Detailed Estimation and Pumpstation Overview. Nathaniel Osgood 3/3/2004
|
|
|
- Jocelyn McDowell
- 9 years ago
- Views:
Transcription
1 Detailed Estimation and Pumpstation Overview Nathaniel Osgood 3/3/2004
2 Announcements TP2 Due Date: March 15 PS4 out tonight Due March 19 Team project Recording of recitation Pietroforte Lecture Important lecture will link to PS 4 Seminars March 16 th & 22 nd
3 Recall the Estimation Phases
4 Detailed Estimates - Methodology After most or all of the detail design work is complete, approximate estimates are supplemented by detailed estimates Stage 1: Quantity takeoff Measurement of material & Labor quantities Quantities usually recapped by trade for control reasons Stage 2: Direct Cost contribution Σ[Quantity] x [Unit Costs] = Estimated direct cost of construction
5 Notes on Detailed Estimates Have differing ranges of uncertainties Distributions typically asymmetric More an art than a science or bookkeeping Detailed quantitative estimates possible but ignore important qualitative factors Wealth of trade-specific and method-specific detail complexity Frequently depends heavily on subcontractor estimates (opaque quotes)
6 Important General Lesson Precision in detailed estimated does not mean accuracy! Two types of complexity at issue Detail complexity (myriad components required) System complexity (dynamic interactions, etc.) Always consider: What are assumptions behind the estimate? What factors are being ignored? How might these factors change the estimate?
7 Cost Classification Direct Cost Labor Cost Material Cost Equipment Cost ST&S Expenses Indirect Cost ( Overhead ) Interest on loans Trailer rental Office costs AC/heat Planning&logistics Supervision
8 Overhead Costs Project Overhead Project specific Management staff, Utilities, Supplies, Engineering, Tests, Drawings, Rents, Permits, Insurance Can and should be estimated directly Can be quite uncertain (mgmt sub. quality, time, etc.) Firm Overhead General office Salaries, office rent, utilities, insurance, taxes, shops/storage yards, other expenses Hard to estimate; often use % multiplier Sometimes distinction unclear (e.g. lumpy central-office investments)
9 Project Organization Estimation Introduction Conceptual Estimation Cost indices Cost-capacity factors Component ratios Parameter costs Detailed Estimation Quantity Takeoff Labor Cost Estimation Probabilistic methods
10 Fair-Cost Estimates Prepared from the actual bid documents provided to the bidders (before award) Used by owner s representative to evaluate changes (after award) May use RS Means or other sources No lump-sum subcontract quotations Somewhat diff. disaggregation than bid May be simplified number of line items May be more detailed in certain breakdowns (related to subcontractor work) Primary basis for measuring job progress, for scheduling and for cost control.
11 Contractor s Bid Estimate Low enough to obtain the work, yet high enough to make profit Often relies on Historical Historical productivity data for company Intuition Intuition on speed of movement Quantity Quantity takeoff for most important items Sometimes less detailed than fair-cost estimates - subcontractors from 30% to 80% of the project Is estimating a streamlined process? A look at bids received for a typical project in a competitive area will sometimes show more than 50% difference between the low and the high bidders
12 Definitive Estimates There comes a time when a definitive estimate can be prepared that will forecast the final project cost with little margin for error This error can be minimized through the proper addition of an evaluated contingency Four categories for purposes of reviewing definitive estimates: Traditional Design-Build Professional CM Unit-price
13 Definitive Estimates - Traditional Lump-sum - definitive estimate = low bidder s quotation + evaluated contingency Fast track guaranteed maximum price, cost- plus-a-fee Definitive estimate will need Detailed project and specifications Firm material quotations Subcontractor quotes Prices for major equipment
14 Definitive Estimates Design-Build Lump-sum, guaranteed maximum price, cost- plus-a-fee Lump-sum can be misleading to an unknowledgeable owner. The cost is known but the facility that is going to be delivered is unknown In guaranteed maximum price and cost-plus plus-a-fee contracts the definite estimates can be obtained earlier if compared to the traditional approach because one entity is performing both design and construction
15 Definitive Estimates - CM The definitive estimate can be accurately prepared about the same time as the guaranteed-maximum or cost-plus plus-a-fee option under traditional approach Examples show that is possible to develop definitive estimates after the detailed design is about 95% complete.
16 Definitive Estimates Unit Price Unit-Price Projects: Usually heavy construction projects like dams, tunnels, highways, and airports - Prices constants while quantities vary within limits inherent in the nature of work. Quantities may overrun or underrun owing to a number of potential causes such as additional foundation, excavation to solid rock, poor ground conditions, etc. Without reliable geological information the final cost may not be known accurately until the end of the project
17 Project Organization Estimation Introduction Conceptual Estimation Cost indices Cost-capacity factors Component ratios Parameter costs Detailed Estimation Quantity Takeoff Labor Cost Estimation Probabilistic methods
18 Quantity Takeoff Really requires thinking! Systematic identification of quantities of materials and work required Key features sought Exhaustive Mutually exclusive Used to calculate several factors Amount of material (e.g. concrete CY) Equipment utilization Labor Breakdown often uses CSI or WBS taxonomies
19 Quantity Takeoff Subtleties I Elements required by construction method E.g. construction joints Reuse of materials and equipment influenced by Specification Schedule (itself being estimated, adjusted) Space (can complicate or prevent concurrency e.g. adequate space for 2 cranes? 2 people?) Must estimate both Cost & Time Sometimes requires iteration Hidden dependencies of cost on schedule
20 Quantity Takeoff Subtleties II Division between different parties Easy to think other party taking care of particular elements E.g. think excavation cost is included in unit cost of piping Choice of construction approach has big impact Estimation of labor costs particularly tricky Prices: In United States, highly detail intensive Productivity: Many qualitative components Impact of Type I vs Type II error
21 Project Organization Estimation Introduction Conceptual Estimation Cost indices Cost-capacity factors Component ratios Parameter costs Detailed Estimation Quantity Takeoff Labor Cost Estimation Probabilistic methods
22 Labor Estimation Most subtle, tricky For easy transferability, should separate into Q: Unit (Quantity) P: $/hour (Labor Price per hour) W: hour/unit (Labor hours per unit -- productivity) Total cost $ = Q * P * W
23 Labor Price Estimation (P) Components Wages (varies by area, jurisdiction, seniority, ) Insurance (varies w/contractor record, work type) Social security (FICA; ½ by employer, employee) Unemployment tax (state) Fringe benefits (apprenticeship, vacation, health ) Wage premiums
24 For shift work Wage Premiums Sometimes adjust hours Overtime 1.5-3x for overtime Some crafts paid overtime if over 32 hours Hazardous/arduous work Work on swinging scaffold Larger crane Underground work
25 Further Issues Complicated, heterogeneous rules, exceptions throughout US complicate estimation Probably more complicated than for other industries Problem particularly acute for union shops Frequently combine into crew-based estimate Reason about price of standard crew Helps factor in labor rules Quite substantial variation between contractors in how handle
26 Labor Productivity Estimation (W) Difficult but critical High importance of qualitative factors (environment, morale, fatigue, learning, etc) The primary means by which to control labor costs Historical data available Department of Labor, professional orgs, state govs..)
27 Productivity Considerations Considerations Location of jobsite (local skill base, jurisdiction rules) Learning curves Work schedule (overtime, shift work) Weather Elaborate work-arounds arounds,, costs Environment Location on jobsite, noise, proximity to matereials Management style Worksite rules
28 Common Productivity Variations Productivity Job Factors for Comparable Installations Building Construction Nonworking supervision Craft skill Job conditions Work conditions Shift work Total building range Industrial Construction Light industrial Heavy industrial Total industrial range Nuclear Power Plants Pre-Three Mile Island Post-Three Mile Island Total nuclear power plant range 1.0 to to to to to to to to to to to to 5.00
29 Learning Curves
30 Productivity Effects of Overtime
31 Project Organization Award Methods General points Bidding Negotiation Lifecycle Costing Estimation Introduction Conceptual Estimation Cost indices Cost-capacity factors Component ratios Parameter costs Detailed Estimation Quantity Takeoff Labor Cost Estimation Probabilistic methods
32 Successive Estimation Top-down approach to rapid estimation Identify Expected value and variance Irreducible uncertainty due to external factors Overall variance is Σ of variance of components Break down highest variance items More detail lowers variance Result: Frequently only have to estimate small portions of total project to get good estimate
33 Range Estimation Estimate Low-Mean Mean-High of bids will receive Estimate range of uncertainty for entire project based on this Can use to reason about confidence intervals
34 Quantity Take-off Assignment 3: Introduction Assignment 3: Example Construction Drawings Construction Methods
35 Assignment 2: What to measure? Formwork (Square Feet) Formwork Formwork Add-on s: Anchor Bolts Joint Filler Chamfer PVC waterstop Construction Joints For the Wet Well Floor For the Operating Floor For Internal walls and partitions (qty) (Linear Feet) (Linear Feet) (Linear Feet) (Linear Feet)
36 How is it constructed? 1. Install Formwork 2. Install rebar 3. Pour concrete 4. Finish it (small slopes etc.) 5. Wait & Repeat (construction joints) 6. Uninstall formwork 7. Point & Patch, Rub Think from bottom to top GRAVITY RULES!
37 Construction Drawings Navigation Drawing Title Cross Section Detail
38 Take-off Template Characterize each object you measure (Description) Specify which plane you measure Specify dimensions of the ENTIRE object Try to keep North consistent Formwork Total (SF) Sum b f b a b c a Sketch 1 Sketch 2 c c a Sketch 3 d Item Description Drawings Sketch a b c 1 Invert Edge Form Sum Qty or d Units Quantity Deriver Signoff
39 Example: Define an object Item Description 1 Invert Edge Form a Invert Slab (bottom) b Invert Slab (W & E sides) c Invert Slab (N & S sides) d
40 Example: Find relevant drawings
41 Example: Define Planes & Dimensions Sides of Invert Slab S-1101, S SF 1,182.0
42 Casting a concrete slab on grade Sequence: 1. Form and edges 2. Reinforcement and embedment 3. Striking off or straightedge 4. Floating (if smoother surface is needed) 5. Control joints 6. Troweling (if very smooth surface is needed) 7. Curing (under damp conditions) (You are not responsible for this formwork in the assignment)
43 Casting a concrete wall Sequence: 1. Coated form (one side only) 2. Reinforcing 3. Ties and inspection 4. Coated form (2 side) 5. Placing concrete 6. Curing 7. Stripping of formwork and snapping off ties 8. Point and Patch 9. Rub
How to Estimate the Cost of Interior Building Finishes from Schematic Drawings. CPE Candidate No. 0714108. December 2014
How to Estimate the Cost of Interior Building Finishes from Schematic Drawings CPE Candidate No. 0714108 December 2014 1 How to Estimate the Cost of Interior Building Finishes from Schematic Drawings Table
Pricing of Construction Contract Change Order Documentation
The contract language contained in this Exhibit will supplement and take precedence over all other change order pricing contract provisions in the Contract Documents provided by the Owner, Design-Builder
LECTURE 10. Resource Allocation and Resource Leveling
LECTURE 10 Resource Allocation and Resource Leveling OUTLINE Review Lecture 9 Introduction The Three Categories Of Resources What Is Resource Allocation? What Is Resource Leveling? Why Level Resources?
PROJECT COST ESTIMATES & FEASIBILITIES
PROJECT COST ESTIMATES & FEASIBILITIES Project Cost and budget management Project success elements Scope meet the scope defined for the project Budget It is within established budget Programme It is designed
The Task. for. PERI Construction-Exercise 2003
The Task for PERI Construction-Exercise 2003 Entitled to participate all educational institutions for civil engineering and construction management. The work must be based on the outlined project and can
How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013
How to Estimate the Cost of Support of Excavation for Foundation Installation CPE Candidate No. 0113013 May 15, 2013 1 How to Estimate the Cost of Support of Excavation for Foundation Installation Table
Cost Estimating Concepts
Cost Estimating Concepts Goal to provide an overview of cost estimating (CE) concepts in order to review CEs prepared by others or to create alternative CEs Why? financial assurance provision based upon
Introduction PURPOSE OF THIS BOOK
1 C H A P T E R Introduction PURPOSE OF THIS BOOK The purpose of this book is to enable the reader to gain fundamental knowledge of estimating the cost of projects to be constructed. Experienced estimators
CHAPTER 4 TYPES OF COST ESTIMATES
CHAPTER 4 TYPES OF COST ESTIMATES 1. INTRODUCTION All projects, both construction and environmental restoration, require cost estimates to plan and budget the project efficiently. Numerous estimates are
Construction Contract Fundamentals. Baker Tilly refers to Baker Tilly Virchow Krause, LLP,
Construction Contract Fundamentals Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. 2010 Baker Tilly Virchow Krause, LLP About
Civil Engineering & Construction
RoadWorks Civil Infrastructure WaterWorks Contract Services Site Preparation Building Construction Track and Rails Works Concrete Works General contracting Civil Engineering & Construction for Microsoft
CHAPTER 2 QUANTITY TAKE-OFF
CHAPTER 2 QUANTITY TAKEOFF The quantity takeoff is an important part of the cost estimate. It must be as accurate as possible and should be based on all available engineering and design data. Use of appropriate
How to estimate the cost of installing an Electrical Distribution Center (EDC)
How to estimate the cost of installing an Electrical Distribution Center (EDC) Candidate Number 0112233 June 2012 Table of Contents 1) Introduction 3 2) Types and Methods of Measurement 3 5 3) Specific
Estimating Activity Durations CSTM 462
Estimating Activity Durations CSTM 462 Estimate activity durations Activity durations should be estimated based on available resources which include labor, material and equipment. These durations should
PREPARING DETAILED BREAKDOWNS FOR CHANGE ORDER PROPOSALS
PREPARING DETAILED BREAKDOWNS FOR CHANGE ORDER PROPOSALS I. GENERAL A. All work to be performed under the change order must be itemized, including the work of all subcontractors. B. Items must be relevant
Project Organization. System and Project Management 1.040/1.401J Nathaniel Osgood
Project Organization System and Project Management 1.040/1.401J Nathaniel Osgood Center for Construction and Research Education Department of Civil and Environmental Engineering Massachusetts Institute
Takeoff and Estimating for Design-Build Contractors
Takeoff and Estimating for Design-Build Contractors Design-build contractors specialize in turnkey projects that vary from one-of-a-kind office buildings to custom residential properties. Each project
SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS
July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional
The minimum reinforcement for the stem wall is the placement of:
PolySteel creates an ideal insulated stem wall for concrete slabs that can make this part of your project easier and faster, in addition to making your finished project more energy-efficient. Figures 3.20
RISK MITIGATION IN FAST TRACKING PROJECTS
Voorbeeld paper CCE certificering RISK MITIGATION IN FAST TRACKING PROJECTS Author ID # 4396 June 2002 G:\DACE\certificering\AACEI\presentation 2003 page 1 of 17 Table of Contents Abstract...3 Introduction...4
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson E: Risk and Procurement Management Presented by Sam Lane [email protected] Ph: 703-883-7149 Presented at the IPM 2002 Fall Conference Prepared by the Washington,
Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06
SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable
After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE
86 :: Certificate in Construction Supervision (CIVIL) 12 ROOF 12.1 INTRODUCTION The structure provided to cover the house surface (floor) is known as roof. For different situation and requirement, it is
HOW TO ESTIMATE THE COST OF A COMMERCIAL FIRE ALARM SYSTEM
HOW TO ESTIMATE THE COST OF A COMMERCIAL FIRE ALARM SYSTEM By Robert Tranford DATE WRITTEN: MAY 25, 2004 The author is Robert Tranford. He obtained an Electrical Masters in 1981. He then founded and served
Product Comparison. www.sageestimating.com 800-628-6583. Windows Technology. Spreadsheet. Estimate Management. Takeoff
The Sage Estimating application is available in two levels: Estimating and Estimating. The following chart describes the key features and capabilities differentiating the two products. Windows Technology
SOMETIMES the cost of installing a landscape plan
Pricing the Landscape Plan SOMETIMES the cost of installing a landscape plan can be quite shocking for those not familiar with all the elements of a landscape. When one breaks down the various expenses
CONSTRUCTION CONTRACT TERMINOLOGY
PAGE 1 ALLOWANCE - in bidding, an amount budgeted for an item for which no exact dollar amount if available; a contingency for unforeseen costs; the classification of connected parts or members according
How to Estimate the Cost of HIGHRISE CAST IN PLACE FLAT SLAB CONSTRUCTION. Peter M Hamilton July 2015
How to Estimate the Cost of HIGHRISE CAST IN PLACE FLAT SLAB CONSTRUCTION Peter M Hamilton July 2015 Peter Hamilton is a Senior Estimator for Tutor Perini Building Corp in New York City. Peter s passion
1.040 Project Management
MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Fred Moavenzadeh Spring 2009
CHAPTER 6 PROJECT CASH FLOW
CHAPTER 6 PROJECT CASH FLOW In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter will deal with project
Contract Administration
Chapter 5 Contract Administration Section 3 Change Orders 5-301 General 5-302 Change Order Policy 5-303 Purpose of Change Orders 5-304 Initiation of Change Orders 5-305 Preliminary Considerations 5-306
Estimate Memorandum/ Basis of Estimate
Estimate Memorandum/ Basis of Estimate To: From: Mary Ann Lasch, FASLA Eric Link, CCT Date: March 14, 2012 Subject: Tiger Grant Pedestrian Walkway and Parking Garage- Conceptual, Rough Order of Magnitude
EVA (C/SCSC) and Basics of Project Control. Nathaniel Osgood 4/7/2004
EVA (C/SCSC) and Basics of Project Control Nathaniel Osgood 4/7/2004 Topics Monitoring cont d EVA (C/SCSC) Definitions and examples Forecasting Project Control General Performance-adjustments adjustments
LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. Table of Contents 1. INTRODUCTION...
TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG [email protected]
TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION PRESENTED BY: BAKANG MOENG [email protected] CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process Contractual arrangement
Reasons for Change Orders
T E X A S D E PA R T M E N T O F T R A N S P O R TAT I O N A change order is defined in the 2004 Standard Specification Book as a written order to the Contractor detailing changes to the specified work,
SUCF PROJECT COST REPORTING GUIDE
SUCF PROJECT COST REPORTING GUIDE State University Construction Fund 353 Broadway / ALBANY, NY 12246 SUCF 900 / 11 Table of Contents Page A. Preface 1 B. Area Takeoff Methodology 1. General 2 2. Net Assignable
Embedded Parts Introduction - Anchors
In the plant construction or process plants such as chemical, petrochemical, gas or power plants various disciplines are brought into contact and built on each other. Civil, mechanical, electro technical
CHAPTER 8 Planning and Budgeting
Copyright 2008 by the Foundation of the American College of Healthcare Executives 6/8/07 Version 8-1 CHAPTER 8 Planning and Budgeting The planning process Budget types Statistics budget Revenue budget
TECHNICAL SPECIFICATIONS CONCRETE SIDEWALKS, DRIVEWAYS AND CURB AND GUTTER
TECHNICAL SPECIFICATIONS CONCRETE SIDEWALKS, DRIVEWAYS AND CURB AND GUTTER I. Scope of Work Work done under this item shall consist of the construction, reconstruction, or alteration of a one-course Portland
SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
Free-Form Concrete Pool
The tranquil beauty and playful shimmer of a reflecting pool or fountain is just the thing to enhance the charm of your garden or patio. Best of all, you can do all the work yourself. Add goldfish or water
Review of 01310 Schedule Specification Requirements District SAP/WBS breakdown Asset template Cost & Resource Loading Stored Material Costs
Agenda Topics: 1. Oracle/Primavera buyout Within the last year, Oracle bought Primavera. Primavera support has been tailored to Oracle s standard. stead of initially speaking to a support representative,
OBJECTIVE To establish procedures for administration of construction manager agreements, including negotiation, contracting and payments.
OP-B-11-D2 ADMINISTRATION OF CONSTRUCTION MANAGER AGREEMENTS SPECIFIC AUTHORITY Sections 240.209(3)(p), 1001.74, 1013.46, F. S. OBJECTIVE To establish procedures for administration of construction manager
CHAPTER 8 PROJECT TIME-COST TRADE-OFF
CHAPTER 8 PROJECT TIME-COST TRADE-OFF In the previous chapters, duration of activities discussed as either fixed or random numbers with known characteristics. However, activity durations can often vary
Sage Estimating. Better Estimates By Every Measure.
Sage Estimating Better Estimates By Every Measure. Industry-Specific Databases Sage Estimating Sage Estimating is powered by tradespecific cost databases, enabling you to turbo-charge takeoffs and final
Evaluation of Building Information Modeling (BIM) Estimating Methods in Construction Education
Evaluation of Building Information Modeling (BIM) Estimating Methods in Construction Education Keith E. Sylvester, Ph.D. and Charlotte Dietrich, Undergraduate Student East Carolina University Greenville,
Document Comparison. AIA Documents A134 2009 and A131CMc 2003
Document Comparison AIA Documents A134 2009 and A131CMc 2003 AIA Document A134 2009 is in the right-hand column. Corresponding sections of AIA Document A131 CMc 2003 are in the left-hand column. Sections
REIMBURSEMENT PROCEDURE for FEMA PUBLIC ASSISTANCE
REIMBURSEMENT PROCEDURE for FEMA PUBLIC ASSISTANCE Financial Assistance Availability The impact of major or catastrophic emergencies can exceed local financial resources. Financial aid and assistance may
VOLUME 4 FINANCIAL OFFER LUMP SUM CONTRACTS. Annex 4.2.1 - Introduction. Annex 4.2.2 - Recapitulation. Annex 4.2.3 - Breakdown of the Lump-sum Price
VOLUME 4 FINANCIAL OFFER LUMP SUM CONTRACTS Annex 4.2.1 - Introduction Annex 4.2.2 - Recapitulation Annex 4.2.3 - Breakdown of the Lump-sum Price Annex 4.2.4 - Daywork Schedule Annex 4.2.5 - Detailed Breakdown
PROJECT PROCUREMENT MANAGEMENT
12 PROJECT PROCUREMENT MANAGEMENT Project Procurement Management includes the processes required to acquire goods and services from outside the performing organization. For simplicity, goods and services,
1.040 Project Management
MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Project Organization Project
Construction Economics & Finance. Module 6. Lecture-1
Construction Economics & Finance Module 6 Lecture-1 Financial management: Financial management involves planning, allocation and control of financial resources of a company. Financial management is essential
Auditing construction contract change orders
Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. Auditing construction contract change orders Presenter Tony Ollmann, CPA,
WORK SCOPE. Domains in which we work:
WORK SCOPE Engineering consulting, technical office, assistance and supervision in industrial works. We specialize in structures, civil works and industrial equipment. Domains in which we work: Industrial
Dynamic Change Management for Fast-tracking Construction Projects
Dynamic Change Management for Fast-tracking Construction Projects by Moonseo Park 1 ABSTRACT: Uncertainties make construction dynamic and unstable, mostly by creating non value-adding change iterations
Note: All dimensions are nominal. All weights are for shipping purposes only. Availability is subject to change.
CHANNEL DrAiNS Durable Designed for maximum durability and drainage, NDS Channel Drains are a proven alternative to traditional concrete drains. UV inhibitors in the grates, channel and component parts
CHANGE ORDER PROTOCOL
CHANGE ORDER PROTOCOL ELECTRI International Prof. Matt Syal, Ph.D., LEED AP Construction Management School of Planning, Design and Construction Michigan State University January 2013 1 M. Syal _2010 PARTS
Hanson Building Products. precast basement solutions
Hanson Building Products precast basement solutions Hanson Building Products Basement Systems Add an extra dimension and combine the inherent flexible, structural and waterproof properties of concrete
HOW TO ESTIMATE THE COST OF T-BAR
HOW TO ESTIMATE THE COST OF T-BAR ACOUSTICAL CEILINGS MICHAEL HILL DATE WRITTEN: MAY OF 2007 The author is Michael Hill, Estimator with Kaiser Foundation Hospitals, National Facilities Services Cost Engineering
Moving Small Mountains Vesuvius Dam Rehab
Moving Small Mountains Vesuvius Dam Rehab Susan L. Peterson, P.E., regional dams engineer, Eastern Region, Bedford, IN Note: The following article, Moving Small Mountains Vesuvius Dam Rehab, by Sue Peterson,
Project Delivery Methods & Contract Types CSTM 102 Spring 2013
Project Delivery Methods & Contract Types CSTM 102 Spring 2013 Schedule February 16- Building Information Modeling February 21- Midterm Review February 23- Midterm In the industry the term Pre-Construction
CHAPTER 5 ESTIMATING WORK ITEMS COSTS, IDIRECT COSTS, MARKUP AND CONTRACT PRICING
CHAPTER 5 ESTIMATING WORK ITEMS COSTS, IDIRECT COSTS, MARKUP AND CONTRACT PRICING The cost of labor, material and equipment expended on the items that were measured in the quantity takeoffs is usually
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Contract Works and What you need to Know
ACN 002 566 743 Brookvale Insurance Brokers Pty Ltd Contract Works and What you need to Know 1. The Need for Contract Works Insurance The growth of large-scale construction projects has been accompanied
PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE
FORM A PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE The following suggested specifications are written as a guide to assist the specifier in writing his own specifications. Specific circumstances
CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION
CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION General 7 www.meadowburke.com 877-518-7665 MB1109 CONCRETE FLOOR SLAB AND CASTING BED CONSTRUCTION Quality Construction Begins at Ground Level Everything
2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS
2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS GENERAL 10/16/2008 The listed average unit prices are based on the
OUTLIER ANALYSIS. Data Mining 1
OUTLIER ANALYSIS Data Mining 1 What Are Outliers? Outlier: A data object that deviates significantly from the normal objects as if it were generated by a different mechanism Ex.: Unusual credit card purchase,
METHOD OF STATEMENT FOR STATIC LOADING TEST
Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents
Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS
Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS 1 Proposal & Plans Received? 2 Review Proposal, highlight important facts. Know proposal well to be able to find answers quickly.
99.37, 99.38, 99.38, 99.39, 99.39, 99.39, 99.39, 99.40, 99.41, 99.42 cm
Error Analysis and the Gaussian Distribution In experimental science theory lives or dies based on the results of experimental evidence and thus the analysis of this evidence is a critical part of the
LOWELL REGIONAL WASTEWATER UTILITY SPECIFICATIONS FOR THE LOWELL MA CONCRETE FLOODWALL REPAIRS
Concrete Repairs LOWELL REGIONAL WASTEWATER UTILITY SPECIFICATIONS FOR THE LOWELL MA CONCRETE FLOODWALL REPAIRS PART 1 - GENERAL 1.01 DESCRIPTION OF WORK A. The work will occur within the City of Lowell
Pricing Your Work (Overhead Recovery Review)
Pricing Your Work (Overhead Recovery Review) To accurately price your work, you need to be aware of three main factors: 1. The Estimate these costs are the direct costs of labor, equipment, materials,
Project Cost Risk Analysis: The Risk Driver Approach Prioritizing Project Risks and Evaluating Risk Responses
Project Cost Risk Analysis: The Risk Driver Approach Prioritizing Project Risks and Evaluating Risk Responses David T. Hulett, Ph.D. Keith Hornbacher, MBA Waylon T. Whitehead Hulett & Associates, LLC Los
AACE International Examinee Format of Definitions Certified Estimating Professional (CEP)
Examinee Format of Definitions Certified Estimating Professional (CEP) The basis behind the selection of terms and definitions is as follows: Estimating Exam Scope The exam will include the following estimating
Introduction to Construction Project/Jobsite Management
Introduction to Construction Project/Jobsite Management Hal Johnston April 23, 2014 Professor Emeritus Construction Management California Polytechnic State University San Luis Obispo, California, US Visiting
OP-B-11-D2 ADMINISTRATION OF CONSTRUCTION MANAGER AGREEMENTS
OP-B-11-D2 ADMINISTRATION OF CONSTRUCTION MANAGER AGREEMENTS SPECIFIC AUTHORITY Sections 240.209(3)(p), 1001.74, 1013.46, F. S. OBJECTIVE To establish procedures for the administration of construction
AGENDA FOR LUNCH SEMINAR WITH FMI AUGUST 28, 2008 12:30 PM INTRODUCTION TO GOVERNMENT CONTRACTING
AGENDA FOR LUNCH SEMINAR WITH FMI AUGUST 28, 2008 12:30 PM INTRODUCTION TO GOVERNMENT CONTRACTING 1. NICRA - What is a NICRA? - Who has a NICRA? - Do I need a NICRA? - How do I get a NICRA? 2. INDIRECT
Bills of Quantity. D. Atkinson December 2000. Nature of Bills
Bills of Quantity D. Atkinson December 2000 Nature of Bills Bills of Quantities comprise a list of items of work which are briefly described. The Bills also provide a measure of the extent of work and
EXHIBIT 2-2-C PROGRESS SCHEDULES
EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,
Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel
Page 1 of 6 ALM Properties, Inc. Page printed from: New York Law Journal Back to Article Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel James E. Hughes New York
SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS
SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS Section Page 36-1 GENERAL... 36.1 36-2 PIPEMAKING EQUIPMENT... 36.1 36-3 TRENCH EXCAVATION... 36.1 36-4 SPECIAL FOUNDATION TREATMENT...
LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD
www.norcalpug.com LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD Bob Fisher and Lance Stracner Ameron Protective Lining J.R. Pipeline Co Inc. Abstract: The
CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING
CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter will
Construction Technologies Career Field Pathways and Course Structure
Courses in Structural Systems (DD) Construction Technologies Career Field Pathways and Course Structure PATHWAY COURSES SUBJECT CODE Construction Technology-Core and Sustainable Construction 1 178000 Carpentry
Estimating Trench Excavation
Estimating Excavation By Steven J. Peterson, PE, MBA Introduction excavation is often performed by hydraulic backhoe excavators. This is because hydraulic excavators are not only good at excavating below
CONCRETE SEGMENTAL RETAINING WALL SYSTEM
CONCRETE SEGMENTAL RETAINING WALL SYSTEM PART 1: GENERAL SPECIFICATIONS 1.01 Work Included A. Work shall consist of furnishing and constructing a Rockwood Vintage TM unit segmental retaining wall (SRW)
SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS
SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING
[Project Name] NZTA Contract No. [Contract Number] Schedule of Prices
[Project Name] NZTA Contract No. [Contract Number] Schedule of Prices Schedule of Prices SP1
COST ESTIMATING METHODOLOGY
NCMA DINNER MEETING TRAINING COST ESTIMATING METHODOLOGY 1 David Maldonado COST ESTIMATING METHODOLOGY TABLE OF CONTENT I. Estimating Overview II. Functional Estimating Methods III. Estimating Methods
10 Steps to Building a More Profitable Construction Business. Leslie Shiner, MBA Sage Certified Consultant
10 Steps to Building a More Profitable Construction Business Leslie Shiner, MBA Sage Certified Consultant Introduction is a pragmatic approach to developing business practices that result in greater profitability.
