1 Proposed Re-development, At 321 London Road, Wyberton Flood Risk Assessment - Revised Prepared By: C Mason C.Eng M.I.C.E May 2015

2 Contents Page No. 1. Introduction 2 2. Site Description 2 3. Flood Hazard 3 4. Probability 4 5. Climate Change 4 6. Detailed Proposals 5 7. Residual Risks 6 8. Off-site Impacts 7 9. Flood Risk Management Conclusions 8 Appendices Appendix A Exception Test Appendix B Emergency Response Strategy Figures 1. Location Plan 2. Site Survey 3. Breach Locations 4. Layout Plan 5. Building Plans 6. Hazard Plans Note: Data relating to flood risk supplied (mainly) by the Environment Agency and reproduced under licence No. CCN/2015/38844 This revised FRA takes into account comments made by the EA on the FRA dated March

3 1.0 Introduction 1.1 The owner of No. 321 London Road, Wyberton wishes to demolish the existing, derelict buildings on the site, and replace them with 4 new residential properties. 1.2 Jenny McIntee (Architectural Practice) has been instructed to prepare the required plans for submission of a planning application. As part of the application, a Flood Risk Assessment (FRA) is required, as the site is in Flood Zone 3 i.e. an area which would have a high degree of flood risk, if no flood defences existed. 1.3 This FRA has been prepared by C. Mason C Eng M.I.C.E. It takes account of the requirements of the National Planning Policy Framework (NPPF) and the accompanying Technical Guide. It relies on data provided by the Environment Agency under Licence No. CCN/2015/38844 and it refers to data in Boston District Councils Strategic Flood Risk Assessment (BDC SFRA). Reference is also made to data supplied by Black Sluice Internal Drainage Board (BSIDB). 2.0 Site Description 2.1 The site location is shown on Figure 1- Location Plan. The Post Code is PE21 7AU and the Grid Reference , The existing buildings on the site include previous residential properties and an old Smithy, together with sheds and outbuildings. The site is situated in a wellestablished residential area, with access available from both London Road and Ralphs Lane. 2.3 Ground levels shown on a Topographical Survey carried out by Axis Surveys Ltd, vary between 2.90m OD and 3.42m OD, with an average level of 3.20m OD (See Figure 2 Site Survey). 2.4 The current land usage would be classed as more vulnerable in Table 2 of the NPPF Technical Guide. The proposed use for residential purposes will remain classified as more vulnerable. 2.5 The EA Flood Map shows that the site is in Flood Zone 3 (a), and this is confirmed by maps in the Boston District Council s SFRA. This indicates that the site is in an area which could be affected by flooding from the sea by a flood that has a 0.5% (1 in 200) or greater chance of happening each year, or from a fluvial river flood that has a 1% (1 in 100) or greater chance of happening each year. This assumes that no flood defences are present. 2.6 More vulnerable classes of development are acceptable in Flood Zone 3 (a), subject to application of the Sequential and Exception Tests. As regards the Sequential Test, the re-development of this brownfield site can only take place on the site. Hence, consideration of alternative sites is irrelevant. The Exception Test, as defined in the NPPF, requires 2 criteria to be met. These are considered in Appendix A Exception Test. 2

4 2.7 Much of the existing site is covered by impermeable surfaces. Re-development may, marginally increase the total equivalent impermeable area (see Section 6 Detailed Proposals). 3.0 Flood Hazard 3.1 The following potential sources of flooding were identified :- Tidal - The Haven Fluvial - South Forty Foot Drain Arterial Drains in Black Sluice IDB area Public sewers Highway drains On site drainage systems 3.2 Tidal flooding could occur by overtopping of the defences, or as a result of the defences failing (i.e. breaching). The defences nearest to London Road consist of hard floodwalls (brick/concrete) with typical crest levels around 6.10m ODN. The Environment Agency s year 2006 Tidal Model predicts a 0.5% tide of 5.93m ODN. Hence, there is a small freeboard against overtopping. The structural condition of the defences is good and failure by breaching is unlikely. Modelling of possible breaches has been carried out for the E.A. Locations are shown in Fig Rising tide levels in the future will increase the possibility of overtopping and breaching. These factors are considered in Section 5 Climate Change and Section 7 Residual Risks. 3.4 The 1%, plus climate change, water level in the South Forty Foot has been modelled at 2.88m ODN. This is considerably higher than the normal operating levels, but still almost half a metre below ground levels at the site. Hence, this potential source of flooding can be discounted. 3.5 The site is located near the boundaries of several Black Sluice IDB catchment boundaries. However, it is believed that the area drains into the Chain Bridge Catchment. Typical water levels in the arterial drains are:- Wyberton Town Drain 1.56m ODN, Old London Road (B1397) 1.61m ODN, and Wyberton by Pass (A16) 1.63m ODN. At Wyberton Marsh P St, operating levels are 2.12m ODN and in Frampton Town Drain 2.55m ODN. All of these levels are well below the average ground level on the site of 3.20m ODN. Hence, the risk of flooding from arterial drainage systems is minimal. 3.6 Anglian Water sewer plans show a public foul sewer flowing eastwards in Ralphs Lane (150mm V.C). This connects into a 225mm V.C sewer on the east side of London Road, flowing northwards (see Figure 3 Anglian Water Sewers). Surcharging of these sewers, resulting from blockages or hydraulic overloading, could lead to flooding on or around the site. However, the sewers are over 2.0m deep, and any resultant flooding is likely to be shallow. It would be quickly dealt with by Anglian Water to avoid flooding in properties. 3.7 No surface water sewers are shown on AWs Plans, but there are gullies in both Ralphs Lane and London Road. There is also a minor watercourse shown to the 3

5 south side of No. 333 London Road. If the localised road drainage system became overloaded, or gullies became blocked, then localised flooding could occur which may impact on the site. Depths would be shallow, with flows following the directions of falls in the road profiles (these appear to be to the south and west, although the whole area is relatively flat). 3.8 On site surface water drainage systems will depend on the permeability of the ground, with preference being given to the use of soakaways. Foul drainage will be connected to AW public sewers. Flooding could occur if pipelines become blocked, but this is a residual risk which can be mitigated by regular inspection and maintenance. Surface water pipe sizes will take into account run-off from a 1 in 100 year, 6 hour storm, with an allowance for climate change. 4.0 Probability 4.1 The Boston DC SFRA shows the relative probability of flooding, from both tidal and fluvial sources, as LOW, allowing for the presence of flood defences (i.e. between 1% and 0.1% per annum). 4.2 The probability of surface water flooding in the locality is shown on EA Maps as LOW (i.e. between 1 in 100 (1%) to 1 in 1000 (0.1%)). However, this seems lower than usual and a figure of between 1 in 30 and 1 in 100 years would seem more realistic i.e. 3.33% to 1% particularly taking into account the localised highway drainage systems. 4.3 The probability of flooding from other sources i.e. arterial drains and underground water is negligible. 5.0 Climate Change 5.1 The NPPF Technical Guidance document provides information to enable potential impacts of climate change to the taken into account. 5.2 Table 4 contains recommended contingency allowances for net sea level rises for periods up to 2115 and Table 5 gives recommended national precautionary sensitivity ranges for peak rainfall intensities, peak river flows, off shore wind speeds and wave heights. 5.3 To the year 2115, these factors are quoted as:- Peak river flow +20% Tide level increase above 1.0m Peak rainfall intensity +30% 5.4 There is continuing debate regarding the future predicted impacts of climate change, particularly on the long term increases in sea level rise. However, if tidal levels in the Haven did rise by over 1.0m, then considerable improvements would be required to the sea defences, to maintain current standards of protection. 5.5 The Environment Agency, working with other organisations (including Port Authorities) is seeking to ensure that Shore-line Management Plans (SMPs) and Catchment Flood Management Plans (CFMPs) are complied with. These will ensure 4

6 that appropriate standards of protection are retained where it is economically viable to do so. 5.6 The River Witham CFMP, indicates that the Environment Agency will adopt a Flood Risk Management Policy involving improvements at Boston, which allows for the impacts of climate change. Hence, the site is likely to remain at similar or improved standards of Tidal Defence, as those which currently exist, into the foreseeable future. 6.0 Detailed Proposals 6.1 The proposed re-development is shown on Figure 4 Layout Plans, and Figure 5 Building Plans. 6.2 Roof water will be taken to soakaways, constructed in compliance with the Building Regs. Pathways will be a gravel or similar permeable materials, and foul sewage will be connected to the main public sewers. Access to the bungalow will be from Ralphs Lane, and access to the 3 houses from London Road. 6.3 The areas of the various elements are:- Overall site area 1280m 2 Roof areas 396m 2 Driveways 140m 2 (permeable materials) Landscaping and gardens 744m m 2 Total This gives a future equivalent impermeable area of:- 396 x 0.9 = x 0.3 = x 0.1 = m 2 say 445m 2 The existing site has less roof area, but more hard surfaces concrete paths and tarmac areas. The equivalent impermeable area is:- Roof areas 263m 2 x 0.9 = Hard Surfaces 144m 2 x 0.7 = Grassed areas 873m 2 x 0.1 = m 2 The increased equivalent impermeable area is only approximately 21m 2. Hence, there will be no significant increase in surface water run-off from the site. Soakaways will be designed to accept run-off in a 1 in 100 year, 6 hour storm plus the impacts of climate change. It flows had to be balanced to pre-existing run-off rates, before discharge, a total storage volume of approximately 18m 3 has been calculated assuming a rainfall event of 150mm in 6 hours. Taking into account the individual roof areas, storage volumes of 5.75m 3, 4.50m 3 (twice) and 3.25m 3 would be needed for the bungalow, the 2, 4 bedroom houses and the 3 bedroom house. If necessary, these storage volumes could be achieved by the use of geo-cellular crates. However, the strong preference is for soakaways designed in accordance with BRE Digest 365, and the Building Regulations. 5

7 6.4 The ground floor levels will be raised by 650mm. This is maximum amount that can be achieved within the constraints of the site dimensions whilst keeping the gradients of ramps reasonable. The finished floor levels of no lower than 3.85m ODN should be above any potential flood level. However, a degree of flood resistance and flood resilience will be included in the design of the buildings. This issue is considered further in Section 9 Flood Risk Management. 6.5 Foul sewers will be connected to the existing public sewers, at locations approved by Anglian Water. 7.0 Residual Risks 7.1 The main residual risks which could impact on the site are overtopping or failure of the Haven defences. Others, which would have lesser consequences are blockages or system failures in the public sewerage systems. 7.2 The Environment Agency have supplied data relating to hazardous conditions arising from overtopping and breaching of the Haven defences. This computer generated 2D, Hazard Mapping is reproduced n Figure 6 Hazard Maps 7.3 From the Hazard Maps the following data has been extracted:- Breach Year Annual Chance % (1 in 200) % (1 in 1000) % (1 in 200) % (1 in 1000) Overtopping % (1 in 200) % (1 in 1000) Max. Velocity (m/s) Max. Depth (m) Max. Hazard Low Low Danger for Most Danger for Most NIL NIL NIL NIL NIL NIL Note: The site is not affected by overtopping for present day (2006) scenarios, or for future (2115) scenarios. Hence, the only residual risk is if a breach occurs. The probability of this occurring is very low. The defences are in good condition, and they are inspected regularly. 7.4 At times of flood dry access/egress in the area would not be possible. However, even if a breach occurred, there would be periods of up to 8 hours or so in which flood water would not be issuing from the river (as tides fall below the level of the gap in the defences). During these periods it is reasonable to assume that Emergency Service vehicles would be able to safely operate along London Road 6

8 (hazard ratings would be significantly reduced from peak values, as flood water spread out and reduced in both depth and velocity). 7.5 Blockages and failures in the public sewerage systems would be quickly dealt with by Anglian Water and consequential flooding would be temporary and probably shallow. 8.0 Off-site Impacts 8.1 No adverse off-site impacts are envisaged as a result of this re-development. 9.0 Flood Risk Management 9.1 The property will be connected to the Environment Agency s Flood Warning Direct system, and an Emergency Response Plan will be drawn up and implemented, similar to the example given in Appendix B. 9.2 The final list of flood resistant/resilience measures should be agreed between the owner (developer), the architects and the Council s Building Inspectors. Appropriate selection of items will help to keep house insurance premiums down. Useful advice can be found in the publication Homeowners Guide to Flood Resilience A living Document, and in the publication Improving the Flood Performance of New Buildings Flood Resilient Construction (produced by the Department of Communities and Local Government). 9.3 Consideration should be given to:- The use of barriers for doors and windows Installation of electric ring mains at first floor level with drops to ground floor sockets and switches. Placing electrical sockets at least 1.0m above ground floor level. Using non-return values on foul sewerage systems. The use of water resistant materials for floors (e.g. 150mm concrete slab with polythene membrane at least 1200 garage). Floor finishes of either sand/cement screeds, ceramic tiles or stone tiles. The use of PVC or ceramic tiles for skirting boards. The use of cement/lime render for walls (1:6:1 cement:sand:lime). Self-sealing covers on airbricks (if applicable). Effective seals at service entry points. At depths predicted on the Hazard Maps, for 2115, the Environment Agency prefer floor levels to be raised by 1.0m, and flood resilience to be incorporated 300mm above predicted flood level. This is not possible on this site, because of relative levels of adjacent properties. Hence, a compromise is suggested where floor levels are raised 650mm above average ground levels, barriers are provided to doors, for a further 650mm, and flood resilience included inside the buildings to a height of at least 1.0m above floor levels. 7

9 10.0 Conclusions 10.1 As a result of this revised FRA the following conclusions have been reached:- The site is in Flood Zone 3 (a) as shown by the EAs Maps and maps in the SFRA. The current use of the land is classified as more vulnerable and the replacement buildings will have the same classification. More vulnerable uses are acceptable in Flood Zone 3 (a) subject to the Sequential and Exception Tests being satisfied. The re-development of these derelict buildings can only be achieved on this site. Hence, the sequential test is not applicable in this case. The Exception Test is shown to be satisfied, by this assessment (see Appendix A). The only significant risk of flooding at this site is from the tidal Haven, and this is related to a very low probability of a breach occurring. Overtopping of the Haven defences does not appear to cause flooding at this site, even in the long term (see EA Hazard Maps) Flood resistant/resilience measures can be included in the design of the new building, to mitigate any residual flood risks. Floor levels will be raised by 650mm, and barriers used on doors. Flood resilience measures will be at least 1.0m above floor levels (see Section 9.3) The use of an Emergency Response Plan will help to increase awareness, and improve safety for residents The re-development of this brownfield site would improve the environment and would help to avoid potential anti-social uses of the derelict buildings. Note. The Environment Agency are promoting and progressing a major project for the construction of a Tidal Barrier which will reduce tidal flood risk in Boston Overall, it is concluded that with appropriate mitigation, the re-development of this site for residential purposes can be achieved safely, without increasing flood risk elsewhere. The site has previously had an outline planning application approved for 4 properties (B/05/0326 approved on 18 th July 2005). Hence, the general principles of re-developing the site were accepted, at that time. 8

10 Appendix A Exception Test A1. The NPPF requires a sequential approach to be adopted which seeks to avoid locating development in relatively high flood risk areas, if possible. However, it is accepted that, where an individual proposes to re-develop their property in an existing flood risk area, the consideration of alternative sites is not likely to be a realistic option. A2. As residential development has been selected for replacement building then the exception test must be applied. For the test to be passed, 2 criteria must be satisfied:- The development must provide wider sustainability benefits to the community that outweigh flood risk etc. Residential developments are needed in Boston, and this brownfield site is becoming derelict, with the strong possibility of being used for anti-social purposes. A FRA must demonstrate that the development will be safe, without increasing flood risk elsewhere, and where possible reduce flood risk overall This FRA demonstrates that the site can be developed safely without increasing flood risk elsewhere. It also shows that mitigation measures can reduce the potential consequences of flooding, by raising floor levels, by introducing resilient construction and by improving the awareness of flooding impacts and self-help measures. 9

11 Appendix B Emergency Response Strategy B1. In situations such as those which exist at London Road i.e. where there is a relatively LOW probability of flooding but potential for SIGNIFICANT consequences, flood warning and emergency response procedures are particularly important. The Emergency Response Strategy for the London Road site will be based on 3 factors:- Increasing awareness Ensuring adequate preparedness Ensuring co-ordinated action B2. Residents will be made aware of:- The nature and extent of potential flooding (low probability/significant consequences) The Environment Agency s Flood Warning Service (get to know the Flood Warning Codes, and the need to register with Floodline) The importance of self-help measures (the need for a Flood Plan actions before and during flooding) Actions to be taken in severe events (protect what you can, but evacuate when told, act on advice of emergency services) An information pack will be supplied containing details of all the above items, with telephone contact numbers, guidance notes, and check lists (as per advice provided by the Environment Agency, Lincolnshire County Council and Boston Borough Council). B3. To ensure adequate preparedness all occupiers will be encouraged to register for the Environment Agency s Flood Warning Service Floodline Warnings Direct). B4 When Flood Warning messages are received all residents should take actions defined in their information packs. These will include, inter alia:- Moving as much as possible upstairs to minimise flood damage. Locating and securing emergency supplies Turning off gas, electricity and water supplies Listing to the local radio station for updates and/or calling Floodline. B5. If an event leads to the issuing of a Severe Flood Warning then residents should listen to, and act on the advice of the emergency services (and of Flood Wardens if any are operating in the locality). 10

12 B6. Following exercise Watermark (in March 2011), various recommendations were made which will influence how major flooding incidents are dealt with, in the future. Flood Wardens in various localities will be kept aware of the developing processes involving multi-agency co-ordination, and they could arrange for essential, key facts to be communicated to all residents (possibly by presentations made by Council or Environment Agency Officers). B7. The main aims of the Emergency Response Strategy are:- To avoid loss of life To save important documents (e.g. Birth/marriage certificates, insurance policies etc.) To protect whatever can be done safely (e.g. electrical goods, TV etc.) To minimise property damage (Note: The process should take into account the needs of children and vulnerable people, and special needs of ethnic groups). 11

13 Figures 1. Location Plan 12

14 2. Site Survey 13

15 3. Breach Locations 14

16 4. Layout Plan 15

17 5. Building Plans Plot 1 Plot 2 16

18 Plot 3 Plot 4 17

19 6. Hazard Plans 18

20 19

Recommendations for future developments

Recommendations for future developments C Recommendations for future developments C.1 Reducing flood risk through site layout and design C.1.1 C.1.2 Flood risk should be considered at an early stage in deciding the layout and design of a site

More information

FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY

FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY London Rd. WATERLOOVILE FOR McCarthy & Stone Ltd. July 2010 Such Salinger Peters Ltd 30558-1- Flood Risk Assessment & Drainage Strategy Contents Paragraph Page

More information

Proposed Construction of Basement Flood Risk Assessment. 35 Edwardes Square London W8 6HH

Proposed Construction of Basement Flood Risk Assessment. 35 Edwardes Square London W8 6HH Proposed Construction of Basement Flood Risk Assessment 35 Edwardes Square London W8 6HH 1 Introduction This FRA has been carried out in accordance with the National Planning Policy Statement (NPPF), the

More information

Littleport Co-located Schools

Littleport Co-located Schools Littleport Co-located Schools February 2015 Morgan Sindall Littleport Co-located Schools 330763 BNI BSE 003 C P:\Cambridge\Murdoch\EST\PROJECTS\330763 Littleport Co-located Schools\12.0 Documents\12.2

More information

Land to the rear of the Black Bull Public House Flood Risk Assessment March 10, 2014 Version 1.0 Ref: RAB 148

Land to the rear of the Black Bull Public House Flood Risk Assessment March 10, 2014 Version 1.0 Ref: RAB 148 Land to the rear of the Black Bull Public House Flood Risk Assessment March 10, 2014 Ref: RAB 148 Lindsey Phillips Turnbull Tweedale Ltd 61 Oaken Lanes Codsall South Staffordshire WV8 2AW R A B C O N S

More information

Proposed Residential Development Land off Cody Road Waterbeach Cambridgeshire. Flood Risk Assessment

Proposed Residential Development Land off Cody Road Waterbeach Cambridgeshire. Flood Risk Assessment Land off Cody Road Waterbeach Cambridgeshire Cedar Barn, White Lodge, Walgrave, Northampton, NN6 9PY T: F: E: W: 01604 781811 01604 781999 [email protected] jppuk.net Proposed Residential Development Land

More information

WEST LONDON PIPELINE AND STORAGE LIMITED AND UNITED KINGDOM OIL PIPELINES LIMITED

WEST LONDON PIPELINE AND STORAGE LIMITED AND UNITED KINGDOM OIL PIPELINES LIMITED WEST LONDON PIPELINE AND STORAGE LIMITED AND UNITED KINGDOM OIL PIPELINES LIMITED WLPS BUNCEFIELD REBUILD Flood Risk Assessment Green Lane Hemel Hempstead Hertfordshire HP2 7HZ September 2009 Prepared

More information

Essex County Council Flood Investigation Report

Essex County Council Flood Investigation Report Essex County Council Stock City of Chelmsford Rev Date Details Author Checked and Approved By 01 February 2015 Draft report for stakeholder consultation Ed Clarke Flood Investigation Engineer Lucy Shepherd

More information

Creating the environment for business

Creating the environment for business 1. Introduction 1.1 Introduction to Water Cycle Strategies (WCS) 1.1.1 Background The water cycle describes the pathways and processes through which water moves through the natural and built environment,

More information

Vital Earth Composting Facility Flood Risk and Drainage Statement

Vital Earth Composting Facility Flood Risk and Drainage Statement Vital Earth Flood Risk and Drainage Statement Final December 2011 Prepared for Vital Earth Ltd Revision Schedule Flood Risk and Drainage Statement December 2011 Rev Date Details Prepared by Reviewed by

More information

London Borough of Merton Local Flood Risk Management Strategy

London Borough of Merton Local Flood Risk Management Strategy Local Flood Risk Management Strategy Summary 2014-2020 Introduction In response to the severe flooding across large parts of England and Wales in summer 2007, the Government has recently enacted the Flood

More information

London Borough of Waltham Forest LOCAL FLOOD RISK MANAGEMENT STRATEGY. Summary Document

London Borough of Waltham Forest LOCAL FLOOD RISK MANAGEMENT STRATEGY. Summary Document LOCAL FLOOD RISK MANAGEMENT STRATEGY Summary Document October 2013 Local Flood Risk Management Strategy Summary 1 Introduction 2 Partner responsibilities 3 What do we know about flooding in the borough?

More information

FLOOD RISK RECENT TRENDS AND POLICY RESPONSES

FLOOD RISK RECENT TRENDS AND POLICY RESPONSES FLOOD RISK RECENT TRENDS AND POLICY RESPONSES DEVELOPING WESTMINSTER S LOCAL PLAN Booklet No. 2 LDF Consultation - CMP Revision November 2013 INTRODUCTION CLLR ROBERT DAVIS Westminster is at risk of flooding

More information

Newbiggin House Farm,

Newbiggin House Farm, Newbiggin House Farm, Near Waberthwaite Flood Investigation Report 32 Flood Event 30/8/2012 Cumbria County Council Version Undertaken by Reviewed by Approved by Date Preliminary Colin Parkes Anthony Lane

More information

INFRASTRUCTURE, FLOOD PROTECTION AND REMEDIATION. Infrastructure Flood Protection Remediation Policies

INFRASTRUCTURE, FLOOD PROTECTION AND REMEDIATION. Infrastructure Flood Protection Remediation Policies INFRASTRUCTURE, FLOOD PROTECTION AND REMEDIATION Infrastructure Flood Protection Remediation Policies DRAFT POOLBEG PLANNING SCHEME 196 FIGURE 9.1: UTILITIES WAYLEAVES Electricity Cables 8m Wayleave for

More information

DWELLING ADJACENT TO 2, FIELD LANE, MORTON, NR GAINSBOROUGH, LINCOLNSHIRE.

DWELLING ADJACENT TO 2, FIELD LANE, MORTON, NR GAINSBOROUGH, LINCOLNSHIRE. FLOOD EMERGENCY PLAN FOR DWELLING ADJACENT TO 2, FIELD LANE, MORTON, NR GAINSBOROUGH, LINCOLNSHIRE. MARCH 2014 Introduction In accordance with Environment Agency advice this Flood Emergency Plan is proportionate

More information

DRAINAGE MANAGEMENT PLAN. HERTFORDSHIRE RESIDUAL WASTE TREATMENT PLANT Hertfordshire County Council

DRAINAGE MANAGEMENT PLAN. HERTFORDSHIRE RESIDUAL WASTE TREATMENT PLANT Hertfordshire County Council DRAINAGE MANAGEMENT PLAN HERTFORDSHIRE RESIDUAL WASTE TREATMENT PLANT Hertfordshire County Council EMPLOYER: Veolia Environmental Services (UK) Plc Veolia House 154A Pentonville Road London N1 9PE Copy

More information

NEW DEVELOPMENT AND EMERGENCY FLOOD PLANS

NEW DEVELOPMENT AND EMERGENCY FLOOD PLANS 23 NEW DEVELOPMENT AND EMERGENCY FLOOD PLANS Turn page Northamptonshire Flood Toolkit This guidance has been developed to support applicants and developers who are required or encouraged to produce and

More information

Action plans for hotspot locations - Ash Study

Action plans for hotspot locations - Ash Study Appendix 9 Action plans for hotspot locations - Ash Study Ash Vale North 1. Local evidence indicates the culvert could not discharge during December 2013 because the outlet was blocked on the western side

More information

Strategic Flood Risk Assessment

Strategic Flood Risk Assessment local development framework Strategic Flood Risk Assessment LOCAL DEVELOPMENT FRAMEWORK ROYAL BOROUGH OF KINGSTON UPON THAMES Level 1 and 2 April 2011 Contents Executive Summary 5 Part 1 - Aiding Planning

More information

Mr & Mrs Clarke Proposed Development at The River House, Balderstone Flood Risk Assessment

Mr & Mrs Clarke Proposed Development at The River House, Balderstone Flood Risk Assessment Proposed Development at The River House, Balderstone D2192-FRA-01 5 Nov 2015 PSA Design Ltd Consulting Engineers The Old Bank House 6 Berry Lane Longridge Preston PR3 3JA Tel. 01772 786066 Fax. 01772 786265

More information

London Borough of Croydon Local Flood Risk Management Strategy

London Borough of Croydon Local Flood Risk Management Strategy London Borough of Croydon Local Flood Risk Management Strategy Summary 2014-2020 Introduction In response to the severe flooding across large parts of England and Wales in summer 2007, the Government has

More information

FLOOD INFORMATION SERVICE EXPLANATORY NOTES

FLOOD INFORMATION SERVICE EXPLANATORY NOTES FLOOD INFORMATION SERVICE EXPLANATORY NOTES Part 1 About the flood maps Limitations of the mapping What the maps don t show Where to find more information Definitions of words used to describe flooding.

More information

The application site is on the edge of flood zones 1 and 2 with flood zone boundary cutting across part of the southern boundary of the site.

The application site is on the edge of flood zones 1 and 2 with flood zone boundary cutting across part of the southern boundary of the site. Flood Risk Assessment Erection of Masjid/ Place of Worship, extended car parking following demolition of 11a Grafton Street & boundary treatment Land adjacent 11/ 11a Grafton Street, Preston, PR1 8JB 0723/

More information

Preliminary Environmental Information Report: Appendix 16.C. Flood Warning and Evacuation Plan

Preliminary Environmental Information Report: Appendix 16.C. Flood Warning and Evacuation Plan Preliminary Environmental Information Report: Appendix 16.C Flood Warning and Evacuation Plan THIS PAGE IS LEFT INTENTIONALLY BLANK Page 2 of 30 Contents SUMMARY 1. INTRODUCTION... 9 1.1 Background...

More information

East Riding of Yorkshire Council

East Riding of Yorkshire Council East Riding of Yorkshire Council Lead Local Flood Authority Interim Standing Advice Revision A - April 2015 1. Introduction From April 2015 the Lead Local Flood Authority (LLFA) became a statutory consultee

More information

Flood Risk Assessment and Drainage Impact Assessment: Planning Guidance for Developers

Flood Risk Assessment and Drainage Impact Assessment: Planning Guidance for Developers Flood Risk Assessment and Drainage Impact Assessment: Planning Guidance for Developers Development and Regeneration Services Glasgow City Council 229 George Street Glasgow G1 1QU May 2011 1. Introduction...-

More information

Bolton s Flood Risk Management Strategy

Bolton s Flood Risk Management Strategy Bolton s Flood Risk Management Strategy www.bolton.gov.uk Public Summary Bolton s Flood Risk Management Strategy Public Summary Introduction Over 5.5 million properties in England and Wales are at risk

More information

Flood Repair and Renew Grant Guidance to Applicants

Flood Repair and Renew Grant Guidance to Applicants Flood Repair and Renew Grant Guidance to Applicants Purpose of the Fund Following an announcement by the Prime Minister on the 12 th February 2014, the Repair and Renew Grant (RRG) scheme has been established

More information

Useful information to help you protect your home or business from the risks of flooding

Useful information to help you protect your home or business from the risks of flooding communities Flood Resilience Guide Useful information to help you protect your home or business from the risks of flooding Contents Introduction...................................................................

More information

1.2 This technical note provides a preliminary investigation into the Flood Risk and provides outline drainage strategies.

1.2 This technical note provides a preliminary investigation into the Flood Risk and provides outline drainage strategies. ODYSSEY MARKIDES TECHNICAL NOTE PROJECT : CHAILEY HOUSE, BLEWBURY JOB NO. : 14-216 NOTE TITLE : PRELIMINARY FLOODING AND DRAIANGE AUTHOR : STEVEN ROOTH APPROVED : ANDREAS MARKIDES DATE : 02/09/2014 1.0

More information

Planning Advice Note Guidance on Producing a Flood Emergency Plan. For planning applicants and developers to accompany a planning application

Planning Advice Note Guidance on Producing a Flood Emergency Plan. For planning applicants and developers to accompany a planning application Planning Advice Note Guidance on Producing a Flood Emergency Plan For planning applicants and developers to accompany a planning application DISCLAIMER The London Borough of Richmond upon Thames, as far

More information

SUFFOLK COASTAL DISTRICT COUNCIL DOMESTIC FLOOD PROTECTION POLICY

SUFFOLK COASTAL DISTRICT COUNCIL DOMESTIC FLOOD PROTECTION POLICY SUFFOLK COASTAL DISTRICT COUNCIL DOMESTIC FLOOD PROTECTION POLICY 1. Introduction 1.1 The Council recognises the threat to local communities from flooding following severe weather events and as a result

More information

Issue: 2 Adopted by Council: 20/02/07. Directorate of Environment and Regeneration Planning Services

Issue: 2 Adopted by Council: 20/02/07. Directorate of Environment and Regeneration Planning Services Issue: 2 Adopted by Council: 20/02/07 Directorate of Environment and Regeneration Planning Services LOCAL PLANNIING GUIIDANCE NOTE NO..19:: SUSTAIINABLE DRAIINAGE SYSTEMS Background The provision of adequate

More information

Strategic Flood Risk Assessment Update 2015

Strategic Flood Risk Assessment Update 2015 Strategic Flood Risk Assessment Update 2015 On behalf of Contents Glossary... iv Executive Summary... 1 1 Introduction... 4 1.1 Overview... 4 1.2 Future Development in Lewisham Borough... 5 2 SFRA Approach...

More information

Flood Evacuation Strategy Hawkins Lane, Burton on Trent

Flood Evacuation Strategy Hawkins Lane, Burton on Trent Flood Evacuation Strategy Hawkins Lane, Burton on Trent Tesco Stores Ltd 10-Apr-14 Issue and Revision Record Rev Date Changes Originator Checker Approver - 10.09.10 N/A BS GB NK A 10.04.14 Amended to suit

More information

Flood Risk & Surface Water Management. Page 1 of 20

Flood Risk & Surface Water Management. Page 1 of 20 Page 1 of 20 Flood Risk & Surface Water Management Flood Risk & Surface Water Management and the Planning Process Introduction The purpose of this document is to increase awareness of the potential of

More information

Homes and Environment Scrutiny Committee. (Environment & Transport)

Homes and Environment Scrutiny Committee. (Environment & Transport) REPORT TO: REPORT NO: Homes and Environment Scrutiny Committee HHPPE/89/15S DATE: 9 September 2015 LEAD MEMBER: Councillor David A Bithell (Environment & Transport) CONTACT OFFICER: Neil Taunt (Tel: 729734)

More information

R enfrewshire Local Plan. Safe Environment. Page. Flooding & Sustainable Urban Drainage 163 Contaminated Land 175 Noise 177 Major-Accident Hazards 179

R enfrewshire Local Plan. Safe Environment. Page. Flooding & Sustainable Urban Drainage 163 Contaminated Land 175 Noise 177 Major-Accident Hazards 179 R enfrewshire Local Plan Safe Environment Page Flooding & Sustainable Urban Drainage 163 Contaminated Land 175 Noise 177 Major-Accident Hazards 179 16 Flooding and Sustainable Urban Drainage OVERVIEW Flooding

More information

Taylor Wimpey UK Ltd. December 2007

Taylor Wimpey UK Ltd. December 2007 Taylor Wimpey UK Ltd December 2007 QM Issue/revision Issue 1 Revision 1 Revision 2 Revision 3 Remarks Draft For Planning Date 3 August 2007 20 December 2007 Prepared by D Gooding P Barton Signature Checked

More information

Cambridge House, Henry Street, Bath BA1 1UR

Cambridge House, Henry Street, Bath BA1 1UR Flood Risk Assessment Cambridge House, Henry Street, Bath BA1 1UR For Full Planning application to BANES Council June 2011 Introduction This report is prepared as requested by B&NES to accompany the planning

More information

Chapter 9: Water, Hydrology and Drainage Land West of Uttoxeter

Chapter 9: Water, Hydrology and Drainage Land West of Uttoxeter Chapter 9: Water, Hydrology and Drainage Land West of Uttoxeter ENVIRONMENTAL STATEMENT: VOLUME 1 9.1 INTRODUCTION 9.1.1 This Chapter considers the effects of the Project on surface water and groundwater

More information

Control filling, grading, dredging, and other development which may increase erosion or flood damage; and

Control filling, grading, dredging, and other development which may increase erosion or flood damage; and ARTICLE 16. FLOOD DAMAGE PREVENTION Section 16-1: Findings of Fact The flood hazard areas of the Town of Lillington are subject to periodic inundation which results in loss of life and property, health

More information

PREVENTION. City of Orem FLOOD DAMAGE PREVENTION 10-1-1

PREVENTION. City of Orem FLOOD DAMAGE PREVENTION 10-1-1 City of Orem FLOOD DAMAGE PREVENTION 10-1-1 CHAPTER 10. Article 10-1. Article 10-2. Article 10-3. Article 10-4. Article 10-5. FLOOD DAMAGE PREVENTION Purposes Definitions General Provisions Administration

More information

FLOOD RISK AND SURFACE WATER DRAINAGE ASSESSMENT HILLHOUSE RESTORATION SITE, OFF JAMESON ROAD, THORNTON CLEVELEYS ON BEHALF OF NPL ESTATES

FLOOD RISK AND SURFACE WATER DRAINAGE ASSESSMENT HILLHOUSE RESTORATION SITE, OFF JAMESON ROAD, THORNTON CLEVELEYS ON BEHALF OF NPL ESTATES FLOOD RISK AND SURFACE WATER DRAINAGE ASSESSMENT HILLHOUSE RESTORATION SITE, OFF JAMESON ROAD, THORNTON CLEVELEYS ON BEHALF OF NPL ESTATES Integra Consulting Engineers Limited NS / 2543 Fountain House

More information

Renfrewshire Strategic Flood Risk Assessment

Renfrewshire Strategic Flood Risk Assessment Background Report Renfrewshire Strategic Flood Risk Assessment 16 Renfrewshire Local Development Plan Main Issues Report December 2011 Renfrewshire Local Development Plan Background Report X Renfrewshire

More information

Wye and Usk Catchment Flood Management Plan. Summary Report January 2010. managing flood risk

Wye and Usk Catchment Flood Management Plan. Summary Report January 2010. managing flood risk Wye and Usk Catchment Flood Management Plan Summary Report January 2010 managing flood risk We are Environment Agency Wales. It s our job to look after your environment and make it a better place for you,

More information

A Guide to the Role of Community Flood Wardens

A Guide to the Role of Community Flood Wardens A Guide to the Role of Community Flood Wardens What is a Community Flood Warden Scheme? Community Flood Warden schemes are completely voluntary, and can consist of a single person or several people acting

More information

PROPERTY RISK MANAGEMENT BUSINESS EMERGENCY, FLOOD PLANNING AND MITIGATION GUIDANCE

PROPERTY RISK MANAGEMENT BUSINESS EMERGENCY, FLOOD PLANNING AND MITIGATION GUIDANCE PROPERTY RISK MANAGEMENT BUSINESS EMERGENCY, FLOOD PLANNING AND MITIGATION GUIDANCE 1 The most common cause of flooding is when the river catchment area receives far greater amounts of water than normal,

More information

5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES

5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES 5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES Flood damage reduction consists of two basic techniques structural and non-structural. Structural methods modify the flood and take the flood away from people

More information

FLOOD RISK ASSESSMENT

FLOOD RISK ASSESSMENT SEVERN ROAD RESOURCE RECOVERY CENTRE FLOOD RISK ASSESSMENT REF 402.0036.00374 September 2009 Severn Road Resource Recovery Centre Ref: 402-0036-00374 Viridor Waste Management i PPS25 Flood Risk Assessment

More information

16. Storm water drainage

16. Storm water drainage 16. Storm water drainage There are three principal ways to dispose of rainwater from roofs, courtyards and paved areas: storm water sewers, soakaways and collection in storage tanks. Storm water sewers,

More information

Guidance on the use of sustainable drainage systems (SUDS) and an overview of the adoption policy introduced by

Guidance on the use of sustainable drainage systems (SUDS) and an overview of the adoption policy introduced by Guidance on the use of sustainable drainage systems (SUDS) and an overview of the adoption policy introduced by Easy guide to Sustainable drainage systems 02 Contents Page Introduction 05 Purpose of this

More information

Product 4 (Detailed Flood Risk) for: Sam Murray (Amey) Site: Land at Kingsnorth Reference: KSL151125 KR79 Date: 30 th November 2015.

Product 4 (Detailed Flood Risk) for: Sam Murray (Amey) Site: Land at Kingsnorth Reference: KSL151125 KR79 Date: 30 th November 2015. Product 4 (Detailed Flood Risk) for: Sam Murray (Amey) Site: Land at Kingsnorth Reference: KSL151125 KR79 Date: 30 th November 2015 Contents Flood Map Confirmation Flood Map Extract Model Output Data Data

More information

SUSTAINABLE URBAN DRAINAGE SYSTEMS

SUSTAINABLE URBAN DRAINAGE SYSTEMS overflow can lead into a permeable conveyance system to increase further the benefit and reduce the need for pipe systems. Pollutant removal rates have been shown to be high, with some pollutants being

More information

A Guide to Flood Resilient Repairs

A Guide to Flood Resilient Repairs A Guide to Flood Resilient Repairs A Guide to Flood Resilient Repairs Some five million people live under the threat of flooding that s one in ten houses in the UK and 200,000 are very high risk. This

More information

FLOOD DAMAGE PREVENTION ORDINANCE

FLOOD DAMAGE PREVENTION ORDINANCE FLOOD DAMAGE PREVENTION ORDINANCE SECTION 1.0 STATUTORY AUTHORIZATION, FINDINGS FO FACT, PURPOSE, AND OBJECTIVES 1.1 STATUTORY AUTHORIZATION The Legislature of the State of Washington has in RCW delegated

More information

Granville Road Estate, London Borough of Barnet. Flood Risk Assessment and Drainage Strategy August 2014. New Granville LLP

Granville Road Estate, London Borough of Barnet. Flood Risk Assessment and Drainage Strategy August 2014. New Granville LLP Granville Road Estate, London Borough of Barnet Flood Risk Assessment and Drainage Strategy August 2014 New Granville LLP Document History JOB NUMBER: 237 DOCUMENT REF: Granville Road FRA REVISIONS: Final

More information

Climate Change Toolkit 07 Designing for Flood Risk

Climate Change Toolkit 07 Designing for Flood Risk Climate Change Toolkit 07 Designing for Flood Risk About this Document This is the seventh of eight components of Climate Change Tools, a package of guidance developed by the RIBA to encourage architects

More information

Sewer Flooding Alleviation in the Counters Creek Catchment

Sewer Flooding Alleviation in the Counters Creek Catchment Sewer Flooding Alleviation in the Counters Creek Catchment London Borough of Hammersmith and Fulham Monday, 14 November 2011 at 7.00pm The Small Hall, Hammersmith Town Hall, King Street, W6 9JU Agenda

More information

INFORMATION BULLETIN BUSINESS FLOOD PLANNING AND MITIGATION GUIDE ACE GLOBAL RISK ENGINEERING. Flood risk assessment. Introduction

INFORMATION BULLETIN BUSINESS FLOOD PLANNING AND MITIGATION GUIDE ACE GLOBAL RISK ENGINEERING. Flood risk assessment. Introduction ACE GLOBAL RISK ENGINEERING INFORMATION BULLETIN BUSINESS FLOOD PLANNING AND MITIGATION GUIDE Introduction The most common cause of flooding is due to established water storage areas (natural and man-made)

More information

Flood Risk Assessment Breakspear House, Hemel Hempstead. Kier Property. October 08

Flood Risk Assessment Breakspear House, Hemel Hempstead. Kier Property. October 08 Flood Risk Assessment Breakspear House, Hemel Hempstead. Kier Property October 08 Prepared by:... Approved by:... Simon Marcos Keith Searle Principal Engineer Associate Director Flood Risk Assessment Rev

More information

Federal Triangle Stormwater Working Group Federal Triangle Floodproofing Seminar BUILDING STRONG SM

Federal Triangle Stormwater Working Group Federal Triangle Floodproofing Seminar BUILDING STRONG SM Federal Triangle Stormwater Working Group Federal Triangle Floodproofing Seminar Initial Risk Flood Risk = Probability of Flooding x Consequences Zoning Building Codes Outreach Evacuation Planning Risk

More information

The site is Lot 1 DP 837271. Survey of this lot and Willarong Road and Koonya Circuit is given in Figure 2.

The site is Lot 1 DP 837271. Survey of this lot and Willarong Road and Koonya Circuit is given in Figure 2. Our Ref : NA49913151-019-L02:BCP/bcp Contact: Dr Brett C. Phillips 8 th May 2015 Cardno (NSW/ACT) Pty Ltd ABN 95 001 145 035 The Manager Bunnings Group Limited, c/- C&M Consulting Engineers 1/142 James

More information

rescue and relief efforts in the aftermath of flooding, (iii) repair of flood damaged public facilities and utilities, and

rescue and relief efforts in the aftermath of flooding, (iii) repair of flood damaged public facilities and utilities, and 1. Purpose (1) It is the purpose of this Ordinance to protect human life, health, and property from flood conditions, to preserve the ability of floodplains to carry and discharge a base flood, and to

More information

2 ND SEPTEMBER 2014. Report of the Bi-Borough Executive Director for Transport and Technical Services

2 ND SEPTEMBER 2014. Report of the Bi-Borough Executive Director for Transport and Technical Services London Borough of Hammersmith & Fulham COMMUNITY SAFETY, ENVIRONMENT & RESIDENTS SERVICES POLICY & ACCOUNTABILITY COMMITTEE 2 ND SEPTEMBER 2014 SURFACE WATER MANAGEMENT PLAN (SWMP) Report of the Bi-Borough

More information

Floor level for a house on a flood-prone site

Floor level for a house on a flood-prone site Determination No 99/005 Floor level for a house on a flood-prone site 1 THE MATTER TO BE DETERMINED 1.1 The matter before the Authority is a dispute as to whether building consent should be granted for

More information

Frequently-Asked Questions about Floodplains and Flood Insurance FLOOD INSURANCE

Frequently-Asked Questions about Floodplains and Flood Insurance FLOOD INSURANCE Frequently-Asked Questions about Floodplains and Flood Insurance What is a floodplain? The floodplain is any area covered by water during normal water flows, and which could be inundated as a result of

More information

Development at 2 St Albans Road, Kingston, London, KT25HQ

Development at 2 St Albans Road, Kingston, London, KT25HQ Development at SuDS Report. Prepared for: Report prepared by: Dave Alonso Divine Ideas (UK) ltd Date: August 2015 Project/Issue number: Appendices Attached: 1510/01/SuDS A, B & C Divine Ideas (UK) Ltd

More information

London Borough of Newham. Local Flood Risk Management Strategy

London Borough of Newham. Local Flood Risk Management Strategy London Borough of Newham Local Flood Risk Management Strategy Version 5, September 2015 Local Flood Risk Management Strategy for the London Borough of Newham Document Management: Version Control Title:

More information

Strategic Flood Risk Assessment (SFRA) Level 1

Strategic Flood Risk Assessment (SFRA) Level 1 Strategic Flood Risk Assessment (SFRA) December 2007 (Final Issue) London Borough of Brent Brent House 349 High Road, Wembley Middlesex HA9 6BZ EXECUTIVE SUMMARY Introduction 1. The London Borough of Brent

More information

Objective 4: Enhanced community education, flood awareness and preparedness

Objective 4: Enhanced community education, flood awareness and preparedness Objective 4: Enhanced community education, flood awareness and preparedness Understanding the extent and full impacts of flooding is essential for planning for potential future pressures on the drainage

More information

Land claims are now being settled in Canterbury.

Land claims are now being settled in Canterbury. Land claims are now being settled in Canterbury. HERE S A SUMMARY OF THE PROCESS Any damage to the house s foundations is covered by the building claim (not the land claim) Trees and gardens are not covered

More information

Chapter 2 Spatial Portrait

Chapter 2 Spatial Portrait 15 November 2013 Dear Julie Fylde Local Plan to 2030 Part 1 Preferred Options Thank you for the opportunity to meet with you on 9 October in respect of the above mentioned document. As discussed at the

More information

St Bees. Flood Investigation Report 37

St Bees. Flood Investigation Report 37 St Bees Flood Investigation Report 37 Flood Event 30/8/2012 Cumbria County Council Version Undertaken by Reviewed by Approved by Date Preliminary Colin Parkes Anthony Lane 6 Feb 2013 Draft Colin Parkes

More information

Development Management Report

Development Management Report Committee and Date Central Planning Committee 5 th April 2012 Item 13 Public Development Management Report Responsible Officer: Stuart Thomas email: [email protected] Tel: 01743 252665 Fax:

More information

Downspout Disconnection Program FAQs

Downspout Disconnection Program FAQs Why is the Village making downspout disconnection mandatory? A mandatory downspout disconnection has been the law for several years in La Grange Park. All gutter downspouts must be disconnected from the

More information

Environment Agency 0800 807 060. Anglian Water 03457 145 145. Local Authority Contact your own local authority directly for more information.

Environment Agency 0800 807 060. Anglian Water 03457 145 145. Local Authority Contact your own local authority directly for more information. NUMBERS USEFUL Environment Agency 0800 807 060 Anglian Water 03457 145 145 AND CONTACTS DEALING WITH FLOODING FROM Local Authority Contact your own local authority directly for more information. SEWERS

More information

Thames Water key Messages for London Borough of Ealing 25 th October 2005

Thames Water key Messages for London Borough of Ealing 25 th October 2005 Thames Water key Messages for London Borough of Ealing 25 th October 2005 Item 1: Drainage & ownership The area of drainage is complex. Thames Water, the Local Authority, the Environment Agency and property

More information