Asbestos Abatement Management Program. Facilities Operations and Development Environmental Health & Safety
|
|
|
- Patrick Walters
- 9 years ago
- Views:
Transcription
1 Asbestos Abatement Management Program Facilities Operations and Development Environmental Health & Safety November 7, 2012
2 INTRODUCTIONS David Kos (EHS) Director of Environmental Affairs David Kehl (EHS) Environmental Safety Officer Ryan Malott (EHS/FDC) Hazardous Material Coordinator
3 Liability Issues Notification Performance Expectations EHS / FDC Asbestos Personnel Contractor and Consultant Roles / Responsibilities Contractor Discussion PURPOSE
4 OSU LIABILITY Renovation / Demolition Projects Sub-Contractors Departmental Funded Projects Project Managers / User Groups Regulatory Inspections
5 HAZARDOUS MATERIALS ASSESSMENTS Contractor Self-Sampling Not acceptable for OSU Work Acceptable for Contractor s Use Licensed Third Party AHES NVLAP Accredited Lab
6 NOTIFICATIONS OSU / ODH / EPA 5 Day Prior for OSU Project Agreement Required for all OSU Work
7
8
9
10
11
12 SUBMITTALS Annual Submittals Contractor License BWC Certificate Liability Insurance Pre-abatement Submittals / Documents Notifications (OSU / ODH / EPA) Project Agreement Supervisor and Worker Submittals Work Plan
13 OSU EHS / FDC STAFF ROLES EHS and FDC Roles and Responsibilities EHS Personnel (David Kos, David Kehl) Roles Responsibilities EHS Website: FDC Personnel (Ryan Malott) Roles Responsibilities FDC Website: Design Standards: OSU Designated Asbestos Coordinators
14 PERFORMANCE EXPECTATIONS Work Quality / University Expectations Full Containment vs. Regulated Area Signage Three Stage Decontamination Chamber Personal Protective Equipment HEPA Filtered Air Filtration Devices (Exterior) Personal Air Monitoring (OSHA) Adequately Wet / Visible Emissions Final Cleaning / Supervisor Visual Inspection Visible Deposits Encapsulation Disposal
15 FULL CONTAINMENT / REGULATED AREA 6-mil Polyethylene (Dark / Clear) Critical Barriers / Primary Barriers View Port Window Adhesive Material AFD Exhaust to Exterior
16 THREE-STAGE DECONTAMINATION & MANOMETERS Clean Room / Shower / Dirty Room Hot and Cold Water 5 Micron Filter Pump Manometer Minimum: inches of H20
17 ENVIRONMENTAL MONITORING Calibration of Pumps Locations of Sampling Angle of Sample Collection 45 Degrees Height of Sample Collection Breathing Zone
18 ENVIRONMENTAL CONCERNS ACM Floor Mastic Post Abatement ACM Floor Mastic Post Abatement
19 ENVIRONMENTAL CONCERNS ACM Floor Mastic Flooring Cracks ACM Floor Mastic Floor Infiltration
20 ENVIRONMENTAL CONCERNS ACM Mastic from Above Floor on Ceiling
21 ENVIRONMENTAL CONCERNS ACM Floor Tile Removal No Containment ACM Floor Tile Removal No Full Containment
22 ENVIRONMENTAL CONCERNS ACM TSI Debris Remains in Soil Post Abatement ACM Drywall Debris Remains in Junction Box - Post Abatement
23 ENVIRONMENTAL CONCERNS ACM Fireproofing Remain Above Beam Post Abatement ACM Fireproofing Remain Above Block Wall Post Abatement
24 ENVIRONMENTAL CONCERNS ACM Transite Fume Hood Sig. Damaged ACM Transite Cabinet Liner Sig. Damaged
25 ENVIRONMENTAL CONCERNS ACM Vibration Damper Improper Removal ACM Vibration Damper Improper Removal
26 ENVIRONMENTAL CONCERNS ACM Residual Insulation / Lockdown ACM Residual Insulation / Lockdown
27 PROJECT OVERSIGHT AND CLEARANCE Project Oversight Third Party Environmental Consultants Roles and Responsibilities Part-time Oversight vs. Full Time Part-time Oversight = Low Risk Projects, Non-friable ACM Full-time Oversight = Higher Risk Projects, Friable ACM Clearance Supervisor Visual Clearance Inspections Third Party Visual Clearance Inspections Final PCM / TEM Air Clearance Sampling Laboratory Accreditation Laboratory Analysis Turn-Around Time
28 CLOSEOUTS Closeout Documents Forty-five (45) Business Days After Project Completion ODH / EPA Notifications (Including All Revisions) Contractor Daily Logs Personal & Environmental Air Monitoring Data Employee Submittals MSDS / SDS (Safety Data Sheets) Waste Manifests / Signed Landfill Receipts
29 CONTRACTOR RESPONSIBILITIES OSU Building Design Standards General Requirements Submit Asbestos Abatement Plan Supervisor Present Outside Work Area Emergency Entries Area Demarcated / Identified Routes Egress
30 ENVIRONMENTAL CONSULTANTS University Compliance Agent Hazardous Materials Assessments Specifications / Drawings Part-time / Full-time Oversight Visual Clearance / Final Air Testing Closeouts
31 CONTRACTOR DISCUSSION Concerns Expectations Questions / Answers
Characteristics/Applications
Facilities Operations and Development Environmental Health & Safety 1314 Kinnear Rd. Columbus, Ohio 43212 Phone (614) 292-1284 Fax (614) 292-6404 http://fod.osu.edu The Ohio State University Asbestos Management
North Carolina State University. Asbestos Management Plan
North Carolina State University 1.0 Introduction Purpose The purpose of this plan is to establish the polices and procedures to be used at North Carolina State University (NCSU) in the management of building
SECTION 02 8213 ASBESTOS ABATEMENT
PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 specification sections shall apply to work of this section.
ASBESTOS MANAGEMENT PROGRAM
ASBESTOS MANAGEMENT PROGRAM Prepared By: Triumvirate Environmental Program Approval Developed: August 2011 Updated: June 2015 Associate Vice President of Public Safety & Administrative Services Date Associate
EXHIBIT A SCOPE OF SERVICES
EXHIBIT A SCOPE OF SERVICES 1.0 INTRODUCTION Asbestos consulting services are required for Item/Segment No. 227775-1, SR-7 (US 441) from Fillmore Street to South of Stirling Road, Hollywood, Broward County,
Questions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project
Questions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project The Watergate Community is currently in the process with the fire suppression and interior renovations
ASBESTOS MANAGEMENT PROGRAM
ASBESTOS MANAGEMENT PROGRAM September 2015 Asbestos Management Program Table of Contents I. Purpose II. III. IV. Definitions Identification of Asbestos Asbestos Sampling V. Notification and Labeling VI.
SPECIFICATION DIVISION 2 NUMBER SECTION DESCRIPTION DIVISION 02 EXISTING CONDITIONS SECTION 028214 ASBESTOS REMEDIATION FLOOR TILE AND MASTIC
ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION
UNOFFICIAL. 1. Owner: Delaware Department of Transportation (DelDOT) WEBSITE
SECTION 01013 - SUMMARY OF THE WORK - ASBESTOS ABATEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
Asbestos Procedures. Asbestos Products
Asbestos Procedures Asbestos Products Where is asbestos known to be located on The Evergreen State College? Please see Appendix A for a list of known asbestos containing materials located on the Olympia
LEGAL REVIEW & UPDATE
LEGAL REVIEW & UPDATE There are lots of laws and regulations designed to protect workers, the general public, and the environment. However, not everyone follows the laws. Many people deliberately break
ASBESTOS BUILDING INSPECTION REPORT. for the. City of East Lansing Waste Water Treatment Plant East Lansing, Michigan 48823.
ASBESTOS BUILDING INSPECTION REPORT for the City of East Lansing Waste Water Treatment Plant East Lansing, Michigan 48823 at the City of East Lansing Waste Water Treatment Plant and Woodingham Pump Station
2. 40 CFR Part 763; The Asbestos Hazard Emergency Response Act (AHERA), EPA Worker Protection Rule, February 25, 1987.
Penn State University Environmental Health and Safety Asbestos Management Program I. Introduction Over the past several decades the hazards of asbestos exposure have become well known. With this influx
The Richard Stockton University ASBESTOS MANAGEMENT PLAN
The Richard Stockton University ASBESTOS MANAGEMENT PLAN January 2015 Asbestos Management Plan Table of Contents I. Introduction II. III. IV. Definitions Identification of Asbestos Notification and Labeling
Asbestos Abatement Work Plan for the Carter Carburetor Superfund Site
for the Prepared for: ACF Industries LLC 101 Clark Street St. Charles, Missouri 63301 Prepared by: AMEC Environment & Infrastructure, Inc. 15933 Clayton Road, Suite 215 Ballwin, Missouri 63011 Project
OGS LIMITED ASBESTOS & LEAD SURVEY REPORT
our people and our passion in every project OGS LIMITED ASBESTOS & LEAD SURVEY REPORT Building 44 Willard Drug Treatment Center 7116 County Road 132 Willard, NY Prepared for: NYSOGS 33 rd Floor, Corning
ASBESTOS MANAGEMENT PLAN
ASBESTOS MANAGEMENT PLAN SAN JOSE STATE UNIVERSITY Environmental Health & Occupational Safety Asbestos Management Plan 1.0 Introduction 2.0 Policy 3.0 Responsibilities 4.0 Contract Administration 5.0 In-House
Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material
Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material Revised November 21, 2013 Application Code of Practice Where asbestos is present or believed to be present in a workplace
Standards for Asbestos Abatement
19a-332a-1. Definitions Standards for Asbestos Abatement 19a-332a-1. Definitions The following definitions shall apply for the purpose of Section 19a-332a-1 to Section 19a-332a- 16 inclusive. (a) "Adequately
UNVERSITY HIGH SCHOOL U0018 65-108-9010-0001 500 W. Gregory St. Normal, IL 61761. School Asbestos Management Plan. Supplemental.
UNVERSITY HIGH SCHOOL U0018 65-108-9010-0001 500 W. Gregory St. Normal, IL 61761 School Asbestos Management Plan Supplemental Prepared By: David Martin Management Planner Environmental Health and Safety
NDSU TABLE OF CONTENTS
NDSU TABLE OF CONTENTS 1.0 INTRODUCTION 2.0 DEFINITIONS AND DESCRIPTIONS 3.0 OPERATIONS AND MAINTENANCE PROCEDURES FOR ACM 4.0 FIBER RELEASE EPISODES 5.0 DEMOLITION INFORMATION 6.0 REMARKS 1.0 INTRODUCTION
Asbestos Inspection Project Procedure
EOSMS 402 Date: 01/13/2014 Page 1 of 6 1) Purpose This document is intended to specify the scope of services required of Asbestos Contractor in asbestos inspection projects at Kennesaw State University
Asbestos Containing Material MANAGEMENT PLAN
Asbestos Containing Material MANAGEMENT PLAN Introduction Extensive research has shown exposure to asbestos containing material (ACM) when it becomes airborne (commonly referred to as friable) poses a
University of Pittsburgh Safety Manual. EH&S Guideline Number: 01-007 ASBESTOS
Page 1 of 5 The inhalation of asbestos fibers in excess amounts can lead to chronic lung disease. Our knowledge of these health effects comes from studies of workers exposed routinely to high concentrations
ASBESTOS IN ROOFING SYSTEMS WORK PRACTICES AND DISPOSAL IN ASSOCIATION WITH ROOFING PROJECTS
ASBESTOS IN ROOFING SYSTEMS WORK PRACTICES AND DISPOSAL IN ASSOCIATION WITH ROOFING PROJECTS 1.0 GENERAL 1.1 SUMMARY A. The following procedures apply to the project manual and drawings for asbestos in
Asbestos abatement Sampling & Analysis. Abatement Project Supervision
Asbestos abatement Sampling & Analysis Abatement Project Supervision TOPICS FOR DISCUSSION Air Sampling PERSONNEL AREA Analysis PCM Analysis TEM Analysis TYPES OF SAMPLING Two types of air sampling are
ASBESTOS MANAGEMENT INTRODUCTION
SECTION: II. General Hygiene/ Safety Chapter: 7. Asbestos Management Revision Date: 12/05/2013 Review Date: ASBESTOS MANAGEMENT INTRODUCTION PURPOSE This policy has been developed to ensure that hazardous
ASBESTOS OPERATIONS AND MAINTENANCE PLAN
UNIVERSITY OF FLORIDA ASBESTOS OPERATIONS AND MAINTENANCE PLAN Administered by: Environmental Health and Safety Building 179 PO Box 112190 Gainesville, Florida 32611 Introduction The following document
Approved by: UBC ACT Committee
The University of British Columbia Asbestos Safety Policy Prepared by: Russell R. English Policy Approved by: UBC ACT Committee Issue Date: April 1, 2004 Replaces: March, 1989 I-B-05 1.0 Policy: This policy
Asbestos Management Plan EC 45 Page 1
Name: Asbestos and ACBM (asbestos containing building material) Management Plan Areas Affected: All buildings that contain asbestos and ACBM on campus Effective Date: 1/1/09 Reviewed/Revised: 12/15/12
SECTION 16 ASBESTOS MANAGEMENT
SECTION 16 ASBESTOS MANAGEMENT 16.1 Asbestos Management Procedure 16.2 Asbestos O&M Procedure Reviewed: October 2008 Revised: February 2003 Date Accepted: April 2002 Draft Date: December 2001 16.1 ASBESTOS
DIVISION 248 ASBESTOS REQUIREMENTS. Asbestos Emission Standards and Procedural Requirements 340-248-0250. Asbestos Abatement Project Exemptions
DIVISION 248 ASBESTOS REQUIREMENTS Asbestos Emission Standards and Procedural Requirements 340-248-0250 Asbestos Abatement Project Exemptions (1) Any person who conducts or provides for the conduct of
Washington University Asbestos Operations and Maintenance Plan
1. Purpose Washington University Asbestos Operations and Maintenance Plan 1.1. The purpose of this Asbestos Operations and Maintenance (O&M) Plan is to minimize the potential for exposure to airborne asbestos
DESERT RESEARCH INSTITUTE MOLD ASSESSMENT AND REMEDIATEION PROCEDURE
1.0 Introduction DESERT RESEARCH INSTITUTE This Desert Research Institute (DRI) Mold Assessment and Remediation Procedure was established to assure that consistent and uniform information is provided to
Asbestos Management Program (EHS Program Manager 7.5)
Asbestos Management Program (EHS Program Manager 7.5) 1.0 Introduction The Weill Cornell Medicine (WCM) Asbestos Management Program protects the WCM community from the health hazards related to asbestos
Saxe Middle School Auditorium Renovation February 4, 2015
Saxe Middle School Auditorium Renovation February 4, 2015 OVERVIEW OF PRESENTATION Renovation of Saxe Auditorium State & Federal Testing requirements Town Hires Tighe & Bond to perform testing Summary
POTENTIALLY HAZARDOUS MATERIALS BUILDING INSPECTION REPORT. for
POTENTIALLY HAZARDOUS MATERIALS BUILDING INSPECTION REPORT for Michigan State University Engineering and Architectural Services Physical Plant Building, Room 101 East Lansing, Michigan 48824-1326 at Michigan
ASBESTOS BACKGROUND INFORMATION
ASBESTOS BACKGROUND INFORMATION Asbestos Facts What is Asbestos? Asbestos is a mineral. It is a natural rock mined from the ground. Most of the asbestos used in this country comes from Quebec in Canada.
June 27, 2013. Project GSA1570019. Rhonda Rance U.S. General Services Administration 450 Golden Gate Avenue, Floor 4 San Francisco, California 94102
June 27, 2013 Project GSA1570019 Rhonda Rance U.S. General Services Administration 450 Golden Gate Avenue, Floor 4 San Francisco, California 94102 Subject: Determination of Asbestos Conditions Former USDA
SPECIFICATIONS FOR ASBESTOS ABATEMENT
SPECIFICATIONS FOR ASBESTOS ABATEMENT Prepared for: City of Fort Worth Texas Department of Environmental Management 1000 Throckmorton Street Fort Worth, Texas Project: Police District #6 1100 Nashville
1200 N. COLORADO WINSLOW, ARIZONA
ASBESTOS HAZORD EMERGENCY RESPONSE ACT (AHERA) INSPECTION & REPORT OF FIINGS FOR IUSTRIAL ARTS 1200 N. COLORADO WINSLOW, ARIZONA Submitted to: MR. RICHARD WILLIAMS BELFOR PROPERTY RESTORATION 23610 N.
ASBESTOS BUILDING INSPECTION REPORT. for. Michigan State University Office of Environmental and Occupational Safety East Lansing, Michigan 48823
ASBESTOS BUILDING INSPECTION REPORT for Michigan State University Office of Environmental and Occupational Safety East Lansing, Michigan 48823 at Bailey Hall Building #315 East Lansing, Michigan 48823
Asbestos Work Permit Procedures
These procedures are to be followed by all persons required to perform the following work: Handling, installation or removal of non-friable manufactured products known to contain asbestos provided no sanding,
ASBESTOS CONTROL PROGRAM
WESTERN UNIVERSITY OCCUPATIONAL HEALTH AND SAFETY ASBESTOS CONTROL PROGRAM Last Update: August 2012 TABLE OF CONTENTS 1.0 INTRODUCTION AND SCOPE... 3 2.0 DEFINITIONS... 4 3.0 HISTORICAL INFORMATION...
ASBESTOS and LEAD-BASED PAINT INVESTIGATION TOWN OF ST. PAUL WILLIS BUILDING ST. PAUL, VIRGINIA
ASBESTOS and LEAD-BASED PAINT INVESTIGATION TOWN OF ST. PAUL WILLIS BUILDING ST. PAUL, VIRGINIA May 22, 2013 Robert R. Jones, Ph.D., REM, AHERA Asbestos Inspector, 5/22/13 Signature Date Asbestos Virginia
Control Provisions under the Air Pollution Control Ordinance
ProPECC PN 2/97 ENVIRONMENTAL PROTECTION DEPARTMENT PRACTICE NOTE FOR PROFESSIONAL PERSONS Handlin of Asbestos Containin Materials in Buildins Introduction Asbestos is a generic name given to a group of
Preparing the Work Area
Preparing the Work Area Work Area Preparation Objectives of Work Area Prep Sequence and Methods for Prep Engineering Controls: Negative Pressure Requirements, Equipment and Set-up Purpose of Area Prep
Decontamination Units
Decontamination Units 1 DECON The worker/personal decontamination system (commonly called the "decon unit or Decon") is specially designed to allow passage to and from the work area during the abatement
Asbestos Frequently Asked Questions
Asbestos Frequently Asked Questions What is asbestos? Asbestos is a mineral which is mined, processed, and used in many building materials. Since 1988, asbestos has been banned in most US building components;
UBC Plant Operations Asbestos Work Procedures April 2004
UBC Plant Operations Asbestos Work Procedures April 2004 These Procedures are for use by UBC Plant Operations, Utilities, Housing & Conferences, and IT Services only and are not intended for use by other
PRE-DEMOLITION ASBESTOS SURVEY
PRE-DEMOLITION ASBESTOS SURVEY For: City of Largo PSTA Building 14840 49th Street North Largo, Pinellas County, Florida Prepared for: Collman & Karsky Architects 4301 Anchor Plaza Parkway, Suite 100 Tampa,
ASBESTOS in DEPARTMENT OF ADMINISTRATION FACILITIES Frequently Asked Questions
The Language Used In This Document Does Not Create An Employment Contract Between The Employee And The Agency. This Document Does Not Create Any Contractual Rights Or Entitlements. The Agency Reserves
FRED GRAHAM'S ASBESTOS SAFETY PROGRAM EXPERT WITNESS SUPPORT SERVICES
FRED GRAHAM'S ASBESTOS SAFETY PROGRAM EXPERT WITNESS SUPPORT SERVICES QUALIFICATIONS If your asbestos lawsuit requires the services of a asbestos safety program expert witness to determine if the property
ASBESTOS MANAGEMENT PROGRAM RISK MANAGEMENT AND SAFETY 2014 Page 1
ASBESTOSS MANAGEMENT PROGRAM RISK MANAGEMENT AND SAFETY 2014 1 TABLE OF CONTENTS 1.0 INTRODUCTION 4 1.1 Policy 4 1.2 Purpose 4 1.3 Scope and Application 4 2.0 EMERGENCY CONTACT INFORMATION 4 2.1 Asbestos
Asbestos Operations and Maintenance Program. San José State University
San José State University One Washington Square San José, California Facilities Development and Operations Department July 25, 2012 1) Purpose and Scope The purpose of the Asbestos Operations and Maintenance
Miami University s Asbestos Operations & Maintenance Program Administered by
Miami University s Asbestos Operations & Maintenance Program Administered by ENVIRONMENTAL SAFETY & RISK MANAGEMENT 529-2829 Table of Contents Purpose 2 Personnel Covered Under the Asbestos Mangement Plan
How To Manage Asbestos From Roofing And Siding
Contents Frequently Asked Questions Asphaltic Roofing and Siding Materials.... 1 Floor Tile.... 4 Non-Traditional Asbestos Abatement Work Practice Approvals.... 6 Survey Requirements.... 7 Vermiculite
Restoration Specific Asbestos and Lead Based Paint Survey Report. 2503 Logan Ave Colorado Springs, CO 80909
Restoration Specific Asbestos and Lead Based Paint Survey Report Property Information: 2503 Logan Ave Colorado Springs, CO 80909 Inspection Conducted By: Shannon Anderson Colorado Cert #14225 Ted Anderson
Asbestos Management Procedures
Asbestos Management Procedures Introduction Asbestos is a naturally occurring mineral which has commonly been used in a variety of building materials due to its strength and unique fire and chemical resistant
Specifications for Removal and Replacement of Water Damaged/Mold Impacted Materials
Specifications for Removal and Replacement of Water Damaged/Mold Impacted Materials Park Potomac Place 12500 Park Potomac Avenue Potomac, Maryland 20854 KEM Project # 21703 Prepared for: Park Potomac Place
May 23, 2014. Mr. Derek Sandgren Helm Properties 1520 Butte House Road, Suite 400 Yuba City, California 95993-2240
May 23, 2014 Mr. Derek Sandgren Helm Properties 1520 Butte House Road, Suite 400 Yuba City, California 95993-2240 RE: Pre-Demolition Asbestos Survey Report 6150 Farrell Street, Marysville, California 95901
NARRATIVE REPORT. The Asbestos Bulk Sample Results Table includes asbestos sampling data.
NARRATIVE REPORT 1.0 BUILDING INFORMATION The original date of construction for Construction Management Engineering was not immediately available; the building has had no major renovations. Construction
WORK PROCEDURES FOR ASBESTOS RELATED ACTIVITIES
California Institute of Technology WORK PROCEDURES FOR ASBESTOS RELATED ACTIVITIES Caltech Environment, Health, and Safety Office 1200 E. California Blvd., M/C 25-6 Pasadena, CA 91125 Phone: 626.395.6727
Wellesley College Asbestos Management Program
Wellesley College Asbestos Management Program Table of Contents Page Policy 2 Impacts of Asbestos Containing Materials (ACM)... 3 Compliance... 3 Objectives... 4 Operational Controls Standard Operating
Asbestos Management Program and Procedures. Northern Illinois University
Asbestos Management Program and Procedures Northern Illinois University Department of Environmental Health and Safety 8/12/2013 INTRODUCTION Contents INTRODUCTION... 2 PURPOSE... 6 DEFINITIONS... 8 GENERAL
COMPLIANCE WITH THIS PUBLICATION IS MANDATORY
BY ORDER OF THE COMMANDER 56TH FIGHTER WING (AETC) AIR FORCE INSTRUCTION 32-1052 LUKE AIR FORCE BASE Supplement 1 5 NOVEMBER 2008 Civil Engineering FACILITY ASBESTOS MANAGEMENT COMPLIANCE WITH THIS PUBLICATION
Asbestos Hazards and Controls
Asbestos Hazards and Controls Environmental and Occupational Health Public Health Ontario Photo provided with the kind permission of Infrastructure Health & Safety Association 5110 Creekbank Road, Mississauga,
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-02 82 16.00 20 (August 2011) ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-02 82 16.00 20 (February 2010) UNIFIED FACILITIES GUIDE SPECIFICATIONS
Final Amendments of 310 CMR 7.15: Asbestos
Final Amendments of 310 CMR 7.15: Asbestos Published in the Massachusetts Register on June 20, 2014, Typographical Corrections Published on November 21, 2014 7.00 AIR POLLUTION CONTROL Definitions Revised
ASBESTOS SCIENCE TECHNOLOGIES, INC.
ASBESTOS SCIENCE TECHNOLOGIES, INC. P.O. Box 505 Bangor, CA 95914 Phone (530) 518-0934 Email - [email protected] Report for Lincoln Elementary School 1582 Lincoln Road Yuba City, Ca. 95993 Mold Report
Asbestos Management Program
Asbestos Management Program Facilities and Operations Revision #4: February 17, 2012 Page IMPORTANT Asbestos related incidents must be reported IMMEDIATELY to your supervisor Emergency Contacts During
Procedures and Guidelines for Texas A&M University-Kingsville Employees
Procedures and Guidelines for Texas A&M University-Kingsville Employees ENVIRONMENTAL HEALTH & SAFETY OFFICE 1010 RETAMA DRIVE SUPPORT SERVICES BUILDING KINGSVILLE, TX 78363 MARCH 2004 TABLE OF CONTENTS