1 SANTIAGO CL Jornadas Técnicas Abr14&15 Dr. José Carlos Mendes Gte Tecnologia Transmissão e Produtos de Potência Gte Desenvolvimento & Engenharia Engenheiro Corporativo Executivo Global ABB Asea Brown Boveri Divisão de Produtos de Potência Transformadores de Potência São Paulo, SP - Brasil [email protected] tel: cel: ABB Brasil Power Products Division : Life Cycle and Operational Cost Optimization From Purchase to Minimum Maintenance ABB Brazil JCM A-1 14 Power de abril de Products 2015 Slide Division 1

2 Context Renewables Energy Content Content q q q q introduction buying by performance to a long life useful life and maintenance transformers and useful life aspects life cycle end of life from purchse to minimum maintenance transport installation knowledge based condition based event based minimum periodic inspection advanced asset managment ABB Brazil JCM A-2 14 Power de abril de Products 2015 Slide Division 2

3 Life Cycle Optimization Transformer Life Cycle ABB Brazil JCM A-3 14 Power de abril de Products 2015 Slide Division 3

4 Useful Life and Reliability Transformer Life Cycle Specification, Design, Manufacturing, Tests, Transportation, Receiving, Storage, Installation, Operation, Monitoring, Maintenance, End of Life ABB Brazil JCM A-4 14 Power de abril de Products 2015 Slide Division 4

5 Life Cycle and Global Evaluation of Alternatives Transformer Life Cycle Warranty of Useful Life Garantida, year Life Cycle, years Capital Cost: purchase transport installation $1 Operation Cost: $2 losses (noload, Load, Auxiliar) maintenance insurance premium repairs performance End of Life Cost: replacement transfer refurbishment $3 NPV, Total Cost / Life Cycle $ = $1+$2+$3 USD$ kva x Useful Life x Overloading Factor ABB Brazil JCM A-5 14 Power de abril de Products 2015 Slide Division 5

6 Life Cycle and Global Evaluation of Alternatives Transformer End of Life cellulose molecule O2 chemical bond ABB Brazil JCM A-6 14 Power de abril de Products 2015 Slide Division 6

7 Life Cycle and Global Evaluation of Alternatives Transformer End of Life Insulation Paper Polymerization Degree DP New Paper - DP tensile strength of a new paper Half Life Paper - DP residual tensile strength of a half-life paper is about 50% of the one of a new paper End of Life Paper - DP residual tensile strength of a end-of-life paper is about 25% of the one of a new paper Dielectric Strength at end-of-life is reduced just about ~ 10% of its original new paper value ABB Brazil JCM A-7 14 Power de abril de Products 2015 Slide Division 7

8 Applications and Operation Optmization From Purchase to Minimum Maintenance - Conclusions ABB Brazil JCM A-8 14 Power de abril de Products 2015 Slide Division 8

9 Transport Factory-to-Site Transportation Process At Site 1. Retrieve, collect and review impact recorder registers: at arrival at final destination installation site after truck unloading verify for abnormal transport accelerations together ABB define actions as needed Long Time Storage critical process 1. In case of long time storage follows specific procedures depending on storage time period: up to 6 months up to 12 months above 12 months assembly oil conservator and oil filled 2. To learn more please see: IEEE Std C Guide for Installation and Maintenance ABB Installation, Operation and Maintenance Manual ABB Brazil JCM A-9 14 Power de abril de Products 2015 Slide Division 9

10 Installation Installation Process Key Aspects 1. Substation pad conditions: high importance to minimum external stresses properly levelled and plan 2. ABB Installation, Operation and Maintenance Manual 3. Right and Qualified Equipment per ABB requirements: lifting equipment dry-air machine or dry-air bottles vacuum pumps thermo vacuum oil processing system 4. Right and Qualified Personal: following and safety CUSTOMER and ABB requirements experience with references in similar power equipment full ABB supervision ABB Brazil JCM A Power de abril de Products 2015 Slide Division 10

11 Installation Installation Process Main Steps 1. Overall external inspection: main tank accessories 2. Open main tank 3. Internal overall inspection 4. Assembly: radiators conservator bushings (C1 and tanδ tests before assembly) all accessories electrical connections replace by new gaskets in all opened man-holes etc ABB Brazil JCM A Power de abril de Products 2015 Slide Division 11

12 Installation Installation Process Final Processing 1. URSI Insulation Surface Moisture: pull vacuum and check for tightness pressurize with super dry-air and check for tightness dew-point readings (12h, 18h, 24h after pressurization) 2. Oil Filling and Processing: pull final vacuum complete (main tank, radiators, conservator) oil filling under vacuum oil circulation oil sampling (2 syringes for DGA and 1000ml bottle for Oil Properties tests) 3. Commissioning Tests: routine tests FRA tests ABB Brazil JCM A Power de abril de Products 2015 Slide Division 12

13 Operation Operation Strategy Extended Useful Life and Minimum Maintenance 1. Knowledge update and develop technical knowledge about the equipment electrical, thermal, mechanical technical limits according to purchase technical specification system operation monitoring to limit over-stressing on equipment's advanced monitoring of few and key operating parameters advanced trend analysis diagnostic of on-line and off-line monitored results condition assessment risk of failure reliability indicators ABB Brazil JCM A Power de abril de Products 2015 Slide Division 13

14 Maintenance Minimum Maintenance Condition Based Minimum Invasive Operation and Performance Data monitoring and data analysis Advanced Monitoring Condition Based Maintenance chronology data, time, number of maneuvers (in and off) data, time, lightning strikes on-line date, time, current, voltage, power, reactive power date, time, temperatures ambient, oil, winding date, time, oil key dissolved gas and moisture date, time, OIP bushing C1 and tanδ variations on-line periodic external inspection oil level, leaking, vibration, rubber bag, silica gel, etc periodic infrared scanning radiators, tank and bushings periodic in lab oil tests Properties, DGA, 2Fal periodic ABB Brazil JCM A Power de abril de Products 2015 Slide Division 14

15 Maintenance Minimum Maintenance Condition Based Minimum Invasive Advanced Monitoring Condition Based Maintenance 4. Maintenance Electrical Tests event & condition based HV OIP condensive bushings C1 & tand test ü on-line monitoring of HV OIP condensive bushings C1 & tand ü consider to install PCORE TEST TERMINAL to C1& tand tests ü eliminate periodic condensive bushings C1 & tand tests FRA Frequency Response Doble M5400 test ü base line before energization ü perform just after a major system event or a major earthquake Core and Winding tests ü commissioning tests at site ü eliminate periodic core and winding tests PCORE Test Terminal HUBBEL Power Systems 1. before 2. after a major system event 3. after a relevant change in the monitored pattern 1. before 2. after a major system event 1. before 2. after a major system event 3. after a relevant change in the monitored pattern ABB Brazil JCM A Power de abril de Products 2015 Slide Division 15

16 Conclusions q Overall 1.Available Technology allows utilization of a Minimum Invasive Condition Based Maintenance Strategy 2.Combined efforts from High Quality Shunt Reactors, Knowledge Based Operation, Monitoring Data Analysis and Asset Managment! q power transformers purchasing process to evaluate overall performance global economic evaluation aligned with Transmission Project ROI regulation requires minimum invasive condition based maintenance q steps to minimum maintenance high quality power transformers from a well known technology knowledge on the power transformers design limits to reliable operation detailed care of all process steps: from purchasing to energization q condition based maintenance time based periodic inspections on-line monitoring of minimum key parameters off-line tests/maintenance supported by on-line monitoring data analysis q advanced asset managment ABB Brazil JCM A Power de abril de Products 2015 Slide Division 16

17 Monitoring On-Line Monitoring and Sensors: load current & voltage ambient temperature top-oil temperature winding hotspot temperature moisture in oil/solid insulation gas in oil H2, CO, C2H4, C2H2 (Hydran) HV OIP cond bushings C1 & tand ISA reactors üs üs üs üs? s? s üs ABB TEC ABB Brazil JCM A Power de abril de Products 2015 Slide Division 17

18 Advanced Asset Management Data Analysis Action EAM Mobile ERP ALGORITHMS Sensors SCADA Historiador Centralized Information Data Storage Data Management Data Protection ABB Methods Data Mining Condition Assessment Models failure risk asset condition Strategic Decisions Maintenance Plan Later Maintenance Replacement ABB Brazil JCM A Power de abril de Products 2015 Slide Division 18

19 Advanced Asset Management Advanced Operational BI Data Processing and Analytics Engineering Workbench Complete Information Fleet to Equipment Health Actionable Notifications Business Process Workflow Optimization &Planning Subject Matter Workbench Enterprise Data Sources Enterprise Asset and Work Management ABB Brazil JCM A Power de abril de Products 2015 Slide Division 19

20 Advanced Asset Management - Potential Benefits ABB Brazil JCM A Power de abril de Products 2015 Slide Division 20

21 Advanced Asset Management - Monitor ABB Brazil JCM A Power de abril de Products 2015 Slide Division 21

22 Advanced Asset Management - Monitor ABB Brazil JCM A Power de abril de Products 2015 Slide Division 22

23 Advanced Asset Management Maintenance Planning ABB Brazil JCM A Power de abril de Products 2015 Slide Division 23

24

Transformer Fleet Management with e-terraassetcare

Transformer Fleet Management with e-terraassetcare Transformer Fleet Management with e-terraassetcare Jean-Michel AGNIER [email protected] Alstom-Grid - http://www.alstom.com/ Asset Management Development Director Alstom Group Thermal Power

More information

Electrical Maintenance Workshop

Electrical Maintenance Workshop Electrical Maintenance Workshop Transformer Maintenance & Testing Thursday, November 6, 2003 Transformer Maintenance & Testing Purpose This presentation provides an overview of the major considerations

More information

Alstom Grid Services. Transformer lifecycle management GRID

Alstom Grid Services. Transformer lifecycle management GRID Alstom Grid Services Transformer lifecycle management GRID Transformer services A COMPLETE RANGE OF SOLUTIONS As a critical component of networks, the power transformer is essential to high voltage electrical

More information

Lessons from the Real World Webinar Series

Lessons from the Real World Webinar Series Lessons from the Real World Webinar Series End-to-End Asset Health September 11, 2013 End-to-End Asset Health 1. The challenge and the opportunity 2. The end-to-end process 3. Asset health center concept

More information

GE Energy Transformer Monitoring: How Moving forward from Monitoring to Diagnostics can Positively Impact Indian Business and Industry

GE Energy Transformer Monitoring: How Moving forward from Monitoring to Diagnostics can Positively Impact Indian Business and Industry GE Energy Transformer Monitoring: How Moving forward from Monitoring to Diagnostics can Positively Impact Indian Business and Industry Brian Sparling, SMIEEE GridTech 2007, Delhi February 5-6, 2007 The

More information

THE VALUE OF POWER FACTOR TESTING

THE VALUE OF POWER FACTOR TESTING THE VALUE OF POWER FACTOR TESTING Nov 1, 2005 12:00 PM by John Bleyer and Phillip Prout, National Grid NATIONAL GRID DISCOVERED A HIGH POWER FACTOR DURING ACCEPTANCE TESTING of a new 40-MVA transformer

More information

On-line monitoring of substation condition a Romanian experience. V. ZAHARESCU, Vl. ROSCA Nova Industrial SA. CN Transelectrica SA Romania

On-line monitoring of substation condition a Romanian experience. V. ZAHARESCU, Vl. ROSCA Nova Industrial SA. CN Transelectrica SA Romania 21, rue d Artois, F-75008 PARIS http : //www.cigre.org B3_201 CIGRE 2012 On-line monitoring of substation condition a Romanian experience C. MOLDOVEANU*, V. BREZOIANU, S. GAL, V. METIU, A. VASILE, V. URSIANU,

More information

DGA - Method in the Past and for the Future

DGA - Method in the Past and for the Future DGA - Method in the Past and for the Future Page 2 May 2012 1970 1973 Doerenburg introduced the differentiation between electrical and thermal failure mode and introduced ratios for fault gases with similar

More information

Transforming know-how into solutions. Siemens Transformer Service TLM

Transforming know-how into solutions. Siemens Transformer Service TLM Transforming know-how into solutions. Siemens Transformer Service TLM TLM Agenda Introduction Instalation and Comissioning Condition Assessment Monitoring Repairs and Retrofit Spare Parts - Solutions After

More information

ESCOM BY G.KALINDE SUBSTATIONS ENGINEER

ESCOM BY G.KALINDE SUBSTATIONS ENGINEER ESCOM BY G.KALINDE SUBSTATIONS ENGINEER Balance Shareholder and Customer Interests Balance Short and Long Term Serviceability Understand trade-offs between Value and Risk Apply Asset Management Tools Build

More information

Siemens TMDS transformer monitoring and diagnostic system. Solutions for transformer life-cycle management. Answers for energy.

Siemens TMDS transformer monitoring and diagnostic system. Solutions for transformer life-cycle management. Answers for energy. Siemens TMDS transformer monitoring and diagnostic system Solutions for transformer life-cycle management Answers for energy. We strive to unlock value in your transformer monitoring and Smart Grid investments.

More information

Root-Cause Analysis of Transformer Failure Scenario at Power Sub-Station

Root-Cause Analysis of Transformer Failure Scenario at Power Sub-Station Root-Cause Analysis of Transformer Failure Scenario at Power Sub-Station AMBUJ KUMAR Department of Electrical Engineering National Institute of Technology, Hamirpur (HP) India Email: [email protected]

More information

Intelligent maintenance decisions with ABB TrafoAssetManagement TM proactive services

Intelligent maintenance decisions with ABB TrafoAssetManagement TM proactive services Intelligent maintenance decisions with ABB TrafoAssetManagement TM proactive services Paul Ammann, Pierre Lorin, Anders Grano ABB Power Products - Transformer Service ABSTRACT Transformers are indispensable

More information

Practical Transformers: Operation, Maintenance and Testing

Practical Transformers: Operation, Maintenance and Testing Practical Transformers: Operation, Maintenance and Testing YOU WILL GAIN: 4 hour live, practical online course Saturday, 2 nd May, 2015 8.00AM WST; 10.00AM AEST An understanding of the fundamental theory

More information

Power transformers. Generator step-up and system intertie power transformers Securing high-quality AC transmission

Power transformers. Generator step-up and system intertie power transformers Securing high-quality AC transmission Power transformers Generator step-up and system intertie power transformers Securing high-quality AC transmission Generator step-up transformers Built to withstand continuous full load Generator step-up

More information

Enhance Power Equipment Reliability with Predictive Maintenance Technologies

Enhance Power Equipment Reliability with Predictive Maintenance Technologies Enhance Power Equipment Reliability with Predictive Maintenance Technologies November 2012/1910DB1208 by S. Frank Waterer, Electrical Engineerinig, Fellow Schneider Electric USA, Inc. Make the most of

More information

Transformer Design & Design Parameters

Transformer Design & Design Parameters Transformer Design & Design Parameters - Ronnie Minhaz, P.Eng. Power Transmission + Distribution GENERATION TRANSMISSION SUB-TRANSMISSION DISTRIBUTION DISTRIBUTED POWER 115/10 or 20 kv 500/230 230/13.8

More information

Vision 2050 An Asset Management Strategy. Jaclyn Cantler Manager, Transmission Planning, PHI

Vision 2050 An Asset Management Strategy. Jaclyn Cantler Manager, Transmission Planning, PHI 1 Vision 2050 An Asset Management Strategy Jaclyn Cantler Manager, Transmission Planning, PHI 2 Agenda Case for Change About Vision 2050 Status Closing System Design Cybersecurity Interface with distributed/dispersed

More information

Hydro Plant Risk Assessment Guide

Hydro Plant Risk Assessment Guide September 2006 Hydro Plant Risk Assessment Guide Appendix E5: Transformer Condition Assessment E5.1 GENERAL Power transformers are key components in the power train at hydroelectric powerplants and are

More information

OPTIMIZE YOUR FLEET MANAGEMENT RESOURCES

OPTIMIZE YOUR FLEET MANAGEMENT RESOURCES OPTIMIZE YOUR FLEET MANAGEMENT RESOURCES PROACTIVE RISK MANAGEMENT Inside View DGA Diagnostic Software: Integrates Lab, On-line and Portable Data Continuous Data Interpretation Automated Alerts And Notifications

More information

electrical services WWW.AU.SGS.COM/INDUSTRIAL

electrical services WWW.AU.SGS.COM/INDUSTRIAL electrical services WWW.AU.SGS.COM/INDUSTRIAL OUR PROFILE SGS offers a full range of electrical engineering services covering the commissioning test of new plant as well as the maintenance and continual

More information

On-line PD Monitoring Makes Good Business Sense

On-line PD Monitoring Makes Good Business Sense On-line PD Monitoring Makes Good Business Sense An essential tool for asset managers to ensure reliable operation, improve maintenance efficiency and to extend the life of their electrical assets. Executive

More information

TMDS Smart Monitor. Solutions for transformer life-cycle management. Answers for energy.

TMDS Smart Monitor. Solutions for transformer life-cycle management. Answers for energy. TMDS Smart Monitor Solutions for transformer life-cycle management Answers for energy. TMDS Smart Monitor Selecting a transformer monitoring solution is a critical step in achieving your company s Smart

More information

Application of On-line Monitoring Systems in the view of Maintenance Engineering of Eletrobras Furnas

Application of On-line Monitoring Systems in the view of Maintenance Engineering of Eletrobras Furnas 1 Application of On-line Monitoring Systems in the view of Maintenance Engineering of Eletrobras Furnas Fabio Abreu Pinto, Eletrobras Furnas, Jorge Santelli da Silva, Eletrobras Furnas, and Marcos E. G.

More information

Electric Power Distribution

Electric Power Distribution Electric Power Distribution A S Pabla Consulting Engineer and Former Chief Engineer Punjab State Electricity Board McGraw-Hill New York Chicago San Francisco Lisbon London Madrid Mexico City Milan New

More information

Certification Awarded to ABB LTDA. AV. DOS AUTONOMISTAS, 1496, VILA CAMPESINA, 06020-902 - OSASCO/SP BRAZIL

Certification Awarded to ABB LTDA. AV. DOS AUTONOMISTAS, 1496, VILA CAMPESINA, 06020-902 - OSASCO/SP BRAZIL Certification Bureau Veritas Certification certifies that the Management System of the above organization has been assessed and found to be in accordance with the requirements of the standard detailed

More information

Attachment 20.64 SA Power Networks: Asset Management Plan 3.2.01 Substation Transformers 2014 to 2025

Attachment 20.64 SA Power Networks: Asset Management Plan 3.2.01 Substation Transformers 2014 to 2025 Attachment 20.64 SA Power Networks: Asset Management Plan 3.2.01 Substation Transformers 2014 to 2025 ASSET MANAGEMENT PLAN 3.2.01 SUBSTATION TRANSFORMERS 2014 TO 2025 Published: October 2014 SA Power

More information

Smart Asset Management

Smart Asset Management Smart Asset Management Stephen McArthur [email protected] Drivers Environment Solar radiation Wind speed and direction Atmospheric pressure Relative humidity Precipitation Conservator tank Key

More information

Proactive Asset Management for GIS A six step process for reducing risk, cost, and improving reliability

Proactive Asset Management for GIS A six step process for reducing risk, cost, and improving reliability White paper Proactive Asset Management for GIS A six step process for reducing risk, cost, and improving reliability Gas Insulated Substations (GIS) are often critical assets for most organizations. GIS

More information

1ZSC000563-AAC en, Rev. 7. Resin impregnated paper bushing, oil to air, type GSB Technical guide

1ZSC000563-AAC en, Rev. 7. Resin impregnated paper bushing, oil to air, type GSB Technical guide 1ZSC000563-AAC en, Rev. 7 Resin impregnated paper bushing, oil to air, type GSB Technical guide Original instruction The information provided in this document is intended to be general and does not cover

More information

A Step-Up Transformer Online Monitoring Experience at Euzébio Rocha UTE [Thermal Power Plant]

A Step-Up Transformer Online Monitoring Experience at Euzébio Rocha UTE [Thermal Power Plant] A Step-Up Transformer Online Monitoring Experience at Euzébio Rocha UTE [Thermal Power Plant] Ivan da Costa Vieira (2) 2 Lucas Pavan Fritoli (3) 3 Fábio Marcelino de Paula Santos (1) 1 ABSTRACT The step-up

More information

ABB LTDA. Av. dos Autonomistas, 1496, Vila Campesina, 06020-902 - Osasco/SP Brazil

ABB LTDA. Av. dos Autonomistas, 1496, Vila Campesina, 06020-902 - Osasco/SP Brazil Av. dos Autonomistas, 1496, Vila Campesina, 06020-902 - Osasco/SP Brazil Bureau Veritas Certification certify that the Management System of the above organization has been audited and found to be in accordance

More information

Discussion on Class I & II Terminology. IEEE PES Transformers Committee Fall Meeting 2011 Boston, MA

Discussion on Class I & II Terminology. IEEE PES Transformers Committee Fall Meeting 2011 Boston, MA Discussion on Class I & II Terminology IEEE PES Transformers Committee Fall Meeting 2011 Boston, MA What is Class I & II? C57.12.00 2010 is the only document we have that defined these terms. 5.10 Insulation

More information

MiCAFIL. 1 RIP Technology. Bushings. Z. Zic 09/2003

MiCAFIL. 1 RIP Technology. Bushings. Z. Zic 09/2003 MiCAFIL 1 RIP Technology Z. Zic 09/2003 )XQFWLRQRI+LJK9ROWDJH%XVKLQJ Uncontrolled (natural) electrical field Capacity-controlled electrical field %XVKLQJV0DLQ,QVXODWLRQ6\VWHPV 7\SH 0DLQ,QVXODWLRQ +RXVLQJFRYHU

More information

Facility Support Services

Facility Support Services Facility Support Services The Precision Group has a breadth of experience delivering innovative, first class facility support service solutions to clients across the public and private sectors. Our expert

More information

www.siemens.com/energy High Voltage Circuit Breakers 3AP Type 72.5 kv to 800 kv Answers for energy.

www.siemens.com/energy High Voltage Circuit Breakers 3AP Type 72.5 kv to 800 kv Answers for energy. s www.siemens.com/energy High Voltage Circuit Breakers AP Type 7.5 kv to 800 kv Answers for energy. The AP High Voltage Circuit Breakers Available up to 800 kv Decades of our experience in high voltage

More information

Online Transformer Insulation Monitoring System BushingGard Product Focus. Maximizing Transformer Uptime and Reliability

Online Transformer Insulation Monitoring System BushingGard Product Focus. Maximizing Transformer Uptime and Reliability Online Transformer Insulation Monitoring System BushingGard Product Focus Maximizing Transformer Uptime and Reliability Critical Energy Transfer... Large power transformers are found around the world at

More information

SEWER CHEWER Wastewater / Sludge Grinder Submersible Gearmotor

SEWER CHEWER Wastewater / Sludge Grinder Submersible Gearmotor INSTALLATION, OPERATION AND MAINTENANCE MANUAL For SEWER CHEWER Wastewater / Sludge Grinder Submersible Gearmotor Yeomans Chicago Corporation 3905 Enterprise Court P.O. Box 6620 Aurora, IL 60598-0620 Phone:

More information

DISSOLVED GAS ANALYSIS OF MINERAL OIL INSULATING FLUIDS

DISSOLVED GAS ANALYSIS OF MINERAL OIL INSULATING FLUIDS DISSOLVED GAS ANALYSIS OF MINERAL OIL INSULATING FLUIDS Written by: Joseph B. DiGiorgio, Ph.D. Dr. DiGiorgio conducts seminars on request. 1996-2013 NTT Copyrighted material. Contact Dr. DiGiorgio Insulating

More information

Brochure. ABB Customer Training Program for Motors and Generators Sharing knowledge and creating value

Brochure. ABB Customer Training Program for Motors and Generators Sharing knowledge and creating value Brochure ABB Customer Training Program for Motors and Generators Sharing knowledge and creating value With expertise, and a comprehensive portfolio of products and life-cycle services, we help value-minded

More information

21 st Century Facilities

21 st Century Facilities Electrical Testing 21 st Century Facilities Facility Owners face tough challenges 24 X 7 reliability needed Non linear loads cause harmonics VFD Computers Switching transients disrupt operations Less customer

More information

Primary and Secondary Electrical Distribution Systems

Primary and Secondary Electrical Distribution Systems Primary and Secondary Electrical Distribution Systems Critical Facilities Round Table 12th Quarterly Membership Meeting June 2, 2006 David D. Roybal. P.E. Eaton Electrical Cutler-Hammer Products Utility

More information

A GUIDE TO TRANSFORMER OIL ANALYSIS BY I.A.R. GRAY Transformer Chemistry Services

A GUIDE TO TRANSFORMER OIL ANALYSIS BY I.A.R. GRAY Transformer Chemistry Services A GUIDE TO TRANSFORMER OIL ANALYSIS BY I.A.R. GRAY Transformer Chemistry Services INTRODUCTION The fault free operation of power transformers is a factor of major economic importance and safety in power

More information

SMART ASSET MANAGEMENT MAXIMISE VALUE AND RELIABILITY

SMART ASSET MANAGEMENT MAXIMISE VALUE AND RELIABILITY SMART ASSET MANAGEMENT MAXIMISE VALUE AND RELIABILITY Electrical equipment is a critical component of your asset portfolio. Beyond its financial value, it plays an even greater role in your business performance.

More information

Customer Support Agreements

Customer Support Agreements Cleveland Brothers Product Support Customer Support Agreements Maximize Uptime Minimize Risk Insulate Prices Increase Profitability Let a CSA go to WORK for your company CUSTOMER SUPPORT AGREEMENTS A CSA

More information

Presentation of the France Transfo factories

Presentation of the France Transfo factories Presentation of the France Transfo factories France Transfo's internationally recognised and highly esteemed expertise is today exported to more than 80 countries throughout the world. Over the past 15

More information

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS Meher Capacitors offers reliable and innovative products and solutions in the fields of Reactive Power Compensation, Power Quality and Energy

More information

Max. Length of HTS Cables in the Future

Max. Length of HTS Cables in the Future Max. Length of HTS Cables in the Future K. Schippl, Nexans Deutschland Industries, Hannover, Germany TOPICS: Limitation of the cable design: 1. Physical limitations 2. Shipping limitations 3. Maintenance

More information

Power Transmission and Distribution. Shunt reactors for medium and highvoltage. From development to use

Power Transmission and Distribution. Shunt reactors for medium and highvoltage. From development to use Power Transmission and Distribution Shunt reactors for medium and highvoltage networks: From development to use From the beginning up to today more quality and reliability for your network A safe power

More information

TRANSFORMERS AFTERMARKET SPARES, SERVICE & REPAIR

TRANSFORMERS AFTERMARKET SPARES, SERVICE & REPAIR TRANSFORMERS SPARES, SERVICE & REPAIR 02 TRANSFORMERS ENERGY SOLUTIONS FOR THE GLOBAL POWER INDUSTRY BRUSH Transformers is globally renowned for the quality of its products, innovation and service. Our

More information

Technical catalogue About KOLEKTOR ETRA has been acting as transformer manufacturer over more than 75 years. Specializing in the manufacturing of power transformers rating up to 500 MVA and 420 kv the

More information

GE Intelligent Platforms. Mine Performance. from GE Predictivity

GE Intelligent Platforms. Mine Performance. from GE Predictivity GE Intelligent Platforms Mine Performance from GE Predictivity Increase throughput and availability If you re like most mining companies, you need to improve both your processes and your equipment availability

More information

ASSESSMENT OF OIL ANALYSIS DATA FOR MEDIUM VOLTAGE DISTRIBUTION TRANSFORMERS

ASSESSMENT OF OIL ANALYSIS DATA FOR MEDIUM VOLTAGE DISTRIBUTION TRANSFORMERS ASSESSMENT OF OIL ANALYSIS DATA FOR MEDIUM VOLTAGE DISTRIBUTION TRANSFORMERS A. Müller 1*, M. Jovalekic 1, S. Tenbohlen 1 1 Institute of Power Transmission and High Voltage Technology, University of Stuttgart,

More information

Instructions for Secondary Unit Substation Transformers 150-3000 KVA, Three Phase

Instructions for Secondary Unit Substation Transformers 150-3000 KVA, Three Phase ABB Inc. Instruction Booklet Distribution Transformers Jefferson City, MO ISO 9001 Certified I.B. 46-060-1, Section E ILUJ000004-BLE Effective: January, 2008 Instructions for Secondary Unit Substation

More information

Step Up Transformer Online Monitoring Experience in Tucuruí Power Plant

Step Up Transformer Online Monitoring Experience in Tucuruí Power Plant 1 Step Up Transformer Online Monitoring Experience in Tucuruí Power Plant José Aliezio. A. Severo, Eletrobras Eletronorte, Klaxon. V. Fantin, Eletrobras Eletronorte, and Marcos E. G. Alves, Treetech Digital

More information

FUNDAMENTAL PRINCIPLES OF TRANSFORMER THERMAL LOADING AND PROTECTION. Abstract. Introduction

FUNDAMENTAL PRINCIPLES OF TRANSFORMER THERMAL LOADING AND PROTECTION. Abstract. Introduction FUNDAMENTAL PRINCIPLES OF TRANSFORMER THERMAL LOADING AND PROTECTION Joe Perez, ERLPhase Power Technologies, Winnipeg, MB, R3Y 1G4 Abstract Power transformers are traditionally protected by differential

More information

ELECTROPUTERE ROTATING ELECTRICAL MACHINES DIVISION

ELECTROPUTERE ROTATING ELECTRICAL MACHINES DIVISION ELECTROPUTERE ROTATING ELECTRICAL MACHINES DIVISION SC ELECTROPUTERE SA SC ELECTROPUTERE SA 1. Vision, Mission, Values SC ELECTROPUTERE SA 2. LOCATION Craiova: Located in the South West of the country,

More information

Dissolved Gas Analysis Guide for Transformers Filled with Beta Fluid

Dissolved Gas Analysis Guide for Transformers Filled with Beta Fluid DSI Ventures, Inc. PHONE: (903) 526-7577 FAX: (903) 526-0021 www.dsiventures.com Dissolved Gas Analysis Guide for Transformers Filled with Beta Fluid Introduction Analysis of dissolved gases in transformer

More information

HI TECH TRANSFORMER MAINTENANCE (PTY) LTD. COMPANY PROFILE AND OVERVIEW 19 March 2012

HI TECH TRANSFORMER MAINTENANCE (PTY) LTD. COMPANY PROFILE AND OVERVIEW 19 March 2012 HI TECH TRANSFORMER MAINTENANCE (PTY) LTD COMPANY PROFILE AND OVERVIEW 19 March 2012 COMPANY BACKGROUND The company was founded in 1996. Ownership changed in 2005. Mainly provided site transformer maintenance

More information

globe reactions made easy Process perfection

globe reactions made easy Process perfection globe reactions made easy Process perfection Benefits More reactions in less time: The Globe oil drain unit and quick clamp allow single hand vessel changes in seconds Space saving: 50ml, 100ml, 250ml,

More information

CDS TROUBLESHOOTING SECTION I. VACUUM. 1.0. Weak vacuum at wand. Gauge reads normal (10hg to 14hg)

CDS TROUBLESHOOTING SECTION I. VACUUM. 1.0. Weak vacuum at wand. Gauge reads normal (10hg to 14hg) CDS TROUBLESHOOTING SECTION I. VACUUM 1.0. Weak vacuum at wand. Gauge reads normal (10hg to 14hg) 1.1. Clogged hoses or wand tube. Disconnect hoses and carefully check for an obstruction. 1.2. Excessive

More information

National Competency Based Skill Training Refrigeration and Air-conditioning Mechanic Logbook

National Competency Based Skill Training Refrigeration and Air-conditioning Mechanic Logbook National Competency Based Skill Training Refrigeration and Air-conditioning Mechanic Logbook Trainee:... Training Provider:... Year:... Trainee Contact no:... Competency Based Skill Training Logbook Introduction

More information

Backup Fuel Oil System Decommissioning & Restoration Plan

Backup Fuel Oil System Decommissioning & Restoration Plan Backup Fuel Oil System Page 1 of 19 Overview of Physical Fuel Oil System and Decommissioning Steps The fuel oil system at Milford Power consists of a number of subsystems. These include the following:

More information

Generators TEM. for small hydroelectric power stations. Electric Machines

Generators TEM. for small hydroelectric power stations. Electric Machines Generators for small hydroelectric power stations TEM Electric Machines Advanced solutions for the cleanest energy Reputable manufacturer of generators for small hydroelectric power stations TED Electric

More information

Subminiature Load Cell Model 8417

Subminiature Load Cell Model 8417 w Technical Product Information Subminiature Load Cell 1. Introduction... 2 2. Preparing for use... 2 2.1 Unpacking... 2 2.2 Using the instrument for the first time... 2 2.3 Grounding and potential connection...

More information

This section applies to the design and installation of transformers.

This section applies to the design and installation of transformers. ELECTRICAL: TRANSFORMERS BASIS OF DESIGN This section applies to the design and installation of transformers. Design Criteria 13.8-kV equipment shall be 15-kV class. Coordinate with short-circuit studies

More information

5.12 Automated Integration of Condition Monitoring with an Optimized Maintenance Scheduler for Circuit Breakers and Power Transformers (T-19)

5.12 Automated Integration of Condition Monitoring with an Optimized Maintenance Scheduler for Circuit Breakers and Power Transformers (T-19) 5.12 Automated Integration of Condition Monitoring with an Optimized Maintenance Scheduler for Circuit Breakers and Power Transformers (T-19) Summary Research Need Research Stem Academic Team Members Industry

More information

Executive summary 2. 1 Introduction 4

Executive summary 2. 1 Introduction 4 Flexible Networks for a Low Carbon Future Future Network Monitoring Strategy September 2015 Contents Executive summary 2 Glossary 3 1 Introduction 4 2 Fundamental principles of monitoring 5 2.1 LCT monitoring

More information

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV 1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled

More information

Autoclave Safety. Autoclaves are sterilizers using high pressure and high temperature steam. The potential safety risks for the operators are:

Autoclave Safety. Autoclaves are sterilizers using high pressure and high temperature steam. The potential safety risks for the operators are: Autoclave Safety Purpose: Sterilization refers to the complete killing of all living organisms, including spores. Common sterilization techniques include the application of wet heat, dry heat, chemicals,

More information

Load Cell Troubleshooting

Load Cell Troubleshooting VPG TRANSDUCERS Load Cells and Weigh Modules Technical Note VPGT-08 Scope Load cells are designed to sense force or weight under a wide range of adverse conditions; they are not only the most essential

More information

TRANSFORMING THE UTILITY INDUSTRY

TRANSFORMING THE UTILITY INDUSTRY TRANSFORMING THE UTILITY INDUSTRY WITH POWER WHEN AND WHERE YOU NEED IT Emerald Transformer offers nationwide services covering every phase of the transformer life cycle. Focused exclusively on the needs

More information

RECOATING AND RENEWING SPF ROOFING SYSTEMS

RECOATING AND RENEWING SPF ROOFING SYSTEMS RECOATING AND RENEWING SPF ROOFING SYSTEMS Procedures, Regional Differences and type of coating systems Bruce Schenke Premium Spray Products REASONS TO RECOAT/RENEW Add a new coating layer to renew the

More information

Semester 2. Final Exam Review

Semester 2. Final Exam Review Semester 2 Final Exam Review Motion and Force Vocab Motion object changes position relative to a reference point. Speed distance traveled in a period of time. Velocity speed in a direction. Acceleration

More information

Making the Most of SáOá SM Services

Making the Most of SáOá SM Services MAINTENANCE PRODUCTS AND SERVICES Making the Most of SáOá SM Services With S O S Services, you don t just get test results, you get accurate analysis from the people who know your Cat equipment best. Your

More information

BELZONA KNOW-HOW VALVES, PIPES AND FITTINGS BELZONA VPF SYSTEM SELECTOR BELZONA KNOW-HOW FOR VALVES, PIPES AND FITTINGS

BELZONA KNOW-HOW VALVES, PIPES AND FITTINGS BELZONA VPF SYSTEM SELECTOR BELZONA KNOW-HOW FOR VALVES, PIPES AND FITTINGS KNOW-HOW FOR THE REPAIR, RENOVATION AND RECLAMATION OF VALVES, PIPES AND FITTINGS B E L Z O N A V P F VPF SYSTEM SELECTOR FOR VALVES, PIPES AND FITTINGS SYSTEM Belzona VPF-1 Belzona VPF-2 Belzona VPF-3

More information

Instructions. Installation, Operation, and Maintenance of Medium Power Substation Transformers. Howard Industries Substation Transformer Division

Instructions. Installation, Operation, and Maintenance of Medium Power Substation Transformers. Howard Industries Substation Transformer Division Instructions Installation, Operation, and Maintenance of Howard Industries Substation Transformer Division IMPORTANT SAFETY INFORMATION Read these instructions carefully before proceeding with installation,

More information

Table Z. Troubleshooting Chart for Air Conditioners. Cause

Table Z. Troubleshooting Chart for Air Conditioners. Cause Troubleshooting Chart for Air Conditioners Type of Unit Complaint Cause With open-type compressor Electric motor will not start Power failure Check circuit for power source Compressor stuck Locate cause

More information

Transformer Thermal Overload Protection - What s It All About?

Transformer Thermal Overload Protection - What s It All About? Transformer Thermal Overload Protection - What s It All About? Glenn Swift, Dave Fedirchuk, Zhiying Zhang APT Power Technologies, Winnipeg, Canada Presented at the 25th Annual Western Protective Relay

More information

BLUESTAR INFRARED. Description: Thermal Properties Comparison. Project Location: Client: 759 South Federal Hwy 225 Bayshore Drive 800-216-1820

BLUESTAR INFRARED. Description: Thermal Properties Comparison. Project Location: Client: 759 South Federal Hwy 225 Bayshore Drive 800-216-1820 BLUESTAR INFRARED We Bring Bad Things to Light SERVING ALL OF FLORIDA Infrared Inspection Services 24 Hour Emergency Service I n f r a r e d I n s p e c t i o n R e p o r t 772-215-8794 Description: Thermal

More information

ON-LINE DIAGNOSTIC CASE STUDY INVOLVING A GENERAL ELECTRIC TYPE U BUSHING

ON-LINE DIAGNOSTIC CASE STUDY INVOLVING A GENERAL ELECTRIC TYPE U BUSHING ON-LINE DIAGNOSTIC CASE STUDY INVOLVING A GENERAL ELECTRIC TYPE U BUSHING Pamelyn Bahr and Jon Christensen Intermountain Power Service Corp. Robert C. Brusetti, P.E. Doble Engineering Company ABSTRACT

More information

Trouble Shooting. Pump

Trouble Shooting. Pump Trouble Shooting Pump Trouble Possible Cause Remedy Oil leaking in the area of water pump crankshaft Worn crankshaft seal, bad bearing, grooved shaft, or failure of retainer o-ring. Excessive play on crankshaft

More information

Investigation on Sampling, Measurement and Interpretation of Gas-in-Oil Analysis for Power Transformers

Investigation on Sampling, Measurement and Interpretation of Gas-in-Oil Analysis for Power Transformers 21, rue d Artois, F-75008 PARIS D1-204 CIGRE 2008 http : //www.cigre.org Investigation on Sampling, Measurement and Interpretation of Gas-in-Oil Analysis for Power Transformers S. Tenbohlen, J. Aragon-Patil,

More information

SPECIFIC INSTRUCTIONS ON HOW TO PERIODICALLY CHECK FOR STRESS CRACKING CAUSED BY CHEMICALS, HANDLING ABUSE & ENVIRONMENTAL DEGRADATION

SPECIFIC INSTRUCTIONS ON HOW TO PERIODICALLY CHECK FOR STRESS CRACKING CAUSED BY CHEMICALS, HANDLING ABUSE & ENVIRONMENTAL DEGRADATION SPECIFIC INSTRUCTIONS ON HOW TO PERIODICALLY CHECK FOR STRESS CRACKING CAUSED BY CHEMICALS, HANDLING ABUSE & ENVIRONMENTAL DEGRADATION Provides the same capability for checking your liquid bulk storage

More information

MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING

MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING Training Title MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING Training Duration 5 days Training Date MV, HV and EHV Switchgear Testing & Commissioning 5 20 24 Apr $3,750 Dubai, UAE In any of the 5 star

More information

CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services

CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services SpecialistS IN ELECTRICAL SUPPORT SERVICES TO MINING, UTILITIES & industry Ampcontrol is committed to supporting our customers to maintain efficient

More information

Dewchecker 2.0. Operating instructions. messen steuern automatisieren - messen steuern automatisieren - messen steuern - automatisieren

Dewchecker 2.0. Operating instructions. messen steuern automatisieren - messen steuern automatisieren - messen steuern - automatisieren Operating instructions Dewchecker 2.0 messen steuern automatisieren - messen steuern automatisieren - messen steuern - automatisieren 1. Application The Dewchecker is suitable for dewpoint measuring of

More information

Thermal Adhesives Ther-O-Bond 1500

Thermal Adhesives Ther-O-Bond 1500 Products / Interface Materials / Adhesives Adhesives Bond 1500 Epoxy casting system for potting and encapsulation Bond 1600 Two part epoxy for bonding Bond 2000 Rapid cure acrylic adhesive bond High strength

More information

SECTION 15750 PACKAGED ROOFTOP AIR CONDITIONING UNITS

SECTION 15750 PACKAGED ROOFTOP AIR CONDITIONING UNITS SECTION 15750 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes requirements for roof mounted, self-contained units, with electric cooling, and electric or reverse refrigeration cycle (heat pump) heating

More information

GE Energy. Solutions

GE Energy. Solutions GE Energy Wind Service Solutions Speed, competency and technology... Faster return to service GE s wind turbine fleet is one of the fastest growing and most reliable in the world. Building on a strong

More information

Technical Electrical Field Service Support. Knowledge + Experience = Power. Field Service

Technical Electrical Field Service Support. Knowledge + Experience = Power. Field Service Technical Electrical Field Service Support Knowledge + Experience = Power Field Service WRE Field Service Wismer & Rawlings Electric Ltd. Substation Testing and Commissioning Mission Statement To be recognized

More information

Facilities Instructions, Standards, and Techniques Volume 4-1B. Maintenance Scheduling for Electrical Equipment

Facilities Instructions, Standards, and Techniques Volume 4-1B. Maintenance Scheduling for Electrical Equipment Facilities Instructions, Standards, and Techniques Volume 4-1B Maintenance Scheduling for Electrical Equipment U.S. Department of the Interior Bureau of Reclamation Denver, Colorado January 2012 REPORT

More information

Energy Transmission and Distribution Services

Energy Transmission and Distribution Services Energy Transmission and Distribution Services Business segment presentation Asset Services Energy is an essential part of our daily lives Industry Education Mobility Workplace Entertainment Homes Healthcare

More information

Perception Fleet. GE Digital Energy. Smart Management System. Transformer Fleet Risk Management Software System. Simple Diagnostics.

Perception Fleet. GE Digital Energy. Smart Management System. Transformer Fleet Risk Management Software System. Simple Diagnostics. GE Digital Energy Perception Fleet Transformer Fleet Risk Management Software System Easy to install and configure, Perception Fleet delivers instantaneous results upon installation. Continuing its legacy

More information

Onshore Wind Services

Onshore Wind Services GE Renewable Energy Onshore Wind Services www.ge.com/wind PITCH TABLE OF CONTENTS: 3 Operate and Maintain 3 Asset and Park Management 5 Turbine Maintenance 8 Enhance and Optimize 8 Wind PowerUp * Services

More information