Plan of Construction Operations (PCO)
|
|
|
- Nathan Preston
- 9 years ago
- Views:
Transcription
1 REQUEST FOR PROPOSAL APPENDIX G Plan of Construction Operations A Taxi A Expansionn CLIENT: TradePort International Corporation, Operators of John C. Munro Hamilton International Airport (YHM) April 2015
2 Plan of Construction Operations (PCO) Airport: Project: Hamilton International Airport A Taxi A Expansion Start Date: 01 June 2015 Finish Date: 14 June 2015 Originator: Name: Ian Rowbotham, P.Eng. Company WSP Canada Inc. Phone FAX [email protected] Project Contacts: Airport Operator: R. Burlakoff Title Facilities Manager Phone FAX [email protected] Other Contact: Ian Rowbotham, P.Eng. Title Consultant Phone FAX [email protected] Page 1 of 6 RDIMS
3 Description of the construction project: In general, the project consists of the widening of the existing Taxilane Alpha from Taxiway Bravo north to Apron II to accommodate B operations. The work consists of two (2) main work areas: 1. Approximately 900m 2 pavement expansion to the east side of the existing Taxilane Alpha into the existing grassed areas bordered by the existing Taxilane Alpha and Apron II, and 2. Approximately 275m 2 pavement expansion to the west side of the existing Taxilane Alpha at the intersection of Taxilane Alpha and Taxiway Bravo. Refer to Drawing CS attached. Stages/phases of the construction & schedules: Stage Construction Start/Finish Construction Activities hours Local Time Monday, 01 June hours Local Time Sunday, 14 June hours Local Time Saturday, 13 June hours Local Time Sunday, 14 June 2015 Civil Works Pavement Removals Common Excavation Subdrain Installation Granular Grading & Compaction Asphalt Paving Pavement Markings Electrical Works Airfield Lighting Reconfiguration Civil Works Pavement Removals Common Excavation Granular Grading & Compaction Asphalt Paving Pavement Markings Electrical Works Airfield Lighting Reconfiguration Page 2 of 6 RDIMS
4 Types & frequency of air traffic: B737 Passenger Aircraft DC-10 Cargo Aircraft General Aviation Aircraft (Jetport, Transport Canada) Disruptions to air traffic: Stage 1: 1. Taxilane Alpha Closed from Stand 11 to Taxiway Bravo 2. Apron II Aircraft Stand 11 push-back exit only 3. Apron II Aircraft Stand 12 Closed. Stage 2: 1. Runway Closed 2. Taxilane Alpha Closed from Stand 12 to Taxiway Bravo 3. Taxiway Bravo Closed 4. Taxiway Delta Closed 5. Apron II Aircraft Stand 12 Closed. Position and height of equipment (relative to runways & taxiways): Maximum Equipment Height = 5m Equipment to be operating in segregated construction zones on Apron II and Taxilane Alpha. All equipment and personnel are to maintain minimum setbacks from runways and taxiways. Work on runway strips and adjacent to taxiways: Construction will take place in segregated construction zones on Apron II and Taxilane Alpha. Refer to Disruptions to Air Traffic above for closures of airfield facilities. Unserviceability markings, barriers and lighting provided: Refer to the attached Drawing CS. Displaced and/or relocated thresholds: Not Applicable Page 3 of 6 RDIMS
5 Declared distance during all phases: DECLARED DISTANCES STAGE 1 RUNWAY TORA 6,010 6,010 10,006 10,006 TODA 6,994 6,994 10,990 10,990 ASDA 6,010 6,010 10,006 10,006 LDA 6,010 6,010 8,398 9,612 DECLARED DISTANCES STAGE 2 RUNWAY TORA CLOSED CLOSED 10,006 10,006 TODA CLOSED CLOSED 10,990 10,990 ASDA CLOSED CLOSED 10,006 10,006 LDA CLOSED CLOSED 8,398 9,612 Access control, vehicle operations and escorts: Access to site as shown on Drawing CS, attached. Construction equipment and personnel are to be escorted at all times by Airside security escorts. AVOP and Restricted Radio Operator Licenses required for all Airside security escorts. Page 4 of 6 RDIMS
6 Communications plan (prior to construction and during construction): Communications Plan (All Stages) Contact information to be completed at the pre-construction meeting. SITE EMERGENCY NUMBER WSP CANADA Inc. ENGINEER HIA AIRPORT FACILITIES MANAGER HIA AIRPORT OPERATIONS TRANSPORT CANADA ATC NAV CANADA CONTRACTOR AIRSIDE SECURITY ESCORTS AIRPORT USERS NOTAMs as per the NOTAM procedure manual: All NOTAM s to be issued by the Airport prior to each construction stage. NOTAM s to be per the Canadian NOTAM Procedures Manual, September , Version Drawing or Blueprints: Refer to Drawing CS attached. Amendments to publications and the Airport Operations Manual This Plan of Construction Operations will be appended to the AOM during construction. No amendments will be required to be made to aeronautical publications or the AOM. Page 5 of 6 RDIMS
7 APPROVAL OF PLAN OF CONSTRUCTION OPERATIONS PROJECT: A, TAXI A EXPANSION AIRPORT NAME: JOHN C. MUNRO HAMILTON INTERNATIONAL AIRPORT AIRPORT OPERATOR and CERTIFICATE HOLDER: JOHN C. MUNRO HAMILTON INTERNATIONAL AIRPORT AIRPORT MANAGER: ROBERT BURLAKOFF, FACILITIES MANAGER CERTIFICATE NUMBER: DATE OF ISSUE: 30 MARCH 2001 I undertake to meet the obligations set out in this plan of construction; and I hereby certify that the information in this plan is complete and accurate and no relevant information has been omitted. Date (Y-M-D) Signature of Airport Operator/Certificate Holder This Plan of Construction Operations Manual/Amendments is approved Date (Y-M-D) for Minister of Transport Canada
8 STAGE I Taxilane Alpha East Expansion: 1. Excavation, subdrain install, airfield lighting modifications, granular subbase, granular base, asphalt paving, pavement markings. 2. Approximately 900 sq.m. pavement expansion. Construction: 1. Construction confined to the area shown. 2. Construction access restricted to the route shown. 3. Active airside pavements adjacent to the construction area and access road to be swept clear of debris by the Contractor on a continuous basis. 4. Construction equipment restricted to 5.0m height within construction area. 5. Contractor to maintain minimum 45m clearance from Taxi B and Taxi D centrelines. Schedule: 1. Approximately 12 working days (Day Time Work from daily). Unserviceable / Closures: 1. Taxilane Alpha CLOSED west of Aircraft Stand 10 to Taxiway Bravo Taxilane Alpha Edgelighting UNSERVICEABLE west of Aircraft Stand Apron II Aircraft Stand 12 CLOSED. 3. Apron II Aircraft Stand 11 available for push-back exit only. Additional Notes: 1. The Airport to advise NavCanada of the current stage of construction and any operational impacts, advisories or NOTAM's. 2. All construction activity to be confined to areas shown. Approved airside escorts with AVOP and Radio License to be provided for radio monitoring services on all airside areas outside of the construction zone. RUNWAY TAXI B PROPOSED TAXILANE ALPHA WEST EXPANSION TAXIWAY STRIP TAXI D 45.0m PROPOSED TAXILANE ALPHA EAST EXPANSION TAXILANE STRIP RUNWAY STRIP TAXI A EDGELIGHTS UNSERVICEABLE SERVICEABLE (27) C/W UNSERVICEABILITY SERVICE ROAD 28m AIRCRAFT STAND NOT AVAILABLE DURING ALL CONSTRUCTION ACTIVITIES CONSTRUCTION WITHIN CONSTRUCTION AREA MONITORED BY APPROVED 36m AIRSIDE ESCORT MINIMUM CLEARANCE (13) C/W UNSERVICEABILITY AIRCRAFT STAND 10 POWER-OUT CENTRELINE AIRCRAFT STAND AVAILABLE FOR PUSH-BACK EXIT ONLY APRON II ACTIVE AIRSIDE PAVEMENTS ADJACENT TO THE CONSTRUCTION AREA AND ACCESS ROAD TO BE SWEPT CLEAR OF DEBRIS BY THE CONTRACTOR ON A CONTINUOUS BASIS. ALL CONSTRUCTION TRAFFIC TO BE ESCORTED FROM GATE X TO CONSTRUCTION AREA BY APPROVED AIRSIDE ESCORT 7 Copyright Reserved THE COPYRIGHTS TO ALL DESIGNS AND DRAWINGS ARE THE PROPERTY OF WSP CANADA INC. REPRODUCTION OR USE FOR OTHER THAN THAT AUTHORIZED BY WSP CANADA INC. IS FORBIDDEN. Notes 1. THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION UNLESS NOTED/REVISED "ISSUED FOR CONSTRUCTION". 2. BASE INFORMATION DERIVED FROM CADD FILES RECEIVED FROM THE CLIENT JULY 2014 AND FROM TOPOGRAPHICAL SURVEY COMPLETED OCTOBER 29, 2014 BY WSP INC. 3. CONSTRUCTION ACCESS SHALL BE BY ACCESS POINTS INDICATED ON SP1. 4. PAVEMENTS BORDERING THE PROJECT LIMITS TO BE KEPT CLEAR OF DEBRIS AND F.O.D. AS INDICATED BY THE CONTRACT ADMINISTRATOR AND WITHIN CONTRACT SPECIFICATIONS. 5. ALL EXISTING STRUCTURES AND SUBSURFACE UTILITIES WITHIN CONSTRUCTION LIMITS TO BE PROTECTED DURING CONSTRUCTION. 6. IT IS THE CONTRACTORS RESPONSIBILITY TO ENSURE ALL UNDERGROUND UTILITY LOCATES HAD BEEN COMPLETED PRIOR TO COMMENCING ANY UNDERGROUND WORKS WITHIN THE CONSTRUCTION LIMITS. 7. ALL DISTURBED AREAS TO BE RESURFACED WITH IMPORTED TOPSOIL AND REVEGETATED WITH SEED AND HYDRAULIC MULCH. 8. CONTRACTOR TO VERIFY EXISTING INVERTS PRIOR TO CONSTRUCTION. 9. ALL REMOVALS TO BE DISPOSED OFF-SITE BY CONTRACTOR UNLESS OTHERWISE INDICATED. 10. ALL UNITS IN METRES UNLESS OTHERWISE NOTED. Legend EXISTING RUNWAY/TAXIWAY STRIP EXISTING EDGE OF PAVEMENT EXISTING LINE MARKING PROPOSED CENTRELINE PROPOSED SUBDRAIN PROPOSED SWALE PROPOSED GRADING LIMIT AIRCRAFT STAND POWER-OUT CENTRELINE AIRCRAFT STAND TAXILANE CLEARANCE EXISTING BUILDING EXISTING CONCRETE PROPOSED PAVEMENT EXPANSION ACTIVE CONSTRUCTION AREA EXISTING CATCHBASIN EXISTING MANHOLE EXISTING AIRFIELD LIGHT EXISTING ELECTRICAL PULLPIT EXISTING AIRFIELD GUIDANCE SIGN PROPOSED CATCHBASIN CONSTRUCTION ACCESS ROUTE TEMPORARY CONSTRUCTION BARRICADE CONSTRUCTION SECURITY ESCORT TAXIWAY STRIP AIC INTERNATIONAL AIR CARGO LOGISTICS FACILITY 3 4 Scale 1: METRES FEET GATE Key Plan ANSI full bleed B (11.00 x Inches) S:\Projects\CYHM Hamilton Apron II Cargojet Operations\CAD\CYHM - Construction Sequencing.dwg April 14, 2015 STAGE II Taxilane Alpha West Expansion: 1. Excavation, subdrain install, airfield lighting modifications, granular subbase, granular base, asphalt paving, pavement markings. 2. Approximately 275 sq.m. taxilane pavement expansion. Construction: 1. Construction confined to the area shown. 2. Construction access restricted to the route shown. 3. Active airside pavements adjacent to the construction area and access road to be swept clear of debris by the Contractor on a continuous basis. 4. All excavation to be backfilled upon Stage completion. Schedule: 1. Approximately 2 working days (24hr Weekend Work from 0700 Saturday to 1900 Sunday). Unserviceable / Closures: 1. Runway CLOSED Runway Edgelighting UNSERVICEABLE Runway Approach Lighting UNSERVICEABLE Runway 06 PAPI UNSERVICEABLE Runway 24 PAPI UNSERVICEABLE. 2. Taxilane Alpha CLOSED west of Aircraft Stand Taxilane Alpha Edgelighting UNSERVICEABLE west of Aircraft Stand Taxiway Bravo CLOSED Taxiway Bravo Edgelighting UNSERVICEABLE. 4. Taxiway Delta CLOSED Taxiway Delta Edgelighting UNSERVICEABLE. 5. Apron II Aircraft Stand 12 CLOSED. Additional Notes: 1. The Airport to advise NavCanada of the current stage of construction and any operational impacts, advisories or NOTAM's. 2. All construction activity to be confined to areas shown. Approved airside escorts with AVOP and Radio License to be provided for radio monitoring services on all airside areas outside of the construction zone. RUNWAY TAXI B PROPOSED TAXILANE ALPHA WEST EXPANSION EXCAVATION TO BE BACKFILLED AT THE END OF EACH WEEKEND SHIFT ALL CONSTRUCTION ACTIVITIES WITHIN CONSTRUCTION AREA MONITORED BY APPROVED AIRSIDE ESCORT TAXIWAY STRIP (5) C/W UNSERVICEABILITY TAXI D TAXIWAY STRIP EDGELIGHTS UNSERVICEABLE SERVICEABLE (4) C/W UNSERVICEABILITY PROPOSED TAXILANE ALPHA EAST EXPANSION TAXILANE STRIP RUNWAY STRIP TAXI A 36m MINIMUM CLEARANCE (12) C/W UNSERVICEABILITY AIC SERVICE ROAD AIRCRAFT STAND 11 POWER-OUT CENTRELINE AIRCRAFT STAND NOT AVAILABLE DURING CONSTRUCTION APRON II ACTIVE AIRSIDE PAVEMENTS ADJACENT TO THE CONSTRUCTION AREA AND ACCESS ROAD TO BE SWEPT CLEAR OF DEBRIS BY THE CONTRACTOR ON A CONTINUOUS BASIS. INTERNATIONAL AIR CARGO LOGISTICS FACILITY 3 ALL CONSTRUCTION TRAFFIC TO BE ESCORTED FROM GATE X TO CONSTRUCTION AREA BY APPROVED AIRSIDE ESCORT REFLECTIVE TAPE (TYP.) STEADY BURNING RED UNSERVICEABILITY LIGHT 0.25m 2.44m NOTES: 1. MAX. SPACING BETWEEN BARRICADES TO BE 3m. 2. BARRICADES TO BE WATER FILLED FOR ANCHORING. 4 BARRICADE TO BE AR 10x96 O V.2 c/w CO1 STEADY BURNING LIGHT OR APPROVED EQUIVALENT LOW PROFILE BARRICADE AND UNSERVICEABILITY LIGHTING NTS GATE 7 KEY PLAN NTS 0 APRIL 15/15 ISSUED FOR TENDER CT ILR No. DATE DESCRIPTION BY APPD REVISION / ISSUE Seals Client: HAMILTON INTERNATIONAL AIRPORT Project: Title: TAXI A EXPANSION CONSTRUCTION STAGING PLAN A Project No. Contract No. CT ILR Design: Checked: JV DRAWING No. CS Drawn:
CHAPTER 8: VISUAL AIDS PROVIDED BY AERODROME MARKINGS, MARKERS, SIGNALS AND SIGNS. Section 8.1: General
CHAPTER 8: VISUAL AIDS PROVIDED BY AERODROME MARKINGS, MARKERS, SIGNALS AND SIGNS Section 8.1: General 8.1.1 Introduction 8.1.1.1 This Chapter specifies the standards for Markers, Markings, Signals and
SECTION 02100 SITE PREPARATION
SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division
The total estimated PFC revenue for the application is $266,900,000. The estimated charge effective date for this application is December 1, 2016.
Public Notice of Application for Authority to Impose and Use Passenger Facility Charges (PFCs) at EWR, LGA, JFK and SWF and Amendment to Approved PFC Applications at EWR, LGA, and JFK The Port Authority
DESCRIPTION OF WORK:
DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works
CHAPTER 7. AIRSPACE 7.1 AFFECTED ENVIRONMENT
CHAPTER 7. AIRSPACE 7.1 AFFECTED ENVIRONMENT 7.1.1 Definition of Resource Airspace management is defined as directing, controlling, and handling flight operations in the volume of air that overlies the
AIRFIELD DRIVING TEST
AIRFIELD DRIVING TEST NAME: COMPANY: DATE: SCORE: 1. Runway incursions are primarily caused by the following errors, except a. Pilot/ground vehicle/controller communication errors b. Lack of airport familiarity
3.1 Aerodrome information to be provided for a certified aerodrome
CHAPTER 3:AERODROME DATA 3.1 Aerodrome information to be provided for a certified aerodrome 3.1.1 Aerodrome chart. An aerodrome chart will contain the following information: a) layout of runways, taxiways
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0
TP 308 IMPACT STUDY TORONTO BILLY BISHOP/TORONTO CITY AIRPORT. for
TP 308 IMPACT STUDY TORONTO BILLY BISHOP/TORONTO CITY AIRPORT for May, 2013 TABLE OF CONTENTS Report TAB 1 Map1: Runway 08-26 Extension TAB 2 Maps 2 & 3: Runway 08-26 Obstacle Assessment TAB 3 Canada Air
FIBER-OPTIC CABLE PLAN CHECK
Engineering Division 201 North Broadway, Escondido, CA 92025 (760) 839-4651, FAX (760) 839-4597 FIBER-OPTIC CABLE PLAN CHECK To: Date: Project: Project No. Address: Check No. Attn: Via: The attached plans
Definition of Tower from the Bradley County Zoning Resolution
Definition of Tower from the Bradley County Zoning Resolution 43. TOWER. Any outdoor structure designed and constructed to support one (1) or more transmitting or receiving devices for telephone, radio
THIS ADDENDUM IS TO BE READ WITH AND CONSTITUTES PART OF THE TENDER DOCUMENTS.
ADDENDUM WSP Project No. 141-21285-00 Addendum No.: 2 Date: May 11, 2015 Contract No.: 13-006 Owner: Consultant: Number of Pages Project Name Hamilton International Airport WSP Canada Inc. 6 (including
EGTR ELSTREE EGTR AD 2.1 AERODROME LOCATION INDICATOR AND NAME EGTR AD 2.2 AERODROME GEOGRAPHICAL AND ADMINISTRATIVE DATA
UNITED KINGDOM AIP AD 2.EGTR-1 8 Jan 2015 EGTR ELSTREE EGTR AD 2.1 AERODROME LOCATION INDICATOR AND NAME EGTR ELSTREE EGTR AD 2.2 AERODROME GEOGRAPHICAL AND ADMINISTRATIVE DATA 1 ARP coordinates and site
Strategic Business Plan
Williams Gateway Airport Authority Strategic Business Plan Fiscal Years 2011-2015 Adopted May 24, 2010 by the Phoenix-Mesa Gateway Airport Authority Board of Directors Page 2 TABLE OF CONTENTS Purpose...4
Airfield Pavement Rehabilitation Planning Choosing the right fix. Rob McLure, M.Eng., P.Eng. Senior Associate Hatch Mott MacDonald
Airfield Pavement Rehabilitation Planning Choosing the right fix Rob McLure, M.Eng., P.Eng. Senior Associate Hatch Mott MacDonald Presentation Objective ¾ Review the pavement rehabilitation strategy development
SECTION 4Aggegate Subbase
The contractor shall moist-cure the completed Lime Treated Subbase for a minimum of days before allowing any traffic on the compacted surface. The contractor shall be responsible for repairing any damages
ROAD OPENING LICENCE APPLICATION FORM PLEASE READ ALL PARTS AND SECTIONS OF THIS FORM IN ADVANCE OF COMPLETING THE APPLICATION
ROAD OPENING LICENCE APPLICATION FORM PLEASE READ ALL PARTS AND SECTIONS OF THIS FORM IN ADVANCE OF COMPLETING THE APPLICATION N.B. WORK MUST NOT COMMENCE UNTIL LICENCE IS ISSUED June 2014 Roads Section
WHICH AIR TRAFFIC CONTROLLER TO CONTACT
WHICH AIR TRAFFIC CONTROLLER TO CONTACT 1. Introduction This article is written in order to explain to all beginners in the IVAO network the basics for any pilot to contact the correct air traffic controller.
SECTION 31 20 00 EARTH MOVING
SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to
1.0 INDEX TO SHEETS URGENT STORM DAMAGE REPAIR AVON PARK AIR FORCE RANGE LOCATION MAP LEGEND LOCATION MAP
5 INDEX TO SHEETS. NOTES AND TYPICAL SECTIONS. H. R. SMITH RD.CULVERT.3 0/5 END BARRIER ACCESS ROAD REPAIR. KISSIMMEE RD. AT MORGAN HOLE CR. ROAD REPAIR.5 RANGE INFRASTRUCTURE REPAIR N 0 000' 3 0,000'
CHAPTER 10 - PERMIT PROCEDURES AND BONDING REQUIREMENTS
CHAPTER 10 - PERMIT PROCEDURES AND BONDING REQUIREMENTS 10.1 APPLICATION REQUIREMENTS AND PROCEDURES 10.1.1 A permit shall be required for any construction or installation within the public right-of-way
Alternatives RIAC 5.1 INTRODUCTION 5.2 WORKING ASSUMPTIONS
CHAPTER 5 Runway/Taxiway Alternatives 5.1 INTRODUCTION This chapter presents the development and analysis of different layouts and configurations of both Runway 10-28 and its related taxiways. A primary
Permit No. Permit Fee: $295.00. Permit Expires (D+90 days): Business Name: Applicants Name: Telephone Number: E-mail Address:
City of Woodland Park Internet Service Provider (IPS) Permit for Installation of Telecommunication Infrastructure within City Owned Rights-of-Way (up to five locations per single permit) Permit No. Permit
New Road 11.0m Asphalt 23m ROW
New Road 11.0m Asphalt 23m ROW Granular A - 150 mm sq. m. $5.35 $69.53 Granular B - 300 mm sq. m. $7.35 $95.54 Concrete Curb and Gutter m. $44.67 $89.34 HL3 Asphalt - 40 mm sq. m. $7.66 $84.23 HL 4 or
EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT. BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309
EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309 FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT FOUR 1.0 SCOPE OF
Los Angeles International Airport North Airfield Assessment
Appendix H-3 LAX SPECIFIC PLAN AMENDMENT STUDY REPORT Los Angeles International Airport North Airfield Assessment May 2007 Prepared for: Los Angeles World Airports One World Way Los Angeles, California
LRSM AD 2.1 AERODROME LOCATION INDICATOR AND NAME LRSM - SATU MARE / Satu Mare
AIP AD 2.121 25 JUL 2013 LRSM AD 2.1 AERODROME LOCATION INDICATOR AND NAME LRSM SATU MARE / Satu Mare LRSM AD 2.2 AERODROME GEOGRAPHICAL AND ADMINISTRATIVE DATA 1 ARP coordinates and site at AD 474212N
SECTION 5 DRAFTING STANDARDS
SECTION 5 DRAFTING STANDARDS 1 SECTION FIVE TABLE OF CONTENTS Description Page TABLE OF CONTENTS... 5-2 GENERAL... 5-3 DRAFTING STANDARDS... 5-5 DRAFTING MINIMUM REQUIREMENTS HANDOUT... 5-8 2 GENERAL 1.
Airport Safety and Construction Management Under The FAA
U.S. Department of Transportation Federal Aviation Administration Advisory Circular Subject: Quality Management for Federally Funded Airport Construction Projects Date: DRAFT Initiated by: AAS-100 AC No.:
VEHICLE CROSSOVER INFORMATION PACK
VEHICLE CROSSOVER INFORMATION PACK CONTENTS Introduction Section A Section B Section C Section D Section E Criteria for approving a vehicle crossover application (Diagrams to demonstrate measurement criteria)
CHAPTER 17: STORM SEWER STANDARDS. 17.00 Introduction. 17.01 Administration. 17.02 Standards 17.1
CHAPTER 17: STORM SEWER STANDARDS 17.00 Introduction 17.01 Administration 17.02 Standards 17.1 17.00 INTRODUCTION The purpose of this chapter is to provide guidance for the design and construction of storm
SECTION 02400 - STORM DRAIN SYSTEM
SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And
AIP AD 2 - VAKJ 1 INDIA 01JUNE 2009
AIP AD 2 - VAKJ 1 INDIA 01JUNE 2009 AD 2. AERODROMES VAKJ 2.1 AERODROME LOCATION INDICATOR AND NAME VAKJ- KHAJURAHO/ DOMESTIC VAKJ AD 2.2 AERODROME GEOGRAPHICAL AND ADMINISTRATIVE DATA 1. ARP coordinates
ITS specification Jointing chambers and pull pits (ITS-02-02)
ITS specification Jointing chambers and pull pits (ITS-02-02) NZ Transport Agency Effective from September 2011 Copyright information This publication is copyright NZ Transport Agency (NZTA). Material
www.faa.gov/runwaysafety
www.faa.gov/runwaysafety A A Pilot s Pilot s Guide to to Safe Safe Surface Operations Introduction Traffic levels rise. Airports expand. And you, the pilot, are expected to understand how to safely taxi
Unit Price Averages Reports
Unit Price Averages Reports 12/7/2015 UNIT PRICE AVERAGES REPORT Disclaimer The information provided in the following Unit Price Averages Report is only for the use of Alberta Infrastructure & Transportation
FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation
644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING
Safety Regulation Group CAP 168. Licensing of Aerodromes. www.caa.co.uk
Safety Regulation Group CAP 168 www.caa.co.uk Safety Regulation Group CAP 168 April 2011 Civil Aviation Authority 2011 All rights reserved. Copies of this publication may be reproduced for personal use,
Guidelines for Fiber Optic Cable Permits
Guidelines for Fiber Optic Cable Permits NOVA District (Fairfax/Arlington) Permits www.virginiadot.org/business/fairfax-permits-main.asp Email: [email protected] 14685 Avion Parkway
SECTION 02221 SELECTIVE DEMOLITION
SECTION 02221 PART 1 -GENERAL 1.01 DESCRIPTION This section includes all material, labor, machinery and supervision required to demolish and remove the following items where applicable and as noted on
FY08 SEWER POINT REPAIRS BID TABULATION
6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "
USE OF A DIGITAL SURVEY VEHICLE FOR PAVEMENT CONDITION SURVEYS AT AIRPORTS. Paul W. Wilke, P.E. Applied Research Associates, Inc.
USE OF A DIGITAL SURVEY VEHICLE FOR PAVEMENT CONDITION SURVEYS AT AIRPORTS Paul W. Wilke, P.E. Applied Research Associates, Inc. August 11, 2014 Words: 3,280 Figures: 3 Tables: 0 Photographs: 3 ABSTRACT
APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT
APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI 48473 810-635-4464 Fee Received: $ Date: / / Receipt No: Demolition Permit (including Right of
Developer s/consultants Field Services Guidelines
Developer s/consultants Field Services Guidelines 2007 Engineering and Works Department DEVELOPER S/CONSULTANT S FIELD SERVICES GUIDELINES Fourth Electronic Edition February 2007 STATEMENT OF COMPLETION
ENGINEERING DESIGN GUIDELINES. for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS
ENGINEERING DESIGN GUIDELINES for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS City of Birmingham Department of Planning, Engineering and Permits Engineering Division Office of the City Engineer 2008 TABLE
CONSTRUCTION PERMIT REQUIREMENTS
CONSTRUCTION PERMIT REQUIREMENTS Any work to be done in the City right-of-way (ROW), in a utility easement, and certain work on private property, requires an Engineering Inspection Permit from the Department
Description of Airport Charges. Swedavia AB 2015. Appendix 3 to Conditions of Services, Swedavia AB
Description of Airport Charges Swedavia AB 2015 Appendix 3 to Conditions of Services, Swedavia AB Contents 1 Swedavias Charges... 3 2 Aircraft Related Charges... 4 2.1 Take-Off Charge... 4 2.2 Emission
It was my assignment to physically inspect the 8 trees on site near the proposed construction,
July 11, 2013 Tariton Properties 2555 Park Blvd Palo Alto, CA 94306 Re: Tree Survey To Whom It May Concern: Assignment It was my assignment to physically inspect the 8 trees on site near the proposed construction,
VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL
VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL I/We hereby agree to furnish to the Village of Lombard all necessary materials, equipment, and labor, to complete the North Industrial
AIRPORT MASTER PLAN 2012
2012 BILLY BISHOP TORONTO CITY AIRPORT 1300 Yonge St. Suite 801 Toronto, ON M4T 1X3 Tel: 647 789-3550 Fax: 647 789-3560 www.wspgroup.com Project No.10517 June 2012 Updated July 2014 EXECUTIVE SUMMARY Billy
DIVISION I GENERAL REQUIREMENTS SECTION 01005
Subdivision Requirements Manual Page 1 of 13 PART I - GENERAL 1.1 Description.1 The requirements of this specification shall apply to the contract as a whole and pertain to all of the work as specified
AAGSC Traffic Management Plan Template
AAGSC Traffic Management Plan Template Table of Contents 1.0 Overview Page 2.0 Objectives of the Traffic Management Plan 3.0 Traffic Management Safety Principals 4.0 Document Control 5.0 Pedestrian Management
Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.
Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer
DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES. Run-off Analysis Methods
DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES Run-off Analysis Methods This document sets forth the minimum design, technical criteria and specifications for the
SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST
This checklist may be used by applicants for encroachment permits, and contractors in development of Site Specific Best Management Practice (SSBMP) Plans or Storm Water Pollution Prevention Plans (SWPPP)
SUBDIVISION ROAD CONSTRUCTION AND INSPECTION PROCEDURES
BOARD OF COUNTY COMMISSIONERS ST. MARY S COUNTY LEONARDTOWN, MARYLAND SUBDIVISION ROAD CONSTRUCTION AND INSPECTION PROCEDURES APRIL, 1991 AMENDED: JUNE, 2002 DEPARTMENT OF PUBLIC WORKS & TRANSPORTATION
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0
Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department
Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth
CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS
December 2014 CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Construction Specifications...
Salt Lake City International Airport CONSTRUCTION SAFETY AND SECURITY COMPLIANCE MANUAL
Salt Lake City International Airport CONSTRUCTION SAFETY AND SECURITY COMPLIANCE MANUAL July 2014 Refer to the Salt Lake City Department of Airport s website for the most current edition of this manual.
SITE-SPECIFIC BEST MANAGEMENT PRACTICES (BMP) PLAN REVIEW CHECKLIST
This checklist may be used by applicants for encroachment permits, and contractors in development of Site- Specific BMP Plans for projects. plan reviewers will use this checklist to review the Site-Specific
SECTION 02200 SUPPORT OF EXCAVATION
SECTION 02200 PART 1 GENERAL 1.01 DESCRIPTION A. Section including specifications for design and installation of excavation support. B. Section also includes specifications for excavation support systems
Los Angeles World Airports
M E M O R A N D U M Los Angeles World Airports Date: Memo To: From: Subject: LAX Station Managers Raymond Jack, Airport Manager II LAX Operations Division Weekly Coordinated Construction Activity Runway
Appendix D GENERAL AVIATION AIRPORTS GROUND VEHICLE OPERATIONS TRAINING PROGRAM
Appendix D GENERAL AVIATION AIRPORTS GROUND VEHICLE OPERATIONS TRAINING PROGRAM Section 1. Airport Driving Rules and Regulations I. Applicability. This training program applies to all users of, and persons
Greater Toronto Airports Authority Airport Construction Code
Greater Toronto Airports Authority Airport Construction Code Toronto Pearson International Airport GTAA Airport Construction Code Current Edition 2006 Third Edition 2002 Second Edition 2000 First Edition
Visual Aids Handbook CAP 637. A compendium of Visual Aids intended for the guidance of Pilots and Personnel engaged in the handling of aircraft
A compendium of Visual Aids intended for the guidance of Pilots and Personnel engaged in the handling of aircraft www.caa.co.uk A compendium of Visual Aids intended for the guidance of Pilots and Personnel
Draft Construction Work Plan Non-Public Properties Newhall Street Neighborhood Site Hamden, Connecticut
Draft Construction Work Plan Non-Public Properties Newhall Street Neighborhood Site Hamden, Connecticut Revision 0 Prepared for: Olin Corporation Cleveland, Tennessee February 2009 TABLE OF CONTENTS INTRODUCTION...
AVIATION INVESTIGATION REPORT A06F0014 MISALIGNED TAKE-OFF
AVIATION INVESTIGATION REPORT A06F0014 MISALIGNED TAKE-OFF AIR CANADA AIRBUS A319-114 C-FYKR LAS VEGAS, NEVADA 30 JANUARY 2006 The Transportation Safety Board of Canada (TSB) investigated this occurrence
COASTAL DEVELOPMENT PERMIT
COASTAL DEVELOPMENT PERMIT ZONE CODE SECTIONS 12.20.2 prior to LCP certification. The MASTER LAND USE APPLICATION INSTRUCTION SHEET 500' RADIUS should also be followed, except that a 100-foot radius map
RISK MANAGEMENT PLAN E6-608 SUNSHINE COAST AIRPORT EXPANSION PROJECT TABLES CONTENTS. 6.1 Introduction...609 6.1.1 Hazard and risk...
E6 Summary & Management Framework RISK MANAGEMENT PLAN CONTENTS TABLES 6.1 Introduction...609 6.1.1 Hazard and risk...609 6.2 assessment...609 6.2.1 Approach...609 6.2.2 register...609 6.2.3 Change in
FLORIDA DEPARTMENT OF TRANSPORTATION GUIDELINE FOR
FLORIDA DEPARTMENT OF TRANSPORTATION GUIDELINE FOR ESTABLISHING CONSTRUCTION CONTRACT DURATION July 2010 DISCLAIMER: The following documentation as a whole was derived from Federal Highway Administration
Construction Management Statement. Introduction. Contents
Construction Management Statement Project Name Dee Point Primary School Introduction On all Morgan Sindall projects, the safety and welfare of all is of paramount importance. This document concentrates
Sample Punch List. Garth Ruffner Landscape Architect (916) 797-2576. Page 1 of 5
Sample Punch List This document is provided primarily for landscape contractors who have not previously worked with Garth and would like to know what issues are frequently addressed by site observation
PIPELINE ROUTING PERMIT. For A NATURAL GAS PIPELINE DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY
PIPELINE ROUTING PERMIT For A NATURAL GAS PIPELINE IN DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY PUC DOCKET No. G002/GP-05-1706 In accordance with the requirements
Permeable Pavement Construction Guide
Permeable Pavement Construction Guide Permeable pavement at Olympic Park, Waitakere Final Construction result What are permeable pavements? Permeable pavements are hard surface paving systems that reduce
Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS
Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS TABLE OF CONTENTS I. RULES AND REGULATIONS A. TABLE OF CONTENTS... 2 B. TERMS AND DEFINITIONS... 3 C. DEVELOPER S/CONTRACTOR S RESPONSIBILITIES...
Form C: Application for Construction Insurance
Form C: Application for Construction Insurance Broker Information: Broker: BFL CANADA Insurance Services Inc. Contact: Address: 200, 1177 West Hastings Street, Vancouver, BC, V6E 2K3 Phone Number: 604-669-9600
CHICO MUNICIPAL AIRPORT MOVEMENT AREA DRIVER TRAINING PROGRAM
CHICO MUNICIPAL AIRPORT MOVEMENT AREA DRIVER TRAINING PROGRAM Introduction In compliance with Federal Aviation Regulations (FAR) Part 139.329, and to provide for a safe operating environment for tenants,
SECTION 1 GENERAL REQUIREMENTS
Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,
Close-Out Documents... 9
Water and Sanitary Sewer Service Connection Requirements Service Connection Requirements... 1 Application for Services... 2 Water Meter Application... 2 Wet Tap/Tie-in Connection Requirements... 3 Meter
ESER was established in 1968 under the name of Tekser Technical Services Inc. Following a change in its name in 1985, it has served its customers under the name of ESER Consulting Engineering Inc. ESER
SWIMMING POOL, SPA, & HOT TUB GUIDELINES
SWIMMING POOL, SPA, & HOT TUB GUIDELINES Pool permit cost is based on the total value of the project. See Permit Fee Schedule Table 1A. A. Adopted construction codes and installation requirements 1. 2015
W. REYNOLDS ST. (SR 574) SEWER LINE REPLACEMENT BID NO. 10-91345-003 Addendum 3a
PROPOSAL AND BID FORM W. REYNOLDS ST. (SR 574) SEWER LINE REPLACEMENT Pursuant to and in compliance with your Invitation to Bid dated February 9, 2010, the Instructions to Bidders, Special Conditions and
IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION
IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION 199 9.1(479,479B) General information. 9.1(1) Authority. The standards contained herein
Sixteenth Meeting of the Cross Polar Trans East Air Traffic Management Providers Work Group (CPWG/16) (Ottawa, Canada 3-6 December 2013)
CPWG/16 IP/19 03/12/13 Sixteenth Meeting of the Cross Polar Trans East Air Traffic Management Providers Work Group (CPWG/16) Agenda Item 5: Status on CPWG/15 Actions (Ottawa, Canada 3-6 December 2013)
Minimum Safety Requirements for temporary Helicopter Landing Areas.
GOVERNMENT OF INDIA OFFICE OF DIRECTOR GENERAL OF CIVIL AVIATION TECHNICAL CENTRE, OPP SAFDARJANG AIRPORT, NEW DELHI CIVIL AVIATION REQUIREMENTS SECTION 4 - AERODROME STANDARDS & AIR TRAFFIC SERVICES SERIES
CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT
Page 1 CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT CIVIC CENTRE 2141 MAJOR MACKENZIE DRIVE MAPLE ONTARIO L6A 1T1 905-832-2281 Page 2 SECTION 1 - GENERAL OBJECTIVES To provide
How To Protect A Swimming Pool
County of Gloucester Codes Compliance Building Department Building Three P. O. Box 329 Gloucester, Virginia 23061 Building Code Guidelines Residential Swimming Pools & Spas KEEP YOUR POOL SAFE CODE REQUIREMENTS
ABBVIE C-TPAT SUPPLY CHAIN SECURITY QUESTIONNAIRE
AbbVie is a participant in the U.S. Customs supply chain security program called the Customs-Trade Partnership Against Terrorism (C-TPAT). Participation in C-TPAT requires AbbVie to ensure that its overseas
Aircraft Noise Control at London Luton Airport. August 2015
Aircraft Noise Control at London Luton Airport August 2015 Aircraft Noise Control at London Luton Airport Foreword London Luton Airport (LLA) continues to place aircraft noise high on its agenda. We recognise
Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile
Chapter 3 CULVERTS Description A culvert is a closed conduit used to convey water from one area to another, usually from one side of a road to the other side. Importance to Maintenance & Water Quality