1 UCD IT Services IT01 IT Services Website Redevelopment Project Initiation Document Version 1.0 1, December 2014 Version History Version Date Summary of Changes Changed by 1 1/12/2014 Brian Morrissey IT Services Website Redevelopment Project Initiation Document Page 1 of 12
2 Contents 1 Objectives & Scope Background to the Project Project Objectives Expected Benefits Project Scope Change Control 4 2 Project Plan Project Approach Milestones & Deliverables Project Plan 6 3 Project Structure Roles & Responsibilities Project Team Meetings 8 4 Risks & Issues Initial Risk & Issue Log Ongoing Management of Risks and Issues 9 5 Communication Plan 10 6 Project Costs Initial Project Budget Ongoing Costs 11 IT Services Website Redevelopment Project Initiation Document Page 2 of 12
3 1 Objectives & Scope This Project Initiation Document (PID) defines the IT Services Website Redevelopment project in detail including objectives, scope, approach, deliverables, timescale and structure of the project so that it can be understood and agreed by all stakeholders. 1.1 Background to the Project The existing website and information architecture has been in place for approximately eight years and is in need of a refresh taking into account new methods of information delivery. 1.2 Project Objectives To provide customers with the information they need in a intuitive manner, on a range of device types, allowing them to make the most of the services we offer. Specifically that would include: To clearly identify the services we provide to the UCD community (and what we do). To make it easy for the website user to find the information they are looking for To offer advice on the best use of our services To offer support and solutions for IT related queries To establish a clear identity for IT Services as a progressive and professional unit To drive engagement and conversation with IT Services through the integration of social media tools, forum applications etc. To build a showcase website exemplifying best practice in website design 1.3 Expected Benefits When complete our new website will provide customers with relevant and actionable information at their fingrtips, regardless of their location. Customers should be more selfsufficient and so may not have to refer to the IT Services Helpdesk or other sources of information in order to avail of a service. 1.4 Project Scope The project will involve a redesign of the IT Services website including the overall look of the site and the navigation. The customer experience will be at the heart of this redesign and the website in that it will be based around services on offer together with quick links to regular tasks customers may wish to do. The website will work equally well on mobile devices and desktop systems. An assessment of current content and the repositioning of same is an important aspect of this project. Compliance with Accessibility Standards will be designed-in from the outset. IT Services Website Redevelopment Project Initiation Document Page 3 of 12
4 The scope will include the following components: 1. Exploratory stage (how are people using the site, what are they looking for from us). 2. Development of Site architecture, navigation and flow. 3. Content Review consider how content is presented and language used. 4. Design of website including new look and feel, potential social media fora and creation of templates ensuring responsive technology, accessibility. 5. Coding and integration ( SiteManager Terminal 4). 1.5 Change Control The Project Initiation Document will be approved on commencement of the project by the relevant project members. Following this, an ongoing Project Plan will be maintained and updated to accommodate any minor changes occur. Once the scope is agreed herein, any further changes to scope or major deviation from the proposed timeframes will be the subject of the change control. IT Services Website Redevelopment Project Initiation Document Page 4 of 12
5 2 Project Plan 2.1 Project Approach We are working with our implementation partner and customers to deliver a reimagined ITS website. The approach is iterative in that we will build the website in parallel, refinig the nav;igation and architecture and adding content. When complete we will publish it in place of the current site. 2.2 Milestones & Deliverables The following milestones, deliverables and target delivery dates have been defined for the project: Milestone Deliverable Responsib ility 0 Project Initiation completed Project Initiation Document completed. Peter McKiernan Reviewers/ Approvers Reviewers: A.N. Other 1 A.N. Other 2 Due Date 1 Requirements completed 2 Partner selection Approval: A. N. Other 3 Statement of Requirements. Comms Group 10/09 3 IA Initial architecture design & stakeholder review. 4 Revised architecture Revised architecture and ITS sign-off. 5 Content review Review of content throughout IT Services. Comms Group 1/10 Heads of Service Heads of Service 20/11 12/01 Comms Group 25/02 The individual(s) listed in the Responsibility column above are responsible for the relevant deliverables. Typically each deliverable will have one or many reviewers and a final approval by one or more individuals. Acceptance and sign-off of a deliverable is required by the Approval person. IT Services Website Redevelopment Project Initiation Document Page 5 of 12
6 2.3 Project Plan The Milestones and Deliverables section below will act as the project plan: Milestone Deliverable Responsib ility 0 Project Initiation completed Project Initiation Document completed. Peter McKiernan Reviewers/ Approvers Reviewers: A.N. Other 1 A.N. Other 2 Due Date 1 Requirements completed 2 Partner selection Approval: A. N. Other 3 Statement of Requirements. Comms Group 10/09 3 IA Initial architecture design & stakeholder review. 4 Revised architecture Revised architecture and ITS sign-off. 5 Content review Review of content throughout IT Services. Comms Group 1/10 Heads of Service Heads of Service 20/11 12/01 Comms Group 25/02 IT Services Website Redevelopment Project Initiation Document Page 6 of 12
7 Project Structure The project comprises a Project Team and a Steering Group. The Steering Group will agree project schedules, approve major deliverables and resolve any critical issues that arise during the lifetime of the project. The Project Team will manage the project on a daily basis and will report regularly to the Steering Group. 2.4 Roles & Responsibilities Define the responsibilities for each group and role within the project. The following are some sample responsibilities for common project groups and roles. Role Responsibilities Names Steering Group Ensure that the project direction is appropriate to the achievement of the ultimate objectives. Review progress reports from the Project Manager and determine actions needed to address deviations. Provide guidance to the Project Team on high level principles to be complied with. Review and approve deliverables. Monitor and proactively manage risks as they arise. Communications Group. Project Sponsor Ensure that resources are provided as required for the project Take action on any issues escalated by the Project Team Project Manager Prepare the Project Plans Determine resource requirements and ensure that appropriate resources are allocated Peter McKiernan Manage the project to ensure that the desired results are achieved within agreed time-scales Monitor progress and report on a regular basis to the Steering Committee Prepare project deliverables and their presentation for approval IT Services Website Redevelopment Project Initiation Document Page 7 of 12
8 Role Responsibilities Names Project Team Conduct the tasks and activities of the project in accordance with the Project Plan Prepare the project deliverables by the agreed due dates Report progress to the Project Manager 2.5 Project Team Meetings The following are the scheduled project governance meetings: Team Attendees Frequency Steering Group Project Team Communications Group. Peter Mckiernan, Sinead O Rourke, Genevieve Dalton, Brian Morrissey. Approx. every two weeks. IT Services Website Redevelopment Project Initiation Document Page 8 of 12
9 3 Risks & Issues 3.1 Initial Risk & Issue Log The following project risks or issues have been identified on commencement of the project. These initial tasks to address these risks or issues are outlined. Risk / Issue Probability H M L Impact H M L Actions to Mitigate Responsibility 3.2 Ongoing Management of Risks and Issues Any additional risks and issues identified will be maintained on an ongoing basis by the Project Manager in separate Risks and Issues logs. IT Services Website Redevelopment Project Initiation Document Page 9 of 12
10 4 Communication Plan Identify the key stakeholders in the project and the plans for interaction and communication with each. Stakeholders are individuals and groups who will be capable of influencing the success of a project, directly impacted by the project as users or customers or involved in approving or implementing project deliverables. The following table highlights the communication and interaction activities planned for each stakeholder group: Stakeholder Actions Responsibility IT Services Website Redevelopment Project Initiation Document Page 10 of 12
11 5 Project Costs 5.1 Initial Project Budget Outline the proposed costs of the project by phase, typically to cover items such as consultancy resource costs, product/vendor & licence costs, training, any specific hardware costs, etc. You might also want to consider adding in an element of contingency into these costs. 5.2 Ongoing Costs Provide an estimate of any ongoing costs such as recurring licence fees, maintenance charges, etc. IT Services Website Redevelopment Project Initiation Document Page 11 of 12
12 Related Documentation It is often useful to list any related documentation here, such as supporting documentation provided by the business/customer. IT Services Website Redevelopment Project Initiation Document Page 12 of 12
It0x Enhanced data storage services Sharepoint Teamsites
UCD IT Services It0x Enhanced data storage services Sharepoint Teamsites Project Initiation Document Version 1.0 2, December 2014 Version History Version Date Summary of Changes Changed by 1 2/12/2014
UCD IT Services. Research Data. Project Initiation Document. Version 1.0 03 rd December 2014. Version History
UCD IT Services Research Data Project Initiation Document Version 1.0 03 rd December 2014 Version History Version Date Summary of Changes Changed by 1.0 03/12/2014 Initial Document 1.1 09/12/2014 Minor
IT1T Integrated Recruitment Systems 2015
UCD IT Services IT1T Integrated Recruitment Systems 2015 Project Initiation Document Version 1.0 2 December 2014 Version History Version Date Summary of Changes Changed by 1.0 02/12/2014 Initial Draft
UCD International UCD IT Services. IT12 - Device Security & Encryption Strategy. Project Initiation Document. Version 1.0 2 nd December 2014
UCD International UCD IT Services IT12 - Device Security & Encryption Strategy Project Initiation Document Version 1.0 2 nd December 2014 Version History Version Date Summary of Changes Changed by 1.0
OE PROJECT CHARTER TEMPLATE
PROJECT : PREPARED BY: DATE (MM/DD/YYYY): Project Name Typically the Project Manager Project Charter Last Modified Date PROJECT CHARTER VERSION HISTORY VERSION DATE (MM/DD/YYYY) COMMENTS (DRAFT, SIGNED,
Transition and Transformation. Transitioning services with minimal risk
IBM Global TECHNOLOGY Servicess and Transformation ing services with minimal risk Summary To transition services is a complex process involving many issues. When outsourcing to IBM, you gain the benefit
IBAPro Project Management Methodology
IBAPro Project Management Methodology A description of the IBApps Project Management Methodology and Implementation Process Version 2.2, June 2013 Contents 1. Project Management... 3 2. Phases... 3 2.1.
Project Scorecard Template
Project Scorecard Template 1. Identify criteria for success: Review the objectives and deliverables in the Project Definition, as well as any other existing information that is relevant to the project.
TRANSITION PLAN TEMPLATE
TRANSITION PLAN TEMPLATE In this template, instructions are included in italics. When you have completed the template and no longer need the instructions, delete them. Provide a brief overview of the transition
Project Management Plan Outline ITSC
Project Management Plan Outline ITSC Date: 02/28/2012 Introduction At start of each project vendors must create a project management plan for ITSC approval, including, at a minimum, the sections described
SCHEDULE 8 Generalist Project Services Framework 2015
SCHEDULE 8 Generalist Project Services Framework 2015 Nominal Insurer And Schedule 8 (Project Services Framework) Page: 1 of 6 Schedule 8 Generalist Project Services Framework Contents Overview... 3 1.
PROJECT PLAN FOR. Project Name Here
PROJECT PLAN FOR Project Name Here Version # DatE Reviewed and Approved for submittal to Executive Sponsor , Project Manager Project Plan Approved for submittal to Executive Sponsor: , Project
Project Start Up. Start-Up Check List. Why a Project Check List? What is a Project Check List? Initial Release 1.0 Date: January 1997
Why a Project Check List? A good way to ensure that all start-up tasks are completed prior to actually starting the project is to develop a start-up check list. The check list can be developed and then
15 Principles of Project Management Success
15 Principles of Project Management Success Project management knowledge, tools and processes are not enough to make your project succeed. You need to get away from your desk and get your hands dirty.
ICT Service Desk Creation
ICT Service Desk Creation Project Initiation Document Document: ICT Service desk Creation: PID Issue Date: 26 th November 2010 Version: 0.1 Draft Version Number: 1.0 Change Control Quality Assurance Document:
Project Management Process
Project Management Process Description... 1 STAGE/STEP/TASK SUMMARY LIST... 2 Project Initiation 2 Project Control 4 Project Closure 5 Project Initiation... 7 Step 01: Project Kick Off 10 Step 02: Project
CASE STUDY 6 SECTOR: NHS DELIVERABLE: NEW MULTIFUNCTION SERVICE DESK THE CLIENT:
CASE STUDY 6 SECTOR: NHS DELIVERABLE: NEW MULTIFUNCTION SERVICE DESK THE CLIENT: The Queen Elizabeth Hospital King s Lynn NHS Foundation Trust (QEH) is a 514 bed general hospital providing services to
How To Write A Project Management Plan
Enter Project Name Project Management Plan (PMP) Kickoff Month, Day, Year 1 Purpose The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents
North European Functional Airspace Block Avinor, Norway EANS, Estonia Finavia, Finland LGS, Latvia. NEFAB Project CHANGE MANAGEMENT MANUAL
NEFAB Project CHANGE MANAGEMENT MANUAL Version 0.5 Page 1 of 38 Revision history Version Date Description Approved 0.5 14/12/2011 Page 2 of 38 Table of Contents 1. Introduction... 4 1.1. The Scope of this
LMI Aerospace PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012
PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012 TABLE OF CONTENTS INTRODUCTION... 2 PROJECT MANAGEMENT APPROACH... 2 PROJECT SCOPE... 2 MILESTONE LIST... 2 SCHEDULE BASELINE
Client Communication Portal Project
Client Communication Portal Project In 2014 Sunnyfield was awarded a grant by the Organisation Transition Fund to develop a Client Communication Portal. The aim of the project was to enhance person centred
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History
ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution
<name of project> Software Project Management Plan
The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor
PROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
Position Description. Enterprise Agreement: Budget Responsibility: Nil
Position Description Position Details Position Scope Title: Division: Project Manager Finance & Corporate Services Enterprise Agreement: Budget Responsibility: Department: Payroll Authority Level: Ambulance
Subject Area 1 Project Initiation and Management
DRII/BCI Professional Practice Narrative: Establish the need for a Business Continuity Plan (BCP), including obtaining management support and organizing and managing the BCP project to completion. (This
Standards for Developing and Implementing Administrative Systems at UC Davis
Page 1 of 7 Standards for Developing and Implementing Administrative Systems at UC Davis Introduction The purpose of this document is to describe Standards for Developing and Implementing Administrative
Project Assessment Framework Establish service capability
Project Assessment Framework Establish service capability July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below.
LGS Project Management Methodology
Page: 32 LGS Project Management Methodoy The LGS project management methodoy is integral to our overall delivery methodoy. Based on inpro, one of the LGS inspiration series documents, our methodoy is compliant
Appendix 2-A. Application and System Development Requirements
Appendix 2-A. Application and System Development Requirements Introduction AHRQ has set up a Distributed Systems Engineering Lab (DSEL) to support all internal development efforts and provide a facility
Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee
Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Page 1 2 Contents 1. Introduction... 3 1.1 Definition of a... 3 1.2 Why have
TRU Website Redesign Project Charter. 1/21/2011 Thompson Rivers University Web Project Team
TRU Website Redesign Project Charter 1/21/2011 Thompson Rivers University Web Project Team INTRODUCTION... 4 BACKGROUND... 4 PROJECT GOALS AND OBJECTIVES... 5 Project Goal... 5 Project Objectives... 5
PMAP. Project Management At Penn PMAP
Project Management At Penn 1 Fundamentals Course Objective To provide you with an overview of Topics Project Management at Penn () Project Governance Phases & Project Management Activities Project Management
MNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
Project Management Guidebook
METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple
Portfolio: Transformation, Modernisation and Regulation
Portfolio: Transformation, Modernisation and Regulation Procurement Committee 19 October 2006 Procurement of E-mail, Calendar and Archiving System Report by: Ward Implications: Head of City Service and
Contract and Vendor Management Guide
Contents 1. Guidelines for managing contracts and vendors... 2 1.1. Purpose and scope... 2 1.2. Introduction... 2 2. Contract and Vendor Management 2.1. Levels of management/segmentation... 3 2.2. Supplier
Programme Governance and Management Plan Version 2
PROCESS FOR CHANGE - Detailed Design Programme Governance and Management Plan Version 2 1 INTRODUCTION In October 2008, the Council approved the selection of seven opportunity themes to take forward from
Creating A Risk Management Plan
Creating A Risk Management Plan A presentation based on the concepts taught in the Risk Management 1A course. Carlos Consulting Group Roseville, CA. (916) 521-2520 www.carlosconsulting.com 1 Objectives
Project Roles and Responsibilities
Project s and This template can be used to define roles and responsibilities Below is a few typical examples of the different types of roles involved in delivering a project and their respective responsibilities.
Project Lifecycle Management (PLM)
Project Lifecycle Management (PLM) Process or Tool? Why PLM? Project Definition Project Management NEW REQUEST/ INITIATIVES SUPPORT (Quick fixes) PROJECT (Start Finish) ONGOING WORK (Continuous) ENHANCEMENTS
Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview
Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview 1/1 Table of Contents 1. Introduction...3 2. Executive Summary...4 3. Program Definition...5 3.1. Program
Project Management: Trainee Guide Module 5 POST IMPLEMENTATION
200 Project Management: Trainee Guide Module 5 POST IMPLEMENTATION Bridges Social Development Project Management Training Program http://training.canadabridges.com 09/09/2009 PROJECT MANAGEMENT TRAINING
Understand why, when and how-to to formally close a project
Project Closure Purpose: Understand why, when and how-to to formally close a project Audience: Project managers, project sponsors, team members and other key stakeholders Learning Objectives: Describe
COMMUNICATIONS MANAGEMENT PLAN <PROJECT NAME>
COMMUNICATIONS MANAGEMENT PLAN TEMPLATE This Project Communications Management Template is free for you to copy and use on your project and within your organization. We hope that you find this template
KMS Implementation Roadmap
KMS Implementation Roadmap Sample Excerpt Prepared by: The Knowledge Compass, Inc. TABLE OF CONTENTS 1. EXECUTIVE SUMMARY 5 1.1 Overview 5 1.2 Project Goals & Objectives 5 1.3 Implementation Approach 5
Organization. Project Name. Project Overview Plan Version # Date
Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents
Ellucian Implementation Methodology. Summary of Project Management and Solution Delivery Phases
Ellucian Implementation Methodology Summary of Project Management and Solution Delivery Phases Rev. 5/10/2013 Table of Contents Overview 3 Project Management Initiation 4 Planning 5 Execution 6 Monitor
Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce
Maturity Model March 2006 Version 1.0 P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value Added product which is outside the scope of the HMSO
Template K Implementation Requirements Instructions for RFP Response RFP #
Template K Implementation Requirements Instructions for RFP Response Table of Contents 1.0 Project Management Approach... 3 1.1 Program and Project Management... 3 1.2 Change Management Plan... 3 1.3 Relationship
WHITE PAPER Business Process Services: A Successful Transition Is the Foundation of World- Class Outsourcing cgi.com
WHITE PAPER Business Process Services: A Successful Transition Is the Foundation of World- Class Outsourcing A summary of the key transition questions asked by our clients In this paper, we examine five
COMMUNICATION MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:
COMMUNICATION MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Document Information Document Title Amendment History Document Version Date Author/Reviewer Modifications 5/28/2014 Page i 2014 CSG
Release Management: Effective practices for IT delivery
Release Management: Effective practices for IT delivery Introduction Today s health plans face a unique combination of technology challenges due to their complex IT environments. These environments serve
1. Project Charter. Sheri Kellogg. Phyllis Short. Project Title: PeopleSoft CSS / HCM Split Description:
1. Stakeholder Name Cecilia Castellano Chris Cox Laura Emch Andy Grant Sheri Kellogg Chastity McCartney Beth Ann Rife Phyllis Short Michelle Simmons Brian Skelding Sharon Swartz Department Admissions Registrar
To provide a procedure and associated guidelines to facilitate the management of project dependencies.
Management DEPENDENCY MANAGEMENT Purpose To provide a procedure and associated guidelines to facilitate the management of project dependencies. Overview Dependencies in this Phase are defined as actions,
Microsoft Solutions for Security. Delivering the Windows Server 2003 Security Guide
Microsoft Solutions for Security Delivering the Windows Server 2003 Security Guide Information in this document, including URL and other Internet Web site references, is subject to change without notice.
Managing Multiple Vendors: Getting the Most from a Complex Team. November 16, 2012
Managing Multiple Vendors: Getting the Most from a Complex Team November 16, 2012 1 Contents About the presenters Context: working with multiple SIs is the norm Benefits and challenges of working with
Project Team Roles Adapted for PAAMCO
Project Team Roles Adapted for PAAMCO Project Roles, Authority & Responsibilities Role a defined funciton assumed by or assigned to a person in the project Authority the right to apply project resources,
Program Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
Disaster Recovery Policy
Disaster Recovery Policy INTRODUCTION This policy provides a framework for the ongoing process of planning, developing and implementing disaster recovery management for IT Services at UCD. A disaster is
MSN Upgrade and Refresh with Remote Support Services
MSN Upgrade and Refresh with Remote Support Services Service Summary Mountain States Networking ( MSN ) shall provide the following Upgrade and Refresh Services to Customer for up to one (1) chassis limited
Project QA and Collaboration Plan for <project name>
Note: Text displayed in blue italics is included to provide guidance to the author and should be deleted or hidden before publishing the document. This template can be used at it is, or to complete and
California Department of Mental Health Information Technology Attention: MHSA-IT 1600 9 th Street, Room 141 Sacramento, CA 95814
IT Project Status Report For an MHSA-Funded IT Project Please send the Signed Original to the following address: California Department of Mental Health Information Technology Attention: MHSA-IT 1600 9
1. Background and business case
1. Background and business case This section explains the context and why the project is being undertaken. It provides the justification for investing the time and resources in the project. 1.1 Reasons
Project Managers Operations
Date: 15 December 2015 Job Title: Department: Location: Senior Project Manager Operations (Interim Projects & logistics) Project Team North Shore Hospital site, Takapuna, Auckland and Waitakere Hospital;
Construction Management System (CMS) Deliverable Review Process
Construction Management System (CMS) Deliverable Review Process State of California Department of Transportation Division of Construction December 21, 2009 Version 1.0 Approvals Name: Title: Mark Leja
Minnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
The PMP Application Process
The PMP Application Process The purpose of this document is to explain the PMP application process and provide helpful links and tools for submitting your application. Reference: The reference for the
SCHEDULE 10. Contract Management and Reporting. the Management Information and reporting requirements,
SCHEDULE 10 Contract Management and Reporting 1. Scope 1.1 This schedule sets out: contract management procedures; and the Management Information and reporting requirements, with which the Service Provider
Project Implementation Process (PIP)
Vanderbilt University Medical Center Project Implementation Process (PIP).......... Project Implementation Process OVERVIEW...4 PROJECT PLANNING PHASE...5 PHASE PURPOSE... 5 TASK: TRANSITION FROM PEP TO
ITIL Implementation Planning
White Paper ITIL Implementation Planning Overview Introduction This paper describes the items that need to be considered in advance of starting an ITIL implementation effort. It is critical to make sure
ITS Project Management Methodology
ITS Project Management Methodology Information Technology Services Project Management Group 11/17/2014 Version 2.1 Author: ITS Project Management Group Document Control Change Record Date Author Version
Before starting it is worth considering what we mean by the term project - basically it can be defined as:
Delivering Successful Projects, Tom Moriarty, MDR Consulting This paper outlines the critical requirements of success in managing projects of all types from the definition of a business need to the delivery
Project Management Guidelines
Project Management Guidelines Overview Section 86-1506 (5) directs the NITC to adopt guidelines regarding project planning and management. The goal of project management is to achieve the objectives of
Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010
Dallas IIA Chapter / ISACA N. Texas Chapter Auditing Tuesday, October Project 20, 2009 Management Controls January 7, 2010 Table of Contents Contents Page # Project Management Office Overview 3 Aligning
Service Integration &
This is a DRAFT document, being published for review & comment The content is therefore subject to change & revision This document is part of the XGOV Strategic SIAM reference set Service Integration &
ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 5 PROJECT CLOSEOUT PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 5 PROJECT CLOSEOUT PHASE Table of Contents Introduction... 3 Project Closeout Phase... 3 Activities and Documents in the Closeout Phase... 4 Project Closeout Task...
How To Manage The Health Benefit Exchange At Mhix
Minnesota Health Insurance Exchange (MNHIX) 1.1.2 Project Charter Date: 09/21/2012 11/9/2012 12:10 PM Page 1 of 18 T A B L E O F C O N T E N T S 1. MNHIX Introduction... 3 1.1 MNHIX Scope... 4 1.2 Critical
ESKISP6056.01 Direct security testing
Direct security testing Overview This standard covers the competencies concerning with directing security testing activities. It includes setting the strategy and policies for security testing, and being
Risk/Issue Management Plan
Risk/Issue Management Plan Centralized Revenue Opportunity System November 2014 Version 2.0 This page intentionally left blank Table of Contents 1. Overview... 3 1.1 Purpose... 3 1.2 Scope... 3 2. Roles
Digital Asset Manager, Digital Curator. Cultural Informatics, Cultural/ Art ICT Manager
Role title Digital Cultural Asset Manager Also known as Relevant professions Summary statement Mission Digital Asset Manager, Digital Curator Cultural Informatics, Cultural/ Art ICT Manager Deals with
Capacity Plan. Template. Version X.x October 11, 2012
Template Version X.x October 11, 2012 This is an integral part of infrastructure and deployment planning. It supports the goal of optimum provisioning of resources and services by aligning them to business
Change Management Tool kit Project Management Guidelines
Change Management Tool kit Project Management Guidelines Projects A project is a piece of work with fixed duration and clearly defined outcomes. Each project must have: 1 Aims: A clear overall purpose
Waterloo CMS Project. Project Charter Information Systems and Technology (IST) University of Waterloo (UW) Waterloo, Ontario, Canada
Waterloo CMS Project Project Charter Information Systems and Technology (IST) University of Waterloo (UW) Waterloo, Ontario, Canada Charter Date: September 4, 2009 Revision Date: February 10, 2010 Maintained
Operations. Group Standard. Business Operations process forms the core of all our business activities
Standard Operations Business Operations process forms the core of all our business activities SMS-GS-O1 Operations December 2014 v1.1 Serco Public Document Details Document Details erence SMS GS-O1: Operations
CONFIGURATION COMMITTEE. Terms of Reference
SWBTB (8/13) 166 (g) CONFIGURATION COMMITTEE Terms of Reference 1. CONSTITUTION 1.1 The Board hereby resolves to establish a Committee of the Board to be known as the Configuration Committee (The Committee).