44. Standard for Wayside Intrusion Detection System Inspection and Testing
|
|
|
- Sarah Kelly
- 9 years ago
- Views:
Transcription
1 44. Standard for Wayside Intrusion Detection System Inspection and Testing Approved June 10, 2003 APTA Rail Transit Standards Fixed Structures Inspection and Maintenance Committee Approved September 28, 2003 APTA Rail Transit Standards Task Force Authorized January 28, 2004 APTA Rail Transit Standards Policy Committee Abstract: This standard provides procedures for inspecting and testing rail transit wayside intrusion detection systems. Keywords: inspection, seismic, seismic relay, signal, test, testing, wayside intrusion detection systems, zone Copyright 2004 by The American Public Transportation Association 1666 K Street, NW, Washington, DC, , USA No part of this publication may be reproduced in any form, in an electronic retrieval system or otherwise, without the prior written permission of The American Public Transportation Association.
2 Introduction (This introduction is not a part of, Standard for Wayside Intrusion Detection System Inspection and Testing.) APTA rail transit safety standards represent an industry consensus on safety practices for rail transit systems to help achieve a high level of safety for passengers, employees, and the general public. This document was created by and for those parties concerned with its provisions; namely, rail transit systems (operating agencies), manufacturers, consultants, engineers, and general interest groups. This standard provides procedures for inspecting and maintaining rail transit wayside intrusion detection systems. APTA recommends this standard for: Individuals or organizations that inspect, maintain, and/or operate rail transit systems Individuals or organizations that contract with others for the inspection, maintenance, and/or operation of rail transit systems Individuals or organizations that influence how rail transit systems are inspected, maintained, and/or operated (including but not limited to consultants, designers, and contractors) This standard intends to meet the following objectives: To ensure special life/safety equipment is operational and reliable To help rail transit systems incorporate safety considerations during the inspection and maintenance process To identify inspection criteria and maintenance standards that provide a high level of passenger and personnel safety The application of any standards, practices, or guidelines contained herein is voluntary. In some cases, federal and/or state regulations govern portions of how a rail transit system operates. In such cases, the government regulations override any conflicting practices this document requires or recommends. Copyright 2004 APTA. All rights reserved. 44.ii
3 Participants APTA greatly appreciates the contributions of the following members of the Signals and Communications Subcommittee who provided the primary effort in drafting the Standard for Wayside Intrusion Detection System Inspection and Testing: Carlton Don Allen, P.E. Sal Arceo Gabrielle Bayme Paul Camera Lenny De Meyer Michael Esford Patrick Lavin Ruben Madrigal Thomas Peacock Stephen Roberts Carey Vaughn The following members of the Rail Transit Standards Fixed Structures Inspection and Maintenance Committee contributed to the review and approval process of the Standard for Wayside Intrusion Detection System Inspection and Testing: James Dwyer, Chair Frank Cihak, Vice Chair Anthony Adams Carlton Don Allen, P.E. Sal Arceo Roger Avery Peter Bertozzi Steven Bezner, P.E. Raymond Borge Michael Brown John Bumanis Clay Bunting R. Sean Burgess Paul Camera David Cappa, P.E. Gricelda Cespedes Robert Chappell Frank Cihak Catherine Cronin Lenny De Meyer Tom Devenny David Dunderdale James Dunn James Dwyer William Early, P.E. Percy Erves Michael Esford Richard Falcon Ray Favetti Peter Fedun, P.E. Steve Feil Robert Fiore John Gaito Ricky Green Mohammad Irshad Patrick Lavin Harry Lupia Frank Machara Ruben Madrigal Michael Monastero Bill Petit David Rankin Pingali Rao, P.E. Richard Raschke James Redding Stephen Roberts Charles Slavis, P.E. Frederick Smith, P.E. Richard Spatz Charles Stanford F. Brian Steets Paul Swanson, P.E. Steven Thompson Fred Tijan Gary Touryan Carey Vaughn James Wang, P.E. APTA Rail Transit Standards Fixed Structures Inspection and Maintenance Committee project consultants: Peter Gentle, P.E., STV Incorporated Carol Rose, STV Incorporated APTA Rail Transit Standards project team: Gabrielle Bayme, Standards Development Program Specialist and Project Editor Saahir Brewington, Administrative Assistant and Project Editor Antoinette Hankins, Program Assistant Thomas Peacock, Director-Operations & Technical Services David Phelps, Senior Project Manager - Rail Programs Copyright 2004 APTA. All rights reserved. 44.iii
4 Contents 1. Overview Scope Purpose Alternate practices Definitions and acronyms Definitions Acronyms Inspection and testing requirements Inspection and testing frequency Training Materials Tools Personal protective equipment Safety Inspection and test procedures Inspection Test Correction of deficiencies Documentation Annex A (informative) Bibliography Copyright 2004 APTA. All rights reserved. 44.iv
5 Standard for Wayside Intrusion Detection Inspection and Testing 1. Overview 1.1 Scope This document establishes standard requirements for inspecting and testing of rail transit wayside intrusion detection systems including right of way intrusion detection systems and seismic detection. 1.2 Purpose The purpose of this standard is to verify that wayside intrusion detection systems are operating safely and as designed through periodic inspection and testing, thereby increasing reliability and reducing the risk of hazards and failures. 1.3 Alternate practices Individual rail transit systems may modify the practices in this standard to accommodate their specific equipment and mode of operation. APTA recognizes that some rail transit systems may have unique operating environments that make strict compliance with every provision of this standard impossible. As a result, certain rail transit systems may need to implement the standards and practices herein in ways that are more or less restrictive than this document prescribes. A rail transit system (RTS) may develop alternates to the APTA standards so long as the alternates are based on a safe operating history and are described and documented in the system s safety program plan (or another document that is referenced in the system safety program plan). Documentation of alternate practices shall: a) Identify the specific APTA rail transit safety standard requirements that cannot be met b) State why each of these requirements cannot be met c) Describe the alternate methods used d) Describe and substantiate how the alternate methods do not compromise safety and provide a level of safety equivalent to the practices in the APTA safety standard (operating histories or hazard analysis findings may be used to substantiate this claim). Copyright 2004 APTA. All rights reserved. 44.1
6 2. Definitions and acronyms For the purposes of this standard, the following definitions and acronyms apply: 2.1 Definitions hazard: Any real or potential condition that can cause injury, death, or damage or loss of equipment or property operations control center (OCC): That facility from which train control, train dispatching, and/or train supervision takes place for the entire RTS or for specific segments of a system if there is more than one control center. Syn: rail control center, rail operations center, rail service control center, train command center original equipment manufacturer (OEM): The enterprise that initially designs and builds a piece of equipment personal protective equipment (PPE): All clothing and other work accessories designed to create a barrier against workplace hazards. Examples include safety goggles, blast shields, hard hats, hearing protectors, gloves, respirators, aprons, and work boots rail transit system (RTS): The organization or portion of an organization that operates rail transit service and related activities. Syn: operating agency, operating authority, transit agency, transit authority, transit system seismic detection system: An accelerometer-based sensing system used to detect seismic activity and produce an electrical signal output. 2.2 Acronyms OCC OEM PPE RTS operations control center original equipment manufacturer personal protective equipment rail transit system 3. Inspection and testing requirements 3.1 Inspection and testing frequency The inspection and testing procedures in this standard shall be performed when wayside intrusion detection systems are placed in service, when they are modified, repaired, or disarranged, or as otherwise deemed necessary by the RTS. The RTS shall determine the need for additional inspection and testing frequencies for wayside intrusion detection systems. A review of the following factors may be useful in making this assessment: Copyright 2004 APTA. All rights reserved. 44.2
7 OEM-recommended intervals Industry experience Operating environment/conditions Historical data Reliability-centered maintenance program development Failure analysis RTS testing and experience Regulatory requirements The frequency of tasks shall comply with applicable federal, state, and local regulations. 3.2 Training The RTS and/or their maintenance contractors shall develop and execute training programs that provide employees with the knowledge and skills necessary to safely and effectively perform the tasks outlined in this standard. 3.3 Materials The following materials are required for inspecting and testing wayside intrusion detection systems: RTS-approved lubricants RTS-approved cleaning solutions Additional materials as required by the OEM and/or RTS 3.4 Tools The following tools are required for inspecting and testing wayside intrusion detection systems: Multi-meter* RTS-approved portable radio Standard tools carried by maintenance personnel Additional tools as required by the OEM and/or RTS * Calibrate in accordance with OEM and/or RTS requirements. Copyright 2004 APTA. All rights reserved. 44.3
8 3.5 Personal protective equipment Personal protective equipment, as required by the RTS, shall be worn at all times during inspection and testing. 3.6 Safety RTS safety rules, procedures, and practices shall be followed at all times during inspection and testing. 3.7 Inspection and test procedures Wayside intrusion detection inspection and testing procedures may be modified for each rail transit system s requirements (see Section 1.3) but shall contain the steps listed in Sections as a minimum Inspection Notify the operations control center (OCC) and/or other authorities of the inspection activities to be performed Inspect wayside junction boxes and other enclosures for rust, corrosion, damage, cracks, breaks, defective latches, hinges, locks, covers, seals, gaskets, loose conduit connections and missing or loose components and hardware. Holes and entrances not used for ventilation should be sealed Inspect junction boxes and enclosures for the presence and condition of stored circuit drawings, terminal list, wire tags and instructions Inspect wayside cables/wiring and hardware for defective insulation, rust, corrosion, missing components, damage, and loose or broken connections, and for damage caused by standing water, water leaks, or retention Inspect the wayside for any condition that may interfere with the operation of intrusion and detection systems and/or revenue operations Inspect wayside equipment for rust, corrosion, damage, cracks, breaks and defective latches, hinges, locks, covers, seals, gaskets, loose conduit connections, loose electrical connections and missing or loose components and hardware Inspect room and other signal equipment housing facilities for defective cable insulation, rust, corrosion, missing components, damage and loose or broken connections and for damage caused by standing water, water leaks or retention. Holes and entrances not used for ventilation should be sealed Ensure covers and locks are in place and secured. Copyright 2004 APTA. All rights reserved. 44.4
9 Notify the OCC and/or other authorities when inspection is complete Test Notify the OCC and/or other authorities of the testing activities to be performed Inspect equipment for active alarms and observe system status lights for proper system operation Check power sources and power supplies for proper values and tolerances Perform system test using RTS procedures to verify proper operation by: a) Simulating an intrusion and/or seismic detection. b) Verifying if applicable, that the relay(s) or device(s) affected by the simulated intrusion and/or seismic detection are activated, have assumed the proper states and their proper indications are received at OCC, locally, and other facilities. c) Verifying if applicable, that the proper intrusion and/or seismic detection zone indications and alarms are received at OCC, locally and other remote facilities Restore the system to normal operation and verify that the relay(s) or device(s) affected by the simulated intrusion and/or seismic detection are de-activated, have assumed the proper state, and the indications are received at OCC, locally, and other facilities Perform additional system functional testing as deemed necessary by the RTS to verify proper and safe system operation Ensure covers, doors and locks are in place and secured Notify the OCC and/or other authorities when testing is complete. 3.8 Correction of deficiencies Deficiencies identified during wayside intrusion detection system inspection and testing shall be corrected and documented in accordance with OEM and/or RTS requirements. 3.9 Documentation Inspection and testing shall be documented, reviewed, and filed in accordance with RTS procedures. Copyright 2004 APTA. All rights reserved. 44.5
10 Annex A (informative) Bibliography [B1] [B2] Original equipment manufacturer (OEM) specifications for wayside intrusion detection systems inspection and testing. Rail transit system (RTS) procedures for wayside intrusion detection systems inspection and testing. Copyright 2004 APTA. All rights reserved. 44.6
2. Standard for Rail Transit Track Inspection and Maintenance
Draft- 2. Standard for Rail Transit Track Inspection and Maintenance Approved June 25, 2002 APTA Rail Transit Standards Fixed Structures Inspection and Maintenance Committee Approved September 3, 2002
16. APTA PR-IM-S-016-02 Standard for Pantograph Current Collection Equipment Periodic Inspection and Maintenance
16. APTA PR-IM-S-016-02 Standard for Pantograph Current Collection Equipment Periodic Inspection and Maintenance Approved October 30, 2002 APTA Passenger Rail Equipment Safety Standards Task Force Authorized
17. APTA PR-IM-S-017-02 Standard for Third Rail Current Collection Equipment Periodic Inspection and Maintenance
17. APTA PR-IM-S-017-02 Standard for Third Rail Current Collection Equipment Periodic Inspection and Maintenance Approved October 30, 2002 APTA Passenger Rail Equipment Safety Standards Task Force Authorized
Sam Docknevich, PSP, Security Service Portfolio Manager. Are You Prepared? The impending impact of Code on Servicing Security Systems
Sam Docknevich, PSP, Security Service Portfolio Manager Are You Prepared? The impending impact of Code on Servicing Security Systems usa.siemens.com/infrastructure-cities Share current and upcoming standards
Electric Panel Pump Control System. Operation, Maintenance and Installation Manual
Manual No. 5EP-OM1-1 Electric Panel Pump Control System Operation, Maintenance and Installation Manual INTRODUCTION... 1 RECEIVING AND STORAGE... 1 DESCRIPTION OF OPERATION... 1 INSTALLATION... 2 SEQUENCE
CalMod Design-Build Electrification Services
SECTION 28 16 00 INTRUSION DETECTION SYSTEM PART 1 - GENERAL 1.1 DESCRIPTION A. This section describes the detailed technical requirements for the Intrusion Detection System (IDS), where the Contractor
Maintenance Report MEDIUM VOLTAGE POWER STATION 500SC / 630SC / 800SC / 900SC / 1000 1SC / 1000 2SC / 1250SC / 1600SC / 1800SC / 2000SC
Maintenance Report MEDIUM VOLTAGE POWER STATION 500SC / 630SC / 800SC / 900SC / 1000 1SC / 1000 2SC / 1250SC / 1600SC / 1800SC / 2000SC Project name: Customer: Address, location of the system: Serial number
3. APTA PR-E-RP-003-98 Recommended Practice for Load Testing of Diesel Engines
3. APTA PR-E-RP-003-98 Recommended Practice for Load Testing of Diesel Engines Approved January 22, 1998 APTA PRESS Task Force Authorized March 17, 1999 APTA Commuter Rail Executive Committee Abstract:
SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL
SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL 1.1 SUMMARY A. This section describes the requirements for the installation of Power Monitors and associated
APPENDIX 2-3 PCAPP EDS INSPECTION LOG SHEETS
APPENDIX 2-3 PCAPP EDS INSPECTION LOG SHEETS Pueblo Chemical Depot Pueblo Chemical Depot (This page intentionally left blank.) PCAPP EDS Daily (When in Use) Operational Inspection Checklist EXAMPLE Inspected
FIRE ALARM SYSTEM TECHNICAL SPECIFICATIONS Page 1 of 10
TECHNICAL SPECIFICATIONS Page 1 of 10 FIRE DETECTION AND ALARM SYSTEM Scope Furnish a complete 24V DC conventional, electrically supervised, zone annunciated, fire detection and alarm system as specified
Prevention through Design: Eliminating Confined Spaces and Minimizing Hazards
Prevention through Design: Eliminating Confined Spaces and Minimizing Hazards American Industrial Hygiene Association Developed by the AIHA Confined Spaces Committee Approved by the AIHA Board of Directors
Respiratory Safety and PPE Module 7. Special Warehouse Worker Hazards in Structural Steel Fabricating and Supply Companies
Respiratory Safety and PPE Special Warehouse Worker Hazards in Structural Steel Fabricating and Supply Companies Drawing from OSHA 3384-09 2011 1 Respiratory Safety and PPE OSHA Grant Information This
SECTION 13850 (28 31 00) FIRE DETECTION AND ALARM SYSTEM
SECTION 13850 (28 31 00) FIRE DETECTION AND ALARM SYSTEM ENGINEERING SPECIFICATION INTELLIGENT REPORTING FIRE DETECTION SYSTEM PART 1 GENERAL 1.1 DESCRIPTION A. This specification includes the furnishing,
RMM 306 Lockout/Tagout (LOTO) Program for the Control of Hazardous Energy Page 2 June 2016
RMM 306 Lockout/Tagout (LOTO) Program for the Control of Hazardous Energy Page 2 3 Related Documents 3.1 Occupational Health and Safety Act, R.S.O. 1990 3.2 Regulations for Industrial Establishments, R.R.O.
Recommended Practice for Installation of Transit Vehicle Fire Protection Systems
Recommended Practice for Installation of Transit Vehicle Fire Protection Systems Approved October 25, 2007 APTA Fire Safety Working Group Approved May 3, 2008 APTA Bus Safety Committee Approved October
Inspection, Testing and Maintenance
Page 18 ABOUT CODE CORNER CCFS would like to remind you to check with your local Authority Having Jurisdiction (AHJ) for questions and opinions concerning your local Fire and Building Codes. The information
Union County Public Schools. Facilities Department. Electrical. Safe Work Practices
1 Union County Public Schools Facilities Department Electrical Safe Work Practices 2 Purpose In accordance with OSHA Standards 1910.331-335, safety-related work practices shall be used by Union County
CPPSEC2021A Install security equipment and systems
CPPSEC2021A Install security equipment and systems Release: 1 CPPSEC2021A Install security equipment and systems Modification History Not Applicable Unit Descriptor Unit descriptor This unit of competency
Heating, Ventilation and Air Conditioning Periodic Inspection and Maintenance
APTA STANDARDS DEVELOPMENT PROGRAM RECOMMENDED PRACTICE American Public Transportation Association 1666 K Street, NW, Washington, DC, 20006-1215 APTA RT-VIM-RP-004-02 Rev 1 First Published: Feb. 2, 2002
Machine/Woodworking Shop The Basic Rules
Machine/Woodworking Shop The Basic Rules 1. Eye protection or face shields are required when working in the shop. A selection of protective goggles and safety glasses are available in the shop. The eyeglasses
NC State University Design and Construction Guidelines Division 26 Fire Alarm Systems
NC State University Design and Construction Guidelines Division 26 Fire Alarm Systems 1.0 Purpose A. The following guideline provides the minimum standards and requirements for fire alarm systems. 2.0
Standard for a Continuity of Operations Plan for Transit Agencies
APTA STANDARDS DEVELOPMENT PROGRAM STANDARD American Public Transportation Association 1666 K Street, NW, Washington, DC, 20006-1215 APTA-SS-SEM-S-001-08 Rev. 1 Rev. 1: April 1, 2013 Published: September
Unit ID: 482 Domain AUTOMOTIVE ELECTRICAL AND ELECTRONICS Title: Install and repair electrical lighting system of vehicles Level: 2 Credits: 6
Unit ID: 482 Domain AUTOMOTIVE ELECTRICAL AND ELECTRONICS Title: Install and repair electrical lighting system of vehicles Level: 2 Credits: 6 Purpose This unit standard specifies the competencies required
OEM Manual MODEL 2350 ELECTRONIC DUAL CYLINDER SCALE
OEM Manual MODEL 2350 ELECTRONIC DUAL CYLINDER SCALE Scaletron Industries, Ltd. Bedminster Industrial Park 53 Apple Tree Lane P.O. Box 365 Plumsteadville, PA 18949 USA Toll Free: 1-800-257-5911 (USA &
ELECTRICAL SAFETY RISK ASSESSMENT
ELECTRICAL SAFETY RISK ASSESSMENT The intent of this procedure is to perform a risk assessment, which includes a review of the electrical hazards, the associated foreseeable tasks, and the protective measures
Ladder Use in Construction Guideline
Ladder Use in Construction Guideline Forward This guideline has been prepared to assist workplace parties in understanding their obligations under the Occupational Health and Safety Act (OHSA) and its
FIRE ALARM AND DETECTION SYSTEMS SECTION 16721
PART 1 - GENERAL 1.01 WORK INCLUDED FIRE ALARM AND DETECTION SYSTEMS SECTION 16721 A. Provide a complete fully addressable, power limited, fire detection and evacuation system. The system shall be connected
Conventional Fire Detection and Extinguishant Control System Specification
Conventional Fire Detection and Extinguishant Control System Specification Page 1 of 9 Scope Furnish a complete 24VDC Conventional, electrically supervised, combined fire detection and extinguishant release
Video Verification Procedures for Burglar Alarms
Video Verification Procedures for Burglar Alarms ANSI/CSAA CS-V-02-2012 Page 1 of 11 Last Revised: 10/7/11 Contents Foreword. 3 Acknowledgments.. 4 Introduction. 6 1 Scope 7 2 General 7 3 Definitions 7
ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1
KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1
Current Monitoring Kit QUICK START GUIDE
Current Monitoring Kit QUICK START GUIDE Pico Technology EL040 Current Monitoring Kit Quick Start Guide CONTENTS 1 Introduction... 1 2 Kit contents... 3 3 Installation... 3 3.1 Connecting the system together...
Current Monitoring Kit
Current Monitoring Kit QUICK START GUIDE DO090-6 CONTENTS Issues: 1) 2.10.02 WP A4 format 2) 2.10.02 Added safety warning 3) 17.3.06 Word A5 format. S1: Removed relay modules. S2: Added MI010. S4.1: added
DENVER PUBLIC SCHOOLS DESIGN AND CONSTRUCTION STANDARDS This Standard is for guidance only. SECTION 17650 SECURITY SYSTEMS
PART 0 DESIGN STANDARDS 0.01 GENERAL DESIGN GUIDELINES A. Inspections and observations by the Owner do not relieve the A/E of contract responsibilities. B. Chain of command 1. The DPS Project Manager is
identify hazards, analyze or evaluate the risk associated with that hazard, and determine appropriate ways to eliminate or control the hazard.
What is a risk assessment? Risk assessment is the process where you: identify hazards, analyze or evaluate the risk associated with that hazard, and determine appropriate ways to eliminate or control the
Operating Manual. Los Angeles Abrasion Machine HM-70A & HM-70AF
Operating Manual Los Angeles Abrasion Machine HM-70A & HM-70AF Rev: 07/19/2012 PHONE: 800-444-1508 P.O. Box 200, Lewis Center, Ohio 43035-0200 FAX: 800-255-5314 740-548-7298 E-mail: [email protected]
City Of Ottawa High Voltage Substation Inspection, Maintenance Rev 00 2015 July 17 and Testing, ROPEC Page 1
2015 July 17 and Testing, ROPEC Page 1 PART 1 GENERAL 1.1. Scope.1 Equipment replacement and testing for a 44 kv 4.16kV/600V substation: a. Replacement of Insulators as indicated on the drawings in Appendix
SECTION 16760 - PLANT INTERCOMMUNICATION SYSTEM. City of San Diego, CWP Guidelines
PART 1 - GENERAL SECTION 16760-1.1 WORK OF THIS SECTION City of San Diego, CWP Guidelines A. The WORK of this Section includes providing plant intercommunication systems with power supplies, signal amplifiers,
ITE/IMSA 2014 Spring Meeting March 6, 2014 Signal Maintenance Practices. Bruce E. Littleton, PE, PTOE Traffic Engineering Supervisor
ITE/IMSA 2014 Spring Meeting March 6, 2014 Signal Maintenance Practices Bruce E. Littleton, PE, PTOE Traffic Engineering Supervisor Traffic Signal Shop Mission Statement Construct, modify and maintain
OCCUPATIONAL SAFETY AND HEALTH PROGRAM
OCCUPATIONAL SAFETY AND HEALTH PROGRAM As stated in NFPA 1500, Standard on Fire Department Occupational Safety and Health Program, "Firefighting has been recognized as the most hazardous occupation in
SAFE ELECTRICAL WORK PRACTICES & 2015 NFPA 70E
SAFE ELECTRICAL WORK PRACTICES & 2015 NFPA 70E This easy-to-use Leader s Guide is provided to assist in conducting a successful presentation. Featured are: INTRODUCTION: A brief description of the program
Understanding Emergency Power Off (EPO)
Understanding Emergency Power Off (EPO) White Paper #22 Executive Summary Emergency Power Off (EPO) is the capability to power down a piece of electronic equipment or an entire installation from a single
STANDARD PRACTICE INSTRUCTION
STANDARD PRACTICE INSTRUCTION DATE: SUBJECT: Crane Safety Program REGULATORY STANDARD: OSHA 29 CFR 1910.179 Overhead and Gantry Cranes OSHA 29 CFR 1926.550 Cranes and Derricks OSHA 29 CFR 1903.1 (The General
POTENTIAL HEALTH & SAFETY HAZARDS
Number: OH&S 18.27.1 Revision Date: 2014.01.28 Crane Safety Procedures 1. PURPOSE 1.1. These procedures provide the University requirements for the operation and management of overhead travelling cranes
TEMPORARY EMPLOYEES SAFETY PROCEDURES
TEMPORARY EMPLOYEES SAFETY PROCEDURES Temporary Agencies will ensure that any temporary employee sent to work at Modern will have received and understand the General Safety Rules. GENERAL SAFETY RULES
Preventative Maintenance Policy
Section 7 - Preventative Maintenance Preventative Maintenance Policy It is the Company Policy of to ensure that all equipment, vehicles, and tools are properly maintained in a condition that will maximize
Installation Instructions for Alarm Module Kit A043F059
Instruction Sheet 07-2013 Installation Instructions for Alarm Module Kit A043F059 1 Introduction The information contained within is based on information available at the time of going to print. In line
SECTION 16721 FIRE ALARM AND SMOKE DETECTION SYSTEMS
SECTION 16721 PART 1 - GENERAL 1.1 SECTION INCLUDES A. Fire Alarm Control Panels B. Manual Fire Alarm Stations C. Automatic Smoke D. Fire Alarm Notification Appliances E. Auxiliary Fire Alarm Equipment
Backup Fuel Oil System Decommissioning & Restoration Plan
Backup Fuel Oil System Page 1 of 19 Overview of Physical Fuel Oil System and Decommissioning Steps The fuel oil system at Milford Power consists of a number of subsystems. These include the following:
To: All Shipowners, Ship Managers, Ship Masters and Classification Societies
海 事 處 船 舶 事 務 科 香 港 中 環 統 一 碼 頭 道 38 號 海 港 政 府 大 樓 ---------- 香 港 郵 箱 4155 號 MARINE DEPARTMENT Shipping Division Harbour Building 38 Pier Road, Central, Hong Kong ----------- G.P.O.Box 4155 網 站 Website
TLIB3078A Inspect, prepare and start an electric tram
TLIB3078A Inspect, prepare and start an electric tram Release: 1 TLIB3078A Inspect, prepare and start an electric tram Modification History Not Applicable Unit Descriptor Unit Descriptor This unit involves
Guide to the electrical parameter classifications of IEC 60950 and IEC 62368 safety standards
Guide to the electrical parameter classifications of IEC 60950 and IEC 62368 safety standards Abstract This Guide is an informative listing of selected terms and definitions found in IEC Glossary entry
Water Leak Detection System
Water Leak Detection System Installation and Operating Manual 505-334-5865 ph 505-334-5867 fax www.rodisystems.com email:[email protected] 936 Highway 516 Aztec, NM 87410-2828 Manual Revisions and Copyright
BroadBand PowerShield. User Manual
BroadBand PowerShield User Manual 990-0375G 12/2006 Chapter 1 General Information The PowerShield provides a power source for broadband telephony and other DC applications. Safety This Safety Guide contains
SECTION 16720 - FIRE AND SMOKE ALARM SYSTEM. City of San Diego, CWP Guidelines
PART 1 -- GENERAL 1.1 WORK OF THIS SECTION SECTION 16720 - City of San Diego, CWP Guidelines A. The WORK of this Section includes providing manual and automatic fire alarm and smoke detection systems meeting
Additional information: -OSHA Instruction CPL 2.103, Field Inspection Reference Manual, Chapter IV, Section A -29 CFR 1910, Subpart I, Appendix B
1 Additional information: -OSHA Instruction CPL 2.103, Field Inspection Reference Manual, Chapter IV, Section A -29 CFR 1910, Subpart I, Appendix B -1910.1000(e) 2 1910.132(h) 72 FR 64341, Nov. 15, 2007
NELSON VOLTAGE MONITOR INSTALLATION & PROGRAMMING MANUAL
NELSON VOLTAGE MONITOR INSTALLATION & PROGRAMMING MANUAL CONTENTS GENERAL INFORMATION...3 INSTALLATION...3 FIELD WIRING...4 PROGRAMMING...4 Circuit Monitor Options...5 Power Frequency...5 Alarm Silence
Module 4, Lesson 12 Fire Alarm Systems
Student Manual Module 4, Lesson 12 Fire Alarm Systems Performance Objectives At the conclusion of this lesson, you will be able to: Identify the components and functions of a fire alarm system and determine
BUILDING OWNERS - SERVICE RELATED ISSUES FOR FIRE ALARM SYSTEMS
BUILDING OWNERS - SERVICE RELATED ISSUES FOR FIRE ALARM SYSTEMS Owners have numerous responsibilities as it pertains to the maintenance and operation of a building s fire safety equipment. The liabilities
Fire Alarm System Monitoring - CAN/ULC-S561-03
Fire Alarm System Monitoring - CAN/ULC-S561-03 Brian McBain ULC Regulatory Services May 4, 2011 Copyright 1995-2007 Underwriters' Laboratories of Canada. All rights reserved. No portion of this material
Wiser Panel Meter, Model Number WISERCTPM200 Installer s Guide
Instruction Bulletin EAV85226 08/2014 Wiser Panel Meter, Model Number WISERCTPM200 Installer s Guide Retain for future use. Product Description Kit Contents The Wiser Panel Meter is for use in energy management
Unit Title: Unit purpose and aim
Unit Title: Preparing and Operating Telescopic Handlers to Lift and Transfer Loads in the Workplace Level: 2 Credit value: 25 Guided learning hours: 83 Unit expiry date: 31/10/2014 Unit purpose and aim
Unit Title: Unit purpose and aim
Unit Title: Preparing and Operating Sideloader Forklifts to Lift and Transfer Loads in the Workplace Level: 2 Credit value: 16 Guided learning hours: 53 Unit expiry date: 31/10/2014 Unit purpose and aim
CONSULTANT PROCEDURES & DESIGN GUIDELINES 28 13 00 ACCESS CONTROL SYSTEM
GENERAL: To provide minimum standards for Access Control Systems. PART 1 Common Work Results for Access Control System 1.1 Owner will provide server and software for connecting control panels through the
Safety and Health Resource Manual. Sample Permit-Required Confined Space Written Program
Sample Permit-Required Confined Space Written Program Purpose The purpose of this document is to communicate Employer s compliance with MIOSHA s requirements for a permit-required confined space entry
SOLAR PV SYSTEM MAINTENANCE GUIDE
SOLAR PV SYSTEM MAINTENANCE GUIDE GUYANA HINTERLANDS STAND-ALONE SOLAR PV INSTALLATIONS IMPROVING HEALTH FACILITY INFRASTRUCTURE (IHFI) GUYANA CONTRACT NO. EPP-I-00-03-00008-00, TASK ORDER 07 APRIL 2013
Owner s Manual & Safety Instructions
Owner s Manual & Safety Instructions Save This Manual Keep this manual for the safety warnings and precautions, assembly, operating, inspection, maintenance and cleaning procedures. Write the product s
WORLDWIDE. GW400k SERIES MAINTENANCE MANUAL PROVEN PERIMETER PROTECTION
ORLDIDE G400k SERIES MAINTENANCE MANUAL PROVEN PERIMETER PROTECTION GEOQUIP LIMITED Kingsfield Industrial Estate, Derby Road irksworth, Matlock, Derbyshire, DE4 4BG Tel : 01629 824891 Fax : 01629 824896
Safety Training Topic PERSONAL PROTECTIVE EQUIPMENT
Safety Training Topic PERSONAL PROTECTIVE EQUIPMENT Purpose of Meeting To remind workers that using personal protective equipment (PPE) can protect them from serious injury. To reince PPE safety rules.
FIREFINDER XLS ADDRESSABLE FIRE ALARM SYSTEM SECTION 13851
FIREFINDER XLS ADDRESSABLE FIRE ALARM SYSTEM SECTION 13851 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and
The Pennsylvania State University ------------- Physical Security Office. Intrusion Alarm. Performance Specification
The Pennsylvania State University ------------- Physical Security Office Intrusion Alarm Performance Specification By PHYSICAL SECURITY OFFICE Group (Access Controls & Electronic Security Programs) and
Clean Water: Supply side potable water, not wastewater. Gray Water/Sewage: Wastewater originating from a drain (sink, toilet, urinal).
Procedures for Emergency Responses to Flooding and Building Water Intrusion PURPOSE: To establish uniform, sanitary, and systematic procedures for responding to flooding and water intrusion emergencies.
Model UT33A: OPERATING MANUAL Table of Contents (1)
Table of Contents (1) Title Overview Unpacking Inspection Safety Information Rules For Safe Operation International Electrical Symbols The Meter structure Functional Buttons LCD Display Measurement Operation
HG600/HG800. Hydro-Power Unit. Installation and Operation Guide
HG600/HG800 Hydro-Power Unit Installation and Operation Guide Copyright 04 HydroSpin, All rights reserved. The data contained in this document is proprietary to HydroSpin. It is disclosed to the receiving
Instructions For SF 6 Refill Kit
S&C Vista Underground Distribution Switchgear UnderCover, Vault-Mounted, and Pad-Mounted Styles Instructions For SF 6 Refill Kit TABLE OF CONTENTS Section Page Section Page INTRODUCTION..................................
ORDINANCE NO. 2124 BE IT ORDAINED BY THE MAYOR AND CITY COUNCIL OF THE CITY OF YORK, NEBRASKA:
ORDINANCE NO. 2124 AN ORDINANCE OF THE CITY OF YORK, NEBRASKA TO ENACT A SECTION TO REGULATE ALARM SYSTEMS, TO PROVIDE FOR THE ISSUANCE OF PERMITS, AND TO IMPOSE A PENALTY FOR THE VIOLATION OF THIS SECTION;
Pressure Vessels (Air Compressors) and LPG Tanks
Pressure Vessels (Air Compressors) and LPG Tanks 1. Identification of Workplace Hazard Any container, tank or vessel that contains pressurized material is a potential hazard to employees due to the force
Developing and Maintaining a Customer Service Culture
APTA STANDARDS DEVELOPMENT PROGRAM RECOMMENDED PRACTICE American Public Transportation Association 1666 K Street NW Washington, DC 20006 APTA BTS-BO-RP-004-09 Published December 31, 2009 APTA Bus Operations
FIRE CODE INTERPRETATION
FIRE CODE INTERPRETATION March 2008 ISSUE: Existing Fire Alarm Systems FCI-08-06 Page 1 of 9 The purpose of this bulletin is to identify conditions where a building fire alarm system may be subject to
Technical Description. Transistor D.C. Chopper Controller Type GS 24 S
Technical Description Transistor D.C. Chopper Controller Type GS 24 S Table of contents 1. Getting started guide 2. General information 2.1. Characteristics 2.2. Accessories 3. Information about the Machine
Release: 1. PRSTS303A Test installed security equipment/system
Release: 1 PRSTS303A Test installed security equipment/system PRSTS303A Test installed security equipment/system Modification History Not applicable. Unit Descriptor This competency standard covers the
Topics of the Presentation
Drill Rig Safety Topics of the Presentation Personnel safety and monitoring PPE Health (Drugs and Alcohol) Drill Rig operation Safe set up procedures Safe operation of machine Safety related accidents
HERNANDO COUNTY FIRE ALARM GUIDELINES
HERNANDO COUNTY FIRE ALARM GUIDELINES To be used for all commercial building fire alarm system plan review. The procedures set forth in this document are the minimum requirements necessary to ensure a
Consortiwm Awdurdodau Lleol Cymru Consortium Local Authorities Wales
Consortiwm Awdurdodau Lleol Cymru Consortium Local Authorities Wales SPECIFICATION FOR LAUNDRY EQUIPMENT MAINTENANCE Maintenance Module 32 March 2011 issue This document has been compiled by the Engineering
Technical Update TAA.TU.11093 Rev. 1
http://www.gambro.com/en/usa_tech/ 800-525-2623 303-222-6500 Technical Update TAA.TU.11093 Rev. 1 Effective: 05 APR 2013 CO# 13084 Product: Subject: From: Phoenix Dialysis System Required Electrical Safety
V1504 Vertical Platform Lift OWNER S MANUAL
V1504 Vertical Platform Lift OWNER S MANUAL (To Be Retained by Owner After Installation by Authorized Savaria Dealer) Part No. 000692 03-m12-2013 2 IMPORTANT Ensure that only an authorized Savaria Dealer
This equipment has been tested and found to comply with the limits for a Class B digital device, pursuant to part 15 of the FCC Rules.
Power Max Level 2 Charging Station en Installation and Operating Instructions This equipment has been tested and found to comply with the limits for a Class B digital device, pursuant to part 15 of the
Engineers Edge, LLC PDH & Professional Training
510 N. Crosslane Rd. Monroe, Georgia 30656 (770) 266-6915 fax (678) 643-1758 Engineers Edge, LLC PDH & Professional Training Copyright, All Rights Reserved Engineers Edge, LLC An Introduction to Communication
Advantium 2 Plus Alarm
ADI 9510-B Advantium 2 Plus Alarm INSTALLATION AND OPERATING INSTRUCTIONS Carefully Read These Instructions Before Operating Carefully Read These Controls Corporation of America 1501 Harpers Road Virginia
INDUSTRY WIDE LABOR-MANAGEMENT SAFETY COMMITTEE SAFETY BULLETIN #23
INDUSTRY WIDE LABOR-MANAGEMENT SAFETY COMMITTEE SAFETY BULLETIN #23 GUIDELINES FOR WORKING WITH PORTABLE POWER DISTRIBUTION SYSTEMS AND OTHER ELECTRICAL EQUIPMENT "ADDENDUM C" WORKING WITH 480 VOLT SYSTEMS
Tech Shop Safety Level 2 - FN000425. Tech Shop / Tool Safety Operations. (Fermilab machines not covered in course FN000258)
Tech Shop Safety Level 2 - FN000425 Tech Shop / Tool Safety Operations (Fermilab machines not covered in course FN000258) Table of Contents Tech Shop / Tool Safety Operations 3 General Rules of Safety
PowerFlex 700S and 700H Frame 12 DC Bus Connector Kit
PowerFlex 700S and 700H Frame 12 DC Bus Connector Kit Installation Instructions This document provides instructions for the installation of a DC bus connector kit for PowerFlex 700S and 700H frame 12 drives
SOUTH CAROLINA. Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard)
SOUTH CAROLINA Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard) 1. Overview: This Standard contains the requirements, in addition
DORMA MODEL PS-406BB POWER SUPPLY INSTALLATION INSTRUCTIONS
Features: INSTALLATION Install in accordance with NFPA 70. DORMA MODEL PS-406BB POWER SUPPLY INSTALLATION INSTRUCTIONS Up to 1.95 Amps Load Capacity Class 2 Rated Outputs Overload, Over Voltage, and Short
Water Leak 1: Intrusion Policy
Water Leak 1: Intrusion Policy {Non-Casualty) 1. Determine Source of Leak Roof Leak- 11 See roof leak" Pressured Pipe leak- 11 See pressured pipe leak" Water Intrusion- See 11 see Water Intrusion leak"
D. Infrared scanning reports with pictures printed in a final report with any deficiencies and actions taken to rectify.
SECTION 263354 STATIC UPS TESTING AND COMMISSIONING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes 1. System start-up services. 2. Battery charging. 3. Load bank testing. 4. Battery load testing. 5.
FVSU-33201301 REPAIR & UPGRADE FIBER OPTIC 280000-1 SECTION 280000 FIRE ALARM SYSTEM CONNECTIVITY
FVSU-33201301 REPAIR & UPGRADE FIBER OPTIC 280000-1 SECTION 280000 FIRE ALARM SYSTEM CONNECTIVITY PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Fire-alarm control unit. 2. Addressable interface
Construction Notification and Start-Up
The University of British Columbia Land and Building Services Prepared by: Frank Geyer Work Procedure Approved by: David Barnes Construction Notification and Start-Up Issue Date: 08 October 2002 Replaces: