1 Alberta Schools Alternative Procurement (ASAP) Projects Public School Construction Program September 19, 2011 Baltimore, USA

2 Presentation Outline P3 s in Alberta - An Overview Alberta Schools (ASAP) Projects P3 Procurement and Process Best Practices in Alberta P3

3 P3 s in Alberta - An Overview Alberta defines P3 s as: An infrastructure project in which a private contractor: - Provides some or all of the financing for the project; - Designs and builds the project, often providing operations and maintenance for the project, and often backed by an extended warranty ; and - Receives payments from the government over an extended period of time, subject to deductions for failing to meet contractually defined performance standards

4 P3s in Alberta - An Overview Manage Project Program Plan Design Build Maintain Program Delivery Facility Management Services P3 Procurement Finance Project Own Building Own Land Manage Project Traditional Procurement Program Plan Design Build Maintain Finance Project Own Building Program Delivery Facility Management Services Own Land Public sector Private partner

5 P3s in Alberta - An Overview A Typical P3 Arrangement Province Availability Payments Capital Contribution Concession Agreement P3 Contractor Subcontractors Investment Payments Private Finance Design Build Operate/ Maintain

6 P3 Characteristics Integrated, whole-life approach to design, construction and maintenance of a facility Demonstrate Value for Money (VfM) Cost Certainty (fixed price for construction) Schedule Certainty (fixed term for construction) Contract period Warranty of 30 years (long-term maintenance) Determine facility performance through output specifications Risk-sharing between private and public sectors

7 P3 Projects in Alberta Constructed and operational - Anthony Henday South East (Edmonton) - North East Stoney Trail (Calgary) - ASAP I - 18 schools (Calgary and Edmonton) Under construction - Anthony Henday North West (Edmonton) - ASAP II - 14 schools (Edmonton, Calgary & surrounding areas) - South East Stoney Trail (Calgary) In procurement - Anthony Henday North East (Edmonton) - ASAP III - 13 schools (across Alberta) - Evan-Thomas Water & Waste Water Treatment Plant (Kananaskis Country)

8 Potential P3 Projects P3 projects that could be considered: - Remaining ring road segments in Calgary and Edmonton. (NE Anthony Henday in procurement) - Water/wastewater Treatment Plant. (Evan-Thomas project in procurement) - Additional social infrastructure such as health care facilities, post-secondary institutions, government buildings

9 Alberta Schools Alternative Procurement Eighteen Schools ASAP I K-4, K-6, and 2 types of K-9 Schools (DBFM) Four School Boards ASAP II Fourteen Schools K-6, 5-9, K-9 (DBFM) and 4 high schools (Design-Build) Eight School Boards Two Municipalities (Edmonton, Calgary) Six Municipalities (Edmonton, Calgary, Sherwood Park, Spruce Grove, Okotoks, Langdon)

10 ASAP III

11 ASAP Projects Consolidated approach to designing, building, financing and maintaining (DBFM) new schools Schools designed using a core design with modular classrooms LEEDTM Silver standard for all schools Project includes 30 year maintenance and renewal (M&R) component

12 Ownership and Access New schools owned and operated by school boards. Private sector will not own or lease schools there will be no 3rd party revenue. Use and access to new schools will be the same as existing schools. School boards will provide: Educational programming Furniture and equipment (supply and install) ICT cabling maintenance

13 Contract Highlights GoA runs transaction process in collaboration with School Boards GoA signs contract Payments made by GoA Performance adjustments monitored by School Boards Turn over provisions at end of term

14 Transaction Process Open, competitive, transparent process. Invite consortia to submit their qualifications (RFQ). Short list to 3 consortia. Invite short-listed teams to submit detailed proposals (RFP). Staged technical submissions during RFP. Legal agreement terms and conditions optimized during RFP. Opportunity for innovation in design during RFP. If proponent passes all stages then submit fully-priced bid. Contract awarded on basis of lowest NPV bid only. No negotiation after award.

15 Maintenance & Renewal Features 30-year life-cycle maintenance: 5 year building evaluation year 25 evaluation to include renewal plan to attain a 30 year old school in good condition Custodial services remain responsibility of school board: cleaning operational support (moving desks, etc.) monitoring boiler cycles scheduling fans

16 Private Financing Payments to contractor (over the 30-year contract) depend on availability and performance If contractor does not perform province cannot pay lender Size of project attractive to institutional investors Investors provide oversight to protect their money

17 Value for Money By constructing a large number of schools at once cost per school is lower Design efficiencies from core school approach Cost and supply chain management by using single consortium Accelerated construction schedule Provide schools where the students live and learn

18 Value for Money PROJECT PSC NPV Bid NPV VFM NEST (2006 $) $ B $650 M $350 M NW AHD (2008 $) $1.6 B $1.4 B $200 M ASAP I (2008 $) $752 M $634 M $97 M ASAP II (2010 $) $358 M $253 M $105 M Compare bids to a Public Sector Comparator, or PSC (cost estimate to deliver using traditional process) to calculate VFM All risks must be accounted (some risks were missed in the SE AHD PSC) Includes design, construction and O&M/Rehab for the next 30 years on net present value (NPV) basis

19 ASAP I - Today Project completed on-schedule Positive feedback from the industry and contractor Minimal changes during construction Schools with early availability were allowed to have school board F&E work started Quality of schools is very good by all reports Contaminated site required compensation for clean-up and acceleration to meet availability

20 ASAP I - Modular installation

21 ASAP I - Our new Schools

22 ASAP II - Today Project to be completed on-schedule Schools will open in September 2012 Very few issues or problems

23 Alberta s Best Practices for P3s Maintain lowest compliant NPV bid wins approach as being fair, simple and transparent Negotiate project agreement upfront - no changes after financial bid submission Allow complete flexibility with financing - provided team has demonstrated capacity, we leave process up to proponents Bundle social infrastructure assets to generate effective economies of scale Assign risk to those who can best manage it Keep technical requirements to maintain standards, but welcome innovation where it makes sense.

24 Concluding Comments P3s not a panacea for all projects P3s complement conventional and other delivery methods Made in Alberta P3s can provide value to Albertans for the right type of projects Social infrastructure offers many interesting challenges and opportunities ASAP approach achieves GoA and Board objectives and delivers value

25

P3 Value for Money Assessment and Project Report. Evan Thomas Water and Wastewater Treatment Facility Project

P3 Value for Money Assessment and Project Report. Evan Thomas Water and Wastewater Treatment Facility Project P3 Value for Money Assessment and Project Report Evan Thomas Water and Wastewater Treatment Facility Project July 2013 Table of Contents 1. Summary: Using a P3 for a Water Treatment Plant - did it work?

More information

Consolidated I&T Data Centre - P3 Canada Fund

Consolidated I&T Data Centre - P3 Canada Fund STAFF REPORT ACTION REQUIRED Consolidated I&T Data Centre - P3 Canada Fund Date: January 16, 2012 To: From: Wards: Reference Number: Government Management Committee Deputy City Manager & Chief Financial

More information

What is Alternate Delivery?

What is Alternate Delivery? What is Alternate Delivery? Hans VanPoorten, MBA, P.Eng. Vice President Advisory Services CSVA Conference, 2011 Presentation Contents P3 History, Market and MMM Credentials Process Typical P3 Infrastructure

More information

Public Health Services - The Cost of Doing Data Centre Project in Ontario, Canada

Public Health Services - The Cost of Doing Data Centre Project in Ontario, Canada VALUE FOR MONEY ASSESSMENT MINISTRY OF GOVERNMENT SERVICES NEW DATA CENTRE - PAGE 1 - - PAGE 2 - - PAGE 3 - - PAGE 4 - Table of Contents Summary...6 Project description...8 Competitive selection process

More information

Alberta Infrastructure and Transportation. Management Framework:

Alberta Infrastructure and Transportation. Management Framework: P3 Public Private Partnerships Alberta Infrastructure and Transportation Management Framework: Assessment Process September 2006 Table of Contents P3Public Private Partnerships Section 1 Introduction...1

More information

Infrastructure Ontario Borrowing Today for the City of Tomorrow Session #1 Steve Rohacek, Vice President, Municipal Business Development & Lending

Infrastructure Ontario Borrowing Today for the City of Tomorrow Session #1 Steve Rohacek, Vice President, Municipal Business Development & Lending Click to edit Master title style Infrastructure Ontario Borrowing Today for the City of Tomorrow Session #1 Steve Rohacek, Vice President, Municipal Business Development & Lending www.infrastructureontario.ca

More information

Business Case. Ottawa Public Library Main Library Facility May 2015

Business Case. Ottawa Public Library Main Library Facility May 2015 Business Case Ottawa Public Library Main Library Facility May 2015 The information contained in this document is proprietary to the Ottawa Public Library and the City of Ottawa. Unauthorized distribution

More information

MARKHAM STOUFFVILLE HOSPITAL EXPANSION AND REDEVELOPMENT PROJECT

MARKHAM STOUFFVILLE HOSPITAL EXPANSION AND REDEVELOPMENT PROJECT Insert VFM letter VALUE FOR MONEY ASSESSMENT MARKHAM STOUFFVILLE HOSPITAL EXPANSION AND REDEVELOPMENT PROJECT - PAGE 1 - - PAGE 2 - - PAGE 3 - - PAGE 4 - Markham Stouffville Hospital Artist s Rendering

More information

Public Private Partnerships

Public Private Partnerships Office of the Comptroller General Practice Guideline 1 Public Private Partnerships Ministry of Finance May 2009 I. INTRODUCTION... 3 II. THE SUBSTANCE OF THE ARRANGEMENT... 7 III. FUNDING ANALYSIS... 9

More information

Risk Management in the Development of a Penta-P Project

Risk Management in the Development of a Penta-P Project Risk Management in the Development of a Penta-P Project Bill Van Meter Regional Transportation District Denver, CO Julie Skeen Jacobs Engineering Denver, CO Damian Carey Jacobs Engineering Denver, CO Don

More information

December 2015. Project Report. Stanton Territorial Hospital 20567651.3

December 2015. Project Report. Stanton Territorial Hospital 20567651.3 Project Report Stanton Territorial Hospital December 2015 1 Purpose of this project report The purpose of this project report ( Project Report ) is to provide key information to the public about the Stanton

More information

REQUEST FOR PROPOSAL SPECTATOR FACILITY FEASIBILITY STUDY ADDENDUM NO. 1

REQUEST FOR PROPOSAL SPECTATOR FACILITY FEASIBILITY STUDY ADDENDUM NO. 1 Financial Management Services Purchasing Division Request for Proposal Spectator Facility Feasibility Study REQUEST FOR PROPOSAL FOR A SPECTATOR FACILITY FEASIBILITY STUDY ADDENDUM NO. 1 This addendum

More information

CAPITAL PLAN G CAPITAL PLAN SPENDING G CAPITAL PLAN FINANCING

CAPITAL PLAN G CAPITAL PLAN SPENDING G CAPITAL PLAN FINANCING CAPITAL PLAN G CAPITAL PLAN SPENDING G CAPITAL PLAN FINANCING 59 TABLE OF CONTENTS. CAPITAL PLAN Capital Plan Spending Capital Plan 2013 16... 63 Investing in Families and Communities... 65 Securing Alberta

More information

RBRC Combo Project Request for Qualifications Additional Information and Clarifications #1. RFQ No. 1708.057. Issued: March 9, 2011

RBRC Combo Project Request for Qualifications Additional Information and Clarifications #1. RFQ No. 1708.057. Issued: March 9, 2011 REQUEST FOR QUALIFICATIONS ROBERTS BANK RAIL CORRIDOR PROGRAM 192 ND STREET, 54 TH AVE., 196 TH STREET COMBO PROJECT RFQ No. 1708.057 ADDITIONAL INFORMATION AND CLARIFICATIONS NO. 1 Issued: March 9, 2011

More information

Request for Proposal. 2016 Salary/Benefits and Staff Reward & Recognition Survey

Request for Proposal. 2016 Salary/Benefits and Staff Reward & Recognition Survey Request for Proposal 2016 Salary/Benefits and Staff Reward & Recognition Survey November 2, 2015 Contents Purpose... 2 College of Physicians & Surgeons of Alberta... 2 Our Organization... 2 Our Vision...

More information

3.05. Infrastructure Ontario Alternative Financing and Procurement. Chapter 3 Section. Background. Alternative Financing and Procurement

3.05. Infrastructure Ontario Alternative Financing and Procurement. Chapter 3 Section. Background. Alternative Financing and Procurement Chapter 3 Section 3.05 Infrastructure Ontario Alternative Financing and Procurement Background Alternative Financing and Procurement Alternative Financing and Procurement (AFP) is the name given to the

More information

The Opportunities and Benefits of Partnerships with the Private Sector. Presentation to: Town of Richmond Hill Council Nov 4, 2015

The Opportunities and Benefits of Partnerships with the Private Sector. Presentation to: Town of Richmond Hill Council Nov 4, 2015 The Opportunities and Benefits of Partnerships with the Private Sector Presentation to: Town of Richmond Hill Council Nov 4, 2015 www.infrastructureontario.ca 1 About Infrastructure Ontario www.infrastructureontario.ca

More information

Consultant Selection Policy for Building Infrastructure Consulting Services (Effective April 1, 2007)

Consultant Selection Policy for Building Infrastructure Consulting Services (Effective April 1, 2007) Consultant Selection Policy for Building Infrastructure Consulting Services (Effective April 1, 2007) 1.0 SCOPE This policy applies to the procurement of consulting services contracted directly by the

More information

PPP GLOSSARY. Availability. Base Case. Bidder BOOT BOT. Business Case. Commercial Operations Date (COD) Concession

PPP GLOSSARY. Availability. Base Case. Bidder BOOT BOT. Business Case. Commercial Operations Date (COD) Concession PPP GLOSSARY Availability Base Case Bidder Bond BOOT BOT Term Business Case Capex Commercial Operations Date (COD) Concession Meaning The period when the facility (or the relevant part thereof) is able

More information

1. Evolution of infrastructure procurement in NSW. 2. Market consultation and outcomes. 3. Response and implementation. 4. Project Deed Evolution

1. Evolution of infrastructure procurement in NSW. 2. Market consultation and outcomes. 3. Response and implementation. 4. Project Deed Evolution Reducing Bid Costs for Outcome-Based Procurements in NSW Infrastructure and Structured Finance Unit: Partnering to Create Partnerships December 2015 1. Evolution of infrastructure procurement in NSW 2.

More information

Public-Private Partnerships Forum PPP Law, Structures and Contracting

Public-Private Partnerships Forum PPP Law, Structures and Contracting Public-Private Partnerships Forum PPP Law, Structures and Contracting AGC California Fall Conference 2010 Hyatt Grand Champions, Indian Wells November 4, 2010 MAKING IT HAPPEN. Overview California PPP

More information

SCHEDULE 4 CONTRACTOR S MANAGEMENT SYSTEMS AND PLANS

SCHEDULE 4 CONTRACTOR S MANAGEMENT SYSTEMS AND PLANS SCHEDULE 4 CONTRACTOR S MANAGEMENT SYSTEMS AND PLANS 1. GENERAL 1.1 Capitalized Terms Capitalized terms used in this Schedule that are the same as the capitalized terms used in the Agreement to Design,

More information

UNIVERSITY HOSPITAL POLICY

UNIVERSITY HOSPITAL POLICY UNIVERSITY HOSPITAL POLICY SUBJECT: PURCHASING SERVICES TITLE: PURCHASING PROCESS Responsible Executive: Executive Director, Supply Chain Management Responsible Office: Supply Chain Management CODING:

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL REQUEST FOR PROPOSAL General Insurance Brokerage Services Date of Issue: December 6, 2012 Closing Location:Prince Rupert, B.C. Mail or courier: Dan Rodin Chief Financial Officer City of Prince Rupert 424-3

More information

REQUEST FOR QUALIFICATIONS for SURREY PRETRIAL SERVICES CENTRE EXPANSION PROJECT RFQ #3225 VOLUME 1 PROJECT BRIEF

REQUEST FOR QUALIFICATIONS for SURREY PRETRIAL SERVICES CENTRE EXPANSION PROJECT RFQ #3225 VOLUME 1 PROJECT BRIEF Ministry of Public Safety and Solicitor General Ministry of Citizens Services Shared Services BC REQUEST FOR QUALIFICATIONS for SURREY PRETRIAL SERVICES CENTRE EXPANSION PROJECT RFQ #3225 VOLUME 1 PROJECT

More information

Public/Private Partnerships and the Public Procurement Process

Public/Private Partnerships and the Public Procurement Process ELEVATING OUR PROFESSIONALISM 48 TH ANNUAL CONFERENCE MAY 17-20, 2015 ORLANDO, FLORIDA Public/Private Partnerships and the Public Procurement Process By Roman Martinez, MPA, CPPO, CPPB DEFINITION OF P3S

More information

INTRODUCTION TO PUBLIC-PRIVATE PARTNERSHIPS

INTRODUCTION TO PUBLIC-PRIVATE PARTNERSHIPS INTRODUCTION TO PUBLIC-PRIVATE PARTNERSHIPS WITH AVAILABILITY PAYMENTS Dr. Silviu Dochia, Senior Associate Michael Parker, Managing Director SUMMARY Public-private partnerships ( P3s ) can provide the

More information

Contract Management The Mavericks Won t Like This!

Contract Management The Mavericks Won t Like This! Contract Management The Mavericks Won t Like This! Keith Wallis How Much Did That Project Cost? Real Life Example Original contract amount $500K Variations scope changes not visible Total variations =

More information

TOWN OF BERLIN REQUEST FOR QUALIFICATIONS

TOWN OF BERLIN REQUEST FOR QUALIFICATIONS TOWN OF BERLIN REQUEST FOR QUALIFICATIONS Notice is hereby given that qualifications will be received by the Town of Berlin, Maryland for: RFQ # 2015 4 Community Solar Garden: Design, Build, Finance, Operate

More information

Bonding P3 Projects. Frequently Asked Questions about P3s and Bonding

Bonding P3 Projects. Frequently Asked Questions about P3s and Bonding Bonding P3 Projects Government entities in the United States have understood the importance of surety bonds and have required bonds for over a century to provide performance and payment assurance for the

More information

Region of Waterloo Finance Department Financial Services and Development Financing

Region of Waterloo Finance Department Financial Services and Development Financing Region of Waterloo Finance Department Financial Services and Development Financing To: Chair Jim Wideman and Members of the Planning and Works Committee Date: May 27, 2014 File Code: T16-01 Subject: Stage

More information

PRE-QUALIFIED RESOURCE LISTS Frequently Asked Questions

PRE-QUALIFIED RESOURCE LISTS Frequently Asked Questions PRE-QUALIFIED RESOURCE LISTS Frequently Asked Questions Human Services PQRs Q1: What is a PQR? A: PQR stands for Pre-Qualified Resource List of pre-qualified service providers. The primary objective of

More information

Request for Proposal. MPAO Data Center Virtualization

Request for Proposal. MPAO Data Center Virtualization Request for Proposal MPAO Data Center Virtualization Maldives Pension Administration Office (MPAO) is accepting bids for supply, installation, configuration and Support for MPAO Data Center Virtualization.

More information

How to do Business with the London. Borough of Sutton

How to do Business with the London. Borough of Sutton How to do Business with the London Borough of Sutton February 2013 1 About this guide This guide has been developed to assist businesses wishing to sell their goods and services to the Borough. Contents

More information

Value for Money Assessment for Public-Private Partnerships: A Primer. December 2012

Value for Money Assessment for Public-Private Partnerships: A Primer. December 2012 Value for Money Assessment for Public-Private Partnerships: A Primer December 2012 Table of Contents 1 Introduction... 1-1 What are Public-Private Partnerships?... 1-1 Using Value for Money Analysis to

More information

Financing Renewable Energy in New Jersey

Financing Renewable Energy in New Jersey Financing Renewable Energy in New Jersey Renewable Energy Procurement Workshop Sustainable Jersey and the Atlantic County Utilities Authority Presenters Douglas J. Bacher, Managing Director Dianna C. Geist,

More information

REQUEST FOR EXPRESSIONS OF INTEREST 4643 EOI

REQUEST FOR EXPRESSIONS OF INTEREST 4643 EOI 4643 EOI REQUEST FOR EXPRESSIONS OF INTEREST 4643 EOI 4643 EOI - FUNCTIONAL CONSULTANT TO LEAD THE IMPLEMENTATION OF THE PURCHASE REQUISITION MODULE IN THE PEOPLESOFT 9.0 FINANCIALS AND SUPPLY CHAIN PRODUCT.

More information

SCHOOL CAPITAL MANUAL March 2015

SCHOOL CAPITAL MANUAL March 2015 SCHOOL CAPITAL MANUAL March 2015 Contact Us Alberta Education www.education.alberta.ca Program and System Support Division Capital Planning 7 th floor, 10155 102 Street Edmonton, AB T5J 4L5 Telephone:

More information

Massachusetts Public-Private Partnership Infrastructure Oversight Commission Introduction to Public-Private Partnerships

Massachusetts Public-Private Partnership Infrastructure Oversight Commission Introduction to Public-Private Partnerships Massachusetts Public-Private Partnership Infrastructure Oversight Commission Introduction to Public-Private Partnerships May 29, 2013 Introduction With you today from KPMG Years of Experience: 30+ Tim

More information

REQUEST FOR QUALIFICATIONS: Professional Engineering Services For Water Treatment Plant Filter Replacement or Rehab

REQUEST FOR QUALIFICATIONS: Professional Engineering Services For Water Treatment Plant Filter Replacement or Rehab Department of Utilities 504 N. Queen Street Palestine, Texas 75801 (903)731-8423 Fax (903)723-2953 REQUEST FOR QUALIFICATIONS: Professional Engineering Services For Water Treatment Plant Filter Replacement

More information

Programme Manager/Procurement Specialist. Suva. Capital Works Manager. As soon as possible. As follows

Programme Manager/Procurement Specialist. Suva. Capital Works Manager. As soon as possible. As follows JOB DESCRIPTION Position: Location of position: Reporting to: Special functional relationships: Term of Appointment: Programme Manager/Procurement Specialist Suva Capital Works Manager Capital Works Programme

More information

Project Brief Emily Carr University of Art + Design Campus Redevelopment Project

Project Brief Emily Carr University of Art + Design Campus Redevelopment Project Emily Carr University of Art + Design Campus Redevelopment Project March 7, 2013 Page i TABLE OF CONTENTS 1 INTRODUCTION... 1 1.1 Purpose of this... 1 2 THE BUSINESS OPPORTUNITY... 2 3 THE PROJECT... 3

More information

Project Implementation: Procurement & Contract Management. April 2012

Project Implementation: Procurement & Contract Management. April 2012 & Contract Management April 2012 & Contract Management We would like to acknowledge the contribution of the Programme Management Department in the preparation of this presentation that will introduce some

More information

How to do Business with the Province of British Columbia

How to do Business with the Province of British Columbia How to do Business with the Province of British Columbia Every year, the B.C. Government buys a wide range of goods and services from businesses of all sizes and types. Your business could be one of them.

More information

School Construction Projects

School Construction Projects The process of educating young people seems to be continually developing. New insights regarding how students most effectively receive retain and gain understanding of information and principles affect

More information

STRUCTURING AND MANAGING CONSTRUCTION RISKS IN PUBLIC PRIVATE PARTNERSHIPS

STRUCTURING AND MANAGING CONSTRUCTION RISKS IN PUBLIC PRIVATE PARTNERSHIPS STRUCTURING AND MANAGING CONSTRUCTION RISKS IN PUBLIC PRIVATE PARTNERSHIPS BY: TIMOTHY J. MURPHY PARTNER MCMILLAN LLP - 2 - STRUCTURING AND MANAGING CONSTRUCTION RISKS IN PUBLIC PRIVATE PARTNERSHIPS Introduction

More information

Public Private Partnership in Hospitals

Public Private Partnership in Hospitals Public Private Partnership in Hospitals Presentation to the International Health Seminar Brazil - Canada October 20, 2010 2008 The Canadian Council for Public-Private Partnerships Overview Healthcare in

More information

LONDON HEALTH SCIENCES CENTRE AND ST. JOSEPH S HEALTH CARE, LONDON (Phase 2) REDEVELOPMENT PROJECTS

LONDON HEALTH SCIENCES CENTRE AND ST. JOSEPH S HEALTH CARE, LONDON (Phase 2) REDEVELOPMENT PROJECTS VALUE FOR MONEY ASSESSMENT LONDON HEALTH SCIENCES CENTRE AND ST. JOSEPH S HEALTH CARE, LONDON (Phase 2) REDEVELOPMENT PROJECTS - PAGE 1 - - PAGE 2 - - PAGE 3 - - PAGE 4 - - PAGE 5 - - PAGE 6 - - PAGE 7

More information

Position Title - Procurement Professional

Position Title - Procurement Professional Employment Type Permanent - Full Time Reference Code 15-EXT-02-331 Location Administration Centre - Midhurst Closing Date 06/04/2015 Position Title - Procurement Professional Position Summary With a focus

More information

Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education

Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education EMAIL contact@fosterinfrastructure.com WEB www.fosterinfrastructure.com Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education

More information

Procurement Processes and Tools

Procurement Processes and Tools Methods of Procurement Purchasing Activities Procurement Processes and Tools There are different methods of procurement, which are utilized to acquire goods or services. There are many factors which determine

More information

PUBLIC PRIVATE PARTNERSHIP HANDBOOK

PUBLIC PRIVATE PARTNERSHIP HANDBOOK PUBLIC PRIVATE PARTNERSHIP HANDBOOK VERSION 2 March 2012 1 CONTENTS Section 1: Introduction to Public Private Partnerships... 3 1.1 What is Public Private Partnership?... 4 1.2 Typical PPP Delivery Models...

More information

City of Calgary Prequalification For Prime Contractor. January 17, 2012

City of Calgary Prequalification For Prime Contractor. January 17, 2012 City of Calgary Prequalification For Prime Contractor January 17, 2012 Presenters Andrew Mardon, Manager, Supply Management, Finance & Supply Jim Nicholson, Procurement Coordinator, Finance & Supply, Strategic

More information

Solar Proposal Evaluation Report. Jackson Township Municipal Utilities Authority Renewable Energy Program Proposals of August 4, 2011

Solar Proposal Evaluation Report. Jackson Township Municipal Utilities Authority Renewable Energy Program Proposals of August 4, 2011 Solar Proposal Evaluation Report Jackson Township Municipal Utilities Authority Renewable Energy Program Proposals of August 4, 2011 Prepared for Jackson Township Municipal Utilities Authority Prepared

More information

How To Write An Integrated Construction Project

How To Write An Integrated Construction Project GUIDANCE FOR ENGINEERING CONSULTANCY FIRMS INTEGRATED CONTRACTS PREFACE Our industry is facing new integrated business models with increasing frequency. The processes driving these models are very different

More information

Learning From Experience. Why and How PPP s Work. George A. Tapas, PE, SE URS Corporation. The Value of Public-Private Partnerships:

Learning From Experience. Why and How PPP s Work. George A. Tapas, PE, SE URS Corporation. The Value of Public-Private Partnerships: THE VALUE OF PUBLIC PRIVATE PRIVATE PARTNERSHIPS: LEARNING FROM EXPERIENCE Panel II: Managing Public Private Partnerships; Design, Build, Finance, Operate and Maintain; Why and How PPP s Work George A.

More information

Non-Merchant Independent Power Projects: An Excellent Source of Yield and Duration for a De-risking Strategy

Non-Merchant Independent Power Projects: An Excellent Source of Yield and Duration for a De-risking Strategy Non-Merchant Independent Power Projects: An Excellent Source of Yield and Duration for a De-risking Strategy Louis Bélanger, CFA, FRM Managing Director, Stonebridge Infrastructure Debt Fund The Stonebridge

More information

Crown corporation responsible for building, managing, financing, and enhancing the value of Ontario public assets

Crown corporation responsible for building, managing, financing, and enhancing the value of Ontario public assets BSE/CSCE Engineers Conference Nassau, Bahamas Jeffrey Plant MBA, P.Eng., PMP, CVS, CQA Vice President Civil Infrastructure October 31, 2014 1 Infrastructure Ontario (IO) Crown corporation responsible for

More information

Introduction from the Chair - Michael Burnett

Introduction from the Chair - Michael Burnett OECD International Transport Forum Roundtable: Public-Private Partnerships for Transport Infrastructure Renegotiations - How to approach them and economic outcomes, George Mason University, Washington

More information

SCHEDULE 11 INSURANCE REQUIREMENTS

SCHEDULE 11 INSURANCE REQUIREMENTS SCHEDULE 11 INSURANCE REQUIREMENTS 1. GENERAL 1.1 Capitalized Terms Capitalized terms used in this Schedule have the definitions as set out in the Agreement to Design, Build, Finance and Maintain Three

More information

Annual Meeting of Senior PPP Officials 2010

Annual Meeting of Senior PPP Officials 2010 Paris _ 12th of April 2010 PPP Risk Pricing PPPs Vs Traditional Procurement PPPs Strengths PPPs around the World Best PPPs Practices PPP Risk Pricing DESIGN DIFFERENT PPP DELIVERY MODELS BOT BUILD FINANCE

More information

Page 97. Executive Head of Asset Planning, Management and Capital Delivery

Page 97. Executive Head of Asset Planning, Management and Capital Delivery Page 97 Agenda Item 7 Report to: Strategy and Resources Committee Date: 16 December 2013 Report of: Executive Head of Asset Planning, Management and Capital Delivery Ward Location: Not applicable Author

More information

Hosted VoIP RFP. Subject

Hosted VoIP RFP. Subject Hosted VoIP RFP Subject RFP-For a 3 year contract, the North Bolivar Consolidated School District desires implement hosted VoIP services. The North Bolivar Consolidated School District wishes to evaluate

More information

Vancouver Island Strata Owners Association in cooperation with Unity Services Corporation. Strata Maintenance & Procurement: A Directed Approach

Vancouver Island Strata Owners Association in cooperation with Unity Services Corporation. Strata Maintenance & Procurement: A Directed Approach Vancouver Island Strata Owners Association in cooperation with Unity Services Corporation Strata Maintenance & Procurement: A Directed Approach Welcome We re going to cover a lot today Setting Standards

More information

MINISTRY OF EDUCATION AND SASKBUILDS SASKATCHEWAN JOINT-USE SCHOOLS PROJECT PROJECT #2

MINISTRY OF EDUCATION AND SASKBUILDS SASKATCHEWAN JOINT-USE SCHOOLS PROJECT PROJECT #2 June 5, 2015 MINISTRY OF EDUCATION AND SASKBUILDS SASKATCHEWAN JOINT-USE SCHOOLS PROJECT PROJECT #2 FINAL REPORT OF THE FAIRNESS ADVISOR ON THE PROCUREMENT PROCESS: RFP STAGE TO: STEERING COMMITTEE, SASKATCHEWAN

More information

Capital Improvement Program: Tracking Transportation Project Completion

Capital Improvement Program: Tracking Transportation Project Completion : Tracking Transportation Project Completion March 20, 2009 Principles Require Data-Driven Performance Promote Strategic Governance Increase Government Transparency Foster a Culture of Accountability 2

More information

Chapter 14 Special Report for the Public Accounts Committee Evergreen and Wackenhut Leases

Chapter 14 Special Report for the Public Accounts Committee Evergreen and Wackenhut Leases Special Report for the Public Accounts Committee Evergreen and Wackenhut Leases Contents Background.............................................................. 183 Scope...................................................................

More information

Closing Location: AAMDC 2510 Sparrow Drive Nisku, Alberta T9N 8N5 cindy.carstairs@aamdc.com

Closing Location: AAMDC 2510 Sparrow Drive Nisku, Alberta T9N 8N5 cindy.carstairs@aamdc.com Request for Proposal (RFP) Online Registration System Contract for AAMDC s Convention Events Closing Date & Time: Friday, August 8, 2014 at 4:30 pm MDT One (1) electronic copy of response in Word or PDF

More information

STAFF REPORT. March 12, 2003. Works Committee. Commissioner, Works and Emergency Services Chief Financial Officer and Treasurer

STAFF REPORT. March 12, 2003. Works Committee. Commissioner, Works and Emergency Services Chief Financial Officer and Treasurer STAFF REPORT March 12, 2003 To: From: Subject: Works Committee Commissioner, Works and Emergency Services Chief Financial Officer and Treasurer Source Separated Organic Waste Processing Services Request

More information

Carlsbad Springs Solar Project

Carlsbad Springs Solar Project Date: July 16, 2015 Qualified Applicant: Invenergy LLC 120 Front Street East, Suite 201 Toronto, ON M5A 4L9 Registered Proponent: Carlsbad Springs Solar Energy Partnership Email: carlsbadspringssolarinfo@invenergyllc.com

More information

City of Gardner Electric, Water and Wastewater Utilities. Request for Information (RFI) 1. Purpose of Request

City of Gardner Electric, Water and Wastewater Utilities. Request for Information (RFI) 1. Purpose of Request City of Gardner Electric, Water and Wastewater Utilities Request for Information (RFI) 1. Purpose of Request The City of Gardner ( City ), faces challenges related to maintaining its basic infrastructure,

More information

Pendleton Solar Energy Centre COMMUNITY ENGAGEMENT PLAN

Pendleton Solar Energy Centre COMMUNITY ENGAGEMENT PLAN Pendleton Solar Energy Centre COMMUNITY ENGAGEMENT PLAN Large Renewable Procurement (LRP) I PENDLETON SOLAR ENERGY CENTRE 844.553-3336 PendletonSolar@edf-en.ca www.pendletonsolar.ca Table of Contents 1.

More information

CITY OF KALAMA REQUEST FOR QUALIFICATIONS ARCHITECTURAL SERVICES. Proposal Due Date: April 13, 2016

CITY OF KALAMA REQUEST FOR QUALIFICATIONS ARCHITECTURAL SERVICES. Proposal Due Date: April 13, 2016 CITY OF KALAMA REQUEST FOR QUALIFICATIONS ARCHITECTURAL SERVICES Proposal Due Date: April 13, 2016 The City of Kalama (CITY) invites proposals for the services of a registered architect and their team

More information

Procurement Guidelines for Non-Profit Housing

Procurement Guidelines for Non-Profit Housing Procurement Guidelines for Non-Profit Housing July 2013 Table of Contents PART 1 INTRODUCTION... 1 1.1 Objectives... 1 1.2 How to Use... 1 PART 2 WORKING WITH BC HOUSING... 3 2.1 Key Stakeholders... 3

More information

Request for Proposals Erate Category 1 Hosted VoIP Service Hinds County School District

Request for Proposals Erate Category 1 Hosted VoIP Service Hinds County School District Request for Proposals Erate Category 1 Hosted VoIP Service Hinds County School District Notice to Bidders Notice is hereby given to interested bidders that the Hinds County School District will receive

More information

The City of Warrensburg, Missouri REQUEST FOR PROPOSAL INTERNET SERVICE PROVIDER

The City of Warrensburg, Missouri REQUEST FOR PROPOSAL INTERNET SERVICE PROVIDER The City of Warrensburg, Missouri REQUEST FOR PROPOSAL INTERNET SERVICE PROVIDER Warrensburg, Missouri is located on U.S. 50 Highway at Missouri 13 Highway approximately 45 minutes from the Kansas City

More information

REQUEST FOR PROPOSALS For. Kelowna and Vernon Hospitals Project

REQUEST FOR PROPOSALS For. Kelowna and Vernon Hospitals Project REQUEST FOR PROPOSALS For The Kelowna and Vernon Hospitals Project VOLUME 2 of 4 Instructions to Proponents Closing Time: Delivery Address: 3:00 pm (local time) Thursday, March 6,2008 Kelowna and Vernon

More information

Village of Nakusp RFQ 2016-1 Source Protection Plan

Village of Nakusp RFQ 2016-1 Source Protection Plan RFQ 2016-1 Source Protection Plan The is requesting quotations from qualified professional consultants or firms to undertake a Source Protection Plan for the Village s surface water sources (Halfway Creek,

More information

In the event there is the need for Addenda, it will be posted to the RMTA website and an acknowledgement form must be signed.

In the event there is the need for Addenda, it will be posted to the RMTA website and an acknowledgement form must be signed. 919 East Main Street, Suite 600, Richmond, Virginia 23219 Telephone 804-523-3300 www.rmaonline.org Fax 804-523-3335 Sheryl B. Johnson, PHR Director of Human Resources October 1, 2015 Dear Benefits Consultant,

More information

TOWN OF GLASTONBURY PROFESSIONAL SERVICES PROCUREMENT NOTICE REQUEST FOR PROPOSAL MERCHANT PAYMENT PROCESSING SERVICES RPGL # 2010-36

TOWN OF GLASTONBURY PROFESSIONAL SERVICES PROCUREMENT NOTICE REQUEST FOR PROPOSAL MERCHANT PAYMENT PROCESSING SERVICES RPGL # 2010-36 TOWN OF GLASTONBURY PROFESSIONAL SERVICES PROCUREMENT NOTICE REQUEST FOR PROPOSAL MERCHANT PAYMENT PROCESSING SERVICES RPGL # 2010-36 The Town of Glastonbury will be accepting proposals from qualified

More information

Draft Model Social Infrastructure PPP Bill

Draft Model Social Infrastructure PPP Bill Draft Model Social Infrastructure PPP Bill RELATING TO PUBLIC-PRIVATE AGREEMENTS FOR PUBLIC BUILDINGS BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF [add state name]: SECTION. The Legislature makes the

More information

Workshop on Implementing PPP projects in Sierra Leone. Timothy J. Murphy David Livingston Freetown, July 9-12, 2013

Workshop on Implementing PPP projects in Sierra Leone. Timothy J. Murphy David Livingston Freetown, July 9-12, 2013 Workshop on Implementing PPP projects in Sierra Leone Timothy J. Murphy David Livingston Freetown, July 9-12, 2013 1 21008613 Who We Are David Livingston PPP Advisor, Ryerson University Chief of Staff

More information

Request for Proposals for Upgraded or Replacement Phone System

Request for Proposals for Upgraded or Replacement Phone System City of Bandon Request for Proposals for Upgraded or Replacement Phone System 7/17/2015 Phone System Request for Proposal Page 1 NOTICE The City of Bandon is accepting Proposals for an upgraded or replacement

More information

4.03. Brampton Civic Hospital Public-private Partnership Project. Chapter 4 Section. Background. Follow-up on VFM Section 3.03, 2008 Annual Report

4.03. Brampton Civic Hospital Public-private Partnership Project. Chapter 4 Section. Background. Follow-up on VFM Section 3.03, 2008 Annual Report Chapter 4 Section 4.03 Brampton Civic Hospital Public-private Partnership Project Follow-up on VFM Section 3.03, 2008 Annual Report Background In 2001, the then Minister of Finance announced that public

More information

Current Employment Opportunities Project Based Consultants

Current Employment Opportunities Project Based Consultants We are always open to hearing from exceptional talent If you are looking for consulting opportunities within the International Development sector, please register your details with us on our website www.maxwellstamp.com/consultants.asp,

More information

PROCUREMENT GUIDE: SELECTING A CONTRACTOR/PROJECT DEVELOPER

PROCUREMENT GUIDE: SELECTING A CONTRACTOR/PROJECT DEVELOPER PROCUREMENT GUIDE: SELECTING A CONTRACTOR/PROJECT DEVELOPER 1. Overview CHP project development and implementation are similar to many central plant construction projects or comprehensive energy conservation

More information

London Green Fund Selection of Waste Urban Development Funds IR-893. Questions and Answers

London Green Fund Selection of Waste Urban Development Funds IR-893. Questions and Answers London Green Fund Selection of Waste Urban Development Funds IR-893 Questions and s Question 1. What restriction, if any, will be placed on the waste UDF s ability to re-invest the initial commitment of

More information

DISASTER RECOVERY PROGRAM HANDBOOK NOT-FOR-PROFIT ORGANIZATIONS, INSTITUTIONS AND CONDO ASSOCIATIONS

DISASTER RECOVERY PROGRAM HANDBOOK NOT-FOR-PROFIT ORGANIZATIONS, INSTITUTIONS AND CONDO ASSOCIATIONS DISASTER RECOVERY PROGRAM HANDBOOK NOT-FOR-PROFIT ORGANIZATIONS, INSTITUTIONS AND CONDO ASSOCIATIONS 2 3 About this hand book This handbook explains the disaster recovery programs offered by the Government

More information

3 JOINT SOURCE SEPARATED ORGANICS TREATMENT FACILITY STATUS REPORT - PROJECT 71335

3 JOINT SOURCE SEPARATED ORGANICS TREATMENT FACILITY STATUS REPORT - PROJECT 71335 3 JOINT SOURCE SEPARATED ORGANICS TREATMENT FACILITY STATUS REPORT - PROJECT 71335 The Environmental Services Committee recommends the adoption of the recommendation contained in the following report dated

More information

PUBLIC PROCUREMENT SYSTEM AND REFORM IN AFGHANISTAN Anwar M. Raufi

PUBLIC PROCUREMENT SYSTEM AND REFORM IN AFGHANISTAN Anwar M. Raufi Anwar M. Raufi 1729 OUTLINE OF THE CONTENTS OF THE TOPIC TO BE PRESENTED 1- Procurement system of Afghanistan before ten years, i.e. before 2001. Afghanistan had a series of provisions regulating procurement

More information

https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework

https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework All interested parties Direct Dial: 020 7901 1849 Email: transmissioncompetition@ofgem.gov.uk Date: 17 November 2015 Dear Colleague EPC Contract Principles for OFTO Build Tenders This letter provides guidance

More information

Minnesota Power PRE QUALIFICATION QUESTIONNAIRE. Engineering, Procurement and Construction of a 10 MW Solar PV Power Plant

Minnesota Power PRE QUALIFICATION QUESTIONNAIRE. Engineering, Procurement and Construction of a 10 MW Solar PV Power Plant Minnesota Power PRE QUALIFICATION QUESTIONNAIRE Engineering, Procurement and Construction of a 10 MW Solar PV Power Plant December 1, 2014 CONTRACTOR s NAME: Project Description: Minnesota Power is developing,

More information

The Inkosi Albert Luthuli Hospital. Cairo, May 25 26, 2008

The Inkosi Albert Luthuli Hospital. Cairo, May 25 26, 2008 The South Africa PPP Program The Inkosi Albert Luthuli Hospital Transaction Cairo, May 25 26, 2008 1 USAID Support (1999-2005) to: Establish the PPP Unit (2000) Develop the policy/regulatory y framework

More information

CITY COUNCIL AGENDA REPORT

CITY COUNCIL AGENDA REPORT CITY COUNCIL AGENDA REPORT Subject: PROPOSED DIGITAL MESSAGING CENTRES - ST. ALBERT CHAMBER OF COMMERCE Recommendation(s): 1. That the St. Albert Chamber of Commerce undertake public consultation in the

More information

Solicitation Addendum One (1) RFQ 09-07 CARPET CLEANING SERVICES

Solicitation Addendum One (1) RFQ 09-07 CARPET CLEANING SERVICES Solicitation Addendum One (1) RFQ 09-07 6829 North 58th Drive, Suite 202 Glendale, Arizona 85301-2599 A signed copy of this Addendum must be received by on or before the Offer Due Date and time. This solicitation

More information

WELCOME! SAME Energy and Sustainability Committee Cracking the Contracting Code for Large-Scale Solar Webinar

WELCOME! SAME Energy and Sustainability Committee Cracking the Contracting Code for Large-Scale Solar Webinar WELCOME! SAME Energy and Sustainability Committee Cracking the Contracting Code for Large-Scale Solar Webinar Committee Chair: Col. John Mogge, RA, F.SAME, USAF (Ret.), CH2M HILL Committee Vice Chair:

More information

GUIDE ON HOW TO DO BUSINESS WITH LIVERPOOL JOHN MOORES UNIVERSITY

GUIDE ON HOW TO DO BUSINESS WITH LIVERPOOL JOHN MOORES UNIVERSITY GUIDE ON HOW TO DO BUSINESS WITH LIVERPOOL JOHN MOORES UNIVERSITY PRODUCED BY LIVERPOOL JOHN MOORES UNIVERSITY PROCUREMENT SERVICE First Issued - ISSUED 11 th February 2011 VERSION 5.0 updated 13/04/15

More information

Massachusetts Residential Solar Loan Program

Massachusetts Residential Solar Loan Program Massachusetts Residential Solar Loan Program FINAL PROGRAM DESIGN - UPDATE September 17, 2015 Problem Statement and Opportunity MA residential solar market has boomed over past 4 years and continued SREC-II

More information

Availability Payment Mechanisms For Transit Projects ADVISORY

Availability Payment Mechanisms For Transit Projects ADVISORY Availability Payment Mechanisms For Transit Projects ADVISORY Agenda Availability Payments Overview Structure Financial Implications Case Study Additional Considerations KPMG Infrastructure 2 What is an

More information

REQUEST FOR PROPOSAL Branded Content Marketing and Contest Development to Target International Markets

REQUEST FOR PROPOSAL Branded Content Marketing and Contest Development to Target International Markets REQUEST FOR PROPOSAL Branded Content Marketing and Contest Development to Target International Markets Contents Introduction... 1 The RFP Process... 1 Project Timetable... 1 Proposal Submission Guidelines...

More information