CHAPTER 5 ESTIMATING WORK ITEMS COSTS, IDIRECT COSTS, MARKUP AND CONTRACT PRICING
|
|
|
- Philip Norman Austin
- 9 years ago
- Views:
Transcription
1 CHAPTER 5 ESTIMATING WORK ITEMS COSTS, IDIRECT COSTS, MARKUP AND CONTRACT PRICING The cost of labor, material and equipment expended on the items that were measured in the quantity takeoffs is usually referred to as the direct costs of the work. The general expenses of a project comprise all of the additional, indirect costs that are also necessary to facilitate the construction of the project. These indirect costs are sometimes titled general requirements of the project or project overheads. This chapter is devoted for the estimating of different items represents the overheads of a project and also discusses the pricing of the project items after defining both the direct costs and markup values. 5.1 Estimating Work Items Cost Estimating the cost of any work items include estimating the cost of labor, equipment and material. The analysis of a given job requires a thorough review of the plans and specifications of the bid documents, an evaluation of the soil investigation report and a visit to the jobsite where the project is to be constructed. For earthwork estimates, the bid documents usually contain a soil report that provides geotechnical information about the soil and subsurface conditions. The estimator can use other sources that help in developing an accurate estimate Swell and compaction factors To estimate the cost of excavating and hauling earth, it is necessary to know the physical properties of earth because the volume changes during construction operations. For an earth work operation, the soil is excavated from its natural state, placed in a hauling unit Cost Estimating 97 Dr. Emad Elbeltagi
2 and transported to the disposal area, where it is distributed and compacted. For example, one cubic meter of soil that is excavated from the ground may occupy 1.25 cubic meters after it is loosened and placed in the hauling unit. After the soil is compacted in place it may occupy 0.9 cubic meter. The soil to be excavated is called bank measure, in its undisturbed condition, prior to excavating or after being compacted in place. Also, any additional requirements to support the excavation operation should be also added to the cost estimating of an excavation operation. For example, excavation support, dewatering, etc Calculating truck requirements The estimator has to determine the optimum number of trucks required to transport excavated materials. A simple formula can be used for this calculation based on the premise that it is desirable to have sufficient trucking capacity to ensure that the excavation equipment is able to operate continuously and not have to waste time waiting for trucks. Obviously, three trucks will be required if it takes 10 minutes to load a truck and 20 minutes for that truck to unload and return for another load, because while the first truck is away, two other trucks can be loaded. Thus, the number of trucks can be calculated as: Number of required trucks = truck cycle time / loading time (5.1) Truck cycle time = loading time + going time + return time + dumping time (5.2) Loading time = truck capacity / production rate of loader (5.3) Truck capacity (bank measure) = truck capacity (loose) / (1+swelling factor) (5.4) Note that the number of trucks obtained from Eq. 5.1 should always be rounded up no matter how small the decimal. Most estimators consider it better to have more rather than less capacity so that the excavator is kept occupied. Cost Estimating 98 Dr. Emad Elbeltagi
3 5.1.3 Waste factors When estimating the material required for any job, it is necessary to add a portion for the wastage of material used. The quantities of material taken off are the unadjusted net amounts calculated from the drawings. Allowance for waste and spillage of this material can be made by increasing the takeoff quantities or by raising the price by the percentage factor considered necessary. The values of waste factors usually lie between one and 10 percent for different materials. Example 5.1 Calculate the equipment and labor prices per m 3 to excavate 3000 m 3 of trench using 0.75 m 3 backhoe costing LE670/day (day = 8 hrs), plus LE4000 for transportation and set up charges. Expected output is 60 m 3 /day with an operator and 0.5 labor at wages of LE40 and LE30 respectively. Solution Operator unit price = LE40/hr; Labor unit price = = LE15/hr Backhoe unit price = 670 / 8 = LE83.75/hr This crew produces 60 m 3 /day, Labor price/m 3 = 55 / 60 = LE0.92/m 3 Equipment price/m3 = / 60 = LE1.4/m 3 Transportation price = 4000 / 3000 = LE1.33/m 3 Then price/m 3 = LE3.65/m 3 Example 5.2 Calculate the price of obtaining a gravel form a pit located 16 km from the work site, where unit price is LE2.5/m 3, using a loader with a rate of 50 m 3 /hr (bank measure) and 12 m 3 trucks to transport the gravel. The loader and trucks are priced at rates of LE450/day and LE300/day respectively. The labor crew consists of one equipment operator at LE40/hr, two labors at LE30/hr and truck driver at LE30/hr. the dump truck travel at an average speed of 20 km/hr. the gravel has swell factor of 12% and 5 minute required to off-load the truck. Cost Estimating 99 Dr. Emad Elbeltagi
4 Solution First: calculate the number of trucks required to have a balanced crew Number of required trucks = truck cycle time / loading time Truck cycle time = loading time + going time + return time + dumping time Loading time = truck capacity / production rate of loader Truck capacity = 12 (loose material) / 1.12 = m 3 (bank measure) Loading time = / 50 = min Travel time = / 20 = 96 min Cycle time = = min No. of trucks = / = 8.86 = 9 trucks Second: calculate the gravel supply price Loader = 450 / 8 = LE56.25/hr Trucks = / 8 = LE337.5/hr Operator = LE40/hr Labors = 2 30 = LE60/hr Drivers = 9 30 = LE270/hr Crew hourly cost = = LE763.76/hr Crew unit price = / 50 = LE15.28/m 3 Then, gravel unit price = crew price + gravel cost = = LE15.78/m 3 Example 5.3 It is required to determine the unit price for plain concrete given the following information: Plain concrete (PC) quantity = 1080 m 3. One cubic meter of PC comprises of 250 kg cement; 0.8 m 3 gravel and 0.4 m 3 sand. The prices of these materials are LE500/ton; LE80/m 3 and LE40/m 3 for cement, gravel and sand respectively. Assume 10% wastage for all these materials. The details of the crew used are shown in the table below. Assume overheads and markup 20%. Cost Estimating 100 Dr. Emad Elbeltagi
5 Crew item No Production Price rate Pump 1 30 m3/hr LE450/day Truck mixer 3 9 m 3 /hr/one LE350/day/one Vibrator 2 - LE100/day/one Labor 5 - LE15/day/one Foreman 1 - LE30/day/one Solution Assume 8-working hours/day Pump production rate = 30 m 3 /hr = 30 8 = 240 m 3 /day Truck mixers production rate = = 216 m 3 /day The crew production rate equals the production rate of the critical resources (the lowest) = 216 m 3 /day Then, duration = 1080 / 216 = 5 days Material cost: Cost per/m 3 = 1.1 ( ) = LE225.5/m 3 Total material cost = = LE243,540 Equipment cost: Equipment cost/day = = LE1700/day Equipment cost = = LE8,500 Labor cost: Labor crew cost/day = = LE105/day Labor cost = = LE525 Item price: Item cost = = LE252,565 Item price = = LE303,078 Then, the item unit price = / 1080 = LE280.63/m Subcontractors In essence, subcontractor quotations should be solicited and analyzed in the same way as material quotes. A primary concern is that the bid covers the work as per plans and specifications, and that all appropriate work alternates and allowances are included. Any Cost Estimating 101 Dr. Emad Elbeltagi
6 exclusion should be clearly stated and explained. Oral bids quotes should be followed up by fax/ and hard copy confirmation. Any unique scheduling or payment requirements must be noted and evaluated prior to submission of the prime bid. Such requirements could affect or restrict the normal progress of the project, and should therefore be known in advance. The estimator should note how long the subcontract bid will be honored. This time period usually varies from 30 to 90 days and is often included as a condition in complete bids. The general contractor may have to define the time limits of the prime bid based on certain subcontractors. The estimator must also note any escalation clauses that may be included in subcontractor bids. Reliability is another factor to be considered when soliciting and evaluating subcontractor bids. Reliability cannot be measured or priced until the project is actually under construction. Most general contractors stay with the same subcontractors for just this reason. A certain unspoken communication exists in these established relationships and usually has a positive effect on the performance of the work. Such familiarity, however, can often erode the competitive nature of bidding. To be competitive with the prime bid, always obtain comparison subcontract prices. The estimator should question and verify the bonding capability and capacity of unfamiliar subcontractors. Taking such action may be necessary when bidding in a new location. Other than word of mouth, these inquiries may be the only way to confirm subcontractor reliability. For major subcontract items such as mechanical, electrical, and conveying systems, it may be necessary to make up spreadsheets in order to tabulate inclusions and omissions. This procedure ensures that all cost considerations are included in the adjusted quotation. Time permitting, it s a good idea to do a takeoff and price these major subcontract items to compare with the subcontractor bids. If time does not permit a detailed takeoff, the estimator should at least budget the work. An assembly s estimate is ideal for this purpose. Cost Estimating 102 Dr. Emad Elbeltagi
7 5.1.5 Preparation of method statement It is an essential part before the cost estimating of a given work item is to prepare its method statement. Method statement represents the way in which the work will be carried out. This includes: 1. Site staff detail who are going to supervise the work. A given supervisor may be experienced with a certain job but not with other job. 2. A schedule of the required materials and the proposed sources of supply. 3. A schedule of the basic cists at the time of tender of the equipment, labor and materials. 4. Details of the proposal for staff housing, offices, workshops and stores. 5. A list of subcontractors the estimator proposes to use. 6. Site layout. 7. Construction method of each work item. 8. List of risks and uncertainties the contractor is going to carry and responses to deal with them. 9. Work breakdown structure of the work. 10. A schedule of the activities showing the labor and materials required. 11. A detailed program of the work (schedule) showing the proposed duration of each work item. 5.2 Estimating Direct Cost The direct cost if each bid item represents the sum of its material, labor, equipment and subcontractor costs. The sum of bid items direct costs gives the estimated direct cost of the contract. The direct cost f a given item can be estimated using the unit rate estimating, operational estimating Unit rate estimating This type of estimating is used in building work and for civil work items where the nature of work is repetitive. It is based on the resources required and their output rates for each Cost Estimating 103 Dr. Emad Elbeltagi
8 category of work. Working drawings and specifications are needed to determine the quantities of materials, equipment, and labor. Current and accurate costs for these items (unit prices) are also necessary. Because of the detail involved and the need for accuracy, unit price estimates require a great deal of time and expense to complete properly. For this reason, unit price estimating is best suited for construction bidding. It can also be effective for determining certain detailed costs in conceptual budgets or during design development. There are some disadvantages of using the unit-rate method for estimating major works. It does not demand the examination of the program (schedule) or the method statement or the risks costs in undertaking the work. Also, the precision and level of detail in pricing an item can give a false sense of confidence in the resulting estimate. This method does not need having a construction schedule Operational estimating Operational estimating, which is the recommended method for estimating civil engineering work, requires the estimator to build up the cost of the operation based on its principles including the total cost of construction equipment, labor and permanent/temporary materials. This method links well with the planning and scheduling process as it embraces the total anticipated time that the construction equipment and labor crew are involved in the operation including all idle time. The operational estimating involves the following: - Prepare the method statement showing the sequence, resources, timing, etc. - Prepare an early completion program with unlimited resources. - Revise the program by smoothing or leveling the resources. Example 5.4 This question relates to the construction of a reinforced concrete basement (50 m 30 m 10 m deep) built below the ground. The contractor s estimate is required to calculate an appropriate BOQ rate. Tis item is listed in the BOQ as follow: Cost Estimating 104 Dr. Emad Elbeltagi
9 No Description Units Quantity E1 Excavation for foundation, material other than top soil, rock or artificial hard material maximum depth 5-10 m m Unit price Total Consider two alternative construction methods: - Method A: open cut with battered sides (the open cut method requires additional work space to allow for erect and strip shutter of the outer face). Accordingly, assume total volume of excavation equals 2.5 net volume. - Method B: Steel cofferdam built around net perimeter of basement. Assume the following net costs (based on quotations from subcontractors): - Excavation open cut, LE3/m 3. - Disposal on site LE1/m 3. - Bring back and fill, LE1/m 3. - Excavation within cofferdam, LE8/m 3. - Sheet piling (assume 15 m deep), LE20/m 2. - Mobilization/demobilization of piling rig, LE5000each way. - Extract cofferdam piling, LE Site overheads, 10%, head office overheads and profit, 12%. Solution Method A (open-cut): Excavation quantity of open-cut = = m 3. Disposal on site = = m 3. Bring back and fill = m 3. Total net cost = = LE157,500 Method B (steel cofferdam): Cost Estimating 105 Dr. Emad Elbeltagi
10 Excavation quantity within cofferdam = m 3 = = LE120,000. Sheet piling mobilization/demobilization (two times) = = LE10,000. Sheet piling ( ) 15 = = LE48,000. Extract cofferdam = LE5,000. Total net cost = LE183,000. Thus, based on the above, the estimator would choose the open-cut method. Net cost of open-cut method = LE157,500 10% site overheads = LE15,750 Subtotal = LE173,250 12% head office overheads and profit = LE20,790 Total = LE194,040 So, the rate to be included in the bill of quantity should be = /15000 = LE12.936/m3. Example 5.5 A grout curtain is to be constructed underneath a dam. This involves drilling through the underlying rock. The total length of the grout holes to be drilled is m distributed over 388 holes. The following table shows the work involved into five activities along with the sued resources. Length No of drilling and Act Description No of holes (m) grouting pits 1 Grout Grout Grout Grout Grout Cost Estimating 106 Dr. Emad Elbeltagi
11 Assume that the drilling and grouting rate equals 20m/day. The drilling rig requires ½ day moving from a hole to another. The cost of the used equipment is LE2300/wk/unit and the cist for grout material is LE5.8/m. the week comprises of 6 days. It is required to determine the duration of each activity. The direct unit cost using the unit rate estimating and the operational estimating. Solution Calculating activities durations: Act drilling and grouting duration (days) Moving rig (days) Total duration (week) / (20 4) = / (2 4) = / (20 2) = / (2 2) = / (20 3) = / (2 3) = / (20 4) = / (2 4) = / (20 3) = / (2 3) = Assume the following activity schedule: Calculating cost using unit-rate estimating: The drilling and grouting rate = 20m/day = 0.05 day/m Time of moving equipment = = 194 days = 194/21390 = day/m Total time = = day/m Daily cost of equipment = 2300 / 6 = LE Grouting unit rate = = LE28.42/m Calculating cost using operational estimating: Cost Estimating 107 Dr. Emad Elbeltagi
12 Total equipment-weeks used = (3+4+3) + 7 = 223 unit.week Cost of equipment = = LE Unit cost rate = /21390 = LE29.58/m 5.3 Estimating Indirect Cost The indirect costs comprises both site and head office (general) overheads Site overheads To accommodate various site situations, it is a good idea for a construction company to develop comprehensive checklists for general jobsite requirements regarding its specialized line of business. Such a list would aid the estimator, ensuring that no important cost items are forgotten under the time pressure of finalizing the bid. Visits to the jobsite by an experienced estimator and a principal of the firm are a must after a preliminary review of drawings and specifications. A site investigation report can be used to collect needed information useful for organizing the future jobsite and, above all, to determine prior bidding costs. Certainly not all items are relevant for each report. If the project is in a remote area or in a harsh environment, more items will be checked and questions answered during the site visit. Later, they will be converted to line items with an estimated cost toward job site overhead. Any missing items will reduce overall profit. A prudent contractor and subcontractor will not be satisfied applying a fee to the direct estimated costs, a fee that is supposed to cover jobsite overhead and markup. The estimated total jobsite overhead costs will become the baseline budget for jobsite overhead expenditure control. These items might include: - Jobsite personnel wages and fringe benefits; - Jobsite personnel project-related travel expenses; - Outside contracted engineering support (surveying, materials testing, etc.); - General use equipment for the benefit of the general contractors and subcontractors (cranes, hoists); - Field buildings; Cost Estimating 108 Dr. Emad Elbeltagi
13 - Site utilities for the job duration; - Horizontal structures (roads, parking, fences, and gates); - Temporary environmental controls requirements; - Winter and summer protection of completed works or works in progress; - Related camp facilities for remote jobs; - Jobsite production facilities (concrete batching plants, quarry, various shops); - Protective aids for workers (gloves, hard hats, etc.) during construction and final cleanup of the project; and - Bonds, insurance, permits, and taxes required in the contract general conditions; - Utilities needed for material storage; - Cost of temporary site utilities General overheads The company home office expenses cannot be chargeable most of the time to a single project. General overhead represents contractor fixed expenses. A general contractor s or subcontractor s main office expense consists of many items. A summary of the major categories is presented below: - Non reimbursable salaries - President - Vice president - Estimating group - Human resource personnel - Secretaries - Payroll clerk - Accounts payable clerks - Total office non reimbursable salaries - Benefits - Office/shops rent - Depreciation of capital expenditures - Office utilities and communication Cost Estimating 109 Dr. Emad Elbeltagi
14 - Office supplies - Office equipment (rented, if owned depreciated) - Office maintenance - Advertising/jobs procurement/public relations - Associations and clubs dues - Licenses and fees - Donations/sponsored research - Trade journals subscriptions and books - Travel - Entertainment - Company sponsored training programs - Accounting services - Legal services - Estimating and project management (not salaries) - Consulting fees (legal, etc.) - Home office vehicles, depreciation, operation expenses - Insurance expenses - Total anticipated home office expense The expense list presented above is not appropriate for all contractors. For smaller contractors who operate from a truck, the list would contain considerably fewer items and for a large contractor, the list could fill pages, but the concept is the same. The expenses should be estimated, and all efforts must be made to stay in the budget and to generate the planned business volume. In general, main office expense ranges from 2.5 to 10% of annual construction billings Construction contingencies Contingency is that amount of money added to an estimate to cover the unforeseen needs of the project, construction difficulties, or estimating accuracy. Many chief estimators or contractor executives add a contingency to the estimate to cover one or possibly more of the following: Cost Estimating 110 Dr. Emad Elbeltagi
15 - Unpredictable price escalation for materials, labor, and installed equipment for projects with an estimated duration greater than 12 months; - Project complexity; - Incomplete working drawings at the time detail estimate is performed; - Incomplete design in the fast-track or design-build contracting approach; - Soft spots in the detail estimate due to possible estimating errors, to balance an estimate that is biased low; - Abnormal construction methods and startup requirements; - Estimator personal concerns regarding project, unusual construction risk, and difficulties to build; - Unforeseen safety and environmental requirements; - To provide a form of insurance that the contractor will stay within bid price. Most often, if for any reason an accurate estimate is not made (95 to 100% accuracy), an estimator never knows how much money to allow for these forgotten items. Many times added contingencies are an excuse for using poor estimating practices such as not enough time, subcontractors not reporting, no time to visit the job site, and so on. Contingency for these reasons is difficult to sell to management and can hurt the credibility of the estimating team. On the other hand compounding building projects bidding complexity justifies the need to add contingency as part of the markup. This construction risk compensation is added to the final direct and jobsite overhead cost. The magnitude depends on the type of contract agreement, type of construction, and certainly project location. Contingency is not potential profit. It includes risk and uncertainty but explicitly excludes changes in the project scope (change orders). The contingency should absolutely not be treated as an allowance. Allowances are costs that are foreseen to be spent, and need to be included in the detail estimate in the proper construction category of work and not as a total for the project. There are many factors that affect the amount of contingency to be included in the estimate. General contingency guidelines also apply to different types of construction. For underground work the contingencies should be increased by 2 to 5% for Cost Estimating 111 Dr. Emad Elbeltagi
16 each design phase. For buildings, it is recommended to decrease the contingencies by 1 to 3% for each phase. In general, contingency reflects the contracting organization s judgment decision to avoid bid cost overrun. On the other hand, too much contingency will create a fat estimate if management is not willing to accept some construction risks. To management, contingency is money it hopes will not be expended, but instead returned as profit at project completion. If the amount of contingency added to the bid is too large the contractor risks not getting the project and recording an additional expense for doing the estimate and bidding. This is the reason that a cost line item is usually not included in the bid Contractor/Subcontractor profit The last item to be included in the bid and representing contractor s return on investment is the profit. The magnitude of desired profit must be decided by the owner for each individual bid, depending on local market conditions, competition, and the contractors need for new work. In the construction industry, markup is defined as the amount added to the estimated direct cost and estimated job into overhead cost to recover the firm s main office allocated overhead (general overhead) and desired profit. The less profit added to a bid, the greater the chance is of being the successful bidder. Bidding a job with a high profit added does not mean the contactor will get the job. Bidding a job below cost with no planned profit or a minimum profit only to get the work is also no guarantee of being a successful contractor. A contractor can go broke by not obtaining enough profitable work. To be competitive, a construction company s general overhead and profit should be close to industry norms. The concept of percentage of return on indirect cost investment must also be considered. The return on indirect cost is calculated by dividing the corporation s annual net profit before taxes by the general overhead cost. General overhead and profit recovery factors are developed from the annual general overhead budget. After bid Cost Estimating 112 Dr. Emad Elbeltagi
17 opening, contractors occasionally ask close competitors what percent they added for profit. Surprisingly, competitors are refreshingly candid in revealing the amount added for profit. This natural curiosity is related to the many kinds of profit. Contractors are intuitively trying to ascertain why competitor A, who lost the job, marked up 2%, and competitor B, who marked up 4%, was awarded the bid. Different kinds of profits are related to several considerations, including the following: - The firm must recoup sufficient profit for return on equity. - The profit must be commensurate with industry averages. - The profit must consider competitive bidding strategies. - The profit must be as high as possible or what the competitive market will bear, while commensurate with the contractor s risk. 5.4 Finalizing a Tender Price The total price of a tender comprises the cost and the markup. The cost includes direct and indirect costs. The markup, on the other hand, includes profit margin, financial charges (cost of borrowing), and a risk allowance margin (Figure 5.1). Price Markup Cost Risk allowance Financial charge Profit Indirect cost Direct cost Figure 5.1: Components of a tender price If you are much involved in the construction business, you must have experienced how difficult it is to decide on a suitable margin to make your bid competitive against other contractors. We need to decide on the markup percentage that makes the bid low enough Cost Estimating 113 Dr. Emad Elbeltagi
18 to win and, at the same time, high enough to make reasonable profit. Generally, contractors often have to main methods of assessing a specific contract markup. Estimating a single percentage markup to be added to the total cost. It is assumed that this percentage will cover all the components of markup as shown in Figure 5.1; and Detailed analysis of the risky components in the project and their impact on the project in terms of increased time and cost. Also, cash flow analysis to estimate the financial charge and estimating a reasonable profit margin. Calculations of the financial charges (cost of borrowing) were, also, presented previously in this chapter based on the cash flow analysis of the contract. Estimating profit and risk allowance margins will be presented in the next subsection. Having all contract costs (direct and indirect), and markup components (profit margin, risk allowance and financial charge), it is time to finalize the bid price. While, the direct cost are associated directly to the contract activities, indirect cost and markup are not associated with specific activities but with the whole contract. Accordingly, pricing policy is the method by which the indirect costs and markup will be distributed among the items of the bill of quantities, so that the bid price is ready to be submitted to the client Balanced bid (straight forward method) In this method the indirect cost and the markup will be distributed among different items based on their direct cost; i.e., the more the direct cost of an item, the more its share from indirect cost and markup. The resulting bid price is called a balance d bid. The share of specific item = Direct cost of this item Total contract direct cost x (total indirect cost + markup) Example 5.5 Assume that the direct cost for an item (a) is LE 400,000 and that item is included in a contract whose price is LE 3,500,000 and its total direct cost is LE 2,800,000. Calculate the price for item (a) considering a balanced bid. Cost Estimating 114 Dr. Emad Elbeltagi
19 Solution Bid price = direct cost + indirect cost + markup Indirect cost + markup (for the whole contract) = Bid price - direct cost = 3,500,000-2,800,000 = LE 700,000 Then, Indirect cost + markup for activity (a) Then, price of activity a = 400,000 2,800,000 = its direct cost + indirect cost = 400, ,000 = LE 500,000 x 700,000 = LE 100, Unbalanced bid (Loading of Rates) The contract price is said to be unbalanced if the contractor raises the prices on certain bid items (usually the early items on the bill of quantities) and decreases the prices on other items so that the tender price remain the same. This process is also called the loading of rates. The contractor usually loads the prices of the first items to ensure more cash at the beginning of the contract and to reduce the negative cash flow and accordingly reduces borrowing of money. Loading of rates may be risky to both the contractor and the owner. If the contractor raised the price for an item and the quantity of this item increased than that was estimated in the bill of quantities then, this situation is more risky to the owner as it will cost the owner more money. On the other hand, if the contractor reduced the price of a specific item and the quantity of that item increased, thus situation will be more risky to the contractor. So, it is better to follow a balanced way of distributing the indirect costs and markup among contract items. Example 5.7 Consider a small contract comprises of five sequential activities of equal duration. The quantity of work in each activity, the direct cost rate, and total cost rate for balanced and unbalanced bid are given in Table 5.1. Determine the effect of Cost Estimating 115 Dr. Emad Elbeltagi
20 unbalanced bid on the contractors profit if: Quantity of activity (B) is increased by 50%. Quantity of activity (C) is increased by 50%. Table 5.1: Data for Example 5.5 Activity A B C D E Quantity Direct Balanced bid Unbalanced bid cost rate Rate Price Rate Price Tender price Solution - Contract total direct cost = 100 ( ) = Contract price = Contract markup and profit = = 1300 = 25% of direct cost - Table 5.2 shows the effect of tender price if the quantity of activity B increased by 50%. - The price of the unbalanced bid (7200) is greater than that of the balanced bid (7000) which means more profit to the contractor and more risk to the owner. Table 5.2: Effect of change in quantity of activity B Activity A B C D E Quantity Direct Balanced bid Unbalanced bid cost rate Rate Price Rate Price Tender price Table 5.3 shows the effect of tender price if the quantity of activity C increased by 50%. - The price of the unbalanced bid (7400) is less than that of the balanced bid (7500) which means less profit and more risk to the contractor. Cost Estimating 116 Dr. Emad Elbeltagi
21 This decrease means that the profit of the contractor has been decreased and thus represents risk to the contractor. Table 5.3: Effect of change in quantity of activity C Activity A B C D E Quantity Direct Balanced bid Unbalanced bid cost rate Rate Price Rate Price Tender price Method related charge As it has been seen before, the prices entered in the conventional bill of quantities may not represent the real cost f the work defined in the individuals items. This is because not all costs are directly related to the quantity of work in that item. Therefore, adjustment fo the price due to a change in a quantity of a particular item may not represent the real variation in cost. For example, a site overhead is mainly a time-related cost. Assume that it will be incurred monthly. In conventional bill of quantitates, the cost of site overheads recovered by spreading it over the quantities proportional rates. If variation occurs and the site facilities are required for a longer period, there is no systematic way for adjusting the contract price. Accordingly, if the time-related cost of the site overheads could be entered in the bill of quantities as a time-related charge, then the cash flow pattern would be more realistic and this item could be adjusted in the case of relevant variation. The method related charge is used to allow for entering items in the bill of quantities for any operation whose cost is not directly linked to the quantities of permanent work. The main advantages of using this method for pricing the bill of quantities are: - It allows a systematic evaluation of variations and changes. - It provides a reasonable payment for work varied in quantities. - It realistically reflects the cost of construction which reduces the effect of inflation and investment required from the contractor. Cost Estimating 117 Dr. Emad Elbeltagi
22 - Improves the cash flow and consequently reduces the need for the loading of rates. The following table shows a BOQ example containing some method-related charge items. Item Description Quantity Unit Unit price Total price 1 Heath Safety Equipment and Monitoring. Project Site Mobilization. Lump Sum Lump Sum 2 Steel Structure Decontamination. a) Decontaminate steel structure 1100 Square Meters b) Load and haul debris to Landfill in Alexandria 5 Ton 3 Walls Decontamination and Coating. a) Support walls 1200 Square Meters b) Rolling Scaffold 1200 Square Meters Cost Estimating 118 Dr. Emad Elbeltagi
23 5.5 Exercises 1. A crew comprising 3 labors and 0.5 foreman is deserved to take (16 hr) 2-days to excavate 36 m 3 of soil. If the average rate of labor is LE21/hr and foreman is LE24/hr. Find the unit cost of excavation. 2. A bill of quantity of a project includes 500m 2 of masonry work. The work will be done by one crew with a production rate of 50 m 2 /day and consists of: Crew member No All-in rate/day Brick layer 2 50 Assistant 1 25 Labor 2 12 Vendor price of 1000 bricks = LE160. Each 55 bricks are estimated to make one square meter of masonry. Each one cubic meter of mortar is used to join brick area of 50 m 2 and consists of: Quantity Material Primary quotation form vendor One cubic meter Sand LE15/m 3 6 sacks (50 kg each) Cement LE240/ton As a contractor, it is required to estimate the item price and the unit price. Assume all material waste as 20% and assume overheads and markup as 20% of total cost. 3. Calculate the price of pit-run gravel delivered to the site per cubic meter (bank measure) based on the following data: - The pit is located 10 km from the site. - Truck costs LE40/hr, including fuel and maintenance; they have 12 cubic meter (loose material) capacity and travel at an average speed of 30 km/hr empty and 20 km/hr loaded. - The swell factor for this material is 20% and the compaction factor is 90%. Cost Estimating 119 Dr. Emad Elbeltagi
24 - Trucks take 5 minutes to unload at the site. - The loader costs LE80/hr and loads material at the pit at the rate of 40 m 3 /hr. - Truck driver s wage is LE32/hr and the equipment operator s wage is LE40/hr. - Gravel price (loose) = LE40/m 3. - Quantity of gravel required to fill an excavated site with dimensions m 3. - Assume overheads and markup of 10%. 4. Consider the following items of a given project. Item Unit Quantity Direct cost (LE) Material Equipment Labor Subcontractor 1 m m m m lump-sum Lump-sum Site overheads = 5% of Direct cost (i.e., LE10500). - General overheads = 5% of Construction cost. - Profit and risk = 10% of Total cost. It is required to: a. Develop a balanced tender price (balanced bid). b. Develop an un-balanced tender price (unbalanced-bid). Cost Estimating 120 Dr. Emad Elbeltagi
CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING
CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter will
CHAPTER 2 QUANTITY TAKE-OFF
CHAPTER 2 QUANTITY TAKEOFF The quantity takeoff is an important part of the cost estimate. It must be as accurate as possible and should be based on all available engineering and design data. Use of appropriate
Introduction PURPOSE OF THIS BOOK
1 C H A P T E R Introduction PURPOSE OF THIS BOOK The purpose of this book is to enable the reader to gain fundamental knowledge of estimating the cost of projects to be constructed. Experienced estimators
How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013
How to Estimate the Cost of Support of Excavation for Foundation Installation CPE Candidate No. 0113013 May 15, 2013 1 How to Estimate the Cost of Support of Excavation for Foundation Installation Table
Cost components. Why estimate? You may ask; why do we need estimates? Estimating can help to: Total project costs. Profit added FINAL BID
Estimating costs for infrastructure projects is a very complex task which requires a lot of experience. It is important that you understand at least the principles of costing. Why estimate? You may ask;
CHAPTER 6 PROJECT CASH FLOW
CHAPTER 6 PROJECT CASH FLOW In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter will deal with project
Pricing of Construction Contract Change Order Documentation
The contract language contained in this Exhibit will supplement and take precedence over all other change order pricing contract provisions in the Contract Documents provided by the Owner, Design-Builder
VOLUME 4 FINANCIAL OFFER LUMP SUM CONTRACTS. Annex 4.2.1 - Introduction. Annex 4.2.2 - Recapitulation. Annex 4.2.3 - Breakdown of the Lump-sum Price
VOLUME 4 FINANCIAL OFFER LUMP SUM CONTRACTS Annex 4.2.1 - Introduction Annex 4.2.2 - Recapitulation Annex 4.2.3 - Breakdown of the Lump-sum Price Annex 4.2.4 - Daywork Schedule Annex 4.2.5 - Detailed Breakdown
CHAPTER 4 TYPES OF COST ESTIMATES
CHAPTER 4 TYPES OF COST ESTIMATES 1. INTRODUCTION All projects, both construction and environmental restoration, require cost estimates to plan and budget the project efficiently. Numerous estimates are
CONSTRUCTION OF PERIMETER FENCE - COMMERCIAL AND T&D OFFICE COMPOUND, ONVERWAGT
BILL Nr1 - PRELIMINARIES 1.0 PRELIMINARY PARTICULARS CONSTRUCTION OF PERIMETER FENCE - COMMERCIAL 1.1 Funding The funding shall be provided by the Guyana Power & light Inc., of 40 Main street, North Cummingsburg,
Contractor s Estimation of Cost and Bidding Strategy. Construction Project Management_Kumar Neeraj Jha
1 Contractor s Estimation of Cost and Bidding Strategy Contents 1.1 Contractor s estimation and bidding process 1.2 Bidding models 1.3 Determination of optimum mark-up level 1.4 Bidding and estimation
Cost Estimating in Construction Part 1, Course #406. Presented by: PDH Enterprises, LLC PO Box 942 Morrisville, NC 27560 www.pdhsite.
Cost Estimating in Construction Part 1, Course #406 Presented by: PDH Enterprises, LLC PO Box 942 Morrisville, NC 27560 www.pdhsite.com This course Cost Estimation in Construction Part 1 provides a study
Quantity Take-off. Quantity Take-off
Quantity Take-off Required Information for Cost Estimate Detailed drawings Specifications Available site data Available resource data (labor, material & equipment) Government regulations Applicable owner
How to estimate the cost of installing an Electrical Distribution Center (EDC)
How to estimate the cost of installing an Electrical Distribution Center (EDC) Candidate Number 0112233 June 2012 Table of Contents 1) Introduction 3 2) Types and Methods of Measurement 3 5 3) Specific
CHAPTER 4 APPLICATIONS IN THE CONSTRUCTION INDUSTRY
CHAPTER 4 APPLICATIONS IN THE CONSTRUCTION INDUSTRY This chapter introduces some topics that are related to the economic evaluation of alternatives such as the depreciation, breakeven analysis and the
PREPARING DETAILED BREAKDOWNS FOR CHANGE ORDER PROPOSALS
PREPARING DETAILED BREAKDOWNS FOR CHANGE ORDER PROPOSALS I. GENERAL A. All work to be performed under the change order must be itemized, including the work of all subcontractors. B. Items must be relevant
Measuring, Estimating and Tendering Processes in Construction and the Built Environment
Unit 9: Measuring, Estimating and Tendering Processes in Construction and the Built Environment NQF Level 3: Guided learning hours: 60 BTEC National Unit abstract Estimating is concerned with the processes
Cost Estimating Procedure. Table of Contents
Cost Estimating Procedure Table of Contents 1.0 PURPOSE... 1 2.0 SCOPE... 1 3.0 REFERENCES... 1 4.0 DESCRIPTION... 1 5.0 PROCEDURE DETAILS... 2 5.1 Developing a Detailed Cost Estimate... 2 5.2 Basis of
CHAPTER 4 COST OF CONSTRUCTION LABOR AND EQUIPMENT
CHAPTER 4 COST OF CONSTRUCTION LABOR AND EQUIPMENT Construction labors influence every part of a project. They operate equipment and fabricate and install materials. Detailed estimate requires the breakdown
Construction Contracts
STATUTORY BOARD FINANCIAL REPORTING STANDARD SB-FRS 11 Construction Contracts This version of SB-FRS 11 does not include amendments that are effective for annual periods beginning after 1 January 2015.
International Accounting Standard 11 Construction Contracts
International Accounting Standard 11 Construction Contracts Objective The objective of this Standard is to prescribe the accounting treatment of revenue and costs associated with construction contracts.
The Task. for. PERI Construction-Exercise 2003
The Task for PERI Construction-Exercise 2003 Entitled to participate all educational institutions for civil engineering and construction management. The work must be based on the outlined project and can
NEC Users Group Workshop Defined Cost
NEC Users Group Workshop Defined Cost [email protected]; July 2014 Turner & Townsend plc July 14 making the difference Introduction Practicalities in assessing of Defined Cost & Disallowed Cost Assumption
CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES
CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES INTRODUCTION What is a Construction Management Plan? The City of Vincent requires careful management of construction involving excavation and retention
The following Accounting Standards Interpretation (ASI) relates to AS 7. ASI 29 Turnover in case of Contractors
108 Accounting Standard (AS) 7 (revised 2002) Construction Contracts Contents OBJECTIVE SCOPE Paragraph 1 DEFINITIONS 2-5 COMBINING AND SEGMENTING CONSTRUCTION CONTRACTS 6-9 CONTRACT REVENUE 10-14 CONTRACT
Mine Plan of Operations Reclamation Bond Checklist
Mine Plan of Operations Reclamation Bond Checklist NOTE: This checklist is provided to assist the operator in calculating the engineering and environmental costs required to properly stabilize, reclaim,
Design Criteria & Service Goals
4.1 Design Life of Improvements The design life of a water system component is sometimes referred to as its useful life or service life. The selection of a design life is a matter of judgment based on
Construction Contracts
65 Accounting Standard (AS) 7 Construction Contracts Contents OBJECTIVE SCOPE Paragraph 1 DEFINITIONS 2-5 COMBINING AND SEGMENTING CONSTRUCTION CONTRACTS 6-9 CONTRACT REVENUE 10-14 CONTRACT COSTS 15-20
NEPAL ACCOUNTING STANDARDS ON CONSTRUCTION CONTRACTS
NAS 13 NEPAL ACCOUNTING STANDARDS ON CONSTRUCTION CONTRACTS CONTENTS Paragraphs OBJECTIVE SCOPE 1 2 DEFINITIONS 3 6 COMBINING AND SEGMENTING CONSTRUCTION CONTRACTS 7 10 CONTRACT REVENUE 11 15 CONTRACT
[Project Name] NZTA Contract No. [Contract Number] Schedule of Prices
[Project Name] NZTA Contract No. [Contract Number] Schedule of Prices Schedule of Prices SP1
CHAPTER 8 PROJECT TIME-COST TRADE-OFF
CHAPTER 8 PROJECT TIME-COST TRADE-OFF In the previous chapters, duration of activities discussed as either fixed or random numbers with known characteristics. However, activity durations can often vary
Unit Price Averages Reports
Unit Price Averages Reports 12/7/2015 UNIT PRICE AVERAGES REPORT Disclaimer The information provided in the following Unit Price Averages Report is only for the use of Alberta Infrastructure & Transportation
Sri Lanka Accounting Standard -LKAS 11. Construction Contracts
Sri Lanka Accounting Standard -LKAS 11 Construction Contracts -405- Sri Lanka Accounting Standard -LKAS 11 Construction Contracts Sri Lanka Accounting Standard LKAS 11 Construction Contracts is set out
ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES
ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES CAPITAL GRANTS PROGRAM / BUILDING GRANTS ASSISTANCE SCHEME Background Non government schools accepting the
Lesson-13. Elements of Cost and Cost Sheet
Lesson-13 Elements of Cost and Cost Sheet Learning Objectives To understand the elements of cost To classify overheads on different bases To prepare a cost sheet Elements of Cost Raw materials are converted
SECTION 02401 SHEETING, SHORING AND BRACING
SECTION 02401 SHEETING, SHORING AND BRACING This section should be edited to reflect soil conditions specific to the project site and the recommendations of a Geotechnical Engineer licensed in the State
REIMBURSEMENT PROCEDURE for FEMA PUBLIC ASSISTANCE
REIMBURSEMENT PROCEDURE for FEMA PUBLIC ASSISTANCE Financial Assistance Availability The impact of major or catastrophic emergencies can exceed local financial resources. Financial aid and assistance may
High Strain Dynamic Load Testing of Drilled Shafts
Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain
Contract Administration
Chapter 5 Contract Administration Section 3 Change Orders 5-301 General 5-302 Change Order Policy 5-303 Purpose of Change Orders 5-304 Initiation of Change Orders 5-305 Preliminary Considerations 5-306
Schedule of Prices. Project Name Contract No. Contract Number
Schedule of Prices Project Name Contract No. Contract Number C3-LS-BP-Issue 2 SP Page 1 Printed 1 March 2011 >: 1. When preparing the schedule
19.2 Applicable Terms
19.0 ACCOUNTING FOR CONSTRUCTION CONTRACTS 19.1 Introduction This chapter covers the following: a. Applicable Terms b. Applicable Standard c. Key IPSAS Provisions d. Accounting Documentation e. Accounting
Hydraulic Excavators
Chapter 8 Hydraulic Excavators Hydraulic excavators are designed to excavate below the ground surface on which the machine rests. These machines have good mobility and are excellent for general-purpose
Preparing cash budgets
3 Preparing cash budgets this chapter covers... In this chapter we will examine in detail how a cash budget is prepared. This is an important part of your studies, and you will need to be able to prepare
Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections
Materials Standard shapes W sections, C channels, Structural T, Angles, Pipes, Tubes, Rods and Plates Fabricated members, Built-up sections Adding plates to beam flanges, Stiffeners to beam webs Built
Applicability / Objective
By Rakesh Agarwal Applicability / Objective APPLICABILITY: applicable to all contracts entered into on or after 1-4-2003 and is mandatory in nature from that date. Based on AS 7 (Construction Contracts)
COMPANY ESTIMATOR BID DAY PHONE NO.
COMPANY ESTIMATOR BID DAY PHONE NO. Work Package: Structural Steel Fabrication & Erection The work in each bid package shall include but shall not be limited to all labor, burden, fringe benefits, materials,
Detailed Estimation and Pumpstation Overview. Nathaniel Osgood 3/3/2004
Detailed Estimation and Pumpstation Overview Nathaniel Osgood 3/3/2004 Announcements TP2 Due Date: March 15 PS4 out tonight Due March 19 Team project Recording of recitation Pietroforte Lecture Important
SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS
July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional
SAMPLE CONSTRUCTION COMPANY. FINANCIAL STATEMENT AND SUPPLENTARY INFORMANTION For the Year Ended December 31, 2011
FINANCIAL STATEMENT AND SUPPLENTARY INFORMANTION For the Year Ended December 31, 2011 The financial statement, prepared by an independent Certified Public Accountant, is essential for bonding purposes.
How To Account For Construction Contracts In Hong Kong Kongsong Accounting Standard 11
HKAS 11 Issued October 2004Revised March 2010 Hong Kong Accounting Standard 11 Construction Contracts COPYRIGHT Copyright 2011 Hong Kong Institute of Certified Public Accountants This Hong Kong Financial
TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth
TABLE OF CONTENTS NO. MP-1 MP-2 MP-3 MP-4 MP-4.01 MP-4.02 MP-4.03 MP-5 MP-5.01 MP-5.02 MP-5.03 MP-5.04 MP-5.05 MP-5.06 MP-5.07 MP-5.08 MP-5.11 MP-5.12 MP-5.13 MP-5.14 MP-5.15 MP-5.16 MP-5.18 MP-5.19 MP-5.20
7 Contract Costing. Basic Concepts. Contract Costing
7 Contract Costing Basic Concepts Contract Costing Sub-contract Extra work Work Certified Value of Work Certified Cost of work certified Work uncertified Progress Payment Contract costing is a form of
Construction Contract Fundamentals. Baker Tilly refers to Baker Tilly Virchow Krause, LLP,
Construction Contract Fundamentals Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. 2010 Baker Tilly Virchow Krause, LLP About
Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling
Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation
Reasons for Change Orders
T E X A S D E PA R T M E N T O F T R A N S P O R TAT I O N A change order is defined in the 2004 Standard Specification Book as a written order to the Contractor detailing changes to the specified work,
SUCF PROJECT COST REPORTING GUIDE
SUCF PROJECT COST REPORTING GUIDE State University Construction Fund 353 Broadway / ALBANY, NY 12246 SUCF 900 / 11 Table of Contents Page A. Preface 1 B. Area Takeoff Methodology 1. General 2 2. Net Assignable
SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
Pupil Transportation Cost and Outsourcing Feasibility Study Performed for the West Plains R-VII Schools May 2013
Pupil Transportation Cost and Outsourcing Feasibility Study Performed for the West Plains R-VII Schools May 2013 The TransPar Group, Inc. of Lee s Summit, Missouri was engaged by the West Plains Schools
National Electric Power Regulatory Authority
National Electric Power Regulatory Authority MECHANISM FOR DETERMINATION OF TARIFF FOR HYDROPOWER PROJECTS Preamble Conservative estimates show total hydroelectric potential in the country to be 45000
Clean Water Revolving Funds (SRF & SWQIF) Loan Application Instructions for Completing the Project Cost Worksheet
Clean Water Revolving Funds (SRF & SWQIF) Loan Application Instructions for Completing the Project Cost Worksheet 1. Entering Cost Figures To complete the Project Cost Worksheet, enter costs incurred to
Section IV. Bidding Forms
Section IV. Bidding Forms Bid Submission Sheet Table of Forms Appendix to Bid Table A. Local Currency Table B. Foreign Currency (FC) Table C. Summary of Payment Currencies Bill of Quantities - Example
The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY
The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY From Financial Management & Accounting for the Construction Industry, CFMA. 2014 Matthew Bender and Company, Inc., a member of the LexisNexis Group.
Contract Works. Proposal Form
Proposal Form Contract Works Specified Contract Works and Legal Liability Arranged through ASR Underwriting Agencies Pty Ltd Underwritten by Certain Underwriters at Lloyd s IMPORTANT NOTES TM PLEASE READ
Introduction. Percent Increase/Decrease. Module #1: Percents Bus 130 1
Module #1: Percents Bus 130 1 Introduction In this module, we are going to use the process of excavating soil to demonstrate the mathematical concept of percent changes and problem solving skills. When
Benchmark Estimating Software
Flexible software for your industry Asphalt Building Civil Cost Engineers Consulting Estimators Facilities Management Landscaping Manufacturing Mining Plumbing Precast Concrete Public Works Rail Road Authorities
Chapter 1 Introduction
1 CHAPTER This chapter lays the foundation for your increased understanding of the process of electrical estimating and submitting bids. It also covers the basic concepts about estimating and bidding that
COST CLASSIFICATION AND COST BEHAVIOR INTRODUCTION
COST CLASSIFICATION AND COST BEHAVIOR INTRODUCTION LESSON# 1 Cost Accounting Cost Accounting is an expanded phase of financial accounting which provides management promptly with the cost of producing and/or
Cost Estimating Concepts
Cost Estimating Concepts Goal to provide an overview of cost estimating (CE) concepts in order to review CEs prepared by others or to create alternative CEs Why? financial assurance provision based upon
GUIDE FOR APPLICANTS GRANTS PROGRAMME 2016/2017 TRAINING IN CONFERENCE INTERPRETING
GUIDE FOR APPLICANTS GRANTS PROGRAMME 2016/2017 TRAINING IN CONFERENCE INTERPRETING The aim of this guide is to give a summary of the main points of the administrative and financial processes governing
Budgetary Planning. Managerial Accounting Fifth Edition Weygandt Kimmel Kieso. Page 9-2
9-1 Budgetary Planning Managerial Accounting Fifth Edition Weygandt Kimmel Kieso 9-2 study objectives 1. Indicate the benefits of budgeting. 2. State the essentials of effective budgeting. 3. Identify
SOMETIMES the cost of installing a landscape plan
Pricing the Landscape Plan SOMETIMES the cost of installing a landscape plan can be quite shocking for those not familiar with all the elements of a landscape. When one breaks down the various expenses
BASIC CONCEPTS AND FORMULAE
7 Contract Costing BASIC CONCEPTS AND FORMULAE Basic Concepts 1. Contract costing:- Contract or terminal costing, as it is termed, is one form of application of the principles of job costing. In fact a
LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. Table of Contents 1. INTRODUCTION...
COST AND MANAGEMENT ACCOUNTING
EXECUTIVE PROGRAMME COST AND MANAGEMENT ACCOUNTING SAMPLE TEST PAPER (This test paper is for practice and self study only and not to be sent to the institute) Time allowed: 3 hours Maximum marks : 100
Quantity Takeoff. Dr. Ahmed Elyamany
Quantity Takeoff Dr. Ahmed Elyamany 1 Outline Importance of Quantity Takeoff Preparation of Quantity Takeoff Measurement Units Measuring excavation, P.C footings, Beams, Columns, slabs, and stairs. Solved
GAS INDUSTRY ACT 2001 COST RECOVERY ORDER IN COUNCIL
GAS INDUSTRY ACT 2001 COST RECOVERY ORDER IN COUNCIL The Lieutenant-Governor as the Governor s deputy, with the advice of the Executive Council, under section 68 of the Gas Industry Act 2001 ( the Act
Module 2: Job-order costing
Module 2: Job-order costing Required reading Overview Chapter 3, pages 69-99 This module introduces the distinctions between two methods of determining unit costs of production joborder costing and process
A contractor s chart of accounts is the heart of the accounting system. Of particular importance is the cost of sales section (beginning in the 41000
CHART OF ACCOUNTS A contractor s chart of accounts is the heart of the accounting system. Of particular importance is the cost of sales section (beginning in the 41000 series and ending in 43000). This
Management Accounting 303 Segmental Profitability Analysis and Evaluation
Management Accounting 303 Segmental Profitability Analysis and Evaluation Unless a business is a not-for-profit business, all businesses have as a primary goal the earning of profit. In the long run, sustained
QUESTIONS & ANSWERS LOG
QUESTIONS & ANSWERS LOG AUTHORIZATION OF EXTRA WORK (AEW) Q: Is an Authorization of Extra Work form required for all increases in quantities, even for an FCP? A: An Authorization of Extra Work (AEW) form
GUIDANCE NOTE 1.5.2 Cost Control: Price Variation Clauses
GUIDANCE NOTE 1.5.2 Cost Control: Price Variation Clauses Office of Government Procurement Cost Control: Price Variation Clauses Document Reference GN 1.5.2 v1.0 22 January 2016 2016 Department of Public
ACCOUNTING FOR LEASES AND HIRE PURCHASE CONTRACTS
Issued 07/85 Revised 06/90 New Zealand Society of Accountants STATEMENT OF STANDARD ACCOUNTING PRACTICE NO. 18 Revised 1990 ACCOUNTING FOR LEASES AND HIRE PURCHASE CONTRACTS Issued by the Council, New
7. Do you perform any out of state work?... If yes, in what states and provide details of work performed
Applicant s Name* (*If more than one entity, attach separate sheet with description of each entity s operations, relationship to each other and ownership.) Contractors Application Agent Applicant Mailing
1.0 Examples on common security provisions/common welfare provisions
1.0 Examples on common security provisions/common welfare provisions Demands for quality Who Period A. Traffic areas on the site 1. Access roads to the site For heavy traffic from the machinery Main contractor
Pricing Your Work (Overhead Recovery Review)
Pricing Your Work (Overhead Recovery Review) To accurately price your work, you need to be aware of three main factors: 1. The Estimate these costs are the direct costs of labor, equipment, materials,
PG 1. Collecting job costing data is simple if you set up your spreadsheet data properly.
PG 1 Collecting job costing data is simple if you set up your spreadsheet data properly. PG 2 Understanding the Basics of Job Costing Spreadsheets Job Costing is the accounting practice of systematically
North American Development Bank. Prequalification of Contractors
North American Development Bank Prequalification of Contractors PREQUALIFICATION NOTE This note is prepared for the exclusive use of the borrower (the purchaser in this document) and should not be included
Construction Planning, Equipment, and Methods
CHAPTER Construction Planning, Equipment, and Methods EQUIPMENT COST Sixth Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering 3a By Dr. Ibrahim Assakkaf ENCE 420
Materials Management:
Materials Management: Damodara U. Kini, P.E. OFTEN OVERLOOKED AS A COST SOLUTION, SUCCESSFULLY MANAGING MATERIALS CAN LEAD TO GREATER SAVINGS. Damodara U. Kini is procurement manager at Raytheon, Engineers
Construction Contracts
Compiled Accounting Standard AASB 111 Construction Contracts This compiled Standard applies to annual reporting periods beginning on or after 1 January 2009 that end on or after 30 June 2009. Early application
Debris Contracting Guidance
RP9580.201 I Debris Contracting Guidance Overview Debris removal and monitoring contracts must meet rules for Federal grants, as provided for in Title 44 Code of Federal Regulations (CFR) 13.36, Procurement
Traffic Management Issue 1.0 Revision: v2 October 2014
Disclaimer IMPORTANT: The information in this guide is of a general nature, and should not be relied upon as individual professional advice. If necessary, legal advice should be obtained from a legal practitioner
Checklist 26: How Owners Can Avoid Litigation on Construction Projects
Checklist 26: How Owners Can Avoid Litigation on Construction Projects While it is impossible to completely avoid litigation on construction projects, certain steps can be taken to minimize the potential
