1 Country Study Myanmar: Sustainable increase in power generation capacity a review of effective options Power-Gen Asia, Kuala Lumpur, September 2014 Shah, Abhay Business Development Manager - Power Plants, Wärtsilä Singapore Pte Ltd. Legal disclaimer This document is provided for informational purposes only and may not be incorporated into any agreement. The information and conclusions in this document are based upon calculations (including software built-in assumptions), observations, assumptions, publicly available competitor information, and other information obtained by Wärtsilä or provided to Wärtsilä by its customers, prospective customers or other third parties (the information ) and is not intended to substitute independent evaluation. No representation or warranty of any kind is made in respect of any such information. Wärtsilä expressly disclaims any responsibility for, and does not guarantee, the correctness or the completeness of the information. The calculations and assumptions included in the information do not necessarily take into account all the factors that could be relevant. Nothing in this document shall be construed as a guarantee or warranty of the performance of any Wärtsilä equipment or installation or the savings or other benefits that could be achieved by using Wärtsilä technology, equipment or installations instead of any or other technology. 1 P a g e

2 1. Abstract Myanmar has a huge potential for fast economic development and growth. However, the growth is very much dependent on the country s capacity to develop a reliable power infrastructure to increase access to electricity and to support industrial development. For that matter, it is crucial that the country conducts a comprehensive evaluation of the appropriate fuel mix and different generation technologies that are available for power generation both in short and long term. This paper provides a review on Myanmar s power system today, assesses the fuel and technology options available, and makes some recommendations for both short and long-term power generation options. The paper recommends dual-fuel medium speed internal combustion engines capable of running on HFO initially and switching to natural gas when available as a practical and feasible solution for increasing Myanmar s permanent power generation capacity quickly. Furthermore, the paper reveals that dual fuel combustion engines prove to be the optimum solution keeping in mind shortterm constraints as well as long-term needs of the country. Medium speed combustion engines have considerably lower life-cycle cost of generation than alternative technologies. 2. Myanmar general overview A few decades ago, the Republic of the Union of Myanmar, formally known as Burma, was considered to be the "Pearl of Asia". It was one of the region's leading economies, with a per capita income more than twice that of its neighbour, Thailand. After decades of isolation and stagnation, the political and economic reforms in the recent years have caused the world to closely focus on Myanmar. Isolation has kept the progress of the country at a very slow pace, hence providing massive potential to grow. Currently, Myanmar has one of the lowest GDP and electricity consumption per capita in the region. With its remarkable natural reserves, untapped oil and gas potential, promising demographics with 62% of the population in working age, and its strategic location, Myanmar has potential to become one of Asia s leading economies. A huge domestic market of approximately 60 million people, the potential to become a low-cost manufacturing hub and a leading position in oil & gas industry have undoubtedly attracted vast foreign interest to Myanmar. Oil and gas have together been the largest source of the country s foreign income for more than two decades. Gas exports were valued at USD 3.3 billion, accounting for almost 40% of all exports in financial year Compared to other ASEAN countries, Myanmar s hydrocarbon reserves are quite significant: proven gas reserves are estimated at 283 billion cubic meters and proven oil reserves at 50 million barrels. Potential gas reserves are expected to be ~ 2.2 trillion cubic meters. Institutions like World Bank, ADB, JICA, and IFC are active in the country and trying to support the development of the Myanmar at a faster pace. 2 P a g e

3 3. Electricity market overview With a measly 29% electrification ratio, more than 2/3 of the Myanmar population lacks access to electricity. With a forecasted GDP growth of ~7 8%, the country has kept electricity on the top of its agenda. The current installed power generation capacity of Myanmar is ~3800 MWe. 68% of it comes from hydro, 29% coming from gas and one coal plant of 120 MW. For the sake of comparison, the neighbouring Thailand, with a similar population as Myanmar, has ten times higher installed power generation capacity. There is a notable difference in available capacity: in the wet season, the available capacity in Myanmar is about ~ 2500 MWe, while in the dry season it can be as low as 1800 MWe due to reduced generation from hydro power plants. Some of the installed plants, for example the gas- and coal-fired ones, cannot run at its rated capacity and efficiency due to ageing and a sub-optimal maintenance history. With forecasted increase of ~15% per year, the annual demand is forecasted to reach ~ MWe by 2030 in a high growth scenario. To match this, the country will need on average 800 to 1000 MWe additions to its power generation capacity every year. The existing subsidies on electricity tariff are putting pressure on governmental budget. With the hike in April 2014, tariff is ranging from 35 Kyat (~3.5 USD cents)/kwh to 150 Kyat (~15 USD cents) /Kwh depending on type of consumers and units consumed. Feeble transmission and distribution (T&D) network are causing very high losses of about 26%. It is almost impossible for the county to rely on national grid for 24/7 power, especially during the dry season or in areas outside of the former capital Yangon. Alternate source of electricity is the only solution for reliable power, which in most cases are diesel-fired, highspeed generators. At many places, these are the only sources of electricity available, which may cost ~ USD cents /Kwh or even more. The entire power sector in Myanmar is under the responsibility of the Ministry of Electric Power (MOEP). In its existing structure, MOEP is the sole player in-charge of transmission, distribution, off-taking, regulation and system planning. Until very recently, all the generation capacity was also owned by MOEP. Keeping in mind the rapid growth, huge need for investments, country s current fiscal situation and scarcity of in-house resources, Myanmar is aggressively looking at external funding and Independent Power Producers (IPP). With a lack of IPP history, readily available project financing, or a bankable framework and contracts, attracting foreign investments is a challenge that the country is trying to overcome. While the country has attracted significant foreign interest from IPP developers, the journey to implement project financed IPP projects has just began. 3 P a g e

4 4. Load demand and transmission & distribution network Due to the availability of hydropower mainly in northern and eastern part of the country and the majority of power demand being around the Yangon region (as illustrated in Figure 1); there is a need to transmit the power from north to south. The power demand in the Yangon region is also expected to remain substantially higher as compared to other parts of the country. Central Myanmar, around Mandalay and the surrounding region, is also coming up as a high demand area. However, the mismatch in demand & supply due to the location difference of generation capacity and load pockets requires a robust, reliable and efficient transmission and distribution system in the country. The country has transmission lines of 230kV, 132kV and 66kV, and it lacks interconnection with neighbouring countries. Power flow from north to south is reaching its capacity limit, especially in the eastern route of the country. There are several single-circuit segments, causing the system to be unreliable. Overall, the capacity and conditions of the T&D network needs substantial improvement. The Government of Myanmar is in the process of making upgrades to the transmission and distribution system. It is envisaged to build several new transmission lines and introducing a 500 kv system and reduce the T&D losses from the current 26%. Figure 1: Myanmar: Power source and Load distribution P a g e

5 5. Quick fix power generation solutions implemented To cater to the rising demand and to meet immediate shortfall, MOEP has awarded a few IPP projects that will use domestic natural gas supplied to MOEP by Myanma Oil and Gas Enterprise (MOGE), a national oil and gas company under the Ministry of Energy. On the tariff structure, fuel cost is settled between Myanma Electric Power Enterprise (MEPE is the off-taker) and MOGE while the IPPs receive a tariff excluding fuel price. There are three IPPs of 25 to 50 MWe each, using high speed gas engines, with unit sizes ranging from 1 MW to 4.3 MWe each. There are a couple of projects above 100 MWe range, using gas turbines to be initially started on open (single) cycle mode and later to be converted to combined cycle. The government has also implemented some short-term rental power plants as temporary solutions to fill the gap between supply and demand, until more efficient and sustainable power plants come up in future. Such plants have been implemented to cater to the immediate requirement of power. The IPPs implemented so far, are not project financed, but mostly equity financed. Also some of these IPPs had to sacrifice on electrical efficiency due to choice of technologies e.g. high speed gas engines. However, such plants have supported the county with quick power through private investments in a critical time of electricity shortage. Clearly, these are short-term focused solutions to cater to an immediate need. Going forward, the country would look at implementing high efficiency and sustainable power plants with lower lifecycle costs through long-term focused solutions. The government has already initiated a couple of power plants in 100 to 200 MW range, with international practices and standards to bring Myanmar to a level playing field with other countries in the region. Going forward, it is important for the country to explore and evaluate various fuel and technology options to be able to meet power demand at lowest life cycle cost in the years to come. 6. Possible fuel options to meet future electricity demand Fuel mix is not only one of the most critical resources but also one of the main constraints while planning power generation capacity, and Myanmar s case is no different. Though the fuel types being used for utility-scale power generation are not too many, it is of utmost importance to evaluate each option in the light of benefits and challenges attached to it, considering local perspective. In this section, the possible primary sources of power and fuel options are evaluated in Myanmar s perspective. 6.1 Hydro Power: Myanmar is one of the few countries blessed with tremendous natural potential of hydro power. Myanmar has developed only ~2.6% of its overall hydro potential of ~108 GW. The IPPs developed by its neighbours China and Thailand dominates the future hydro power development and about half of such electricity is expected to be allocated to these countries. Overall, hydro is expected to remain the dominant source of electricity for Myanmar in years to come. 5 P a g e

6 Along with its benefit, hydro power is also prone to seasonal variations. Myanmar has two distinct seasons: Dry season is prominent in the country, typically lasting from April to June and affecting the hydro power. Hydro power generation in dry season can be as low as 60% of the generation in the wet season. This being a big variation, the country faces even bigger challenge to meet the power demand during the dry season. Large hydro plants take several years, sometimes more than a decade to develop before coming into operation. Also, the environmental and social impact of developing hydro power makes it difficult to implement potential projects in the most effective and timely manner. The mismatch between dam locations and demand hubs of the country also means that Myanmar needs robust T&D network to transport the electricity from such hydro power plants to where it is most needed. The additional cost, time and power losses associated with such T&D network are not to be forgotten. Hence, due to the long development cycle, seasonal variation in power output and the dependence on weather conditions, Myanmar cannot rely solely on hydro power, especially in the dry season and in the near future. The country must look at fossil fuels to complement hydro power. Thermal power plants are reliable irrespective of weather conditions, can be developed faster, and are easier to install closer to power demand. 6.2 Natural gas: Myanmar has gas reserves; however, currently supply is insufficient to meet local demand, due to existing long-term export contracts with Thailand and China. Recently, the country has awarded more than 35 offshore and onshore blocks for further exploration. However, it will take several years before these blocks will come into production. On the positive side, the government has announced that future gas will be used domestically before any export. Currently available gas is planned to be consumed by existing power stations, plants under construction or development. Additional gas is expected to come online around 2021, if no delay occurs in the exploration and development schedule. This means that, although in the longer run Myanmar will have additional domestic gas, for short- to medium-term it will have to rely on other fossil fuel for power generation. 6.3 Coal: Myanmar s only coal plant is running at 50% of its rated capacity of 120 MW. The county has stalled the development of big coal power plants in past, on the basis of environmental impact. The future policy of the Government on coal plants remains to be seen. Even if the country decides to pursue coal plants due to cheaper generation cost, implementing coal plants will be challenging, especially in the short term. There is less than 1 million ton/year domestic coal available; however, the quality is poor, and reserves are not significant. Hence, relying on imported coal is mandatory. In addition to logistic infrastructural development for importing the coal, other challenges like the longer 6 P a g e

7 development and construction period required by coal power plants and unwillingness of multilaterals to finance coal power projects, make it challenging for coal to be considered as a short-term solution for Myanmar. Going forward, cheaper hydro power will remain as the first priority to get dispatched. Coal plants are typically used for baseload operation and are not operationally flexible enough to provide load following or perform quick start-and-stop cycles. This means that even if coal plants are chosen as part of the generation mix by the government of Myanmar, sufficient capacity of such plants may not be operational in near future. Hence, liquid fuels need to be considered as part of the short-term solution. 6.4 Liquefied natural gas (LNG): LNG is an option to supplement gas supply where gas is either not available or not sufficient in the right location. LNG is more often used, either to reduce the cost of generation as compared to an alternate fuel or to reduce emissions. Some countries also consider using LNG for fuel security or diversity. In the context of Myanmar, if the country imports LNG, the cost of gas along with its transportation, storage and re-gasification, could be as high as USD/MMBTU, depending on the size of the terminal, number of tanks and the location of power plants. This is 35 to 45% expensive as compared to the commercial price of domestic gas, which is in the range of ~12 USD/MMBTU. It is noteworthy that the real cost of gas to various ministries may be much lower than 12 USD/MMBTU. And already MOEP has heavy subsidy in existing tariff with prevailing fuel prices in the country. LNG import terminals and storage tanks take several years to develop and construct. For Myanmar, where the key motive to have LNG is to make gas available for immediate use, the expensive LNG may not be available before 3 5 years after the decision to import LNG is made. Keeping in mind the country s gas reserve, the imported LNG may be useful only for a limited period. And if the LNG is not available at the right time, the value of expensive LNG may not yield benefits to Myanmar. However, if the power tariff from the use of expensive LNG can be accepted by the country and imported LNG may be a part of the long-term solution, it may be considered for future perspective; but certainly not in the short term. 6.5 Liquid fuels (diesel, HFO and crude oil): Diesel: Currently, most of the diesel used in Myanmar is imported. Using diesel in back-up generators to keep the lights on is widely seen in Myanmar. For any country, using diesel in utility-scale power plants, especially on baseload, is the least preferred solution, mainly due to its cost (see figure 2). In addition to small back-up generators, diesel can also be used in medium speed combustion engines as well as gas turbines. 7 P a g e

8 USD/ton Heavy fuel oil (HFO): Historically, HFO is average ~35% cheaper than diesel, and it can be shipped to Myanmar for example from Singapore. Lower cost than diesel is the key reason that it is widely used as fuel in power generation in various countries like Brazil, Dominican Republic, India, Bangladesh, Philippines, Cambodia, and several countries in Africa and Middle East. Many of these countries use HFO, even in utility scale power plants, where liquid fuel is the practically most feasible option. It is possible to use a commercially available HFO quality which is compliant with World Bank s Emission guidelines, which are applicable in Myanmar currently /3/2010 1/3/2011 1/3/2012 1/3/2013 1/3/2014 Diesel (Singapore, 0.5% S) HFO (Singapore, 3.5% S, 380cSt) Spread (savings from using HFO instead of Diesel) Figure 2: Evolution of spot prices of HFO and diesel in Singapore hub, including the spread between them There are private companies who have initiated importing HFO to Myanmar and making it locally available for power generation Crude oil: Myanmar not only has proven crude oil reserves of 50 MMbbl but also has a current production of about bbl/day, which will be increased in the years to come. Currently, sufficient crude oil is not available locally in Myanmar and there is a huge shortfall between demand and supply. However, as more and more onshore and offshore blocks will start to be explored, crude oil may be available, which can be used in power generation. Most of the prime movers that can burn HFO (boilers, combustion engines, etc.) can also burn crude oil. 6.6 Wind and Solar power: In recent years, renewable energy like wind and solar power are being looked at, especially in developed countries, due to its minimum impact on the environment. Myanmar is in a very early stage of evaluating the potential of such renewable energy in the country as well in its mix. Wind and solar power cannot be used for baseload power generation due to its intermittent nature depending on the weather. Typically, such renewable capacity also requires backup power from alternate back up sources that makes it more expensive for baseload power. Hence, looking at the current plans on wind and solar power development, accounting for the higher cost of generation and the intermittency, it may not be practical for Myanmar to implement large-scale wind or solar power plants in the short term. 8 P a g e

9 SUMMARY OF FUEL OPTIONS FOR MYANMAR IN SHORT TERM So, what is the most optimal fuel choice for Myanmar between 2016 and e.g. 2021? Looking at all possible options for the generation mix presented above, hydro power will be the top priority for Myanmar s power generation. In the absence of sufficient hydro power in the dry season and due to its longer development cycle, thermal plants will also be required in Myanmar. Sufficient additional domestic gas will not be available before ~2021.Even if coal would be approved for power generation by the Government of Myanmar, a coal plant would take several years to come online. LNG infrastructure will not only take several years to implement, but will also be very expensive. Wind and solar cannot provide standalone, constant reliable power for base load demand. Hence, the optimal and most practical solution for the country would be to use HFO, which is substantially cheaper than diesel, for an interim period before additional gas is available; and switch over to gas, once available. Hydro Takes several years to come online Seasonal variations make it unreliable in dry season Need robust T&D lines for bigger plants, which will demand addtiional time, cost and T&D losses Not suitable for short-term reliable power supply Natural Gas Not enough domestic natural gas for next 5 7 years Ideal fuel for Myanmar but only when readily available in sufficienct quantity Not suitable for short-term reliable power supply Coal LNG Wind, Solar Not sufficienct good quality domestic coal Takes several years to come online emissions impact Need robust T&D lines for bigger plants, which will demand additional time, cost and T&D losses Not suitable for short-term relaible power supply Takes several years to come online Much more expensive than domestic gas Domestic gas will be available in medium to long term. Current challange is to find fuel for immediate use Not suitable for short-term relaible power supply Intermittent nature of wind and solar, makes it weather dependant and hence un-reliable Needs back-up from themal power plants Expensive power and takes many years to come online Not suitable for short-term reliable power supply Diesel Possible to use in short term. Expensive fuel and very high cost of generation HFO ~30-35% cheaper than diesel Possible to use in short term Possible to meet World Bank's Emission Guidelines Ideal fuel to be used temporarily before domestic gas is available Figure 3: HFO represents the optimal fuel for immediate temporary use before additional domestic gas is available 9 P a g e

10 7. Technology options based on gas and liquid fuel The focus for the country is to implement additional power generation capacity in next ~5-7 years, which is not only affordable, but also sustainable and provides the cheapest lifecycle cost of generation. Different prime mover technologies which can burn liquid fuel and gas are briefly analysed here. The inland transportation of heavier equipment to many parts of the Myanmar can be a challenge due to existing road and bridge conditions. For many locations river transportation is to be considered and this also needs to be evaluated while selecting the optimum technology. The following commercially available and well-accepted technology options that can use liquid fuels and/or gas are reviewed here. 1) Choice between open and combined cycle plants 2) High speed diesel generators and high speed gas engines 3) Gas turbines on open cycle as well as combined cycle 4) Medium speed gas engines on open cycle as well as combined cycle 5) Dual fuel power plants based on combustion engines or gas turbines. 7.1 Open cycle vs. combined cycle power plants: Combined cycle (CC) power plants are a well-accepted solution to increase the plant output, without additional fuel consumption and hence increasing the electrical efficiency, and are typically used for baseload. CC power plant needs additional investments in equipment like waste heat recovery boilers and steam turbines and hence, requires much higher capital investment in USD/KWe compared to an open cycle power plant. CC power plants are the most efficient solutions for baseload applications where the plant is not expected to be running at lower/partial load or started/stopped frequently. However, if the power plants are expected to be running on variable/lower load or starting-stopping frequently, it is important to evaluate if the improved efficiency is worth the additional capital investment Looking at the current load pattern, there is as high as 40% variation between peak and offpeak load demand in Myanmar. For each plant, the decision of whether the plant should be open cycle or combined cycle depends on several factors listed below: a) the electrical efficiency of the plant on open cycle b) additional investment needed to make the plant combined cycle and corresponding increase in electrical efficiency and output c) cost of fuel d) expected operating and load profile of the plant e) other relevant factors like availability of water, plant construction time etc. 10 P a g e

11 In summary, a detailed feasibility study on lifecycle cost of generation for each plant will indicate the optimal solution between open cycle and combined cycle solution. The key aspect here is that the feasibility study should be made based on an expected running profile for a specific plant and fuel (including running on possible backup fuel). An inaccurate forecast of the load pattern may result in sub-optimal selection. 7.2 High speed diesel engines or gas engines: High speed diesel engines are widely used in Myanmar for back-up power, and also a couple of IPPs implemented based on high speed gas engines. These engines typically run at 1200 to 1500 rpm and are available in a range from less than 1 MW to ~ 5 MW, each. The benefits of these engines are low CAPEX and faster construction time. However, such engines are generally not used for baseload application due to its poor electrical efficiency and shorter equipment life time. Hence, when compared with other available solutions based on lifecycle cost including fuel, high speed engines are not optimal solutions for long-term applications. High speed engines are not used in combined cycle mode considering the additional CAPEX and incremental improvement in performance. In most cases, high speed engines are used for backup or short term power generation, where efficiency is not of prime importance. 7.3 Gas turbines on open cycle and combined cycle This is one of the most widely used technologies in power generation industry. Open cycle gas turbines provide net lifecycle efficiencies of ~30 40%, at typical Myanmar ambient conditions, depending on type and size. Due to such lower efficiencies, most applications use combined cycle gas turbines to enhance electrical efficiency. Latest bigger-sized combined cycle gas turbine power plants, of >400 MW, provide the highest possible efficiency. Combined cycle gas turbine plants typically take 24 to 36 months to construct; and provide optimal efficiency when running at full load. However, the efficiency drops substantially when operating at part-load, which is typically the case for most grid-connected plants that ramp their capacity down during low demand hours e.g. at night time. Especially, in countries like Myanmar where baseload power generation may be met with hydro or other cheaper source of power, for example coal, if available. The load on some of the gas power plants may be reduced in different times of the day or during wet seasons. 7.4 Medium speed combustion engine power plants These are power plants based on internal combustion engines, typically in the range of 500 to 750 rpm. The size of these engines may vary from 4 MW to 20 MWe each. Medium speed engines can burn a variety of liquid fuels, like HFO, crude oil, diesel, liquid biofuel etc. in 11 P a g e

12 Efficiency (%) addition to natural gas. These engines provide a best-in-class ISO efficiency of >48% on open cycle and on combined cycle even higher efficiency of >52%. In recent years, the plant sizes based on medium speed engines have increased to more than 600 MWe, with multiple modular units. The higher efficiency and operational as well as fuel flexibility makes it a competitive solution. Some of the most attractive characteristics of such power plants are that it can maintain high efficiency even on partial load (Figure 4), its fuel flexibility to burn multi fuels efficiently, higher availability and reliability due to multiple units, low gas pressure requirement of 6 barg and operational flexibility. It has the capacity of starting from hot standby mode and reaching full load in mere 2 to 5 minutes, and can be stopped in 1 minute. Furthermore, starts and stops do not affect the maintenance cost of the plant. Faster construction time is one of the important benefits of such plants. An open cycle plant based on medium speed combustion engines can be constructed in less than 12 months, whereas a combined cycle plant can be constructed in ~18 months % 20% 40% 60% 80% 100% Plant load Medium sp. comb. engines - open cycle Gas turbine - open cycle Medium sp. comb. engines - combined cycle *<30% load, the plant is assumed to operate on open cycle Gas turbine - combined cycle Figure 4: Performance comparison of engine- and gas turbine-based technologies on part-load 7.5 Dual fuel power plants liquid fuel first and gas when it is available. Dual fuel power plants can burn different types of fuels, namely natural gas as well as various liquid fuels. The benefits of such power plants are best recognised when they need to rely on alternate fuel in the absence of its intended primary fuel. For example, certain gas power plants can temporarily run on liquid fuel in the absence of a to-be-developed, malfunctioning or temporarily unavailable gas supply. 12 P a g e

13 Depending on the technology, some gas-based power plants can use liquid fuel as a backup. For example, medium speed combustion engine power plants can use even HFO or crude oil in addition to diesel, minimizing the running cost by making use of the cheapest fuel available at any given time. Once gas becomes available, the plant can seamlessly start to consume gas as primary fuel, without any modification. The ISO efficiency of combustion engine based dual fuel plants on liquid fuel mode can be as high as 44 47% on open cycle and > 51% on combined cycle, including at partial loads. Gas turbine technology can also burn diesel oil in addition to gas but considering the high price of diesel, this option is not economical. It is not common to use HFO in gas turbines. The turbine efficiency when running on liquid fuel is affected and maintenance schedule as well as costs are negatively and drastically affected. SUMMARY OF TECHNOLOGY OPTIONS FOR MYANMAR As mentioned in the summary of Section 6, liquid fuel will have an important role to play in Myanmar. It is crucial to note that plants will not be running on liquid fuel for a long time, but only for a temporary period when Myanmar is facing the gas shortage. Considering the gas availability in a few years from now, dual fuel medium speed engines represent the optimal solution to increase the power generation capacity in the short term due to its ability to efficiently burn HFO, capability to switchover to gas, faster construction period and performance on liquid fuel as well as gas mode. These plants can burn cheaper HFO instead of diesel before domestic gas or imported LNG is available, and will later be switched to burn gas efficiently, as soon as it is available. Figure 5: Typical 200 MW open cycle power plant based on dual fuel combustion engines. 13 P a g e

14 8. Centralized vs. decentralized power plants Myanmar has implemented or initiated a few power plants in the range of MWe in the last couple of years. Also going forward, at least in short-term the planned project sizes are also in similar range. There are some discussions on the possibility of implementing bigger gas-fired and coal power plants of e.g. 500 MW or even bigger, but such plans seem to be rather long term. The government s focus on mid sized plants is rightfully addressing some of the challenges linked to implementing bigger power plants in Myanmar. Some of these challenges are described below: 1) Readily available, competitive and reliable fuel supply for bigger power plants 2) Development and construction of bigger power projects takes 3 5 years, whereas country needs immediate power. 3) Strengthening and developing the T&D network to evacuate the power. This will require not only additional time, but also finance. 4) Raising the finance for bigger power plants, especially in the absence of IPP framework and bankable project agreements would be challenging. It is important to look at the impact of transmitting the power using the existing T&D infrastructure and the associated losses. The following figure 6 illustrates the possible effect on electrical efficiency of having power plants closer to the load pocket. If the electricity needs to be transported from a bigger and high efficiency plant (e.g. 55% net, lifecycle electrical efficiency at site conditions), considering the losses, the net efficiency at the point of consumption will be substantially lower. Electrical efficiency at generation point η e,g 55% Transmission & distribution system losses L trans 26% Electrical efficiency at consumption point η e,c = 40. 7% Figure 6: Simplified view of impact of power system losses on net efficiency On the other hand, installing a power plant with a smaller capacity (e.g MWe) closer to the load demand is not only faster to construct, but also easier to finance and would avoid putting all the eggs in one basket. Not only the T&D losses, but also the additional time and cost needed for developing the required T&D network are reduced to a great extent. Such smaller, de-centralized plants that can provide net efficiency of ~ 50% are valuable considering the net electrical efficiency at point of consumption. 14 P a g e

15 9. Preliminary feasibility case studies In this section, life-cycle costs of different dual fuel and gas power plants using combustion engine and gas turbine technologies are evaluated. Two scenarios are considered for preliminary feasibility study. The cost of capital is assumed as 11.7%. And the fuel costs assumed in the study are indicated below. Gas-12USD/MMBTU HFO-770 USD/Ton Diesel-1060 USD/Ton Lube oil- 3USD/Litre 9.1 Scenario 1: Using liquid fuel for temporary period, until gas is available 50 MW open cycle plant & 100 MW combined cycle power plant Life-cycle costs of two different power plant sizes are being compared in this section. It is assumed that plant will run on liquid fuel for first 4 years and later on use gas as primary fuel. Comparison 1: 50MW open-cycle plant using dual fuel combustion engine and dual fuel gas turbine technology Comparison 2: 100MW combined cycle plant using dual fuel combustion engine and gas dual fuel turbine technology Feasibility study yields the following conclusions: Combustion engines can use cheaper HFO during the initial operating years when gas is not available. However, gas turbines would need to use more expensive diesel/light fuel oil because of its inability to us HFO efficiently and optimally. In the case of a 50 MW open cycle power plant, the average tariff of the power generated from a dual fuel gas turbine plants is more than 19% higher than the same power generated from a dual fuel combustion engine based plant. The tariff will in both cases be high for the initial 4 years, due to the high fuel cost i.e. HFO/diesel, but the average tariff for the 20 years reduces, due to the lower cost of gas during the later years. Combustion engines have higher efficiency both in liquid fuel and gas mode. The calculated achievable savings are 7 MUSD per year, adding up to a total of ~140 MUSD savings for a 20-year project lifetime by using dual fuel combustion engines. Similar results are obtained for the 100 MW combined cycle power plant. Savings of 7.15 MUSD per year can be obtained by choosing dual fuel combustion engines over similar CCGT, resulting in ~143 MUSD savings for a 20 years project lifetime. Brief details can be found in the table 1, table 2 and figure 7 below. 15 P a g e

16 Table 1: 50 MW open cycle dual fuel power plant: key figures for dual fuel combustion engines (DF) and gas turbines (GT) based power plants Assumptions/Results 50MW DF Engine plant - HFO mode (1-4 yrs) 50MW DF Engine plant - Gas mode 50MW GT Diesel mode (1-4 yrs) 50MW GT - Gas mode Configuration 6x20V34DF 6x20V34DF 1xLM6000PG 1xLM6000PG EPC cost (MUSD) Construction Time (months) O&M cost (USD/MWh) Lube Oil Cons. (kg/h) Net life-cycle output (MW) Net life-cycle efficiency@ 80% (MW) Power generation (MWh/year) ) ) 41.3% 44.3% 36.8% 1) 37.9% 1) ) Based on GT Pro software (including degradation factor of 0.5% for Engine plant / 2% for GT plants & part load impact of 80%capacity factor) Site conditions ambient temp 30C, relative humidity 60%, 20masl. Gas MN >80. Table 2: 100 MW CC dual fuel power plant: key figures for combustion engines (DF) and gas turbines (GT) based power plants Assumptions/Results 100 MW DF Engine plant- HFO mode (1-4 yrs) 100 MW DF Engine plant - gas mode 100 MW GT - diesel mode (1-4 yrs) 100 MW GT - gas mode Configuration 6x18V50DF-HFO 6x18V50DF-Gas LM LM EPC cost (MUSD) Construction Time (months) O&M cost (USD/MWh) Lube Oil Cons. (kg/h) Net Life-cycle output (MW) Net Life-cycle efficiency@ 80% (MW) Power generation (MWh/year) ) 111 2) 45.2% 48.0% 45.2% 2) 47.7% 2) ) Based on GT Pro software (including degradation factor of 0.5% for Engine plant / 2% for GT plants & part load impact of 80%capacity factor). Site conditions ambient temp 30C, relative humidity 60%, 20masl. Gas MN > P a g e

17 Tariff comparison 50 MW Tariff comparison 100 MW Average: Average: Average: ROE Average: ROE Debt service Debt service DF - HFO mode (1-4yrs) DF - Gas mode GT - Diesel mode (1-4yrs) O&M cost GT - Gas mode Fuel expenses 60.0 DF - HFO mode (1-4yrs) DF - Gas mode GT - Diesel mode (1-4yrs) GT - Gas mode O&M cost Fuel expenses Figure 7: 20 Year average tariff in USD/MWh for a 50 MW simple cycle plant (left) and a 100 MW combined cycle plant (right) based on dual fuel technology 9.2 Scenario 2: Using only gas 50 MW open cycle plant & 200 MW combined cycle power plant In this analysis, we compare the life-cycle costs of the following technologies. It is assumed that gas is available for the entire 20 years under study. Comparison 1: 50 MW open-cycle gas engine and 50 MW open-cycle gas turbine Comparison 2: 200 MW combined cycle gas engine plant and 200 MW combined cycle gas turbine plant The following conclusions could be drawn: In the case of a 50 MW open cycle power plant, the average tariff of power generated from the gas turbine plant is ~14% higher than the same power generated from combustion engines. Engines have a higher net efficiency of 44.8% on open cycle as compared to 37.9% with gas turbines. The calculated achievable savings by using combustion engines are 4.6 MUSD per year, for a total of ~92 MUSD savings for 20 years life cycle. In the case of a 200 MW combined cycle power plant, the average tariff of power generated from the gas turbine plants ~ USD/MWh, whereas that of combustion engine is ~ USD/MWh. The calculated achievable savings by using combustion engines are 3.9 MUSD per year, for a total of ~78 MUSD savings for a 20 year lifecycle. Brief details can be found in the table 3 and figure 8 below. 17 P a g e

18 Table 3: 50 MW open cycle and 200 MW combined cycle gas-fired power plant: key figures for combustion engines (SG) and gas turbines (GT) Assumptions/Results 50 MW SG 50 MW 200 MW SG 200 MW combined Gas Engine plant open cycle GT Gas Engine plant cycle GT Configuration 6x20V34SG 1xLM6000PG 10 x 18V50SG CC Frame 6FA EPC cost (MUSD) Construction Time (months) O&M cost (USD/MWh) Lube Oil Cons. (kg/h) Net Life-cycle output (MW) ) ) Net Life-cycle efficiency@ 80% (MW) ) ) Power generation (MWh/year) ) Based on GT Pro software (including degradation factor of 0.5% for Engine plant / 2% for GT plants & part load impact of 80%capacity factor). Site conditions ambient temp 30C, relative humidity 60%, 20masl. Gas MN >80. Tariff comparison 50MW & 200MW Debt service ROE O&M Cost Fuel expenses MW SG 50MW GT 200 MW SG 200MW GT Figure 8 : 20 Year average tariff in $/MWh of 50 MW open cycle and 200 MW combined cycle gas-fired power plant based on gas engines (SG) and gas turbines (GT) SUMMARY OF PRELIMINARY FEASIBILITY STUDY Based on the feasibility analysis, medium speed combustion engines have lower total lifecycle costs both in dual fuel and gas based applications. 18 P a g e

19 10. Long-term outlook In the long run, when enough hydro plants have been constructed, enough domestic gas is available or Myanmar considers additional renewable energy, the operating profile of some of the thermal power plants which are being installed now, will change. Dual fuel power plants would be running on gas mode. Hydro and coal power plants, if installed, would be running on baseload because of their low generation cost. However, gas power plants, due to their higher cost of generation, would be performing the load following to match the supply and demand during the different times of the day and different days of the year. Especially, if the country installs renewable energy, the flexibility in the grid is of utmost importance to respond quickly to the sudden power demand variations when wind is not blowing or sun is not shining. It is important to note the capability of gas power plants to respond to such situations in long term and run on partial load or quick start mode. Combined cycle gas turbine plants, when run on load following mode/partial load, have a substantially reduced efficiency. Due to their minimum stable load requirement, these plants cannot run at a very low load on combined cycle, and are forced to run on inefficient open cycle. The higher capital investment made in the combined cycle of the plant may not benefit much, if the plant is not run on higher load. Inability of combined cycle plants to carry out quick starts and stops, and huge impact on maintenance costs for every start and stop, make combined cycle gas turbines plants rather in-flexible in nature as compared to medium speed combustion engines. Medium speed combustion engines, which provide best-in-class efficiency in open cycle mode, are also capable to run on combined cycle, if needed and provides grid stability by providing operational flexibility and quick start-stop as described in Section 7 earlier. 11. Conclusion Myanmar faces major challenges for its power sector in the near future, headlined by the need to increase its power generation capacity. Many of the traditional solutions are not suitable in current situation: hydro and coal power plants take too long to develop and construct, a shortage of domestic gas is expected to last until further exploration yields results in ~2021 or even later, time is needed to develop a functioning LNG infrastructure and the high cost of imported LNG increases the cost of gas-fired generation dramatically. Considering these challenges, Myanmar will have to consider liquid fuel for power generation to meet the load demand in the immediate future. Being much cheaper than diesel, HFO should be the fuel of choice for Myanmar in the short term. However, when cheaper gas is available, such HFO fired plants should be switched to use gas. This paper demonstrates that medium speed engine based dual fuel power plants can run efficiently on HFO for a given period of time; and can later seamlessly switched to consume gas when available, without any modifications. This will make it possible to not only burn the 19 P a g e

20 cheapest liquid fuel when it is absolutely needed but also to provide an immediate solution for today s problems and hedge for tomorrow, making the best possible use of the country s indigenous hydrocarbon resources. The optimal technology for each project must be chosen based on a feasibility study specific to such project. According to preliminary feasibility study, it is important to select the most suitable technology for every project through technology-neutral tenders/requests for proposals. This will be the only way for the optimal solution to be selected for each specific power plant project. Some of the important criteria that must be considered in such feasibility studies are expected realistic running profiles of the power plants, efficiencies at various operating loads (and not only at full load) and performance parameters on both liquid fuel & gas mode, including the long-term impact on performance that may occur at the given site conditions. The life cycle cost analysis performed as part of this paper shows that medium speed combustion engine plants provide the best possible efficiency on HFO mode, as well as the lowest life cycle costs when compared to alternate technologies. In addition to this, the life cycle cost evaluation demonstrated that combustion engine-based power plants also provide lower life cycle costs when running on gas. In the long run, hydro or coal power plants would be running on baseload, and some of the gas power plants could run to cater to intermediate or peaking load. Hence, it is also important to consider the possibility to run gas and dual fuel plants flexibly in terms of their technical ability to do so, as well as the impact on the cost of generation. In that sense, the unmatchable operational flexibility of combustion engines, paired with their near-constant efficiency at any load, make them once again the optimal solution in long run. 20 P a g e

Role of Natural Gas in a Sustainable Energy Future

Role of Natural Gas in a Sustainable Energy Future Role of Natural Gas in a Sustainable Energy Future Alexander Medvedev, Deputy Chairman of Gazprom Management Committee, Director General of Gazprom Export 2 nd Ministerial Gas Forum Doha, 30 November 2010

More information

Prospects and Incentives for Use of Alternative Energy Technologies in the Arab Electric Power Generation Sector

Prospects and Incentives for Use of Alternative Energy Technologies in the Arab Electric Power Generation Sector Prospects and Incentives for Use of Alternative Energy Technologies in the Arab Electric Power Generation Sector Samir AlKotob Arab Fund for Economic and Social Development Objectives To overview the Arab

More information

Electricity Demand and Supply in Myanmar

Electricity Demand and Supply in Myanmar RAJAWALI FOUNDATION INSTITUTE FOR ASIA Electricity Demand and Supply in Myanmar Prepared for Proximity Designs Myanmar This research paper was written by David Dapice ([email protected]), of the

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY 1. 1. Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): ENERGY 1. 1. Sector Performance, Problems, and Opportunities Country Partnership Strategy: Bangladesh, 2011 SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Power generation gap. Bangladesh endures long

More information

CSP-gas hybrid plants: Cost effective and fully dispatchable integration of CSP into the electricity mix

CSP-gas hybrid plants: Cost effective and fully dispatchable integration of CSP into the electricity mix CSP-gas hybrid plants: Cost effective and fully dispatchable integration of CSP into the electricity mix Erik Zindel Director Marketing CSP (Power Block) Siemens AG PowerGen Europe 2012 Köln Messe, 12-14

More information

Keisuke Sadamori Director, Energy Markets and Security International Energy Agency Kuala Lumpur, 8 October

Keisuke Sadamori Director, Energy Markets and Security International Energy Agency Kuala Lumpur, 8 October Keisuke Sadamori Director, Energy Markets and Security International Energy Agency Kuala Lumpur, 8 October The context Southeast Asia is a key pillar of Asia s growth A mix of countries with disparate

More information

Comparison of Electricity Supply and Tariff Rates in South Asian Countries

Comparison of Electricity Supply and Tariff Rates in South Asian Countries Comparison of Electricity Supply and Tariff Rates in South Asian Countries By Faisal Jamil, Energy Specialist (Economics) Introduction A reliable, accessible and affordable supply of energy produced in

More information

GLOBAL RENEWABLE ENERGY MARKET OUTLOOK 2013

GLOBAL RENEWABLE ENERGY MARKET OUTLOOK 2013 GLOBAL RENEWABLE ENERGY MARKET OUTLOOK 213 FACT PACK GUY TURNER HEAD OF ECONOMICS AND COMMODITIES APRIL 26, 213 GLOBAL RENEWABLE ENERGY MARKET OUTLOOK, 26 APRIL 213 1 INTRODUCTION This year s Global Renewable

More information

Glossary of Energy Terms. Know Your Power. Towards a Participatory Approach for Sustainable Power Development in the Mekong Region

Glossary of Energy Terms. Know Your Power. Towards a Participatory Approach for Sustainable Power Development in the Mekong Region Glossary of Energy Terms Know Your Power 2012 Towards a Participatory Approach for Sustainable Power Development in the Mekong Region List of terms Terms Page Terms Page Avoided cost 10 Installed capacity

More information

Global growth rates Macroeconomic indicators CEDIGAZ Reference Scenario

Global growth rates Macroeconomic indicators CEDIGAZ Reference Scenario Medium and Long Term Natural Gas Outlook CEDIGAZ February 215 Global growth rates Macroeconomic indicators CEDIGAZ Reference Scenario 4 3 %/year 199-213 213-235 6 Main consuming markets - %/year (213-235)

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY. 1. Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): ENERGY. 1. Sector Performance, Problems, and Opportunities Country Operations Business Plan: Philippines, 2013 2015 SECTOR ASSESSMENT (SUMMARY): ENERGY 1. Sector Performance, Problems, and Opportunities 1. Challenges. Economic growth has been impeded in the Philippines

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY 1

SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Country Partnership Strategy: Uzbekistan 2012 2016 SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. The energy sector underpins Uzbekistan s sustained

More information

1. EXECUTIVE SUMMARY AND KEY RECOMMENDATIONS

1. EXECUTIVE SUMMARY AND KEY RECOMMENDATIONS 1. EXECUTIVE SUMMARY AND KEY RECOMMENDATIONS EXECUTIVE SUMMARY Energy policy in Greece has the potential to make a significant contribution to the country s economic recovery. Increasing competition and

More information

NATURAL GAS DEMAND AND SUPPLY Long Term Outlook to 2030

NATURAL GAS DEMAND AND SUPPLY Long Term Outlook to 2030 1. Background On different occasions, Eurogas is asked to present its views on the future of the European gas industry. The forecasts are mainly needed for conferences and bilateral discussions with European

More information

Electricity Rates Forecasting:

Electricity Rates Forecasting: Electricity Rates Forecasting: Muskrat Falls Will Options: Stabilize Rates for Consumers Legal S92A, Good Faith and Regulatory Proceedings in Quebec Department of Natural Resources October 2012 Department

More information

Republic of Zambia OPPORTUNITIES IN THE ENERGY SECTOR IN ZAMBIA

Republic of Zambia OPPORTUNITIES IN THE ENERGY SECTOR IN ZAMBIA Republic of Zambia OPPORTUNITIES IN THE ENERGY SECTOR IN ZAMBIA Presentation Outline COUNTRY PROFILE KEY POWER SECTOR PLAYERS OVERVIEW OF THE ENERGY SECTOR IN ZAMBIA ZAMBIA ENERGY SITUATION PRESENTLY RESULT

More information

Electricity market drivers

Electricity market drivers Daniel Assandri Head of Power Systems ABB (China) Ltd Electricity market drivers March 2008 Global T&D Market Drivers ABB Power Systems division - slide # 2 ABB s view on and market drivers The Americas

More information

Smart solutions for fleets of all types & sizes of power generation. Marcus König, E F IE SGS / September 2013

Smart solutions for fleets of all types & sizes of power generation. Marcus König, E F IE SGS / September 2013 Smart solutions for fleets of all types & sizes of power generation Marcus König, E F IE SGS / September 2013 Instrumentation, Controls & Electrical The Siemens structure: Four Sectors close to the customer

More information

SECTION 1. PREAMBLE 3 SECTION 2. EXECUTIVE SUMMARY 4 ABOUT US 6

SECTION 1. PREAMBLE 3 SECTION 2. EXECUTIVE SUMMARY 4 ABOUT US 6 CONTENTS SECTION 1. PREAMBLE 3 SECTION 2. EXECUTIVE SUMMARY 4 ABOUT US 6 Disclaimer notice on page 8 applies throughout. Page 2 SECTION 1. PREAMBLE The New Energy Outlook (NEO) is Bloomberg New Energy

More information

Levelized Cost of New Electricity Generating Technologies

Levelized Cost of New Electricity Generating Technologies Levelized Cost of New Electricity Generating Technologies The Energy Information Administration (EIA) produces forecasts of energy supply and demand for the next 20 years using the National Energy Modeling

More information

SOLARRESERVE. BASELOAD SOLAR Power. Improving Mining Economics with Predictable Energy Costs

SOLARRESERVE. BASELOAD SOLAR Power. Improving Mining Economics with Predictable Energy Costs SOLARRESERVE BASELOAD SOLAR Power Improving Mining Economics with Predictable Energy Costs UNDERSTANDING THE POWER REQUIREMENTS OF THE MINING INDUSTRY Mining operations, particularly those operating off-grid,

More information

Energy Megatrends 2020

Energy Megatrends 2020 Energy Megatrends 2020 Esa Vakkilainen 1 NOTE The data included in the following is mainly based on International Energy Agency's (IEA) World Energy Outlook 2007 IEA is considered the most reliable source

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY 1

SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Country Partnership Strategy: Kazakhstan 2012 2016 SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Overview. Oil accounts for about a quarter

More information

Energy & Environment Market Trends, Smart Technologies, New Fuels, Future Business Models and Growth Opportunities

Energy & Environment Market Trends, Smart Technologies, New Fuels, Future Business Models and Growth Opportunities & Environment Market Trends, Technologies, New Fuels, Future Business Models and Growth Opportunities September 2014 OUR COVERAGE & VISION: IDENTIFYING OPPORTUNITIES FROM UPSTREAM TO POINT OF USE Oil &

More information

WHEN AN EFFECTIVE EU ENERGY POLICY?

WHEN AN EFFECTIVE EU ENERGY POLICY? WHEN AN EFFECTIVE EU ENERGY POLICY? A. Clerici ABB Italy Honorary Chairman of WEC Italy Chairman of WEC WG The future role of nuclear in Europe 1 INDEX 1. General Comments 2. Vulnerability 3. Transmission

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The Republic of the Union of Myanmar Project: Urgent Rehabilitation and Upgrade Project Phase I Loan Agreement:

More information

Adapting Gas-Power Generation to New Role in Low-Carbon Energy Systems

Adapting Gas-Power Generation to New Role in Low-Carbon Energy Systems Adapting Gas-Power Generation to New Role in Low-Carbon Energy Systems Sandra Scalari Enel Ingegneria e Ricerca SpA Copenhagen, May 27-28 th 2014 Enel Presentation Generation Shift & Market in Europe Enel

More information

Electricity Insight NEW ZEALAND S ENERGY OUTLOOK. Preview of key insights: Exploring the uncertainty in future electricity demand and supply

Electricity Insight NEW ZEALAND S ENERGY OUTLOOK. Preview of key insights: Exploring the uncertainty in future electricity demand and supply NEW ZEALAND S ENERGY OUTLOOK Electricity Insight Exploring the uncertainty in future electricity demand and supply Preview of key insights: Lower demand growth and excess supply should put strong downward

More information

Gas-Fired Power HIGHLIGHTS

Gas-Fired Power HIGHLIGHTS Gas-Fired Power HIGHLIGHTS PROCESS AND TECHNOLOGY STATUS Approximately 21% of the world s electricity production is based on natural gas. The global gas-fired generation capacity amounts to 1168 GW e (2007).

More information

Levelized Cost and Levelized Avoided Cost of New Generation Resources in the Annual Energy Outlook 2015

Levelized Cost and Levelized Avoided Cost of New Generation Resources in the Annual Energy Outlook 2015 June 2015 Levelized Cost and Levelized Avoided Cost of New Generation Resources in the Annual Energy Outlook 2015 This paper presents average values of levelized costs for generating technologies that

More information

Natural Gas and Electricity Coordination Experiences and Challenges

Natural Gas and Electricity Coordination Experiences and Challenges 1 Natural Gas and Electricity Coordination Experiences and Challenges Challenges Facing the New England Power System Gordon van Welie, President and CEO, ISO New England 2015 IEEE Power & Energy Society

More information

SPANISH EXPERIENCE IN RENEWABLE ENERGY AND ENERGY EFFICIENCY. Anton Garcia Diaz Economic Bureau of the Prime Minister

SPANISH EXPERIENCE IN RENEWABLE ENERGY AND ENERGY EFFICIENCY. Anton Garcia Diaz Economic Bureau of the Prime Minister SPANISH EXPERIENCE IN RENEWABLE ENERGY AND ENERGY EFFICIENCY Anton Garcia Diaz Economic Bureau of the Prime Minister «Symposium on Strengthening Sino-Spain cooperation in multiple Fields» New Energy Cooperation

More information

Renewable Electricity and Liberalised Markets REALM. JOULE-III Project JOR3-CT98-0290 GREECE ACTION PLAN. By ICCS / NTUA K. Delkis

Renewable Electricity and Liberalised Markets REALM. JOULE-III Project JOR3-CT98-0290 GREECE ACTION PLAN. By ICCS / NTUA K. Delkis Renewable Electricity and Liberalised Markets REALM JOULE-III Project JOR3-CT98-0290 GREECE ACTION PLAN By ICCS / NTUA K. Delkis October 1999 INTRODUCTION AND BACKGROUND Background to Renewable Energy

More information

The Cost of Generating Electricity A COMMENTARY

The Cost of Generating Electricity A COMMENTARY The Cost of Generating Electricity A COMMENTARY on a study carried out by PB Power for The Royal Academy of Engineering THE ROYAL ACADEMY OF ENGINEERING Costs of Generating Electricity Commentary by the

More information

The Real Cost of Electrical Energy. Outline of Presentation

The Real Cost of Electrical Energy. Outline of Presentation 2 Outline of Presentation Data Sources Electricity Demand and Supply Cost to Meet Demand Profile Electricity Pricing Cost Impact of Dispatching Generation (Load Following) Simplifying Assumptions Electricity

More information

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid Pakistan Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid Final Report: Executive Summary - November 2015 for USAID Energy Policy

More information

Levelised Unit Electricity Cost Comparison of Alternate Technologies for Baseload Generation in Ontario

Levelised Unit Electricity Cost Comparison of Alternate Technologies for Baseload Generation in Ontario Canadian Energy Research Institute Levelised Unit Electricity Cost Comparison of Alternate Technologies for Baseload Generation in Ontario Matt Ayres Senior Director, Research Electricity Morgan MacRae

More information

Kyrgyzstan: Power Generation & Transmission

Kyrgyzstan: Power Generation & Transmission Kyrgyzstan: Power Generation & Transmission October, 2010 Author: Artyom Zozulinsky, Business & Commercial Assistant, US Embassy Bishkek Contents SUMMARY... 2 POWER SECTOR OVERVIEW... 2 Infrastructure...

More information

World Energy Outlook 2007: China and India Insights. www.worldenergyoutlook.org International Energy Agency

World Energy Outlook 2007: China and India Insights. www.worldenergyoutlook.org International Energy Agency World Energy Outlook 27: China and India Insights www.worldenergyoutlook.org International Energy Agency Why Focus on China & India? Increase in World Primary Energy Demand, Imports & Energy-Related CO

More information

Dual Fuel Medium Speed Product. Presenter Name Date

Dual Fuel Medium Speed Product. Presenter Name Date Dual Fuel Medium Speed Product Presenter Name Date Contents Caterpillar, Inc. Overview Our Product Line Dual Fuel Product Dual Fuel Conversion Performance & Maintenance References Caterpillar, Inc. Making

More information

Energy White Paper at a glance

Energy White Paper at a glance and Science Energy White Paper at a glance WWW. i Energy White Paper at a glance The Australian Government made an election commitment to deliver an Energy White Paper to give industry and consumers certainty

More information

Energy [R]evolution vs. IEA World Energy Outlook scenario

Energy [R]evolution vs. IEA World Energy Outlook scenario Energy [R]evolution vs. IEA World Energy Outlook scenario New set of scenarios takes climate crisis into account World Energy Outlook (WEO) 2008 for the first time takes the climate crisis really into

More information

Developing solar in emerging markets

Developing solar in emerging markets Developing solar in emerging markets Swedbank Conference March 17, 2016 Our values Predictable Driving results Change makers Working together Disclaimer The following presentation is being made only to,

More information

Draft consolidated baseline and monitoring methodology ACM00XX

Draft consolidated baseline and monitoring methodology ACM00XX Draft consolidated baseline and monitoring methodology ACM00XX Consolidated baseline and monitoring methodology for new grid connected fossil fuel fired power plants using a less GHG intensive technology

More information

The new Gas Turbine Portfolio to meet the market requirements for Distributed Generation

The new Gas Turbine Portfolio to meet the market requirements for Distributed Generation PowerGen Europe, 9-11 June 2015 The new Gas Turbine Portfolio to meet the market requirements for Distributed Generation Nicholas Muntz, Dr. Thorsten Krol Security classification Siemens AG 2015 All rights

More information

Summary of the Impact assessment for a 2030 climate and energy policy framework

Summary of the Impact assessment for a 2030 climate and energy policy framework Summary of the Impact assessment for a 2030 climate and energy policy framework Contents Overview a. Drivers of electricity prices b. Jobs and growth c. Trade d. Energy dependence A. Impact assessment

More information

THE PRODUCTION OF ELECTRICITY FROM WOOD AND OTHER SOLID BIOMASS

THE PRODUCTION OF ELECTRICITY FROM WOOD AND OTHER SOLID BIOMASS THE PRODUCTION OF ELECTRICITY FROM WOOD AND OTHER SOLID BIOMASS RTP TM /ADVANCED CYCLE VS. COMBUSTION STEAM CYCLES OR WHY NOT SIMPLY COMBUST? For decades, the only commercial option available for the production

More information

Danish Energy Model RE Policy Tools MAIN Asian Dialog, Bali January 20-22 2014. Mr. Henrik Breum Special Advisor

Danish Energy Model RE Policy Tools MAIN Asian Dialog, Bali January 20-22 2014. Mr. Henrik Breum Special Advisor Danish Energy Model RE Policy Tools MAIN Asian Dialog, Bali January 20-22 2014 Mr. Henrik Breum Special Advisor Agenda Danish Energy Model RE Policy Tools Introduction The Danish Energy Model Past, now

More information

Asian Journal on Energy and Environment

Asian Journal on Energy and Environment As. J. Energy Env. 2005, 6(02), 139-144 Asian Journal on Energy and Environment ISSN 1513-4121 Available online at www.asian-energy-journal.info The Small Hydropower Project as the Important Renewable

More information

Projected Costs of Generating Electricity

Projected Costs of Generating Electricity Executive Summary Projected Costs of Generating Electricity 2015 Edition Projected Costs of Generating Electricity 2015 Edition INTERNATIONAL ENERGY AGENCY NUCLEAR ENERGY AGENCY ORGANISATION FOR ECONOMIC

More information

Port Jackson Partners

Port Jackson Partners Port Jackson Partners NOT JUST A CARBON HIT ON ELECTRICITY PRICES Many factors will drive a doubling of electricity prices in many states by 15. This will have a major impact on virtually all businesses.

More information

South Hook Gas Company Ltd is a London-based liquefied natural gas (LNG) import company, which owns and manages the regasification

South Hook Gas Company Ltd is a London-based liquefied natural gas (LNG) import company, which owns and manages the regasification Energy for growth South Hook Gas Company Ltd is a London-based liquefied natural gas (LNG) import company, which owns and manages the regasification capacity and the gas supply from the South Hook LNG

More information

Adding fuel to the fire North America s hydrocarbon boom is changing everything. Steven Meersman. Roland Rechtsteiner

Adding fuel to the fire North America s hydrocarbon boom is changing everything. Steven Meersman. Roland Rechtsteiner Adding fuel to the fire North America s hydrocarbon boom is changing everything Steven Meersman Mark Pellerin Roland Rechtsteiner What if the gasoline that you put in your car came from natural gas instead

More information

CHILE LEVELISED COST OF ENERGY

CHILE LEVELISED COST OF ENERGY CHILE LEVELISED COST OF ENERGY PRESENTED TO NRDC TYLER TRINGAS, ENERGY ECONOMICS APRIL 2011 Chile Levelised Cost of Energy, April 2011 1 CONTENTS Introduction Objectives Levelised Cost of Energy Model

More information

ACCELERATING GREEN ENERGY TOWARDS 2020. The Danish Energy Agreement of March 2012

ACCELERATING GREEN ENERGY TOWARDS 2020. The Danish Energy Agreement of March 2012 ACCELERATING GREEN ENERGY TOWARDS The Danish Energy Agreement of March 2012 The most ambitious energy plan of the world In March 2012 a historic new Energy Agreement was reached in Denmark. The Agreement

More information

THE NET BENEFITS OF LOW AND NO-CARBON ELECTRICITY TECHNOLOGIES

THE NET BENEFITS OF LOW AND NO-CARBON ELECTRICITY TECHNOLOGIES GLOBAL ECONOMY & DEVELOPMENT WORKING PAPER 73 MAY 2014 Global Economy and Development at BROOKINGS THE NET BENEFITS OF LOW AND NO-CARBON ELECTRICITY TECHNOLOGIES Charles R. Frank, Jr. Global Economy and

More information

UNECE Energy Week Geneva. in Energy Security

UNECE Energy Week Geneva. in Energy Security UNECE Energy Week Geneva Investing in Energy Security Committee on Sustainable Energy and related Meetings Wednesday 28 November 2007 Special Session: Investing in and Financing the Hydrocarbon Sector

More information

Good afternoon, and thanks to the Energy Dialogue for your kind invitation to speak today.

Good afternoon, and thanks to the Energy Dialogue for your kind invitation to speak today. Good afternoon, and thanks to the Energy Dialogue for your kind invitation to speak today. Europe is at the forefront of a global transition to a cleaner energy economy. At the same time globally energy

More information

Geneva, 17-19 March 2009 COUNTRY REPORT: MALAWI

Geneva, 17-19 March 2009 COUNTRY REPORT: MALAWI CONFÉRENCE DES NATIONS UNIES SUR LE COMMERCE ET LE DÉVELOPPEMENT UNITED NATIONS CONFERENCE ON TRADE AND DEVELOPMENT Multi-Year Expert Meeting on Services, Development and Trade: The Regulatory and Institutional

More information

Fuel cell microchp: Greener and cheaper energy for all

Fuel cell microchp: Greener and cheaper energy for all Fuel cell microchp: Greener and cheaper energy for all Paddy Thompson General Manager Business Development Ceramic Fuel Cells Ltd. May 2013 1 What does our generation mix look like today? 2 Will the lights

More information

Energy Options in a Carbon Constrained World. Martin Sevior, School of Physics, University of Melbourne http://nuclearinfo.net

Energy Options in a Carbon Constrained World. Martin Sevior, School of Physics, University of Melbourne http://nuclearinfo.net Energy Options in a Carbon Constrained World. Martin Sevior, School of Physics, University of Melbourne Energy underpins our Civilization Imagine one week without Electricity Imagine one week without Motorized

More information

WORLD ENERGY INVESTMENT OUTLOOK 2014 FACTSHEET OVERVIEW

WORLD ENERGY INVESTMENT OUTLOOK 2014 FACTSHEET OVERVIEW OVERVIEW More than $1.6 trillion was invested in 2013 in energy supply, a figure that has more than doubled in real terms since 2000, and a further $130 billion to improve energy efficiency. Renewables

More information

Wind Power and District Heating

Wind Power and District Heating 1 Wind Power and District Heating New business opportunity for CHP systems: sale of balancing services Executive summary - Both wind power and Combined Heat and Power (CHP) can reduce the consumption of

More information

FIXED CHARGE: This is a cost that goes towards making the service available, including

FIXED CHARGE: This is a cost that goes towards making the service available, including ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer

More information

Making Coal Use Compatible with Measures to Counter Global Warming

Making Coal Use Compatible with Measures to Counter Global Warming Making Use Compatible with Measures to Counter Global Warming The J-POWER Group is one of the biggest coal users in Japan, consuming approximately 2 million tons of coal per year at eight coal-fired power

More information

Emissions Comparison for a 20 MW Flywheel-based Frequency Regulation Power Plant

Emissions Comparison for a 20 MW Flywheel-based Frequency Regulation Power Plant Emissions Comparison for a 20 MW Flywheel-based Frequency Regulation Power Plant Beacon Power Corporation KEMA Project: BPCC.0003.001 May 18, 2007 Final Report with Updated Data Emissions Comparison for

More information

Perspectives on CRMs from an Academic Point of View

Perspectives on CRMs from an Academic Point of View Perspectives on CRMs from an Academic Point of View Prof. Dr. Jan Horst Keppler Professor of economics, Université Paris-Dauphine Scientific Director, Chaire European Electricity Markets (CEEM) Conference

More information

Netherlands National Energy Outlook 2014

Netherlands National Energy Outlook 2014 Netherlands National Energy Outlook 2014 Summary Michiel Hekkenberg (ECN) Martijn Verdonk (PBL) (project coordinators) February 2015 ECN-E --15-005 Netherlands National Energy Outlook 2014 Summary 2 The

More information

Techno-Economics of Distributed Generation and Storage of Solar Hydrogen

Techno-Economics of Distributed Generation and Storage of Solar Hydrogen Techno-Economics of Distributed Generation and Storage of Solar Hydrogen Philipp Grünewald, Tim Cockerill, Marcello Contestabile, Imperial College London, UK Abstract For hydrogen to become a truly sustainable

More information

ASEAN POWER GRID : ROAD TO MULTILATERAL POWER TRADING. Presented By: Bambang Hermawanto Chairman, ASEAN Power Grid Consultative Committee (APGCC)

ASEAN POWER GRID : ROAD TO MULTILATERAL POWER TRADING. Presented By: Bambang Hermawanto Chairman, ASEAN Power Grid Consultative Committee (APGCC) ASEAN POWER GRID : ROAD TO MULTILATERAL POWER TRADING Presented By: Bambang Hermawanto Chairman, ASEAN Power Grid Consultative Committee (APGCC) ERC Forum 2015, Bangkok 01 October 2015 Overview of ASEAN

More information

INDONESIA S COUNTRY REPORT ENCOURAGING CLEAN ENERGY INITIATIVE

INDONESIA S COUNTRY REPORT ENCOURAGING CLEAN ENERGY INITIATIVE DEWAN PERWAKILAN RAKYAT REPUBLIK INDONESIA INDONESIA S COUNTRY REPORT ENCOURAGING CLEAN ENERGY INITIATIVE As part of the international community, Indonesia shares its concern on the environment and development

More information

Unlocking Electricity Prices:

Unlocking Electricity Prices: Volume 2 A BidURenergy White Paper Unlocking Electricity Prices: A White Paper Exploring Price Determinants by: Mark Bookhagen, CEP pg. 2 Written by Mark Bookhagen, CEP Introduction In order to be classified

More information

GENERATION TECHNOLOGY ASSESSMENT

GENERATION TECHNOLOGY ASSESSMENT SPO PLANNING ANALYSIS GENERATION TECHNOLOGY ASSESSMENT Technology Cost & Performance Milestone 2 Public Technical Conference OCTOBER 30, 2014 NOTE: ALL IRP MATERIALS ARE PRELIMINARY & SUBJECT TO CHANGE

More information

Energy Projections 2006 2030 Price and Policy Considerations. Dr. Randy Hudson Oak Ridge National Laboratory

Energy Projections 2006 2030 Price and Policy Considerations. Dr. Randy Hudson Oak Ridge National Laboratory Energy Projections 2006 2030 Price and Policy Considerations Dr. Randy Hudson Oak Ridge National Laboratory There is perhaps no single current topic so potentially impacting to all life on this planet

More information

A Discussion of PEM Fuel Cell Systems and Distributed Generation

A Discussion of PEM Fuel Cell Systems and Distributed Generation A Discussion of PEM Fuel Cell Systems and Distributed Generation Jeffrey D. Glandt, M. Eng. Principal Engineer, Solutions Engineering May 2011 The information contained in this document is derived from

More information

COMPARISON OF ELECTRICITY GENERATION COST OF NPP WITH ALTERNATES IN PAKISTAN

COMPARISON OF ELECTRICITY GENERATION COST OF NPP WITH ALTERNATES IN PAKISTAN COMPARISON OF ELECTRICITY GENERATION COST OF NPP WITH ALTERNATES IN PAKISTAN IAEA INPRO dialogue forum 8 toward nuclear energy system sustainability: economics, resource availability and institutional

More information

Electricity Supply. Monthly Energy Output by Fuel Type (MWh)

Electricity Supply. Monthly Energy Output by Fuel Type (MWh) Ontario Energy Report Q4 Electricity October December Electricity Supply Electricity production was lower in Q4 than in previous years, with milder than normal weather in October and December resulting

More information

COMPETITIVENESS COMPARISON OF THE ELECTRICITY PRODUCTION ALTERNATIVES (PRICE LEVEL MARCH 2003)

COMPETITIVENESS COMPARISON OF THE ELECTRICITY PRODUCTION ALTERNATIVES (PRICE LEVEL MARCH 2003) LAPPEENRANTA UNIVERSITY OF TEHCNOLOGY RESEARCH REPORT EN B-156 COMPETITIVENESS COMPARISON OF THE ELECTRICITY PRODUCTION ALTERNATIVES (PRICE LEVEL MARCH 2003) Risto Tarjanne, Kari Luostarinen ISBN 951-764-895-2

More information

Developing Power Projects in Southern Africa. Cape Town Presentation 8 th February 2016

Developing Power Projects in Southern Africa. Cape Town Presentation 8 th February 2016 Developing Power Projects in Southern Africa Cape Town Presentation 8 th February 2016 Company Highlights AFR now participating in the development of three large-scale power projects in Botswana Completion

More information

Ministry of Power & Energy

Ministry of Power & Energy Ministry of Power & Energy Institutional Frame work Power sector overview Renewable energy policy Major issues and barriers Institutional Framework Sustainable Energy Authority The Sri Lanka Sustainable

More information

CSP. Feranova Reflect Technology. klimaneutral natureoffice.com DE-296-558771 gedruckt

CSP. Feranova Reflect Technology. klimaneutral natureoffice.com DE-296-558771 gedruckt RENEWABLE SOURCES RENEWABLE SOURCES CSP Feranova Reflect Technology klimaneutral natureoffice.com DE-296-558771 gedruckt Gedruckt auf 100% Recyclingpapier Circlesilk Premium White 200/150 g/m 2 2012 Feranova

More information

GB Electricity Market Summary

GB Electricity Market Summary GB Electricity Market Summary SECOND QUARTER 2014 APR TO JUN Recorded Levels of UK Generation by Fuel (based upon DECC Energy Trends & FUELHH data): GAS: 10.8GW WIND: 2.6GW AUGUST 2014 COAL: 10.1GW BIOMASS:

More information

Busting Myths about Renewable Energy

Busting Myths about Renewable Energy Symposium on Renewable Energy: the Future for Australia, UNSW 15 April 2014 Busting Myths about Renewable Energy Dr Mark Diesendorf Institute of Environmental Studies University of New South Wales Sydney,

More information

The Outlook for Nuclear Energy In a Competitive Electricity Business

The Outlook for Nuclear Energy In a Competitive Electricity Business 1776 I STREET N.W. SUITE 400 WASHINGTON, D.C. 20006 202.739.8000 The Outlook for Nuclear Energy In a Competitive Electricity Business Executive Summary: Nuclear Units Competitive, Profitable in Deregulated

More information

Draft Electric Resource Plan 2009 2018 Technical Workshop. Technology Screening Analysis

Draft Electric Resource Plan 2009 2018 Technical Workshop. Technology Screening Analysis Draft Electric Resource Plan 2009 2018 Technical Workshop Technology Screening Analysis June 15, 2009 www.lipower.org Resource Planning Process Overview Process Methodology Screening Analysis Determine

More information

The economic competitiveness of nuclear energy

The economic competitiveness of nuclear energy How competitive is nuclear energy? by J.H. Keppler* The economic competitiveness of nuclear energy will be crucial for determining its future share in world electricity production. In addition, the widespread

More information

Russia: energy market developments. Marc-Antoine Eyl-Mazzega Russia Programme Manager Paris, 16 December 2014

Russia: energy market developments. Marc-Antoine Eyl-Mazzega Russia Programme Manager Paris, 16 December 2014 Russia: energy market developments Marc-Antoine Eyl-Mazzega Russia Programme Manager Paris, 16 December 2014 IEA: 29 Members, worldwide engagement IEA member countries Accession countries Key Partner countries

More information

From today s systems to the future renewable energy systems. Iva Ridjan US-DK summer school AAU Copenhagen 17 August 2015

From today s systems to the future renewable energy systems. Iva Ridjan US-DK summer school AAU Copenhagen 17 August 2015 From today s systems to the future renewable energy systems Iva Ridjan US-DK summer school AAU Copenhagen 17 August 2015 STRUCTURE OF ENERGY SYSTEMS 8/17/2015 Copenhagen, Denmark 2 Components Demand Heat

More information

LAZARD'S LEVELIZED COST OF ENERGY ANALYSIS VERSION 8.0 SEPTEMBER 2014

LAZARD'S LEVELIZED COST OF ENERGY ANALYSIS VERSION 8.0 SEPTEMBER 2014 SEPTEMBER 2014 Introduction Lazard s Levelized Cost of Energy Analysis ( LCOE ) addresses the following topics: Comparative levelized cost of energy for various technologies on a $/MWh basis, including

More information

H1 2014 LEVELISED COST OF ELECTRICITY - PV

H1 2014 LEVELISED COST OF ELECTRICITY - PV H1 2014 LEVELISED COST OF ELECTRICITY - PV JENNY CHASE 4 FEBRUARY 2014 LCOE OF PV, FEBRUARY 2014 1 PV EXPERIENCE CURVE, 1976-2013 (2013 $/W) 100 Cost per W (2013 $) 1976 10 1985 2003 2006 1 2012 2013 Q3

More information

Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply. www.siemens.com/siestorage

Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply. www.siemens.com/siestorage Totally Integrated Power SIESTORAGE The modular energy storage system for a reliable power supply www.siemens.com/siestorage Totally Integrated Power (TIP) We bring power to the point. Our products, systems,

More information

Options to Bring Down the Cost of Electricity in Jamaica

Options to Bring Down the Cost of Electricity in Jamaica Options to Bring Down the Cost of Electricity in Jamaica Final Report 23 June 2011 Options to Bring Down the Cost of Electricity in Jamaica Final Report 23 June 2011 Copyright Castalia Limited. All rights

More information