 2014 Table of Content WENRA Safety Reference Levels
NUCLEAR POWER PLANT SYSTEMS and OPERATION
Revision 4 July 2005 NUCLEAR POWER PLANT SYSTEMS and OPERATION Reference Text Professor and Dean School of Energy Systems and Nuclear Science University of Ontario Institute of Technology Oshawa, Ontario
International Action Plan On The Decommissioning of Nuclear Facilities
International Action Plan On The Decommissioning of Nuclear Facilities A. Introduction Decommissioning is defined by the International Atomic Energy Agency (the Agency) as the administrative and technical
A MTR FUEL ELEMENT FLOW DISTRIBUTION MEASUREMENT PRELIMINARY RESULTS
A MTR FUEL ELEMENT FLOW DISTRIBUTION MEASUREMENT PRELIMINARY RESULTS W. M. Torres, P. E. Umbehaun, D. A. Andrade and J. A. B. Souza Centro de Engenharia Nuclear Instituto de Pesquisas Energéticas e Nucleares
WWER Type Fuel Manufacture in China
WWER Type Fuel Manufacture in China Yang Xiaodong P.O. Box 273, CJNF, YiBin City, Sichuan, China, [Fax: (+86)8318279161] Abstract: At CJNF, a plan was established for implementation of technical introduction
May 23, 2011 Tokyo Electric Power Company
Analysis and evaluation of the operation record and accident record of Fukushima Daiichi Nuclear Power Station at the time of Tohoku-Chihou-Taiheiyou-Oki-Earthquake (summary) May 23, 2011 Tokyo Electric
Office for Nuclear Regulation
ONR GUIDE CONTAINMENT: CHEMICAL PLANTS Document Type: Nuclear Safety Technical Assessment Guide Unique Document ID and Revision No: NS-TAST-GD-021 Revision 2 Date Issued: March 2013 Review Date: March
MCQ - ENERGY and CLIMATE
1 MCQ - ENERGY and CLIMATE 1. The volume of a given mass of water at a temperature of T 1 is V 1. The volume increases to V 2 at temperature T 2. The coefficient of volume expansion of water may be calculated
Piping Systems for Nuclear Power Industry. Prague, October 2011
Piping Systems for Nuclear Power Industry Prague, October 2011 Introduction of the company Leading Czech supplier of piping systems for power engineering 60 years of experience in the field of power industry
Safety Requirements Specification Guideline
Safety Requirements Specification Comments on this report are gratefully received by Johan Hedberg at SP Swedish National Testing and Research Institute mailto:[email protected] -1- Summary Safety Requirement
Design & Implementation about Mining Enterprise EAM (Enterprise Asset Management) System
Design & Implementation about Mining Enterprise EAM (Enterprise Asset Management) System Wang Huan, Li Changliang, Wang Dianlong Anshan Iron and Steel Group Corporation Mining Industry Company Abstract:
Gas Absorption Heat Pumps. Future proofing your heating and hot water
Gas Absorption Heat Pumps Future proofing your heating and hot water Gas Absorption Heat Pumps 1 Contents Gas Absorption Heat Pumps (GAHPs) The heating solution What is a Gas Absorption Heat Pump? How
New units at the Paks NPP background of the project and human resource issues
New units at the Paks NPP background of the project and human resource issues Prof. Dr. Attila Aszódi Government Commissioner, Paks-2 project Prime Minister s Office, Hungary Professor, Institute of Nuclear
Preliminary validation of the APROS 3-D core model of the new Loviisa NPP training simulator
Preliminary validation of the APROS 3-D core model of the new Loviisa NPP training simulator Anssu Ranta-aho, Elina Syrjälahti, Eija Karita Puska VTT Technical Research Centre of Finland P.O.B 1000, FI-02044
BWR Description Jacopo Buongiorno Associate Professor of Nuclear Science and Engineering
BWR Description Jacopo Buongiorno Associate Professor of Nuclear Science and Engineering 22.06: Engineering of Nuclear Systems 1 Boiling Water Reactor (BWR) Public domain image by US NRC. 2 The BWR is
Presentation by Mrs. Ton Nu Thi Ninh Former Ambassador of Viet Nam to EU Former Vice Chair Foreign Affairs Committee, National Assembly of Viet Nam
Presentation by Mrs. Ton Nu Thi Ninh Former Ambassador of Viet Nam to EU Former Vice Chair Foreign Affairs Committee, National Assembly of Viet Nam Viet Nam s nuclear energy planning & development What
Accidents of loss of flow for the ETTR-2 reactor: deterministic analysis
NUKLEONIKA 2000;45(4):229 233 ORIGINAL PAPER Accidents of loss of flow for the ETTR-2 reactor: deterministic analysis Ahmed Mohammed El-Messiry Abstract The main objective for reactor safety is to keep
Announcement of a new IAEA Co-ordinated Research Programme (CRP)
Announcement of a new IAEA Co-ordinated Research Programme (CRP) 1. Title of Co-ordinated Research Programme Design and engineering aspects of the robustness of digital instrumentation and control (I&C)
U.S. NUCLEAR REGULATORY COMMISSION STANDARD REVIEW PLAN OFFICE OF NUCLEAR REACTOR REGULATION
U.S. NUCLEAR REGULATORY COMMISSION STANDARD REVIEW PLAN OFFICE OF NUCLEAR REACTOR REGULATION NUREG-0800 (Formerly NUREG-75/087) 9.2.2 REACTOR AUXILIARY COOLING WATER SYSTEMS REVIEW RESPONSIBILITIES Primary
IAEA Safety Standards for Regulatory Activities
Safety Standards for Regulatory Activities April 2010 Gustavo Caruso Regulatory Activities Section Division of Nuclear Installation Safety International Atomic Energy Agency Content Safety Standards and
Operating Performance: Accident Management: Severe Accident Management Programs for Nuclear Reactors REGDOC-2.3.2
Operating Performance: Accident Management: Severe Accident Management Programs for Nuclear Reactors REGDOC-2.3.2 September 2013 Accident Management: Severe Accident Regulatory Document REGDOC-2.3.2 Canadian
Safety of New Nuclear Power Plants
Safety of New Nuclear Power Plants Example: VVER-1200/V491 H. Hirsch A. Y. Indradiningrat Workshop on the Paks II NPP Project Budapest, Energiaklub, 08.10.2014 New NPP in Paks: Reactor Type In the EIA
( 1 ) Overview of Safety Measures ( 2 ) Overview of Measures for Attaining Greater Safety and Reliability
Contents 1 Effort for New Regulatory Requirements ( 1 ) Overview of a Gist of New Regulatory Requirements in Nuclear Regulation Authority ( 2 ) Major Requirements of a Gist of New Regulatory Requirements
The Role of Nuclear Knowledge Management
The Role of Nuclear Knowledge Management A. Introduction The Agency has been a focal point for nuclear knowledge and information since its establishment in 1957. Nuclear knowledge management (NKM) came
Overview of the Multi-nuclide Removal Equipment (ALPS) at Fukushima Daiichi Nuclear Power Station. March 29, 2013 Tokyo Electric Power Company
Overview of the Multi-nuclide Removal Equipment (ALPS) at Fukushima Daiichi Nuclear Power Station March 29, 2013 Tokyo Electric Power Company Purpose of Installing the Multi-nuclide Removal Equipment Installation
The integrity evaluation of the reactor building at unit4 in the Fukushima Daiichi nuclear power station
The integrity evaluation of the reactor building at unit4 in the Fukushima Daiichi nuclear power station May 2012 Government and TEPCO s Mid-to Long Term Countermeasure Meeting Management Council Outline
Seoul Communiqué 2012 Seoul Nuclear Security Summit
Seoul Communiqué 2012 Seoul Nuclear Security Summit We, the leaders, gathered in Seoul on March 26-27, 2012, renew the political commitments generated from the 2010 Washington Nuclear Security Summit to
STUDIES FOR A MULTIPURPOSE RESEARCH REACTOR FOR THE CRCN/CNEN-PE
STUDIES FOR A MULTIPURPOSE RESEARCH REACTOR FOR THE CRCN/CNEN-PE Antônio C. O. Barroso*, José R. Maiorino, João M. L. Moreira **, José L. Bastos, José E. R. da Silva, Fernando R. de A. Lima, Mitsuo Yamaguchi,
Flow distribution and turbulent heat transfer in a hexagonal rod bundle experiment
Flow distribution and turbulent heat transfer in a hexagonal rod bundle experiment K. Litfin, A. Batta, A. G. Class,T. Wetzel, R. Stieglitz Karlsruhe Institute of Technology Institute for Nuclear and Energy
Test Section for Experimental Simulation of Loss of Coolant Accident in an Instrumented Fuel Assembly Irradiated in the IEA-R1 Reactor
2013 International Nuclear Atlantic Conference - INAC 2013 Recife, PE, Brazil, November 24-29, 2013 ASSOCIAÇÃO BRASILEIRA DE ENERGIA NUCLEAR - ABEN ISBN: 978-85-99141-05-2 Test Section for Experimental
Lead-Cooled Fast Reactor BREST Project Status and Prospects
資 料 4-3 第 11 回 GIF-LFR pssc (イタリア ピサ 2012 年 4 月 16 日 ) ロシア 側 発 表 資 料 V. S. Smirnov State Atomic Energy Corporation ROSATOM Open Joint-Stock Company N.A. Dollezhal Research and Development Institute of
RC-17. Alejandro V. Nader National Regulatory Authority Montevideo - Uruguay
RC-17 Radiation Protection in Waste Management and Disposal Implementing the Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management Alejandro V. Nader
Belgian Stress tests specifications Applicable to all nuclear plants, excluding power reactors 22 June 2011
Belgian Stress tests specifications Applicable to all nuclear plants, excluding power reactors 22 June 2011 Introduction Considering the accident at the Fukushima nuclear power plant in Japan, the European
The Physics of Energy sources Nuclear Reactor Practicalities
The Physics of Energy sources Nuclear Reactor Practicalities B. Maffei [email protected] www.jb.man.ac.uk/~bm Nuclear Reactor 1 Commonalities between reactors All reactors will have the same
Establishing and Operating a Quality Management System Experiences of the EUROSAI Training Committee Seminar in Budapest
Workshop Management of an SAI Berlin (Germany), 9-11 April 2008 Establishing and Operating a Quality Management System Experiences of the EUROSAI Training Committee Seminar in Budapest (Dr. Árpád Kovács,
THE DECOMMISSIONING OF COMMERCIAL MAGNOX GAS XA9848063 COOLED REACTOR POWER STATIONS IN THE UNITED KINGDOM
THE DECOMMISSIONING OF COMMERCIAL MAGNOX GAS XA9848063 COOLED REACTOR POWER STATIONS IN THE UNITED KINGDOM G. HOLT Magnox Electric pic, Berkeley Centre, Berkeley, Gloucestershire, United Kingdom Abstract
RADIOACTIVE WASTE MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES AUSTRALIA NATIONAL NUCLEAR ENERGY CONTEXT
RADIOACTIVE WASTE MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES AUSTRALIA NATIONAL NUCLEAR ENERGY CONTEXT Australia is one of the only developed countries that does not use electricity, either indigenous
21.1 Functions, Basic Configuration, and Interfaces
21 (6.2.M) Site Services Building 21.1 Functions, Basic Configuration, and Interfaces 21.1.1 Functions The primary functions performed by the site services building are to house, support, provide a suitable
Radiation Protection s Benefits in the Production of Iodine-131
Radiation Protection s Benefits in the Production of Iodine-131 Daniel M. Cestau *, Ariel N. Novello, Cecilia Bravo, Pablo Cristini, Marcelo Bronca, Eduardo Carranza, Ricardo Bavaro, Julián Cestau and
8 Emergency Operating Procedures (EOPs) and Severe Accident Management Guidelines (SAMGs) - Issue 06
8-1 8 Emergency Operating Procedures (EOPs) and Severe Accident Management Guidelines (SAMGs) - Issue 06 Table of contents 8 Emergency Operating Procedures (EOPs) and Severe Accident Management Guidelines
Long term support solutions for Nuclear Instrumentation & Control
Long term support solutions for Nuclear Instrumentation & Control...ensuring the long-term safety and availability of your I&C systems. 02 LONG TERM SUPPORT SOLUTIONS Maintaining the safe and reliable
MISSION REPORT ON THE INTEGRATED NUCLEAR INFRASTRUCTURE REVIEW (INIR)
MISSION REPORT ON THE INTEGRATED NUCLEAR INFRASTRUCTURE REVIEW (INIR) Counterpart: Ministry of Economy 18 to 22 March 2013 Warsaw, Poland CONTENTS 1. EXECUTIVE SUMMARY... 3 2. INTRODUCTION... 5 3. OBJECTIVES
Westinghouse AP1000 PWR and the Growing Market for New Nuclear Power Plants
Westinghouse AP1000 PWR and the Growing Market for New Nuclear Power Plants Westinghouse Electric Company & The Nuclear Fuel Cycle Royal Commission - South Australia November 4, 2015 1 AP1000 is a trademark
The Price-Anderson Act and the Three Mile Island Accident
The Price-Anderson Act and the Three Mile Island Accident OECD/NEA Workshop Nuclear Damages, Liability Issues, and Compensation Schemes Overview Overview of Nuclear Liability in U.S. Three Mile Island
TURKISH NUCLEAR POWER PROGRAMME NUCLEAR ENERGY PROJECT IMPLEMENTATION DEPARTMENT
TURKISH NUCLEAR POWER PROGRAMME NUCLEAR ENERGY PROJECT IMPLEMENTATION DEPARTMENT 0 75 75 150 km Kocaeli (İzmit) BOSBORUS 0 İzmir Konya ANKARA 150 mi İçel (Mersin) REPUPLIC OF CYPRUS Iskenderun Adana SYRIA
NUCLEAR POWER OVERALL GOOD FOR THE SOCIETY Finnish German Energy Day, 7th November 2012
NUCLEAR POWER OVERALL GOOD FOR THE SOCIETY Finnish German Energy Day, 7th November 2012 Tanhua Jarmo Teollisuuden Voima Oyj 2 EU ENERGY ROADMAP 2050 NUCLEAR POWER IN ALL SCENARIOS Consumption of electricity
The Piping System Model a New Life Cycle Document. Elements of the Piping System Model
Piping System Model as a Life Cycle Document White Paper Introduction When designing piping systems, a variety of documents are created providing the details necessary to design, purchase, build, and test
INSPECTION OF STATE OF SPENT FUEL ELEMENTS STORED IN RA REACTOR SPENT FUEL STORAGE POOL
CH01$0025 INSPECTION OF STATE OF SPENT FUEL ELEMENTS STORED IN RA REACTOR SPENT FUEL STORAGE POOL V. G. ADEN, S. YU. BULKIN, A. V. SOKOLOV Research and Development Institute of Power Engineering, P. Box
The ACR : Advanced Design Features for a Short Construction Schedule
Transactions of the 17 th International Conference on Structural Mechanics in Reactor Technology (SMiRT 17) Prague, Czech Republic, August 17 22, 2003 Paper # S01-3 The ACR : Advanced Design Features for
Nuclear Safety Regulation Reform in Japan
Nuclear Safety Regulation Reform in Japan 18th January 2012 Shuichi KANEKO Cabinet Secretariat Government of JAPAN 1 Contents Background of the Reform Process of the Reform Basic System for Nuclear Safety
Training Meeting on Post-Fukushima Research and Development Strategies and Priorities
Training Meeting on Post-Fukushima Research and Development Strategies and Priorities IAEA Headquarters Vienna, Austria 15 18 December 2015 Ref. No.: 622-I3-TR-48057 Information Sheet A. Background Against
Edgar Koonen 12th IGORR Conference October 27-31 2009, Beijing P.R.China. The BR2 reactor at SCK CEN, Mol
Edgar Koonen 12th IGORR Conference October 27-31 2009, Beijing P.R.China The BR2 reactor at SCK CEN, Mol BR2 reactor = one of the major high flux MTR type reactors of the world, operated by SCK CEN a tank-in-pool
GENERAL REGULATIONS ON ENSURING SAFETY OF NUCLEAR POWER PLANTS OPB-88/97, NP-001-97 (PNAE G- 01 011-97) Cover page. Contents
GENERAL REGULATIONS ON ENSURING SAFETY OF NUCLEAR POWER PLANTS OPB-88/97, NP-001-97 (PNAE G- 01 011-97) Cover page Contents Federal Nuclear and Radiation Safety Authority of Russia (Gosatomnadzor of Russia)
Prospect of Hitachi Nuclear Business (Boiling Water Reactor)
Prospect of Hitachi Nuclear Business (Boiling Water Reactor) 42 Prospect of Hitachi Nuclear Business (Boiling Water Reactor) Masahito Yoshimura Shoichiro Kinoshita Hiroshi Arima Nobuo Tada OVERVIEW: To
L.S. de Carvalho, J. M de Oliveira Neto 1. INTRODUCTION IAEA-CN-164-5P01
IAEA-CN-164-5P01 Advanced Technology Application Station Blackout Core Damage Frequency Reduction The Contribution of AN AC Independent Core Residual Heat Removal System L.S. de Carvalho, J. M de Oliveira
Overview of Worldwide Nuclear Decommissioning
Overview of Worldwide Nuclear Decommissioning Patrick O Sullivan International Atomic Energy Agency 12 th December 2014 International Seminar Nuclear decommissioning : an opportunity for global and sustainable
Radioactive waste managment in Estonia past, present and future
Radioactive waste managment in Estonia past, present and future Ivo Tatrik [email protected] Content 1. Status of ALARA 2. Decomission of Paldiski Former Navy Submarine Training Centre 3. Decomission
Green House, Hungary
Further information Skanska AB www.skanska.com Contact Noel Morrin, SVP Sustainability & Green Support [email protected] Green House, Hungary Case Study 109 Aspects of Sustainability This project
INTERNATIONAL ATOMIC ENERGY AGENCY WAGRAMERSTRASSE 5, P.O. BOX 100, A-1400 VIENNA, AUSTRIA FACSIMILE: (+43 1) 26007, TELEPHONE: (+43 1) 2600
INTERNATIONAL ATOMIC ENERGY AGENCY WAGRAMERSTRASSE 5, P.O. BOX 100, A-1400 VIENNA, AUSTRIA FACSIMILE: (+43 1) 26007, TELEPHONE: (+43 1) 2600 - CRAFT - The International Project on COMPLIMENTARY SAFETY