Facility Operations Integration

Size: px
Start display at page:

Download "Facility Operations Integration"

Transcription

1 Facility Operations Integration James Bartone, Schneider Electric Kevin Dalton, Digital Realty Trust Philip Beatty, Bradford Engineers Jason Schafer, Schneider Electric Michael Jordan, Vantage Data Centers

2 Program Summary Facility Operations Integration during design, construction, commissioning, and sustained operations Facilitated discussion of industry experts representing the following perspectives: DC Owner/Developer DC Designer DC Commissioning Consultant DC Facilities Operator

3 Problem Statement Universal DC Industry Problem Inadequate or inaccurate Facility Operations Documentation results in non-optimized data center performance due to uncertainty or lack of information Process Issue Lack of operational focus & required documentation during design and construction Incompatible data collection formats utilized during design, construction, and commissioning Inadequately specified requirements for operational documents turnover at project completion Non-integrated change management system

4 Recommendation A new TGG white paper provides prescriptive measures for better data collection, integration, and change management practices throughout the entire facility lifecycle Defines required operational documents for turnover to Facility Operations team Recommends employing a commissioning consultant from schematic design phase through Go Live turnover Presents a formulated approach for producing a holistic facility sequence of operations manual that is delivered to the Facility Operations team at turnover

5 Sequence of Operations Sequence of Operations and the Data Center Lifecycle Planning & Programming Design Construction Commission Turnover & Transition Operations Site Analysis Elec. Coord n Study Project Summary QA/QC Inspections O & M Manuals QA/QC Procedures MOPS, SOPs, EOPs Environmental Reports Arc Flash Study Shop Drawings Functional Test Scripts Vendor Contact List Training Materials (Drills, Classes, etc.) Owner s Project Requirements CFD Air Flow Model Submittals Integrated Systems Test Report Spare Parts List Training Records & Certification Building Program IFC Drawings Equipment List Issue Resolution Log As-Built Drawings Maintenance History (CMMS) Basis of Design Specifications Change Order Log Commissioning Report Control Network Diagrams Project Impact Analysis Cx Plan & Ops Sequences Punch List Update Systems Diagrams Panel Schedules Updated OpDocs & SOO Regulatory Documents Permits Inspection Reports Cert. of Substantial Completion Update Systems Narrative Sequence of Ops Manual Software Back-up Disks Change Control Log Certificate of Occupancy Warranties

6 Introductions Moderator: Owner: Designer: Commissioner: Operator: James Bartone Schneider Electric Kevin Dalton Digital Realty Trust Philip Beatty Bradford Engineers Jason Schafer Schneider Electric Michael Jordan Vantage Data Centers

7 FOI Survey Question #1 SEQUENCE OF OPERATIONS Do you have written Sequences of Operations for the Power and Cooling systems in your data center (i.e. documentation beyond electrical oneline drawings, HVAC control diagrams & O&M manuals)? Yes No cc36d0ad37af8eaa4da

8 FOI Survey Question # 2 FACILITY INFORMATION MODEL How would you best describe your current Facility Information Model? A. Blueprints and 2D drawing files + O&Ms B. 3D CADD drawing files + O&Ms C. BIM (3D Building Information Model) 7f5f59c6821a13e48

9 FOI Survey Question # 3 INFRASTRUCTURE MANAGEMENT How would you describe your critical infrastructure management system? A. No formal systems in place. B. Multiple separate systems monitored on separate screens (i.e. EPMS, BMS, etc.) C. DCIM ( single pane monitoring and control of multiple systems) e5f8660da03116a6

10 FOI Survey Question # 4 DCIM STANDARDS When do you foresee an industry accepted DCIM standard? A. 2 Years B. 5 Years C. 10 Years e25d018

11 Read the New Whitepaper The Green Grid White Paper #52 An Integrated Approach to Operational Efficiency and Reliability at:

A Framework for Developing and Evaluating Data Center Maintenance Programs

A Framework for Developing and Evaluating Data Center Maintenance Programs A Framework for Developing and Evaluating Data Center Maintenance Programs White Paper 178 Revision 0 by Bob Woolley > Executive summary Inadequate maintenance and risk mitigation processes can quickly

More information

Denver International Airport Data Center Commissioning Plan

Denver International Airport Data Center Commissioning Plan Denver International Airport Data Center Jefferson County School District Columbine High School Renovation Date July 25th, 2014 Prepared by Patrick Corrigan, QCxP Commissioning Engineer McKinstry McKINSTRY

More information

Project Management Plan for

Project Management Plan for Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...

More information

ASSET Connect. The next level in Critical Environment Operational Efficiency

ASSET Connect. The next level in Critical Environment Operational Efficiency Connect The next level in Critical Environment Operational Efficiency 10-30% is the potential efficiency gain from optimized Data Centers and Critical Environments Operational Efficiency of Your Critical

More information

Construction Management Standards of Practice

Construction Management Standards of Practice Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388

More information

Energy Design Resources Commissioning Plan Outline Template

Energy Design Resources Commissioning Plan Outline Template IMPORTANT NOTICE: This sample document is provided for instructional purposes only. CCC is not rendering advice concerning any commission project or practices. This document is neither approved nor intended

More information

Modeling Building Automation and Control Systems Jim Sinopoli, Managing Principal Smart Buildings, LLC

Modeling Building Automation and Control Systems Jim Sinopoli, Managing Principal Smart Buildings, LLC Modeling Building Automation and Control Systems Jim Sinopoli, Managing Principal Smart Buildings, LLC 2013 Many building owners and facility managers lack good documentation for their automation control

More information

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES A. The Owner will contract separately and directly for the majority of the commissioning work

More information

Commissioning of Mission Critical Facilities

Commissioning of Mission Critical Facilities Commissioning of Mission Critical Facilities Terry L. Rodgers, CPE, CPMP VP of Sustainable Operations Primary Integration Solutions Paul Liesman SVP of FM & Commissioning Syska Hennessy Group AIA Quality

More information

Commissioning of Fire Protection and Life Safety Systems. Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA

Commissioning of Fire Protection and Life Safety Systems. Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA Commissioning of Fire Protection and Life Safety Systems Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA Fire Protection Engineering s role in sustainability through Commissioning

More information

Volume II- Project Development Processes

Volume II- Project Development Processes Volume II- Project Development Processes This section outlines the procedures that are expected of capital projects at The University of Chicago. These requirements supplement the planning procedures required

More information

Delivering results with Datacenter Clarity LC TM

Delivering results with Datacenter Clarity LC TM Philippe Heim Boston, September 9th, 2015 Delivering results with Datacenter Clarity LC TM siemens.com Intro movie Page 2 20XX-XX-XX Table of contents 1 Challenges 2 Integrated DCIM solution overview 3

More information

CA/NV AWWA SCADA Seminar SCADA Master Planning. Presented by: Philip Gaberdiel Cell: 818-843-1855 ext. 8435 phil.gaberdiel@we-inc.

CA/NV AWWA SCADA Seminar SCADA Master Planning. Presented by: Philip Gaberdiel Cell: 818-843-1855 ext. 8435 phil.gaberdiel@we-inc. CA/NV AWWA SCADA Seminar SCADA Master Planning Presented by: Philip Gaberdiel Cell: 818-843-1855 ext. 8435 [email protected] Presentation Outline SCADA Master Plan Goals and Objectives SCADA Master

More information

Top 10 Mistakes in Data Center Operations. Eric Gallant Regional Director Lee Technologies

Top 10 Mistakes in Data Center Operations. Eric Gallant Regional Director Lee Technologies Top 10 Mistakes in Data Center Operations Eric Gallant Regional Director Lee Technologies Lee Technologies AGENDA Lee s Top 10 Working Group Breakouts Group 1 - Feedback of Top 10 Group 2 - What Can We

More information

Data Center Commissioning: What you need to know

Data Center Commissioning: What you need to know Data Center Commissioning: What you need to know Course # CXENERGY1511 AIA Provider # 50111116 AABC Commissioning Group CxEnergy Conference Henderson, NV April 30, 2015 Presented by: Judson H. Adams, P.E.,

More information

Safety Plan Reviews in 3D Christopher Santulli, PE. April 23, 2012 Times Square Marriott Marquis

Safety Plan Reviews in 3D Christopher Santulli, PE. April 23, 2012 Times Square Marriott Marquis Safety Plan Reviews in 3D Christopher Santulli, PE April 23, 2012 Times Square Marriott Marquis Safety Responsibility Building Code 3301.1 Responsibility for safety (abbr.) Nothing in this chapter shall

More information

Managing risk in construction projects how to achieve a successful outcome*

Managing risk in construction projects how to achieve a successful outcome* how to achieve a successful outcome* Project risk and controls Slaying the dragon Scott Jardine *connectedthinking PwC Contents Background to the dragon Project risk management Project controls Background

More information

4.4 Commissioning, Handover and Warranty

4.4 Commissioning, Handover and Warranty 4.4 Commissioning, Handover and Warranty 4.4.1 Building Commissioning and Manuals The Building Commissioning formalizes the review and integration of all project expectations during the planning and design,

More information

Introducing eco_dc_expert Group to Decathlon TM

Introducing eco_dc_expert Group to Decathlon TM Febr. 2013 Klaus Landl EMEA Datacenter-Systems-DCIM Introducing eco_dc_expert Group to Decathlon TM ABB Group February 9, 2013 Slide 1 ABB Data Center Landscape News: ABB ranked #1 Smart Grid company to

More information

Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive

Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86

More information

COMMISSIONING OF FIRE ALARM SYSTEMS

COMMISSIONING OF FIRE ALARM SYSTEMS COMMISSIONING OF FIRE ALARM SYSTEMS OWNER FURNISHED The owner directly contracts an independent third party commissioning agent for this project. This Commissioning Plan has been included for reference

More information

Commissioning Fundamentals and a Practical Approach

Commissioning Fundamentals and a Practical Approach PDHonline Course P146 (2 PDH) Commissioning Fundamentals and a Practical Approach Instructor: Timothy D. Blackburn, MBA, PE 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone

More information

Incorporating BIM into Facilities Management

Incorporating BIM into Facilities Management Incorporating BIM into Facilities Management Greg Alevras, VP of Business Development, North America Sam Arabia CM-BIM, Director, Torcon Facilities Solutions Meet Our Presenter(s): Greg Alevras - ARCHIBUS

More information

ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan)

ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan) ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan) Part 1: Project-Specific Quality Plan Part 2: Company Quality Manual Part 3: Submittal Forms Part 4:

More information

Process Plant Construction: A Handbook for Quality Management

Process Plant Construction: A Handbook for Quality Management Process Plant Construction: A Handbook for Quality Management Process Plant Construction: A Handbook for Quality Management Patrick Noble ISBN: 978-1-4051-8725-1 Hardcover 232 pages January 2009, Wiley-Blackwell

More information

Top 10 Mistakes in Data Center Operations: Operating Efficient and Effective Data Centers

Top 10 Mistakes in Data Center Operations: Operating Efficient and Effective Data Centers Top 10 Mistakes in Data Center Operations: Operating Efficient and Effective Data White Paper 2 Revision 0 by Bob Woolley > Executive summary How can you avoid making major mistakes when operating and

More information

WESTERN MICHIGAN UNIVERSITY

WESTERN MICHIGAN UNIVERSITY WESTERN MICHIGAN UNIVERSITY Facilities Management Department DeVon Miller Building Commissioning Administrator 1 INTRODUCTION DeVon C. Miller, CPMP, LEED AP Building Commissioning Administrator Engineering

More information

Exhibit C: Scope of Work and Schedule of Deliverables

Exhibit C: Scope of Work and Schedule of Deliverables Exhibit C: Scope of Work and Schedule of Deliverables Project Scope of Work Phases: A City Hall Envelope Renovations B City Hall Skylight Replacement C City Hall Chiller Replacement D City Hall Annex Plaza

More information

Mecklenburg County. Electronic Plans. Management (EPM) System. Customer User Guide

Mecklenburg County. Electronic Plans. Management (EPM) System. Customer User Guide Mecklenburg County Electronic Plans Management (EPM) System Customer User Guide Version: 2.0 Updated March 14, 2012 Table of Contents 1 - Introduction...3 1.1 Overview...3 1.2 Technical Requirements...3

More information

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project. DIVISION 23 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) SECTION 23 08 02 PART 1 GENERAL 1.01 AUTHORITY (CxA) A. The Commissioning Authority (CxA) has been contracted or will be contracted directly

More information

City of Raleigh Public Utilities Department. Wastewater EMS Manual

City of Raleigh Public Utilities Department. Wastewater EMS Manual City of Raleigh Public Utilities Department Wastewater EMS Manual TABLE OF CONTENTS PAGE 2 Wastewater EMS Manual Table of Contents Management Direction 1) EMS Manual 2) Management Policy Planning 3) Process

More information

Understanding Power Usage Effectiveness (PUE) & Data Center Infrastructure Management (DCIM)

Understanding Power Usage Effectiveness (PUE) & Data Center Infrastructure Management (DCIM) Understanding Power Usage Effectiveness (PUE) & Data Center Infrastructure Management (DCIM) Salim Janbeh Physical Infrastructure Consultant [email protected] PANDUIT You Can t Manage What You Don t Measure:

More information

The Hitchhikers Guide to Data Center Facility Operations

The Hitchhikers Guide to Data Center Facility Operations by Steven Manos The Hitchhikers Guide to Data Center Facility Operations The following is a very simplistic list of the types of questions/criteria any organization should consider in evaluating the outsourcing

More information

S c h n e i d e r E l e c t r i c BUSINESS IMPACT. Jack Hack Enterprise System Engineer 19 November 2015

S c h n e i d e r E l e c t r i c BUSINESS IMPACT. Jack Hack Enterprise System Engineer 19 November 2015 S c h n e i d e r E l e c t r i c BUSINESS IMPACT Datacenter means business - create the bridge between IT en Facilities. Jack Hack Enterprise System Engineer 19 November 2015 1 Your ability to compete

More information

GRAFIK 5000TM/6000 /7000TM System Onsite Startup

GRAFIK 5000TM/6000 /7000TM System Onsite Startup 369625c 1 04.04.13 GRAFIK 5000TM/6000 /7000TM System What Standard GRAFIK 5000TM/6000 /7000TM Startup includes: Three visits to the job site during normal business hours. A pre-wire visit, a Startup visit,

More information

The Building Commissioning Association

The Building Commissioning Association Best Practices in Commissioning Existing Buildings Building Commissioning Association EXECUTIVE SUMMARY The Building Commissioning Association (BCA) defines Existing Building Commissioning (EBCx) as: a

More information

Guide Specification SECTION 23 08 00 - COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY

Guide Specification SECTION 23 08 00 - COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY SECTION 23 08 00 - COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. HVAC Commissioning description. 2. HVAC Commissioning responsibilities. 1.2 REFERENCES A. American Society

More information

Commissioning Plan Preparation Guide. Version 2.0 (Replaces Project Test Plans Preparation Guide, Version 1.0, September 2012)

Commissioning Plan Preparation Guide. Version 2.0 (Replaces Project Test Plans Preparation Guide, Version 1.0, September 2012) Commissioning Plan Preparation Guide Version 2.0 (Replaces Project Test Plans Preparation Guide, Version 1.0, September 2012) September 2013 Commissioning Plan Preparation Guide Contents 1.0 Introduction...

More information

Building Commissioning 17900-1

Building Commissioning 17900-1 SECTION 17900 BUILDING COMMISSIONING PART 1 - GENERAL 1.01 WORK DESCRIPTION: A. General: 1. The Commissioning process is a joint team effort to ensure that all mechanical equipment, controls, and systems

More information

The Life-Cycle of Commissioning for New Construction

The Life-Cycle of Commissioning for New Construction The Life-Cycle of Commissioning for New Construction A Case Study at NGA Campus East Owner/Facility Manager: Dan Kailey and Matt Burkholder National Geospatial-Intelligence Agency (NGA) Commissioning Service

More information

Data center management suite. Providing optimal control and efficiency to data center management. www.siemens.com/datacenters

Data center management suite. Providing optimal control and efficiency to data center management. www.siemens.com/datacenters Data center management suite Providing optimal control and efficiency to data center management www.siemens.com/datacenters Streamline operations with Siemens suite of integrated management tools You work

More information

H.V.A.C. Design Plumbing Design

H.V.A.C. Design Plumbing Design H.V.A.C. Design H.V.A.C. Design Mira Costa College Arts Complex CP Upgrade 1. PART 1 GENERAL 1.1. DESCRIPTION SECTION 23 09 00 HVAC INSTRUMENTATION AND CONTROL 2. PART 2 - PRODUCTS 2.1. Materials

More information

Design Consultant Project Management Requirements

Design Consultant Project Management Requirements Design Consultant Project Management Requirements Version 2 April 25, 2013 AWTP Program Design Consultant Contents 1.0 Introduction... 1 2.0 General Management... 1 3.0 Project Management Plan... 1 4.0

More information

National Environmental Balancing Bureau 8575 Grovemont Circle Gaithersburg, MD 20877-4121 ph: 301-977-3698 fax: 301-977-9589 www.nebb.

National Environmental Balancing Bureau 8575 Grovemont Circle Gaithersburg, MD 20877-4121 ph: 301-977-3698 fax: 301-977-9589 www.nebb. National Environmental Balancing Bureau 8575 Grovemont Circle Gaithersburg, MD 20877-4121 ph: 301-977-3698 fax: 301-977-9589 www.nebb.org PROCEDURAL STANDARDS FOR WHOLE BUILDING SYSTEMS COMMISSIONING

More information

1 The quality management system (QMS) is the corner stone of compliance to GMP. The QMS is made up of several documents, that when followed ensures the GMP compliance of the process, facility and company.

More information

Revised Work Scope Dated April 23 rd, 2015

Revised Work Scope Dated April 23 rd, 2015 Revised Work Scope Dated April 23 rd, 2015 2.4 SCOPE OF SERVICES The following combines the Scope of Services included in RFQ No. 671 dated March 12, 2015 and the Invitation to Interview letter dated March

More information

How to Monitor Large & Live Data Centers. PI makes data centers Green!

How to Monitor Large & Live Data Centers. PI makes data centers Green! How to Monitor Large & Live Data Centers PI makes data centers Green! Introduction On an average day, someone on ebay - sells a vehicle every minute - sells auto parts every second - sells diamond jewelry

More information

Construction Project Management Software UserView. Lessons from real software users

Construction Project Management Software UserView. Lessons from real software users Construction Project Management Software UserView Lessons from real software users Abstract We surveyed construction professionals for three months to better understand the use and effectiveness of software

More information

FIRE ALARM SYSTEM SUBMITTAL CHECKLIST AND APPLICATION

FIRE ALARM SYSTEM SUBMITTAL CHECKLIST AND APPLICATION PERMITS AND INSPECTIONS FIRE ALARM SYSTEM SUBMITTAL CHECKLIST AND APPLICATION 911 Assigned PROJECT LOCATION Subdivision: Lot: Blk: Sec: PROJECT New Construction Addition/Remodel Demolition Other: Number

More information

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES. Part I: Qualifications Information

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES. Part I: Qualifications Information REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES A. General Information Part I: Qualifications Information The Tacoma School District is soliciting Qualifications for onsite

More information

Project Start Up. Start-Up Check List. Why a Project Check List? What is a Project Check List? Initial Release 1.0 Date: January 1997

Project Start Up. Start-Up Check List. Why a Project Check List? What is a Project Check List? Initial Release 1.0 Date: January 1997 Why a Project Check List? A good way to ensure that all start-up tasks are completed prior to actually starting the project is to develop a start-up check list. The check list can be developed and then

More information

Solar Home System. User Manual. AEH-SHS01-10W2L Solar Home System 2 Lamps

Solar Home System. User Manual. AEH-SHS01-10W2L Solar Home System 2 Lamps Solar Home System User Manual AEHSHS0110W2L Solar Home System 2 Lamps All rights reserved Specifications subject to change without prior notice 2 Dear Customer, Thank you for purchasing Schneider Electric

More information

Asset management it s a simple concept. Know your system s

Asset management it s a simple concept. Know your system s Asset Management for Small Communities The Village of Weedsport Story by Timothy Taber and James Saroodis Asset management it s a simple concept. Know your system s assets equipment, pipes, machinery and

More information

California Department of Technology, Office of Technology Services WINDOWS SERVER GUIDELINE

California Department of Technology, Office of Technology Services WINDOWS SERVER GUIDELINE Table of Contents 1.0 GENERAL... 2 1.1 SUMMARY...2 1.2 REFERENCES...2 1.3 SUBMITTALS...2 1.3.1 General...2 1.3.2 Service Request...3 1.4 EXPECTATIONS...3 1.4.1 OTech...3 1.4.2 Customer...3 1.5 SCHEDULING...4

More information

Technical Specifications for West Campus Data Center HVAC System

Technical Specifications for West Campus Data Center HVAC System Technical Specifications for West Campus Data Center HVAC System I. Mechanical Systems Requirements A. HVAC Primary Data Centers, Automation HVAC is to be provided on a 24 hours per day, 365 days per year

More information

Visualization, Management & Optimization Keys for an efficient Data Center Sergio Uribe - CommScope

Visualization, Management & Optimization Keys for an efficient Data Center Sergio Uribe - CommScope Visualization, Management & Optimization Keys for an efficient Data Center Sergio Uribe - CommScope May 14,15-2014 Before to start Lopsided data center budget growth Allocating the cost of IT inefficiency

More information

BIM and Facilities Management

BIM and Facilities Management AUTODESK WHITEPAPER BIM and Facilities Management Building information modeling (BIM) is changing the way buildings are designed and constructed but is it changing how they re operated and maintained?

More information

BIM UNDERSTANDING THE PROCESS The State of the Art Tool in Design and Construction SPONSORED BY SAME, DC POST IN ASSOCIATION WITH ACEC M/W

BIM UNDERSTANDING THE PROCESS The State of the Art Tool in Design and Construction SPONSORED BY SAME, DC POST IN ASSOCIATION WITH ACEC M/W BIM UNDERSTANDING THE PROCESS The State of the Art Tool in Design and Construction SPONSORED BY SAME, DC POST IN ASSOCIATION WITH ACEC M/W Insanity: doing the same thing over and over again and expecting

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE DIVISION PROCEDURES MANUAL PROGRAM AND PROJECT MANAGEMENT

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE DIVISION PROCEDURES MANUAL PROGRAM AND PROJECT MANAGEMENT SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE DIVISION PROCEDURES MANUAL PROGRAM AND PROJECT MANAGEMENT SECTION 6: QUALITY ASSURANCE PROCEDURE: PM 6.02 TITLE: QUALITY ASSURANCE AUDITS DATE:

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services

More information

Powerful information management services and software for the oil, gas, and chemical industries

Powerful information management services and software for the oil, gas, and chemical industries Powerful information management services and software for the oil, gas, and chemical industries RELIEF SYSTEM SERVICES Provenance Consulting has relief system design experience in all aspects of the petrochemical

More information

Foreseer Services. Product application guide. Table of contents

Foreseer Services. Product application guide. Table of contents Product application guide Foreseer Services Table of contents 1.0 General.......................................... 2 1.1 What are Foreseer Software and Engineering Services.... 3 1.1.1 Foreseer Service

More information

Vendor Performance Evaluation Requirements

Vendor Performance Evaluation Requirements Vendor Performance Evaluation Requirements The awarded vendor should note that the Contract Administrator will document the contractor s performance by completing a Vendor Performance Evaluation based

More information

Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho

Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho REQUEST FOR QUALIFICATIONS Independent School District No. 1, Lewiston, Idaho ( District ) is seeking responses from individuals

More information

Datacenter Infrastructure Management (DCIM) Solution

Datacenter Infrastructure Management (DCIM) Solution Datacenter Infrastructure Management (DCIM) Solution Figure 1. Asset Management in 3D, Real-Time Reporting, CFD Modeling & Analysis Description Datacenter Clarity provides the tools to accurately and efficiently

More information

SECTION 25 15 16 INTEGRATED AUTOMATION SOFTWARE FOR CONTROL OF MONITORING NETWORKS

SECTION 25 15 16 INTEGRATED AUTOMATION SOFTWARE FOR CONTROL OF MONITORING NETWORKS SECTION 25 15 16 INTEGRATED AUTOMATION SOFTWARE FOR CONTROL OF MONITORING NETWORKS Specifier: The Specifier/Design Professional is responsible for the accuracy of all project specifications, including

More information

Project Close Out Summary

Project Close Out Summary Project Close Out Summary 1. Final Cleaning and Inspection 2. Testing and Certification 3. Demonstration of Systems and Equipment 4. Inspections by Authorities Having Jurisdiction 5. O&M Manuals and As

More information

Florida Power & Light Company. Business Heating Ventilation & Air Conditioning ( HVAC ) Program Standards. Effective: November 9, 2015

Florida Power & Light Company. Business Heating Ventilation & Air Conditioning ( HVAC ) Program Standards. Effective: November 9, 2015 Florida Power & Light Company Business Heating Ventilation & Air Conditioning ( HVAC ) Program Standards Effective: November 9, 2015 Table of Contents Eligibility Requirements - Chiller... 2 Rebate Amount

More information

Service Catalog. it s Managed Plan Service Catalog

Service Catalog. it s Managed Plan Service Catalog Service Catalog it s Managed Plan Service Catalog 6/18/2012 Document Contents Contents Document Contents... 2 Overview... 3 Purpose... 3 Product Description... 3 Plan Overview... 3 Tracking... 3 What is

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM

San Antonio Water System Standard Specifications for Construction ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM 903.1 DESCRIPTION: This item shall govern the preparation and implementation of the Contractor s Construction Quality Control/Quality Assurance (QC/QA) Program for

More information

The Real Cost of Manual Asset Management

The Real Cost of Manual Asset Management The Real Cost of Manual Asset Management No Limits Software White Paper #3 By David Cole 2011 No Limits Software. All rights reserved. No part of this publication may be used, reproduced, photocopied,

More information

Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK

Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK Facility Services Project Management Methodology Framework 1 - Executive Summary The purpose of this document is to introduce the University community

More information

through DCIM as a Datacenter Clarity LC powered by PI System

through DCIM as a Datacenter Clarity LC powered by PI System How provides Data Center Operation through DCIM as a with Datacenter Clarity LC powered by PI System Presented by Salvatore Cimmino, Claridion Inc. Rémi Duquette, MAYA HTT Ltd. About Claridion A 17 years

More information

HVAC MAINTENANCE SUPERVISOR (Range 121)

HVAC MAINTENANCE SUPERVISOR (Range 121) (Range 121) DEFINITION Supervises, plans, coordinates and performs a variety of fundamental and skilled work in the building and mechanical trades to ensure the overall physical integrity of District Locations.

More information

Top 10 Mistakes in Data Center operations:

Top 10 Mistakes in Data Center operations: Top 10 Mistakes in Data Center operations: Operating Efficient and Effective Data Centers By Lee Kirby Vice President, Business Development and Strategic Accounts Lee Technologies Top 10 Mistakes in Data

More information

Facility Safety and Emergency Management (FSE)

Facility Safety and Emergency Management (FSE) Facility Safety and Emergency Management (FSE) Standard FSE.1 [Safety and security] The organization plans and implements a program to provide a safe and secure physical environment. Intent of FSE.1 The

More information

12.4.1 Optional Lab: Schedule Task Using GUI and at Command in Windows 7

12.4.1 Optional Lab: Schedule Task Using GUI and at Command in Windows 7 12.4.1 Optional Lab: Schedule Task Using GUI and at Command in Windows 7 Introduction Print and complete this lab. In this lab, you will schedule a task using the Windows 7 GUI and schedule a task in a

More information

Phased Building Information Management (BIM) and Modeling Implementation Plan. David J. Gutierrez, AIA September, 2014

Phased Building Information Management (BIM) and Modeling Implementation Plan. David J. Gutierrez, AIA September, 2014 Phased Building Information Management (BIM) and Modeling Implementation Plan David J. Gutierrez, AIA September, 2014 1 Current State: Design and construction data is not shared, maintained, or updated

More information

Equipment Identification Process for PMCS

Equipment Identification Process for PMCS Equipment Identification Process for PMCS 1. Purpose: The Equipment Identification (EQ ID) Process provides a comprehensive maintenance service to our campus and is critical to our organization s purpose

More information

BlueCielo Meridian Today

BlueCielo Meridian Today BlueCielo Meridian Today Positioning of our current product portfolio BlueCielo Meridian Customer Day June 26, 2014 Gilze Rijen The Netherlands Edwin van Dijk, Business Solution Specialist BlueCielo ECM

More information

By the Citrix Publications Department. Citrix Systems, Inc.

By the Citrix Publications Department. Citrix Systems, Inc. Licensing: Setting Up the License Server on a Microsoft Cluster By the Citrix Publications Department Citrix Systems, Inc. Notice The information in this publication is subject to change without notice.

More information

Georgia School Boards Association. Risk Management Fund Claims Manual

Georgia School Boards Association. Risk Management Fund Claims Manual Georgia School Boards Association Risk Management Fund Claims Manual July 1, 2015 - June 30, 2016 Table of Contents Section GSBA Claims Services 1 GSBA Claim Team..2 GSBA Liability Claim Reporting Procedures..3

More information

Sedgwick White Paper Integrated Disability Management

Sedgwick White Paper Integrated Disability Management Sedgwick White Paper Integrated Disability Management claims and care management solutions / P. 1 Every day, valuable employees are absent from work resulting in lost productivity. It has never been more

More information

CalMod Design-Build Electrification Services

CalMod Design-Build Electrification Services SECTION 28 16 00 INTRUSION DETECTION SYSTEM PART 1 - GENERAL 1.1 DESCRIPTION A. This section describes the detailed technical requirements for the Intrusion Detection System (IDS), where the Contractor

More information

The Green Grid, Metrics and DCMM. Presented by: Jay Taylor

The Green Grid, Metrics and DCMM. Presented by: Jay Taylor The Green Grid, Metrics and DCMM Presented by: Jay Taylor About The Green Grid A not-for-profit international consortium committed to advancing resource efficiency in business computing ecosystems and

More information

T146 Electro Mechanical Engineering Technician MTCU Code 51021 Program Learning Outcomes

T146 Electro Mechanical Engineering Technician MTCU Code 51021 Program Learning Outcomes T146 Electro Mechanical Engineering Technician MTCU Code 51021 Program Learning Outcomes Synopsis of the Vocational Learning Outcomes* The graduate has reliably demonstrated the ability to: 1. fabricate

More information

DTW Works Master Specification Version 2006

DTW Works Master Specification Version 2006 Issued 2006/08/01 Section 13852 Multiplex Fire Alarm System Page 1 of 10 PART 1 GENERAL 1.1 RELATED WORK.1 Section 01330 Submittal Procedures..2 Section 01780 Closeout Procedures..3 Section 01810 Commissioning..4

More information