1 TABLE OF CONTENTS. 1. BIM Execution Plan. BIM Execution Plan- UF Minor Projects Template UF of 20 pages Processes...

Size: px
Start display at page:

Download "1 TABLE OF CONTENTS. 1. BIM Execution Plan. BIM Execution Plan- UF Minor Projects Template UF-000 2 of 20 pages. 1.1. Processes..."

Transcription

1

2 1 TABLE OF CONTENTS 1. BIM Execution Plan 1.1. Processes Addendum to UF Contracts Methodology Project Overview / General Information Project Collaboration Team Roles and Responsibilities Project Goals Collaboration Meetings Project Specific Sustainability Goals BIM Software and Information Exchange Design Tools Information Exchange Modeling Plan General Directives Model Management Modeling Plan by Project Phase Analysis Model(s) Protocols... Error! Bookmark not defined Owners BIM Integration Requirements... Error! Bookmark not defined General Directives... Error! Bookmark not defined Owners BIM Template Files and Revit Project Standards for Design Team s Use... Error! Bookmark not defined Coordination Guidelines General File Format Compatibility Constructability Reviews Project Close Out Appendix BIM Execution Plan- UF Minor Projects Template UF of 20 pages

3 1. BIM Execution Plan 1.1. Processes BIM Execution Plan- UF Minor Projects Template UF of 20 pages

4 1.2. Addendum to UF Contracts This Guide is incorporated by reference into the UF minor projects annual contracts consisting of the Agreement between Owner and Professional and Agreement for Construction Management Services Agreement Between Owner and Professional for Minor Projects Continuing Professional Services (Reference Exhibit A / UF contract for specific language) Agreement for Construction Management Services (Reference Exhibit A 8.9 UF contract for specific language) 1.3. Methodology University of Florida Minor projects encompass a wide range of scale and complexity, with total construction costs up to $2 million. Such variation necessitates a flexible approach to the process of BIM execution for minor projects. The document body of the annual contracts is relatively fixed, therefore language within the project specific contract exhibits, and accompanying BIM Execution Plan shall provide the necessary guidance for each project. This BIM Execution Plan template shall be tailored project specific and authored by the owner s PM, Design team, and CM team representatives. Each UF division utilizing the minor projects annual contract, (Housing/IFAS/PPD/FPC) will determine the extent of BIM execution for individual projects within their respective areas. The scope of this BIM execution plan is intended to include new construction, renovation, remodeling, and building utility type projects. Relative to BIM model level of development protocols, it is recognized that design firms may have existing measures in place that efficiently utilize one or the other within its internal workflows. AIA E202 BIM Protocol UF LOD Table (.xls) 1.4. Project Overview / General Information Project Name: Albert W Gator Building, UF-000 Project Address: UF Main Campus Brief Project Description BIM Execution Plan- UF Minor Projects Template UF of 20 pages

5 1.5. Project Collaboration Team Name: Role / Title: Company: Phone: Name: Role / Title: Company: Phone: Name: Role / Title: Company: Phone: Insert PM here Owner - Project Manager University of Florida xxxx@ufl.edu (352) 273-nnnn Insert here Design Team BIM Manager Architects name@architects.com (nnn) nnn-nnnn Insert here Construction BIM Manager Building Contractor name@buildingcontractor.com (nnn) nnn-nnnn 1.6. Roles and Responsibilities Design Team BIM Manager (Insert name here) Individual assigned by the Design Team to serve as the main point of contact between the Design Team, the Construction Team, and UF for all BIM related issues. This individual shall have sufficient BIM experience required for the size and complexity of the project and shall have relevant proficiency in the BIM authoring and coordination software. Responsibilities include the following: 1. Responsible for the overall development and delivery of the Building Information Model. 2. Monitors compliance with the BIM Execution Plan and related BIM Level of Detail (LOD) Matrix. 3. Responsible for the development, coordination, publication, and verification that all Building Information Model configurations are in place as required for the integration of the design phase and construction phase model information, elements, etc. 4. Coordinates the file management procedures and protocols for the BIM Model. 5. Responsible for the coordination and set-up of shared file servers to be utilized for the Building Information Model, including related access, permissions, protocols, etc. 6. Prepares, assembles, and facilitates the use of the Building Information Model for design meetings, coordination meetings, and BIM deliverables. BIM Execution Plan- UF Minor Projects Template UF of 20 pages

6 7. Assumes responsibility for the proper classification of all spaces, equipment, and components within the Building Information Model (in accordance with UF protocols and downstream use for UF Facility Management). 8. Schedules, coordinates, and facilitates BIM technical meetings between the Design-Build Team and all design disciplines. 9. Coordinates and facilitates the clash detection and coordination efforts among all design disciplines. 10. Determines the project BIM geo-reference point(s), and ensures that the models from all design disciplines are properly referenced and coordinated with the geo-reference point(s). 11. Primary interface between the Design-Build Team and UF for BIM data and file transfers as required at each design phase or otherwise necessary. 12. Ensures that the BIM design deliverables specified and/or required by contract are provided in accordance with the Contract Documents. 13. Ensures that the 2D project drawings and project specifications produced for bidding and construction purposes are properly derived from and adequately represent the information contained within the Building Information Model. 14. Coordinates with the Construction BIM Manager to ensure that all requirements for the final BIM Model deliverables are achieved. Construction Team BIM Manager (Firm & Coordinator Name) Individual assigned to serve as the main point of contact for the Construction Team for BIM related issues. This individual shall have sufficient BIM experience required for the size and complexity of the project and shall have relevant proficiency in the BIM authoring and coordination software. Responsibilities include the following: 1. Responsible for the overall development of BIM Model content and information that is developed from construction operations. 2. Serves as the main point of contact for BIM related issues between the Construction Team, Subcontractors, Suppliers, and the Design Team, UF, and others as required. 3. Ensures that the Construction Team has the necessary hardware, BIM authoring and analysis software, and adequate training to facilitate the use of the BIM Model as a tool during construction. 4. Responsible for the integration and/or coordination of the construction schedule with the Construction BIM Model. 5. Facilitates the use of trade models for the purpose of trade coordination and clash detection (when available or provided by trade contractors). 6. Communicates requests by trade contractors for data extraction sets to the Design Team and ensures that these requests are fulfilled. 7. Coordinates with the Design Team to facilitate timely updates to the Construction BIM Model for design changes that may occur after construction has commenced. 8. Works with Lead Trade Fabrication Modelers as may be required for procurement and construction activities. BIM Execution Plan- UF Minor Projects Template UF of 20 pages

7 9. Coordinates updates to the BIM Model as necessary to reflect the as-built or as-constructed conditions in the final As-Built BIM Model. Responsibilities Related to the Final As-Built BIM Model Design Team Responsibilities 1. The Design Team will manage and update the Revit Model(s) through the end of the construction phase, incorporating all updates and/or revisions to the model(s) as necessary to reflect design changes initiated by ASI, RFI, Owner Changes, or coordination with existing conditions. 2. All model updates by the Design Team shall be complete at Substantial Completion at which time the Revit Model(s) shall be transmitted to the Construction Team who shall be responsible for the construction related updates to the model(s). 3. One (1) week prior to Final Completion, the Construction Team will transmit the Revit Model(s) back to the Design Team who shall then be responsible for the final preparations and delivery of the As-Built BIM Model to the Owner. Construction Team Responsibilities 1. During the construction phase, the Construction Team will maintain red-line as-built drawings. 2. At Substantial Completion, the Design Team will transmit the Revit Model(s) to the Construction Team who will then incorporate the following updates and/or revisions into the model(s): a. All updates and/or revisions to the model(s) as necessary to reflect the as-built information obtained from the red-line as-built drawings. b. Final updates to material/equipment data and properties where installations differ from the basis of design included in the Design Team Model(s). c. Incorporation or linking of certain close-out documents to the Revit Model(s) (TBD examples: Submittal Information, O&M Manuals, Documentation Photos). 3. All model updates by the Construction Team shall be complete one (1) week prior to Final Completion at which time the Revit Model(s) shall be transmitted back to the Design Team who shall be responsible for the final preparations and delivery of the As-Built BIM Model to the Owner. BIM Execution Plan- UF Minor Projects Template UF of 20 pages

8 1.7. Project Goals The BIM collaboration team shall present, discuss, and agree upon project specific goals. The relevant project experience, team strengths, BIM competencies, and scheduling factors should be considered during this discussion. The team should list goals and objectives for using BIM and collaborative project management technologies and processes to measure the achievement of these objectives. (sample language in red below) Project Specific Goal Visualization Requirements Sustainability/LEED Documentation Coordination/Clash Detection Learning Experience O&M Integration Facilitate Cost Estimating Subcontractor Use (Bidding, Understanding, Fabrication) Describe Requirements/Considerations The BIM Model will be utilized to convey the design to the Project Team. This should be of particular benefit to the client occupants, in visualizing and understanding the design during the early phases of the project. When applicable, the design team will capture BIM model associated sustainability/leed documentation in designated drawing sheets The Design-Build Team will utilize AutoDesk Revit Architecture, Revit Structure, Revit MEP, and Navisworks Manage to coordinate design disciplines and perform clash detection analyses within the BIM Model. It is expected that the technical skills, efficiency, and familiarity of team members and their respective firms with various BIM processes will be improved over the course of the project. Primary UF goal. Where Revit models of fixtures/equipment of sufficient quality and accuracy are available from the manufacturer, they should be utilized in the project model. There is also an option to embed links (i.e. URL s) from major fixtures/equipment within the As-Built BIM Model to file folders containing project-specific information such as submittals, shop drawings, O&M s, etc. The delivery method for this information will be coordinated with UF. Various components of the CM cost estimating effort may be derived directly from the BIM Model. Also, the BIM Model may be utilized for verification of manual take-off quantities. AE/MEP design models maybe used as basis for sub-contractors 3D shop drawings. The CM BIM manager will coordinate export of Revit for use by subs when applicable. BIM Execution Plan- UF Minor Projects Template UF of 20 pages

9 Collaboration Meetings There will be different types of Collaboration meetings needed for the project, including general progress meetings, design coordination meetings, etc. In the space below, list the types of meetings necessary for the project, meeting host(s), required attendees, and required technology. (Sample text in red below) Meeting Type Host Required Attendees Required Technology Design Meetings BIM Model Progress/Coordination Architect / Design Disciplines Design Team Revit Architecture, Revit Structure, Revit MEP, Projector, Laptop PC Design Presentations BIM Model Presentations to Project Team Design Team Coordination BIM Model Coordination/Clash Detection CM Team Coordination BIM Model Coordination/Clash Detection CM As-Built Coordination As-Built BIM Model Progress/Coordination Owner / User Group Architect / Design Disciplines Construction Manager Architect / Construction Manager Owner, Design Team, CM, Team, User Group Design Team CM Team, Subcontractors, Owner, Design Team CM Team, Subcontractors, Owner, Design Team Revit Architecture, Revit Structure, Revit MEP, Projector, Laptop PC Revit Architecture, Revit Structure, Revit MEP, Navisworks, Projector, Laptop PC Navisworks, Projector, Laptop PC Revit Architecture, Revit Structure, Revit MEP, Navisworks, Projector, Laptop PC Project Specific Sustainability Goals and LEED Certification Documentation The project may have certain LEED EB requirements. UF project manager shall notify project team of any requirements Sustainable Design Tools and Execution When the scale of the project is applicable, the Design Team may employ a variety of BIM software for sustainable design including the ones identified in the analysis Model Matrix. The model analysis done in BIM sustainability software such as, but not limited to, Autodesk Ecotect, 3ds Max Design, Revit MEP, and IES may be utilized to analyze the design model for potential issues that may improve, correct, or optimize the design models of various design disciplines. BIM Execution Plan- UF Minor Projects Template UF of 20 pages

10 1.8. BIM Software and Information Exchange Design Tools The professional shall develop the design at each stage using building information modeling (BIM) software and related technologies specifically, the 2011 or later versions of Autodesk "Revit Architecture" for Architectural content, Autodesk "Revit Structure" for structural content, and Autodesk "Revit MEP" for Mechanical, Electrical, Plumbing, Fire Protection, and Telecom/Technology content Information Exchange Collaboration Tools For general project correspondence and milestone/phase BIM deliverables, the team will use the UF SharePoint platform as a means of sharing and storing information. During the design phase, BIM-related files utilized by the design team will be shared through the FTP site of the lead Architect. During the construction phase, BIM-related files may be shared utilizing either the Construction Managers FTP site or the UF SharePoint FTP site Version Control In recent years, BIM software platforms have incorporated substantial changes and/or advancements in their programs, technologies, capabilities, features, interoperability, etc. through annual software upgrades. It shall be the Design Team BIM Manager s responsibility to monitor and regulate software version updating if required during the course of the Project. It is understood that a number of the software tools utilized in this BIM Execution Plan are not backwards compatible and must be carefully synchronized. Since the majority of the BIM software platforms utilized on this project do not contain backward capabilities, the entire Project Team will need to evaluate the advantages and disadvantages of performing software upgrades during the design phase, and reach an agreement on whether or not to proceed with such upgrades if/when they may become available Agreements Electronic File Transfer Agreement (EFTA), Access Rights This language shall be discussed and agreed upon by the team. It is recognized that various firms may have corporately executed EFTA protocols that will have to be addressed. Typically, the Construction Manager, will sign and return to the Architect of record an Electronic File Transfer Agreement (EFTA) relative to BIM Files utilized by Contractor, Subcontractors or BIM Execution Plan- UF Minor Projects Template UF of 20 pages

11 1.9. Modeling Plan Other Third Party Recipients. The executed EFTA will constitute an agreement between Architect and the Construction Manager and any of the CM s Subcontractors and/or Subsubcontractors granted access to the Model files Intellectual Property Rights The Model Files are considered the intellectual property of the Model authors. Sharing of the Models does not affect the Model author s copyright or intellectual property rights in any way Owner s Use of Models The Owner will have unlimited use of the Design Models produced for the Project. The Owner acknowledges that the Design Models are an Instrument of the Designer s Service and that the Designer does not represent or guarantee that the Models will be useful to the Owner for any purposes beyond those uses that they were authored for General Directives Advanced planning around which models will be required during the different phases of the project, the responsible party(s) for model update and distribution, and predetermination of model content and format will help the project run more efficiently and cost-effectively during every phase Model Management Unless otherwise agreed upon in this BIM Execution Plan, the Project Architect of Record shall be established as the lead party responsible for managing the design model, and shall facilitate the establishment of initial protocols relating to model management. Subsequently, the model manager from each design discipline may have specific responsibilities as deemed necessary and agreed upon by the project team Model Creation Strategies Each party - such as the Owner, Architect, Contractor, or Sub-Consultants that are responsible for contributing or receiving modeling content will be required to assign a model manager to the project. Each respective model manager shall help coordinate and attend all such meetings related to the BIM Execution Plan. As the project progresses into the construction phase, various responsibilities for Model management may be assigned to the Construction Manager as agreed upon in this BIM Execution Plan. The final As-Built Deliverable will be turned over to Owner s Project Manager Techniques and Protocols BIM Execution Plan- UF Minor Projects Template UF of 20 pages

12 File Naming Conventions All Project central files and model files shall have a consistent naming convention as established by the principle design firm for discipline specific model coordination. The Design Team BIM Manager shall coordinate this activity with all sub-consultants and design disciplines. (The naming convention as illustrated below is for example and is not a specific requirement. The lead design team BIM model manager shall establish for project) File Type Naming Convention Discipline Authoring Software Revit Project File 01SD_091511_UF000_ARCH Architectural Revit Architecture 2011 (.rvt) Revit Project File (.rvt) Revit Project File (.rvt) Revit Project File (.rvt) Revit Project File (.rvt) Navisworks File (.nwd) 01SD_091511_UF000_STRUCT Structural Revit Structure SD_091511_UF000_MEPT Mechanical, Electrical, Plumbing and Telecommunications Revit MEP SD_091511_UF000_CONST Construction Manager Revit Architecture SD_091511_UF000_COORD All Design Disciplines Revit Architecture 2011 Revit Structure 2011 Revit MEP SD_091511_UF000_COORD Navisworks Navisworks Manage 2011 Coordination File All Design Disciplines View Naming Conventions Model views shall have a consistent naming convention as established by the Design Team BIM Manager. Consistent view naming allows for the automatic sorting of views for ease of identification. The protocol facilitates low maintenance of the view name as project conditions change throughout the Project Sheet Sizes and Naming Conventions Preferred format size for Construction Drawings is 24" X 36" (Architectural "D" Size). Other sizes may be used if required (coordinate with UF). Sheet names should be descriptive of drawing content and the building discipline represented (i.e., A-1, P-1, and M-1 would be typical designations for Architectural, Plumbing, and Mechanical Drawings, respectively). BIM Execution Plan- UF Minor Projects Template UF of 20 pages

13 Origin and Orientation The (0,0,0) Project Origin Coordinate will be established in the project Architectural Design Model. All subsequent models created for the Project will be based on this common coordinate. If the (0,0,0 ) project coordinate becomes compromised in any model, during any phase of the Project, the Architect s Model Manager will direct the process for reestablishing the appropriate (0,0,0) Project Origin Coordinate. All of the project models will be oriented to True North. The Project Team will rotate scope boxes and/or plan callouts in order to represent plan drawings orthogonally on the drawing sheets. This shall be the normally agreed upon orientation unless deemed otherwise by the Architect of Record Units and Tolerances The Revit Project Units and Tolerances settings affect the way that information in the model is displayed. It does not limit tolerances of how things are modeled. The Project will utilize the Revit Project Unit settings as established by the Architect s model manager. Modifications to the settings should be made as necessary and agreed to by the Project Team Grids and Levels Routinely, naming conventions for Grids and Levels will be established in the Architectural drawings unless otherwise directed by the lead Architect s model manager WorkSets Generally, the project team should always simplify, and keep Worksets to a minimum to facilitate efficient project team workflow. The disciplined use of Worksets will allow the project team to work more efficiently and will promote the collaborative BIM project delivery platform. The Project Team should discuss the applicability of the use of Revit tools that will help to ensure that all elements are assigned to their proper Worksets. (Ex: Use of the Gray Inactive Worksets option, Application of color filters to Worksets in the Revit View Visibility settings.) D CAD File Linking Protocols The Design Team BIM Manager shall establish protocols for 2D Cad file linking and/or importing, otherwise the following protocols are recommended for use by the team: Minimize the number of 2D CAD files linked to the model. 2D CAD files should be audited and purged before linking. Set reference links from the link management menu to Overlay. Always link to 2D CAD files instead of importing them. BIM Execution Plan- UF Minor Projects Template UF of 20 pages

14 Never explode 2D CAD files within a Revit file. Pin position of linked file D model linking protocols The Design Team BIM Manager shall establish protocols for 3D Model linking, otherwise the following protocols are suggested for use by the team; Set reference links from the link management menu to Overlay. Create an individual Workset for each Revit Model linked into the Project. Workset Naming & Use Conventions (above) for additional information. Use the Specify Worksets option when linking 3D models. Only open the Worksets needed for model collaboration. Close Worksets: Grids and Levels, (All) Link-, Scope Boxes, and other Worksets containing information not required for model collaboration. Use the Positioning: Auto - Origin to Origin option when linking 3D models. Pin position of linked file Custom Parameter definitions The Design Team BIM Manager shall audit and monitor the use of custom parameters introduced into the model environment for consistency of naming schema and avoidance of duplication. Shared parameter files shall be properly organized and included when file transfers occur Family creation and type Catalog file management Family creation shall be consistent with the Level of Development (LOD) Matrix in which the component is being utilized. Refer to Section below for LOD by phase. Type catalogs shall be fully developed and properly populated with the associated data elements necessary for family functionality Modeling Plan Modeling Plan Overview It is the owners (UF) understanding that with such a broad range of costs and scale for minor projects, multiple project types will exist requiring varying degrees of document development, BIM model content, and complexity of creation. Specific examples are as indicated below; New Building/Addition This scale typically involves a stand-alone new building or major addition having a construction cost under the $2,000,000 threshold for minor projects. It is the owner s (UF) requirement that projects of this magnitude be fully documented in BIM in a manner similar to UF major projects, comprehensively utilizing the tools and BIM Execution Plan- UF Minor Projects Template UF of 20 pages

15 methodologies as specified herein this BIM Execution Plan. Although UF minor projects presently are not required to have an approved Facility program, the design team will be expected to follow the SUS/UF design guidelines for space standards. To facilitate this process, the owner will provide a Revit template which includes the required space standards and coding schemas for use by the designer. Completion of the template will be a required deliverable at DD and 100%CD phases Large Scale Minor This scale typically involves larger scale minor renovation/remodeling, or utility infrastructure projects having a construction cost greater than $100,000 with work scope including demolition and construction of architectural, structural, and MEP building elements. Design documents shall be developed in BIM in a manner consistent with the protocols as indicated in this BIM Execution Plan document. It is understood that routinely, renovation and remodeling projects may require substantial demolition plans. Architectural elements shall be modeled with demolition depicted by use of the Revit Phases functionality whenever possible. A considerable number of UF buildings were either originally modeled in BIM or have BIM Architectural models developed from the conversion of 2D CAD drawings. These will be made available by the owner for applicable buildings to facilitate the design effort. For buildings that do not have existing as-built MEP BIM models, design requiring considerable demolition of MEP elements such as equipment, piping, ductwork, electrical, etc., use of the Revit detail lines functionality is acceptable over modeling existing elements to be demolished. All new MEP (equipment, systems, piping, electrical, etc.) shall be modeled using the core Revit functionality for creation of those elements, be modeled suitable for coordination and clash detection, and conform to the agreed upon LOD table developed by the project team Small Scale Minor This scale typically involves smaller scale minor renovation/remodeling, or utility infrastructure projects having a construction cost less than $100,000 with work scope including limited demolition and construction of architectural, structural, MEP building elements, and cosmetic finishes. When available, the owner s architectural BIM models will be provided to facilitate the design process. For buildings that do not have existing as-built MEP BIM models, liberal use of the Revit detail lines functionality is acceptable for minor demolition and plan view documentation of architectural and MEP elements such as equipment, piping, ductwork, electrical, etc. All new MEP equipment and/or systems that will require turn over of operations and maintenance documentation to the owner shall be modeled in BIM Level of Development by Project Phase A detailed modeling plan shall be developed for each phase of the project and shall clearly describe the desired model maturity and Level of Development (LOD) necessary for the various phases of project design. BIM Execution Plan- UF Minor Projects Template UF of 20 pages

16 All design modeling will be performed utilizing Autodesk "Revit" software platforms (Architecture, Structure, MEP), versions 2011 or later. The design team shall collectively coordinate platform versioning for compatibility purposes during the design process. Any deviations shall require approval from the Owner. At each design phase, the model maturity shall be developed to the extent that it will generate the drawing document deliverables with the content, level of detail, and format as required by the UF Design Services & Commissioning Guide and shall be consistent with level of development as described by phase below. The resulting output, depicted in traditional two-dimensional drawing format with drawing sheets organized by discipline, dimensioned and detailed, shall serve as validation of the accuracy and completeness contained within the building information model(s). In general, the Design Team shall follow the UF Design Services & Commissioning Guide for each design phase, however, the Design Team shall not be required to create additional drawings, models, etc. that may be indicated in these guidelines when deemed unnecessary for construction purposes, or to the BIM Model. It is understood that not all project designs will require the same phases and durations. Adjustments to the model(s) level of development and phase durations will be agreed upon as necessary by the project team (for example; a small minor project may only require a 50% and 100%CD review, whereas a larger scale minor project may require conceptual, advanced Schematic, design development, 60% CD, and 100% CD review phases) Area Calculations - UF Design Services Guide Requirements Purpose and Scope For UF minor projects resulting in new buildings, additions to existing, otherwise the creation of new square footage, at the end of each design phase, the Design Professional shall calculate the area of the project using the following method and compare this information to the owner s requirements as outlined in a space summary form or Facilities Program template document. Area calculations may be obtained utilizing Autodesk Revit Software; 1. Building Gross Square Feet: Determine the total building gross square feet by adding the sum of the floor areas of the building included within the outside faces of exterior walls for all stories, or areas that have floor surfaces. Gross area should be computed by measuring from the outside face of exterior walls, disregarding cornices, pilasters, buttresses, etc., which extend beyond the wall face. Gross area should include basements (except unexcavated portions), attics, garages, enclosed porches, penthouses, mechanical equipment floors, lobbies, mezzanines, all balconies (inside and outside) utilized for operational functions, and corridors, provided they are within the outside face lines of the building. Stairways, elevator shafts, mechanical service shafts, and ducts are to be counted as gross area on each floor through which the shaft passes. Exclude open courts and light wells, portions of upper floors eliminated by rooms or lobbies that rise above single floor height, and non-enclosed covered walkways. BIM Execution Plan- UF Minor Projects Template UF of 20 pages

17 2. Net Assignable Square Feet: Determine the sum of room areas excluding nonassignable areas. Room area is defined as the net area of the room in square feet, measured between the inside surfaces of walls and partitions. Non-assignable areas include interior circulation space (including stairs), custodial areas, mechanical areas, structural areas, public rest rooms, exterior circulation space (including stairs), elevators, and telephone/data communication equipment areas. 3. Non-Assignable Square Feet: Determine the net room area of all non-assignable spaces as defined in Item 2 above. 4. Covered Walkway Gross Square Feet: Measure floor area, excluding any areas which were included in Building Gross Square Feet calculations. 5. Impervious Surface Gross Square Feet: Measure impervious surfaces created as part of the project site plan including sidewalks, service drives, parking, plazas, etc. that are not covered in Paragraph 3 above Coordination Guidelines General BIM Coordination guidelines shall be established by the Contractor for the purpose of supplementing the coordination process between trades and design disciplines File Format Compatibility All coordination drawings shall be produced in file formats compatible with other coordination team members. All Construction Documents shall be generated from the BIM model(s). BIM Model coordination and clash detection will be performed utilizing the BIM Model and AutoDesk Revit/Navisworks software platforms Constructability Reviews The BIM model shall be utilized for the purpose of constructability reviews. Use of the BIM Model for constructability review shall not be considered as in kind replacement for reviewing the traditional printed 2D line drawing documents but as a supplementary effort to improve the review process. Constructability reviews shall be accomplished as follows: An analysis and evaluation of the constructability of the design concepts, narratives, or drawings. An analysis and evaluation of the design concepts, narratives, or drawings in regard to the completeness of intended bid categories, conflicts or overlaps in the divisions of the work. BIM Execution Plan- UF Minor Projects Template UF of 20 pages

18 An evaluation of design details affecting construction including, without limitation, unusual or custom materials. Address problems, conflicts, defects, or deficiencies in the design concepts and offer resolutions Resolution of Interferences The Design Team shall participate in the coordination meetings as necessary to timely resolve design conflicts and/or coordination issues. Design changes made during this process shall be properly documented by the Contractor and Design Team and the model(s) shall be updated as necessary Navisworks Requirements Methodology Navisworks files should be created at all critical coordination milestones. This record format will document a coordinated section of the model, either by area of the building or between specific critical trades. The Collision report showing all applicable collisions as either Approved or Resolved along with the Navisworks file shall be uploaded together to the project collaboration system. A text or HTML document shall also be uploaded which describes and references the approved coordination NWD File with respect to what has and has not been coordinated. Reports should be published in a standard XML, HTML, or Text format as created by Navisworks and agreed upon by the Project Team. 2. Project Close Out Navisworks Reports Minimum Requirements Navisworks Reports shall include the following information at a minimum: Description of collision report. Date of collision report run. List of all collisions detected in the model(s), their status, and the proposed solution to resolve the conflicts. Graphical representation of the model geometry corresponding to each collision detected in the model(s) Concurrent As-Built Documentation BIM Execution Plan- UF Minor Projects Template UF of 20 pages

19 The contractor shall submit a plan to the Owner for review, prior to the start of construction that outlines the process for concurrent as-built documentation. Concurrency is mandated. Methods for recording as-built information are left to the discretion of the Contractor. Potential options include traditional methods and/or periodic laser scanning of completed or partially completed primary systems coordinated with the sequence of construction Documentation Methodology: Determination of the methodology and execution of compiling the Final As-Built BIM Model(s) shall depend upon the relative experience and strengths of the various team members and agreed upon by all respective parties in this BIM Execution Plan. Acceptable documentation workflows shall be as follows: As-built modeling will be a collaborative effort between the Architect, Design Consultants, and the Construction Team. During the construction process, the Design Team will incorporate changes triggered by requests for information (RFIs), Architect s Supplemental Instructions, and Change Orders into the Architectural, Structural, and MEP design models. At specified periods during the construction process, the Construction Team will document in their copy of the Revit BIM model(s), 3D Coordinated Navisworks model(s), or on red-line drawings, all changes generated from shop drawings, coordination drawings, and field changes. Optionally, the completed form of the in-place construction may also be verified at these specified dates using laser scanning. The construction team will incorporate all changes as well as as-built model information differing from the basis of design included in the original construction documents (equipment boiler plate specifications, etc.). The finished model shall be reviewed for accuracy and completeness by the Design Team and Owner prior to finalization. Optionally, the Design Team may be contractually required to deliver the Final As-Built BIM Model. Subsequently, the Design Team may elect to perform all final updates to the model(s) based on information and markups received from the Construction Team. These methodologies shall be discussed and agreed upon by the project team during the initial stages of the BIM execution process. Refer to Section 1.6 of this BIM Execution Plan for responsibilities and workflows related to the Final As-Built BIM Model Documentation Requirements: (For project specific requirements, see Model LOD Matrix for Final As-Built Model). Primary systems fall into two categories - Primary Architectural Systems and Primary Engineering Systems. Primary Architectural Systems include, but may not be limited to, structural framing, partition systems with structure, flooring systems, partition systems with bulkheads, partition systems with BIM Execution Plan- UF Minor Projects Template UF of 20 pages

20 expansion control, vertical transportation systems with primary engineering systems, millwork and casework systems horizontal ceiling systems with window openings, bulkheads, partitions, exterior skin systems with window openings, structure, roof edge conditions, parapets, roof penetrations, and equipment locations. Primary Engineering Systems include, but may not be limited to, major HVAC, piping, sewerage and/or conduit systems, primary HVAC duct runs, primary fire protection main runs, lighting, fire protection and HVAC outlet locations, power and data outlets, primary electrical conduits, ceiling grids layouts, primary data, audio visual, security and communication distribution systems (cable trays, etc) Operations and Maintenance Documentation 3. Appendix Where Revit models of fixtures/equipment of sufficient quality and accuracy are available from the manufacturer, they should be utilized in the project model. There is also an option to embed links (i.e. URL s) from major fixtures/equipment within the As-Built BIM Model to file folders containing project-specific information such as submittals, shop drawings, O&M s, etc. The delivery method for this information will require further discussions with UF FP&C, UF PPD, User Group, etc. to determine the most useful delivery method, taking into account subjects such as hardware/software availability to staff, staff software proficiencies, etc. which may tend to limit the accessibility of the documentation photos should they be embedded into the Revit Model file. BIM Execution Plan- UF Minor Projects Template UF of 20 pages

2012 BIM Guidelines and Standards (Rev. 00) University at Albany

2012 BIM Guidelines and Standards (Rev. 00) University at Albany A. Building Information Modeling (BIM) Guidelines: The Office of AECM will require the submission of BIM modeling files as part of an electronic file submission to the AECM project manager as requested

More information

School Building Authority of West Virginia BUILDING INFORMATION MODELING (BIM) EXECUTION PLAN SBA FORM 191

School Building Authority of West Virginia BUILDING INFORMATION MODELING (BIM) EXECUTION PLAN SBA FORM 191 School Building Authority of West Virginia BUILDING INFORMATION MODELING (BIM) EXECUTION PLAN SBA FORM 191 Section 1: General 1.0 Alignment with Organizational Vision In the space provided below, read

More information

BIM: FOR PROJECT MANAGERS. 2011 CSI Southwest Region Conference Program 1B 8:45am 11:00am

BIM: FOR PROJECT MANAGERS. 2011 CSI Southwest Region Conference Program 1B 8:45am 11:00am BIM: FOR PROJECT MANAGERS ANA BAKER BRANDON GARRETT 2011 CSI Southwest Region Conference Program 1B 8:45am 11:00am 1 2 3 4 BIM Overview BIM Level of Development Evolution of the Drawing Process BIM Workflow

More information

Execution Plan Template Design Modeling

Execution Plan Template Design Modeling Execution Plan Template Design Modeling NEW CONSTRUCTION By signature below, this Execution Plan is herewith adopted and incorporated into the Agreement, dated, for Professional Design Services between

More information

SECTION 3: ANNEX J UNC CHARLOTTE ILM IMPLEMENTATION PLAN (New Section)

SECTION 3: ANNEX J UNC CHARLOTTE ILM IMPLEMENTATION PLAN (New Section) University of North Carolina at Charlotte Design and Construction Manual Section 3, Annex J UNC Charlotte ILM Implementation Plan SECTION 3: ANNEX J UNC CHARLOTTE ILM IMPLEMENTATION PLAN (New Section)

More information

Revit MEP. Autodesk Navisworks

Revit MEP. Autodesk Navisworks What is BIM? Autodesk BIM is an intelligent model-based process that helps owners and service providers achieve business results by enabling more accurate, accessible, and actionable insight throughout

More information

STATE OF MINNESOTA. BIM GUIDELINE State of Minnesota s Facilities Administration Data Capture Plan

STATE OF MINNESOTA. BIM GUIDELINE State of Minnesota s Facilities Administration Data Capture Plan STATE OF MINNESOTA BIM GUIDELINE State of Minnesota s Facilities Administration Data Capture Plan January 2014 TABLE OF CONTENTS GENERAL INFORMATION BUILDING INFORMATION MODELING (BIM)... 1 PURPOSE OF

More information

CITY COLLEGE OF SAN FRANCISCO (CCSF) Building Information Modeling (BIM) Standards for Design-Bid Build Projects. CCSFBIMS Version 1.

CITY COLLEGE OF SAN FRANCISCO (CCSF) Building Information Modeling (BIM) Standards for Design-Bid Build Projects. CCSFBIMS Version 1. CITY COLLEGE OF SAN FRANCISCO (CCSF) Building Information Modeling (BIM) Standards for Design-Bid Build Projects CCSFBIMS Version 1.0 Prepared by: CCSF Facilities Planning & Construction (FPC) Department

More information

CAD Standards Guideline For Facility Documentation and Construction Projects

CAD Standards Guideline For Facility Documentation and Construction Projects CAD Standards Guideline For Facility Documentation and Construction Projects Page 1 of 12 Table of Contents A. Software B. CAD Methods 1. Layer Standards 2. Font 3. Lineweights 4. External References 5.

More information

Autodesk Revit LEARNING PATH BUILDING DESIGN SUITE

Autodesk Revit LEARNING PATH BUILDING DESIGN SUITE Autodesk Revit LEARNING PATH FUNDAMENTALS Duration: 3 days Cost: R5 500 (excl VAT) Revit MEP Duration: 3 days Cost: R5 500 (excl VAT) Revit Structure Duration: 3 days Cost: R5 500 (excl VAT) REVIT ADVANCED

More information

BIM Extension into Later Stages of Project Life Cycle

BIM Extension into Later Stages of Project Life Cycle BIM Extension into Later Stages of Project Life Cycle Pavan Meadati, Ph.D. Southern Polytechnic State University Marietta, Georgia This paper discusses the process for extending the implementation of the

More information

How To Design A Bim Project

How To Design A Bim Project BIM Virtual Construction & Integrated Project Delivery Randy LaNear BIM Manager Barnhart - Heery Synonyms & Related Terms Integrated Practice Integrated Project Delivery Virtual Building (Environment)

More information

BIM GUIDE. Developed for

BIM GUIDE. Developed for BIM GUIDE Developed for BIM GUIDE Protocols and Project Execution Plan 1 Table of Contents.. Objective... P. 4.. Roles & Responsibilities... P. 5.. Contract Strategies... P. 8.. Level of Development...

More information

Olilo's AEC Design Services. SrinSoft Inc, Partners of

Olilo's AEC Design Services. SrinSoft Inc, Partners of Olilo's AEC Design Services SrinSoft Inc, Partners of Olilo provides design services that include design and analysis, cost estimation, 3D modeling, 2D drafting, conversion from 2D to 2D, quantity take-off,

More information

All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal.

All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal. 2.02 DESIGN DEVELOPMENT PHASE GENERAL The Architect shall prepare the Design Development Documents from the approved Schematic Design. The Design Development Documents shall consist of drawings and other

More information

CAD Standards Guideline For Facility Documentation and Construction Projects

CAD Standards Guideline For Facility Documentation and Construction Projects CAD Standards Guideline For Facility Documentation and Construction Projects Implemented March 2010 Page 1 of 9 Table of Contents A. Software B. CAD Methods 1. Layer Standards 2. Font 3. Lineweights 4.

More information

Applies to: All Employees within the Facilities Management Department (FMD)

Applies to: All Employees within the Facilities Management Department (FMD) Building Area Measurement Guidelines Applies to: All Employees within the Facilities Management Department (FMD) GUIDELINES: Issued: December 17, 2013 Author: FMD Physical Planning Team PURPOSE: To establish

More information

Design Development Quality Management Phase Checklist Project Phase Checklist Series

Design Development Quality Management Phase Checklist Project Phase Checklist Series Best Practices Design Checklist Project Phase Checklist Series Contributed by Micheal J. Lough, AIA, Principal, Integral Consulting The AIA collects and disseminates Best Practices as a service to AIA

More information

2301.1 Scope: Communications and Electronic Systems addressed in this section include:

2301.1 Scope: Communications and Electronic Systems addressed in this section include: Chapter 23 COMMUNICATIONS / ELECTRONIC SYSTEMS SECTION 2301 - GENERAL 2301.1 Scope: Communications and Electronic Systems addressed in this section include: 1. Fire Alarm System 2. Telecommunication and

More information

The use of BIM in plumbing projects creates deeper project knowledge, delivers a more robust product, and can reduce total project costs.

The use of BIM in plumbing projects creates deeper project knowledge, delivers a more robust product, and can reduce total project costs. BIM for plumbing design The use of BIM in plumbing projects creates deeper project knowledge, delivers a more robust product, and can reduce total project costs. BY JUNCHENG (JAMES) YANG, PE, CPD, LEED

More information

Facilities Management

Facilities Management Facilities Management June 29, 2015 THIS PAGE INTENTIONALLY LEFT BLANK University of South Florida BIM Guidelines and Standards Page 2 of 32 BIM Guidelines and Standards Table of Contents SECTION 1: BIM

More information

NEW YORK CITY DEPARTMENT OF DESIGN + CONSTRUCTION

NEW YORK CITY DEPARTMENT OF DESIGN + CONSTRUCTION NEW YORK CITY DEPARTMENT OF DESIGN + CONSTRUCTION July 2012 BIM Guidelines Michael R. Bloomberg, Mayor David J. Burney, FAIA, Commissioner David Resnick, AIA, Deputy Commissioner TABLE OF Contents Message

More information

Schematic Design: Quality Management Phase Checklist Project Phase Checklist Series

Schematic Design: Quality Management Phase Checklist Project Phase Checklist Series Best Practices : Project Phase Series Contributed by Micheal J. Lough, AIA, Principal, Integral Consulting The AIA collects and disseminates Best Practices as a service to AIA members without endorsement

More information

LANSING COMMUNITY COLLEGE 14205.00 TLC BUILDING SERVER ROOM UPGRADES SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.

LANSING COMMUNITY COLLEGE 14205.00 TLC BUILDING SERVER ROOM UPGRADES SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1. SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings,

More information

LACCD Building Information Modeling Standards For Design-Bid Build Projects

LACCD Building Information Modeling Standards For Design-Bid Build Projects LACCD Building Information Modeling Standards For Design-Bid Build Projects (LACCD BIMS) Interim Version 2.0 Prepared by: September 9, 2009 TABLE OF CONTENTS 1. INTRODUCTION 1 1.1. Overview 1.2. Main Objectives

More information

Exhibit C: Scope of Work and Schedule of Deliverables

Exhibit C: Scope of Work and Schedule of Deliverables Exhibit C: Scope of Work and Schedule of Deliverables Project Scope of Work Phases: A City Hall Envelope Renovations B City Hall Skylight Replacement C City Hall Chiller Replacement D City Hall Annex Plaza

More information

Excerpts from the Canadian National Building Code (NBC)

Excerpts from the Canadian National Building Code (NBC) Excerpts from the Canadian National Building Code (NBC) Reproduced here with Permission of the Copyright Owner, the National Research Council of Canada, Institute for Research in Construction. For more

More information

OPTIONAL IMAGE OR RENDERING OF BUILDING OR SITE

OPTIONAL IMAGE OR RENDERING OF BUILDING OR SITE OPTIONAL IMAGE OR RENDERING OF BUILDING OR SITE MIT BIM Execution Plan v3.2 2 MIT Project Name MIT Project Number DEVELOPED IN COLLABORATION WITH Construction Company Architect AND Engineer MIT BIM Execution

More information

Using the Coordination Monitoring Feature in Revit Structure to Manage Projects Across Disciplines

Using the Coordination Monitoring Feature in Revit Structure to Manage Projects Across Disciplines Using the Coordination Monitoring Feature in Revit Structure to Manage Projects Across Disciplines John Herridge, AIA Autodesk, Inc. SE204-1 Intended for existing Revit users, this session explores the

More information

Design without compromise. Autodesk Revit. Architecture 2010

Design without compromise. Autodesk Revit. Architecture 2010 Design without compromise. Autodesk Revit Architecture 2010 BIM Simply a Better Way of Working Deliver projects faster, more economically, and with enhanced potential for reduced environmental impact.

More information

University of Northern Iowa Design Documents Standards. October 2014

University of Northern Iowa Design Documents Standards. October 2014 University of Northern Iowa Design Documents Standards October 2014 2014 UNI BUILDING AND DESIGN STANDARDS 1.1 CONTRACT DOCUMENT FORMAT 1.1.1 The Electronic Word Programs used for the Project manual shall

More information

Certified Instructors & Curriculum

Certified Instructors & Curriculum Our Promise. TPM is dedicated to provide the most extensive and high-quality training programs to help you maximize your investment. Although the investment in time and money may seem substantial, it will

More information

Table of Contents. I Introduction 2. II Definitions & Area Calculation 2. III Room Numbering 7. IV Appendix A 9

Table of Contents. I Introduction 2. II Definitions & Area Calculation 2. III Room Numbering 7. IV Appendix A 9 Table of Contents I Introduction 2 II Definitions & Area Calculation 2 III Room Numbering 7 IV Appendix A 9 I. Introduction A. Purposes The purposes of this document are to: B. Benefits 1. Clarify and

More information

WESTERN MICHIGAN UNIVERSITY

WESTERN MICHIGAN UNIVERSITY WESTERN MICHIGAN UNIVERSITY Facilities Management Department DeVon Miller Building Commissioning Administrator 1 INTRODUCTION DeVon C. Miller, CPMP, LEED AP Building Commissioning Administrator Engineering

More information

Innovative capture and modeling of existing building conditions using 3D laser scanning. Entry B Submission

Innovative capture and modeling of existing building conditions using 3D laser scanning. Entry B Submission Innovative capture and modeling of existing building conditions using 3D laser scanning Entry B Submission Executive Summary As a large owner organization, understanding and developing new technologies

More information

Proceedings of Meetings on Acoustics

Proceedings of Meetings on Acoustics Proceedings of Meetings on Acoustics Volume 19, 2013 http://acousticalsociety.org/ ICA 2013 Montreal Montreal, Canada 2-7 June 2013 Architectural Acoustics Session 5aAAa: Room Acoustics Computer Simulation

More information

T170 Interior Design Technology MTCU Code 61833 Program Learning Outcomes

T170 Interior Design Technology MTCU Code 61833 Program Learning Outcomes T170 Interior Design Technology MTCU Code 61833 Program Learning Outcomes Synopsis of the Vocational Learning Outcomes The graduate has reliably demonstrated the ability to 1. analyze a client's needs

More information

A WORKFLOW ANALYSIS FOR BIM SOFTWARE: ARCHITECTURAL AND MECHANICAL ENGINEERING DEPARTMENT OF ARUP TURKEY

A WORKFLOW ANALYSIS FOR BIM SOFTWARE: ARCHITECTURAL AND MECHANICAL ENGINEERING DEPARTMENT OF ARUP TURKEY ISTANBUL TECHNICAL UNIVERSITY FACULTY OF ARCHITECTURE DEPARTMENT OF DESIGN COMPUTING BIM 2037 / BUILDING INFORMATION MODELS INSTRUCTOR: Salih OFLUOĞLU A WORKFLOW ANALYSIS FOR BIM SOFTWARE: ARCHITECTURAL

More information

Revised Work Scope Dated April 23 rd, 2015

Revised Work Scope Dated April 23 rd, 2015 Revised Work Scope Dated April 23 rd, 2015 2.4 SCOPE OF SERVICES The following combines the Scope of Services included in RFQ No. 671 dated March 12, 2015 and the Invitation to Interview letter dated March

More information

Practical Strategy and Workflow for Large Projects: A Realistic Solution

Practical Strategy and Workflow for Large Projects: A Realistic Solution Practical Strategy and Workflow for Large Projects: A Realistic Solution Marco Brasiel/Diego Faria Frazillio & Ferroni SE3193 This class presents a strategy for development of structural projects using

More information

Building Information Modeling for MEP Engineering. Revit MEP 2008

Building Information Modeling for MEP Engineering. Revit MEP 2008 Building Information Modeling for MEP Engineering Revit MEP 2008 Design Intuitively with Tools That Work the Way Engineers Think Revit MEP software is an intuitive design tool that works the way engineers

More information

NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES. Level III Content Outline

NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES. Level III Content Outline Fire Alarm Systems Level III Content Outline The skills and knowledge listed under each task are suggestive of those involved in that task, but are not intended to constitute an exhaustive listing. 3.1

More information

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES A. The Owner will contract separately and directly for the majority of the commissioning work

More information

BIM UNDERSTANDING THE PROCESS The State of the Art Tool in Design and Construction SPONSORED BY SAME, DC POST IN ASSOCIATION WITH ACEC M/W

BIM UNDERSTANDING THE PROCESS The State of the Art Tool in Design and Construction SPONSORED BY SAME, DC POST IN ASSOCIATION WITH ACEC M/W BIM UNDERSTANDING THE PROCESS The State of the Art Tool in Design and Construction SPONSORED BY SAME, DC POST IN ASSOCIATION WITH ACEC M/W Insanity: doing the same thing over and over again and expecting

More information

Getting Started with BIM (Building Information Modeling)

Getting Started with BIM (Building Information Modeling) Getting Started with BIM (Building Information Modeling) Curt Egli Synergis Building Solutions Engineer Session Summary This session will walk you through issues you should consider when strategizing,

More information

DIA Survey Requirements. Thomas Breitnauer, PLS thomas.breitnauer@flydenver.com DIA Land Surveyor December 10, 2014

DIA Survey Requirements. Thomas Breitnauer, PLS thomas.breitnauer@flydenver.com DIA Land Surveyor December 10, 2014 DIA Survey Requirements Thomas Breitnauer, PLS thomas.breitnauer@flydenver.com DIA Land Surveyor December 10, 2014 Survey Requirements - During Pre-Construction meeting - Contractor should receive a survey

More information

Building Information Modeling Management To Facility Management

Building Information Modeling Management To Facility Management To Building Information Modeling Management To Facility Management I: INTRODUCTION - aaecs Team Thomas J. Jeff Prine, CCM, LEED AP COO Program / Facility Management Specialist Bonnie K. Gorman, Assoc.

More information

Using the Autodesk Revit GSA Spatial Template

Using the Autodesk Revit GSA Spatial Template Autodesk Revit Template for the U.S. General Services Administration Using the Autodesk Revit GSA Spatial Template This document helps you to get started in using the GSA Spatial Template Revit file in

More information

Building Commissioning 17900-1

Building Commissioning 17900-1 SECTION 17900 BUILDING COMMISSIONING PART 1 - GENERAL 1.01 WORK DESCRIPTION: A. General: 1. The Commissioning process is a joint team effort to ensure that all mechanical equipment, controls, and systems

More information

PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT

PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT - INTRODUCTION 1.1. General. Kuwait Ports Authority (KPA) through the Ministry Of Finance (MOF) wishes

More information

The Shorten AutoCAD the road solution for mechanical, electrical, to done. and plumbing engineering. AutoCAD AutoCAD.

The Shorten AutoCAD the road solution for mechanical, electrical, to done. and plumbing engineering. AutoCAD AutoCAD. The Shorten AutoCAD the road solution for mechanical, electrical, to done. and plumbing engineering. AutoCAD AutoCAD Civil 3D MEP 2009 More Productivity, Same Skills Michigan-based Peter Basso Associates

More information

Getting More Value from your BIM Process with Autodesk Collaboration and Data Management Products

Getting More Value from your BIM Process with Autodesk Collaboration and Data Management Products Autodesk Vault Professional 2014 Getting More Value from your BIM Process with Autodesk Collaboration and Data Management Products Building Information Modeling (BIM) is a process that relies on intelligent

More information

Autodesk Revit Architecture. Design without compromise.

Autodesk Revit Architecture. Design without compromise. Autodesk Revit Architecture Design without compromise. Definitive Design From conception to construction documentation, design projects within an intuitive environment. Building information modeling and

More information

RESOURCE GUIDE. A guide for implementing Building Information Modeling in State of Maryland and Washington DC public school construction projects

RESOURCE GUIDE. A guide for implementing Building Information Modeling in State of Maryland and Washington DC public school construction projects BIM RESOURCE GUIDE A guide for implementing Building Information Modeling in State of Maryland and Washington DC public school construction projects First Draft May 213 ASBO MD/DC BIM COMMITTEE MEMBERS

More information

Turner Innovation Series BIM Conference Istanbul May 2012. Brian Krause, Dan Gramer, Turner Construction Company

Turner Innovation Series BIM Conference Istanbul May 2012. Brian Krause, Dan Gramer, Turner Construction Company 1 Why BIM? Excessive Re-Work and Waste TURNER INNOVATION SERIES May 2012 BIM for Design, Preconstruction, & Construction Brian Krause Manager, Integrated Building Solutions bkrause@tcco.com Value Value

More information

Effective Collaboration using Revit Structure and AutoCAD MEP

Effective Collaboration using Revit Structure and AutoCAD MEP REVIT STRUCTURE Effective Collaboration using Revit Structure and AutoCAD MEP This white paper explains how structural engineers using Revit Structure software and mechanical/electrical/plumbing (MEP)

More information

Multi-user Collaboration with Autodesk Revit Worksharing

Multi-user Collaboration with Autodesk Revit Worksharing AUTODESK REVIT WHITE PAPER Multi-user Collaboration with Autodesk Revit Worksharing Contents Contents... 1 Autodesk Revit Worksharing... 2 Starting Your First Multi-user Project... 2 Autodesk Revit Worksets...

More information

Building Measurement Services

Building Measurement Services Building Measurement Services Robert Parfet Excerpt from The Architect s Handbook of Professional Practice, Update 2003 Building owners and landlords need accurate measurements and area calculations to

More information

5.2 Drawing Information. 0400 Consultants Procedure Manual. 5.2 Drawing Information: 5.2.2 Large Format Document Standards: Page 1 of 5

5.2 Drawing Information. 0400 Consultants Procedure Manual. 5.2 Drawing Information: 5.2.2 Large Format Document Standards: Page 1 of 5 Page 1 of 5 5.2 : 5.2.1 General Information:.1 Final drawings for all projects shall be one of the following sizes: 11" x 17", 24" x 36" or 30" x 42". The dimensions refer to the outside edge or cut line.

More information

Collaboration. Jason Howden. Archaus Architects

Collaboration. Jason Howden. Archaus Architects Jason Howden Archaus Architects Over View Why Collaborate? Basic Principles Coordination of Architectural, Structural and MEP Disciplines Interference and Clash Detection Copy Monitor Best Practise Data

More information

d e n v e r a r t m u s e u m

d e n v e r a r t m u s e u m d e n v e r a r t m u s e u m The Denver Art Museum Expansion will be a dramatic addition to the downtown Denver skyline and will help place Denver among the top art centers in the nation. The new addition

More information

Design without compromise. Autodesk Revit. Architecture

Design without compromise. Autodesk Revit. Architecture Design without compromise. Autodesk Revit Architecture Definitive Design From conception to construction documentation, design projects within an intuitive environment. Building information modeling and

More information

GUIDELINES FOR AUGUST 1995

GUIDELINES FOR AUGUST 1995 GUIDELINES FOR ELECTRICAL ENGINEERING SERVICES AUGUST 1995 PUBLISHED BY: PROFESSIONAL ENGINEERS AND GEOSCIENTISTS OF NEWFOUNDLAND & LABRADOR (PEGNL) P.O. Box 21207, St. John's, NL A1A 5B2 Telephone: (709)

More information

Guide, Instructions and Commentary to the 2013 AIA Digital Practice Documents

Guide, Instructions and Commentary to the 2013 AIA Digital Practice Documents Guide, Instructions and Commentary to the 2013 AIA Digital Practice Documents AIA Document E203 2013, Building Information Modeling and Digital Data Exhibit AIA Document G201 2013, Project Digital Data

More information

BIM for Interior Designers BIM IN PRACTICE

BIM for Interior Designers BIM IN PRACTICE 8 BIM for Interior Designers BIM IN PRACTICE 8 BIM for Interior Designers Contributors: Julia Allen, Geyer Dominik Holzer, AEC Connect Edited by Belinda Hodkinson, SKM BIM utreach 1 Educating Clients -

More information

New Zealand BIM Handbook Appendix D - BIM Uses definitions July 2014. A guide to enabling BIM on building projects

New Zealand BIM Handbook Appendix D - BIM Uses definitions July 2014. A guide to enabling BIM on building projects New Zealand BIM Handbook Appendix D - BIM Uses definitions July 2014 A guide to enabling BIM on building projects Appendix D BIM USES DEFINITIONS CONTENTS BIM Uses 2 Existing Condition Modelling... 4 Cost

More information

Transition to 3D Fabrication Workflows

Transition to 3D Fabrication Workflows Autodesk Autodesk Fabrication Solutions Transition to 3D Fabrication Workflows Autodesk is committed to the use of Building Information Modeling (BIM) to drive integrated and connected data across the

More information

Fire Alarm Systems Certification

Fire Alarm Systems Certification Fire Alarm Systems Certification The skills and knowledge listed under each task are suggestive of those involved in that task, but are not intended to constitute an exhaustive listing. 2.1 Submittal Preparation

More information

Building Information Modeling (BIM) Requirements for PT Projects Today s Capabilities for a BIM based Design

Building Information Modeling (BIM) Requirements for PT Projects Today s Capabilities for a BIM based Design Building Information Modeling (BIM) Requirements for PT Projects Today s Capabilities for a BIM based Design Florian Aalami CEO ADAPT Corporation florian@adaptsoft.com What is BIM? The ability to model

More information

CAD Standards. Design Guidelines and Standards. June 2004. Office of the University Architect

CAD Standards. Design Guidelines and Standards. June 2004. Office of the University Architect Design Guidelines and Standards CAD Standards June 2004 Office of the University Architect Construction Management P.O. Box 210181 Cincinnati, Ohio 45221-0181 Table of Contents Contents CAD STANDARDS Introduction...

More information

Delaware Community Schools

Delaware Community Schools REQUEST FOR PROPOSALS GUARANTEED ENERGY SAVINGS and Facility Improvement Program November 4, 2009 Table of Contents I. Request For Proposal... 3 II. Time Line... 4 III. Proposal Content and Format... 5

More information

Commercial Building Permit Application & Submittal Guidelines

Commercial Building Permit Application & Submittal Guidelines Building Inspection Department 1625 13 th Street, Suite 106 Lubbock, Texas 79457 (806) 775-2087 (806) 775-2088 http://buildinsp.ci.lubbock.tx.us/ Commercial Building Permit Application & Submittal Guidelines

More information

PROJECT REQUIREMENT, PR 20 VIRTUAL DESIGN & CONSTRUCTION (VDC), BUILDING INFORMATION MODEL (BIM)

PROJECT REQUIREMENT, PR 20 VIRTUAL DESIGN & CONSTRUCTION (VDC), BUILDING INFORMATION MODEL (BIM) PROJECT REQUIREMENT, PR 20 VIRTUAL DESIGN & CONSTRUCTION (VDC), BUILDING INFORMATION MODEL (BIM) A. GENERAL: 1. Summary: Design/Builder will employ VDC and BIM tools to facilitate the construction, coordination,

More information

From 3D Laser Scanning to Revit. Processes, Products and Questions

From 3D Laser Scanning to Revit. Processes, Products and Questions From 3D Laser Scanning to Revit Processes, Products and Questions Topics Scanning Overview Recommended Processes Best Practices Up-front questions to ask Tools and Technologies, including the new Scan

More information

BIM. Guidelines & Standards for Architects, Engineers, and Contractors. Initiated: Sept. 10th, 2009. Revised: July 1st, 2015

BIM. Guidelines & Standards for Architects, Engineers, and Contractors. Initiated: Sept. 10th, 2009. Revised: July 1st, 2015 BIM Guidelines & Standards for Architects, Engineers, and Contractors Initiated: Sept. 10th, 2009 Revised: July 1st, 2015 Acknowledgements Indiana University is indebted to those many organizations that

More information

Collaborating Across Disciplines with Revit Architecture, MEP, and Structure

Collaborating Across Disciplines with Revit Architecture, MEP, and Structure Collaborating Across Disciplines with Revit Architecture, MEP, and Structure David Cohn AB104-3 Are you ready to take the next step and use building information modeling to share data across the entire

More information

BIM Implementation Strategies

BIM Implementation Strategies BIM Implementation Strategies Howard Ashcraft Senior Partner Hanson Bridgett Dennis R. Shelden, Ph.D. Chief Technology Officer Gehry Technologies Who we are Dennis R. Shelden, Ph.D., Chief Technology Officer

More information

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1

More information

COMMON FOR ARCHITECTS AND ENGINEERS Excerpts from HB 2284, 82 nd R

COMMON FOR ARCHITECTS AND ENGINEERS Excerpts from HB 2284, 82 nd R Legislation passed by the 82 nd legislature has modified the Texas Engineering Practice Act and the Texas Architect Practice Act. In order to give the public a clearer understanding of these changes, the

More information

SUPPLEMENTAL TERMS AND CONDITIONS TO STATE FORM SC-5.1TC ARCHITECT/ENGINEER AGREEMENT TERMS AND CONDITIONS DESIGN/BID/BUILD

SUPPLEMENTAL TERMS AND CONDITIONS TO STATE FORM SC-5.1TC ARCHITECT/ENGINEER AGREEMENT TERMS AND CONDITIONS DESIGN/BID/BUILD ATTACHMENT 2 UNIVERSITY OF COLORADO BOULDER SUPPLEMENTAL TERMS AND CONDITIONS TO STATE FORM SC-5.1TC ARCHITECT/ENGINEER AGREEMENT TERMS AND CONDITIONS DESIGN/BID/BUILD Table of Contents, Exhibits Delete

More information

CPIx on Line. Post Contract-Award Building Information Modelling (BIM) Execution Plan (BEP) Supporting the HMG Construction Strategy.

CPIx on Line. Post Contract-Award Building Information Modelling (BIM) Execution Plan (BEP) Supporting the HMG Construction Strategy. CPIx on Line Post Contract-Award Building Information Modelling (BIM) Execution Plan (BEP) Project Name: Project Address: Project Number: Date: Document No: Date: March 2013 Revision: R1 Status: Published

More information

Capital Project Delivery Handbook

Capital Project Delivery Handbook Capital Project Delivery Handbook Volume One Facilities Planning & Construction 1 FACILITIES PLANNING & CONSTRUCTION 3/8/09 2 FACILITIES PLANNING & CONSTRUCTION 1. WELCOME TO FACILITIES PLANNING & CONSTRUCTION...

More information

Request for Qualifications 2015-162

Request for Qualifications 2015-162 Kitsap County Human Services Department Request for Qualifications 2015-162 Architectural and Project Management Services - Kitsap County Work Release Facility Remodel Response Deadline: November 17, 2015

More information

CME 405 Building Information Modeling for Construction Management 3 Credits (3 Lecture Hours)

CME 405 Building Information Modeling for Construction Management 3 Credits (3 Lecture Hours) CME 405 Building Information Modeling for Construction Management 3 Credits (3 Lecture Hours) Lecture Meets in 154 Baker Hall, Monday, Wednesday, and Fridays 9:30-10:25 AM Instructor Paul Crovella 219

More information

DESIGN IS GOOD BUSINESS

DESIGN IS GOOD BUSINESS COMPENSATING YOUR ARCHITECT The creature comforts are one thing, but for a house to become a home it s got to be elevated to the point that it s about raising one s spirits as well. SAMUEL MOCKBEE Building

More information

Request for Proposal Autodesk CAD Support

Request for Proposal Autodesk CAD Support Request for Proposal Autodesk CAD Support Introduction Denver Water is inviting your firm to submit a proposal to provide Autodesk product-based services and support to meet the requirements of Denver

More information

THIS PAGE INTENTIONALLY LEFT BLANK

THIS PAGE INTENTIONALLY LEFT BLANK Facilities Management June 29, 2015 THIS PAGE INTENTIONALLY LEFT BLANK Page 2 of 31 CAD Guidelines and Standards Table of Contents SECTION 1: THE PURPOSE OF USING CAD DATA STANDARDS... 5 1.1 Industry Standards...

More information

NECESSITY OF SCHOOL CONSTRUCTION STAGE III DESIGN REVIEWS

NECESSITY OF SCHOOL CONSTRUCTION STAGE III DESIGN REVIEWS NECESSITY OF SCHOOL CONSTRUCTION STAGE III DESIGN REVIEWS Rhode Island Department of Education School Building Authority 255 Westminster Street, Providence, RI 02909 Telephone (401)222-4600 Website: www.ride.ri.gov

More information

BIM and Digital Fabrication

BIM and Digital Fabrication REVIT BUILDING INFORMATION MODELING BIM and Digital Fabrication This whitepaper examines how structural building information models are being used for the digital fabrication of structural steel and the

More information

Request for Proposal East Tower Nursing Unit and Infrastructure Upgrade Grossmont Hospital

Request for Proposal East Tower Nursing Unit and Infrastructure Upgrade Grossmont Hospital Request for Proposal East Tower Nursing Unit and Infrastructure Upgrade Grossmont Hospital June 21, 2007 The Grossmont Healthcare District (GHD) will accept proposals for Architectural and Engineering

More information

NUMBER 107-011-100 EFFECTIVE DATE. July 23, 2003

NUMBER 107-011-100 EFFECTIVE DATE. July 23, 2003 STATEWIDE POLICY NUMBER 107-011-100 EFFECTIVE DATE SUPERSEDES Policy 125-6-100 July 23, 2003 PAGE NUMBER Division Enterprise Asset Management July 23, 2003 Pages 1 of 9 REFERENCE ORS 276.004 and other

More information

APPENDIX E GUIDELINES FOR PREPARING CAPITAL PROJECT COST ESTIMATES

APPENDIX E GUIDELINES FOR PREPARING CAPITAL PROJECT COST ESTIMATES APPENDIX E GUIDELINES FOR PREPARING CAPITAL PROJECT COST ESTIMATES The capital project cost estimate is a tool to assist agencies and institutions in creating a project construction budget. It can also

More information

Covance Construction Management Staffing Plan Chandler, Arizona

Covance Construction Management Staffing Plan Chandler, Arizona INTRODUCTION: This Construction Management (CM) Staffing Plan has been prepared for Covance to identify the critical organizational structure necessary to successfully complete the Chandler project according

More information

Coordinating and Sharing Information with Revit Architecture and Revit Structure Best Practices!

Coordinating and Sharing Information with Revit Architecture and Revit Structure Best Practices! Revit Architecture and Revit Structure Best Practices! Erleen Hatfield Thornton-Tomasetti Uk Jung SE304-1 This class identifies best practices using Revit Architecture and Revit Structure for sharing and

More information

Phased Building Information Management (BIM) and Modeling Implementation Plan. David J. Gutierrez, AIA September, 2014

Phased Building Information Management (BIM) and Modeling Implementation Plan. David J. Gutierrez, AIA September, 2014 Phased Building Information Management (BIM) and Modeling Implementation Plan David J. Gutierrez, AIA September, 2014 1 Current State: Design and construction data is not shared, maintained, or updated

More information

ADDENDUM NUMBER ONE (1)

ADDENDUM NUMBER ONE (1) Page 1 of 1 MINNESOTA DEPARTMENT OF TRANSPORTATION Office of Maintenance: Building Services Section ADDENDUM NUMBER ONE (1) ADDENDUM DATE: 19 October 2012 Request for Proposals for Designer Selection for

More information

BIM Department. BIM Modeling Using Faro Focus3D Laser Scanner

BIM Department. BIM Modeling Using Faro Focus3D Laser Scanner BIM Modeling Using Faro Focus3D Laser Scanner Contents What is Laser Scanning? Advantages of Laser Scanning BIM Workflow Process Scanner Unit Set-up and Scanning Processing Scan Files BIM Software Creating

More information

Construction Management Standards of Practice

Construction Management Standards of Practice Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388

More information

What s New in Autodesk Revit 2014

What s New in Autodesk Revit 2014 Building Design Suite 2014 What s New in Revit 2014 * Revit 2014 software is only available as part of the Building Design Suite 2014 Premium and Ultimate Editions. New & Enhanced Features Platform & For

More information

Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344

Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344 Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344 Table of Contents SERIES DEFINITION... 2 EXCLUSIONS... 2 OCCUPATIONAL INFORMATION... 3 TITLES... 6 EVALUATING

More information