1 April 30,
2 Facility Stabilization and Deactivation C (Period 3) After facilities are turned over by USEC and accepted by DOE: Perform minimal stabilization and deactivation activities for facilities to put into safe configuration for long-term S&M. Submit a Stabilization and Deactivation Plan. Perform the necessary facility stabilization and deactivation activities including, but not limited to, the following: Evaluate and determine the need for the continued safety requirements for monitoring and/or maintaining systems. Perform deactivation and/or verification activities that support facilities stabilization, per DOE O 420.1B, Facility Safety and contractor safety basis documentation. Perform uranium deposit/hold-up removal or Tc-99 treatment necessary to minimize long-term S&M cost. 2
3 Goal for S&M and Utility Operations Goal is to achieve for approximately 2/3 reduction in cost of S&M Program 3
4 Facility Stabilization and Deactivation C Uranium Hold-up/Deposits Due to enormous surface area of the uranium process systems within the Paducah cascade, a significant amount of uranium has been chemically and physically absorbed to the inner walls of the piping and cell components (commonly referred to as hold-up) It has been estimated as much as 7,500 kgs of uranium may be present. Uranium deposits are also caused by wet air in leakage. The moisture in the air upon entering the cascade reacts with UF 6 to form various uranium oxy-fluorides with the most common being UO 2 F 2 and are deposited near the leak. The uranium deposits can range from a few pounds caused by seal failures to several hundred pounds from expansion joints. It is estimated to be approximately 5,000 lbs of UO 2 F 2 within the cascade. 4
5 Facility Stabilization and Deactivation C Technetium-99 Estimates have been made that approximately 540 to 550 kilograms of Tc- 99 were fed into the PGDP cascade between 1953 and Approximately 325 kgs were fed into the cascade during period 1953 to Approximately 214 kgs were fed into the cascade during the period 1962 to No Tc-99 was fed into the cascade during the period 1983 to present. 5
6 Facility Stabilization and Deactivation C Technetium-99 (Cont.) The first large scale CIP began in 1956 and concluded in Most all of the stages were removed, cleaned or decontaminated and new barrier installed in the first cascade improvement program which was concluded in July The second CIP began in 1975 and concluded in The converters were replaced in the purge cascade with converters obtained from K-27 in Oak Ridge. Tc-99 should have been less than what was present on the existing purge cascade converters at that time because of the anticipated higher levels of Tc-99 in the Paducah purge cascade at that time. Approximately 11 kgs of Tc-99 were removed by MgF 2 traps located in C-310 purge cascade in a 10-month period of time. It is uncertain how many trap change outs were performed. 6
7 Facility Stabilization and Deactivation C Technetium-99 (Cont.) Equipment failures, UF 6 trapping media, C-310 vent and UF 6 product are some of the paths where Tc-99 are removed from the cascade. During each CIP significant amounts of Tc-99 were removed from the equipment. The estimated amount of Tc-99 remaining in the cascade is less than 50 kgs. The Tc-99 is not evenly distributed in the cascade. Highest concentrations are in upper cells near the purge cascade and very low concentrations are in the cells near the tails withdrawal. Historical UF6 sampling program of product and tails UF 6. USEC Tc-99 product specifications for Tc-99. 7
8 Facility Stabilization and Deactivation C Technetium-99 (Cont.) ppb Average Tc-99 Concentrations in PGDP Product Tc Conc Fiscal Year 8
9 Facility Stabilization and Deactivation C Utility Optimization (Period 3) Ensure decisions for optimizing utilities and laboratory services are based on documented cost/benefit analyses that evaluate overall costs to DOE. Use energy savings performance contracts to the maximum extent possible where determined to be cost effective. Support the continued analytical services to the DUF 6 Conversion Plant, the on-going environmental remediation and other site tenants/contractors. Use/need of utilities for its operations is minimized to the maximum extent and work aggressively to isolate and shutdown GDP and associated support facilities at the site. Submit and implement a Utility Optimization Program Plan consistent with the Federal Energy Management Program and DOE Order O 436.1, where applicable. 9
10 C-611 Water Treatment and Distribution Facilities Assess the capabilities for purposes of transferring these DOE assets to local community water districts or for deactivating the on-site water treatment facilities and relying solely on community water districts water supplies. Assess the site s near-term and long-term DOE operational needs. The C-611 Water Treatment System provides the water supply to the Paducah Site. Currently, an average 26 million gallons per day (mgd) is required with a peak of 30 to 32 mgd usage. The water treatment process is based on conventional water treatment techniques which include softening, coagulation, flocculation, sedimentation, and chlorination. Raw water is obtained from the Ohio River through an intake station and pumped through water-softening units at the facility. 10
11 C-615 Sewage Disposal Plant Assess the capabilities of the on-site sewage collection and treatment systems and facilities for purposes of replacing these facilities through use of more efficient modular treatment systems or use of local community sewage treatment districts. Assess the site s near-term and long-term DOE operational needs. The C-615 Sewage Disposal Plant provides the sewage handling and treatment for the Paducah Site. Sewage is handled by four 400 gallons per minutes (gpm) basin pumps and 75 gpm sludge pumps which provide a basic plant capacity of 350 gpm. Normal flow is between 200 and 300 gpm. The sewage collection system services all the occupied plant buildings with the exception of some remote facilities. The plant consists of chemical, mechanical, and biological treatment prior to discharge. The pant provides secondary treatment. It consists of a comminutor, primary and secondary settling basins, trickling filter, sludge digester and settling beds, chlorinator, and contact chamber. 11
12 Power Distribution Assess the capabilities and configuration of the on-site power distribution system and facilities for purposes of: 1) consolidating on-site power distribution to the C-531 Switchyard as quickly as possible, 2) evaluating and determining if construction/installation of a replacement switchyard(s) (high and low side) is cost effective, 3) transferring options or ownership of the four existing switchyards (C-531, C-533, C- 535, C-537), two relay houses (C-532, C-536), and other related support systems/facilities to electrical utilities. Assess the site s near-term and long-term DOE operational needs. As radiological and PCB contamination exists in the switchyards and on/near associated support facilities and assets, any recommendation must ensure appropriate controls are in place to properly control contaminants and ensure protection of personnel entering or commercially utilizing the facilities and systems. 12
13 Power Distribution Switchyards C-531, C-533, C-535, and C-537 switchyards contain the 161kilovolt (kv) electrical system components necessary for operation of the PGDP. The plant typically uses between 900 megawatts and 2000 megawatts of electrical power per hour, depending on the plant s production targets and availability of reasonably priced power. The plant was built with the capacity to use up to 3000 megawatts. Electrical power comes into the plant at 161,000 volts through the overhead transmission lines from TVA s Shawnee Steam Plant and Electric Energy, Inc. (EEI) at Joppa, Illinois. The power flows through more than 80 circuit breakers to large transformers (35) located throughout the plant. 13
14 Power Distribution Switchyards Of the eighteen transmission lines entering the PGDP, twelve are owned by the Tennessee Valley Authority (TVA) and six are owned by EEI. Kentucky Utilities owns one line that comes to the plant and goes out but does not provide feed to the plant. In addition the four PGDP switchyards are connected by five 161kV tie lines owned by DOE and leased by USEC. 14
15 C-600 Steam Plant Shutdown Deactivate and shutdown the C-600 Steam Plant. However, heat, compressed air, nitrogen, and chilled water will still be required for certain facilities that currently utilize the RCW system (residual heat). Evaluate the site s need (including tenants/contactors) for heat, compressed air, nitrogen and chilled water, which will include alternate sources, properly sized, for the utilities and upon approval by DOE, implement the modifications. The plant produces steam used to heat, vaporize UF 6, obtain UF 6 samples, maintain process temperatures, clean equipment, and provide heat for other miscellaneous buildings and process operations. It consists of three water wall tube boilers (two coalfired and one oil-and gas-fired) each capable of producing 100,000 pounds of steam per hour at 250 pounds per square inch plus associated equipment. Some of the site facilities such as C-100, C-300, and C-710 currently utilize the chilled water system for building air conditioning and the steam for heating. The use of electrostatic precipitators and low-sulpher coal helps the plant keep atmospheric emissions below environmental limits. The steam plant uses approximately 35,000 tons of coal per year. 15
16 Alternative Heat and Chilled Water Systems Provide a provision of an alternative heat supply to the facilities currently utilizing waste heat for facility heating systems. Evaluate modifications to the chilled water system to provide air conditioning for the C- 100, C-101, C-102, C-200, C-300, C-400 office areas, C-710 and C-720 office areas that are currently cooled. Facility modifications should be sized and installed only for these facilities/areas which the Contractor (or the other site s contractors/tenants) expects to utilize for support of this PWS. Systems were designed and built to pump heated recirculating cooling water (RCW) from the process buildings to the buildings requiring space heating. The pumped water is known as recirculating heating water (RHW). Shutdown of the gaseous diffusion process will result in loss of waste heat source, RCW and RHW, and the internal radiant heat from the process within each buildings. Steps must be taken to provide alternate sources of heat or to winterize the buildings if the uranium enrichment process is shutdown. 16
17 Analytical Laboratory Assess the capabilities of the on-site Analytical Laboratory (C-709 and C-710) for purposes of privatization of the facilities and equipment. Assess the need of analytical services (lease, transfer, or purchase) from existing on-site tenants/contractors to determine the type of analytical services needed. The C-709 Plant Laboratory Annex and the C- 710 Technical Services Building house laboratories with an array of modern analyzers and test equipment, offices, a conference room, and vault for records retention and storage. The laboratory facilities analyze over 100,000 various types of analytical tests per year, such as analyzing for metals, radiological, organics, inorganics, volatiles, and semivolatiles. Media types such as groundwater, concrete, soil, air, waste waters are processed through the laboratory, also supporting the environmental cleanup programs. 17
Environmental Cleanup Update Briefing on the Portsmouth Gaseous Diffusion Plant Joel Bradburne DOE Site Lead Portsmouth/Paducah Project Office
Environmental Cleanup Update Briefing on the Portsmouth Gaseous Diffusion Plant Joel Bradburne DOE Site Lead Portsmouth/Paducah Project Office Bristol Village Activity Center Waverly, Ohio October 27,
Ann Arbor Wastewater Treatment Plant Facilities Renovations Project September 2015
Ann Arbor Wastewater Treatment Plant Facilities Renovations Project September 2015 The Facilities Master Plan was completed in 2004 and identified the need for improvements to the City of Ann Arbor s Wastewater
CHAPTER 8 UPGRADING EXISTING TREATMENT FACILITIES
CHAPTER 8 UPGRADING EXISTING TREATMENT FACILITIES 8-1. General. Upgrading of wastewater treatment plants may be required to handle increased hydraulic and organic loadings to meet existing effluent quality
Cambridge Wastewater Treatment Facility
Cambridge Wastewater Treatment Facility Emergency Situations If you have a water or sewer emergency that relates to the City s utility system call the Public Works office at 763-689-1800 on normal working
Description of the Water Conserv II Facility
Description of the Water Conserv II Facility Introduction The Water Conserv II (WCII) Water Reclamation Facility provides service to a majority of the southwest section of Orlando. The WCII facility has
WASTEWATER TREATMENT OBJECTIVES
WASTEWATER TREATMENT OBJECTIVES The student will do the following: 1. Define wastewater and list components of wastewater. 2. Describe the function of a wastewater treatment plant. 3. Create a wastewater
Tampa Bay Seawater Desalination Plant
Tampa Bay Seawater Desalination Plant Project History How The Plant Works Desal Fun Facts 2575 Enterprise Road, Clearwater, FL 33763-1102 Phone: 727.796.2355 / Fax: 727.791.2388 www.tampabaywater.org Tampa
NEW JERSEY CENTER OF EXCELLENCE
Overview NEW JERSEY Page 1 The Plant (CUP) provides electricity via a cogeneration system, chilled water for environmental cooling, steam for heating, and compressed air primarily for HVAC control Serves
ABSTRACT DCMCCT PROJECT OVERVIEW
Title: Case Study of the Austin Energy Dell Regional Children s Medical Center of Central Texas Packaged Hybrid CHP Energy Plant in Austin, Texas Authors: Mr. Ed Mardiat, Burns & McDonnell Mr. Jim Teigen,
HIGHLY ENRICHED URANIUM INVENTORY
U NITE D DEPARTMENT OF ENERGY STATES OF A M ERICA HIGHLY ENRICHED URANIUM INVENTORY AMOUNTS OF HIGHLY ENRICHED URANIUM IN THE UNITED STATES U.S. DEPARTMENT OF ENERGY OFFICE OF SECURITY AND SAFETY PERFORMANCE
How To Clean Up A Uranium Enrichment Plant
GAO United States General Accounting Office Testimony Before the Committee on Energy and Natural Resources, U.S. Senate For Release on Delivery Expected at 9:00 a.m. CST Saturday, December 6, 2003 NUCLEAR
HOW DOES A NUCLEAR POWER PLANT WORK?
HOW DOES A NUCLEAR POWER PLANT WORK? O n t a r i o P o w e r G e n e r a t i o n P U T T I N G O U R E N E R G Y T O U S G O O D E O N T A R I O P O W E R G E N E R A T I O N What a Nuclear Reactor Does
Fats, Oil and Grease. Best Management Practices Manual. Information, Pollution Prevention, and Compliance Information For Food Service Facilities
Fats, Oil and Grease Best Management Practices Manual Information, Pollution Prevention, and Compliance Information For Food Service Facilities Pinellas County Utilities Water Quality Management Division
University of Maryland College Park District Energy System. IDEA Campus Energy Conference February 9, 2012
University of Maryland College Park District Energy System IDEA Campus Energy Conference February 9, 2012 UMCP District Energy System The University of Maryland district energy system consists of a well
Heating Water by Direct Steam Injection
Heating Water by Direct Steam Injection Producing hot water by direct steam injection provides a solution where large volumes of hot water at precise temperatures are required, and where energy and space
RULE 1102. DRY CLEANERS USING SOLVENT OTHER THAN PERCHLOROETHYLENE
(Adopted January 6, 1978)(Amended August 3, 1979)(Amended July 11, 1980) (Amended August 3, 1990)(Amended December 7, 1990) (Amended November 17, 2000) RULE 1102. DRY CLEANERS USING SOLVENT OTHER THAN
Background. 179 million gallons saved for make-up water
Essential Expertise for Water, Energy and Air Gallatin Steel Achieves Significant eroi Savings Through the Use of Nalco Innovative Technologies Background Gallatin Steel is a mini-mill that produces steel
CyberFortress Data Center at Innovation Park Infrastructure and Topology Guide. Innovation Park Charlotte. NC 28262. DRAFT V0.
Innovation Park Charlotte. NC 28262 DRAFT V0.1 Page 2 CyberFortress Data Center at Innovation Park BECO South purchased Innovation Park in March 2010 and immediately launched a dramatic top-to-bottom $30M
A Primer on Protecting Idle Boilers By Howard Benisvy, Member ASHRAE
The following article was published in ASHRAE Journal, December 2002. Copyright 2002 American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. It is presented for educational purposes
Coagulation and Flocculation
Coagulation and Flocculation Groundwater and surface water contain both dissolved and suspended particles. Coagulation and flocculation are used to separate the suspended solids portion from the water.
COOLING WATER MANAGEMENT
COOLING WATER MANAGEMENT Intent To minimize the carbon-footprint, water usage and environmental impact of HVAC cooling systems and process cooling systems, generally by optimizing the control of water
Energy Audits Waste Water Treatment Plants
Energy Audits Waste Water Treatment Plants Ohio Water Environment Association Conference June 20, 2012 Presented by: Samuel J. Morgan, P.E., LEED AP CT Consultants, Inc. World Energy Trend US Total Energy
Septic System Owner s Manual
Septic System Owner s Manual Sponsored by: copyright 2013 No part of this publication may be reproduced without our consent. www.callbrownies.com Brownie s Septic and Plumbing has provided quality service
INTRODUCTION. Three Mile Island Unit 2
INTRODUCTION here was an accident at Three Mile Island Unit 2 on March 28,1979. It caused extensive damage to the plant's nuclear fuel core. Most of the plant's major systems were relatively undamaged.
D&D of the French High Enrichment Gaseous Diffusion Plant
D&D of the French High Enrichment Gaseous Diffusion Plant Christophe BEHAR, Philippe GUIBERTEAU CEA/DAM BP12-91680 Bruyeres le Chatel France Bernard DUPERRET, Claude TAUZIN AREVA/COGEMA BP44-26701 Pierrelatte
5. Environmental Analysis
5.11 The potential for adverse impacts on utilities and service systems was evaluated based on information concerning current service levels and the ability of the service providers to accommodate the
Historic Flood Impact on the Nashville Drinking Water System. Scott Potter, Director Metro Water Services, Nashville, TN
Historic Flood Impact on the Nashville Drinking Water System Scott Potter, Director Metro Water Services, Nashville, TN Historic Event = 13.53 /48 Hours May 1 6.32 of Rain = 3rd greatest one-day rainfall
Subpart 1. Installation. All plumbing systems must be. installed and tested according to this chapter and chapter 4715,
4658.4500 PLUMBING SYSTEMS; NEW CONSTRUCTION. Subpart 1. Installation. All plumbing systems must be installed and tested according to this chapter and chapter 4715, the Minnesota Plumbing Code. Subp. 2.
March 21, 2012. Environmental Management Program Strategies: A National Responsibility
Written Statement of David Huizenga Senior Advisor for Environmental Management United States Department of Energy Before the Subcommittee on Energy and Water Development Committee on Appropriations United
ELECTRODE BOILERS VAPOR POWER INTERNATIONAL
ELECTRODE BOILERS WITH JET-FLO Technology VAPOR POWER INTERNATIONAL ELECTRODE boilers The Electrode Steam Boiler with Jet-Flo technology consists of an insulated pressure vessel and is fully enclosed in
Glossary of Heating, Ventilation and Air Conditioning Terms
Glossary of Heating, Ventilation and Air Conditioning Terms Air Change: Unlike re-circulated air, this is the total air required to completely replace the air in a room or building. Air Conditioner: Equipment
Chemical Decontamination and Fluid Handling Services
Chemical Decontamination and Fluid Handling Services Westinghouse is a global industry expert in decontamination and fluid handling processes, with proven abilities in decontamination and remediation work.
GUIDELINES FOR LEACHATE CONTROL
GUIDELINES FOR LEACHATE CONTROL The term leachate refers to liquids that migrate from the waste carrying dissolved or suspended contaminants. Leachate results from precipitation entering the landfill and
Hazardous Waste Accumulation, Storage, & Labeling
Nadine Deak, Kalamazoo District Office 269-567-3592 or [email protected] Jenny Bennett, Gaylord District Office 989-705-2421 or [email protected] Hazardous Waste Accumulation, Storage, & Labeling
UTILITIES AND ENERGY MANAGEMENT
UTILITIES AND ENERGY MANAGEMENT University of Texas at Austin increases investment in co-generation to achieve greater utility reliability and economy. ENVIRONMENTAL BENEFITS AND ENERGY SAVINGS Power plant
Boiling Water Reactor Systems
Boiling Water (BWR) s This chapter will discuss the purposes of some of the major systems and components associated with a boiling water reactor (BWR) in the generation of electrical power. USNRC Technical
CREATING A GREEN FUTURE THROUGH WATER REMEDIATION
CREATING A GREEN FUTURE THROUGH WATER REMEDIATION Cornerstone Principles for Conducting Business Active Treatment Systems, Inc. goes to great lengths to instill in every employee the importance of ethical
University of Iowa Power Plant
University of Iowa Power Plant Contents Purpose... 2 History... 3 Cogeneration... 6 Boilers... 7 Environmental Impact... 10 Steam Turbine Generators... 12 Modernization... 14 Biomass Fuel Initiative...
Element D Services Plumbing
Medical Vacuum and Gas PART 1 - GENERAL 1.01 OVERVIEW A. This section addresses medical vacuum, waste anesthetic gas disposal, compressed air, oxygen, nitrous oxide, nitrogen and carbon dioxide systems.
Remediation of VOC Contaminated Groundwater
Remediation of VOC Contaminated Groundwater Background Contaminated groundwater has become an ever-increasing problem in the United States and around the world. Treatment and disposal of waste is a serious
Building Energy Systems. - HVAC: Heating, Distribution -
* Some of the images used in these slides are taken from the internet for instructional purposes only Building Energy Systems - HVAC: Heating, Distribution - Bryan Eisenhower Associate Director Center
Use of Substitute Fuels in Large Combustion Plants (LCPs)
Use of Substitute Fuels in Large Combustion Plants (LCPs) By Pat Swords Content of the Presentation What are substitute fuels What is the experience to date with these fuels What are the regulatory implications
Case Study: Innovative Energy Efficiency Approaches in NOAA s Environmental Security Computing Center in Fairmont, West Virginia
Case Study: Innovative Energy Efficiency Approaches in NOAA s Environmental Security Computing Center in Fairmont, West Virginia Prepared for the U.S. Department of Energy s Federal Energy Management Program
Columbia University Master Planning & Optimization
Columbia University Master Planning & Optimization February 20, 2014 Mr. Frank Martino Vice President, Operations 1 Agenda Columbia University Campus District Energy Overview Evolution of Columbia s District
Georgia Department of Public Health. Georgia Onsite Sewage Management Systems. Background and Use of Onsite Wastewater Treatment Systems in Georgia
Georgia Department of Public Health Georgia Onsite Sewage Management Systems Background and Use of Onsite Wastewater Treatment Systems in Georgia Background On-site sewage management systems are designed
10 Nuclear Power Reactors Figure 10.1
10 Nuclear Power Reactors Figure 10.1 89 10.1 What is a Nuclear Power Station? The purpose of a power station is to generate electricity safely reliably and economically. Figure 10.1 is the schematic of
12 November 2008 *** I:\CIRC\MEPC\01\642.DOC INTERNATIONAL MARITIME ORGANIZATION 4 ALBERT EMBANKMENT LONDON SE1 7SR
INTERNATIONAL MARITIME ORGANIZATION 4 ALBERT EMBANKMENT LONDON SE1 7SR Telephone: 020 7735 7611 Fax: 020 7587 3210 IMO E Ref. T5/1.01 MEPC.1/Circ.642 12 November 2008 2008 REVISED GUIDELINES FOR SYSTEMS
HOW TO SELECT A LOW VOLUME (L.V ) BOILER
HOW TO SELECT A LOW VOLUME (L.V ) BOILER FREQUENTLY ASKED QUESTIONS OR COMMENTS ON BOILERS Dear Potential Customer: Low Volume Operator Exempt boilers have been marketed in Ontario to eliminate the requirement
How a Ground Source Heat Pump Works for a School or College
How a Ground Source Heat Pump Works for a School or College Vertical System Image courtesy of Climate Master 1 Geothermal avoids the need for outdoor equipment..reducing vandalism and liability Image courtesy
Waste to Energy in Düsseldorf. for a clean city.
Waste to Energy in Düsseldorf for a clean city. Waste Management in Düsseldorf. Düsseldorf s public utilities company known as Stadtwerke Düsseldorf operates a waste to energy plant (WtE) that has been
DEVELOPMENT OF A CAMPUS WIDE DISTRICT CHILLED WATER SYSTEM SAMFORD UNIVERSITY
DEVELOPMENT OF A CAMPUS WIDE DISTRICT CHILLED WATER SYSTEM SAMFORD UNIVERSITY Mr. Rick Stephens, Director of Campus Planning Samford University, Birmingham, Alabama Mr. David W. Wade, P. E., President
A HOMEOWNERS GUIDE ON-SITE SEWAGE MANAGEMENT SYSTEMS
GEORGIA DEPARTMENT OF HUMAN RESOURCES ENVIRONMENTAL HEALTH SECTION A HOMEOWNERS GUIDE TO ON-SITE SEWAGE MANAGEMENT SYSTEMS March 12, 2002 WHAT IS AN ON-SITE SEWAGE MANAGEMENT SYSTEM An on-site sewage management
CWD BALDWIN PLANT NEW RESIDUALS HANDLING SYSTEM
CWD BALDWIN PLANT NEW RESIDUALS HANDLING SYSTEM OTCO Water Workshop March, 2011 Frank Woyma Plant Manager Nick Pizzi Vice-President EE&T ENVIRONMENTAL ENGINEERING & TECHNOLOGY, INC. Objectives Review the
RULE 8-8 - ORGANIC COMPOUNDS - WASTEWATER COLLECTION AND SEPARATION SYSTEMS
BAY AREA AIR QUALITY MANAGEMENT DISTRICT RULE 8-8 - ORGANIC COMPOUNDS - WASTEWATER COLLECTION AND SEPARATION SYSTEMS (ADOPTED: January 17, 1979) (AMENDED: November 1, 1989; October 6, 1993; June 15, 1994;
Final Plan for the Conversion of Depleted Uranium Hexafluoride
U.S. Department of Energy Final Plan for the Conversion of As Required by Public Law 105-204 July 1999 Office of Nuclear Energy, Science and Technology Final Plan for the Conversion of EXECUTIVE SUMMARY
SUMMIT COUNTY COMBINED GENERAL HEALTH DISTRICT
Slide 1 Point of Sale Inspections for Property Transfers SUMMIT COUNTY COMBINED GENERAL HEALTH DISTRICT Slide 2 What does the rule say? Effective September 1, 2008, prior to a property transfer, any property
CERTIFICATION TO OPERATE WATER AND WASTEWATER TREATMENT SYSTEMS APPLICATION INSTRUCTIONS
COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION STATE BOARD FOR CERTIFICATION OF WATER AND WASTEWATER SYSTEMS OPERATORS CERTIFICATION TO OPERATE WATER AND WASTEWATER TREATMENT SYSTEMS
NEVADA CITY WASTEWATER TREATMENT INQUIRY
NEVADA CITY WASTEWATER TREATMENT INQUIRY REASON FOR INVESTIGATION The 2003-2004 Grand Jury investigated the status of wastewater treatment in unincorporated Nevada County. This year, the Grand Jury investigated
CHAPTER 13 LAND DISPOSAL
CHAPTER 13 LAND DISPOSAL Supplemental Questions: Which of Shakespeare's plays is the source of the opening quote? The Tempest [1611-1612],Act: I, Scene: i, Line: 70. 13-1. Cite four reasons landfills remain
SECTION 5 COMMERCIAL REFRIGERATION UNIT 22 CONDENSERS
SECTION 5 COMMERCIAL REFRIGERATION UNIT 22 CONDENSERS UNIT OBJECTIVES After studying this unit, the reader should be able to explain the purpose of the condenser in a refrigeration system. describe differences
CONTAMINANT REMOVAL FROM CENTRIFUGAL SYSTEMS
CONTAMINANT REMOVAL FROM CENTRIFUGAL SYSTEMS BULLETIN 240-10-3 June 2004 Supersedes June 1983 Many centrifugal systems get little maintenance. As a result they operate with the refrigerant highly contaminated
Forgotten savings: Heat recovery from surface blowdown
Forgotten savings: Heat recovery from surface blowdown 1. Introduction The purpose of this article is to inform thermal plant operators of the interesting fuel savings that can be obtained by recovering
Portable leak detection instrument improves heat rate at electric power plant. By Terrence O'Hanlon, CMRP Reliabilityweb.com
Portable leak detection instrument improves heat rate at electric power plant. By Terrence O'Hanlon, CMRP Reliabilityweb.com By using a ruggedized portable ultrasonic leak detector, Mr. Brian Thorp, PdM
4 th & Carey Groundwater. Remediation Project and Reverse Osmosis Water Treatment System
4 th & Carey Groundwater Remediation Project and Reverse Osmosis Water Treatment System Contaminated City Well Well #8 4 th and Carey Groundwater contamination from industry was discovered in the Southeast
Maricopa Association of Governments. Technical Memorandum No. 1 INFRASTRUCTURE DEVELOPMENT COSTS. August 2001
Maricopa Association of Governments Technical Memorandum No. 1 INFRASTRUCTURE DEVELOPMENT COSTS August 2001 3033 NORTH 44TH STREET, SUITE 101 PHOENIX, ARIZONA 85018 (602) 263-9500 FAX (602) 265-1422 Technical
SEATTLE STEAM COMPANY FREQUENTLY ASKED QUESTIONS
SEATTLE STEAM COMPANY FREQUENTLY ASKED QUESTIONS What products/services does Seattle Steam provide? The company provides thermal energy (heat) produced at two central heating plants in downtown Seattle.
2. AUDIT OBSERVATIONS
Drinking Water Audit Report Local Authority: Kerry County Council Date of Audit: 16/09/08 Plant Inspected: Dromin Water Treatment Plant Listowel File Reference: DW2008/554 Supply Code (1300PUB1204) Auditors:
Water Incursion Standard Operating Procedure
Water Incursion Standard Operating Procedure Purpose: To provide a standardized procedure in the event of water incursion into any Penn State University facility. References: A Brief Guide to Mold, Moisture
Inventory of Performance Monitoring Tools for Subsurface Monitoring of Radionuclide Contamination
Inventory of Performance Monitoring Tools for Subsurface Monitoring of Radionuclide Contamination H. Keith Moo-Young, Professor, Villanova University Ronald Wilhelm, Senior Scientist, U.S. EPA, Office
Layout Planning of Waste-to-Energy Plants
Layout Planning of Waste-to-Energy Plants Layout Planning of Waste-to-Energy Plants Falko Weber The layout planning of waste incineration and solid recovered fuel power plants is subject to certain local
Residuals Management Somersworth Drinking Water Treatment Facility. Ian Rohrbacher, Treatment Operator IV
Residuals Management Somersworth Drinking Water Treatment Facility A HISTORICAL OVERVIEW OF SURFACE WATER TREATMENT RESIDUALS HANDLING Ian Rohrbacher, Treatment Operator IV Background We are a Grade III
The City of Boulder 75 th Street Wastewater Treatment Facility
The City of Boulder 75 th Street Wastewater Treatment Facility Wastewater Collection and Treatment The Foundation of Public Health Wastewater Collection Boulder s wastewater collection system, also known
David Mezzacappa, P.E. SCS Engineers Contractor to U.S. EPA on LMOP
LMOP Workshop: LFG Collection & LFG Energy Technologies David Mezzacappa, P.E. SCS Engineers Contractor to U.S. EPA on LMOP Introduction Goal convert LFG into a useful energy form Technologies include:
ABC CIRCUITS 10 Circuit Drive Circuit Town, IN 12345 SLUG CONTROL PLAN
ABC CIRCUITS 10 Circuit Drive Circuit Town, IN 12345 SLUG CONTROL PLAN The purpose of this plan is to provide detailed instructions for slug prevention and control. A complete copy of this plan is maintained
Orange County Sanitation District
Orange County Sanitation District The Orange County Sanitation District operates large wastewater treatment plants in Fountain Valley and Huntington Beach, CA. These plants treat about 230 million gallons
Federal Wage System Job Grading Standards for Air Conditioning Equipment Operating, 5415. Table of Contents
Federal Wage System Job Grading Standards for Air Conditioning Equipment Operating, 5415 Table of Contents WORK COVERED... 2 WORK NOT COVERED...2 TITLES... 2 GRADE LEVELS... 2 HELPER AND INTERMEDIATE JOBS...
Energy From Waste or Waste-to-Energy. Pyromex. The Solution to Multiple Energy & Environmental Issues James Pfeiffer, CEM
Energy From Waste or Waste-to-Energy Pyromex The Solution to Multiple Energy & Environmental Issues James Pfeiffer, CEM 1 Agenda Who is PowerHouse Energy What is Pyromex How Does Pyromex Work History of
Best Management Practices Fats, Oils, & Grease
Best Management Practices Fats, Oils, & Grease for Food Service Facilities Public Works Department Environmental Division Table of Contents A. Introduction B. Purpose of the Manual 1 C. Frequently Asked
Some Criteria for Choosing a Steam Boiler for a Microbrewery
Some Criteria for Choosing a Steam Boiler for a Microbrewery Jack Coe Rite Engineering and Manufacturing Corporation Breweries rely on steam heating for a number of functions, primarily to heat the brew
21.1 Functions, Basic Configuration, and Interfaces
21 (6.2.M) Site Services Building 21.1 Functions, Basic Configuration, and Interfaces 21.1.1 Functions The primary functions performed by the site services building are to house, support, provide a suitable
SECTION 6 EXISTING WASTEWATER MANAGEMENT SYSTEMS
SECTION 6 EXISTING WASTEWATER MANAGEMENT SYSTEMS This section will describe the Town s existing wastewater management systems. This includes on-site disposal systems and private collection systems. The
California Wastewater
Abridged Edition L A Y P E R S O N S G U I D E T O California Wastewater Prepared by the Water Education Foundation Contents The Layperson s Guide to California Wastewater is prepared and distributed by
ENERGY SERVICES ENVIRONMENTAL BENEFITS AND ENERGY SAVINGS
ENERGY SERVICES University of California Los Angeles reduces operating costs and air pollution with landfill gasfueled cogeneration and creative financing. ENVIRONMENTAL BENEFITS AND ENERGY SAVINGS Reduced
Facility Classification Standards
Facility Classification Standards Approval Date: April 3, 2009 Effective Date: April 3, 2009 Approved By: Nancy Vanstone, Deputy Minister Version Control: Replaces Facility Classification Standards dated
BASIC WATER TREATMENT OF STEAM BOILERS
BASIC WATER TREATMENT OF STEAM BOILERS Steve Kenny and Dave Pope Chemco Water Technology Vancouver, WA This is a brief discussion on low-pressure steam boiler chemistry. It provides dry kiln boiler operators
YOUR SEPTIC SYSTEM UNCOVERED
YOUR SEPTIC SYSTEM UNCOVERED By Raymond King District Director of Environmental Health It s underground where you can t see it. You don t really understand how it works. When it doesn t work your toilets
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection
Regulated Waste Storage
Regulated Waste Storage Storage of both hazardous and non-hazardous waste is subject to federal and state regulations. Additionally, improper storage of wastes has the potential to contaminate soil, surface
Evaluation Of Hybrid Air- Cooled Flash/Binary Power Cycle
INL/CON-05-00740 PREPRINT Evaluation Of Hybrid Air- Cooled Flash/Binary Power Cycle Geothermal Resources Council Annual Meeting Greg Mines October 2005 This is a preprint of a paper intended for publication
K. P. Catlett D. G. Adler U.S. Department of Energy, Oak Ridge, TN. P. D. Moss Science Applications International Corporation, Oak Ridge, TN
PREVENTING WASTE - SUPPORTING CLEANUP: POLLUTION PREVENTION USED IN CONJUNCTION WITH CERCLA ACTIVITIES AT BEAR CREEK VALLEY, OAK RIDGE RESERVATION, OAK RIDGE, TN K. P. Catlett D. G. Adler U.S. Department
WASTE WATER TREATMENT SYSTEM (OPERATING MANUALS )
Page 1 of 76 1.0 PURPOSE The purpose of the Wastewater Treatment System is to remove contaminates from plant wastewater so that it may be sent to the Final Plant Effluent Tank and eventually discharged
Second Place: Industrial Facilities or Processes, New
Second Place: Industrial Facilities or Processes, New Photo: Paul Howell Texas Medical Center in Houston is the largest medical center in North America. It has a chilled water system of 160,000 tons. Big