Project Rijksweg 15, Maasvlakte-Vaanplein
|
|
|
- Evan Fisher
- 10 years ago
- Views:
Transcription
1 Project Rijksweg 15, Maasvlakte-Vaanplein challenges of a DBFM-contract Adrie Franken, Contractmanager A15 MaVa Rijkswaterstaat
2 Topics Project scope Procurement strategy characteristics of the DBFM-contract stakeholder management Tender strategy Succesfactors Struggles 2 NETLIPSE Conference Vienna
3 Overview project area A15 3 NETLIPSE Conference Vienna
4 Project objectives Provide a solid and sustainable solution that: Improves accessibility Port of Rotterdam to the hinterland Improves trafic safety A15 Solves nautical bottleneck Botlekbridge Restrictions & conditions: realised before end 2015 minimal disrubtion of traffic Use PPP 4 NETLIPSE Conference Vienna
5 Projectscope 40 km highway: 16 km widening: partly 2x3 2x5 and 2x2 2x3 2 traffic junctions (Re)construction of 40 associated structures Construction of new Botlekbridge 2x2 traffic lanes, 2 railroad lines, bicycle/pedestrian lane 2x 87m passage width Reconstruction 2 tunnels All traffic systems 5 NETLIPSE Conference Vienna
6 Procurement strategy: 1 DBFM-contract DBFM because of: Policy dutch government to stimulate PPP Life cycle cost approach Better performance Maximum participation of private party Smaller administration (RWS) One contract because of: Reduction of (geographical) interfaces Reduction of (internal) interfaces (Integral scope including road, structure, traffic systems eg) Minimizing management capacity PDO Contractsum : approx. 1.5 billion 6 NETLIPSE Conference Vienna
7 DBFM contract From construction.. to service-providing Service = technical availability of the (new) infrastructure Change in attitude and thinking! 7 NETLIPSE Conference Vienna
8 DBFM-contract : Payment structure Commencement Date Interim Availability Date Completion Date Availability Date Expiry Date 100%GAP 40% GAP 20% GAP Development Phase G A P Operational Phase 8 NETLIPSE Conference Vienna
9 DBFM-contract : Assignment of tasks PDO (project organisation): Road Decision procedure (incl Reference design) Political / Stakeholder commitment Acces to area Consortium: Design, build, finance, maintain Licences/permits Pipes and cables Traffic and Netwerk management Communication Incident management Technical availability of infra New Botlek Bridge 9 NETLIPSE Conference Vienna
10 Stakeholder management Stable project environment necessary Major stakeholders: Port of Rotterdam City of Rotterdam Other local authorities Rijkswaterstaat Safety/Fire Department Rijnmond 10 NETLIPSE Conference Vienna
11 Stakeholdermanagement -2 - Strategic Stakeholder management : interaction and control Road Decision Governance Agreement between RWS and 15 local authorities Deliver agreements between PDO and each local authority DBFM-contract More formal relationship as usual Cold feet local authorities 11 NETLIPSE Conference Vienna
12 Tender: strategy Ceiling Price Value for money / Economical most value bid Price and quality Quality = fullfilling of additional preferences plus adoption of listed risks (± 45% of ceiling price) Competitive Dialogue 12 NETLIPSE Conference Vienna
13 Tender : Preferences Preferences : additional on Requirements Preferences related to projectgoals: Collaboration & Roledistribution, minimizing traffic disruption, Riskprofile specific critical project items (Opening Permit Tunnel, interface traffic control centre) Maximum total value : 40% of ceiling price Judgement by expert committee Value unfullfilled preferences will be add up to bid 13 NETLIPSE Conference Vienna
14 Tender : listed Risks Listed Risks will be distributed during dialogue between Consortium and PDO. If risk is not taken by consortium: the value of the risk will be add up to bid If risk is taken by consortium: Compensation of the ceiling price Maximum total value : 40% of ceiling price 14 NETLIPSE Conference Vienna
15 Tender Economical most valuable bid: sum of: a) value of bid b) value of unfulfilled Preferences c) value Listed risks remained by PDO 15 NETLIPSE Conference Vienna
16 Tender: Competitive Dialogue 5 - Competitive Dialogue: Prequalificationphase qualification fitted consortia Outline proposal selection 3 best consortia Consultationphase Optimizing contract Dialogue phase optimizing bid ; judgement value of bid Final submission phase submission and selection preferred bidder Completionphase contract Tender period : 18 months 16 NETLIPSE Conference Vienna
17 Tender: interaction Milestone driven Meetings: Formal meetings (descision making) informal technical meetings (discussion) attitude : focus on project objectives and interests PDO, facilitate consortia 17 NETLIPSE Conference Vienna
18 Tender : result Completion within planning preferred bidder: A-Lanes A15 (Ballast Nedam, Strukton, Strabag, John Laing) Bid characteristics: 70% of preferences are fullfilled All Listed Risks are adopted by consortium Completion Date 7 months earlier than reference planning Price significant below Ceiling Price 18 NETLIPSE Conference Vienna
19 Success factors Governance Agreement and Deliver Agreements with local authorities Strategic stakeholder management Focus on project goals during tendering (paying mechanism, preferences, discussion during dialogue) Milestone driven Competitive Dialogue Informal technical meetings during Competitive Dialogue 19 NETLIPSE Conference Vienna
20 Struggles Up to date information of assets, subsoil etc Complexity of project Information management Chance of attitude consortia long term supllier of availibility of infra instead of classic contractor Customer-oriented Chance of attitude PDO and Clients Organisation From implicit to explicit From solution thinking to purpose thinking /from technical to functional specifications detached involvement Good teammembers 20 NETLIPSE Conference Vienna
21 afterall. DBFM demands much more of contractor and PDO than regular (D&C-) contracts But. DBFM and Competitive Dialogue leads to further professionalism of project management 21 NETLIPSE Conference Vienna
22 Discussion 22 NETLIPSE Conference Vienna
Introduction. Evaluating Value for Money. Hans de Kievit Senior PPP Consultant. Projects: Auditing Public Private Partnerships; the work continues
Evaluating Value for Money Auditing Public Private Partnerships; the work continues Seminar for Supreme Audit Institutions 26 and 27 November 2012 The Hague, The Netherlands Introduction Hans de Kievit
Rijkswaterstaat. Basic Principles of PPP
Basic Principles of PPP Auditing Public Private Partnerships; the work continues Seminar for Supreme Audit Institutions 26 and 27 November 2012 The Hague, The Netherlands The Directorate-General for Public
Utrechtseweg 148 3818 ER Amersfoort +31 (0)33-461 58 52 [email protected] www.ttfmc.nl
Rijkswaterstaat Paths (roads) to the future N.a. 2004 BAM Infraconsult / BAM Wegen Won Innovation programme Consultancy Rijkswaterstaat Sea locks IJmuiden N.a. 2006 BAM Civiel Won Innovation programme
PPPs: INSIGHTS FROM NORTH AMERICA. Presenter: Brian Middleton. www.jacobs.com worldwide
PPPs: INSIGHTS FROM NORTH AMERICA Presenter: Brian Middleton AGENDA Overview of US PPP market Case studies of sample projects Summary/Conclusions PPPs: An insight from North America SUMMARY OF PPPs IN
Selectie van uitgevoerde tenders. TTF Marketing & Communicatie b.v. Utrechtseweg 148, 3818 ER Amersfoort, +31 (0)33-461 58 52, www.ttfmc.
Selectie van uitgevoerde tenders Rijkswaterstaat Paths (roads) to the future N.a. 2004 BAM Infraconsult / BAM Wegen Won Innovation programme Consultancy Rijkswaterstaat Sea locks IJmuiden N.a. 2006 BAM
Procurement Processes and Tools
Methods of Procurement Purchasing Activities Procurement Processes and Tools There are different methods of procurement, which are utilized to acquire goods or services. There are many factors which determine
Practical experiences with Best Value Procurement of the engineering services for the Blankenburgtunnel in Rotterdam Area
Practical experiences with Best Value Procurement of the engineering services for the Blankenburgtunnel in Rotterdam Area Wim Leendertse Carlita Vis 19 november 2013 Ministry of Infrastructure and Environment
Asset Management Policy for Major PFI Projects
Asset Management Policy for Major PFI Projects Agenda Asset Management Drivers Typical AM positioning in Motorway PFI Asset management Strategy Works Planning and Scheduling Innovation & Risk Mitigation
GUIDELINES FOR TOTAL PROJECT COST MANAGEMENT
GUIDELINES FOR TOTAL PROJECT COST MANAGEMENT March 2013 MINISTRY OF STRATEGY AND FINANCE TABLE OF CONTENTS CHAPTER Ⅰ GENERAL PROVISIONS Article 1 (Purpose)... 1 Article 2 (Definition of Total Project Cost)...
Presentation BIM. Simplify the information chain at infrastructure projects; Pilot DBFM-SAA. Benno Koehorst 11 October 2012, kickoff meeting V-Con
Presentation BIM Simplify the information chain at infrastructure projects; Pilot DBFM-SAA Benno Koehorst 11 October 2012, kickoff meeting V-Con 29 mei 2012 What is BIM? Building Information Models Task
How To Write An Integrated Construction Project
GUIDANCE FOR ENGINEERING CONSULTANCY FIRMS INTEGRATED CONTRACTS PREFACE Our industry is facing new integrated business models with increasing frequency. The processes driving these models are very different
The Dutch Railway System. Logistics & Railway Infrastructure Forum NL Indonesia April 30 th 2015
The Dutch Railway System Logistics & Railway Infrastructure Forum NL Indonesia April 30 th 2015 1 Welkom Eigenaar: ProRail 27 november 2014 Welkom Eigenaar: ProRail 27 november 2014 Exchange of knowledge
Scrim And Texture Data Collection Contract Management S Chamberlain
Scrim And Texture Data Collection Contract Management S Chamberlain Introduction Transit New Zealand (Transit) has been successfully managing SCRIM and texture data collection through external suppliers
PROGRAMME FOR INTERNATIONAL STUDENT ASSESSMENT (PISA) 2018: CALL FOR TENDER PROCESS. An Overview
PROGRAMME FOR INTERNATIONAL STUDENT ASSESSMENT (PISA) 2018: CALL FOR TENDER PROCESS An Overview Launch of the PISA 2018 Procurement Process In January 2014, the OECD plans to launch the first Call for
The Competitive Dialogue:
The Competitive Dialogue: A powerful tool to procure Value for Money PPP Projects Respa Conference on PPPs 23&24 June 2014, Danilovgrad, Montenegro Today s presentation Introduction and background What
Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education
EMAIL [email protected] WEB www.fosterinfrastructure.com Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education
Contents. Public Private Comparator
Contents Introduction 7 Module 1: Inception report 15 Step 1a: describe the alternatives, scope, plan & parties involved 17 Step 1b: create the communication plan 23 Module 2: Qualitative analysis 31 Step
Preliminary Draft JOB DESCRIPTIONS AND QUALIFICATIONS OF KEY PERSONNEL. XXXXX PPP Unit
Preliminary Draft JOB DESCRIPTIONS AND QUALIFICATIONS OF KEY PERSONNEL XXXXX PPP Unit Chief Executive Officer Job Description: The CEO is tasked with the establishment of a PPP Unit for the Government
ROAD PROJECT LONGITUDINAL DE LA SIERRA SECTION 2
ROAD PROJECT LONGITUDINAL DE LA SIERRA SECTION 2 LOCATION Location Cajamarca and La Libertad regions SECTION 2: CIUDAD DE DIOS CAJAMARCA-CHIPLE, CAJAMARCA-TRUJILLO AND CHILETE DEVIATION -PE-3N JUNCTION
Determining contract management professionalism within Rijkswaterstaat
Eindhoven, June 2013 Determining contract management professionalism within Rijkswaterstaat By J.M.H. (Joep) Hotterbeekx BSc Industrial Engineering and Management Sciences TU/e 2011 Student identity number
ROAD SAFETY AUDIT MANAGEMENT
ROAD SAFETY AUDIT MANAGEMENT Transportation Research Record Devin Duranleau, Corresponding Author KPH Turcot, un partenariat S.E.N.C. 4333 Boulevard Grande-Allée Boisbriand, QC J7H 1M7 Tel: 778-838-5711,
Infrastructure Asset Management in a Large Scale European PPP Project. AgileAssets Article
Infrastructure Asset Management in a Large Scale European PPP Project AgileAssets Article Page 2 Infrastructure Asset Management in a Large Scale European PPP Project How European PPP (Public-Private Partnership)
12-3-2014. After MGI. MGI celebration series. Hilbert Davelaar Project Manager GIS&ICT. Wageningen, 12 March 2013
After MGI MGI celebration series Hilbert Davelaar Project Manager GIS&ICT Wageningen, 12 March 2013 1 Introduction 2 Hilbert Davelaar MSc 2000 2003 WUR BLP 2003 2005 WUR MGI Thesis: Participatory planning
How to involve Dutch Industry in ITER & DEMO?
How to involve Dutch Industry in ITER & DEMO? Nuclear Fusion Energy symposium, Eindhoven, October 30 th, 2014 Eric Boom, EB Consultancy ([email protected]) Contents Scope of this presentation The Past
CONTRACT MANAGEMENT FRAMEWORK
CONTRACT MANAGEMENT FRAMEWORK August 2010 Page 1 of 20 Table of contents 1 Introduction to the CMF... 3 1.1 Purpose and scope of the CMF... 3 1.2 Importance of contract management... 4 1.3 Managing contracts...
Deliverable 1 Task Report Case Study: Vienna-Budapest M1/M15 privately financed toll road
Contract No TREN/05/FP6TR/S07.41077/513499 Funding Infrastructure: Guidelines for Europe - FUNDING Instrument: Sixth Framework Programme Thematic Priority: Sustainable Surface Transport Deliverable 1 Task
MINISTRY OF TRANSPORT AND COMMUNICATIONS OF KYRGYZ REPUBLIC. CAREC Transport Corridor 1 (Bishkek-Torugart Road) Project 3
MINISTRY OF TRANSPORT AND COMMUNICATIONS OF KYRGYZ REPUBLIC CAREC Transport Corridor 1 (Bishkek-Torugart Road) Project 3 financed by the Asian Development Bank under Loan 2755-KGZ (SF) TERMS OF REFERENCE
Lao PDR Public-Private Partnership Policy
Lao PDR Public-Private Partnership Policy Supported by the Asian Development Bank GRANT-0309 LAO Governance and Capacity Development in Public Sector Management Program (Public Private Partnerships) Table
The Mersey Gateway Project
The Mersey Gateway Project The Mersey Gateway Project is a major scheme to build a new six-lane toll bridge over the River Mersey in the north west of England. It will link the towns of Runcorn and Widnes
Consultancy Services Proposal
Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847
Expression of interest for the delivery of an Initial Operating Segment
Expression of interest for the delivery of an California High-Speed Rail Authority DB International GmbH Marc Giesen, Director Consulting [email protected] Oskar-Sommer-Strasse 15 60596 Frankfurt
Schiphol- Amsterdam-Almere. The use of Open BIM and GIS. Henk Schaap Consultant RWS BIM program 2014-03-23
Schiphol- Amsterdam-Almere The use of Open BIM and GIS Henk Schaap Consultant RWS BIM program 2014-03-23 (the Dutch Directorate General for Public Works and Water Management) is the state executive agency
Director of Asset Management and Repairs
Job details Job title: Director of Asset Management Responsible to: Executive Director of Property Responsible for: Location: Overview of the role The overall purpose of the Director of Asset Management
Good Practice Framework. Performance Management
Good Practice Framework Performance Management Decision Gatewa y Good Practice Framework Strategic Planning STRATEGIC PLANNING Policy Context Needs Assessment Strategic Review Outcomes Continuous Improvement
DoES-QW2 Suitability Assessment Declaration
SECTION 1: PROJECT PARTICULARS: Project Title as EU/eTenders Contract Notice: Description as EU/eTenders Contract Notice: Address: Form of Contract: Contractor s Role: Project Category: Areas of work involving
Consolidated I&T Data Centre - P3 Canada Fund
STAFF REPORT ACTION REQUIRED Consolidated I&T Data Centre - P3 Canada Fund Date: January 16, 2012 To: From: Wards: Reference Number: Government Management Committee Deputy City Manager & Chief Financial
The Victorian Public Sector values dictate the way we interact with each other, with our the market and guide the way that we make decisions.
POSITION DESCRIPTION Position Title: Procurement Officer New Position Department: Finance Compliance & Procurement Date: 22/10/2015 Reports to (position): Procurement Manager Grade: 5 Positions that report
Florida Transportation Commission: A Meeting of the Modes
Florida Transportation Commission: A Meeting of the Modes Corridors of the Future: A National and I-95 Corridor Perspective George Schoener, Executive Director I-95 Corridor Coalition February 12, 2007
CONGESTION AND INCIDENT MANGEMENT APPLICATIONS FOR DISTRIBUTED ACOUSTIC SENSING TECHNOLOGY NZTA CASE STUDY
CONGESTION AND INCIDENT MANGEMENT APPLICATIONS FOR DISTRIBUTED ACOUSTIC SENSING TECHNOLOGY NZTA CASE STUDY Authors Russell Pinchen, Senior ITS Engineer, New Zealand Transport Agency, 1 Queen Street, Auckland
New on the Horizon: Revenue recognition for building and construction
NOVEMBER 2011 Building & Construction New on the Horizon: Revenue recognition for building and construction KPMG s Building & Construction practice KPMG s Building & Construction practice provides integrated
Coastal Highway Route E39 Project
Coastal Highway Route E39 Project Teknologidagene 22th September 2015 Trondheim Kjartan J Hove/ Jørn Arve Hasselø/ Harald I. Johnsen Norwegian Public Roads Administration Coastal Highway Route E39 E39
1. RECOMMENDATIONS. It is recommended that:
Clause No. 7 in Report No. 3 of was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on February 20, 2014. (Mayor Hackson declared an interest in this
M8 M73 M74 Motorway Improvements Project
M8 M73 M74 Motorway Improvements Project October 2013 Introduction This major transport infrastructure project will complete and upgrade the M8 and key sections of the M73 and M74 to finalise the motorway
Work Breakdown Structure Element Dictionary Construction
Initiation CON 5.1 Initiation encompasses deliverables associated with the development, implementation and control of the project s schedule, budget and scope, including the solicitation for a contractor
1. BACKGROUND. Terms of Reference. Background
GOVERNMENT OF SAINT VINCENT AND THE GRENADINES Caribbean Regional Communications Infrastructure Project TERMS OF REFERENCE FOR CONSULTING SERVICES For the Design of a National Broadband Network SVG CARCIP
I N BVRG H + Lochend Care Home. I Purpose of report. The Executive of the Council. 31 January 2006
+ D I N BVRG H + THE CITY OF EDINBURGH COUNCIL Lochend Care Home The Executive of the Council 31 January 2006 I Purpose of report 1.I To outline to the Executive the options available to the Council for
Provisional Measures for Construction Project Management
Provisional Measures for Construction Project Management Article 1 Article 2 Purpose and Basis This Provisional Measure is promulgated in accordance with relevant Chinese laws and administrative regulations
Investment projects on PKP Polish Railway Lines network
Railway Kolej of the nowoczesnych new technologies technologii Railway of the new technologies Investment projects on PKP Polish Railway Lines network Warsaw, October 2012 Jacek Poniewierski Director of
E. Specific requirements for innovation procurement (PCP/PPI) supported by Horizon 2020 grants
E. Specific requirements for innovation procurement (PCP/PPI) supported by Horizon 2020 grants The following requirements apply to PCPs and PPIs for which the tender preparation and/or the call for tender
Availability Payment Mechanisms For Transit Projects ADVISORY
Availability Payment Mechanisms For Transit Projects ADVISORY Agenda Availability Payments Overview Structure Financial Implications Case Study Additional Considerations KPMG Infrastructure 2 What is an
REQUEST FOR MAYORAL DECISION MD405. Title: Disaster Recovery Services
REQUEST FOR MAYORAL DECISION MD405 Title: Disaster Recovery Services Executive Summary: In May 2006, the GLA entered into an agreement with a recovery partner to offer immediate replacement IT equipment
BEST PRACTICE GUIDELINES FOR CONTRACTING OUT GOVERNMENT SERVICES
PUMA POLICY BRIEF BEST PRACTICE GUIDELINES FOR CONTRACTING OUT GOVERNMENT SERVICES Contracting out government services is one of the principal markettype mechanisms applied in OECD Member countries. Its
Infrastructure Ontario Borrowing Today for the City of Tomorrow Session #1 Steve Rohacek, Vice President, Municipal Business Development & Lending
Click to edit Master title style Infrastructure Ontario Borrowing Today for the City of Tomorrow Session #1 Steve Rohacek, Vice President, Municipal Business Development & Lending www.infrastructureontario.ca
Becoming Tender Ready
Becoming Tender Ready Difference Between Procurement & Tendering Procurement is the process of acquiring goods, works and services, covering both acquisition from third parties and from in-house providers.
Developing by Public Private Partnership (PPP): Meeting infrastructure needs successfully.
Developing by Public Private Partnership (PPP): Meeting infrastructure needs successfully. Vicky D. Kefala Head, Investments & Development Projects Consolidated Contractors Company (CCC) MBA Finance, BA
PRESIDIO PARKWAY FINANCIAL PROPOSAL 2.1.2. FINANCIAL PROPOSAL EXECUTIVE SUMMARY GOLDEN LINK PARTNERS
2.1.2. EXECUTIVE SUMMARY The Presidio Parkway Project (the Project ) is a landmark transaction in a high profile location and as the Project is the first transportation P3 in the State, its success is
https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework
All interested parties Direct Dial: 020 7901 1849 Email: [email protected] Date: 17 November 2015 Dear Colleague EPC Contract Principles for OFTO Build Tenders This letter provides guidance
TENDER SPECIFICATION DOCUMENT WEST MIDLANDS INTERNATIONAL TRADE LLP MARKETING FILMS ON EXPORTING AND GOVERNMENT SUPPORT 14/15 15/16
TENDER SPECIFICATION DOCUMENT WEST MIDLANDS INTERNATIONAL TRADE LLP MARKETING FILMS ON EXPORTING AND GOVERNMENT SUPPORT 14/15 15/16 Tender for the Supply of Film Production Date: March 2015 West Midlands
Alberta Schools Alternative Procurement (ASAP) Projects. Public School Construction Program September 19, 2011 Baltimore, USA
Alberta Schools Alternative Procurement (ASAP) Projects Public School Construction Program September 19, 2011 Baltimore, USA Presentation Outline P3 s in Alberta - An Overview Alberta Schools (ASAP) Projects
Level Crossing Crash Taxonomy for Connected Vehicle Safety Research
Level Crossing Crash Taxonomy for Connected Vehicle Safety Research Adrian Hellman Systems Safety and Engineering Division August 5, 2014 Volpe The National Transportation Systems Center Advancing transportation
How to write a proposal
How to write a proposal Workshop Innovative space-based solutions for Future Cities July 8-9, 2014 Vienna Rob Postema Telecommunications and Integrated Applications Directorate European Space Agency ESA
Public Private Partnership (PPP) Review
2013 Public Private Partnership (PPP) Review Public Private Partnership (PPP) Review Photo on the cover: Finnish Transport Agency Online publication (pdf) (www.liikennevirasto.fi) ISBN 978-952-255-388-1
Request for Proposals for consulting services: Independent review of the ICANN Address Supporting Organization (ASO)
Request for Proposals for consulting services: Independent review of the ICANN Address Supporting Organization (ASO) Deadline for applications: 31-January-2011 ASO review ToR Page 1/10 1 Instructions to
Public Private Partnership in Hospitals
Public Private Partnership in Hospitals Presentation to the International Health Seminar Brazil - Canada October 20, 2010 2008 The Canadian Council for Public-Private Partnerships Overview Healthcare in
Gary Cooke, Cabinet Member for Corporate and Democratic Services
From: To: Decision No: Subject: Classification: Gary Cooke, Cabinet Member for Corporate and Democratic Services The Property Sub Committee N/A Total Facilities Management 2 nd Biannual Review Unrestricted
Supplier Performance Management Program. CEA Edmonton Buildings Committee November 13, 2012
Supplier Performance Management Program CEA Edmonton Buildings Committee November 13, 2012 Supplier Performance Management Program - Background Consulting Services Review (Dec 14, 2009): The Office of
Contract management: renewal and transition. Report to Parliament 10 : 2013 14
Contract management: renewal and transition Report to Parliament 10 : 2013 14 Queensland Audit Office Location Level 14, 53 Albert Street, Brisbane Qld 4000 PO Box 15396, City East Qld 4002 Telephone (07)
Tender to Develop Guidelines for Cruise Terminal Investment, Planning and Design
Tender to Develop Guidelines for Cruise Terminal Investment, Planning and Design Release Date: September 14 th, 2015 Deadline for Submissions: November 6 th, 2015 Opening Date: November 11 th, 2015 Final
INVITATION FOR LIMITED TENDER FOR SUPPLY OF TECHNICAL MANPOWER
INVITATION FOR LIMITED TENDER FOR SUPPLY OF TECHNICAL MANPOWER Sealed tenders are hereby invited in two separate sealed covers (Technical and Commercial offers) from eligible registered manpower supplier
Ministry of Information and Communication Technology EXPRESSION OF INTEREST
EXPRESSION OF INTEREST Consultancy Services for SubmarineFibre Optic Connectivity in Rodrigues (Authorised under Section 24(2) of the Public Procurement Act 2006) Reference No. : MICT/Q3/2012/EOI 1.0 Introduction
E. Specific requirements for innovation procurement (PCP/PPI) supported by Horizon 2020 grants
E. Specific requirements for innovation procurement (PCP/PPI) supported by Horizon 2020 grants This annex applies to PCPs and PPIs for which the tender preparation and/or the call for tender implementation
Role and Use of Advisers. in preparing and implementing PPP projects
European PPP Expertise Centre European PPP Expertise Centre European PPP Expertise Centre European PPP Expertise Centre in preparing and implementing PPP projects in preparing and implementing PPP projects