Improving the Efficiency of Managing a Construction Project: A Collaborative Web-based Solution

Size: px
Start display at page:

Download "Improving the Efficiency of Managing a Construction Project: A Collaborative Web-based Solution"

Transcription

1 Improving the Efficiency of Managing a Construction Project: A Collaborative Web-based Solution 2011 WEAU Mid Year Conference Prepared by Jeremy Williams, PE Given by Clint Rogers, PE 1

2 Jeremy s CM Background Quail Creek WTP Expansion Orem 20 MG Reservoir Weber South WTP Expansion AVWTP Process Improvements Project 2

3 Sludge Drying Beds Backwash Tank Utility/Chlorine Bldg. Floc Basins Operations/Chemical Bldg. Filter Bldg. Backwash Water Recovery Bldg. 1MG Clearwell Pump Station 3

4 4

5 Carollo Engineers and CUWCD have found that efficiencies and collaboration can be greatly improved by using a web-based document management system for construction management. 5

6 Why is This Important? Communication with design team Document changes and clarifications during construction Communication between contractor and its subcontractors and field personnel Reference material for Owner Submittal integrity is everything 6

7 Outline Evolution of document management Project overview Our experience with web-based document management 7

8 First, Man Created Paper... And it Was Awesome. 8

9 Then We Discovered the Electron... 9

10 More Electrons... CONTRACT MANAGEMENT SOFTWARE FILE SHARING OR COLLABORATION SOFTWARE 10

11 Web-based Document Management Prolog PMWeb Procore EaDoc And many others 11

12 Carollo Engineers and CUWCD evaluated the different methods and chose the one that best met the project s needs. 12

13 Our Criteria Method chosen needed to allow for Owner and Engineer to work together as the Construction Management Team (CMT) Full electronic document management to facilitate information transfer and provide for Owner s records after the project is complete 13

14 Case Study: Ashley Valley WTP Located just north of Vernal, Utah (150 mi. from Owner, Engineer, and Contractor offices) Original Construction from Began Production of Culinary Water in mgd Original Design Capacity (30 mgd ultimate) Direct Filtration, Declining Rate Treatment Plant Two Water Sources Treatment Challenges/Constraints Water Quality Regulations 14

15 Sludge Drying Beds Backwash Tank Utility/Chlorine Bldg. Floc Basins Operations/Chemical Bldg. Filter Bldg. Backwash Water Recovery Bldg. 1MG Clearwell Pump Station 15

16 AVWTP Process Improvement Project (cont.) Construction Schedule July 30, 2010 to October 15, 2012 Milestone 1: March 15, 2011 Milestone 2: March 15, 2012 Substantial Completion: April 30, 2012 Project Cost $12.3 million New Processes Floc/Sed Building, Clarifier, Filter Modifications, valve vaults, yard piping, misc site work 16

17 Potential Project Challenges Location Coordination Complexity Efficiency Things are not always as they appear 17

18 Web-based Document Management Best Fit the Project s Needs EaDoc chosen by CMT 18

19 Project Set Up Under Profile Tab 19

20 Flow Chart defines Chain of Communication 20

21 Flow Chart defines Chain of Communication 21

22 Start Tab Memos, Daily Logs, Minutes 22

23 Work Tab Submittals, RFIs, etc. 23

24 Documents Tab Specs, Drawings, Reference Docs 24

25 Finance Tab Pay Requests, PCOs, COs 25

26 Help Tab User s Manual and Online Support only a click away 26

27 Document Features All Items Are Similar 27

28 Document Features All Items Are Similar 28

29 Document Features Cover Sheets Automatically Generated 29

30 Document Features History Automatically Created with Electronic Signatures 30

31 Benefits Logs, history, electronic signatures are automatically created eliminates as much potential human error as possible 31

32 Benefits Logs are fully searchable and reports are easily customized. 198 Not shared 32

33 Benefits Use Reference Tab for File Sharing 33

34 Other Benefits Electronic signatures, recorded histories Chain of communication controlled by project organization, follows the flow chart Pure electronic archive and directories created ready to turn over to the Owner at the end of the project Online support 34

35 Drawbacks Cost - $ upfront Learning curve 35

36 Drawbacks Have to learn program defaults, what works, what doesn t work, customization Files are only as good as what s put in X 36

37 Contractor s Opinion: We want to use this on all of our future projects, so much so that we ll pay for it if the Owner doesn t. Justin Morris Morris Electric 37

38 Conclusion Web-based solution instrumental for CM Team approach ability to collaborate greatly increased without slowing the project down Efficiency of document transfer among all parties greatly increased Web-based solution worth the cost hundreds of hours of admin time saved over the course of the project 38

39 Conclusion Owner will receive complete record documents for the project, already archived and easily filed 39

40 O&M Manuals of Yesterday 40

41 Carollo SharePoint EOM 3D Images 41

42 Acknowledgements Central Utah Water Conservancy Magna Water District Jordan Valley Water Conservancy District Provo River Water Users Association 42

43 43

44 44

45 45

Terms of Reference. Aqaba Water and Wastewater Utility Asset Valuation

Terms of Reference. Aqaba Water and Wastewater Utility Asset Valuation Technical Support for Procurement and Project Management and Private Sector Participation to the Ministry of Water and Irrigation, Water Authority of Jordan and the Jordan Valley Authority Support for

More information

William E. Dunn Water Reclamation Facility. Facility Overview & Information

William E. Dunn Water Reclamation Facility. Facility Overview & Information William E. Dunn Water Reclamation Facility Facility Overview & Information General Area Served: Plant History Facility Highlights Northern Pinellas County St. Joseph Sound to East Lake Road (E/W) Tampa

More information

DGS Prolog Manager & Prolog Converge User Manual

DGS Prolog Manager & Prolog Converge User Manual DGS Prolog Manager & Prolog Converge User Manual Table of Contents Prolog Overview Flowchart 1 Entering a New Project 2 Solicitations 7 Contracts Module 14 Change Orders 21 Change Order Workflow Diagram

More information

CWD BALDWIN PLANT NEW RESIDUALS HANDLING SYSTEM

CWD BALDWIN PLANT NEW RESIDUALS HANDLING SYSTEM CWD BALDWIN PLANT NEW RESIDUALS HANDLING SYSTEM OTCO Water Workshop March, 2011 Frank Woyma Plant Manager Nick Pizzi Vice-President EE&T ENVIRONMENTAL ENGINEERING & TECHNOLOGY, INC. Objectives Review the

More information

World s #1 most widely used construction management software.

World s #1 most widely used construction management software. World s #1 most widely used construction management software. WHAT IS PROCORE? One platform. All your project management needs. Construction project management has evolved beyond the traditional pen, paper,

More information

City of South Haven Water Plant Projects. Monthly Status Report

City of South Haven Water Plant Projects. Monthly Status Report City of South Haven Water Plant Projects Monthly Status Report Report 13 October 19, 2009 Project No. G07734WP CITY OF SOUTH HAVEN WATER PLANT PROJECTS MONTHLY PROGRESS REPORT NO. 13 PREPARED FOR: THE

More information

Oracle Primavera P6 Project Portfolio Management & Oracle Primavera Contract Management

Oracle Primavera P6 Project Portfolio Management & Oracle Primavera Contract Management Oracle Primavera P6 Project Portfolio Management & Oracle Primavera Contract Management Primavera Project Management Solution Seattle, Washington nu-solutions.com Anchorage, Alaska Who we are Nu Solutions

More information

Advanced_O&M_Task_List_Example_Tool_06_02_16: O&M Example

Advanced_O&M_Task_List_Example_Tool_06_02_16: O&M Example Name Type of O&M Activity O&M Activity Frequency O&M Tracking Location Runa Valves Exercise mainline valves. Semi Inspect pumps, motors, and controls Once per week / Onsite Kreger 6 inch PVC Lakeview Heights

More information

Indiana s Newest Filtration Facility; East Chicago

Indiana s Newest Filtration Facility; East Chicago Indiana s Newest Filtration Facility; East Chicago Innovation and Value-Added Benefits Behind East Chicago s Membrane Treatment Facility Eric Horvath, PE and Kara M. Boyles, PhD, PE August 1, 2012 Presentation

More information

John P. Masek, PE, SE Summary of Education and Experience

John P. Masek, PE, SE Summary of Education and Experience EDUCATION Washington University, Saint Louis, Missouri, B.S. Civil Engineering, 1981 Washington University, Saint Louis, Missouri, M.S. Structural Engineering, 1981 GPA= 3.6/4.0 Thesis: A Comparison of

More information

Projectmates User Guide for Montclair State University Facilities Construction Projects

Projectmates User Guide for Montclair State University Facilities Construction Projects Projectmates User Guide for Montclair State University Facilities Construction Projects Systemates, Inc. Dallas, Texas 214.217.4100 www.montclair.edu/projectmates Copyright 2013 Systemates, Inc. Page 1

More information

REQUEST FOR PROPOSAL. for CONSTRUCTION MANAGEMENT SERVICES. for the ENCINA WASTEWATER AUTHORITY FY 2015 MAJOR PLANT REHABILITATION PROJECT

REQUEST FOR PROPOSAL. for CONSTRUCTION MANAGEMENT SERVICES. for the ENCINA WASTEWATER AUTHORITY FY 2015 MAJOR PLANT REHABILITATION PROJECT REQUEST FOR PROPOSAL for CONSTRUCTION MANAGEMENT SERVICES for the ENCINA WASTEWATER AUTHORITY FY 2015 MAJOR PLANT REHABILITATION PROJECT Ref: Admin.15 12265c September 23, 2015 Proposals Due November 2,

More information

Request for Proposals PROFESSIONAL SERVICES FOR DRINKING WATER, WASTEWATER AND STORMWATER PROJECTS OPEN-END CONTRACTS 2016-18

Request for Proposals PROFESSIONAL SERVICES FOR DRINKING WATER, WASTEWATER AND STORMWATER PROJECTS OPEN-END CONTRACTS 2016-18 Request for Proposals PROFESSIONAL SERVICES FOR DRINKING WATER, WASTEWATER AND STORMWATER PROJECTS OPEN-END CONTRACTS 2016-18 Page 2 of 8 1. INTRODUCTION Capital Region Water (CRW) is requesting proposals

More information

HTTP communication between Symantec Enterprise Vault and Clearwell E- Discovery

HTTP communication between Symantec Enterprise Vault and Clearwell E- Discovery Securing HTTP communication between Symantec Enterprise Vault and Clearwell E- Discovery Requesting and Applying an SSL Certificate to secure communication ion from Clearwell E-Discovery to Enterprise

More information

April 30, 2013 E M. Environmental Management. www.em.doe.gov. safety performance cleanup closure

April 30, 2013 E M. Environmental Management. www.em.doe.gov. safety performance cleanup closure April 30, 2013 1 Facility Stabilization and Deactivation C.1.3 - (Period 3) After facilities are turned over by USEC and accepted by DOE: Perform minimal stabilization and deactivation activities for facilities

More information

DRAFT Public Outreach Document for What s an SSMP?

DRAFT Public Outreach Document for What s an SSMP? DRAFT Public Outreach Document for What s an SSMP? This easy to read document is developed and provided to interested parties to assist in educating cities, agencies, their management, elected officials

More information

CIMS Information Systems Used to Manage Capital Projects. Samuel Hutchins September 14, 2010

CIMS Information Systems Used to Manage Capital Projects. Samuel Hutchins September 14, 2010 CIMS Information Systems Used to Manage Capital Projects Samuel Hutchins September 14, 2010 Department Overview Department Created in October 2007 to manage Capital Improvements Program Cost recovery for

More information

Facing The Challenges In Houston s Water System: Past, Present, and Future

Facing The Challenges In Houston s Water System: Past, Present, and Future Facing The Challenges In Houston s Water System: Past, Present, and Future Jun Chang, P.E. D.WRE Deputy Director Department of Public Works and Engineering Presented to HCEC February 17, 2012 Past Regulatory

More information

Ann Arbor Wastewater Treatment Plant Facilities Renovations Project September 2015

Ann Arbor Wastewater Treatment Plant Facilities Renovations Project September 2015 Ann Arbor Wastewater Treatment Plant Facilities Renovations Project September 2015 The Facilities Master Plan was completed in 2004 and identified the need for improvements to the City of Ann Arbor s Wastewater

More information

How To Water System

How To Water System Mid-Monroe Water System: Soluble Iron and Manganese Removal via Oxidation & Filtration Daniel Rickard, P.E. Engineering Project Manager Pennsylvania-American Water Company Who Is American Water We are

More information

Historic Flood Impact on the Nashville Drinking Water System. Scott Potter, Director Metro Water Services, Nashville, TN

Historic Flood Impact on the Nashville Drinking Water System. Scott Potter, Director Metro Water Services, Nashville, TN Historic Flood Impact on the Nashville Drinking Water System Scott Potter, Director Metro Water Services, Nashville, TN Historic Event = 13.53 /48 Hours May 1 6.32 of Rain = 3rd greatest one-day rainfall

More information

Dan Ott Managing Engineer Collection System Johnson County Wastewater, KS and Rick Nelson CH2M HILL

Dan Ott Managing Engineer Collection System Johnson County Wastewater, KS and Rick Nelson CH2M HILL Dan Ott Managing Engineer Collection System Johnson County Wastewater, KS and Rick Nelson CH2M HILL What is JCW s strategy for meeting wet weather performance targets? SSO s Basement Back-ups Serving Johnson

More information

NEVADA CITY WASTEWATER TREATMENT INQUIRY

NEVADA CITY WASTEWATER TREATMENT INQUIRY NEVADA CITY WASTEWATER TREATMENT INQUIRY REASON FOR INVESTIGATION The 2003-2004 Grand Jury investigated the status of wastewater treatment in unincorporated Nevada County. This year, the Grand Jury investigated

More information

Description of the Water Conserv II Facility

Description of the Water Conserv II Facility Description of the Water Conserv II Facility Introduction The Water Conserv II (WCII) Water Reclamation Facility provides service to a majority of the southwest section of Orlando. The WCII facility has

More information

NextGEN Project Managers

NextGEN Project Managers Presenter Ed Coffin Product Advisor/Product Trainer/Database Consultant ConEst Software Systems [email protected] www.conest.com Estimating and Project Management The link between a well built estimate

More information

Upper Occoquan Service Authority Centreville, Virginia A Case Study

Upper Occoquan Service Authority Centreville, Virginia A Case Study Upper Occoquan Service Authority Centreville, Virginia A Case Study Dennis Clough, Managing Director Energy Systems Group Upper Occoquan Service Authority About the Upper Occoquan Service Authority 54

More information

Residuals Management Somersworth Drinking Water Treatment Facility. Ian Rohrbacher, Treatment Operator IV

Residuals Management Somersworth Drinking Water Treatment Facility. Ian Rohrbacher, Treatment Operator IV Residuals Management Somersworth Drinking Water Treatment Facility A HISTORICAL OVERVIEW OF SURFACE WATER TREATMENT RESIDUALS HANDLING Ian Rohrbacher, Treatment Operator IV Background We are a Grade III

More information

Highly Colored Water Removal Using Nanofiltration Membranes at the Colored Water Treatment Facility. Adam Zacheis, Project Manager Carollo Engineers

Highly Colored Water Removal Using Nanofiltration Membranes at the Colored Water Treatment Facility. Adam Zacheis, Project Manager Carollo Engineers Highly Colored Water Removal Using Nanofiltration Membranes at the Colored Water Treatment Facility Adam Zacheis, Project Manager Carollo Engineers Topics 1. Background - Mesa Water District (Mesa) Water

More information

OPERATIONS & MAINTENANCE FY 2012-2013 Adopted Budget

OPERATIONS & MAINTENANCE FY 2012-2013 Adopted Budget SERVICE DESCRIPTION To maintain all of the transferred and accepted infrastructure within the district including water, wastewater, and stormwater systems, streetlights, traffic signals, and landscaping

More information

North San Jose Neighborhoods Planning Taskforce

North San Jose Neighborhoods Planning Taskforce North San Jose Neighborhoods Planning Taskforce Key Topics Water Supply Flooding Related Topics Storm Water Storm Sewer Sanitary Sewer Water Conservation Treatment Plant Water Background Responsible Agencies

More information

Town of New Castle Utility Department Introduction

Town of New Castle Utility Department Introduction Town of New Castle Utility Department Introduction Town of New Castle Utility Department Mission Statement Our commitment is to ensure that our customers receive high quality water and wastewater treatment

More information

Backing Up, Restoring, & Transferring PCLaw Data

Backing Up, Restoring, & Transferring PCLaw Data Contents Closing All Applications Creating PCLaw Backups Transferring Data to Another Location Restoring Data Transferring Data from Another Location PCLaw Data Export Modules About Backing Up, Restoring,

More information

Terry Biederman, PE- Director of Public Works Greg Gucwa, PE- Principal Johnson and Anderson Engineering

Terry Biederman, PE- Director of Public Works Greg Gucwa, PE- Principal Johnson and Anderson Engineering DON T JUST REHAB IT, RENEW IT! WATERFORD TOWNSHIP, MICHIGAN IMPROVEMENTS TO A 3.0 MGD SEWAGE PUMPING STATION Terry Biederman, PE- Director of Public Works Greg Gucwa, PE- Principal Johnson and Anderson

More information

A Long-Range Plan: Melbourne s Drinking Water Supply

A Long-Range Plan: Melbourne s Drinking Water Supply April 2002 A Long-Range Plan: Melbourne s Drinking Water Supply The long-term water supply of South Brevard County must be dependable, flexible, and affordable. With those goals in mind, we continue to

More information

APPENDIX F. Baker County. Mason Dam Hydroelectric Project FERC No. P-12686. Turbidity Monitoring Plan

APPENDIX F. Baker County. Mason Dam Hydroelectric Project FERC No. P-12686. Turbidity Monitoring Plan APPENDIX F Baker County Mason Dam Hydroelectric Project FERC No. P-12686 Turbidity Monitoring Plan April 2011 857 Table of Contents 1.0 Introduction 1 2.0 Purpose and Scope 2 3.0 Turbidity Monitoring and

More information

[UNIFIER USER MANUAL]

[UNIFIER USER MANUAL] 2015 [UNIFIER USER MANUAL] This manual is intended to provide HRSD commissioned Engineers and Contractors guidance on using the Unifier Enterprise Project Management System TABLE OF CONTENTS 1. UNIFIER

More information

ORANGE COUNTY SANITIATION DISTRICT CAPITAL IMPROVEMENT PROGRAM PERFORMANCE REPORTS

ORANGE COUNTY SANITIATION DISTRICT CAPITAL IMPROVEMENT PROGRAM PERFORMANCE REPORTS ORANGE COUNTY SANITIATION DISTRICT CAPITAL IMPROVEMENT PROGRAM PERFORMANCE REPORTS CONTENTS: Construction Change Order Summary Report Design Consultant PSA Amendment Summary Report Contractors Active Projects

More information

QuickBooks 2012 What's New and Improved

QuickBooks 2012 What's New and Improved QuickBooks 2012 What's New and Improved By Laura Madeira Register to win over $8K of QuickBooks Software* www.quick-training.com/free-quickbooks-2012 A brief review of the new and improved features and

More information

KAWERAU DISTRICT COUNCIL BUSINESS DISASTER RECOVERY PLAN 2011

KAWERAU DISTRICT COUNCIL BUSINESS DISASTER RECOVERY PLAN 2011 KAWERAU DISTRICT COUNCIL BUSINESS DISASTER RECOVERY PLAN 2011 Kawerau District Council Private Bag 1004 Ranfurly Court KAWERAU 3169 Tel (07) 306 9009 Fax (07) 323 8072 Email [email protected]

More information

2. AUDIT OBSERVATIONS

2. AUDIT OBSERVATIONS Drinking Water Audit Report Local Authority: Kerry County Council Date of Audit: 16/09/08 Plant Inspected: Dromin Water Treatment Plant Listowel File Reference: DW2008/554 Supply Code (1300PUB1204) Auditors:

More information

Energy Audits Waste Water Treatment Plants

Energy Audits Waste Water Treatment Plants Energy Audits Waste Water Treatment Plants Ohio Water Environment Association Conference June 20, 2012 Presented by: Samuel J. Morgan, P.E., LEED AP CT Consultants, Inc. World Energy Trend US Total Energy

More information

Dewatering - Time and Cost Relief by way of Trenchless Construction

Dewatering - Time and Cost Relief by way of Trenchless Construction North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 TA-T3-04 Dewatering - Time and Cost Relief by way of Trenchless Construction Jenn Stillman,

More information

Administrator s Guide ALMComplete Support Ticket Manager

Administrator s Guide ALMComplete Support Ticket Manager Administrator s Guide ALMComplete Support Ticket Manager This guide provides an overview of ALMComplete s Support Manager with setup instructions. SoftwarePlanner Release 9.6.0 and higher April 2011 1

More information

White Paper. www.geodecisions.com

White Paper. www.geodecisions.com White Paper www.geodecisions.com A Geo Spatial Total Asset Management System (TAMS) To Improve Asset Management Decision Making Fall 2013 Abstract This paper describes a Geospatial Total Asset Management

More information

Cambridge Wastewater Treatment Facility

Cambridge Wastewater Treatment Facility Cambridge Wastewater Treatment Facility Emergency Situations If you have a water or sewer emergency that relates to the City s utility system call the Public Works office at 763-689-1800 on normal working

More information

Genesee Advanced Water Treatment Facility

Genesee Advanced Water Treatment Facility Genesee Advanced Water Treatment Facility State Revolving Fund Loan Public Hearing April 28, 2015 Project Purpose Upgrade critical components of the District's water system Develop a more robust water

More information

AVImarkSettings for Microsoft Office

AVImarkSettings for Microsoft Office June 24, 2013 AVImark Software Support Address: 5 Sugar Creek Road Piedmont, MO 63957 Support Phone: 877.838.9273 Support Fax: 573.223.4306 Corporate Phone: 855.838.7638 Corporate Fax: 573.223.3551 AVImarkSettings

More information

Application for the Construction or Installation of Aboveground Storage Tank (AST) Systems or Associated Underground or Over-water Piping Systems

Application for the Construction or Installation of Aboveground Storage Tank (AST) Systems or Associated Underground or Over-water Piping Systems Page 1 of 5 Application for the Construction or Installation of Aboveground Storage Tank (AST) Systems or Associated Underground or Over-water Piping Systems New Hampshire Department of Environmental Services

More information

Instructions and Helpful Hints. for Preparation of. Emergency Action Plans

Instructions and Helpful Hints. for Preparation of. Emergency Action Plans Instructions and Helpful Hints for Preparation of Emergency Action Plans using the fillable form electronic template for the NRCS sample EAP June 25, 2007 Introduction Emergency Action Plans (EAPs) are

More information

Communication Manager configuration for BLU-103

Communication Manager configuration for BLU-103 Avaya Aura Communication Manager configuration for BLU-103 Application Notes for Configuring BLU-103 VoIP Solution with Avaya Aura Session Manager 6.3 and Avaya Aura Communication Manager 6.3 10653 South

More information

ADVERTISEMENT FOR BIDS DUCKETT CREEK SANITARY DISTRICT TP1 CLARIFIERS #1 AND #2 REHABILITATION

ADVERTISEMENT FOR BIDS DUCKETT CREEK SANITARY DISTRICT TP1 CLARIFIERS #1 AND #2 REHABILITATION ADVERTISEMENT FOR BIDS DUCKETT CREEK SANITARY DISTRICT TP1 CLARIFIERS #1 AND #2 REHABILITATION Notice is hereby given that the Duckett Creek Sanitary District will receive sealed proposals at the Duckett

More information

Maricopa Association of Governments. Technical Memorandum No. 1 INFRASTRUCTURE DEVELOPMENT COSTS. August 2001

Maricopa Association of Governments. Technical Memorandum No. 1 INFRASTRUCTURE DEVELOPMENT COSTS. August 2001 Maricopa Association of Governments Technical Memorandum No. 1 INFRASTRUCTURE DEVELOPMENT COSTS August 2001 3033 NORTH 44TH STREET, SUITE 101 PHOENIX, ARIZONA 85018 (602) 263-9500 FAX (602) 265-1422 Technical

More information

BlueCielo Meridian Today

BlueCielo Meridian Today BlueCielo Meridian Today Positioning of our current product portfolio BlueCielo Meridian Customer Day June 26, 2014 Gilze Rijen The Netherlands Edwin van Dijk, Business Solution Specialist BlueCielo ECM

More information

High-Rate Retention Treatment Facility for CSO Control in Windsor Riverfront East

High-Rate Retention Treatment Facility for CSO Control in Windsor Riverfront East High-Rate Retention Treatment Facility for CSO Control in Windsor Riverfront East Jian Li, Ph.D., P.Eng., PE Senior Environmental Engineer Stantec Consulting Ltd. Water & Wastewater Treatment BMP Forum

More information

Real-time energy and water quality management system designed for success!

Real-time energy and water quality management system designed for success! Real-time energy and water quality management system designed for success! Texas Water 2012 San Antonio, TX April 13, 2012 Manuel Perez Energy Manager Peter Martin Vice President Brian Skeens Global Technology

More information

5. Environmental Analysis

5. Environmental Analysis 5.11 The potential for adverse impacts on utilities and service systems was evaluated based on information concerning current service levels and the ability of the service providers to accommodate the

More information

Water Water Treatment Plant Tour

Water Water Treatment Plant Tour Water Water Treatment Plant Tour Don Rankin, Superintendent Topeka, KS 66606 785-368-3111 Tel 785-368-3825 FAX For a complete list of contacts with phone numbers, FAX numbers and email addresses, click

More information

DEWATERING AND WATER TREATMENT OPERATIONS OF THE OTTAWA RIVER SEDIMENT REMEDIATION PROJECT

DEWATERING AND WATER TREATMENT OPERATIONS OF THE OTTAWA RIVER SEDIMENT REMEDIATION PROJECT DEWATERING AND WATER TREATMENT OPERATIONS OF THE OTTAWA RIVER SEDIMENT REMEDIATION PROJECT William J. Cretens 1 ABSTRACT The Ottawa River Sediment Remediation Project, performed in Toledo, Ohio in 2010,

More information

Engineering Documents in Expedition

Engineering Documents in Expedition Engineering Documents in Expedition Document Number Revision 0 Approved By Wayne L. Cornell, PE January 10, 2006 Active Divisions/Departments Raytheon Polar Services Company Facilities, Engineering, Maintenance,

More information

Greater Ouachita Water Company. April 2015 Monthly Operations & Maintenance Report

Greater Ouachita Water Company. April 2015 Monthly Operations & Maintenance Report Greater Ouachita Water Company April 2015 Monthly Operations & Maintenance Report Severn Trent Services 6725 Cypress ST. West Monroe, LA 71291 United States T: +1 318 322 3741 www.severntrentservices.com

More information

FIELD INVESTIGATION REPORT FI2009040701 (Maui, Water Treatment Facilities)

FIELD INVESTIGATION REPORT FI2009040701 (Maui, Water Treatment Facilities) FI2009040701 - Page 1 of 9 STATE OF HAWAII DEPARTMENT OF LAND AND NATURAL RESOURCES COMMISSION ON WATER RESOURCE MANAGEMENT Stream Protection and Management Branch FIELD INVESTIGATION REPORT FI2009040701

More information

Tampa Bay Seawater Desalination Plant

Tampa Bay Seawater Desalination Plant Tampa Bay Seawater Desalination Plant Project History How The Plant Works Desal Fun Facts 2575 Enterprise Road, Clearwater, FL 33763-1102 Phone: 727.796.2355 / Fax: 727.791.2388 www.tampabaywater.org Tampa

More information

Wastewater Nutrient Removal

Wastewater Nutrient Removal Wastewater Nutrient Removal An overview of phosphorus and nitrogen removal strategies Presented by: William E. Brown, P.E. Peter C. Atherton, P.E. Why are nutrients an issue in the environment? Stimulates

More information

This presentation premiered at WaterSmart Innovations. watersmartinnovations.com

This presentation premiered at WaterSmart Innovations. watersmartinnovations.com This presentation premiered at WaterSmart Innovations watersmartinnovations.com Cutting Our Losses: The Los Angeles Water Loss Audit Experience WaterSmart Conference October 2, 2013 Penny Falcon, P.E.

More information

LDPCSD Water Supply Emergency Response Plan Status Update 2-4-15

LDPCSD Water Supply Emergency Response Plan Status Update 2-4-15 LDPCSD Water Supply Emergency Response Plan Status Update 2-4-15 1 EMERGENCY OVERVIEW The Lake Don Pedro Community Services District (LDPCSD) provides domestic potable water service to 1450 connections

More information

GETTING STARTED WITH QUICKEN with Online Bill Pay 2010-2012 for Windows

GETTING STARTED WITH QUICKEN with Online Bill Pay 2010-2012 for Windows GETTING STARTED WITH QUICKEN with Online Bill Pay 2010-2012 for Windows Refer to this guide for instructions on how to use Quicken s online account services to save time and automatically keep your records

More information

Request for Information (RFI) Instructions (SharePoint)

Request for Information (RFI) Instructions (SharePoint) Request for Information (RFI) Instructions (SharePoint) Contractor Creates a New RFI View 1 When a contractor selects RFI forms from the menu, they will get the form shown in View 1. 1. The RFI number

More information

Exercise Safe Commands and Audit Trail

Exercise Safe Commands and Audit Trail Exercise Safe Commands and Audit Trail Table of Contents Exercise 1: Secure Objects with Safe Commands...2 Exercise 2: Record User Actions in the Audit Trail... 13 3.1 Setting up the SQL Server for Audit

More information

Cloud Hosted IP PBX BGAdmin Training

Cloud Hosted IP PBX BGAdmin Training Cloud Hosted IP PBX BGAdmin Training Welcome! Welcome to AirePBX! This BGAdmin (Business Group Administrator) training is designed to help you get comfortable with administration features and functions

More information

Altoona Water Authority. Infrastructure Overview

Altoona Water Authority. Infrastructure Overview Altoona Water Authority Infrastructure Overview Mission Statement As stewards of the community s water system, our mission is to provide a clean, safe, reliable water supply and to collect and treat wastewater

More information

City of Riverside WASTEWATER COLLECTION AND TREATMENT FACILITIES INTEGRATED MASTER PLAN

City of Riverside WASTEWATER COLLECTION AND TREATMENT FACILITIES INTEGRATED MASTER PLAN WASTEWATER COLLECTION AND TREATMENT FACILITIES INTEGRATED MASTER PLAN VOLUME 10: CAPITAL IMPROVEMENT PLAN AND OVERALL IMPLEMENTATION SCHEDULE CHAPTER 1: CAPITAL COSTS AND IMPLEMENTATION SCHEDULE FINAL

More information

# 14-28: Water Enterprise Plan Development

# 14-28: Water Enterprise Plan Development City of Beverly Hills Public Works Services Department 345Foothill Road Beverly Hills, CA. 90210 # 14-28: Water Enterprise Plan Development Request for Proposal For Professional Planning and Engineering

More information

DCO No. Released By: Effective Date Document No. Rev.

DCO No. Released By: Effective Date Document No. Rev. 1.0 Purpose The Engineering Change Order is a tool utilized by the Safety that records and tracks the design and review process for engineering jobs. 2.0 Scope All new designs and modifications to existing

More information

Banner Workflow. Creating FOAPAL Requests

Banner Workflow. Creating FOAPAL Requests Banner Workflow Creating FOAPAL Requests Workflow s automated processes allow business events to trigger user emails, automated activities, and notifications. Workflow s automated approval notifications

More information

Miguel Ortiz, Sr. Systems Engineer. Globanet

Miguel Ortiz, Sr. Systems Engineer. Globanet Miguel Ortiz, Sr. Systems Engineer Globanet Agenda Who is Globanet? Archiving Processes and Standards How Does Data Archiving Help Data Management? Data Archiving to Meet Downstream ediscovery Needs Timely

More information

NHCRWA BOARD VISITS NORTHEAST WATER PURIFICATION PLANT

NHCRWA BOARD VISITS NORTHEAST WATER PURIFICATION PLANT NHCRWA BOARD VISITS NORTHEAST WATER PURIFICATION PLANT If you have ever wondered what roughly $100 million will buy these days, there s a major construction project adjacent to Lake Houston that provides

More information

Business/Project Management Software By BASEBUILDERS

Business/Project Management Software By BASEBUILDERS præsto AE Business/Project Management Software By BASEBUILDERS ios Everything from Project Tracking to Time Slips to Invoices to Email. Praesto AE makes Managing your Projects and Business SIMPLE. Even

More information

SSMS Built in Reports for Server and Database Monitoring

SSMS Built in Reports for Server and Database Monitoring SQL Server Documentation SSMS Built in Reports for Server and Database Monitoring I sometimes discover that the built in reports for SQL Server within SSMS are an unknown, sometimes this is because not

More information

Design Criteria & Service Goals

Design Criteria & Service Goals 4.1 Design Life of Improvements The design life of a water system component is sometimes referred to as its useful life or service life. The selection of a design life is a matter of judgment based on

More information

Quick Start Guide. Microsoft Access 2013 looks different from previous versions, so we created this guide to help you minimize the learning curve.

Quick Start Guide. Microsoft Access 2013 looks different from previous versions, so we created this guide to help you minimize the learning curve. Quick Start Guide Microsoft Access 2013 looks different from previous versions, so we created this guide to help you minimize the learning curve. Change the screen size or close a database Click the Access

More information