Los Angeles Metro Rapid
|
|
|
- Dora Thornton
- 9 years ago
- Views:
Transcription
1 Los Angeles Metro Rapid
2 Why BRT In Los Angeles Public dissatisfied with slow bus service Average bus speeds had declined by 10% since late- 1980s LADOT found that 50% of the time a bus is in service it is stopped Metro and City of Los Angeles developed Metro Rapid Program Goal of Rapid to improve bus speeds by 20-25% Did not go in with specific ridership projection Ridership increased followed with improved service 2
3 Metro Rapid Began in June 2000 with two demonstration lines Wilshire/Whittier Ventura Two demo lines resulted in up to a 49% increase in corridor ridership Up to an average 29% improvement in bus travel times 1/3 of the ridership were new to transit, 1/3 from other parallel corridors, and another 1/3 from existing corridor riding more often 3
4 Metro Rapid Attributes 1. High Capacity Buses 2. Branded Buses and Stations 3. Bus Signal Priority 4. Frequent Service 5. Simple Route Alignment 6. Less Frequent Stops 7. Integrated with Local Bus Service 8. Level Boarding and Alighting 9. Exclusive Lanes 10. Off-vehicle Fare Payment Primary Attributes Expansion Attributes 4
5 High Capacity Buses All buses CNG powered 60-foot low floor articulated buses with 3 doors and 57 seats Also use low floor 45-foot buses with 46 seats 5
6 Branded Stations 6
7 Metro Rapid Rapid began as new service in addition to local service on two demo corridors Allowed customers to choose and adjusted Local/Rapid service levels accordingly Later tried to implement Rapid cost neutral Consent Decree later allowed no more than 1/3 of local service on corridor to become Rapid 7
8 Bus Signal Priority Metro uses two bus signal priority systems that reduce bus delay and assist in maintaining bus spacing Majority of routes use loops and transponders A few routes with large segments outside the City of Los Angeles use an onboard computer that requests bus signal priority via wireless communications MTA Page 8
9 Passenger Information Real-time next bus information at stations 9
10 Metro Rapid Bus Stops Local bus stop spacing averages every.2 miles Metro Rapid stop spacing averages every.7 miles Metro Light Rail average station spacing every 1.0 miles Metro Heavy Rail average station spacing every 1.2 miles Metro Rapid stops typically busiest bus stops on route Minimum of 250 daily boardings at stop 10
11 Where We Are Today Regional network is nearly complete 21 Metro Rapid Corridors operated by Metro 3 additional Rapid corridors operated by two Municipal Operators Approximately 400 Peak Buses Nearly 400 miles through 33 cities 1,500 intersections with Bus Signal Priority Passenger travel times improved by an average of 20% over local service Corridor Ridership has increased on those corridors with Metro Rapid service 51% of all system bus boardings are in Rapid corridors 11
12 What s Next Exclusive bus lanes Board approved Wilshire BRT Project in May 2011 Off-vehicle fare payment Beginning Countywide Bus Lane Study that will also look at operational measures to improve bus speeds 12
13 Wilshire BRT Project Goals Improve bus passenger travel times (24%). Improve bus service reliability (32%). Improve traffic flow along Wilshire Boulevard. Repave the curb lanes along damaged portions of Wilshire Boulevard. Encourage shift from automobile use to public transit (increase in ridership of 15-20%). Improve air quality in Los Angeles County. Minimize impacts to existing on-street parking. 13
14 Typical Wilshire Operation Today
15 Future Wilshire Operation 15
16 Wilshire BRT Project Just completed environmental analysis in May 2011 Wilshire Boulevard from MacArthur Park to Santa Monica City Line Project length 12.7 miles within City & County of L.A. Includes 7.7 miles of dedicated peak period bus lanes Buses would operate with mixed flow traffic where no bus lanes Bus lanes operate in weekday peak periods 7:00 am to 9:00 am and 4:00 pm to 7:00 pm Right-turning autos and bikes allowed Buses restricted to curb lanes except to pass when necessary 16
17 Wilshire BRT Project, contd. Other Improvements to corridor Traffic signal improvements (enhanced TPS, left-turn arrows) Turn lanes Selective street widening & street resurfacing/repaving 17
18 Wilshire BRT Project 18
19 Countywide BRT & Street Design Study August 2011 Board directed staff to study minimum of 5 BRT corridors including dedicated bus lanes Began RFP process for consultant to help with study Study will identify corridors that can accommodate dedicated peak period bus lanes & other bus speed improvements Study will also look at street design improvements around bus stops/stations Study will also include operational strategies such as all door boarding Dwell times on Metro Orange Line with pre-paid fares is half the time as Rapid Study to be completed by October
20 Questions 20
When is BRT the Best Option? 1:30 2:40 p.m.
TRB/APTA 2004 Bus Rapid Transit Conference When is BRT the Best Option? 1:30 2:40 p.m. Paul Larrousse Director, National Transit Institute (NTI) (Moderator) TRB/APTA 2004 Bus Rapid Transit Conference Session
Evaluation Criteria and Mode Progression for RouteAhead Rapid Transit Projects
Evaluation Criteria and Mode Progression for RouteAhead Rapid Transit Projects C2012-0684 ATTACHMENT 2 The RouteAhead draft 30-year rapid transit plan was developed in coordination with the Investing in
Light Rail Transit in Phoenix
4. Presentation and Discussion: Phoenix Light Rail Implementation Wulf Grote Planning and Development Director, Phoenix Valley Metro Light Rail Transit in Phoenix Broadway Citizen s Task Force February
transit service policy july 2012
transit service policy july 2012 TABLE OF CONTENTS SECTION 1: INTRODUCTION, PURPOSE & BACKGROUND 3 1.1 Introduction 3 1.2 Purpose 4 1.3 Background 5 SECTION 2: DESIGNING A REGIONAL TRANSIT NETWORK 7 2.1
Mount Royal College Transit Service Plan
Mount Royal College Transit Service Plan Background In 2007 November response to Council Report C2007-78 West LRT Alignment, Budget and Project Delivery, Council directed the Administration to report back
Montgomery County Bus Rapid Transit System Information Technology Needs
Montgomery County Bus Rapid Transit System Information Technology Needs Department of Technology Services Department of Transportation Montgomery County Government, MD 3/7/2012 2011 by Montgomery County
Near Westside Neighborhood and University Avenue Corridor Transportation Study. Public Workshop #2. September 12 and 23, 2013
Near Westside Neighborhood and University Avenue Corridor Transportation Study Public Workshop #2 September 12 and 23, 2013 Presentation Outline: Brief Review of Study Scope, Background, and Current Conditions
BRT BUS RAPID TRANSIT SERVICE DESIGN GUIDELINES
BRT BUS RAPID TRANSIT SERVICE DESIGN GUIDELINES TABLE OF CONTENTS 1. Vision Statement...1 2. Modal Overview...1 3. Planning and Implementation Process...4 4. BRT Policies...4 4.1 BRT System Performance
Date August 28, 2013
Date August 28, 2013 To From Subject San Fernando Valley Service Council Scott Page, Service Planning Manager Staff s Review of Past Chair Kymberleigh Richards Email, Proposed Resource Recovery Strategies
MEMORANDUM. Robert Nichols, Acting Corridor Design Manager Northgate Link Extension
MEMORANDUM DATE: September 23, 2014 TO: Robert Nichols, Acting Corridor Design Manager Northgate Link Extension FROM: SUBJECT: COPIES: Katherine Casseday, PE, PTOE, Casseday Consulting Tony Lo, PE, Parsons
National Bus Rapid Transit Institute (NBRTI) At the University of South Florida
National Bus Rapid Transit Institute (NBRTI) At the University of South Florida History of the NBRTI In January 2001, the National BRT Institute was created at USF s Center for Urban Transportation Research
d r a f t Division Street: 15.4 du/a Damen Avenue: 14.1 du/a Western Avenue: 12.8 du/a
Transit [take transit: We live in the City, people. We can t expect to have parking. ] The ability of people to travel by transit is not only an equity issue, it is a matter of economic vitality for the
Transitways and the RouteAhead for Calgary Transit
Transitways and the RouteAhead for Calgary Transit Chris Jordan, P.Eng., M.Sc., Manager, Strategic Planning, Calgary Transit, Transportation, City of Calgary Jen Malzer, P.Eng., M.Sc., Senior Transit Planner,
Measuring the Street:
Measuring the Street: New Metrics for 21st Century Streets 1 Measuring the Street: New Metrics for 21st Century Streets New York City s streets are constantly called on to the meet new and varied needs
Los Angeles County Metropolitan Transportation Authority. (Metro) Advanced Transportation Management System (ATMS) Overview
Los Angeles County Metropolitan Transportation Authority Los Angeles County Metropolitan Transportation Authority (Metro) Advanced Transportation Management System (ATMS) Overview June, 2010 ATMS is Supported
Bus Priority Measures in Calgary: Past, Present and Future. Chris Jordan, M.Sc., P.Eng., Coordinator, Strategic Transit Planning, Calgary Transit
Bus Priority Measures in Calgary: Past, Present and Future Chris Jordan, M.Sc., P.Eng., Coordinator, Strategic Transit Planning, Calgary Transit Nora Kajdy, P.Eng., Transit Priority Engineer, Calgary Transit
Bus Rapid Transit Service Design
APTA STANDARDS DEVELOPMENT PROGRAM RECOMMENDED PRACTICE American Public Transportation Association 1666 K Street, NW, Washington, DC, 20006-1215 APTA BTS-BRT-RP-004-10 Approved October, 2010 APTA Bus Rapid
ORANGE COUNTY TRANSPORTATION AUTHORITY. Final Long-Range Transportation Plan - Destination 2035. Attachment A
ORANGE COUNTY TRANSPORTATION AUTHORITY Final Long-Range Transportation Plan - Destination 2035 Attachment A DESTINATION 2035 DESTINATION 2035 EXECUTIVE SUMMARY ATTACHMENT A Moving Toward a Greener Tomorrow
Improving Access in Florida International University Biscayne Bay Campus Executive Summary
EXECUTIVE SUMMARY Improving Access in Florida International University Biscayne Bay Campus Executive Summary Prepared for: Miami-Dade County Metropolitan Planning Organization (Miami-Dade MPO) Prepared
Overview of the Travel Demand Forecasting Methodology
Overview of the Travel Demand Forecasting Methodology Prepared by the Central Transportation Planning Staff (CTPS) Authors: Scott A. Peterson, Manager Ian Harrington, Chief Planner March 29, 2008 1 OVERVIEW
Mayors Welcome Strong Surrey Votes Yes Coalition Support. Yes Vote Would Vastly Improve Transit and Transportation in Fast Growing City
Mayors Welcome Strong Surrey Votes Yes Coalition Support Yes Vote Would Vastly Improve Transit and Transportation in Fast Growing City February 11, 2015 Vancouver, BC The Mayors Council on Regional Transportation
SWANSEA METRO PROJECT (BUS RAPID TRANSIT) Gwyn Ephraim Arup David Whitehead City and County of Swansea
SWANSEA METRO PROJECT (BUS RAPID TRANSIT) Gwyn Ephraim Arup David Whitehead City and County of Swansea 1. INTRODUCTION 1.1 Background In the last decade a new 'intermediate' form of public transport has
Frequently Asked Questions (FAQs) about DART
Frequently Asked Questions (FAQs) about DART What is DART? Where can I take the bus? Where can I take the train? How much does it cost to park at a station? Can I take a train to American Airlines Center?
5.0 FINANCIAL ANALYSIS AND COMPARISON OF ALTERNATIVES
5.0 FINANCIAL ANALYSIS AND COMPARISON OF ALTERNATIVES 5.1 FINANCIAL ANALYSIS The cost of a transportation investment falls into two categories: capital costs, and operating and maintenance (O&M) costs.
MANAGEMENT PLAN. Fiscal Year 2015-2016
MANAGEMENT PLAN Fiscal Year 2015-2016 May 6, 2015 Table of Contents I. Executive Summary... 2 Omnitrans Vision... 5 Omnitrans Mission Statement... 5 II. Strategic Initiatives... 5 Implementation... 6 Strategic
Addendum to the Arterial Transitway Corridors Study
January 2013 1 Addendum to the Arterial Transitway Corridors Study The Arterial Transitway Corridors Study (ATCS) evaluated and prioritized arterial bus rapid transit (BRT) improvements to nine corridors
FY16 Budget Public Forum. Saturday, April 25, 2015
FY16 Budget Public Forum Saturday, April 25, 2015 Metro is Everywhere Metro is a lot more than buses and trains. Anyone who has boarded a bus or a train, driven on the freeway, used the toll roads, stopped
LRT LIGHT RAIL TRANSIT SERVICE GUIDELINES
LRT LIGHT RAIL TRANSIT SERVICE GUIDELINES LIGHT RAIL TRANSIT SERVICE GUIDELINES LIGHT RAIL TRANSIT SERVICE GUIDELINES TABLE OF CONTENTS 1. Vision Statement...1 2. Modal Overview...1 3. Planning and Implementation
Proposed Service Design Guidelines
Proposed Service Design Guidelines July 2015 I. Introduction During Phase II of the Reimagining CityBus project, feedback from public outreach and data analysis conducted during Phase I of the project
TABLE OF CONTENTS TABLES FIGURES
TABLE OF CONTENTS Introduction...1 1. On-Site Stacking...2 2. Number of School Driveways...2 3. School Driveway Standards...3 3A. Driveway Spacing...3 3B. Driveway Location...4 3C. Driveway Lane Widths
CHAPTER 5-CMPO TRANSPORTATION VISION PLANS (2035 & BEYOND)
Regional Transportation Plan 2035 28 CHAPTER 5-CMPO TRANSPORTATION VISION PLANS (2035 & BEYOND) The Cache Transportation Vision Plan shows roadway, bicycle, transit and pedestrian projects that attempt
Strategic Regional Transit Plan
Strategic Regional Transit Plan December 2008 Chapter 6: Run Time nalysis (Chapter 6 originally prepared October 2007) RUN TIME NLYSIS TLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 SCREEN TWO LTERNTIVES...
Best Practice: Bus Rapid Transit (BRT) System
REPORT UPDATED: MAY 4, 2012 CITY: JAKARTA POLICY AREAS: CLIMATE CHANGE; TRANSPORTATION BEST PRACTICE TransJakarta is a bus rapid transit (BRT) system designed to provide the citizens of Jakarta with a
Transit Service Assessment
Technical Memorandum #1 Transit Service Assessment June 213 Table of Contents 1. Existing Service Summary... 1 1.1 Service Overview... 1 1.2 Service Characteristics... 1 2. Ridership and Productivity...
TRAIN WRAPS TIMETABLE ADS TICKETS STATION POSTERS METROLINK MATTERS NEWSLETTER STATION SAMPLING WEBSITE: METROLINKTRAINS.COM
METROLINK MATTERS TIMETABLES METROLINKTRAINS.COM HOW-TO-RIDE GUIDE DESTINATION GUIDE TICKETS TRAIN WRAPS STATION POSTERS ON-BOARD BANNERS & POSTERS STATION SAMPLING ADVERTISING RATES & INFORMATION METROLINK
College of Southern Maryland. Hughesville Transportation Study
College of Southern Maryland Project Overview Existing Conditions Transit Service Land Use CSM Student Demographics Recommendations Methodology Transit Recommendations Transportation Demand Management
4.5 TRANSPORTATION, TRAFFIC AND SAFETY
4.5 TRANSPORTATION, TRAFFIC AND SAFETY This section provides an overview of transportation and traffic and evaluates the operational and construction impacts associated with the proposed project and its
ExpressLanes CAG Summit. March 2, 2010
ExpressLanes CAG Summit March 2, 2010 1 Project Goals Move More People, Not More Vehicles > Increase Throughput of HOT lanes > Effectiveness (Mode Shift) > Efficiency (Cost of Project Relative to Benefits)
PAPS- LA. http://discoverlosangeles.com/ http://en.wikipedia.org/wiki/los_angeles
PAPS- LA Know more about the City of Los Angeles at : http://www.lacity.org/index.htm http://discoverlosangeles.com/ http://en.wikipedia.org/wiki/los_angeles 1. Which official documents do you need to
Applying for Access. Access Services. What is Access?
Access Services Applying for Access > Access Services overview > Eligibility criteria > Other transportation options > How to get Access What is Access? Access Services is a public transit agency dedicated
2012 King County Metro Transit Peer Agency Comparison on Performance Measures
2012 Peer Agency Comparison on Performance Measures Department of Transportation Metro Transit Division King Street Center, KSC-TR-0415 201 S. Jackson St Seattle, WA 98104 206-553-3000 TTY Relay: 711 www.kingcounty.gov/metro
Metro Met..,.u... T,...,...,...,
~ ""... c,., Metro Met..,.u... T,...,...,..., One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2ooo Tel metro. net 37 EXECUTIVE MANAGEMENT COMMITTEE MARCH 20,2014 SUBJECT: ACTION: INNOVATIVE WAYS TO
Metropolitan Setting l
Metropolitan Setting l GENERAL CHARACTERISTICS Los Angeles lies at the heart of one of the most complex metropolitan regions in the United States. As a major center of commerce, finance, and industry in
Questions and Answers about the Orange Bus/Rail Investment Plan
Why are transit improvements needed? Questions and Answers about the Orange Bus/Rail Investment Plan The Triangle Region is now home to 1.5 million people. The U.S. Census and the 2035 Joint Long Range
CAPACITY AND LEVEL-OF-SERVICE CONCEPTS
CHAPTER 2 CAPACITY AND LEVEL-OF-SERVICE CONCEPTS CONTENTS I. INTRODUCTION...2-1 II. CAPACITY...2-2 III. DEMAND...2-2 IV. QUALITY AND LEVELS OF SERVICE...2-2 Service Flow Rates...2-3 Performance Measures...2-3
Expo Light Rail Line. Expo Board Presentation Monthly Project Status Update May 7, 2015
Expo Board Presentation Monthly Project Status Update May 7, 2015 Expo Phase 1 Phase 1 Project Status Closeout Status Completing Closeout of Remaining Elements of Work Final As-Builts nearing completion
Get Connected with Metro-North
Metro-North s Deals&Getaways! GOING TO AN AIRPORT? Get Connected with Metro-North 8/14 For more information visit us online at www.mta.info/ mnr. GET CONNECTED WITH METRO NORTH Take Metro-North to New
Lincoln Downtown Master Plan Update
Lincoln Downtown Master Plan Update Table of Contents Executive Summary........................................... 1 Complete Streets Framework.................................... 3 Promenade Creating
Multi Modal Roadway Transportation Impact Fees and Asset Value
January 2010 SB 360 Article Series: Factors to be Considered in Transitioning from a Road Impact Fee to a Mobility Fee Contributing Authors: Steven A. Tindale, P.E., AICP Robert P. Wallace, P.E., AICP
URBAN PUBLIC TRANSPORT PLANNING IN TEHRAN AND THE OUTCOME OF THE IMPLEMENTED BRT LINES
United Nations Forum on Climate Change Mitigation, Fuel Efficiency and Sustainable Urban Transport URBAN PUBLIC TRANSPORT PLANNING IN TEHRAN AND THE OUTCOME OF THE IMPLEMENTED BRT LINES S. MEHDI TASHAKKORI
Ne w J e r s e y Tr a f f i c Co n g e s t i o n :
Ne w J e r s e y Tr a f f i c Co n g e s t i o n : A Growing Crisis January 2008 Cover photo : Route 3, Passaic County introduction A rising tide of traffic congestion threatens to increase roadway gridlock,
in Marina Del Rey Prepared by: County of Los Angeles Department of Public Works
Planned Public Works Projects in Marina Del Rey Prepared by: County of Los Angeles Department of Public Works Planned Projects in Marina Del Rey Waterline Projects Phase II Phase III Roadway Projects Admiralty
7.0 Transportation Management
7.0 Transportation Management I. Introduction The Kansas City region has invested considerable effort and resources in the design and implementation of its regional multimodal transportation system. As
GREAT STREETS FOR LOS ANGELES
GREAT STREETS FOR LOS ANGELES STRATEGIC PLAN City of Los Angeles Department of Transportation 1 2 OFFICE OF THE MAYOR City of Los Angeles 200 N Spring St Los Angeles, CA 90012 wwwlamayororg @LAMayorsOffice
30 Years of Smart Growth
30 Years of Smart Growth Arlington County s Experience with Transit Oriented Development in the Rosslyn-Ballston Metro Corridor A Presentation by the Arlington County Department of Community Planning,
~ Metro Metrapolita Tnnsportation Authority
~ Metro Metrapolita Tnnsportation Authority One Gateway Plaza Los Angeles, CA 90012-2952 213-922.2000 Tel metro. net EXECUTIVE MANAGEMENT COMMITTEE OCTOBER 16, 2014 SUBJECT: ACTION: CUSTOMER EXPERIENCE
Traffic Signal Priority (TSP) and Automatic Vehicle Tracking System (AVTS) For Calgary Transit Buses
Traffic Signal Priority (TSP) and Automatic Vehicle Tracking System (AVTS) For Calgary Transit Buses (Project #2001-06) Calgary Transit Transit Planning 2004 July Introduction The purpose of this report
March 2015 Prepared by the Department of Finance & Performance Management. 2013 Regional Peer Review PERFORMANCE MEASURES
March 2015 Prepared by the Department of Finance & Performance Management 2013 Regional Peer Review PERFORMANCE MEASURES CONTENTS CONTENTS... 1 EXECUTIVE SUMMARY... 2 SNAPSHOT... 4 PEER SELECTION... 5
Wilmington to Newark Commuter Rail Improvement Project
Wilmington to Newark Commuter Rail Improvement Project The Delaware Transit Corporation (DTC), a subsidiary of the Delaware Department of Transportation (DelDOT), is undertaking a rail capacity expansion
Memo. Date: January 18, 2013. StarTran Advisory Board. From: Brian Praeuner. Review of Peer Transit Systems
Memo Date: January 18, 2013 To: StarTran Advisory Board From: Brian Praeuner Re: Review of Peer Transit Systems This memo is in response to the StarTran Advisory Board s request for additional information
Integrated Public Transport Service Planning Guidelines. Sydney Metropolitan Area
Integrated Public Transport Service Planning Guidelines Sydney Metropolitan Area December 2013 CONTENTS 1. INTRODUCTION 3 1.1 Purpose 3 1.2 Background 3 1.3 Travel in Sydney Metropolitan Area 5 1.4 Objectives
ATTACHMENT TO NOTICE TO FIXED GUIDEWAY SYSTEM VEHICLE SUPPLIERS REQUEST FOR INFORMATION (RFI 001)
ATTACHMENT TO NOTICE TO FIXED GUIDEWAY SYSTEM VEHICLE SUPPLIERS REQUEST FOR INFORMATION (RFI 001) INTRODUCTION To supplement and expand its understanding of available fixed guideway transit system vehicle
Monitoring Program Results and Next Steps
8 Monitoring Program Results and Next Steps The improving economy and greater levels of employment observed in 2014 have generally resulted in higher demands on the transportation network. This is apparent
A smart mobile fare collection system for public transit
A smart mobile fare collection system for public transit A W A R D S Powerful Answers Award HopOn s Unique Solution HopOn is a unique solution that can be easily integrated in every form of public transit:
FREDericksburg Regional Transit (FRED) REAL-TIME SCHEDULING SOFTWARE, BUS STOP ANNUNCIATOR AND TRANSIT WEBSITE PROCUREMENT
FREDericksburg Regional Transit (FRED) REAL-TIME SCHEDULING SOFTWARE, BUS STOP ANNUNCIATOR AND TRANSIT WEBSITE PROCUREMENT Technical Memorandum and Concept of Operations Prepared for: Prepared by: March
Integrated Public Transport Control Systems Information Day
Integrated Public Transport Control Systems Information Day www.wyg.com creative minds safe hands Tender Procedure 1 Integrated Package Electronic Ticketing AVL / RTPI On-bus CCTV Intersection CCTV / Bus
Item No. 11.1.4 Halifax Regional Council January 14, 2014
Item No. 11.1.4 Halifax Regional Council January 14, 2014 TO: Mayor Savage and Members of Halifax Regional Council SUBMITTED BY: Richard Butts, Chief Administrative Officer DATE: December 18, 2013 Mike
Florida Avenue Multimodal Transportation Study. June 19, 2013
Florida Avenue Multimodal Transportation Study June 19, 2013 Today s Agenda Team & project introduction Project Timeline What you said Tools we use Mapped data and what clues it can provide Highlights
Technical Memorandum PERFORMANCE MEASURES. Prepared by:
Technical Memorandum PERFORMANCE MEASURES Prepared by: March 2014 TABLE OF CONTENTS Executive Summary... 1 1. Introduction... 2 1.1 Performance Measures and the Public Sector... 2 1.2 National Focus: MAP
CHAPTER 7 TRANSPORTATION MANAGEMENT/ INTELLIGENT TRANSPORTATION SYSTEMS
CHAPTER 7 TRANSPORTATION MANAGEMENT/ INTELLIGENT TRANSPORTATION SYSTEMS Introduction Transportation Management is an integral part of managing the existing transportation system to enhance the capacity
Transportation Alternatives
1 Transportation Alternatives Transportation alternatives involve a variety of components: Location Alternatives - when and where service is provided - general location as well as level of service on the
ExpressPark - An Intelligent Parking Management System for Downtown Los Angeles
ExpressPark - An Intelligent Parking Management System for Downtown Los Angeles Daniel Mitchell, P.E., PTOE and Peer Ghent, P.E. Abstract Partnering with Metro and Caltrans, the City of Los Angeles Department
Appendix J Santa Monica Travel Demand Forecasting Model Trip Generation Rates
Appendix J Santa Monica Travel Demand Forecasting Model Trip Generation Rates SANTA MONICA TRAVEL DEMAND FORECASTING MODEL TRIP GENERATION RATES SUBMITTED BY: 201 Santa Monica Blvd., Suite 500 Santa Monica,
Multi-Modal Corridor Degree of Complexity: High Cost/Benefit: High
Multi-Modal Corridor Degree of Complexity: Cost/Benefit: Maintain the same level of service for Ensures continuous flow through the Might impact other transportation Consider road diet and/or different
Transit Technology Alternatives
Transit Technology Alternatives Fixed Guideway Systems (see http://www.apta.com/research/info/define/index.cfm) Heavy rail - HR Heavy Rail is a system that is totally separated from its surroundings and