700 Life-Cycle Cost Analysis
|
|
|
- Alice Hopkins
- 10 years ago
- Views:
Transcription
1 Table of Contents 700 Life-Cycle Cost Analysis Introduction Discount Rate Initial Construction Future Rehabilitation Introduction Rehabilitation Schedules Flexible Pavement Rigid Pavement Composite Pavement Unbonded Concrete Overlay Fractured Slab Techniques Whitetopping Total Cost Discounting Results Presentation July 2014
2 700 Life-Cycle Cost Analysis 701 Introduction Life-Cycle Cost Analysis (LCCA) is a process for evaluating the economic worth of a pavement segment by analyzing initial costs and discounted future costs such as surface treatment, resurfacing, rehabilitation, and reconstruction costs over a defined analysis period. This section outlines some of the requirements for preparing an LCCA. Other details about the LCCA are given in Section Discount Rate ODOT uses the discount rate provided by the Office of Management and Budget (OMB) in Circular A-94. Specifically, the 30-year real interest rate is used. The current discount rate can be found on the OMB website at Initial Construction All alternatives for initial construction are designed using the procedures outlined in this Manual. Initial construction is considered to take place in year zero. All differential pavement items are to be included in the analysis such as excavation, stabilization, pavement removed, base, and pavement. Non-pavement items and items common to all alternatives can be neglected. Items such as striping, signing, lighting, guardrail, barrier, underdrains, culverts, bridges, embankment, etc., are not pavement items, are essentially equal for all alternatives and are not to be included in the analysis. On new locations, earthwork items including stabilization are common to all pavement alternatives and are essentially equal and are not to be included. For rehabilitations that raise the elevation of the existing pavement, a cost needs to be included for maintaining clearance under overhead structures and for meeting elevations of at-grade bridges. This cost can be calculated in various ways, most common is to calculate the cost to remove the existing pavement, excavate down, and build back up with new pavement. Another way is to calculate the cost of jacking the bridges, including any approach work necessary on overheads. A third option could be a combination of the two. It is not important which method is selected for computing cost of maintaining clearance. What is important is that the costs are included in the analysis. The same method of calculating the costs is to be used for all alternatives. The method used in the LCCA for computing cost of maintaining clearance does not have to be the actual method used in the plans and in construction. 703 Future Rehabilitation Introduction The future rehabilitation required to keep the pavement in serviceable condition for the next 35 years must be predicted. Routine and reactive maintenance performed by ODOT forces are not included in the analysis due in part to lack of dependable data. Only contract rehabilitation projects are considered. ODOT does not use salvage value. The rehabilitation schedules listed below result in approximately equal condition at the end of the analysis period. The salvage values are considered equal and are not included in the analysis. July
3 703.2 Rehabilitation Schedules The rehabilitation schedules given below were developed from an analysis of ODOT pavement performance data. The analysis will be updated periodically and the rehabilitation schedules updated accordingly. The schedules below are to be used without deviation. The schedules list only major items of work. The LCCA should include the specification items needed to complete the work described such as tack coats and pavement sawing Flexible Pavement Flexible pavement includes new pavement on a new alignment and complete replacement of existing pavement. Year 14: 1.5" overlay with planing (driving lanes only). Year 24: 3.25" overlay with planing (driving lanes and shoulders) with 1% patching planed surface. Year 34: 1.5" overlay with planing (driving lanes only) Rigid Pavement Rigid pavement includes new pavement on a new alignment and complete replacement of existing pavement. Year 22: Diamond grinding (driving lanes plus one foot of each shoulder) and full dept rigid repairs of 4% of the driving lanes surface area. Year 32: 3.25" asphalt overlay and full depth rigid repair of 2% of the driving lanes surface area Composite Pavement Composite pavement includes new pavement on a new alignment and complete replacement of existing pavement. The performance of newly constructed composite pavements has not been studied as relatively few have been constructed. Since composite pavement is a hybrid of rigid and flexible pavements, a hybrid rehabilitation schedule may be derived from the rigid and flexible schedules. The timing, width, and thickness of each rehabilitation shall be the same as the flexible pavement schedule given in Section A quantity of full depth rigid repairs equal to 2% of the driving lanes surface area shall be included with the overlay at years 14 and 34, and 3% at year Unbonded Concrete Overlay An unbonded concrete overlay is a new concrete pavement built on top of an old concrete pavement with a bondbreaker layer in between. The future rehabilitation schedule is the same as rigid pavement given in Section Fractured Slab Techniques Fractured slab techniques include crack & seat, and rubblize & roll. The future rehabilitation schedule for all fractured slab techniques is the same as flexible pavement given in Section July
4 Whitetopping Whitetopping is a new concrete pavement built on an old flexible pavement. rehabilitation schedule is the same as rigid pavement given in Section The future 704 Total Cost Once all the costs for initial construction and future rehabilitation have been calculated, they are summed to determine the net present value of each alternative. Future rehabilitation costs are discounted to account for and the time value of money Discounting Discounting is a simple yet effective way to account for the time value of money. The discount rate can be thought of as the difference between market interest rates and the general rate of inflation. For example, if one-year Certificates of Deposit (CD) are paying 5.5% while inflation is running 2.0% per year, the discount rate would be 3.5%. Similarly, if CDs are paying 8.0% and inflation is running 4.5%, the discount rate is still 3.5%. Using a discount rate eliminates the need to predict what inflation will do for the next 35 years or what return one might get on an investment. The formula for applying the discount rate is as follows: (P/F,i%,n) = () where: (P/F,i%,n) = discount factor i = discount rate from OMB Circular A-94 n = year costs occur An example of how to use the discount rate and calculate total cost is shown in Figure Results Presentation The Office of Pavement Engineering prepares all LCCAs and pavement selection packages. A standard format for presenting the information is still evolving. Once a standard is established, a general description will be added to this Manual. July
5 700 Life-Cycle Cost Analysis List of Figures Figure Date Subject July 2014 Discounting Example
6 Discounting Example July 2014 Reference Section Given: $ Initial Construction (Year 0): $16,000,000 $ First Rehabilitation (Year 14): $1,400,000 $ Second Rehabilitation (Year 24): $2,300,000 $ Third Rehabilitation (Year 34): $1,400,000 Problem: Solve for the net present value using a discount rate of 1.9%. Solution: Calculate the discount factor for each year using the equation given in Section (P/F,1.9%,0) = (P/F,1.9%,14) = (P/F,1.9%,24) = (P/F,1.9%,34) = (.) (.) (.) (.) = 1.0 = = = Multiply costs by discount factors and sum to find Net Present Value (NPV). NPV = ( )*(1)+( )*(0.7684)+( )*(0.6365)+( )*(0.5273) = $19,300,000
Paving Capitalization Work Categories and Treatments
Statement of ODOT Infrastructure Capitalization Policy Government Accounting Standards Board (GASB) 34 requires public agencies to capitalize infrastructure assets on their financial statements for periods
SECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway.
Page 1 Revised 3/2/10 See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway. For New/Reconstruction projects: The cross slope of the driving lanes range from 1.5% to
Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements
University of Pittsburgh Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements Authors: J. M Vandenbossche S. Sachs August 2013 1. Introduction Bonded concrete overlays of asphalt
CHAPTER 2 LCCA APPROACHES
2.1 LCCA Basis CHAPTER 2 LCCA APPROACHES When making decisions about pavement design, LCCA: Compares pavement alternatives; and Identifies the best strategy based on current information as well as meeting
Chapter 7: Pavement Rehabilitation 7-1 Asphalt Pavement Overlays 7-1 Surface Preparation Methods 7-2 Concrete Pavement Preparation 7-3 Recycling
7-1 Asphalt Pavement Overlays 7-1 Surface Preparation Methods 7-2 Concrete Pavement Preparation 7-3 Recycling Asphalt Pavements 7-7 Chapter 7 Pavement Rehabilitation Pavement rehabilitation can be accomplished
Life Cycle Cost Analysis (LCCA)
v01-19-11 Life Cycle Cost Analysis (LCCA) Introduction The SHRP2 R-23 Guidelines provide a number of possible alternative designs using either rigid of flexible pavements. There is usually not a single
LIFE-CYCLE COST ANALYSIS PROCEDURES MANUAL
LIFE-CYCLE COST ANALYSIS PROCEDURES MANUAL Note to the User To use this manual, the reader must have the life-cycle cost analysis software program RealCost, Version 2.2 California Edition. The program
CHAPTERS 600 670 PAVEMENT ENGINEERING CHAPTER 600 GENERAL ASPECTS
HIGHWAY DESIGN MANUAL 600-1 May 7, 2012 CHAPTERS 600 670 PAVEMENT ENGINEERING CHAPTER 600 GENERAL ASPECTS Topic 601 - Introduction Pavement engineering involves the determination of the type and thickness
OHIO ASPHALT PAVING CONFERENCE
OHIO ASPHALT PAVING CONFERENCE 38 th Annual Conference Wednesday, 2/6/2013 Fawcett Center Campus of The Ohio State University 2400 Olentangy River Road Columbus, Ohio 43210 REHAB STRATEGIES FOR LOCAL
Cost Considerations of In-Place Recycling as a Pavement Rehabilitation Alternative Brian Diefenderfer, PhD, PE Alex Apeagyei, PhD, PE
Cost Considerations of In-Place Recycling as a Pavement Rehabilitation Alternative Brian Diefenderfer, PhD, PE Alex Apeagyei, PhD, PE A partnership of the Virginia Department of Transportation and the
KENTUCKY TRANSPORTATION CABINET POLICY FOR FEDERALLY FUNDED PAVEMENT REHABILITATION AND PREVENTATIVE MAINTENANCE PROJECTS
KENTUCKY TRANSPORTATION CABINET POLICY FOR FEDERALLY FUNDED PAVEMENT REHABILITATION AND PREVENTATIVE MAINTENANCE PROJECTS I. GENERAL The following policy shall apply when the intent of the project is to
VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL
VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL I/We hereby agree to furnish to the Village of Lombard all necessary materials, equipment, and labor, to complete the North Industrial
Final Report Evaluation of I-Pave Low Volume Road Design Software
Final Report Evaluation of I-Pave Low Volume Road Design Software May 2015 Michael I Darter, William R. Vavrik, Dinesh Ayyala 2015 2014 Applied Research Associates, Inc. 1 Objectives 1. Obtain all documentation
Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES
Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering Geotechnical Bulletin GB 1 PLAN SUBGRADES Geotechnical Bulletin GB1 was jointly developed by the Offices
Case Studies - Concrete Overlays
Case Studies - Concrete Overlays Lessons Learned - Concrete Overlays Purdue Road School March 6, 2013 Today s Topic 1. Overlays 2. New Full-depth 3. Pervious 4. Roller Compacted 5. Full Depth Patching
Joint Rehabilitation. Driving Forces for Concrete Pavement Joint Repairs
Long Life Concrete Pavement Joint Performance Joint Rehabilitation Gary Fick, Trinity Construction Management Services, Inc. Representing the National CP Tech Center Driving Forces for Concrete Pavement
I-66 Pavement Rehabilitation
I-66 Pavement Rehabilitation Fall Asphalt Conference Richmond, VA David Shiells, P.E. Virginia Department of Transportation David White Superior Paving Corporation October 2, 2012 Project Location 2 Goal
Rehabilitation for Concrete Pavements
Rehabilitation for Concrete Pavements www.asphaltalliance.com Overview Effective rehab for PCC Break PCC into small segments Overlay with Hot Mix Asphalt Road-userfriendly Rubblize and pave in off-peak
COST EFFECTIVE ROAD MAINTENANCE MARCH 2015
COST EFFECTIVE ROAD MAINTENANCE MARCH 2015 According to the University of New Hampshire technology transfer Center the goal of a Road Surface Management Plan should be the following: Maximize Return on
LIFE-CYCLE COST COMPARISON FOR MUNICIPAL ROAD PAVEMENTS
LIFE-CYCLE COST COMPARISON FOR MUNICIPAL ROAD PAVEMENTS HEIN, David K., P.Eng. Applied Research Associates, Inc., 5401 Eglinton Avenue West, Suite 105, Toronto, ON, CANA- DA, M9C 5K6. Tel: 416-621-9555
LCCA Defined (FHWA) LCCA Policy Statement (9/96) LCCA Policy Statement (9/96) Policy Statement Con t... Use of LCCA. CE 4401 Pavement Design
LCCA Defined (FHWA) CE 4401 Pavement Design Introduction to Life Cycle Cost Analysis A process for evaluating the total economic worth of a useable project segment by analyzing initial costs and discounted
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
Transportation Infrastructure Asset Management
2015 NW Region TTAP& BIA Symposium Transportation Infrastructure Asset Management March, 2015 Happy Longfellow, PE [email protected] (206) 394-3649 ASSET MANAGEMENT OVERVIEW What? Why? How? Inventory
Eric Ross Federal Highway Administration Proposed Office of Performance Management
Life-Cycle Cost Analysis a Decision Making Tool Eric Ross Federal Highway Administration Proposed Office of Performance Management FHWA Tools Team Evaluation and Economic Investment Team development and
Pavement Rehabilitation Selection Rehabilitation Techniques
Pavement Rehabilitation Selection Rehabilitation Techniques Bituminous Pavement Rehabilitation Techniques Overlays Bituminous Concrete Pre-overlay Treatments Mill and Overlay Mill and Inlay Recycling Options
CONCRETE REPAIR GUIDELINES. Concrete repairs can be broken down into four basic types, plus special repairs and planing.
CONCRETE REPAIR GUIDELINES Concrete repairs can be broken down into four basic types, plus special repairs and planing. Note: It is recommended that investigation into soundness of pavement be performed
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains
Planning Level Cost Estimation Tool. User s Manual
Planning Level Cost Estimation Tool User s Manual Atlanta Regional Commission Submitted By: User s Manual Table of Contents 1. INTRODUCTION... 1 2. OBJECTIVE... 1 3. FRAMEWORK OF THE TOOL... 2 4. HOW TO
Pavement Management Implementation: Success Stories for Maryland Counties
Pavement Management Implementation: Success Stories for Maryland Counties September 25, 2015 Aaron D. Gerber, P.E. How Does Your Organization Manage Pavement Assets? By Experience/Past Practice? By Customer
SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION:
September 22, 2009 Updated November 16, 2009 SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION: 1. DESCRIPTION: The cross slopes of the roadway are to be constructed as detailed in the plans and within
Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E.
Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir Presented By: Doug Stachler, P.E. Project Organization Owner Delaware County Engineers Office Design Consultant CH2M HILL Contractor Double
AirCost LCCA Software An overview of AAPTP 06 06 Paul M. Dalbey, P.E.
AirCost LCCA Software An overview of AAPTP 06 06 Paul M. Dalbey, P.E. American Concrete Pavement Association, Southeast Chapter Concrete Airport Pavement Workshop Atlanta, GA Otb October 28, 2010 Overview
Pipe Repair Strategies on I-29
Pipe Repair Strategies on I-29 Research Advisory Committee 2012 Andy Mastel NDDOT- Materials and Research Division Pipe Location In the Fargo District Along Interstate 29 RP 75, North Bound Pipe Description
NOTICE TO CONTRACTORS. CALL ORDER 700 FEDERAL PROJECT NO. STPD-6-2(122) LOCATION: US-34/US-6,CULBERTSON-McCOOK COUNTIES: HITCHCOCK RED WILLOW
NOTICE TO CONTRACTORS CALL ORDER 700 FEDERAL PROJECT NO. STPD-6-2(122) LOCATION: US-34/US-6,CULBERTSON-McCOOK COUNTIES: HITCHCOCK RED WILLOW The Nebraska Department of Roads will receive sealed bids in
DRAFT MAINTAINING HOUSTON S STREETS REPAIR, REHABILITATION, RECONSTRUCTION. Using the Full Range of Tools for a Challenging Job
MAINTAINING HOUSTON S STREETS REPAIR, REHABILITATION, RECONSTRUCTION Using the Full Range of Tools for a Challenging Job Report To: TTI Committee May 13, 2014 1 Pavement Management - Suggested Treatments
Rehabilitation by cracking and seating of concrete pavement optimized by FWD analysis
Rehabilitation by cracking and seating of concrete pavement optimized by FWD analysis H. C. Korsgaard & J. P. Pedersen Carl Bro Pavement Consultants, Kokbjerg 5, DK6000 Kolding M. Rasmussen Copenhagen
Concrete Pavement Rehabilitation
Concrete Pavement Rehabilitation Rehabilitating Concrete Pavements using CPR 3 Restoration Resurfacing Reconstruction By Tim Smith Director Transportation & Public Works Cement Association of Canada, April
INFRASTRUCTURE CAPITALIZATION Chapter 12 INFRASTRUCTURE CAPITALIZATION (GASB 34)
Chapter 12 INFRASTRUCTURE CAPITALIZATION (GASB 34) 12.1 The following section includes excerpts from Governmental Accounting Standards Series, Publication No. 171-A, Statement No. 34 of the Government
1.0 INDEX TO SHEETS URGENT STORM DAMAGE REPAIR AVON PARK AIR FORCE RANGE LOCATION MAP LEGEND LOCATION MAP
5 INDEX TO SHEETS. NOTES AND TYPICAL SECTIONS. H. R. SMITH RD.CULVERT.3 0/5 END BARRIER ACCESS ROAD REPAIR. KISSIMMEE RD. AT MORGAN HOLE CR. ROAD REPAIR.5 RANGE INFRASTRUCTURE REPAIR N 0 000' 3 0,000'
PAVEMENT REHABILITATION MANUAL
PAVEMENT REHABILITATION MANUAL Chapter 6 - Comparison of Alternative Rehabilitation Strategies Issued by: Queensland Department of Transport and Main Roads Pavements, Materials & Geotechnical Branch For
LIFE-CYCLE COST ANALYSIS PROCEDURES MANUAL
LIFE-CYCLE COST ANALYSIS PROCEDURES MANUAL State of California Department of Transportation Division of Maintenance Pavement Program LCCA Procedures Manual August 213 DISCLAIMER This manual is intended
Unit Price Averages Reports
Unit Price Averages Reports 12/7/2015 UNIT PRICE AVERAGES REPORT Disclaimer The information provided in the following Unit Price Averages Report is only for the use of Alberta Infrastructure & Transportation
Improving Rehabilitation Selection for Pavement Life Cycle Cost Analysis
Improving Rehabilitation Selection for Pavement Life Cycle Cost Analysis ACPA Mid Year Meeting Applying Life Cycle Cost Analysis for Fair Pavement Type Selection Workshop June 24, 2014 Jim Mack, PE, MBA
Pavement Management Systems
Pavement Management Systems Presented by Bill Weiss, P.E. Applied Pavement Technology, Inc. (APTech) At the 2015 Municipal Streets Seminar Ames, Iowa Why Pavement Management??? Pavements are expensive
Pavement Management Office
Department of Transportation and Public Works Puerto Rico Pavement Management Office PAVEMENT PRESERVATION SEPPP 1 GOALS AND OBJECTIVES PRHTA has been collecting data for more than twenty (20) years with
Date: 10/10/2014 Initiated by: AAS-100
U.S. Department of Transportation Federal Aviation Administration Advisory Circular Subject: Airport Pavement Management Program (PMP) Date: 10/10/2014 Initiated by: AAS-100 AC No: 150/5380-7B Change:
How To Manage The County Of Simcoe'S Infrastructure
Asset Management Plan Asset Management Plan Table of Contents 1.0 Executive Summary... 2 2.0 Introduction... 4 3.0 State of County of Simcoe s Infrastructure... 7 4.0 Levels of Service... 14 5.0 Asset
Construction Specifications for Keyhole Pavement Coring and Reinstatement
F I N A L Construction Specifications for Keyhole Pavement Coring and Reinstatement Gas Technology Institute 1700 S. Mount Prospect Rd. Des Plaines, Illinois 60018 www.gastechnology.org Version 13 October
Safe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
Township of Enniskillen. Asset Management Plan
Township of Enniskillen Asset Management Plan 2014 1 TABLE OF CONTENTS Page A. Introduction 3 B. State of Local Infrastructure 4 C. Desired Levels of Service 7 D. Asset Management Strategy 8 E. Financing
REHABILITATION OF CONCRETE BEAM BRIDGES IN CROATIAN STATE ROAD NETWORK
REHABILITATION OF CONCRETE BEAM BRIDGES IN CROATIAN STATE Danijel Tenžera, Krešimir Futivić, Boris Ukrainczyk Summary Bridge structures deteriorate with years of use and exposure to adverse environmental
HIGHWAYS DEPARTMENT GUIDANCE NOTES ON THE USE OF WATERPROOFING MEMBRANES ON CONCRETE BRIDGE DECKS
HIGHWAYS DEPARTMENT GUIDANCE NOTES ON THE USE OF WATERPROOFING MEMBRANES ON CONCRETE BRIDGE DECKS Research & Development Division RD/GN/033 June 2008 THE USE OF WATERPROOFING MEMBRANES ON CONCRETE BRIDGE
The unit costs are based on the trend line of the 3 low bids for the average quantity.
Page 1 of 8 COST ESTIMATE GENERAL INSTRUCTIONS The unit costs are based on the trend line of the 3 low bids for the average quantity. Apply the Unit Costs to ordinary structures. Unit Costs should generally
Thin Whitetopping Application at Williamsburg Regional Airport and Other Thin Whitetopping Airport Applications.
Thin Whitetopping Application at Williamsburg Regional Airport and Other Thin Whitetopping Airport Applications. Author: Gary L. Mitchell, P.E. Director Airports, American Concrete Pavement Association
RANDOM/GRID BLOCK CRACKING EXTREME SEVERITY. Transverse Cracking- Extreme Severity. Alligator Cracking- High. Severity
RANDOM/GRID BLOCK CRACKING EXTREME SEVERITY Transverse Cracking- Extreme Severity Slab Cracking Class II Regular Joint- High Severity Pattern Cracking-High Severity Alligator Cracking- High Severity Shoulder
Presentation to NYSAMPO, June 2015 Steve Wilcox, P.E., Director, Maintenance Program Planning Bureau NYSDOT
Presentation to NYSAMPO, June 2015 Steve Wilcox, P.E., Director, Maintenance Program Planning Bureau NYSDOT Comprehensive Asset Management Planning What Is Your Asset Management Organization? What Do You
PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS
C PROJECT ESTIMATE ASSUMPTIONS AND EXCLUSIONS In support of the alternatives development process, preliminary cost estimates were prepared for each of the three Candidate Build Alternatives. The cost estimates
LIMITED SCOPE CONCEPT DEVELOPMENT REPORT
LIMITED SCOPE CONCEPT DEVELOPMENT REPORT Route 33 Resurfacing Project Eastbound: Milepost 24.2 to Milepost 28.9 Westbound: Milepost 24.3 to Milepost 28.9 Manalapan & Freehold Townships, Monmouth County
Pavement Surface Evaluation and Rating. Manual RATING RATING RATING PASER RATING. Concrete Roads
Pavement Surface Evaluation and Rating PASER Manual Concrete Roads RATING 10 RATING 7 RATING 4 RATING 1 Contents Introduction 2 Rigid pavement performance 2 Pavement conditions and defects 3 Evaluation
Project Information. New Hope - Lambertville Toll Bridge - Pavement Rehabilitation & Approach Bridges Repairs -
Project Information Existing Conditions Cracked and settled pavement. Structural failure within the asphalt pavement section. Anticipated Project Elements Reconstruction of all asphalt pavement on US Route
September 1, 2003 CONCRETE MANUAL 5-694.900 CONCRETE PAVEMENT REHABILITATION 5-694.900
September 1, 2003 CONCRETE MANUAL 5-694.900 5-694.901 GENERAL CONCRETE PAVEMENT REHABILITATION 5-694.900 Concrete Pavement Rehabilitation is an extremely valuable tool of the Minnesota Department of Transportation
Chapter 22. Lump Sum Project Guidelines
Chapter 22 Lump Sum Project Guidelines 22.1 General...22-1 22.2 Project Selection...22-3 22.3 Plans Preparation...22-5 22.4 Preliminary Estimate...22-7 22.5 Specifications...22-9 22.6 Contracts Administration...22-11
SECTION 4Aggegate Subbase
The contractor shall moist-cure the completed Lime Treated Subbase for a minimum of days before allowing any traffic on the compacted surface. The contractor shall be responsible for repairing any damages
Chapter 8 Benefit/Cost Ratios and Other Measures
Chapter 8 Benefit/Cost Ratios and Other Measures BENEFIT COST 8-1 Rash, Riley, Reed, and Rogers Consulting has a contract to design a major highway project that will provide service from Memphis to Tunica,
Los Angeles County Department Of Public Works. Land Development Division. Bond Calculation Sheets
Los Angeles County Department Of Public Works Land Development Division Bond Calculation Sheets Effective July 1, 2015 COUNTY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS LAND DEVELOPMENT DIVISION ROADS COST
Nevada DOT Cold In-Place Recycling Federal Highway Administration National Review Close out meeting, August 25, 2005
Nevada DOT Cold In-Place Recycling Federal Highway Administration National Review Close out meeting, August 25, 2005 Purpose The purpose of this review is to capture for technical deployment the most advanced
3.1 Historical Considerations
3. Recommended Scope of Bridge improvements 3.1 Historical Considerations In the fall of 2000, an outside consultant, Fraser Design, suggested that the existing 4 th St. Bridge is potentially eligible
APPENDIX B. I. Background Information
APPENDIX B GUIDELINES FOR IDENTIFYING AND REPAIRING LOCALIZED AREAS OF DISTRESS IN AC PAVEMENTS PRIOR TO CAPITAL PREVENTIVE MAINTENANCE OR REHABILITATION REPAIRS I. Background Information A. AC Pavement
Local Road Assessment and Improvement Drainage Manual
Local Road Assessment and Improvement Drainage Manual Donald Walker, T.I.C. Director, author Lynn Entine, Entine & Associates, editor Susan Kummer, Artifax, design Transportation Information Center University
Catch Basin Rehabilitation Road Commission for Oakland County, Michigan
Date: Location: September 14, 2011, 9:45a.m. start East side of street in front of 4656 Maura Lane, West Bloomfield Participants: Oakland County Michelle Belanger, Rick Hall, Matt Mountain, Gary Flounory,
C. Section 014510 TESTING LABORATORY SERVICE.
SECTION 014500 QUALITY CONTROL PART 1 GENERAL 1.01 RELATED REQUIREMENTS A. Drawings and General Provisions of Contract, including General and Special Conditions and other Division 1 Specification Sections,
Road Rehabilitation and Reconstruction Using AutoCAD Civil 3D
Road Rehabilitation and Reconstruction Using AutoCAD Civil 3D Contents Introduction... 3 Introduction to Corridor Targets... 3 Surface Targets... 4 Width and Offset Targets... 5 Elevation or Slope Targets...
ODOT Major Construction, Bikeways and Enhancements Report for Lucas County. (State Fiscal Years 2007 to 2010)
Bikeways and Enhancements Report for Lucas County (State Fiscal Years 2007 to 2010) Statewide Construction Summary by Major Work Type (in Millions) WORK TYPE SFY 2007 SFY 2008 SFY 2009 SFY 2010 TOTAL #
Chapter 4 ASSET INVENTORY AND CONDITION CHAPTER 4 ASSET INVENTORY AND CONDITION PAGE 33
Chapter 4 ASSET INVENTORY AND CONDITION CHAPTER 4 ASSET INVENTORY AND CONDITION PAGE 33 This page intentionally left blank. PAGE 34 MINNESOTA GO MNDOT TRANSPORTATION ASSET MANAGEMENT PLAN ASSET INVENTORY
Nebraska Department of Roads Drainage and Erosion Control Manual December 2011 Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY
Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY Policy: This policy will replace all previous policies regarding the selection of pipe material for cross drains, drive pipe, drop pipe, storm
Standards for Specifying Construction Of Airports
Standards for Specifying Construction Of Airports FAA Standard Materials in FAARFIELD Thickness Design Presented to: X ALACPA Seminar on Airport Pavements and VIII FAA Workshop By: David R. Brill. P.E.,
Traffic volumes adopted for pavement designs are based on the parameters contained in Section 7 of this report.
11. Pavements 11.1 Pavement design Preliminary pavement designs have been developed for the highway travel lanes (through carriageways), the inner and outer shoulders, on and off ramps and service roads.
Grinding equipment that causes raveling, aggregate fractures or disturbance to the joints shall not be permitted.
Guide Specification: Diamond Grinding for City Streets Publication Date: May 24, 2010 SCOPE City streets are defined as roadways with a closed drainage system along with numerous structures such as manholes,
Rural Road Maintenance Handbook Module 16 Rural Road Maintenance Cost Estimate
After fulfilling Module 16, you will be able to: Understand the structure of cost estimating sheets and the steps to establish a cost estimate for rural road maintenance Establish cost estimate Self -
The State of Michigan Transportation Asset Management Council 2005 PASER Survey Of Genesee County
The State of Michigan Transportation Asset Management Council 2005 PASER Survey Of Genesee County Prepared by the Genesee County Metropolitan Planning Commission Staff The State of Michigan Transportation
Evaluation of Long-Lasting Perpetual Asphalt Pavement Using Life-Cycle Cost Analysis. Arnar Agustsson Sulton Azamov
Evaluation of Long-Lasting Perpetual Asphalt Pavement Using Life-Cycle Cost Analysis Arnar Agustsson Sulton Azamov Contents 1. Perpetual Asphalt Pavement 2. Scope 3. Methodology 4. Performance 5. Alternatives
Airfield Pavement Rehabilitation Planning Choosing the right fix. Rob McLure, M.Eng., P.Eng. Senior Associate Hatch Mott MacDonald
Airfield Pavement Rehabilitation Planning Choosing the right fix Rob McLure, M.Eng., P.Eng. Senior Associate Hatch Mott MacDonald Presentation Objective ¾ Review the pavement rehabilitation strategy development
Section 402. STORM SEWERS
402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide
SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or
Earth Retaining Structures
Earth Retaining Structures and Asset Management Earth Retaining Structures and Asset Management A Critical Component Tool in Maintaining Public Safety Earth Retaining Structures (ERS) are often an overlooked
Impacts of Increased Loading Due to Heavy Construction Traffic on Thin Pavements
Impacts of Increased Loading Due to Heavy Construction Traffic on Thin Pavements Author: Harry Sturm, P. Eng. Stantec Consulting Ltd. 16-77 Mississauga Road Mississauga, ON L5N 7G2 Phone: (95) 817-296
P. ALTERNATE TECHNICAL CONCEPTS FOR CONSTRUCTION, STAGING AND TRAFFIC CONTROL
P. ALTERNATE TECHNICAL CONCEPTS FOR CONSTRUCTION, STAGING AND TRAFFIC CONTROL 1.0 Description. 1.1 This specification allows bidders the opportunity to include in their overall bid proposal, pricing for
STATE HIGHWAY ASSET MANAGEMENT MANUAL
STATE HIGHWAY ASSET MANAGEMENT MANUAL Manual Number: SM020 Effective From: October 1996 Re-issued: August 2000 Transit New Zealand PO Box 5084 WELLINGTON Telephone (04) 499 6600 Facsimile (04) 499 6666
Section 11.5 TESTING AND CORRECTING ASPHALT PAVEMENT SURFACE DEFICIENCIES
Section 11.5 TESTING AND CORRECTING ASPHALT PAVEMENT SURFACE DEFICIENCIES 11.5.1 Purpose To provide a uniform procedure for determining that the last structural layer meets the applicable straightedge
Asphaltic Wedge Paving
OFFICIAL NOTICE ADVERTISEMENT FOR BIDS Notice is hereby given by the Town of Oregon, Dane County, Wisconsin, will receive sealed bids for Road Construction as listed in this request until 4:00 P.M., Local
Life-Cycle Cost Analysis in Pavement Design
Publication No. FHWA-SA-98-079 Life-Cycle Cost Analysis in Pavement Design - In Search of Better Investment Decisions - Pavement Division Interim Technical Bulletin September 1998 This Interim Technical
Jointed Plain Concrete Pavement (JPCP) Preservation and Rehabilitation Design Guide
CALIFORNIA DEPARTMENT OF TRANSPORTATION DIVISION OF DESIGN Office of Pavement Design Pavement Design & Analysis Branch Jointed Plain Concrete Pavement (JPCP) Preservation and Rehabilitation Design Guide