1 UCD IT Services It0x Enhanced data storage services Sharepoint Teamsites Project Initiation Document Version 1.0 2, December 2014 Version History Version Date Summary of Changes Changed by 1 2/12/2014 Brian Morrissey IT Services Website Redevelopment Project Initiation Document Page 1 of 11

2 Contents 1 Objectives & Scope Background to the Project Project Objectives Expected Benefits Project Scope Change Control 3 2 Project Plan Project Approach Milestones & Deliverables Project Plan 5 3 Project Structure Roles & Responsibilities Project Team Meetings 7 4 Risks & Issues Initial Risk & Issue Log Ongoing Management of Risks and Issues 8 5 Communication Plan 9 6 Project Costs Initial Project Budget Ongoing Costs 10 IT Services Website Redevelopment Project Initiation Document Page 2 of 11

3 1 Objectives & Scope This Project Initiation Document (PID) defines the Sharepoint Teamsites project in detail including objectives, scope, approach, deliverables, timescale and structure of the project so that it can be understood and agreed by all stakeholders. 1.1 Background to the Project We are examining the use of Sharepoint Teamsites in providing a solution to some document management requirements of a model office. It is anticipated that this the type of service could provide value to UCD customers. 1.2 Project Objectives To assess the suitability of Sharepoint Teamsites in providing a framework for document storage and sharing for administrative offices at UCD. 1.3 Expected Benefits A suitable framework/template would provide offices with a mechamism for storing and sharing documents based on Office Project Scope The project will involve working with a pilot group in IT Services to develop a Teamsite environment that meets their document storage needs. The intention would be to develop a solution which could then be reused elsewhere with little or no redevelopment. IT Services staff will also participate in training in the solution so that they can handle issues which may arise. 1.5 Change Control The Project Initiation Document will be approved on commencement of the project by the relevant project members. Following this, an ongoing Project Plan will be maintained and updated to accommodate any minor changes occur. Once the scope is agreed herein, any further changes to scope or major deviation from the proposed timeframes will be the subject of the change control. IT Services Website Redevelopment Project Initiation Document Page 3 of 11

4 2 Project Plan 2.1 Project Approach We will work with an implementation partner and IT Services Admin group to develop a solution to meets their needs. We will ensure that the approach is reusable by other departments who could benefit from this template-style approach. 2.2 Milestones & Deliverables The following milestones, deliverables and target delivery dates have been defined for the project: Milestone Deliverable Responsib ility 0 Project Initiation completed Project Initiation Document completed. BM Reviewers/ Approvers Due Date 1 Requirements completed 2 Partner selection 3 Initial design & Training Statement of Requirements. Initial design & IT Services staff training. WS & IT Admin IT Admin & WS 20/01 WS Web Services 20/02 WS WS & IT Admin 20/03 4 Design review Customer acceptance testing IT Admin IT Admin 10/04 5 Revised design Revised design and customer sign-off. 6 Production use Review how service is meeting needs and prepare demo for other potential customers. IT Admin WS & IT Admin 20/04 All WS & IT Admin 20/05 The individual(s) listed in the Responsibility column above are responsible for the relevant deliverables. Typically each deliverable will have one or many reviewers and a final approval by one or more individuals. Acceptance and sign-off of a deliverable is required by the Approval person. IT Services Website Redevelopment Project Initiation Document Page 4 of 11

5 2.3 Project Plan The milestone listing below is essentially the plan. Milestone Deliverable Responsib ility 0 Project Initiation completed Project Initiation Document completed. BM Reviewers/ Approvers Due Date 1 Requirements completed 2 Partner selection 3 Initial design & Training Statement of Requirements. Initial design & IT Services staff training. WS & IT Admin IT Admin & WS 20/01 WS Web Services 20/02 WS WS & IT Admin 20/03 4 Design review Customer acceptance testing IT Admin IT Admin 10/04 5 Revised design Revised design and customer sign-off. 6 Production use Review how service is meeting needs and prepare demo for other potential customers. IT Admin WS & IT Admin 20/04 All WS & IT Admin 20/05 IT Services Website Redevelopment Project Initiation Document Page 5 of 11

6 3 Project Structure The project comprises a Project Team and a Steering Group. The Steering Group will agree project schedules, approve major deliverables and resolve any critical issues that arise during the lifetime of the project. The Project Team will manage the project on a daily basis and will report regularly to the Steering Group. 3.1 Roles & Responsibilities Define the responsibilities for each group and role within the project. The following are some sample responsibilities for common project groups and roles. Role Responsibilities Names Steering Group Ensure that the project direction is appropriate to the achievement of the ultimate objectives. Review progress reports from the Project Manager and determine actions needed to address deviations. Provide guidance to the Project Team on high level principles to be complied with. Review and approve deliverables. Monitor and proactively manage risks as they arise. Brian Morrissey Kate Griffin Project Sponsor Ensure that resources are provided as required for the project IT Admin Take action on any issues escalated by the Project Team Project Manager Prepare the Project Plans Determine resource requirements and ensure that appropriate resources are allocated Peter McKiernan Manage the project to ensure that the desired results are achieved within agreed time-scales Monitor progress and report on a regular basis to the Steering Committee Prepare project deliverables and their presentation for approval IT Services Website Redevelopment Project Initiation Document Page 6 of 11

7 Role Responsibilities Names Project Team Conduct the tasks and activities of the project in accordance with the Project Plan Prepare the project deliverables by the agreed due dates Report progress to the Project Manager Web Services, IT Admin, IT Communications. 3.2 Project Team Meetings The following are the scheduled project governance meetings: Team Attendees Frequency Steering Group Project Team Brian Morrissey & Kate Griffin. WS & IT Admin staff. IT Communications. Monthly. Every 2 weeks IT Services Website Redevelopment Project Initiation Document Page 7 of 11

8 4 Risks & Issues 4.1 Initial Risk & Issue Log The following project risks or issues have been identified on commencement of the project. These initial tasks to address these risks or issues are outlined. Risk / Issue Solution deemed unsuitable Sharepoint service unreachable Solution does not perform well (slow or cumbersome) Probability H M L Impact H M L Actions to Mitigate Y Y Ensure continuous stakeholder engagement Y Y Cloud-based services can occasionally be unavailable. Y Y I expect that these type of issues would be uncovered before the production phase. Respon sibility 4.2 Ongoing Management of Risks and Issues Any additional risks and issues identified will be maintained on an ongoing basis by the Project Manager in separate Risks and Issues logs. IT Services Website Redevelopment Project Initiation Document Page 8 of 11

9 5 Communication Plan Close communications between all participants is expected throughout the project. When the solution reaches the production stage, we will embark on a servies of customer-focused communications based around the experience of the IT Admin group in using the service. Stakeholder Actions Responsibility IT Services Website Redevelopment Project Initiation Document Page 9 of 11

10 6 Project Costs 6.1 Initial Project Budget Cost of engaging a partner to develop the service is estimated at 10, Ongoing Costs It is not anticipated that there would be on-going costs. There may well be amandments to the standard template to suit other departments but they will be expected to meet that cost. IT Services Website Redevelopment Project Initiation Document Page 10 of 11

11 Related Documentation It is often useful to list any related documentation here, such as supporting documentation provided by the business/customer. IT Services Website Redevelopment Project Initiation Document Page 11 of 11

IT Services Website Redevelopment

IT Services Website Redevelopment UCD IT Services IT01 IT Services Website Redevelopment Project Initiation Document Version 1.0 1, December 2014 Version History Version Date Summary of Changes Changed by 1 1/12/2014 Brian Morrissey IT

More information

UCD IT Services. Research Data. Project Initiation Document. Version 1.0 03 rd December 2014. Version History

UCD IT Services. Research Data. Project Initiation Document. Version 1.0 03 rd December 2014. Version History UCD IT Services Research Data Project Initiation Document Version 1.0 03 rd December 2014 Version History Version Date Summary of Changes Changed by 1.0 03/12/2014 Initial Document 1.1 09/12/2014 Minor

More information

IT1T Integrated Recruitment Systems 2015

IT1T Integrated Recruitment Systems 2015 UCD IT Services IT1T Integrated Recruitment Systems 2015 Project Initiation Document Version 1.0 2 December 2014 Version History Version Date Summary of Changes Changed by 1.0 02/12/2014 Initial Draft

More information

UCD International UCD IT Services. IT12 - Device Security & Encryption Strategy. Project Initiation Document. Version 1.0 2 nd December 2014

UCD International UCD IT Services. IT12 - Device Security & Encryption Strategy. Project Initiation Document. Version 1.0 2 nd December 2014 UCD International UCD IT Services IT12 - Device Security & Encryption Strategy Project Initiation Document Version 1.0 2 nd December 2014 Version History Version Date Summary of Changes Changed by 1.0

More information

OE PROJECT CHARTER TEMPLATE

OE PROJECT CHARTER TEMPLATE PROJECT : PREPARED BY: DATE (MM/DD/YYYY): Project Name Typically the Project Manager Project Charter Last Modified Date PROJECT CHARTER VERSION HISTORY VERSION DATE (MM/DD/YYYY) COMMENTS (DRAFT, SIGNED,

More information

SCHEDULE 8 Generalist Project Services Framework 2015

SCHEDULE 8 Generalist Project Services Framework 2015 SCHEDULE 8 Generalist Project Services Framework 2015 Nominal Insurer And Schedule 8 (Project Services Framework) Page: 1 of 6 Schedule 8 Generalist Project Services Framework Contents Overview... 3 1.

More information

LGS Project Management Methodology

LGS Project Management Methodology Page: 32 LGS Project Management Methodoy The LGS project management methodoy is integral to our overall delivery methodoy. Based on inpro, one of the LGS inspiration series documents, our methodoy is compliant

More information

IBAPro Project Management Methodology

IBAPro Project Management Methodology IBAPro Project Management Methodology A description of the IBApps Project Management Methodology and Implementation Process Version 2.2, June 2013 Contents 1. Project Management... 3 2. Phases... 3 2.1.

More information

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History

More information

How To Write A Project Management Plan

How To Write A Project Management Plan Enter Project Name Project Management Plan (PMP) Kickoff Month, Day, Year 1 Purpose The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents

More information

TRANSITION PLAN TEMPLATE

TRANSITION PLAN TEMPLATE TRANSITION PLAN TEMPLATE In this template, instructions are included in italics. When you have completed the template and no longer need the instructions, delete them. Provide a brief overview of the transition

More information

LMI Aerospace PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012

LMI Aerospace PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012 PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012 TABLE OF CONTENTS INTRODUCTION... 2 PROJECT MANAGEMENT APPROACH... 2 PROJECT SCOPE... 2 MILESTONE LIST... 2 SCHEDULE BASELINE

More information

SCHEDULE 10. Contract Management and Reporting. the Management Information and reporting requirements,

SCHEDULE 10. Contract Management and Reporting. the Management Information and reporting requirements, SCHEDULE 10 Contract Management and Reporting 1. Scope 1.1 This schedule sets out: contract management procedures; and the Management Information and reporting requirements, with which the Service Provider

More information

Contract and Vendor Management Guide

Contract and Vendor Management Guide Contents 1. Guidelines for managing contracts and vendors... 2 1.1. Purpose and scope... 2 1.2. Introduction... 2 2. Contract and Vendor Management 2.1. Levels of management/segmentation... 3 2.2. Supplier

More information

Subject Area 1 Project Initiation and Management

Subject Area 1 Project Initiation and Management DRII/BCI Professional Practice Narrative: Establish the need for a Business Continuity Plan (BCP), including obtaining management support and organizing and managing the BCP project to completion. (This

More information

COMMUNICATIONS MANAGEMENT PLAN <PROJECT NAME>

COMMUNICATIONS MANAGEMENT PLAN <PROJECT NAME> COMMUNICATIONS MANAGEMENT PLAN TEMPLATE This Project Communications Management Template is free for you to copy and use on your project and within your organization. We hope that you find this template

More information

Project Scorecard Template

Project Scorecard Template Project Scorecard Template 1. Identify criteria for success: Review the objectives and deliverables in the Project Definition, as well as any other existing information that is relevant to the project.

More information

Project Start Up. Start-Up Check List. Why a Project Check List? What is a Project Check List? Initial Release 1.0 Date: January 1997

Project Start Up. Start-Up Check List. Why a Project Check List? What is a Project Check List? Initial Release 1.0 Date: January 1997 Why a Project Check List? A good way to ensure that all start-up tasks are completed prior to actually starting the project is to develop a start-up check list. The check list can be developed and then

More information

Risk/Issue Management Plan

Risk/Issue Management Plan Risk/Issue Management Plan Centralized Revenue Opportunity System November 2014 Version 2.0 This page intentionally left blank Table of Contents 1. Overview... 3 1.1 Purpose... 3 1.2 Scope... 3 2. Roles

More information

Project Roles and Responsibilities

Project Roles and Responsibilities Project s and This template can be used to define roles and responsibilities Below is a few typical examples of the different types of roles involved in delivering a project and their respective responsibilities.

More information

<name of project> Software Project Management Plan

<name of project> Software Project Management Plan The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor

More information

Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview

Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview 1/1 Table of Contents 1. Introduction...3 2. Executive Summary...4 3. Program Definition...5 3.1. Program

More information

Ellucian Implementation Methodology. Summary of Project Management and Solution Delivery Phases

Ellucian Implementation Methodology. Summary of Project Management and Solution Delivery Phases Ellucian Implementation Methodology Summary of Project Management and Solution Delivery Phases Rev. 5/10/2013 Table of Contents Overview 3 Project Management Initiation 4 Planning 5 Execution 6 Monitor

More information

Organization. Project Name. Project Overview Plan Version # Date

Organization. Project Name. Project Overview Plan Version # Date Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents

More information

Project Management: Trainee Guide Module 5 POST IMPLEMENTATION

Project Management: Trainee Guide Module 5 POST IMPLEMENTATION 200 Project Management: Trainee Guide Module 5 POST IMPLEMENTATION Bridges Social Development Project Management Training Program http://training.canadabridges.com 09/09/2009 PROJECT MANAGEMENT TRAINING

More information

KMS Implementation Roadmap

KMS Implementation Roadmap KMS Implementation Roadmap Sample Excerpt Prepared by: The Knowledge Compass, Inc. TABLE OF CONTENTS 1. EXECUTIVE SUMMARY 5 1.1 Overview 5 1.2 Project Goals & Objectives 5 1.3 Implementation Approach 5

More information

COMMUNICATION MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:

COMMUNICATION MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: COMMUNICATION MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Document Information Document Title Amendment History Document Version Date Author/Reviewer Modifications 5/28/2014 Page i 2014 CSG

More information

Programme Governance and Management Plan Version 2

Programme Governance and Management Plan Version 2 PROCESS FOR CHANGE - Detailed Design Programme Governance and Management Plan Version 2 1 INTRODUCTION In October 2008, the Council approved the selection of seven opportunity themes to take forward from

More information

Project Management Plan Outline ITSC

Project Management Plan Outline ITSC Project Management Plan Outline ITSC Date: 02/28/2012 Introduction At start of each project vendors must create a project management plan for ITSC approval, including, at a minimum, the sections described

More information

Creating A Risk Management Plan

Creating A Risk Management Plan Creating A Risk Management Plan A presentation based on the concepts taught in the Risk Management 1A course. Carlos Consulting Group Roseville, CA. (916) 521-2520 www.carlosconsulting.com 1 Objectives

More information

PROJECT PLAN FOR. Project Name Here

PROJECT PLAN FOR. Project Name Here PROJECT PLAN FOR Project Name Here Version # DatE Reviewed and Approved for submittal to Executive Sponsor , Project Manager Project Plan Approved for submittal to Executive Sponsor: , Project

More information

Project Team Roles Adapted for PAAMCO

Project Team Roles Adapted for PAAMCO Project Team Roles Adapted for PAAMCO Project Roles, Authority & Responsibilities Role a defined funciton assumed by or assigned to a person in the project Authority the right to apply project resources,

More information

1. Background and business case

1. Background and business case 1. Background and business case This section explains the context and why the project is being undertaken. It provides the justification for investing the time and resources in the project. 1.1 Reasons

More information

ITIL Implementation Planning

ITIL Implementation Planning White Paper ITIL Implementation Planning Overview Introduction This paper describes the items that need to be considered in advance of starting an ITIL implementation effort. It is critical to make sure

More information

APPLYING PROJECT MANAGEMENT TECHNIQUES TO QEHS

APPLYING PROJECT MANAGEMENT TECHNIQUES TO QEHS APPLYING PROJECT MANAGEMENT TECHNIQUES TO QEHS Mary F. McDonald, CQA President/Principal Consultant Individual Solution Options/Quality Services (ISO/QS), Inc. Austin, TX 78739 Tel: (512) 282-0181 E-mail:

More information

Project Management Guidelines

Project Management Guidelines Project Management Guidelines Overview Section 86-1506 (5) directs the NITC to adopt guidelines regarding project planning and management. The goal of project management is to achieve the objectives of

More information

Project Governance A N T I C I P A T I N G A N A U D I T

Project Governance A N T I C I P A T I N G A N A U D I T Project Governance A N T I C I P A T I N G A N A U D I T Public sector Project Management characteristics Multi-million rand projects Often National interest projects Subject to intense scrutiny Uncertainty

More information

ESKISP6056.01 Direct security testing

ESKISP6056.01 Direct security testing Direct security testing Overview This standard covers the competencies concerning with directing security testing activities. It includes setting the strategy and policies for security testing, and being

More information

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce Maturity Model March 2006 Version 1.0 P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value Added product which is outside the scope of the HMSO

More information

OE PROJECT CHARTER TEMPLATE

OE PROJECT CHARTER TEMPLATE PROJECT : BearBuy Implementation PREPARED BY: Vanessa Wong and Jon Conhaim DATE (MM/DD/YYYY): 07/23/2011 PROJECT CHARTER VERSION HISTORY VERSION DATE COMMENTS (DRAFT, SIGNED, REVISED CURRENT STATUS) (MM/DD/YYYY)

More information

Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee

Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Page 1 2 Contents 1. Introduction... 3 1.1 Definition of a... 3 1.2 Why have

More information

ICT Service Desk Creation

ICT Service Desk Creation ICT Service Desk Creation Project Initiation Document Document: ICT Service desk Creation: PID Issue Date: 26 th November 2010 Version: 0.1 Draft Version Number: 1.0 Change Control Quality Assurance Document:

More information

Operations. Group Standard. Business Operations process forms the core of all our business activities

Operations. Group Standard. Business Operations process forms the core of all our business activities Standard Operations Business Operations process forms the core of all our business activities SMS-GS-O1 Operations December 2014 v1.1 Serco Public Document Details Document Details erence SMS GS-O1: Operations

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

CONFIGURATION COMMITTEE. Terms of Reference

CONFIGURATION COMMITTEE. Terms of Reference SWBTB (8/13) 166 (g) CONFIGURATION COMMITTEE Terms of Reference 1. CONSTITUTION 1.1 The Board hereby resolves to establish a Committee of the Board to be known as the Configuration Committee (The Committee).

More information

Position Description. Enterprise Agreement: Budget Responsibility: Nil

Position Description. Enterprise Agreement: Budget Responsibility: Nil Position Description Position Details Position Scope Title: Division: Project Manager Finance & Corporate Services Enterprise Agreement: Budget Responsibility: Department: Payroll Authority Level: Ambulance

More information

Project Charter and Scope Statement

Project Charter and Scope Statement Prepared by: Mike Schmidt Version: 1.0 Last Revision Date: April 14, 2010 Create Date: May 6, 2010 EXECUTIVE SUMMARY... 3 1 INTRODUCTION... 4 2 PROJECT OBJECTIVES... 4 2.1 MISSION... 4 2.2 OBJECTIVES...

More information

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution

More information

Disaster Recovery Policy

Disaster Recovery Policy Disaster Recovery Policy INTRODUCTION This policy provides a framework for the ongoing process of planning, developing and implementing disaster recovery management for IT Services at UCD. A disaster is

More information

Project Implementation Process (PIP)

Project Implementation Process (PIP) Vanderbilt University Medical Center Project Implementation Process (PIP).......... Project Implementation Process OVERVIEW...4 PROJECT PLANNING PHASE...5 PHASE PURPOSE... 5 TASK: TRANSITION FROM PEP TO

More information

Minnesota Health Insurance Exchange (MNHIX)

Minnesota Health Insurance Exchange (MNHIX) Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration

More information

Streamlining the First Year: Block Scheduling

Streamlining the First Year: Block Scheduling Streamlining the First Year: Block Scheduling Project Sponsor: Emanuel Pollack, Interim Vice Provost for Undergraduate Affairs Project team lead Mike Kamowski, Director, Office of Student Systems Services

More information

Release Management: Effective practices for IT delivery

Release Management: Effective practices for IT delivery Release Management: Effective practices for IT delivery Introduction Today s health plans face a unique combination of technology challenges due to their complex IT environments. These environments serve

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

NSW Government ICT Benefits Realisation and Project Management Guidance

NSW Government ICT Benefits Realisation and Project Management Guidance NSW Government ICT Benefits Realisation and Project Management Guidance November 2014 CONTENTS 1. Introduction 1 2. Document purpose 1 3. Benefits realisation 1 4. Project management 4 5. Document control

More information

To provide a procedure and associated guidelines to facilitate the management of project dependencies.

To provide a procedure and associated guidelines to facilitate the management of project dependencies. Management DEPENDENCY MANAGEMENT Purpose To provide a procedure and associated guidelines to facilitate the management of project dependencies. Overview Dependencies in this Phase are defined as actions,

More information

PROJECT SCOPE STATEMENT

PROJECT SCOPE STATEMENT PROJECT SCOPE STATEMENT Note: Any work not explicitly included in the Project Scope Statement is implicitly excluded from the project. Project Name: Prepared by: BI - IT Governance Amy Winkel Date: 12/20/2010

More information

Appendix 3: CMT Programme Board Highlight Report - Template and Guidance notes

Appendix 3: CMT Programme Board Highlight Report - Template and Guidance notes Appendix 3: CMT Board Highlight Report - Template and Guidance notes What is it? This is an exception report that provides a quick means of assessing a programme s status. It allows CMT programme board

More information

Qlik UKI Consulting Services Catalogue

Qlik UKI Consulting Services Catalogue Qlik UKI Consulting Services Catalogue The key to a successful Qlik project lies in the right people, the right skills, and the right activities in the right order www.qlik.co.uk Table of Contents Introduction

More information

North European Functional Airspace Block Avinor, Norway EANS, Estonia Finavia, Finland LGS, Latvia. NEFAB Project CHANGE MANAGEMENT MANUAL

North European Functional Airspace Block Avinor, Norway EANS, Estonia Finavia, Finland LGS, Latvia. NEFAB Project CHANGE MANAGEMENT MANUAL NEFAB Project CHANGE MANAGEMENT MANUAL Version 0.5 Page 1 of 38 Revision history Version Date Description Approved 0.5 14/12/2011 Page 2 of 38 Table of Contents 1. Introduction... 4 1.1. The Scope of this

More information

Crosswalk Between Current and New PMP Task Classifications

Crosswalk Between Current and New PMP Task Classifications Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the

More information

PROCESS FOR CHANGE Programme Governance Plan

PROCESS FOR CHANGE Programme Governance Plan High Level Design Stage and Beyond Arrangements for Programme and Project Management Recognising the complexity of delivering all the elements of the programme in a tight timescale the following governance

More information

Waterloo CMS Project. Project Charter Information Systems and Technology (IST) University of Waterloo (UW) Waterloo, Ontario, Canada

Waterloo CMS Project. Project Charter Information Systems and Technology (IST) University of Waterloo (UW) Waterloo, Ontario, Canada Waterloo CMS Project Project Charter Information Systems and Technology (IST) University of Waterloo (UW) Waterloo, Ontario, Canada Charter Date: September 4, 2009 Revision Date: February 10, 2010 Maintained

More information

Template K Implementation Requirements Instructions for RFP Response RFP #

Template K Implementation Requirements Instructions for RFP Response RFP # Template K Implementation Requirements Instructions for RFP Response Table of Contents 1.0 Project Management Approach... 3 1.1 Program and Project Management... 3 1.2 Change Management Plan... 3 1.3 Relationship

More information

Project Management Guidebook

Project Management Guidebook METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple

More information

PROJECT CHARTER GUIDE

PROJECT CHARTER GUIDE Treasury Board of Canada Secretariat Secrétariat du Conseil du Trésor du Canada Enhanced Management Framework for Information Technology PROJECT CHARTER GUIDE February 1999 Chief Information Officer Branch

More information

Project Risk Analysis toolkit

Project Risk Analysis toolkit Risk Analysis toolkit MMU has a corporate Risk Management framework that describes the standard for risk management within the university. However projects are different from business as usual activities,

More information

Establish Collaborative Strategies to Better Manage a Global Vendor Network Devise a Proper Float Plan

Establish Collaborative Strategies to Better Manage a Global Vendor Network Devise a Proper Float Plan Establish Collaborative Strategies to Better Manage a Global Vendor Network Devise a Proper Float Plan CBI s Biopharmaceutical Forum on Clinical and Commercial Global Supply Chain Excellence Sandy Onorato

More information

Change Management Procedure For Increase Bandwidth to University Buildings Project

Change Management Procedure For Increase Bandwidth to University Buildings Project Change Management Procedure For Increase Bandwidth to University Buildings Project Version number 1.0 Draft as of 4/11/2011 Printed on 7/1/2011 Author William M. Jones Owner William M. Jones Change Management

More information

Project Lifecycle Management (PLM)

Project Lifecycle Management (PLM) Project Lifecycle Management (PLM) Process or Tool? Why PLM? Project Definition Project Management NEW REQUEST/ INITIATIVES SUPPORT (Quick fixes) PROJECT (Start Finish) ONGOING WORK (Continuous) ENHANCEMENTS

More information

OE PROJECT CHARTER Business Process Management System Implementation

OE PROJECT CHARTER Business Process Management System Implementation PROJECT NAME: PREPARED BY: DATE (MM/DD/YYYY): Andrea Lambert, Senior Business Process Consultant, OE Program Office 09/15/2014 PROJECT CHARTER VERSION HISTORY VERSION DATE COMMENTS (DRAFT, SIGNED, REVISED

More information

Retained Fire Fighters Union. Introduction to PRINCE2 Project Management

Retained Fire Fighters Union. Introduction to PRINCE2 Project Management Retained Fire Fighters Union Introduction to PRINCE2 Project Management PRINCE2 PRINCE stands for: PRojects IN Controlled Environments and is a structured method which can be applied to any size or type

More information

Project Risks. Risk Management. Characteristics of Risks. Why Software Development has Risks? Uncertainty Loss

Project Risks. Risk Management. Characteristics of Risks. Why Software Development has Risks? Uncertainty Loss Project Risks Risk Management What can go wrong? What is the likelihood? What will the damage be? What can we do about it? M8034 @ Peter Lo 2006 1 M8034 @ Peter Lo 2006 2 Characteristics of Risks Uncertainty

More information

INTRODUCTION: Project Status Reports. The status report formats/examples start on page 3

INTRODUCTION: Project Status Reports. The status report formats/examples start on page 3 What This Is INTRODUCTION: The status report formats/examples start on page 3 Five different formats and types of status information for summarizing and communicating project status to the team and Management.

More information

Contract Management. Brief 22. Public Procurement. September 2011

Contract Management. Brief 22. Public Procurement. September 2011 Brief 22 September 2011 Public Procurement Contract Management C O N T E N T S The process of contract management Contract management in practice Post contract performance review www.sigmaweb.org This

More information

INTERNAL AUDIT DIVISION AUDIT REPORT 2013/020. Audit of the Umoja software system (SAP) implementation

INTERNAL AUDIT DIVISION AUDIT REPORT 2013/020. Audit of the Umoja software system (SAP) implementation INTERNAL AUDIT DIVISION AUDIT REPORT 2013/020 Audit of the Umoja software system (SAP) implementation Overall results relating to effective implementation and configuration of the SAP system were initially

More information

SAP Product Stewardship Network Supplier Enablement Service Description (English)

SAP Product Stewardship Network Supplier Enablement Service Description (English) SAP PRODUCT STEWARDSHIP NETWORK - SUPPLIER ENABLEMENT - SERVICE DESCRIPTION SAP Product Stewardship Network Supplier Enablement Service Description (English) Table of Content 1 Definitions... 3 2 Introduction...

More information

IT Project Management Methodology. Project Risk Management Guide. Version 0.3

IT Project Management Methodology. Project Risk Management Guide. Version 0.3 NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Risk Management Guide Version 0.3 Project Risk Management Support Guide version 0.3 Page 1 Version Date Author

More information

CDC UNIFIED PROCESS JOB AID

CDC UNIFIED PROCESS JOB AID CDC UNIFIED PROCESS JOB AID Independent Verification & Validation Activities Document Purpose This Job Aid is a brief document listing the items to be noted, checked, remembered, and delivered when completing

More information

e-tourism Marketing Specialist

e-tourism Marketing Specialist ! Role Profile for e-tourism Marketing Specialist e-jobs-observatory.eu European Profiles in e-tourism Functions e-tourism Marketing Specialist 1 e-tourism Marketing Specialist 1. Role Profile Role title

More information

Project Management Framework

Project Management Framework Information Services Project Management Framework October 2003 Document ID No. Page 1 of 1 Contents 1. Introduction Page 3 2. Use of Framework Page 3 3. Project Register and Monitoring Page 4 4. Project

More information

MNLARS Project Audit Checklist

MNLARS Project Audit Checklist Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?

More information

Terms of Reference. Project Management Advisor for the Development of a Public Debt Management System (PDMS)

Terms of Reference. Project Management Advisor for the Development of a Public Debt Management System (PDMS) Terms of Reference Project Management Advisor for the Development of a Public Debt Management System (PDMS) (A) Background The Commonwealth is a voluntary association of 53 countries that support each

More information

Transition and Transformation. Transitioning services with minimal risk

Transition and Transformation. Transitioning services with minimal risk IBM Global TECHNOLOGY Servicess and Transformation ing services with minimal risk Summary To transition services is a complex process involving many issues. When outsourcing to IBM, you gain the benefit

More information

Progress Report Template -

Progress Report Template - Progress Report Template - Project Name Project Website Report compiled by Kultur, University of Southampton (lead institution) http://kultur.eprints.org Victoria Sheppard Reporting period Oct 07 Apr 08

More information

Project Management Process

Project Management Process Project Management Process Description... 1 STAGE/STEP/TASK SUMMARY LIST... 2 Project Initiation 2 Project Control 4 Project Closure 5 Project Initiation... 7 Step 01: Project Kick Off 10 Step 02: Project

More information