Auditing construction contract change orders
|
|
|
- Stanley Gregory
- 9 years ago
- Views:
Transcription
1 Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. Auditing construction contract change orders
2 Presenter Tony Ollmann, CPA, CCA Director Baker Tilly 22
3 Auditing construction contract change orders Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International Baker Tilly Virchow Krause, LLP
4 About Baker Tilly > Established in 1931 > One of the top 20 largest accounting and advisory firms in the United States according to Accounting Today s 2013 list of Top 100 Firms > More than 1,400 professionals > Baker Tilly Virchow Krause, LLP is the largest US Baker Tilly International independent member firm > Baker Tilly International is the eighth largest public accounting network with representation in more than 131 countries > Convenient, seamless resource for worldwide needs 4
5 About Baker Tilly From concept and funding to controls and compliance, Baker Tilly has more than 250 dedicated construction and real estate industry professionals to assist with your facility development project through h all stages of the development lifecycle. l 5 5
6 Overview Today s topics: Auditing construction contract change orders What are change orders? Audit risks Change order red flags Change order testing Case studies 6
7 Learning objectives > Learn how to identify change orders > Learn how to decompose a change order > Determine the underlying change order driver > Understand the risk associated with different types of change orders > Develop strategies for auditing change orders and managing construction professionals 7
8 What are change orders? 7.3 CONSTRUCTION CHANGE DIRECTIVES A Construction Change Directive is a written order prepared by the Architect and signed by the Owner and Architect, directing a change in the Work prior to agreement on adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner may by Construction Change Directive, without t invalidating the Contract, t order changes in the Work within the general scope of the Contract consisting of additions, deletions or other revisions, the Contract Sum and Contract Time being adjusted accordingly. Source: AIA 133 Standard Form of Agreement Between Owner and Construction Manager 8
9 What are change orders? Change orders are referred to in a number of ways: > Change orders > Change directives > RFI > Engineering change notice > Field change request All amount to the same thing, an owner s authorization to change the terms of the prevailing contract 9
10 AIA change directive documentation 7.3.3If the Construction Change Directive provides for an adjustment to the Contract Sum, the adjustment shall he based on one of the following methods:.1 Mutual acceptance of a lump sum properly itemized and supported by sufficient substantiating data to permit evaluation;.2 Unit prices stated in the Contract Documents or subsequently agreed upon;.3 Cost to he determined in a manner agreed upon by the parties and a mutually acceptable fixed or percentage fee; or.4 As provided in Section Source: AIA 133 Standard Form of Agreement Between Owner and Construction Manager 10
11 Why do change orders occur? > Owner initiated change to the project > Contingency expenditure > Change in construction conditions > Change in specifications > Change in building code > Change in market conditions 11
12 Change in specifications Due to completion of construction documents, changes in building code or refined materials specifications additional labor and materials are required to deliver the scope of work Resulting from: > Bids based on incomplete construction documents > Regulatory design review demands design changes > Equipment specified is modified or changed 12
13 Change in market conditions The cost of procuring construction services, supplies and equipment are materially different than the estimated costs Resulting from: > Dramatic material shortages > Labor shortages > Commodity price speculation 13
14 Change in field conditions Construction conditions are not what was expected or reported to the contractors t May include: > Unusually inclement or adverse weather > Unreported soil conditions > Environmental hazards 14
15 Owner initiated change orders Represent new or additional work not planned for in the estimated t scope May result in: > Increase to the GMP > Change to the construction schedule > Use of contractor s contingency budget > Use of owner s contingency budget > Reduction to another part of the project budget 15
16 Change order audit risks Audit risk categories > Unauthorized change orders > Unnecessary change orders > Redundant or duplicate change orders > Overpriced change orders 16
17 Unauthorized change orders Work that is performed and charged for without having been authorized by the owner Why does this happen? > Miscommunication > Procrastination > Budget overruns > Schedule delays > Rework > Warranty work > Quality issues 17
18 Unnecessary change orders Change orders that have been properly approved dbut tdeliver no apparent value to the project Resulting from > Existing scope > Unnecessary add on 18
19 Overpriced change orders Change orders that have been approved but are overpriced for the scope of work proposed Overpricing i comes from: > Inflated labor rates > Inflated hours > Exaggerated profit margins > Compounded fee computation (fee on fee) 19
20 Contingency budgets and allowances Contractors contingency: Contractor s budget for in scope budget changes Owner s contingency: Owner s budget for scope changes Allowances: Segregated construction budget dedicated for a specific use that may not have a budget and contract or GMP time. 20
21 Change order red flags > No rejected change orders > Project end change orders > Significant value engineering adjustments > Changing contractors t during construction > Too few change orders > Material substitutions > No contractor s contingency reconciliation > No negotiated change orders > Remodeling projects > Too few change orders > Change order value greater than 10% of original i budget > Bids prepared at less than 100% of construction documents > Remodeling projects 21
22 Audit program Change order audit program planning: > Documentation ti and control > Authorization > Price analysis > Scope analysis 22
23 Documentation and control Change Order Date Date 3% Total change Number Submitted Approved Contractor Description Change Order Reason Submitted Change Submitted Fee order amount 1 11/5/2007 Footing corrections, backfill and pumping Change in conditions $ 12, $ $ 13, /15/2007 Sand, 90 loads Change in conditions $ 5, $ $ 5, /5/2007 Undocumented change order Change in conditions $ 12, $ $ 12, Change Order Adjustment Change Order Adjustment $ 1 7/27/2007 Lobby floor change Owner initiated change $ 3, $ $ 4, Change in conditions $ (1,410.00) $ (42.30) $ (1,452.30) 1 Landscaping changes Owner initiated change $ 1, $ $ 1, Owner initiated change $ 2, $ $ 2, Sanitary Sewer Change Change in Scope $ 16, $ $ 17, Change Order Adjustment Change Order Adjustment $ $ 1 Substitute granite for marble Owner initiated change $ (358.00) $ (10.74) $ (368.74) 1 Plumbing changes Owner initiated change $ 8, $ $ 9, Revisions resulting from state plan 1 review Code Compliance $ 8, $ $ 8, Change OrderAdjustment Change OrderAdjustment $ $ Revisions resulting from local code 1 compliance Code Compliance $ 61, $ 1, $ 63, Change Order Adjustment Change Order Adjustment $ $ Eliminate vinyl trim and substitute 1 vinyl for stone Owner initiated change $ (4,157.00) $ (124.71) $ (4,281.71) 1 Owner initiated adds and deletes Owner initiated change $ 4, $ $ 4, Code compliance from reviews Code Compliance $ 6, $ $ 6, Owner initiated adds and deletes Owner initiated change $ (19,417.00) $ (582.51) $ (19,999.51) 1 Owner initiated adds and deletes Owner initiated change $ 7, $ $ 7, Change Order Adjustment Change Order Adjustment $ $ 1 Additional cultured stone Owner initiated change $ 6, $ $ 7, Design oversight. No towel bars Design deficiency $ 1, $ $ 1, Substitute Western doors for Legace Owner initiated change $ 72, $ 2, $ 74, Added one month of general conditions to compensate for lost production time resulting from permit issues Change in conditions $ 46, $ 1, $ 48, Change Order Adjustment Change Order Adjustment $ $ 1 Total Change Order #1 $ 230,
24 Change order schedule checklist > Verify all change orders are authorized Look for rejected items being resubmitted > Decompose consolidated change orders into individual line items > Look for duplicate change orders Same value at with different dates Same documentation used individually and consolidated > Verify all computations > Look for old line items 24
25 Change order pricing Case Study Facts Scope: Add outlets, lights, dimmers per owners request Electrical contractor s invoice Labor cost: 280 $95 $26,600 Material cost: Outlets, switches, lights. Supported with supplier invoices $15,000 Analysis: > Materials were passed through at cost > Overhead and profit were at contract t terms > Labor was at contracted rate > Owner was overcharged $2,660 or 6% of the change order value Subtotal $41,600 Why? Labor rate Overhead and profit 10% already included $4,160 (per contract terms) overhead and profit Total $45,760 25
26 Change order pricing audit checklist > Request detail backup for lump sum change orders > Verify labor rates with base contract > Verify hours are appropriate for scope of work > Verify quantities are appropriate for scope of work > OCIP projects make sure to discount labor rates for owner paid workers compensation insurance > Negative change orders should include a CM fee credit > Verify that general conditions changed before accepting a GC fee adjustment Resources > TRA-SER > Equipment Watch > Composite crew rate analysis > RS Means > Labor burden analysis 26
27 Polling question #4 What is a composite crew rate? A. Average crew billing rate B. Weighted average crew billing rate Please respond using the polling section in the WebEx screen to the right. 27
28 Composite crew rate analysis Labor Burden Total Hourly Fully Loaded Composite Composite Crew Planning Rate Rate Wage Quantity Hours Daily Wage Rate Raw Wage Raw Wage 2009 Superintendent % $ - $ $ $ General Foreman % $ - $ $ $ Foreman % $ - $ $ $ Journeyman % 00% $ - $ $ 3, $ 3, Apprentice % $ - $ $ $ % $ 5, $ 5, % Superintendent % $ - $ $ $ General Foreman % $ - $ $ $ Foreman % $ - $ $ $ Journeyman % $ - $ $ 3, $ 3, Apprentice % $ - $ $ $ % $ 5, $ 5, % % Superintendent % $ - $ $ $ General Foreman % $ - $ $ $ Foreman % $ - $ $ $ Journeyman % $ - $ $ 3, $ 3, Apprentice % 00% $ - $ $ $ $ 5, $ 5,
29 Third party pricing: RS Means 29
30 Labor burden analysis Contractor Name: Rate Applicability Period: Contractor Labor Rate Calculation Occupation: Superintendent Straight Time Reported Base Wage ($ Per Hour) $ $ Taxable Benefits (Vacation -As applicable Subtotal Taxable Wages & Benefits $ $ Union Benefits 401K assume 2% of wages $ 0.77 Health & Welfare assume $1000 per month $ 5.77 Safety $ 0.03 Substance Testing $ 0.04 Skills Training $ 1.00 Reported 35% $ Total Benefits $ 7.61 $ Subtotal t Base Rate + Fringes $ $ Insurance Workers Compensation (2%) $ 0.85 Liability Insurance (1.5%) $ 0.64 Payroll Taxes: State Unemployment e (3.9% of $12,300) $ 0.23 Fed Unemployment (6.2% of $7,000) $ 0.21 Medicare (1.45%) $ 0.61 F.I.C.A. (7.65%) $ 3.24 Reported 50% $ Total Tax & Insurance $ 5.78 $ Cost Per Hour $ $ Contract Hourly Rate $ Premium (Discount) $
31 Change order scope analysis Know what is allowed in the contract!! > Examine the change order scope for the source of the change > If you can t discover the source from the documentation ask the subcontractor for an explanation. > Examples of typical non-allowable change orders Rework for quality Rework for plan and specification compliance It is already in the plans and specifications i It should have been in the plans and specifications. An owner has a realistic expectation that the construction drawings will satisfy local and state building code. Design oversight may result in the architect compensating the contractor for rework 31
32 Contractor s contingency Case study facts: > Original lump sum contract value: $6,000,000 with a $50,000 contractor s contingency budget > Change orders reviewed and approved of $750,000 increasing the contract value to $6,750,00 > Contract requires the owner to approve any use of the contingency budget Analysis: > Review of the change order log shows no documented use of contingency budget > Contractor billed through 100% of the change orders with 9% for CM and GC fees > The final application was adjusted for the contingency and the owner was credited $54,
33 Upcoming webinar Wednesday, June 5 Noon to 1:00 PM CT Subcontract default insurance Guest Speakers: Tim Cleary, M3 Insurance and Tim Anderson, Construction Risk Underwriters Registration for this event, today s presentation and other topics in this webinar series can be found at 33
34 Questions? Tony Ollmann, CPA, CCA Director Reminder To qualify for the CPE credit, you must complete the evaluation form at the end of the webinar. 34
35 Disclosure Pursuant to the rules of professional conduct set forth in Circular 230, as promulgated by the United States Department of the Treasury, nothing contained in this communication was intended or written to be used by any taxpayer for the purpose of avoiding penalties that may be imposed on the taxpayer by the Internal Revenue Service, and it cannot be used by any taxpayer for such purpose. No one, without our express prior written permission, may use or refer to any tax advice di in this communication in promoting, marketing, kti or recommending a partnership or other entity, investment plan, or arrangement to any other party. Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. The information provided here is of a general nature and is not intended to address specific circumstances of any individual or entity. In specific circumstances, the services of a professional should be sought Baker Tilly Virchow Krause, LLP 35
36
Qualitative analysis: Analyzing the construction schedule. 2014 Baker Tilly Virchow Krause, LLP
Qualitative analysis: Analyzing the construction schedule 2014 Baker Tilly Virchow Krause, LLP About Baker Tilly > Established in 1931 > One of the top 20 largest accounting and advisory firms in the United
Construction auditing: Continuous monitoring of active construction projects
Construction auditing: Continuous monitoring of active construction projects Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International.
Auditing Engineer-Procure-Construct (EPC) Projects
Auditing Engineer-Procure-Construct (EPC) Projects Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. 2012 Baker Tilly Virchow
Construction Contract Fundamentals. Baker Tilly refers to Baker Tilly Virchow Krause, LLP,
Construction Contract Fundamentals Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. 2010 Baker Tilly Virchow Krause, LLP About
Analyzing contract terms: General requirements
Analyzing contract terms: General requirements Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. About Baker Tilly > Established
Owner s project control review. 2014 Baker Tilly Virchow Krause, LLP
Owner s project control review 2014 Baker Tilly Virchow Krause, LLP About Baker Tilly > Established in 1931 > One of the top 20 largest accounting and advisory firms in the United States according to Accounting
Construction Contract Audit Fundamentals
Construction Contract Audit Fundamentals Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. 2010 Baker Tilly Virchow Krause,
Construction Fraud: Stories from the Field
Construction Fraud: Stories from the Field Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. 2010 Baker Tilly Virchow Krause,
Subcontractor default insurance. 2013 Baker Tilly Virchow Krause, LLP
Subcontractor default insurance 2013 Baker Tilly Virchow Krause, LLP History of the market > 1996: Created by demand of contractors with the goal of taking back control when subcontractors default. > 2012:
Post-Construction Auditing and Fraud Detection
Post-Construction Auditing and Fraud Detection Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. 2010 Baker Tilly Virchow Krause,
REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office
REQUEST FOR PROPOSALS (RFP) - Construction Management Services From: Germantown School District Project: Germantown School District Addition & Renovations to Rockfield Elementary School N132 W18473 Rockfield
Fundamentals of a Construction Audit. August 7, 2014
Fundamentals of a Construction Audit August 7, 2014 Agenda Definitions Risk Based Approach What Determines Risk Fraud Construction Risks What to Audit Red Flags Why Audit Prevention Wrap-up 1 Definitions
Pricing of Construction Contract Change Order Documentation
The contract language contained in this Exhibit will supplement and take precedence over all other change order pricing contract provisions in the Contract Documents provided by the Owner, Design-Builder
Compensation Methods for Architectural Services
Compensation Methods for Architectural Services Compensation Methods for Architectural Services By: Thomas R. Gossen, AIA, PE Secretary/Treasurer and Chief Operating Officer Gossen Livingston Associates,
ON-TIME AND ON-BUDGET: KEY ISSUES IN NEGOTIATING CONSTRUCTION CONTRACTS
ON-TIME AND ON-BUDGET: KEY ISSUES IN NEGOTIATING CONSTRUCTION CONTRACTS ACC REAL ESTATE COMMITTEE PRESENTATION SEPTEMBER 17, 2009 SEAN T. BOULGER, ESQ. WILMER CUTLER PICKERING HALE AND DORR LLP I. Introduction
PREPARING DETAILED BREAKDOWNS FOR CHANGE ORDER PROPOSALS
PREPARING DETAILED BREAKDOWNS FOR CHANGE ORDER PROPOSALS I. GENERAL A. All work to be performed under the change order must be itemized, including the work of all subcontractors. B. Items must be relevant
Understanding changes to the Trust Services Principles for SOC 2 reporting
Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. Understanding changes to the Trust Services Principles for SOC 2 reporting
Utility consulting. > > Operate as a quasi-standalone business with its own profit center > > Focus solely on internal customers
Shared services utility accounting How using a service company approach can help with cost allocations for multiple utility departments Cost allocations can strain a relationship Cost allocations are a
Document Comparison. AIA Documents A134 2009 and A131CMc 2003
Document Comparison AIA Documents A134 2009 and A131CMc 2003 AIA Document A134 2009 is in the right-hand column. Corresponding sections of AIA Document A131 CMc 2003 are in the left-hand column. Sections
PNC is a registered mark of The PNC Financial Services Group, Inc.( PNC ) 2013 The PNC Financial Services Group, Inc. All rights reserved.
The seminar and/or webinar and materials that you will view were prepared for general information purposes only by Baker Tilly and are not intended as legal, tax or accounting advice or as recommendations
State and local tax update for law firms. Baker Tilly refers to Baker Tilly Virchow Krause, LLP,
State and local tax update for law firms Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. 2010 Baker Tilly Virchow Krause,
$&71R SENATE BILL NO. 1105 (SUBSTITUTE FOR SENATE BILL 812 BY SENATOR SCHEDLER)
Regular Session, 2001 $&71R SENATE BILL NO. 1105 (SUBSTITUTE FOR SENATE BILL 812 BY SENATOR SCHEDLER) BY SENATOR SCHEDLER AN ACT To enact Part XXV of Chapter 1 of Title 22 of the Louisiana Revised Statutes
HIPAA Compliance: Are you prepared for the new regulatory changes?
HIPAA Compliance: Are you prepared for the new regulatory changes? Baker Tilly CARIS Innovation, Inc. April 30, 2013 Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed
Financial Institutions Industry Insights
February 2011 Address the heightened risks of your mortgage lending and servicing activities with enhanced internal controls The continuing stress within the housing and mortgage finance industries has
RFQ 00318348 NORTHSTAR AUDITING SERVICES ADDENDUM NO. 1 REF. LOCATION DESCRIPTION OF CHANGE. Revised Scope of Work. Work tasks have been revised.
RFQ 00318348 NORTHSTAR AUDITING SERVICES ADDENDUM NO. 1 DATE PUBLISHED: MAY 18, 2016 TO ALL PROSPECTIVE SUBMITTERS: THE FOLLOWING CHANGES ARE MADE: REF. LOCATION DESCRIPTION OF CHANGE Attachment A Attachment
POST AWARD CONTRACT MANAGEMENT
POST AWARD CONTRACT MANAGEMENT POST AWARD CONTRACT MANAGEMENT Overview of Types of Contracts and Award Methods Understanding the Contract Contents of the Contract Contract Performance Designating an agency
MICHIGAN STATE HOUSING DEVELOPMENT AUTHORITY LOW INCOME HOUSING TAX CREDIT PROGRAM COST CERTIFICATION GUIDELINES TABLE OF CONTENTS
MICHIGAN STATE HOUSING DEVELOPMENT AUTHORITY LOW INCOME HOUSING TAX CREDIT PROGRAM COST CERTIFICATION GUIDELINES TABLE OF CONTENTS 1. Cost Certification Guidelines PAGE I General 1 II Identity of Interest
Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive
Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86
idelpi Software Quick Install and Basic Configuration Guide
idelpi Software Quick Install and Basic Configuration Guide (Trial version) This documentation helps you in installing the trial version of idelpi construction software on your computer. Prerequisites
Labor Compliance Program Guidebook For School Districts
Labor-Management-Consultants P.O. Box 24455 Oakland, CA 94623 Phone: (510) 835-7603 Fax: (510) 835-7613 www.davillier-sloan.com [email protected] Labor Compliance Program Guidebook For School Districts
Quick Guide to Cost and Price Analysis for HUD Grantees and Funding Recipients
Quick Guide to Cost and Price Analysis for HUD Grantees and Funding Recipients Who is this guide for? This guide is for all HUD grantees and funding recipients that contract for services and/or supplies
Memorandum Potentially Affected AIA Contract Documents AIA Document A105 2007 AIA Document B105 2007 Important Information
Memorandum Important information related to requirements of state or local laws to include additional provisions in residential construction contracts Potentially Affected AIA Contract Documents AIA Document
Bond Program Standard Operating Procedures
Los Angeles Community College District Bond Program Standard Operating s Volume III Construction Version Review 3 Issuance Date LACCD Program Management Office 515 S. Flower Street, Suite 900 Los Angeles,
INTERNAL CONTROL MATRIX FOR AUDIT OF LABOR AND ACCOUNTING CONTROLS Version No. 4.2 June 2006
INTERNAL CONTROL MATRIX FOR AUDIT OF LABOR AND ACCOUNTING CONTROLS Version No. 4.2 June 2006 Control Objectives ExampleControl Activities Audit Procedures 1. MANAGEMENT REVIEWS Monitor the overall integrity
CHAPTER 23. Contract Management and Administration
Date Issued: June 12, 2009 Date Last Revised: September 28, 2015 CHAPTER 23. Contract Management and Administration Table of Contents CHAPTER 23. Contract Management and Administration... 23-1 23.1 Policy...
OUR COMPANY SOLICITATION FOR BIDS and CONTRACT FOR SERVICE. (Project)
OUR COMPANY SOLICITATION FOR BIDS and CONTRACT FOR SERVICE (Project) PART I GENERAL TERMS AND CONDITIONS 1. REQUIREMENTS 1.1. Pricing will be per unit shown and charges will be totaled in the extension
Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel
Page 1 of 6 ALM Properties, Inc. Page printed from: New York Law Journal Back to Article Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel James E. Hughes New York
Tel: (617) 727-4050 Fax: (617) 727-5363. OWNER S PROJECT MANAGER GUIDELINES M.G.L. c. 149, 44A1/2
The Commonwealth of Massachusetts Executive Office for Administration and Finance Division of Capital Asset Management One Ashburton Place Boston, Massachusetts 02108 Tel: (617) 727-4050 Fax: (617) 727-5363
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
STANDARD SUBCONTRACT AGREEMENT FOR BUILDING CONSTRUCTION
STANDARD SUBCONTRACT AGREEMENT FOR BUILDING CONSTRUCTION THIS AGREEMENT made at Columbus, Ohio on by and between Lincoln Construction, Inc., hereinafter referred to as the Contractor, and, hereinafter
Year-End Fringe Benefit Reporting and Other Reporting Requirements
and Other Reporting Requirements November 2013 TO: RE: All Business Clients Year-End Fringe Benefit Reporting and Other Reporting Requirements DATE: November 20, 2013 Certain fringe benefits paid for or
Construction Company Capacity Assessment
Business/Firm Name: Vendor NCDOT Number: Contact Address: Construction Company Capacity Assessment Name/Title of Person Taking Assessment: Phone Contact Information: Email Contact Information: List Current
Audits of Automobile Body and Repair Shops
Audits of Automobile Body and Repair Shops If you are in certain retail businesses, industry specific audit procedures may be performed by the IRS in addition to the standard procedures performed during
ACCOUNTING SYSTEM REQUIREMENTS for PROFESSIONAL CONSULTANTS. Background and Authority
ACCOUNTING SYSTEM REQUIREMENTS for PROFESSIONAL CONSULTANTS The Office of Inspector General, Florida Department of Transportation, has prepared this Primer to illustrate and explain some required elements
Construction Change Orders
Construction Change Orders Michael E. Purdy Contracts Manager University of Washington (206) 221-4235 [email protected] 1 Agenda Tools to Prevent Change Orders 4 Elements of Change Orders Authorization
CHAPTER 7 COST PRINCIPLES
CHAPTER 7 COST PRINCIPLES 7101. Cost Principles. (a) Definitions. (1) Actual Costs are all direct and indirect costs which have been incurred for services rendered, supplies delivered, or construction
Capital Projects and Construction: Building in Risk Management and Project Controls
Capital Projects and Construction: Building in Risk Management and Project Controls Making Every Dollar Count The global economic crisis sparked by the subprime mortgage debacle, the collapse of the securitized
GCBT. The Effect of Obamacare on Construction Companies. Strategies for compliance leading to more competitive bidding
February 2013 The Effect of Obamacare on Construction Companies Strategies for compliance leading to more competitive bidding by Jeffrey Bennett, MBA, QPFC and Thomas Santa Barbara, QPFC GCBT Government
Reasons for Change Orders
T E X A S D E PA R T M E N T O F T R A N S P O R TAT I O N A change order is defined in the 2004 Standard Specification Book as a written order to the Contractor detailing changes to the specified work,
Village of Nakusp RFQ 2016-1 Source Protection Plan
RFQ 2016-1 Source Protection Plan The is requesting quotations from qualified professional consultants or firms to undertake a Source Protection Plan for the Village s surface water sources (Halfway Creek,
TOOLING DEFINITIONS, COST AND AUDIT GUIDELINES
INTRODUCTION AND SCOPE This document sets forth the rights of Lear Corporation or its subsidiaries or affiliates (Lear) with regard to the auditing of 1) tooling paid for by Lear and used either (a) by
STANDARD CONTRACT EXECUTION FORMS
THE BIDDING AND CONTRACT PROVISIONS Document Section 00 50 00 - Standard Contract Execution Forms (Standard Contract Set) STANDARD CONTRACT EXECUTION FORMS 1. EXECUTION OF THE AGREEMENT 1.1 Extraneous
CLARK COUNTY DEPARTMENT OF ADMINISTRATIVE SERVICES PURCHASING & CONTRACTS DIVISION
CLARK COUNTY DEPARTMENT OF ADMINISTRATIVE SERVICES PURCHASING & CONTRACTS DIVISION Clark County Government Center 500 Grand Central Parkway, 4th Floor Las Vegas, NV 89106 Phone: (702) 455-2897 Fax: (702)
Request for Qualifications. Owner s Project Manager. Design and Construction of a New School Facility. K~8 Charter School
Request for Qualifications Owner s Project Manager Design and Construction of a New School Facility K~8 Charter School 26 Madeira Avenue New Bedford, MA 02746 REQUEST FOR QUALIFICATIONS (RFQ) Issued: 4/16/2014
CONSTRUCTION & DESIGN AGREEMENTS FOR OWNERS. Presented by ALEXANDER F. FERRINI, III
CONSTRUCTION & DESIGN AGREEMENTS FOR OWNERS Basics for Projects of All Sizes Presented by ALEXANDER F. FERRINI, III Why do I need an agreement? Why do I need an agreement? Why do I need an agreement? Design
24 CFR PART 85 85.36 Procurement. States. Procurement standards.
85.36 Procurement. (a) States. When procuring property and services under a grant, a State will follow the same policies and procedures it uses for procurements from its non-federal funds. The State will
HOUSE BILL No. 2087. By Committee on Insurance 1-26. AN ACT enacting the Kansas professional employer organization licensing
Session of 00 HOUSE BILL No. 0 By Committee on Insurance - 0 0 AN ACT enacting the Kansas professional employer organization licensing act. Be it enacted by the Legislature of the State of Kansas: Section.
1 of 4 DOCUMENTS. NEW JERSEY REGISTER Copyright 2011 by the New Jersey Office of Administrative Law. 43 N.J.R. 1571(a)
Page 1 1 of 4 DOCUMENTS NEW JERSEY REGISTER Copyright 2011 by the New Jersey Office of Administrative Law VOLUME 43, ISSUE 14 ISSUE DATE: JULY 18, 2011 RULE PROPOSALS LABOR AND WORKFORCE DEVELOPMENT THE
Consulting Master Services Agreement
Consulting Master Services Agreement THIS CONSULTING AGREEMENT (this Agreement ), made and entered into this 21st day of June, 2002, by and between PrimeContractor, a StateName EntityType, its successors
Government Contracting in 2015: Balancing Risks to Reap Rewards - Compliance Update
Government Contracting in 2015: Balancing Risks to Reap Rewards - Compliance Update Baker Tilly Beers & Cutler, PLLC, is a wholly-owned subsidiary of Baker Tilly Virchow Krause, LLP. 2015 Baker Tilly Beers
TEXAS DEPARTMENT OF TRANSPORTATION. Fourth Quarter 2007
TEXAS DEPARTMENT OF TRANSPORTATION Introduction This article is a supplement to the Guide to Contract Change Orders or CO Guide (published as a Tips article, 4th Qtr., 2006). Use this article along with
An organization which employs, or is about to employ, any of the above, has a financial or other interest in the firm selected for award.
85.36 Procurement (a) States. When procuring property and services under a grant, a State will follow the same policies and procedures it uses for procurements from its non-federal funds. The State will
ALTA Title Insurance & Settlement Company Best Practices
ALTA Title Insurance & Settlement Company Best Practices N e w C a s t l e T i t l e 7 5 0 N o r t h 3 r d S t r e e t, S u i t e B ( 6 0 8 ) 7 8 3-9 2 6 5 ( 6 0 8 ) 7 8 3-9 2 6 6 5 / 2 2 / 2 0 1 5 0 5/22/15
PASSAIC VALLEY TITLE SERVICE, INC. ALTA Best Practices Manual
PASSAIC VALLEY TITLE SERVICE, INC. ALTA Best Practices Manual July 2015 Page 1 of 7 1. Best Practice: Passaic Valley Title Service, Inc. [PVTS] has established and maintains all of the necessary License(s)
SECTION III. Examples of Exhibits to Support Indirect Cost Rate Proposals
SECTION III Examples of Exhibits to Support Indirect Cost Rate Proposals SECTION III Examples of Exhibits to Support Indirect Cost Rate Proposals Index Exhibits Description Page Numbers Exhibit A Personnel
CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING
CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter will
Executive Office for Administration & Finance. Request for Qualifications For Construction Management Services
Executive Office for Administration & Finance Request for Qualifications For Construction Management Services Massachusetts State Project (Project Number) (Full Project Name and Location), Massachusetts
Chapter 693 1999 EDITION. Plumbers. 693.025 Insurance required of certain providers of low-flow showerheads or faucet aerators
Chapter 693 1999 EDITION Plumbers GENERAL PROVISIONS 693.010 Definitions 693.020 Application 693.025 Insurance required of certain providers of low-flow showerheads or faucet aerators LICENSING 693.030
MONITORING PERFORMANCE
MONITORING PERFORMANCE Monitoring the performance of the contractor is a key function of proper contract administration. The purpose is to ensure that the contractor is performing all duties in accordance
How To Build A House
CONTRACT TO BUILD A HOUSE AT I. Contract Parties Now comes (builder s name) (address) and (buyer s name) (address) to hereby agree to build a house on property located at (common address) and legally described
HADDON TOWNSHIP BOARD OF EDUCATION 500 RHOADS AVENUE WESTMONT, NJ 08108 REQUEST FOR PROPOSAL
HADDON TOWNSHIP BOARD OF EDUCATION 500 RHOADS AVENUE WESTMONT, NJ 08108 REQUEST FOR PROPOSAL A. PURPOSE: The Haddon Township Board of Education is seeking proposals from qualified respondents as follows:
General Terms and Conditions of Purchase
General Terms and Conditions of Purchase Supplement 1 Federal Acquisition Regulation (FAR) Government Contract Provisions 1. When the materials or products furnished are for use in connection with a U.S.
How To Write A Contract With The Highway Patrol
Agreement No. 2 FUNDING AGREEMENT BETWEEN CALIFORNIA HIGHWAY PATROL AND SACRAMENTO TRANSPORTATION AUTHORITY THIS AGREEMENT, is made and entered into this day of, 2010, by and between the California Highway
CHAPTER 260. AN ACT concerning employee leasing companies. BE IT ENACTED by the Senate and General Assembly of the State of New Jersey:
CHAPTER 260 AN ACT concerning employee leasing companies. BE IT ENACTED by the Senate and General Assembly of the State of New Jersey: C.34:8-67 Definitions relative to employee leasing companies. 1. For
SCHEDULES OF CHAPTER 40B MAXIMUM ALLOWABLE PROFIT FROM SALES AND TOTAL CHAPTER 40B COSTS EXAMINATION PROGRAM
7/30/07 SCHEDULES OF CHAPTER 40B MAXIMUM ALLOWABLE PROFIT FROM SALES AND TOTAL CHAPTER 40B COSTS Instructions: EXAMINATION PROGRAM This Model Program lists the major procedures and steps that should be
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) Administration of Project: School District Board + OFCC Project Name Groveport Madison High School Response Deadline 10/17/2014 4:00pm local time Project
Schedule Q (Revised 1/5/15)
Schedule Q (Revised 1/5/15) CONSTRUCTION CONTRACTOR INSURANCE REQUIREMENTS Section 0.0 Introduction of the Owner-Controlled Insurance Program The City of Oakland (City) has implemented an Owner-Controlled
ORACLE SERVICES PROCUREMENT
ORACLE SERVICES PROCUREMENT KEY FEATURES Create contracts for services with complex payment terms Incorporate progress payment schedule into services contracts Track and report progress based on schedule
Seattle Public Schools The Office of Internal Audit
seaonly Seattle Public Schools The Office of Internal Audit Capital Internal Audit Report Issue Date: December 16, 2014 Executive Summary Background In accordance with the Capital Risk Assessment and Audit
Career Path Project Engineer to Project Manager 1
Career Path Project Engineer to Project Manager 1 The Career Path standards listed below are designed to help a Project Engineer at Samet Corporation understand what skills, knowledge and experience they