Cost Estimating Concepts
|
|
|
- Kristin Davis
- 9 years ago
- Views:
Transcription
1 Cost Estimating Concepts
2 Goal to provide an overview of cost estimating (CE) concepts in order to review CEs prepared by others or to create alternative CEs
3 Why? financial assurance provision based upon detailed thirdparty contractor costs is required by regulations
4 Outline Part 1 - cost estimating definitions, phases & methodologies Part 2 estimate development and format Part 3 key elements of a cost estimate Part 4 cost estimating over time
5 Part 1 Cost Estimating Definitions, Phases & Methodologies
6 working definition a cost estimate is a documented summary of all dollar costs based upon a well-defined scope.
7 3 cost estimate phases site characterization +100% to -50% conceptual design +50% to -30% final design +15% to -10%
8 3 cost estimating methods benchmark based upon data from past projects factored to new projects parametric based upon more specific parameters and more precise pricing detailed a bottoms-up estimate based upon a more extensive breakdown of the required activities
9 Benchmark Cost Estimate Examples 1 Cap 10 $200K/ac = $2M 2 Construct 1,500 LF of 25-foot deep slurry $250/LF = $375K
10 benchmark comparisons The age of a past project should be taken into account when comparing cost estimates. The scale of the project should be considered. The complexity of a project will also influence the costs.
11 Parametric Cost Estimating RACER is focused on remedial actions and corrective actions CostPro is for closures & post closures Both build cost estimates based upon parameters such as acreage, depth to groundwater, tonnage, volume, etc.
12 Detailed Cost Estimates basis of quantity calculations unit prices & sources extended costs work rate assumptions crew & equipment assumptions disposal assumptions other documentation
13 definition of detailed CE regulations do not define detailed 1986 FR notice preamble states: the cost estimates must contain sufficient detail to allow them to be evaluated the agency expects the detailed CEs to support the detailed activities described in the closure/post-closure plans
14 Closure/Post Closure CEs 3rd-party costs no parents or subsidiaries most expensive option maximum quantities salvage value of wastes not allowable economic value of wastes not allowable must adjust for inflation annually during active life of the facility
15 Corrective Action CEs 2003 Interim Guidance no detailed regulations regulatory flexibility & discretion CE and FA at remedy select FA can be required prior to CA 400 incremental CEs and FA good idea to adjust annually
16 Definitions Summary Part 1 three CE phases (100%, 50%, 15%) three general methodologies (benchmark, parametric, detailed) Regulatory requirements
17 Part 2 Estimate Development and Format
18 a well-developed cost estimate involves: Scoping Pricing Documenting
19 Scoping a scope begins with a permit, order, investigation and/or design
20 Work Breakdown Structure use a Work Breakdown Structure (WBS) when developing or defining the scope
21 WBS Example No. 1 Level 1 Storage Unit Closure Level 2 Remove/Dispose Waste Materials Clean Building Surfaces Conduct Confirmation Sampling Level 3 Sampling Labor Analytical Costs Reporting Packaging and Labeling Loading Transportation Disposal
22 WBS Example No. 2 Facility A Activity 1 Capping Activity 2 Slurry Wall Activity 3 GW Extraction
23 wbs example no. 2 cont d Activity 1 Capping Year 1 Cap Construction Annual Sampling & Analysis Annual Inspection & Maintenance
24 Pricing (quantification) first specified number of units: how many items/events, etc. second conversions, work rates, frequency, crews, etc. third unit pricing & extended costs
25 Quantities may be obtained from plans, specs, etc. or calculated by estimator from other specified quantities (e.g., tons derived from cubic yards) or inferred by estimator performance- based design, for example
26 Documenting basis of quantities calculations & conversions crew configurations work rates (productivity) unit pricing sources other assumptions
27 Why Document the Cost Estimate? 1. To create a defensible and transparent cost estimate. 2. To make future updating easier. 3. To allow for easier use of cost estimate or individual elements by others in the future.
28 Summary Part 2 three basic CE essentials: scoping (including WBS) pricing documenting
29 Part 3 - Basic CE Elements units of measure unit pricing productivity direct costs indirect costs contingencies
30 Units of Measure (UOM) UOMs provide definition to activities and determine their pricing sources (e.g., tons, cubic yards, gallons, linear feet, lump sum, hours, days, each, acres, etc.)
31 UOMs must match the activity For example, soil excavation and loading costs are may be based on cubic yards, while soil transportation & disposal costs may be based on tonnage.
32 Unit Pricing Sources RCRA & CERCLA files Prior Estimates Bids Contracts Vendor quotes Catalogs and on-line sources
33 unit pricing is affected by: locality factors work rates safety levels site conditions
34 Location Factors location factors adjust unit pricing to account for the variability in prices across geographic areas
35 work rate (productivity) is a function of: labor quantity equipment quantity and type
36 Safety Factor May be appropriate at some sites or for some activities (e.g., tank cleanout). Unit costs found in R.S. Means and other sources will likely assume a Safety Level D.
37 site conditions confined spaces vs. open areas topography active facility vs. closed geology
38 Direct Costs (DCs) Direct costs consist of the labor, equipment and material directly related to a specific activity.
39 Indirect Costs Indirect costs represent sitewide costs which are not specifically attributable to a work activity
40 Indirect Costs Facility operators may inadvertently exclude some or all indirect costs (i.e., procurement, utilities, security, planning, mobilization, travel, bonds, insurance, site management) because these costs often are internal costs to the facility, and are not easily tracked and quantifiable.
41 other terms for indirect costs: Engineering Expenses Administrative Costs Site Management Costs Overhead Costs Construction Mgmt. Costs General Conditions
42 Indirect Costs Typically calculated as a % of DCs. Variable for site complexity & volumes. Applied to the entire cost estimate or only portions (e.g., capital versus O&M). Some DCs already may be burdened.
43 Indirect Cost factors include: Construction/Project Management Engineering during construction G&A costs (home office costs) Change Orders Insurance/bonds/permits Profit Project Management during O&M
44 site-wide indirect cost and profit EPA Region 4 removal projects range from 19% to 25%. RSMeans cost data range from 10% to 25%.
45 Construction Management/ Project Management Bidding, planning, permitting, contract administration, reporting, etc. Mobilization, crew travel expenses, review of plans, construction inspection, engineering surveys, change orders, subcontractor oversight, O&M manual preparation, security, IDW disposal, etc.
46 G&A/Overhead Overhead are the costs incurred by an employer over and above direct salaries and benefits paid to employees working on a project (e.g., insurance, office rent, office equipment costs, and administrative costs including support staff salaries).
47 Contractor Profit Calculated as a % of contractor DCs & OH. Applied to both capital and O&M costs. Sub profit ranges from 5 to 12% of DC & OH. General contractor profit: 4 to 15% for their own work and 4 to 8% for subs.
48 O&M Project Support Provided during O&M activities to monitor, evaluate, and report the progress of the activities. May be full-time or part-time. Typically ranges from 10 to 20% of the total annual O&M costs.
49 Contingencies Contingencies account for errors of omission and unforeseen circumstances Actual factor applied depends on the complexity of the site, detail level of the estimate, and stage of project planning. Typically 10 to 25% of total cost.
50 Summary Part 3 units of measure unit pricing productivity direct costs indirect costs contingencies
51 Part 4 Cost Over Time Inflation Present Value (discounting) Nominal vs. Real Discount Rates Excel Calculations Perpetual Care Value Decision Tree
52 Inflation Inflation measures the change in the cost of goods and services over time. Implicit Price Deflator for GDP is a measure of the change in prices of all new, domestically produced, final goods and services and is published by the Bureau of Economic Analysis (BEA).
53 Inflation of Past Costs Unit price in 2003: $ Current Year: 2008 Inflated 2008 Price = $ $ Year GDP Deflator
54 Inflating Future Costs Important to select a realistic inflation rate for future costs. Reasonable to use the average inflation rate for a period in the past. For example, the average GDP inflation rate for the past 20 years is 2.39%. Cost in Year X = Cost in Year Y * (Inflation Rate) (Y-X)
55 Inflation Example 2008 Unit Cost = $10,000 Assumed Future Inflation Rate = 2.39% Anticipated Unit Cost in 2015 = $10,000 * ( ) ( ) = $11,798
56 Inflating Future Cost Employ the latest Congressional Budget Office s (CBO) Economic forecast
57 Post Closure Costs Multiply estimated one-year costs by the number of years remaining in the postclosure care period to obtain the total post-closure cost estimate. Post closure regulations do not recognize the time value of money.
58 present value analysis: projects long-term costs in present-day terms compares alternative remedies by stating the costs current dollars recognizes the time value of money and is not used for post-closure projections
59 Present Value The present value of a future amount is the present principle figure that must be deposited today at a given interest rate to yield the desired future amount.
60 Nominal vs. Real Discount Rates Nominal discount rates are used with data that has been inflated prior to applying the nominal rate. Real discount rates are used with data that has not been adjusted for inflation (out-years not inflated).
61 Present Value Calculations Present values are determined by using discount rates (interest rates) which are presumed to have long-term validity. OMB in Circular A-94, Appendix C, indicates a 30-year real discount rate of 2.8% and a 30-yr nominal discount rate of 4.9% (January, 2008).
62 Present Value Calculation Basic Present Value Calculation is: Future Payment PV = (1 + Annual Discount Rate) n Cost in 2011 = $10,000 Annual Discount Rate = 2.8% n = number of years = 2 Present Value in 2009$ = $10,000/(1.028) 2 = $9,463
63 Excel Calculations Excel has a Present Value function (PV) and a Net Present Value (NPV) function. The PV function is used with constant annual cash flows. The NPV function is used with irregular annual cash flows.
64 Excel Present Value Function PV(rate,nper,pmt) Rate is the annual discount rate in decimal format (2.8% = or 7% = 0.07) Nper is the total number of payments (10 yrs) Pmt is the annual payment ($10,000/yr) Assumes payments are made at the end of each year Undiscounted cost of $100,000 ($10,000*10 yrs) PV(0.028,10,-10000) = $86,179 PV(0.07,10,-10000) = $70,236
65 Excel Net Present Value Function NPV(rate,value1,value2, ) Each value can vary and is entered individually Use if annual costs fluctuate and you want to calculate in one function. Annual discount rate of 2.8% Assume undiscounted capital costs of $1,200,000 Year 1: $100,000 - Year 3: $400,000 Year 2: $500,000 - Year 4: $200,000 NPV(0.028, , , , ) = $1,117,692
66 Excel Present Value If the base year of the O&M is different than the base year of the cost estimate you have to discount the PV function to the base year. Example: Calculate the PV of O&M costs of $10,000 per year for 10 years starting in 2015 for a cost estimate with a base year of PV(0.028,10,-10000)/(1.028) 5 = $75,065
67 Perpetual Care Value for FA To calculate an investment target for Facilities where the long-term care term (period of operation) is indefinite: Annual Cost /Interest rate = Perpetual Care Value example: $100K/.03 = $3.333 Million
68 Decision Tree Analysis develop an estimate for each alternative remedy. assign a probability to each alternative remedy and multiply by the cost of each to develop target cost estimate at any point in the remedy selection process.
69 Example Decision Tree Soil Disposal 3,000 cy Probabilistic Result ($142.50/cy) = $427,500 Low Landfill Tipping Fee $91.50/cy = $274.5K Medium Landfill Tipping Fee $135.00/cy = $405K High Landfill Tipping Fee $208.50/cy = $625.5K 25% 50% 25%
70 Summary Part 4 Inflation Present Value Nominal vs. Real Discount Rates Excel Calculations Perpetual Care Value Decision Tree
71 Questions
Cost Estimating for RCRA Financial Assurance
Cost Estimating for RCRA Financial Assurance A good cost estimate is a key link between an approved permit, plan, or remedy selection and the need to obtain adequate financial assurance Many if not most
CHAPTER 4 TYPES OF COST ESTIMATES
CHAPTER 4 TYPES OF COST ESTIMATES 1. INTRODUCTION All projects, both construction and environmental restoration, require cost estimates to plan and budget the project efficiently. Numerous estimates are
PROJECT COST MANAGEMENT
7 PROJECT COST MANAGEMENT Project Cost Management includes the processes required to ensure that the project is completed within the approved budget. Figure 7 1 provides an overview of the following major
1.040 Project Management
MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Project Financial Evaluation
Overview of the Remedial Action Cost Engineering Requirements (RACER ) Software
Overview of the Remedial Action Cost Engineering Requirements (RACER ) Software For More Information, Please Contact: Andrew Schleppi RACER Product Line Manager 717 17th Street, Suite 2600 Denver, CO 80202
Cost Analysis Key Components Guidance and Checklist
Cost Analysis Key Components Guidance and Checklist A Mandatory Reference for ADS Chapter 300 New Edition Date: 04/02/2013 Responsible Office: M File Name: 300mad_040213 COST ANALYSIS KEY COMPONENTS GUIDANCE
Quick Guide to Cost and Price Analysis for HUD Grantees and Funding Recipients
Quick Guide to Cost and Price Analysis for HUD Grantees and Funding Recipients Who is this guide for? This guide is for all HUD grantees and funding recipients that contract for services and/or supplies
Helen Mercury Mine EE/CA OPINION OF PROBABLE COST
G Cost Estimates Helen Mercury Mine EE/CA Alternative 2: Limited Action 3 Minor Road Improvements 4 Clear & Grub diversion channel areas 5 Surveying 6 Cleanup & Demobilization 7 Pull back of material 8
PROJECT PROCUREMENT MANAGEMENT
12 PROJECT PROCUREMENT MANAGEMENT Project Procurement Management includes the processes required to acquire goods and services from outside the performing organization. For simplicity, goods and services,
Performance Management for Environmental Remediation Projects. William C. Lattin, PMP US Department of Energy Idaho Operations Office
Performance Management for Environmental Remediation Projects William C. Lattin, PMP US Department of Energy Idaho Operations Office Course Objectives Awareness of the types of cost estimating used to
Auditing Capital Projects and Project Controls. March 2013
Auditing Capital Projects and Project Controls March 2013 Internal Audit Perspective Oversight Insight Foresight Is the process operating as planned? Are controls, resources, and performance measures adequate
Independent Government Cost Estimate Guide and Template
Independent Government Cost Estimate Guide and Template A Mandatory Reference for ADS Chapter 300 New Edition Date: 04/02/2013 Responsible Office: M File Name: 300maa_040213 INDEPENDENT GOVERNMENT COST
Solutions to Problems: Chapter 5
Solutions to Problems: Chapter 5 P5-1. Using a time line LG 1; Basic a, b, and c d. Financial managers rely more on present value than future value because they typically make decisions before the start
SOMETIMES the cost of installing a landscape plan
Pricing the Landscape Plan SOMETIMES the cost of installing a landscape plan can be quite shocking for those not familiar with all the elements of a landscape. When one breaks down the various expenses
[Project Name] NZTA Contract No. [Contract Number] Schedule of Prices
[Project Name] NZTA Contract No. [Contract Number] Schedule of Prices Schedule of Prices SP1
PRESENT VALUE ANALYSIS. Time value of money equal dollar amounts have different values at different points in time.
PRESENT VALUE ANALYSIS Time value of money equal dollar amounts have different values at different points in time. Present value analysis tool to convert CFs at different points in time to comparable values
Schedule of Prices. Project Name Contract No. Contract Number
Schedule of Prices Project Name Contract No. Contract Number C3-LS-BP-Issue 2 SP Page 1 Printed 1 March 2011 >: 1. When preparing the schedule
Unit 5: Cost Management (PMBOK Guide, Chapter 7)
(PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for
Amortization Cost. Depreciation. Overhead. Making Solid (Waste) Decisions With Full Cost Accounting 1EPA
United States Environmental Protection Agency EPA530-K-96-001 June 1996 1EPA Solid Waste and Emergency Response (5306W) Making Solid (Waste) Decisions With Full Cost Accounting Amortization Cost Depreciation
Macroeconomics Instructor Miller GDP Practice Problems
Macroeconomics Instructor Miller GDP Practice Problems 1. Gross domestic product in the economy is measured by the A) total number of goods and services produced in the economy. B) dollar value of all
CHAPTER 5 FINANCIAL BENEFIT-COST ANALYSIS
CHAPTER 5 FINANCIAL BENEFIT-COST ANALYSIS 122 HANDBOOK FOR THE ECONOMIC ANALYSIS OF WATER SUPPLY PROJECTS CONTENTS 5.1 Introduction...123 5.2 Financial Revenues...124 5.3 Project Costs...126 5.3.1 Investments...127
Life Cycle Cost Analysis (LCCA)
v01-19-11 Life Cycle Cost Analysis (LCCA) Introduction The SHRP2 R-23 Guidelines provide a number of possible alternative designs using either rigid of flexible pavements. There is usually not a single
Lease Analysis Tools
Lease Analysis Tools 2009 ELFA Lease Accountants Conference Presenter: Bill Bosco, Pres. [email protected] Leasing 101 914-522-3233 Overview Math of Finance Theory Glossary of terms Common calculations
Project Cost Management
Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-982-9 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-982-9 The material contained within
Objectives. Single Audit: Recent Changes and Preparation Tips. Overview. Overview 1/20/2016
Objectives Single Audit: Recent Changes and Preparation Tips January 21, 2016 Discuss and review recently issued Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal
TOPIC 12 CONTRACT COST AND PRICE ANALYSIS
CONTRACT AUDIT GUIDE FRAMEWORK TOPIC 12 CONTRACT COST AND PRICE ANALYSIS Objective To determine whether the agency effectively conducts cost or price analysis to arrive at fair and reasonable prices for
Module 5: Interest concepts of future and present value
Page 1 of 23 Module 5: Interest concepts of future and present value Overview In this module, you learn about the fundamental concepts of interest and present and future values, as well as ordinary annuities
Chapter 14 Special Report for the Public Accounts Committee Evergreen and Wackenhut Leases
Special Report for the Public Accounts Committee Evergreen and Wackenhut Leases Contents Background.............................................................. 183 Scope...................................................................
THE MYTH OF DEEP PIPES: CRITICALITY AND PIPE REHABILITATION STRATEGIES
THE MYTH OF DEEP PIPES: CRITICALITY AND PIPE REHABILITATION STRATEGIES Ken Harlow, Director of Management Services, Brown and Caldwell [email protected] Introduction A fundamental principal of asset
If I offered to give you $100, you would probably
File C5-96 June 2013 www.extension.iastate.edu/agdm Understanding the Time Value of Money If I offered to give you $100, you would probably say yes. Then, if I asked you if you wanted the $100 today or
CHAPTER 23 LIFE-CYCLE COST ESTIMATE
CHAPTER 23 LIFE-CYCLE COST ESTIMATE 1. INTRODUCTION Life-cycle costs (LCCs) are all the anticipated costs associated with a project or program alternative throughout its life. This includes costs from
Introduction PURPOSE OF THIS BOOK
1 C H A P T E R Introduction PURPOSE OF THIS BOOK The purpose of this book is to enable the reader to gain fundamental knowledge of estimating the cost of projects to be constructed. Experienced estimators
Excel Financial Functions
Excel Financial Functions PV() Effect() Nominal() FV() PMT() Payment Amortization Table Payment Array Table NPer() Rate() NPV() IRR() MIRR() Yield() Price() Accrint() Future Value How much will your money
Overview of the Remedial Action Cost Engineering Requirements (RACER ) Software
Overview of the Remedial Action Cost Engineering Requirements (RACER ) Software For More Information, Please Contact: Andrew Schleppi RACER Product Line Manager 717 17th Street, Suite 2600 Denver, CO 80202
Presented by: Laura Davis, President Strategic Consulting Solutions, Inc. PDS Consulting Solutions, LLC November 12, 2015
Presented by: Laura Davis, President Strategic Consulting Solutions, Inc. PDS Consulting Solutions, LLC November 12, 2015 Agenda Introductions RFP Process Types of Costs Pricing of Direct Costs Pricing
APPENDIX G VOLUME DETERMINATION DRAFT FEASIBILITY STUDY
PORTLAND HARBOR RI/FS APPENDIX G VOLUME DETERMINATION DRAFT FEASIBILITY STUDY DRAFT Prepared for The Prepared by Anchor QEA, LLC TABLE OF CONTENTS TABLE OF CONTENTS... I LIST OF FIGURES... II LIST OF TABLES...
CHAPTER 2 QUANTITY TAKE-OFF
CHAPTER 2 QUANTITY TAKEOFF The quantity takeoff is an important part of the cost estimate. It must be as accurate as possible and should be based on all available engineering and design data. Use of appropriate
How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013
How to Estimate the Cost of Support of Excavation for Foundation Installation CPE Candidate No. 0113013 May 15, 2013 1 How to Estimate the Cost of Support of Excavation for Foundation Installation Table
NOTICE: For details of the project history please look under the Work Plan section of this website.
NOTICE: This Exposure Draft is available to show the historic evolution of the project. It does not include changes made by the Board following the consultation process and therefore should not be relied
Bills of Quantity. D. Atkinson December 2000. Nature of Bills
Bills of Quantity D. Atkinson December 2000 Nature of Bills Bills of Quantities comprise a list of items of work which are briefly described. The Bills also provide a measure of the extent of work and
The Total Economic Impact Of SAS Customer Intelligence Solutions Intelligent Advertising For Publishers
A Forrester Total Economic Impact Study Commissioned By SAS Project Director: Dean Davison February 2014 The Total Economic Impact Of SAS Customer Intelligence Solutions Intelligent Advertising For Publishers
Chapter 2 Present Value
Chapter 2 Present Value Road Map Part A Introduction to finance. Financial decisions and financial markets. Present value. Part B Valuation of assets, given discount rates. Part C Determination of risk-adjusted
Potential Dredged Material Storage Facilities and Their Impact on Public Processing Facility Economic Modeling Summary Report
Port of New York and New Jersey Feasibility Analysis for a Dredged Material Public Processing Facility Potential Dredged Material Storage Facilities and Their Impact on Public Processing Facility Economic
Chapter 6 Valuing Bonds. (1) coupon payment - interest payment (coupon rate * principal) - usually paid every 6 months.
Chapter 6 Valuing Bonds Bond Valuation - value the cash flows (1) coupon payment - interest payment (coupon rate * principal) - usually paid every 6 months. (2) maturity value = principal or par value
CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING
CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter will
Incorporating Greener Cleanups into Remedy Reviews
Association of State and Territorial Solid Waste Management Officials (ASTSWMO) Incorporating Greener Cleanups into Remedy Reviews Prepared by the Greener Cleanups Task Force Under the Sustainability Subcommittee
CHAPTER 6 PROJECT CASH FLOW
CHAPTER 6 PROJECT CASH FLOW In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter will deal with project
CHAPTER 9 Time Value Analysis
Copyright 2008 by the Foundation of the American College of Healthcare Executives 6/11/07 Version 9-1 CHAPTER 9 Time Value Analysis Future and present values Lump sums Annuities Uneven cash flow streams
UNDERGROUND STORAGE TANK SYSTEM CLOSURE REPORT FORM
APPENDIX D COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF ENVIRONMENTAL CLEANUP AND BROWNFIELDS UNDERGROUND STORAGE TANK SYSTEM CLOSURE REPORT FORM - Facility I.D. Facility
GASB Statement 49 Accounting and Financial Reporting for Pollution Remediation Obligations Implementation Issues in a Question and Answer Format
GASB Statement 49 addresses accounting and financial reporting standards for pollution (including contamination) remediation obligations, which are obligations to address the current or potential detrimental
COST AND PERFORMANCE REPORT
COST AND PERFORMANCE REPORT Pump and Treat of Contaminated Groundwater at the United Chrome Superfund Site Corvallis, Oregon September 1998 Prepared by: SITE INFORMATION Identifying Information: United
700 Life-Cycle Cost Analysis... 700-1
Table of Contents 700 Life-Cycle Cost Analysis... 700-1 701 Introduction... 700-1 701.1 Discount Rate... 700-1 702 Initial Construction... 700-1 703 Future Rehabilitation... 700-1 703.1 Introduction...
Construction Planning, Equipment, and Methods
CHAPTER Construction Planning, Equipment, and Methods EQUIPMENT COST Sixth Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering 3a By Dr. Ibrahim Assakkaf ENCE 420
Debris Contracting Guidance
RP9580.201 I Debris Contracting Guidance Overview Debris removal and monitoring contracts must meet rules for Federal grants, as provided for in Title 44 Code of Federal Regulations (CFR) 13.36, Procurement
Estimate Memorandum/ Basis of Estimate
Estimate Memorandum/ Basis of Estimate To: From: Mary Ann Lasch, FASLA Eric Link, CCT Date: March 14, 2012 Subject: Tiger Grant Pedestrian Walkway and Parking Garage- Conceptual, Rough Order of Magnitude
What is the net present value of the project (to the nearest thousand dollars)?
corporate finance, final exam practice questions, NPV *Question 1.1: Net Present Value A firm invests $200,000 in machinery that yields net after-tax cash flows of $90,000 at the end of each of the next
7 CFR Parts 3400, 3401, 3402, 3403, 3405, 3406, 3407, 3415, 3430, and 3431
This document is scheduled to be published in the Federal Register on 02/16/2016 and available online at http://federalregister.gov/a/2016-02473, and on FDsys.gov Billing Code: 3410-KS-P DEPARTMENT OF
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson E: Risk and Procurement Management Presented by Sam Lane [email protected] Ph: 703-883-7149 Presented at the IPM 2002 Fall Conference Prepared by the Washington,
CHAPTER 6. Accounting and the Time Value of Money. 2. Use of tables. 13, 14 8 1. a. Unknown future amount. 7, 19 1, 5, 13 2, 3, 4, 6
CHAPTER 6 Accounting and the Time Value of Money ASSIGNMENT CLASSIFICATION TABLE (BY TOPIC) Topics Questions Brief Exercises Exercises Problems 1. Present value concepts. 1, 2, 3, 4, 5, 9, 17, 19 2. Use
WILDCAT CANYON ROAD SPECIFICATION NO. 16-11001 SLIDE REPAIR BIDDER'S PROPOSAL (continued)
BIDDER'S PROPOSAL (continued) Item Estimated No. Description Quantity Unit Unit Cost Total Cost BASE BID 1 Traffic Control 1 LS $ $ 2 Construction Area Signs 1 LS $ $ 3 Excavation Safety 1 LS $ $ 4 Reset
rate nper pmt pv Interest Number of Payment Present Future Rate Periods Amount Value Value 12.00% 1 0 $100.00 $112.00
In Excel language, if the initial cash flow is an inflow (positive), then the future value must be an outflow (negative). Therefore you must add a negative sign before the FV (and PV) function. The inputs
consulting engineers and scientists
consulting engineers and scientists Incorporating Sustainable Principles into Cleanups June 2014 Presented by: Rich Truax, PE GEI Consultants, 650 Personnel Nationwide Rich Truax, P.E. Sr. Program Manager
Net Present Value and Capital Budgeting. What to Discount
Net Present Value and Capital Budgeting (Text reference: Chapter 7) Topics what to discount the CCA system total project cash flow vs. tax shield approach detailed CCA calculations and examples project
The Business Case Justification
The Business Case Justification Solutions for Capital Project Delivery Improvement (White Paper) Table of Contents Page Introduction... 3 Business Case Structure... 5 Business Case Process... 6 Detailed
RCRA Corrective Action Workshop On Results-Based Project Management: Fact Sheet Series
United States Environmental Protection Agency Office of Solid Waste RCRA Corrective Action Workshop On Results-Based Project Management: Fact Sheet Series EPA March 2000 www. FACT SHEET #1 HISTORY OF RCRA
Problem Set 4: Intro to Corporate Finance. Problem Set 4: Introduction Corporate Real Estate Self-Correcting, Hyperlinked File
Problem Set 4: Introduction Corporate Real Estate Self-Correcting, Hyperlinked File Overview The purpose of this problem set is to extend basic Time Value of Money (TVM) concepts to a range of corporate
CHAPTER 53 COST ACCOUNTING STANDARDS
CHAPTER 53 COST ACCOUNTING STANDARDS A. REQUIREMENTS 0F COST ACCOUNTING SYSTEMS 1. The Defense Business Operations Fund shall have a cost estimating and cost accounting system or, as needed, systems specifically
Project Procurement Management
Project Procurement Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note
Analyzing contract terms: General requirements
Analyzing contract terms: General requirements Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. About Baker Tilly > Established
Part 610 Natural Resource Economics Handbook
Part 610 Natural Resource Economics Handbook 610.20 Introduction Subpart C Discounted Cash Flow Analysis A. Benefits and costs of conservation practices do not necessarily occur at the same time. Certain
Project Management Planning
Initial Release 1. Overview of Project Paralleling the development of the schedule is the development of a budget. At the initial stages of project planning, budgeting is the determination of costs associated
PCB Cleanups. Kurt Limesand EPA Region 7 Waste Remediation and Permitting. 5/1/13 U.S. Environmental Protection Agency 1
PCB Cleanups Kurt Limesand EPA Region 7 Waste Remediation and Permitting 5/1/13 U.S. Environmental Protection Agency 1 40 CFR Part 761 Polychlorinated Biphenyls (PCBs) Subpart D: Storage and disposal 761.61
Project Management. Sources of Funds
Project Management Sources of Funds After a grant award is made, the funds are received at the college in several different ways. Some agencies send lump sum portions of the entire award at intervals during
CHAPTER 7: NPV AND CAPITAL BUDGETING
CHAPTER 7: NPV AND CAPITAL BUDGETING I. Introduction Assigned problems are 3, 7, 34, 36, and 41. Read Appendix A. The key to analyzing a new project is to think incrementally. We calculate the incremental
Developing Critical Path Method Scheduling (CPM)
Developing Critical Path Method Scheduling (CPM) Pretest 1. An activity which is on critical path has a planned duration of 5 days. What is the total float for the activity? a. 0 b. 1 c. 2 d. 3 Pretest
Cost Estimating Procedure. Table of Contents
Cost Estimating Procedure Table of Contents 1.0 PURPOSE... 1 2.0 SCOPE... 1 3.0 REFERENCES... 1 4.0 DESCRIPTION... 1 5.0 PROCEDURE DETAILS... 2 5.1 Developing a Detailed Cost Estimate... 2 5.2 Basis of
FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation
644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING
National Heavy Duty Truck Transportation Efficiency Macroeconomic Impact Analysis
National Heavy Duty Truck Transportation Efficiency Macroeconomic Impact Analysis Prepared for the: Union of Concerned Scientists 2397 Shattuck Ave., Suite 203 Berkeley, CA 94704 Prepared by: Marshall
Geographic Information System Tools for Management of US DOE Sites 14125
Geographic Information System Tools for Management of US DOE Sites 14125 John Montgomery*, Cliff Carpenter*, Leonard Turton**, Steve Pawel** *US DOE, Office of Legacy Management **S.M. Stoller Corporation
Module 5: Interest concepts of future and present value
file:///f /Courses/2010-11/CGA/FA2/06course/m05intro.htm Module 5: Interest concepts of future and present value Overview In this module, you learn about the fundamental concepts of interest and present
LEGAL SERVICES CORPORATION OFFICE OF INSPECTOR GENERAL FINAL REPORT ON SELECTED INTERNAL CONTROLS RHODE ISLAND LEGAL SERVICES, INC.
LEGAL SERVICES CORPORATION OFFICE OF INSPECTOR GENERAL FINAL REPORT ON SELECTED INTERNAL CONTROLS RHODE ISLAND LEGAL SERVICES, INC. RNO 140000 Report No. AU 16-05 March 2016 www.oig.lsc.gov TABLE OF CONTENTS
Detailed Estimation and Pumpstation Overview. Nathaniel Osgood 3/3/2004
Detailed Estimation and Pumpstation Overview Nathaniel Osgood 3/3/2004 Announcements TP2 Due Date: March 15 PS4 out tonight Due March 19 Team project Recording of recitation Pietroforte Lecture Important
You just paid $350,000 for a policy that will pay you and your heirs $12,000 a year forever. What rate of return are you earning on this policy?
1 You estimate that you will have $24,500 in student loans by the time you graduate. The interest rate is 6.5%. If you want to have this debt paid in full within five years, how much must you pay each
How to calculate present values
How to calculate present values Back to the future Chapter 3 Discounted Cash Flow Analysis (Time Value of Money) Discounted Cash Flow (DCF) analysis is the foundation of valuation in corporate finance
INSE 6230 Total Quality Project Management
Total Quality Project Management Lecture 9 Project Procurement Management Procurement means acquiring goods and/or services from an outside source Other terms include purchasing and outsourcing Offshoring
THE PROJECT MANAGEMENT KNOWLEDGE AREAS
THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human
UNDERSTANDING HEALTHCARE FINANCIAL MANAGEMENT, 5ed. Time Value Analysis
This is a sample of the instructor resources for Understanding Healthcare Financial Management, Fifth Edition, by Louis Gapenski. This sample contains the chapter models, end-of-chapter problems, and end-of-chapter
Los Angeles County Department Of Public Works. Land Development Division. Bond Calculation Sheets
Los Angeles County Department Of Public Works Land Development Division Bond Calculation Sheets Effective July 1, 2015 COUNTY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS LAND DEVELOPMENT DIVISION ROADS COST
CITY CLERK MEMORANDUM 15-70
CITY CLERK MEMORANDUM 15-70 DATE: November 12,2015 TQ: Honorable Mayor and Members of City Council FROM: Bruce Applegate, Acting City Clerk SUBJECT: ADDITIONS TO THE NOVEMBER 16, 2015 CITY COUNCIL AGENDA
NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9
NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9 A G U I D E T O A I M U K TA X B E N E F I T S 2 AIM Note for Mining, Oil and Gas Companies Contents Introduction 1 Companies to which this Note
Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices
: A CDOT Guide to Better Project Management Practices Project Management practices have been a part of the CDOT culture for many years. However, with a transitioning workforce and increasing demands, it
PRIVATE EQUITY INSIGHTS
In this Energy Investment Education Whitepaper, we discuss, Why It Is Financially Better To Own A Portfolio Of Producing Oil & Gas Working Interest Instead of Producing Royalty Interest. Paul Anthony Thomas