1 Technical Assignment 1: Construction Project Management October The Salamander Resort and Spa Paul Roberts
2 TABLE OF CONTENTS EXECUTIVE SUMMARY... 1 LOCAL CONDITIONS... 2 CLIENT INFORMATION... 3 BUILDING SYSTEMS SUMMARY... 4 PROJECT COST EVALUATION... 6 PROJECT SCHEDULE SUMMARY PROJECT DELIVERY SYSTEM STAFFING PLAN APPENDIX A: D4COST ESTIMATE APPENDIX B: R.S. MEANS 2009 REFERENCE PAGES APPENDIX C: PROJECT SCHEDULE SUMMARY APPENDIX D: SITE PLAN OF EXISTING CONDITIONS... 20
3 EXECUTIVE SUMMARY Technical Assignment 1 summarizes the existing conditions and construction management methods utilized on The Salamander Resort and Spa. This report is broken up into eight sections, each of which is briefly described below. This report includes an analysis of the local conditions of the site and some issues that are prevalent to the contractor. The next section gives some background information on the owner of the project. The owner is very involved and focused on the resulting quality of the building. The building systems overview outlines the types of systems present and issues surrounding the construction. Two different project cost estimates were performed, a parametric and a square foot. These two estimates vary significantly with the actual project cost but the differences are justified in the analysis. A summary schedule highlights the major activities and milestones through the life of the project. The existing site conditions plan outlines the building footprint, utilities, and pedestrian/vehicular traffic flow. Finally, a project delivery organizational plan and on site staffing plan is included. These help to familiarize you with the people and companies involved. The Salamander Resort and Spa, owned by Salamander Hospitality, is being constructed as a luxury high end resort. Located less than 40 miles from Washington D.C., they hope to bring in guests looking for a weekend vacation. The main building is one story above grade with an attached four story guest house that lodges all the rooms. The joined basement houses all the service rooms and mechanical spaces. The project duration is four years and will cost approximately $93 million. The building exterior is a combination of stone veneer and stucco. Turner Construction is contracted with the owner through a cost plus fee and GMP. Turner holds lump sum contracts with all subcontractors while the owner hold contracts with all the architects, engineers, and consultants. The Salamander Resort is looking to become the first Resort of its kind to be LEED Certified. 1
4 LOCAL CONDITIONS Figure (1) Figure (2) The project is located in the town of Middleburg, Virginia on route 50, about 40 miles west of Washington D.C. and 120 miles north of Richmond (Figure 1). Figure (2) shows the site boundary in blue and the resort location in red. Preferred Methods of Construction: Much of the residential properties in old town Middleburg are masonry and brick construction. To match this look, Salamander Resort uses a stone façade on the main entrance area. Construction Recycling: All recycling is collected on site and removed by a third party company to a local recycling plant. Tipping Fee: In 2008, the tipping fee in Loudon County is $60/ton. (Loundon County Solid Waste Management Planning District) Soil Type: The regional soil consists of a blend of deep, well drained, silty soils and clays. During footing excavation, the subsurface water level was not reached. 2
5 CLIENT INFORMATION Salamander Hospitality is a company formed in 2005 in part by the current CEO Sheila Johnson. Her goal is to grow the company by acquiring one of a kind properties and managing them to provide an unforgettable experience. Salamander Hospitality specializes in the management of luxury resorts and hotels, like the Salamander Resort and Spa. Their focus on owner and customer satisfaction is what drives this company. Salamander Hospitality also owns and manages the Innisbrook Resort and Golf Club in Florida and the Woodlands Inn in South Carolina. Both of these properties reflect the mission that Salamander Hospitality set out to achieve. Owner Expectations: Cost: Most of the funding for this project comes directly from Salamander Hospitality. The high end nature of this project can lead to changes in interior and exterior finishes throughout the project and it is one of the goals of the contractor to minimize the cost impact of these. Quality: The owner is looking for a very high quality finished product that will serve the needs of her client base. Only the finest fixtures, furniture, and wood details are used. This requires the contractor to provide special attention to the installation process in order to ensure the best looking product. Schedule: The owner had initially set a Spring 2010 completion date but has since pushed that back to Spring This has provided the contractor with significant float time, and allows for easier trade coordination. Safety: It is critical that the contractor provide a safe environment for all the workers on site. 3
6 BUILDING SYSTEMS SUMMARY Building Systems Summary Yes No Work Scope Issues X Demolition required? X Structural steel frame Mobile crane for erection X Cast in place concrete Crane and bucket placement. Wood formwork X Precast concrete X Mechanical system Mechanical room located in basement of main building, northeast corner. Dry sprinkler system X Electrical system Main 3200A 480/277 3 phase 4W and secondary120/208v 3 phase 4W X Masonry Stone veneer on main building at entrance X Curtain wall X Support of excavation Excavation: All foundations should be a minimum of 36 below grade Building spread and strip footings shall bear on undisturbed natural soils or compacted fill with a bearing pressure of 3500 psf. Utility lines shall not be placed through of below foundations without structural engineer s approval Concrete: A 3000 psi reinforced concrete was used for 5 interior slab on grade The guest house utilized 9 and psi post tensioned reinforced concrete on metal deck with continuous welded wire fabric. Typical 16x28 reinforced concrete columns utilized in guest house. Structural Steel: Rolled shapes and Round HSS Shapes ASTM A992, ASTM A gage Lok Floor composite metal decking used in the guest house 1 ½ deep, wide rib, 20 gage galvanized roof decking used for both the guest house and main building Lightgage steel roof trusses with 8 lightgage purlin at 48 on center 4
7 Mechanical System: 15 main AHU s, 9 Variable Frequency Drive (VFD) and 6 Constant Volume (CV) 6 heat recovery AHU s. 3 located in the main lodge, 2 in the spa, and 1 in the laundry room 1950 gpm cooling tower located on the main roof serves chillers 1 3 Mechanical room located in basement in north east corner Electrical System: From utility, main 3200A 480/277V 3 phase 4W switchboard with secondary 120/208V 3 phase Uninterrupted Power Supply (UPS) for 4 th floor guest house and 1 st floor main building Indoor emergency diesel generator (650kW 480/277V 3 phase 4W) Custom designed light fixtures and chandeliers LEED Design Features: Green slate roofing made from recycled rubber and PVC piping Minimize irrigation by using native plants and species Maximize opportunity to use building materials made from recycled products Use low emitting paints, carpets, and window treatments Protection procedures in place to conserve 250 of the 340 acres 5
8 PROJECT COST EVALUATION Actual Costs Construction Cost $ 93,802, Construction Cost/SF $ Total Project Cost Estimate $ 135,280, Total Project Cost Estimate/SF $ Building Systems Costs (Cost and Cost/SF) Building System Cost Cost/SF Excavation and Fill $ 277,443 $ 1.21 Building Concrete $ 7,191,105 $ Structural Steel and Metal Deck $ 2,023,292 $ 8.83 Plumbing $ 13,766,120 $ Electric $ 10,674,385 $ Finish Carpentry & Architectural Millwork $ 4,120,000 $ Windows, Doors, and Glazing $ 1,285,355 $ 5.61 Gypsum Drywall Work $ 5,911,608 $ General Requirements $ 1,893,275 $ 8.26 The Total Project Cost Estimate includes land, design/consultant fees, furniture, fixtures, equipment, and development/marketing in addition to construction costs. The Turner Construction Project Manager on site estimated all these additional costs because the owner did not release the official data. As seen in the chart, the most expensive systems in the building are the plumbing and electric. 6
9 D4Cost Estimating See Appendix A for the detailed D4Cost Estimate The D4Cost estimate was calculated by selecting two similar projects in the database and combining their attributes into one estimate. The closest projects that D4 had in the database were motel/hotels. I chose The Hampton Inn and Suites Hotel because it is a high end hotel located in Chicago. The Inn on Lake Superior is more similar because of the amenities offered but does not come close to the luxury that the Salamander Resort offers. Projects Used in D4 Cost Estimate Use Project Name Size (SF) Floors Building Cost Hotel/Motel Hampton Inn and Suites Hotel 162, $ 13,797,591 Hotel/Motel The Inn on Lake Superior 65,345 3 $ 4,073,012 Parametric D4Cost Estimate Division Name Percent Sq. Cost Amount 0 Bidding Requirements 7.22 $ 9.60 $ 2,200,317 1 General Requirements 3.75 $ 4.99 $ 1,144,345 2 Site Work 4.08 $ 5.42 $ 1,242,343 3 Concrete $ $ 6,400,073 4 Masonry 6.09 $ 8.09 $ 1,855,012 5 Metals 1.56 $ 2.07 $ 475,578 6 Wood & Plastics 4.78 $ 6.36 $ 1,457,405 7 Thermal & Moisture Protection 1.91 $ 2.54 $ 581,897 8 Doors & Windows 6.39 $ 8.50 $ 1,947,182 9 Finishes $ $ 3,467, Specialties 0.35 $ 0.47 $ 107, Equipment 0.09 $ 0.12 $ 26, Furnishings 0.05 $ 0.06 $ 13, Special Construction 0.68 $ 0.90 $ 206, Conveying Systems 2.49 $ 3.31 $ 758, Mechanical $ $ 5,978, Electrical 8.60 $ $ 2,620,616 Total Building Costs $ $ 30,483,633 7
10 The D4Cost estimate reported at $132.99/SF with a total project cost of $30,483,633. This value is approximately one third of the actual project cost. This significant difference is due in part to the use of the building. The D4 projects are mainly hotel oriented while the Salamander project is a full resort with spa, restaurant, guest rooms, and horse stables/pastures. The Hampton Inn utilizes precast concrete, whereas The Salamander Resort does not. If the three projects had more similar structural, mechanical, and electrical systems the estimate would be closer. The amount of custom interior work, lighting fixtures and woodwork, found on this project also contributes to the difference. 8
11 R.S. Means Square Foot Estimate: See Appendix B for the reference pages from R.S. Means 2009 The following R.S. Means square foot estimate is based off M.350: 4 7 Story Hotel with Face Brick and Concrete Back Up. The costs are calculated using an area of 229,213 square feet and 2,828 perimeter. Basement addition along with height, perimeter, and location adjustments were used. A majority of the structural framing is done with reinforced concrete. Exterior Wall Face Brick with Concrete Block Back up S.F. Area 195,000 L.F. Area 850 Steel Frame $ R/Conc. Frame $ Story Height Adjustment: = 1.75 $1.25/ft * (1.75) = $2.19/sq. ft. Perimeter Adjustment: = $1.75/100 ft * (1978 ) = +$34.62 Basement Addition: +$32.20/sq ft Sub Total Per Square Foot Estimate: = $226.61/sq ft. Project Location Adjustment Arlington, Virginia is the closest location listed in RS Means. $ * 0.93 = $210.75/sq ft. Sub Total Construction Cost $210.75/sq ft. * (229,213 sq ft.) = $48,306,640 9
12 Common Additives: (5) 5000 lb. capacity $170,700 each +$853,500 (1) Security camera and $1850 and (37) additional $1000 each +$38,850 (4) 125 lb. $32,800 each +$131,200 (1) 50 lb. $12,200 each +$12,200 (2) Laundry $66,500 each +$133,000 (1) Laundry $35,500 each +$35,500 Common Additives Total = +$1,204,250 Total Construction Cost: $48,306,640 + $1,204,250 = $49,510,890 $216.00/SF The R.S. Means square foot estimate is about $45 million less than the actual project cost. Part of this difference can be attributed to using a hotel as the basis for the estimate, as R.S. Means does not have a category for resorts. Another reason for the difference comes in the façade, R.S. Means uses Face Brick with Concrete Clock Back Up while The Salamander Resort uses a stone veneer and stucco. Other discrepancies were discussed in the analysis of the D4Cost estimate. The R.S. Means estimate for this project is more accurate than the D4Cost estimate partly because the Means estimate is more tailored to this project, while the D4 Cost is based off other buildings. While neither estimate had a good basis for comparison, the R.S. Means estimate is would be fairly accurate if it included more of the specialty items and finishes found in The Salamander Resort. 10
13 PROJECT SCHEDULE SUMMARY See Appendix C for the Project Schedule Summary Turner Construction was awarded the construction contract from Salamander Hospitality to construct The Salamander Resort and Spa. The project was originally planned to be completed in March 2010, but was pushed back one year per the owner s request. This allowed Turner to spread out the trades and even put several on hold. For example, all interior framing was completed by January 2009 but drywall and rough ins were put on hold for 11 months to accommodate the new schedule. It also leads to less congestion on site due to fewer trades having to work simultaneously. Foundation The total duration of the foundation work was approximately 6 months. The foundation consisted of reinforced concrete spread footings excavated down to a minimum of 36 inches below the slab on grade. No formwork was needed because the excavation holes were dug to the correct footing size. Structural Superstructure for The Salamander Resort and Spa took about 6 months to complete. It consisted of both concrete and steel framing. The basement and guest wing have concrete framing throughout and the main building has steel framing on the first floor. This created challenges in the schedule when both concrete and steel were being installed simultaneously. Finishes Turner has allocated a large amount of time to the finishes due to the complexities of the project. A majority of the fixtures are custom designed for this project and are more likely to require additional time to install. Like many of the activities, finishes would be able to finish in less time than the allotted if the schedule was optimized for time. 11
14 PROJECT DELIVERY SYSTEM The project delivery method used is a design build. A design build method was chosen because a large portion of the lighting system and custom interior work was not designed at bid time. When Turner took over the project in 2007 it had already undergone three complete redesigns under a different general contractor. The owner initially wanted to fast track the process to make up for lost ground but this was later altered to fit their needs more accurately. The Owner, Salamander Hospitality, holds direct contracts with all the design architects, engineers, consultants. The contract between the Owner and Turner Construction is a Cost Plus Fee with a Guaranteed Maximum Price (GMP). Turner Construction holds lump sum contracts with all the subcontractors. The contractor was selected through a competitive process based upon qualification, fee, and a general conditions proposal. Turner Construction uses a Contractor Controlled Insurance Program (CCIP) which includes workers compensation and general liability. The Owner separately purchased Builders Risk Insurance. There is no Performance Bond on this project. See the following page for the project delivery system organizational chart. 12
15 Owner Salamander Hospitality Cost plus Fee and GMP Development Manager Mark G. Anderson Consultants Architect Architecture Inc. Design Architect Winberly Allison Tong and Goo Structural Engineer Rathgeber/Goss Associates Interior Designer Forrest Perkins Food Service Consultants CINI, Little General Contractor Turner Construction Civil Engineer PHR+A Landscape Architect Oculus MEP Engineer RG Vanderweil Engineers Spa Consultant Blue Spas Life Safety Consultant Rolf Jensen and Associates Lump Sum Electrical Contractor HVAC Contractor Excavating Contractor Concrete Contractor Other Contractors 13
16 STAFFING PLAN Turner Construction has eight people working on site, one project manager, three superintendents, and four engineers. There are more people on this site than usual because of the complexity of the systems and installation. The Project Engineer and Assistant Engineer are responsible for RFI s and submittals on a daily basis. The Superintendents are responsible for work flow, schedule changes, and subcontractors. Below is the Turner Construction on site staff. Project Superintendent Roger Shepard Asst. Superintendent 1 Chris Kayton Asst. Superintendent 2 Project Manager Mark Miller Asst. Engineer Tamika McCory Project Engineer There Swanson MEP Engineer Andy Yohe Asst. Engineer Pragnya Kappagantula 14
17 APPENDIX A: D4COST ESTIMATE 15
18 16
19 APPENDIX B: R.S. MEANS 2009 REFERENCE PAGES 17
20 18
21 APPENDIX C: PROJECT SCHEDULE SUMMARY 19
22 Technical Assignment 1: Construction Project Management 2009 APPENDIX D: SITE PLAN OF EXISTING CONDITIONS 20
SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM
Shepherd University Board of Governors June 9, 2005 Agenda Item No. 9 SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM In 1994 construction began on the Byrd Science and
KIEWIT CM/GC Enabling/Utilities
South Terminal Redevelopment Program KIEWIT CM/GC Enabling/Utilities Contract Value $50 million M/WBE Goal 20 percent Contact John Todd, LEED AP Project Manager 303.930.9046 [email protected] General
SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE NOTICE TO PROPERTY OWNER
NOTICE TO PROPERTY OWNER Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule. If your home or business is below
ST. MONICA FOOD PANTRY HOUSTON, TEXAS
PROJECT MANUAL FOR ST. MONICA FOOD PANTRY HOUSTON, TEXAS OWNER: ST. MONICA CATHOLIC CHURCH 8421 W. MONTGOMERY ROAD HOUSTON, TEXAS 77088 ARCHITECT: C SIX ARCHITECTURE, LLC 4606 F.M. 1960 WEST, STE 400 HOUSTON,
VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10
VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 SECTION B1: PREPARATION GUIDE B1.1 INTRODUCTION... B1-1
TD AMERITRADE Park Omaha
TD AMERITRADE Park Omaha November 19, 2009 Report No. 6 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment
Technical Assignment 2 TABLE OF CONTENTS
2 TABLE OF CONTENTS Executive Summary...3 Introduction..5 Gravity Loads......6 Design Codes......7 Materials..8 Existing Structural System.. 10 Existing Floor System 15 Alternate Floor Framing Systems...17
Repair and Remodeling Estimating Methods. 4th Edition. RSMeans
Brochure More information from http://www.researchandmarkets.com/reports/2214808/ Repair and Remodeling Estimating Methods. 4th Edition. RSMeans Description: This estimating guide for repair and remodeling
Special Use Commercial Properties
Contents Overview of Special Use Commercial Properties...3 Understanding Fast Food Restaurants...3 Understanding Gasoline Service Stations...4 Understanding Self-Service Cashier Booths...5 Understanding
Think Of Us First! When It s Time to Distribute Your Plans
Think Of Us First! When It s Time to Distribute Your Plans CONSTRUCTION NOTEBOOK WILL LIST YOUR PLANS AND SPECS FREE CALL TODAY FOR DETAILS 702-876-8660 Why use Experience We have over 60 years of experience
REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update
REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS MEETING DATE: March 16, 2011 SUBJECT: PRESENTER: ATTACHMENTS: Construction Management Update David Berry Yes 1. Construction Management
MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS
Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT
Hunter College school of Social Work Thesis Proposal
Fall 2009 Hunter College school of Social Work Thesis Proposal To analyze how energy efficiency can be implemented using facade and green roof redesign. It ties structural engineering concepts with existing
CONSTRUCTION LAW. Mechanical Roofing Contractor. Electrical Class A Air Conditioning. Contractor Class B Air Conditioning
CONSTRUCTION LAW I. Contractor Licensing 1. The Basic Rule: No person who is not certified or registered shall engage in the business of contracting in this state. FS 489.113. Pinellas County Code 22-14
Saint Cloud Business Center
Saint Cloud Business Center 14 7th Avenue North Saint Cloud, MN 56303 For Sale Located on 7th Avenue in the heart of downtown across from the Court House Square. A large professional reception area with
TAX APPRAISAL DISTRICT OF BELL COUNTY STORES & COMMERCIAL IMPROVEMENT CLASSIFICATION GUIDE
TAX APPRAISAL DISTRICT OF BELL COUNTY STORES & COMMERCIAL IMPROVEMENT CLASSIFICATION GUIDE 1/22/2008 1 STORES & COMMERCIAL BUILDINGS 1. General Construction Class Descriptions 2. Types a. Class A - Fireproofed
Important Information for Owners of Buildings in Flood Zones
Important Information for Owners of Buildings in Flood Zones Rebuilding your home after the storm? Adding on, renovating, or remodeling your home? Here is information YOU need to know about the 50 percent
Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities
Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 MINORITY AND WOMEN S BUSINESS ENTERPRISE PARTICIPATION
APPLICATION FOR NON-SUBSTANTIAL DAMAGE / IMPROVEMENT REVIEW
APPLICATION FOR NON-SUBSTANTIAL DAMAGE / IMPROVEMENT REVIEW Parcel Number: Owner s Name: Co-Owner s Name: Owner s Mailing Address: Owner Phone Number: FIRM Panel: Lowest Floor Elevation (excluding garage):
ADDENDUM NO. 1. DATE: February 10, 2015 INVITATION FOR BID: IFB K150015033 1801 Commerce Road Renovations Project DATED: February 9, 2015
ADDENDUM NO. 1 DATE: February 10, 2015 INVITATION FOR BID: IFB K150015033 1801 Commerce Road Renovations Project DATED: February 9, 2015 RECEIPT DATE: March 17, 2015 at 2:30 p.m. OPENING DATE: March 18,
SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE APPLICATION REVIEW
CITY OF EDGEWATER BUILDING DEPARTMENT 104 North Riverside Drive Edgewater, Florida 32132 Phone: (386) 424-2400 X 1514 FAX: (386) 424-2423 SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE APPLICATION SUBSTANTIAL
LITITZ MUTUAL INSURANCE COMPANY 2 North Broad Street Lititz, Pennsylvania - MAIN OFFICE -
The original section of this building was constructed in 1941. The exterior walls are built of good quality stone. In the early 1980 s a similar addition was added to the north elevation. The exterior
C-2 Construction, Inc. - NAICS Codes
C-2 Construction, Inc. - NAICS Codes 212313 - Crushed and Broken Granite Mining and Quarrying This U.S. industry comprises: (1) establishments primarily engaged in developing the mine site, and/or mining
2. What building projects are exempted? (permit not required)
BUILDING AND SAFETY DEPARTMENT 1. What building projects require a permit? Following is a list of projects that require building permits based on Appendix chapter 1 of the California Building Code and
SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request
SECTION 00 0110 PROCUREMENT AND CONTRACTING REQUIREMENTS 1.1 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS A. 00 0101 - Project Title Page B. 00 0105 - Certifications Page C. 00 0110 - Table
Construction Technologies Career Field Pathways and Course Structure
Courses in Structural Systems (DD) Construction Technologies Career Field Pathways and Course Structure PATHWAY COURSES SUBJECT CODE Construction Technology-Core and Sustainable Construction 1 178000 Carpentry
WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME
WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME 1 THE BUILDING PROCESS The focus of Woodland Homes building department is Quality, Service and Predictability. Through
COMMONLY USED RESIDENTIAL BUILDING CODES
COMMONLY USED RESIDENTIAL BUILDING CODES INTERNATIONAL RESIDENTIAL CODE (2009) form revised 5/10 FOUNDATION 1. DESIGN OF FORMWORK. Section 1906.1 IBC 2009, Section R404.1.2.3.6 IRC 2009, ACI 318 Section
C I T Y O F P E A R S A L L
The Largest City Between San Antonio and Laredo COMMUNITY DEVELOPMENT C I T Y O F P E A R S A L L A Business-Friendly, Family-Oriented Community Building Department Application Information (Please read
Marketing Coordinator Bootcamp Session 2: ABCs of AEC
Marketing Coordinator Bootcamp Session 2: ABCs of AEC Debbie Chen, LEED AP, APMP CF Proposal Development Director Louis Berger [email protected] Matthew Daw, PE, LEED AP Principal Keast & Hood [email protected]
REQUIREMENTS FOR SUBMITTING PLANS FOR NEW CONSTRUCTION
RESIDENTIAL: REQUIREMENTS FOR SUBMITTING PLANS FOR NEW CONSTRUCTION 2 COMPLETE SETS OF PRINTS WITH ENGINEERS STAMP ON FOUNDATION PLAN INCLUDING ELECTRICAL, PLUMBING, ETC. SITE PLAN SHOWING HOUSE LOCATION
BMIC S APPETITE GUIDE EFFECTIVE JUNE 2013
The following guide is a general list of Builders Mutual s appetite for business classes residential and commercial WorkSafe workers compensation and Builders Best general liability (including trade contractors),
CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714
CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714 BUILDING DIVISION (714) 961-7120 Single Family Residential New Construction, Additions & Alterations Submittal Requirements Required agency approvals
HomeSpec REPORT SUMMARY
HomeSpec 04/25/2007 Ms. Rachel Trujeque Re: 13038 West Plum Road Lot #1225 - Peoria, AZ. 85383 - Pre Drywall Inspection Dear Ms. Trujeque, At your request, a visual pre drywall inspection of the above
Veterans Memorial Coliseum Options Study Appendix A - Deconstruction Scope of Work and Cost Estimate August 31, 2015
Stage 1 DA.01 Fencing and cameras deployed Baseline - 3-5 years for Stage 1 for purposes of this study costs are described for a 3 year period $45,000 $0 Stage 1 DA.02 Secure all building doors and access
City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage
City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage Property Address: Company Name: Contractor Name: Contractor Address: City: State: Zip: License Number: Phone Number
Notice to Property Owners
Modification or Repair of your Flood Prone Property Notice to Property Owners Rebuilding or Remodeling Your Home If your home or business sustained damage, or if you are making improvements to the structure
BUILDING ASSESSMENT QUESTIONNAIRE. B. TENANTS Is there more than one tenant in the building? YES
Department of Health and Human Services, Division of Public Health Occupational and Environmental Epidemiology Branch 1912 Mail Service Center, Raleigh, North Carolina 27699-1912 BUILDING ASSESSMENT QUESTIONNAIRE
Name of course: Residential Construction Site Management (RCSM) Level 1
Name of course: Residential Construction Site Management (RCSM) Level 1 Core (required courses) or Optional (elective course): Required Delivery Method: This is an online course only with no classroom
SECTION 3 ONM & J STRUCTURAL ANALYSIS
Historic Boynton Beach High School Existing Building Assessment City of Boynton Beach February 10, 2011 SECTION 3 ONM & J STRUCTURAL ANALYSIS STRUCTURAL ENGINEERS SPECIAL INSPECTORS STRUCTURAL CONDITION
OPTIMUS WORK CLASSIFICATION LIST ENTER ALL THAT APPLY
Cost Code # Description Cost Code # Description 01 00 00.001 General Requirements 02 00 00.001 Existing Conditions 01 31 19.13.001 Preconstruction Meetings 02 21 00.001 Surveys 01 32 33.001 Photographic
Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components
Infrastructure Facility Condition Summary Weighted Avg Condition Score Facility Components Systems Surveyor/ Date Done Comments G Sitework.9 Site Improvements Parking Pedestrian Paving Site Development
Estimated Cost of Repair
1 Applicant: Property: Home: Business: Assessor: Applicant Number: Type of Loss: Hurricane Date Contacted: 1/18/2014 Date of Loss: 10/29/2012 Date Received: 1/14/2014 Date Inspected: 2/4/2014 Date Entered:
When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are:
When is a Permit Required? The most common types of projects that require permits are: -New Houses or buildings -Room Additions or Expansions -Structural repairs, remodeling and alterations -Accessory
EAST LYME HIGH SCHOOL
Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed
Sustainable Strategies for Rehabilitation Projects: 9th Street Office Building Adaptive Reuse Case Study
Sustainable Strategies for Rehabilitation Projects: 9th Street Office Building Adaptive Reuse Case Study Robert C. Burns, AIA, LEED AP Principal Director of Historic Architecture 804. 648. 5040, ext. 1107
Basic Requirements for Residential Plan Review _
Basic Requirements for Residential Plan Review _ Below you will find the basic requirements for your plan submittal. General: Drawn to scale Plan Size minimum: 9 x 12 Designer, Engineer, or Architect name,
Occupancy: Assembly (A-3) and Business -Includes offices, seminar rooms, classrooms, and café facility. Duke University Medical School
Introduction Background The Duke School of Nursing building offers a new three-story state of the art facility that has helped strengthen the quality and integrity of the School of Nursing at Duke. The
Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders
INTRODUCTORY INFORMATION TABLE OF CONTENTS 00 0101 PROJECT TITLE PAGE PROCUREMENT REQUIREMENTS (PROJECT MANUAL) Tab A - Invitation for Bids Tab B - Instructions to Bidders Tab C Bid Form for General Bids
D Sample Notices to Property Owners, Sample Affidavits, and Other Material
D Sample Notices to Property Owners, Sample Affidavits, and Other Material These samples are offered to illustrate specific points in the Desk Reference. States and communities should examine them carefully
Additions and Alterations
Additions and Alterations Addition and alteration construction is a miscellaneous grouping of home improvement and renovation projects that are generally geared toward the enhancement of an existing principal
Estimating Database Checklist
Estimating Database Checklist If you are creating a new estimating database for projects, the following list offers a thorough listing of Main and Sub Categories. You can also use it as a checklist to
PROJECT SUMMARY. Scope of work details: (If phased construction, please see plan submittal guidelines.)
APPENDIX B BUILDING CODE SUMMARY FOR ALL COMMERCIAL FIRE RESTORATION PROJECTS (EXCEPT 1 AND 2-FAMILY DWELLINGS AND TOWNHOUSES) (Reproduce the following data on the building plans sheet 1 or 2) Name of
Residential Building Permits
LANE COUNTY PUBLIC WORKS Residential Building Permits LAND MANAGEMENT DIVISION 3050 N. DELTA HWY, EUGENE OR 97408 i CONTACT PHONE NUMBERS: Building Program: (541) 682-4651 Inspection Requests: (888) 299-2821
SUBSTANTIAL IMPROVEMENT/DAMAGE NOTICE TO PROPERTY OWNERS
SUBSTANTIAL IMPROVEMENT/DAMAGE NOTICE TO PROPERTY OWNERS Rebuilding or repairing your home/business after the storm? Adding on, renovating, or remodeling your home/business? Here s information YOU need
Building Condition Assessment Report
Building Condition Assessment Report Asset C3c - Oak Terrace Cottage 121 Address Riverview Lands, 2601 Lougheed Highway, Coquitlam, BC. V5C 4J2 Construction Year Size (Gross Floor Area) 1920. 2,553 Sq.Ft.
Development Services Guidelines
Dear Customer/Developer: Balcones Heights 3300 Hillcrest San Antonio, Texas 78201 210-735-9148 ext 246 Fax: 210-735-9409 Development Services Guidelines Welcome to the City of Balcones Heights, we look
INDUSTRIALS COLD STORAGE FACILITIES
CAL 98 INDUSTRIALS COLD STORAGE FACILITIES AVERAGE CLASS C LOW/AVERAGE CLASS S OCCUPANCY DESCRIPTION: Cold storage facilities are designed to keep stored commodities at various temperature levels. Some
Residential Foundations and Basements
Residential Foundations and Basements Disclaimer All of the following information is based on the 2006 International Residential Code with Kentucky Amendments. As some information is paraphrased, article
AT&T Internet Data Center Site Specification New York III (Secaucus, NJ)
AT&T Internet Data Center Site Specification New York III (Secaucus, NJ) Site Biography Market Area: New York City, New Jersey, Upstate NY and Lower Connecticut Location: Secaucus, NJ 07094 Address: 15
Elevating Your House. Introduction CHAPTER 5
CHAPTER 5 Elevating Your House Introduction One of the most common retrofitting methods is elevating a house to a required or desired Flood Protection Elevation (FPE). When a house is properly elevated,
BUILDING SAFETY UNIT
POLICY Page 1 of 5 SUBMITTAL REQUIREMENTS FOR ONE AND TWO FAMILY DWELLINGS, ADDITIONS AND RENOVATIONS All submittals shall be site specific and designed to the provisions of the 2012 International Residential
NATIONAL FLOOD INSURANCE PROGRAM (NFIP) SUBSTANTIAL DAMAGE/ SUBSTANTIAL IMPROVEMENT (50% RULE)
NATIONAL FLOOD INSURANCE PROGRAM (NFIP) SUBSTANTIAL DAMAGE/ SUBSTANTIAL IMPROVEMENT (50% RULE) If your home or business is located within a 100-year floodplain and it was constructed through a County Building
Residential Prototype III. Multi-Story. The Multi-Story. Your connection to ideas + answers. Prepared by: AISC Steel Solutions Center
Multi-Story Residential Prototype III The Multi-Story Residential Prototype III Prepared by: AISC Steel Solutions Center What s this? This package tells the story of a fictitious project with an imaginary
Career Path Project Engineer to Project Manager 1
Career Path Project Engineer to Project Manager 1 The Career Path standards listed below are designed to help a Project Engineer at Samet Corporation understand what skills, knowledge and experience they
Building, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements
Building, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements Charles County Government Planning and Growth Management P.O. Box 2150, La Plata, MD 20646 (301) 645-0692 Schedule
Preparation for 2015 Residential Code Changes Discussion with Local Builders and Designers
City of Duluth Preparation for 2015 Residential Code Changes Discussion with Local Builders and Designers Thank you for taking the time to join us today. We know you are busy and your time is valuable.
GREEN SCHOOLS CASE STUDY. West Wing Elementary
GREEN SCHOOLS CASE STUDY School School name: School Deer Valley Union School District Address: 26716 N. High Desert Drive, Peoria, Arizona Contact: Jerry Cipriano Phone number: 602-467-5131 General location:
SECTION 02400 - STORM DRAIN SYSTEM
SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And
Building Condition Assessment Report
C2 - Nurses Resident (aka Administration) Building Condition Assessment Report Asset Address Address Construction Year Size (Gross Floor Area) Asset Type Floors Above Ground Inspection Date C2 - Nurses
InfoforBuilding.com Owner-Builder Spreadsheet
InfoforBuilding.com Owner-Builder Spreadsheet 2002 InfoforBuilding.com. All rights reserved. www.infoforbuilding.com *Please see notes for directions KEY to boxes Required input Indicates owner-builder
TOWN OF JUNO BEACH 340 Ocean Drive Juno Beach, FL 33408 Phone: (561) 656-0302 Fax: (561) 775-0812
TOWN OF JUNO BEACH 340 Ocean Drive Phone: (561) 656-0302 Fax: (561) 775-0812 Application for Building Permit & Certificate of Occupancy OFFICE USE ONLY: Date: Permit #: Tracking #: Job Address: Property
Development Services Guidelines
Dear Customer/Developer: Balcones Heights 3300 Hillcrest San Antonio, Texas 78201 210-735-9148 ext 246 Fax: 210-735-9409 Development Services Guidelines Welcome to the City of Balcones Heights, we look
BUILDING PERMIT SPECIFICATIONS
BUILDING PERMIT SPECIFICATIONS The below noted requirements are based upon La Plata County Building Code. These specifications are not intended as a complete set of requirements, but are intended to provide
Analysis II Façade Redesign: Architectural Precast Panels
Analysis II Façade Redesign: Architectural Precast Panels Analysis II Façade Redesign: Architectural Precast Panels Overview: This analysis covers the comparison of the current EIFS façade and my proposed
NOTICE TO CONTRACTORS
NOTICE TO CONTRACTORS Notice is hereby given that San Luis Obispo County Community College District, ( District ) is accepting sealed Informal Bidding Prequalification Applications and Formal Bidding Prequalification
APPLICATION FOR NEW CONSTRUCTION
CITY OF ELKINS 401 DAVIS AVE ELKINS WV 26241 Date Pd: Receipt #: Session #: PHIL ISNER BLDG INSPECTOR / CODE ENFORCEMENT OFFICER 304-636-1414 Ext 1431 APP. DATE APPLICATION FOR NEW CONSTRUCTION APPLICANT
Lot Number. City. Architect Name SUBCONTRACTORS - COMPLETE AND ATTACH LIST ON PAGE 4
New Construction Permit Application Village of Shorewood Building Division One Towne Center Blvd Shorewood, IL 60404 (815)553-2310 Fax (815)744-6766 SUBMISSION CHECKLIST - Complete this application and
PROJECT COST ESTIMATES & FEASIBILITIES
PROJECT COST ESTIMATES & FEASIBILITIES Project Cost and budget management Project success elements Scope meet the scope defined for the project Budget It is within established budget Programme It is designed
Cost Estimation for Materials and Installation of Hot Water Piping Insulation
Cost Estimation for Materials and Installation of Hot Water Piping Insulation Prepared for Pacific Northwest National Laboratory Under Contract Number: 18O9O2 By Gary Klein, Managing Partner Affiliated
Civil Engineering and Architecture (CEA) Detailed Outline
Civil Engineering and Architecture (CEA) Detailed Outline Unit 1: Overview of Civil Engineering and Architecture (23 days) Lesson 1.1: History of Civil Engineering and Architecture 1. Many features of
LAYING BLOCK AND BRICK
LAYING BLOCK AND BRICK Products highlighted in this section: SAKRETE Type N Mortar Mix SAKRETE Type S Mortar Mix Brick And Block Laying Basics The first step in building a brick or block wall is to construct
48. AQUARIUM. Aquarium. Classification: Cluster: Location: Close to junction of Inselrhue and Loiter Way, Belle Isle. Total Area: No.
Classification: Cluster: Location: Total Area: No. of Stories Aquarium Acreage Owned: Acquired: 1904 Most Recent Improvements: THE AQUARIUM Close to junction of Inselrhue and Loiter Way, Belle Isle Two
Substantial Improvement/Damage Notice to Property Owners
Substantial Improvement/Damage Notice to Property Owners Rebuilding, Remodeling, Adding on, or Renovating Your Home Here is infonnation YOU need to know about the 50% Rule If your home or business is below
MURCH ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1929 BUILDING AREA 47,700 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 491 WARD 3 PROPOSED PROGRAM CAPACITY 500 Site Plan MURCH - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
SODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST
SODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST SODA SPRINGS HIGH SCHOOL REPAIRS AND UPGRADES SITE Construction Estimate = $100,000
Residential Building Permits Information
City of Bonham Building Department 514 Chestnut St. Bonham, Texas 75418 OFFICE: (903) 583-7555 FAX: (903)583-5761 Residential Building Permits Information Application for Permits: To apply for a permit,
Inspecting to a higher standard.
Inspecting to a higher standard. Rob Hopkin Silver Spring, MD 20902 Monday, June 2, 2014 ProTec Inspection Services Inc. 19736 Selby Ave Poolesville, MD 20837 301-972-8531 www.protec-inspections.com [email protected]
Nominal Life Expectancy for Building Components
Nominal Life Expectancy for Building Components Building System Page A. HVAC 2 B. Elevator/Escalator 6 C. Plumbing 7 D. Roofing 8 E. Electrical 10 F. Fire/Life/Safety/Security System 11 G. Interior Finishes
VILLAS OF TRADITIONS AT GREY OAKS
Report of Turnover Survey VILLAS OF TRADITIONS AT GREY OAKS Grey Oaks Development Naples, Collier County, Florida Forge Engineering Project Number 2907-001.01 March 2015 Richard P..Lundberg, P.E cn=richard
Information for Construction Contractors. Terry O Neill Taxpayer Service Specialist
Information for Construction Contractors Terry O Neill Taxpayer Service Specialist Today s Webinar Definitions and details 4 types of contractors Sales tax for each type of contractor Materials, Equipment,
Applications for building permits will not be reviewed until all of the required information has been submitted.
NOTICE: Applications for building permits will not be reviewed until all of the required information has been submitted. Once all items are submitted a minimum of ten (10) working days are required to
A TO Z HOME INSPECTIONS PROFESSIONAL HOME INSPECTION SERVICES FOR HOME BUYERS AND SELLERS
A TO Z HOME INSPECTIONS PROFESSIONAL HOME INSPECTION SERVICES FOR HOME BUYERS AND SELLERS Insurance Inspection Report 1234 Main Street Tallahassee, Florida Report Prepared For: Charles Smith Report Prepared
MAJOR 2015 MN RESIDENTIAL CODE CHANGES Effective Date: January 24 th, 2015
MAJOR 2015 MN RESIDENTIAL CODE CHANGES Effective Date: January 24 th, 2015 **Disclaimer: This document is to serve as informational purposes only. This is not a code book or a final interpretation of the
Chapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory