NSW Government ICT Benefits Realisation and Project Management Guidance

Size: px
Start display at page:

Download "NSW Government ICT Benefits Realisation and Project Management Guidance"

Transcription

1 NSW Government ICT Benefits Realisation and Project Management Guidance November 2014

2 CONTENTS 1. Introduction 1 2. Document purpose 1 3. Benefits realisation 1 4. Project management 4 5. Document control 7

3 1. INTRODUCTION The NSW Government ICT Investment Policy and Guidelines (Policy) assists agencies to embed the NSW Government ICT Strategy in investment decisions. While the Policy establishes a collaborative approach to ICT investment across government, it also recognises that agencies are responsible for their own investments. The Portfolio governance role of the ICT Board 1 sets out six key responsibilities, one of which is to ensure that approaches to benefits realisation and project management support cost effective investment in ICT. 2. DOCUMENT PURPOSE This guidance provides agencies with information on approaches to benefits realisation that will support cost effective investment in ICT. It is consistent with Treasury policy paper TPP08-05 Guidelines for Capital Business Cases, which requires agencies to develop a Benefits Realisation Strategy as part of the business case and gateway process. This guidance also outlines best practice principles and concepts in benefits realisation and project management as they apply to ICT investments. It references the NSW Government Benefits Realisation Management Framework which is available at Agencies are encouraged to adopt and tailor, where appropriate, to meet the unique conditions of their ICT investments, recognised benefits realisation and project management methodologies to optimise their use and value. This guidance is provided on the basis that agencies are responsible for the planning, delivery and management of their own ICT investments. It provides a structured approach for agencies to manage and demonstrate the realisation of benefits from business change programs. It helps practitioners show the linkage between investment and government policy priorities, agency business objectives and service delivery outcomes. 3. BENEFITS REALISATION The NSW Government Benefits Realisation Management Framework (June 2014) 2 applies to NSW Government ICT investments. Effective benefits realisation is a critical factor in achieving the expected business outcomes from ICT investments. Benefits realisation is an important consideration in the development of business cases and informs portfolio management, governance and decision making by the NSW Government. The purpose of the Benefits Realisation Framework is to provide: best practice principles drawn from latest experiences and proven practice in setting up and managing programs across NSW agencies standardised approaches to benefits realisation management for program directors and managers, change managers, project managers, business analysts and program management office staff 1 Portfolio governance role of the ICT Board, 14 May

4 consistent terminology and benefits categorisation introduction and guidance for program sponsors and business leaders. Planning for the realisation of benefits commences at the earliest stage of the project life cycle, as benefits may rely on the strategic use of deliverables to change the way business processes are run. Benefits realisation is an integral part of each stage of the ICT investment. 3.1 Principles ICT-enabled business change programs represent a large portion of government expenditure. Benefits realisation principles support a comprehensive approach to ICT investment planning and provide opportunities for improved government performance through more sustainable, consistent and standardised solutions. The following benefits realisation principles support agencies to achieve better value from investments in ICT. Benefits Realisation Principles Scoping Benefits management starts by defining objectives and the benefits they deliver Identifying and understanding benefits refines the business case Intermediate outcomes are needed to realise end benefits, and are just as important Development Benefits Realisation Management needs to integrate with an organisation s financial, program and change management strategies Benefits are enabled by successful change people, process, technology and organisational Benefits need to be owned and managed by a designated person within the business Benefits need to be communicated Measurement and analysis Benefits must be measurable and linked to performance data and reporting frameworks Benefits realisation requires a baseline and benefit targets in order to measure resulting outcomes Disbenefits need to be recognised and mitigated Benefits can be tangible (financial or non-financial) or intangible, e.g. improvements in quality, efficiency, access, and financial performance The same benefits cannot be claimed by two or more projects Monitoring and evaluation Benefits are not automatically realised; active monitoring is required Benefits are dynamic; they need to be regularly reviewed and updated Benefits tracking continues after a program/ project is completed 2

5 3.2 Process Benefits realisation can be divided into four phases: 1. Understand: define vision, objectives and potential benefits ensuring alignment with strategic drivers 2. Plan: prioritise the benefits and business change required to determine a plan for achieving the objectives 3. Manage and Report: measure, analyse and understand the program outcomes to proactively support the delivery of benefits 4. Evaluate: identify learnings from program activities to inform strategic decisions and priorities. Understand Evaluate Plan Manage and Report Figure 1: Benefits realisation process Agencies are encouraged to ensure each phase has clearly articulated tasks and deliverables. Whilst the specific details will change to meet the needs to the investment, below is some generic guidance: Tasks Articulate the vision Identify key stakeholders Map and estimate scale of benefits Develop benefits profiles Update baseline data Review benefits register Handover benefits reporting and measurements to BAU team Deliverables Business case Benefits realisation strategy First draft benefits register Benefits reporting format Periodic reports on benefit performance Updated benefits register Lessons learnt and post-implementation report 3

6 Conduct post-implementation review Capture lessons to inform continuous improvement Tailored benefits tools and templates Business case variation report 3.3 Evaluation Well planned and executed evaluation provides evidence of the efficiency and/or effectiveness of a project. Evaluation reports achievement against set targets and enables agencies to identify learnings and corrective actions required, and quantify outcomes from project activities to inform strategic decisions and priorities. Evaluation should ideally take place across the lifecycle of a program/project, from design and piloting through to implementation. It should not be seen as post-program/project activity only. It is a continuous process that commences as soon as business change starts to be delivered. The focus early in the program/project life will be on reporting progress in achieving intermediary outcomes of the program/project, e.g. new capabilities successfully delivered, change outcomes achieved, etc. In the post implementation phase, (reporting should continue beyond program closure) the focus is on the achievement of the desired business and strategic benefits. This phase answers the following key questions: Has the transition to BAU been managed? Have benefits been optimised with all key stakeholders? Has progress towards the vision/end state been reported against? Have lessons learnt been captured and communicated? Key principles that underpin the conduct of good evaluations include: evaluation should be built into program/project design evaluations should be methodologically rigorous with appropriate scale and design evaluations should be conducted with the right mix of expertise and independence evaluations should be timely to support and influence decision making evaluation processes should be transparent and open to scrutiny. A whole of government approach to evaluation can be found in the NSW Government Evaluation Framework It is recommended agencies consult this document to gain a more complete understanding of the evaluation needs and appropriate frameworks. 4. PROJECT MANAGEMENT ISO 21500:2012(E) - Guidance on project management defines project management as the application of methods, tools, techniques and competencies to a project, and includes the integration of the various phases of the project life cycle. Project management is the process used to enable the delivery of a project on time, within budget, according to specification and at a quality that meets professional standards and management expectations. It involves a different set of issues and skill set to the management of daily agency operations. A project is normally less predictable, more subject to change and has a longer planning horizon than the delivery of daily ICT services. 4

7 The purpose of the guidance below is to provide direction in the management of ICT projects, describing what agencies should expect from a project and addressing key considerations. This guidance applies throughout the life cycle of all projects regardless of their size or complexity. The life cycle of a project starts from the development of a concept for investment in ICT, and concludes with a post implementation review to assess whether the expected business benefits were realised. 4.1 Characteristics of successful projects To be successful, a project should have: Clearly defined business objective(s): business objectives should be understood and defined in the project's business case and expected, measurable benefits specified Well-defined and agreed scope: project scope includes what the project will do and won t do ; an agreed and well-defined project scope sets realistic expectations and provides a framework for project delivery and benefits realisation Partnership approach: a project is a partnership between the business unit that requests the project and the ICT staff assigned to the project, and should be considered to be a business initiative with an element of ICT rather than an ICT initiative that supports the business Project Sponsor: ownership and accountability for a project rests with the Project Sponsor, who is the owner and champion of the project and should be the individual with the greatest stake in the outcome of the project Support of senior management: role of senior management on a project will vary according to its scale and complexity, but senior management would normally monitor progress of projects that are critical to agency operation or which require significant levels of investment Stakeholder management and communications: this includes identifying stakeholders, their impact on the project and giving appropriate understanding and attention to their needs and expectations Project controls: pro-active and effective project control throughout all stages of the project ensures the success of a project; controls include project plans, risk and issues management, change management and quality control Regular progress reporting: reports on a project s progress should be available for senior management and other interested parties, on a regular basis and in a format consistent across the agency Benefits realisation: Planning and organising for the delivery of benefits must start as early as possible in the project life cycle, through a benefits realisation approach as discussed above. 5

8 4.2 Key considerations Development approach A project's level of risk will typically grow as the degree of customisation increases. Off-the-shelf solutions should be selected unless a compelling argument exists for development of new services. Phased or modular implementation Given the current rate of technological change and the potential rate at which an agency's business environment can change, it is not advisable to initiate a large scale project that runs for multiple years and has one major deliverable. Large projects should be undertaken on a phased or modular basis, with manageable deliverables at the conclusion of each phase or module. The business objectives of a project with an extended duration should be regularly reviewed and formally reconfirmed with the project's sponsor. If internal or external influences make it clear that a project will not meet its business objectives, or if it becomes apparent that a project will significantly exceed its time or cost estimates, it is the responsibility of senior management to reassess the project. The business case for any project will need to be reviewed and revised by its sponsor. If insufficient justification is found for the project to continue, it should be stopped. User participation Successful projects typically have high levels of user participation through measures such as membership of the project team or user focus groups. Clear roles and responsibilities Projects must have a well-defined structure with the roles and responsibilities of all participants clearly documented. In particular, the project's sponsor must be identified and this individual must assume ownership of, and ultimate accountability for, the project. Competent project team It is essential that appropriate resources are assigned to, and retained by, a project throughout its life cycle. Factors such as skills and expertise are to be taken into consideration in organising a project team. Use of a project management methodology does not guarantee that a project will be well managed. The methodology must be applied by skilled and experienced project managers and the project team members must be adequately trained in its use. Agencies may choose to employ external resources to complete a project successfully, including project management resources. If this occurs, the agency must retain overall responsibility for and control over the project. 4.3 Project risk management AS/NZS ISO 31000: Risk Management Principles and Guidelines defines risk as the effect of uncertainty on objectives, where an effect is the deviation from what is expected. All projects have some level of risk and while many risks cannot be eliminated, they can be managed and reduced. Project risk management is a continuous process that begins as part of 6

9 management planning and continues to be reviewed and monitored throughout the project to reduce risks to a manageable level. AS/NZS ISO identifies seven elements in the risk management process: Communication and consultation: exchanging information about risk management with internal and external stakeholders Establishing the context: defining the internal and external parameters to be considered when managing risk and setting the scope of an agency s risk management process Risk identification: finding, recognising and describing risks; initial project risks are identified through assessment of the project objectives and anticipated implementation approach Risk analysis: understanding the nature and level of risks so decisions can be made about whether a risk needs to be treated; at the start of each project phase, the specific risks associated with that phase are identified and risk profiles of similar projects are reviewed Risk evaluation: deciding which risks require further treatment by comparing against established risk criteria, and in what order; an impact analysis of the risks is performed to determine the relative exposure of the risk in terms of time and cost Risk treatment: identifying, selecting and implementing responses to risks that fall outside the levels an agency is prepared to accept or tolerate; two types of management actions may be adopted, (i) preventive action where the project environment is modified to minimise the identified risk, and (ii) contingency action which provides a buffer that will be available to address an unanticipated event Monitoring and review: continually checking that each component of the risk management process is performing as desired. The NSW Treasury s Risk Management Toolkit for the NSW Public Sector (TPP12-03) provides detailed guidance. 5. DOCUMENT CONTROL Document history Date Version Description Author November Approved Office of Finance and Services Contact: Ray Evans, Director, Strategic Policy, Office of Finance and Services ray.evans@finance.nsw.gov.au Telephone: (02)

Confident in our Future, Risk Management Policy Statement and Strategy

Confident in our Future, Risk Management Policy Statement and Strategy Confident in our Future, Risk Management Policy Statement and Strategy Risk Management Policy Statement Introduction Risk management aims to maximise opportunities and minimise exposure to ensure the residents

More information

NSW Government ICT Governance Framework for Whole of Government Investments

NSW Government ICT Governance Framework for Whole of Government Investments NSW Government ICT Governance Framework for Whole of Government Investments November 2014 CONTENTS 1. Introduction 1 2. Scope and application 2 3. Purpose 2 4. Outcomes 2 5. Governance framework 3 6. Governance

More information

The date the initiative has been given approval to proceed. This excludes any initiatives in start-up or concept stage.

The date the initiative has been given approval to proceed. This excludes any initiatives in start-up or concept stage. Data glossary This glossary provides definitions of the terms related to data collection for this site. It has been provided so that interested parties can quickly and easily check the terms as they encounter

More information

The Gateway Review Process

The Gateway Review Process The Gateway Review Process The Gateway Review Process examines programs and projects at key decision points. It aims to provide timely advice to the Senior Responsible Owner (SRO) as the person responsible

More information

OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT)

OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT) OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT) 3 DAY COURSE INTRODUCTION The principles of project management are generic and therefore can be applied to all projects regardless of business sector.

More information

Information Sharing Lessons Learned from Gateway Reviews: Gate 5 Benefits Realisation Review

Information Sharing Lessons Learned from Gateway Reviews: Gate 5 Benefits Realisation Review Information Sharing Lessons Learned from Gateway Reviews: Gate 5 Benefits Realisation Review October 2013 The purpose of this document is to share lessons learned to support agencies to better identify

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

Project Assessment Framework Establish service capability

Project Assessment Framework Establish service capability Project Assessment Framework Establish service capability July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below.

More information

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce Maturity Model March 2006 Version 1.0 P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value Added product which is outside the scope of the HMSO

More information

TEC Capital Asset Management Standard January 2011

TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard Tertiary Education Commission January 2011 0 Table of contents Introduction 2 Capital Asset Management 3 Defining

More information

WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)?

WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)? WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)? Due to the often complex and risky nature of projects, many organizations experience pressure for consistency in strategy, communication,

More information

Avondale College Limited Enterprise Risk Management Framework 2014 2017

Avondale College Limited Enterprise Risk Management Framework 2014 2017 Avondale College Limited Enterprise Risk Management Framework 2014 2017 President s message Risk management is part of our daily life, something we do regularly; often without realising we are doing it.

More information

december 08 tpp 08-5 Guidelines for Capital Business Cases OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper

december 08 tpp 08-5 Guidelines for Capital Business Cases OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper december 08 Guidelines for Capital Business Cases OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper Preface The NSW Government is committed to the ongoing improvement of public services by ensuring

More information

The Human Capital Management Systems Business Case A Checklist to assist agencies developing a business case

The Human Capital Management Systems Business Case A Checklist to assist agencies developing a business case The Human Capital Management Systems Business Case A Checklist to assist agencies developing a business case Final version for release Human Capital Management See more at psc.nsw.gov.au/hcm Index - Business

More information

Gateway review guidebook. for project owners and review teams

Gateway review guidebook. for project owners and review teams Gateway review guidebook for project owners and review teams The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and

More information

1 Context. 2 Background. CiCS Development Portfolio Definition 2015 Background

1 Context. 2 Background. CiCS Development Portfolio Definition 2015 Background CiCS Development Portfolio Definition 2015 Background 1 Context CiCS Vision We will be an innovative and influential department, respected by the University and recognised as a leader in the sector, delivering

More information

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3)

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) 1st February 2006 Version 1.0 1 P3M3 Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value

More information

White Paper. Benefits and Value

White Paper. Benefits and Value Benefits and Value The only purpose of undertaking any business activity is to create value! If undertaking the work destroys value the activity should not be started. Any value proposition though is in

More information

Adoption of a PPM Solution Using An Agile Approach. Andy Robinson

Adoption of a PPM Solution Using An Agile Approach. Andy Robinson Adoption of a PPM Solution Using An Agile Approach Andy Robinson 1 Agenda Drivers for using a Portfolio and Project Management system Organisational maturity Where to start Planning, delivery, realisation

More information

ICT Business Case Guide

ICT Business Case Guide ICT Business Case Guide JULY 2012 AGIMO is part of the Department of Finance and Deregulation Contents Introduction 3 First Pass Business Case 5 1. Executive Summary 6 2. Current Situation 7 3. Proposed

More information

Project, Programme and Portfolio Management Delivery Plan 6

Project, Programme and Portfolio Management Delivery Plan 6 Report title Agenda item Project, Programme and Portfolio Management Delivery Plan 6 Meeting Performance Management and Community Safety Panel 27 April 2009 Date Report by Document number Head of Strategy

More information

Understanding programmes and Programme Management

Understanding programmes and Programme Management GUIDELINES FOR MANAGING PROGRAMMES Understanding programmes and Programme Management NOVEMBER 2010 CONTENTS Who is this guidance aimed at?... 2 What is a programme, and how does a programme differ from

More information

Enterprise Risk Management Framework 2012 2016. Strengthening our commitment to risk management

Enterprise Risk Management Framework 2012 2016. Strengthening our commitment to risk management Enterprise Risk Management Framework 2012 2016 Strengthening our commitment to risk management Contents Director-General s message... 3 Introduction... 4 Purpose... 4 What is risk management?... 4 Benefits

More information

Part B1: Business case developing the business case

Part B1: Business case developing the business case Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project

More information

UNSOLICITED PROPOSALS

UNSOLICITED PROPOSALS UNSOLICITED PROPOSALS GUIDE FOR SUBMISSION AND ASSESSMENT January 2012 CONTENTS 1 PREMIER S STATEMENT 3 2 INTRODUCTION 3 3 GUIDING PRINCIPLES 5 3.1 OPTIMISE OUTCOMES 5 3.2 ASSESSMENT CRITERIA 5 3.3 PROBITY

More information

CAPABILITY MATURITY MODEL & ASSESSMENT

CAPABILITY MATURITY MODEL & ASSESSMENT ENTERPRISE DATA GOVERNANCE CAPABILITY MATURITY MODEL & ASSESSMENT www.datalynx.com.au Data Governance Data governance is a key mechanism for establishing control of corporate data assets and enhancing

More information

JUNE 2010. Assurance for high risk projects

JUNE 2010. Assurance for high risk projects JUNE 2010 Assurance for high risk projects Our vision is to help the nation spend wisely. We apply our unique perspective of public audit to help Parliament and government drive lasting improvement in

More information

Xavier Catholic College Risk Management - Policy & Procedure

Xavier Catholic College Risk Management - Policy & Procedure Xavier Catholic College Risk Management Policy 18 March 2013 Sourced from CSOHS Online. Source CSO Broken Bay 2012 Page 1 Risk Management Policy (Draft) PURPOSE Risk management is the culture, processes

More information

DORSET & WILTSHIRE FIRE AND RESCUE AUTHORITY Performance, Risk and Business Continuity Management Policy

DORSET & WILTSHIRE FIRE AND RESCUE AUTHORITY Performance, Risk and Business Continuity Management Policy Not Protectively Marked Item 6 Appendix B DORSET & WILTSHIRE FIRE AND RESCUE AUTHORITY Management Policy The Dorset & Wiltshire Fire and Rescue Authority () is the combined fire and rescue authority for

More information

Analyst - EDI. healthalliance Purpose, Vision and Principles. Purpose Statement

Analyst - EDI. healthalliance Purpose, Vision and Principles. Purpose Statement Principles Vision Purpose Statement Analyst - EDI healthalliance Purpose, Vision and Principles healthalliance provides shared services to benefit NZ health organisations. We will deliver increasing value

More information

The Risk Management strategy sets out the framework that the Council has established.

The Risk Management strategy sets out the framework that the Council has established. Derbyshire County Council Management Policy Statement The Authority adopts a proactive approach to Management to achieve Best Value and continuous improvement and is committed to the effective management

More information

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) Copyright: Australian Institute of Project Management Document Information Document

More information

Transition and Transformation. Transitioning services with minimal risk

Transition and Transformation. Transitioning services with minimal risk IBM Global TECHNOLOGY Servicess and Transformation ing services with minimal risk Summary To transition services is a complex process involving many issues. When outsourcing to IBM, you gain the benefit

More information

RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT

RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) Risk should be defined as An uncertain event that, should it occur, would have an effect (positive or negative) on the project or business objectives.

More information

ESKISP6056.01 Direct security testing

ESKISP6056.01 Direct security testing Direct security testing Overview This standard covers the competencies concerning with directing security testing activities. It includes setting the strategy and policies for security testing, and being

More information

OE PROJECT CHARTER TEMPLATE

OE PROJECT CHARTER TEMPLATE PROJECT : PREPARED BY: DATE (MM/DD/YYYY): Project Name Typically the Project Manager Project Charter Last Modified Date PROJECT CHARTER VERSION HISTORY VERSION DATE (MM/DD/YYYY) COMMENTS (DRAFT, SIGNED,

More information

Risk Management Policy Adopted by:

Risk Management Policy Adopted by: Risk Management Policy Adopted by: Infigen Energy Limited Infigen Energy (Bermuda) Limited Infigen Energy RE Limited in its capacity as Responsible Entity of Infigen Energy Trust Adopted: 17 December 2009

More information

An Introduction to the PRINCE2 project methodology by Ruth Court from FTC Kaplan

An Introduction to the PRINCE2 project methodology by Ruth Court from FTC Kaplan An Introduction to the PRINCE2 project methodology by Ruth Court from FTC Kaplan Of interest to students of Paper P5 Integrated Management. Increasingly, there seems to be a greater recognition of the

More information

The Asset Management Landscape

The Asset Management Landscape The Asset Management Landscape ISBN 978-0-9871799-1-3 Issued November 2011 www.gfmam.org The Asset Management Landscape www.gfmam.org ISBN 978-0-9871799-1-3 Published November 2011 This version replaces

More information

Authorised by the Victorian Government 1 Treasury Place, Melbourne, 3002

Authorised by the Victorian Government 1 Treasury Place, Melbourne, 3002 Project Governance Project Governance The Secretary Department of Treasury and Finance 1 Treasury Place Melbourne Victoria 3002 Australia Telephone: +61 3 9651 5111 Facsimile: +61 3 9651 5298 www.dtf.vic.gov.au

More information

University of Edinburgh Knowledge Strategy Committee. 8 June 2012. Use of the Project Governance Toolkit for Shared Academic Timetabling

University of Edinburgh Knowledge Strategy Committee. 8 June 2012. Use of the Project Governance Toolkit for Shared Academic Timetabling University of Edinburgh Knowledge Strategy Committee 8 June 2012 Use of the Project Governance Toolkit for Shared Academic Timetabling Brief description of the paper Shared Academic Timetabling has been

More information

ESKITP7145.01 Manage IT service delivery performance metrics

ESKITP7145.01 Manage IT service delivery performance metrics Overview This sub-discipline covers the competencies required to manage the monitoring, analysis and communication of IT service delivery performance metrics. Monitoring service level performance is a

More information

A Risk Management Standard

A Risk Management Standard A Risk Management Standard Introduction This Risk Management Standard is the result of work by a team drawn from the major risk management organisations in the UK, including the Institute of Risk management

More information

Report to Parliament No. 4 for 2011 Information systems governance and security. Financial and Assurance audit. Enhancing public sector accountability

Report to Parliament No. 4 for 2011 Information systems governance and security. Financial and Assurance audit. Enhancing public sector accountability Financial and Assurance audit Report to Parliament No. 4 for 2011 Information systems governance and security ISSN 1834-1128 Enhancing public sector accountability RTP No. 4 cover.indd 1 15/06/2011 3:19:31

More information

Project Management Guidelines

Project Management Guidelines Project Management Guidelines Overview Section 86-1506 (5) directs the NITC to adopt guidelines regarding project planning and management. The goal of project management is to achieve the objectives of

More information

Issue No: 2.0 First Published: Sept 1997 Current Version: May 2002. Table of Contents 1. INTRODUCTION...2 2. OBJECTIVES AND SCOPE OF GUIDELINE...

Issue No: 2.0 First Published: Sept 1997 Current Version: May 2002. Table of Contents 1. INTRODUCTION...2 2. OBJECTIVES AND SCOPE OF GUIDELINE... Department of Commerce Guidelines Change Management Guideline Issue No: 2.0 First Published: Sept 1997 Current Version: May 2002 Table of Contents 1. INTRODUCTION...2 2. OBJECTIVES AND SCOPE OF GUIDELINE...2

More information

COCA-COLA HELLENIC BOTTLING COMPANY RISK MANAGEMENT POLICY

COCA-COLA HELLENIC BOTTLING COMPANY RISK MANAGEMENT POLICY COCA-COLA HELLENIC BOTTLING COMPANY RISK MANAGEMENT POLICY 1. INTRODUCTION The effective management of risk is central to the ongoing success and resilience of Coca-Cola Hellenic Bottling Company (CCHBC).

More information

ENTERPRISE RISK MANAGEMENT POLICY

ENTERPRISE RISK MANAGEMENT POLICY ENTERPRISE RISK MANAGEMENT POLICY TITLE OF POLICY POLICY OWNER POLICY CHAMPION DOCUMENT HISTORY: Policy Title Status Enterprise Risk Management Policy (current, revised, no change, redundant) Approving

More information

Assurance Reviews Process - A Handbook for Conducting Assurance Reviews Resource Management Guide No. 105. Archived

Assurance Reviews Process - A Handbook for Conducting Assurance Reviews Resource Management Guide No. 105. Archived Assurance Reviews Process - A Handbook for Conducting Assurance Reviews Resource Management Guide No. 105 SEPTEMBER 2014 Commonwealth of Australia 2014 ISBN 978-1-922096-69-2 (Online) With the exception

More information

Risk Management Strategy & Implementation Plan 2014 2016

Risk Management Strategy & Implementation Plan 2014 2016 St George s Healthcare NHS Trust: the next decade Risk Management Strategy & Implementation Plan 2014 2016 DRAFT VERSION 6.0 UPDATED 19.11.14 Executive summary We know, from external assurances received

More information

Risk Management Policy

Risk Management Policy Risk Management Policy Risk Management Policy Record Number D14/79827 Responsible Manager Manager Strategy and Governance Last reviewed 10 March 2015 Adoption reference Council Resolution number 90.5 Previous

More information

Single Stage Light Business Case Template

Single Stage Light Business Case Template Better Business Cases Single Stage Light Business Case Template Prepared by: Prepared for: Date: Version: Status: Better Business Cases Single Stage Light Business Case Template Document Control Document

More information

Middlesbrough Manager Competency Framework. Behaviours Business Skills Middlesbrough Manager

Middlesbrough Manager Competency Framework. Behaviours Business Skills Middlesbrough Manager Middlesbrough Manager Competency Framework + = Behaviours Business Skills Middlesbrough Manager Middlesbrough Manager Competency Framework Background Middlesbrough Council is going through significant

More information

THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini)

THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini) PAGE 1 THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini) Ing. Guido Mattu More than 25 years experience in Engineering and Project Management activities

More information

ARCHITECTURE SERVICES. G-CLOUD SERVICE DEFINITION.

ARCHITECTURE SERVICES. G-CLOUD SERVICE DEFINITION. ARCHITECTURE SERVICES. G-CLOUD SERVICE DEFINITION. Table of contents 1 Introduction...3 2 Architecture Services...4 2.1 Enterprise Architecture Services...5 2.2 Solution Architecture Services...6 2.3 Service

More information

Project organisation and establishing a programme management office

Project organisation and establishing a programme management office PROJECT ADVISORY Project organisation and establishing a programme office Leadership Series 1 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital

More information

VISION FOR LEARNING AND DEVELOPMENT

VISION FOR LEARNING AND DEVELOPMENT VISION FOR LEARNING AND DEVELOPMENT As a Council we will strive for excellence in our approach to developing our employees. We will: Value our employees and their impact on Cardiff Council s ability to

More information

FINANCIAL MANAGEMENT MATURITY MODEL

FINANCIAL MANAGEMENT MATURITY MODEL Definition: Financial management is the system by which the resources of an organisation s business are planned, directed, monitored and controlled to enable the organisation s goals to be achieved. Guidance

More information

Project Governance A N T I C I P A T I N G A N A U D I T

Project Governance A N T I C I P A T I N G A N A U D I T Project Governance A N T I C I P A T I N G A N A U D I T Public sector Project Management characteristics Multi-million rand projects Often National interest projects Subject to intense scrutiny Uncertainty

More information

State Records Guideline No 25. Managing Information Risk

State Records Guideline No 25. Managing Information Risk State Records Guideline No 25 Managing Information Risk Table of Contents 1 Introduction... 4 1.1 Purpose... 4 1.2 Authority... 4 2 Risk Management and Information... 5 2.1 Overview... 5 2.2 Risk management...

More information

MANAGING DIGITAL CONTINUITY

MANAGING DIGITAL CONTINUITY MANAGING DIGITAL CONTINUITY Project Name Digital Continuity Project DRAFT FOR CONSULTATION Date: November 2009 Page 1 of 56 Contents Introduction... 4 What is this Guidance about?... 4 Who is this guidance

More information

Delivering e-procurement Local e-gov National e-procurement Project Overarching Guide to e-procurement for LEAs

Delivering e-procurement Local e-gov National e-procurement Project Overarching Guide to e-procurement for LEAs 1. Introduction Background The National e-procurement Project (NePP) and Centre for Procurement Performance (CPP) are working to support and enable schools to meet their e- Government targets and to gain

More information

IDMS PMSA Infrastructure Project Management Congress, Durban, 16/17 September 2013. Greg Evans: Strategic Executive Engineering Unit

IDMS PMSA Infrastructure Project Management Congress, Durban, 16/17 September 2013. Greg Evans: Strategic Executive Engineering Unit IDMS PMSA Infrastructure Project Management Congress, Durban, 16/17 September 2013 Greg Evans: Strategic Executive Engineering Unit IDMS Infrastructure Delivery Management System IDMS SECTION ONE Introduction

More information

Leading forecasting practices in the private sector. Prepared by Deloitte LLP on behalf of the National Audit Office

Leading forecasting practices in the private sector. Prepared by Deloitte LLP on behalf of the National Audit Office Leading forecasting practices in the private sector Prepared by Deloitte LLP on behalf of the National Audit Office June 2013 Disclaimer Limitations of our report You are responsible for determining whether

More information

Queensland Treasury. Queensland Government. Program Evaluation Guidelines

Queensland Treasury. Queensland Government. Program Evaluation Guidelines Queensland Treasury Queensland Government Program Evaluation Guidelines November 2014 Document details Security Classification Date of Review of Security Classification Authority Author PUBLIC November

More information

Project Services. How do we do it?

Project Services. How do we do it? Project Services Many organisations struggle with inconsistent or poor project management performance across their business. Sometimes the failure to deliver on time and on budget (or at all!) is simply

More information

Selecting a project management methodology

Selecting a project management methodology VICTORIAN GOVERNMENT CIO COUNCIL Project Management Selecting a project management methodology Guideline This guideline provides advice for selecting and tailoring a project management methodology. Keywords:

More information

DSDM Case Study. An Agile Approach to Software Systems Development for the Highways Agency

DSDM Case Study. An Agile Approach to Software Systems Development for the Highways Agency DSDM Case Study An Agile Approach to Software Systems Development for the Highways Agency Government agencies are constantly striving to develop software systems that support business objectives, deliver

More information

Project Management Fact Sheet:

Project Management Fact Sheet: Project Management Fact Sheet: Developing a Business Case Version: 1.2, November 2008 DISCLAIMER This material has been prepared for use by Tasmanian Government agencies and Instrumentalities. It follows

More information

Director: Improvement and Corporate Services. Improvement & Corporate Services

Director: Improvement and Corporate Services. Improvement & Corporate Services HAY Job description JOB TITLE: DIRECTORATE: GRADE: Director: Improvement and Corporate Services Improvement & Corporate Services Director DATE PREPARED: March 2013 REPORTS TO: Chief Executive JOB PURPOSE:

More information

Network Rail Infrastructure Projects Joint Relationship Management Plan

Network Rail Infrastructure Projects Joint Relationship Management Plan Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf

More information

Reference Process for Enterprise Architecture enabled ICT Planning

Reference Process for Enterprise Architecture enabled ICT Planning Reference Process for Enterprise Architecture enabled ICT Planning NSW GEA Toolkit R1 April 2015 Contact ea@finance.gov.nsw Strategic Policy Department of Finance, Services & Innovation 1 Table of Contents

More information

Electronic Discharge Summary Systems Self-Evaluation Toolkit

Electronic Discharge Summary Systems Self-Evaluation Toolkit Electronic Discharge Summary Systems Self-Evaluation Toolkit September 2011 Electronic Discharge Summary Systems: Self Evaluation Toolkit, 2011 ISBN Print 978-0-9870617-2-0 Commonwealth of Australia 2011

More information

POSITION DESCRIPTION. Role Purpose. Key Challenges. Key Result Areas

POSITION DESCRIPTION. Role Purpose. Key Challenges. Key Result Areas POSITION DESCRIPTION Position Title Manager, Technical Services Support Position Number Reports to Manager Technology Services Functional Auth HRM Auth Region IT Services Centre Head Office Date Feb 2011

More information

Project Risk Management. Presented by Stephen Smith

Project Risk Management. Presented by Stephen Smith Project Risk Management Presented by Stephen Smith Introduction Risk Management Insurance Business Financial Project Risk Management Project A temporary endeavour undertaken to create a unique product

More information

UNITED NATIONS OFFICE FOR PROJECT SERVICES. ORGANIZATIONAL DIRECTIVE No. 33. UNOPS Strategic Risk Management Planning Framework

UNITED NATIONS OFFICE FOR PROJECT SERVICES. ORGANIZATIONAL DIRECTIVE No. 33. UNOPS Strategic Risk Management Planning Framework UNOPS UNITED NATIONS OFFICE FOR PROJECT SERVICES Headquarters, Copenhagen O.D. No. 33 16 April 2010 ORGANIZATIONAL DIRECTIVE No. 33 UNOPS Strategic Risk Management Planning Framework 1. Introduction 1.1.

More information

POL ENTERPRISE RISK MANAGEMENT SC51. Executive Services Department BUSINESS UNIT: Executive Support Services SERVICE UNIT:

POL ENTERPRISE RISK MANAGEMENT SC51. Executive Services Department BUSINESS UNIT: Executive Support Services SERVICE UNIT: POL ENTERPRISE RISK MANAGEMENT SC51 POLICY CODE: SC51 DIRECTORATE: Executive Services Department BUSINESS UNIT: Executive Support Services SERVICE UNIT: Executive Support Services RESPONSIBLE OFFICER:

More information

The PMO as a Project Management Integrator, Innovator and Interventionist

The PMO as a Project Management Integrator, Innovator and Interventionist Article by Peter Mihailidis, Rad Miletich and Adel Khreich: Peter Mihailidis is an Associate Director with bluevisions, a project and program management consultancy based in Milsons Point in Sydney. Peter

More information

Appendices to Practice Guide to Project Management for IT Projects under an Outsourced Environment

Appendices to Practice Guide to Project Management for IT Projects under an Outsourced Environment Appendices to Practice Guide to Project Management for IT Projects under an Outsourced Environment [S19a] Version 2.1 March 2011 COPYRIGHT NOTICE 2011 by the Government of the Hong Kong Special Administrative

More information

Benefits realisation. Gate

Benefits realisation. Gate Benefits realisation Gate 5 The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and Planning, January 2010. The Queensland

More information

INTEGRATING RECORDS MANAGEMENT

INTEGRATING RECORDS MANAGEMENT INTERNATIONAL RECORDS MANAGEMENT TRUST INTEGRATING RECORDS MANAGEMENT IN ICT SYSTEMS Good Practice Indicators CONTENTS Figure 1: Designing a Records Management Improvement Programme iv Figure 2: Integrating

More information

Part One: Introduction to Partnerships Victoria contract management... 1

Part One: Introduction to Partnerships Victoria contract management... 1 June 2003 The diverse nature of Partnerships Victoria projects requires a diverse range of contract management strategies to manage a wide variety of risks that differ in likelihood and severity from one

More information

Strategic Risk Management for School Board Trustees

Strategic Risk Management for School Board Trustees Strategic Management for School Board Trustees A Management Process Framework May, 2012 Table of Contents Introduction Page I. Purpose....................................... 3 II. Applicability and Scope............................

More information

Risk Management Plan 2012-2015

Risk Management Plan 2012-2015 Risk Management Plan 2012-2015 This controlled document shall not be copied in part or whole without the express permission of the author or the author s representative. Revision Date Previous Revision

More information

Asset management strategy

Asset management strategy Asset management strategy 2012-2017 The asset management strategy 2013 2017 has been prepared by MidCoast Water to support the implementation of its strategic objectives. This plan should be read in conjuction

More information

IndigoBlue Governance Framework

IndigoBlue Governance Framework Overview IndigoBlue IndigoBlue Winner of Agile Consultancy of the Year 2011/12, IndigoBlue is one of the leading consultancies in the UK focused on Agile processes for strategic consultancy, and programme

More information

Business continuity management policy

Business continuity management policy Business continuity management policy health.wa.gov.au Effective: XXX Title: Business continuity management policy 1. Purpose All public sector bodies are required to establish, maintain and review business

More information

Programme Manager Relationship Management System

Programme Manager Relationship Management System Programme Manager Relationship Management System Russam Ref 4573 Job Profile This document is a generic description for the role. Any specific requirements in the published advert should also be taken

More information

The Department for Business, Innovation and Skills IMA Action Plan PRIORITY RECOMMENDATIONS

The Department for Business, Innovation and Skills IMA Action Plan PRIORITY RECOMMENDATIONS PRIORITY RECOMMENDATIONS R1 BIS to elevate the profile of information risk in support of KIM strategy aims for the protection, management and exploitation of information. This would be supported by: Establishing

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

Page 1 of 24. To present the Asset Management Policy 2014 for Council adoption.

Page 1 of 24. To present the Asset Management Policy 2014 for Council adoption. Page 1 of 24 COMMUNITY AND SERVICES SPECIAL COMMITTEE REPORT 9 DECEMBER 2104 AGENDA ITEM 6.1 ASSET MANAGEMENT POLICY 2014 REVIEW Director: Manager: Ian Butterworth Director Infrastructure and Engineering

More information

FlyntGroup.com. Enterprise Risk Management and Business Impact Analysis: Understanding, Treating and Monitoring Risk

FlyntGroup.com. Enterprise Risk Management and Business Impact Analysis: Understanding, Treating and Monitoring Risk Enterprise Risk Management and Business Impact Analysis: Understanding, Treating and Monitoring Risk 2012 The Flynt Group, Inc., All Rights Reserved FlyntGroup.com Enterprise Risk Management and Business

More information

Risk Management. National Occupational Standards February 2014

Risk Management. National Occupational Standards February 2014 Risk Management National Occupational Standards February 2014 Skills CFA 6 Graphite Square, Vauxhall Walk, London, SE11 5EE T: 0207 0919620 F: 0207 0917340 E: info@skillscfa.org www.skillscfa.org Skills

More information

Telstra Service Management Framework. Your assurance of first-class network support

Telstra Service Management Framework. Your assurance of first-class network support Telstra Service Framework Your assurance of first-class network support The Service Framework delivers comprehensive, integrated support Service Frame work SERVICE IMPROVEMENT & REPORTING Performance &

More information

WATE R O&M S E RV I CE S An asset management perspective

WATE R O&M S E RV I CE S An asset management perspective WATE R O&M S E RV I CE S An asset management perspective Smart asset management solutions create long term value With more than 150 years of water industry experience and responsibility for operations

More information

Role Description Enterprise Architect and Solutions Delivery Manager

Role Description Enterprise Architect and Solutions Delivery Manager Role Description Enterprise Architect and Solutions Delivery Manager Cluster Agency Division Location Classification/Grade/Band Kind of Employment NSW Health Cancer Institute NSW Information Technology

More information

Department of Infrastructure and Planning: Governance Framework for Infrastructure Delivery Special Purpose Vehicles

Department of Infrastructure and Planning: Governance Framework for Infrastructure Delivery Special Purpose Vehicles Department of Infrastructure and Planning: Governance Framework for Infrastructure Delivery Special Purpose Vehicles Governance Framework for Special Purpose Vehicles Table of Contents Executive Summary...3

More information

Project Management for Implementing the Smart Grid By Power System Engineering, Inc. Abstract PM Methodology Using a Repeatable Project Management

Project Management for Implementing the Smart Grid By Power System Engineering, Inc. Abstract PM Methodology Using a Repeatable Project Management Project Management for Implementing the Smart Grid By Power System Engineering, Inc. Abstract PM Methodology Using a Repeatable Project Management Approach Project management solutions for the Smart Grid

More information

CAT-MIS Project Management

CAT-MIS Project Management CAT-MIS Project Management Communicat Accounting Transition to Management Information System Project Management Communicat utilises our proven CAT-MIS Project Management method for the implementation of

More information

Improving Project Governance

Improving Project Governance Improving Project Governance By Phil Mann 31 October 2012 Overview This whitepaper provides a synopsis of the Victorian Government s Ombudsman s Own motion investigation into ICT-enabled, November 2011.

More information