1 COST EFFECTIVE ROAD MAINTENANCE MARCH 2015 According to the University of New Hampshire technology transfer Center the goal of a Road Surface Management Plan should be the following: Maximize Return on Investment (ROI) for each dollar spent on road maintenance Maintain highest possible town-wide road quality Generate long term budgetary estimates and work plans The above chart is from the Maine RSMS 11 Program. The TIME element on the above chart will vary greatly from road to road depending on how well it was initially constructed.
2 Similar chart from the Corp of Engineers Website MicroPAVER topic. The TIME element on the above chart will vary greatly from road to road depending on how well it was initially constructed. 2
3 Repair Strategies: There are many repair strategies that used on Town Highways. The better the condition of the road the least expensive the repair strategy. The following repair strategies have been used in the attached Capital Plan. No Maintenance: No work is required Routine Maintenance: This is the most cost effective use of funds and includes ditching, cleaning culverts and patching. Preventative: This strategy includes crack filling, chip seals, shimming, overlays or a combination of these depending on the nature of the road surface. Rehabilitate: This strategy includes milling/shimming/overlaying or reclamation of the existing pavement followed by 4 of new pavement. It is important to review the existing base material prior to any type of rehabilitation, as an undesirable base will not adequately support a reclaim project even if stabilized with cement, asphalt or chloride. Reconstruct: This includes the complete excavation of the existing pavement and inadequate base material, installation of new drain pipes and underdrains where appropriate, installation of fabric as needed, 1.5 to 2 of new gravel base (depending on the road) and new pavement (2.5 minimum base, 1.5 minimum top) Defer: It is important to recognize when a road has gone beyond the point of rehabilitation than it should be classified as a candidate for Reconstruction. There are cases where capital funds can be saved on this type of road by simply deferring maintenance until the road has reached the end of its useful life. Deferring can free up Capital funding for use on other roads. If selected appropriately deferred roads can save money by preventing overlays and reclamations on roads that will not hold up. Deferring a road needing Capital Improvements may require a shim or shim/chip seal to hold the road in place long enough for the Capital Improvement. 3
4 Repair Concepts: According to the Chart from the Maine Local Roads Center on the previous page, it is more cost effective to take care of the good roads than to address the poor or failed roads. For this reason it is imperative to preserve the GOOD roads (Preventative Category) with chip seals and or pavement overlays prior to the significant drop in condition. According to the University of New Hampshire technology transfer the guiding principals of a Road Surface Management Plan should be as follows: Use money as efficiently as possible Make repair decisions based on road surveys Avoid worst first methodology Avoid arbitrary repair selection Prepare multi year road maintenance plan A Vermont Local Roads article printed in December 2011 titled Pay now or later: Tips for saving dollars for the long haul points out the following: Spending money before rapid depreciation is money well spent Providing good foundations is good road management Cheaper is not always better It may mean the Town does not accomplish all it wants to 4
5 3/24/2015 Low Cost Budgeting for Town Highway Projects Preventative Maintenance Cost Cost Life Expect.* Avg. Yearly Cost Chip Seals ($/SY) ($/mile) (years) ($/mile-year) 3/8" Chip Seal (conventional) $2.40 $31,000 8 $3,875 3/8" Chip Seal (10% rubber) $3.30 $43, $4,300 3/8" Chip Seal (20% rubber) $4.20 $55, $4,600 Bonded Wearing Coarse (Interstate) $6.00 $80, $6,700 Road posting (paved and gravel roads) $0.00 $0 labor Benefits of rubber chip seal: Life expectancy is longer, can sweep in 1/2 to 1 hour vs 5 days. Minimal loose stone with rubber added. * Life Expectancy: This may vary by 2 years +/-, depending on the road condition and traffic. NOTE: Costs per mile based on 22' width road and a minimum of 20,000 SY contract Preventative Maintenance Cost Cost Life Expect.* Avg. Yearly Cost Paving ($/TON);($/SY) ($/mile) (years) ($/mile) Shim (1/2" Tons/mile) $75/TON $30,000 5 $6,000 Overlay (1" Tons/mile) $75/TON $60, $6,000 Shim/Overlay (1.5" - 1,150 Tons/mile) $75/TON $90, $9,000 Shim/Chipseal (traditional) $2.40/SY $61, $6,100 Shim/Chipseal (10% rubber) $3.30/SY $73, $7,300 Shim/overlay/Chipseal (10% rubber) $4.20/SY $133, $13,300 The following is in addition to paving ($/SY) Micromill (remove high spots) $1.00 $13, $1,300 Mill (up to 2") $2.50 $32, $3,200 * Life Expectancy: This may vary by 2 years +/-, depending on the road condition and traffic. NOTE: Costs per mile based on 22' width road and a minimum of 20,000 SY contract Cost Life Expect.* Avg. Yearly Cost Rehabilitation & Reconstruction ($/mile) (years) ($/mile) Rehabilitation Reclaim, 4" pavement $300, $15,000 Reclaim + $400, $20,000 (includes minimal: ditching, reclaim, tree removal, traffic control, new culverts, 4 mix) Reclaim, stabilize base, 4" pavement $350, $14,000 Reclaim, add 6" gravel, 4" pavement $400, $16,000 Reclaim, add 12" gravel, 4" pavement $500, $17,000 Reconstruction $1,000, $20,000 (includes: ditching, reclaim, tree removal, traffic control, new culverts, 4 mix) * Life Expectancy: This may vary by 5 years +/-, depending on the road condition and traffic. NOTE: Costs per mile based on 22' width road MINIMUM RECOMMENDED BUDGET: GOOD Cond. FAIR Cond. POOR Cond. Very Poor Condition Preservation $/mile pavement $5,300/MILE $7,300/MILE $9,000/MILE $12,000/MILE Plus Capital Work $ $$ $$$ $$$$$$ Prepared by Everett Hammond, PE Hammond Engineering, Springfield, VT office cell
6 Chip Seal Advantages: 1. Pavement Preservation at the lowest cost ($43,000/mile vs $60,000/mile) 2. Extends time between overlays 3. Provides good skid resistance 4. Provides an effective moisture barrier against water intrusion that can weaken the base 5. Reduces oxidation in the underlying pavement, resulting in less need for crack filling 6. Reduces the need to crack fill, particularly when applied early to a newer pavement 7. Salt brine holds longer Chip Seal Disadvantages: 1. Loose stones shortly after application could crack windshields. Utilization of the rubber application drastically reduces this possibility as the chip seal can be swept in as little as 1 hour with a 10% minimum rubber chip seal.
7 Truck Distributer Spraying Asphalt
8 Truck Distributer Spraying Asphalt
9 Spreader Application of Treated Aggregate
10 Spreader Application of Treated Aggregate
11 Immediate Rolling for Proper Embedment
12 Immediate Rolling for Proper Embedment
13 Same Day Sweeping and Re-Opening to Traffic
14 Road Surface Two Months After Chip Seal
15 Road Surface 1 Year After Chip Seal
16 Road Surface 10 Years After Chip Seal (Reclaim, excavation of inferior material, fabric installation, installation of reclaim material, 12 new gravel, base pavement, top pavement, chip seal)
17 Chip Sealed Streets in Charlestown (2014)
18 Chip Sealed Streets in Charlestown (2014)
Pavement Management Implementation: Success Stories for Maryland Counties
Pavement Management Implementation: Success Stories for Maryland Counties September 25, 2015 Aaron D. Gerber, P.E. How Does Your Organization Manage Pavement Assets? By Experience/Past Practice? By Customer
Nevada DOT Cold In-Place Recycling Federal Highway Administration National Review Close out meeting, August 25, 2005
Nevada DOT Cold In-Place Recycling Federal Highway Administration National Review Close out meeting, August 25, 2005 Purpose The purpose of this review is to capture for technical deployment the most advanced
Chapter 7: Pavement Rehabilitation 7-1 Asphalt Pavement Overlays 7-1 Surface Preparation Methods 7-2 Concrete Pavement Preparation 7-3 Recycling
7-1 Asphalt Pavement Overlays 7-1 Surface Preparation Methods 7-2 Concrete Pavement Preparation 7-3 Recycling Asphalt Pavements 7-7 Chapter 7 Pavement Rehabilitation Pavement rehabilitation can be accomplished
OHIO ASPHALT PAVING CONFERENCE
OHIO ASPHALT PAVING CONFERENCE 38 th Annual Conference Wednesday, 2/6/2013 Fawcett Center Campus of The Ohio State University 2400 Olentangy River Road Columbus, Ohio 43210 REHAB STRATEGIES FOR LOCAL
Appendix D:When to Pave a Gravel Road
Appendix D:When to Pave a Gravel Road D1 Appendix D: When to Pave a Gravel * Road by Kentucky Transportation Center, University of Kentucky at Lexington,KY Contents A Word About the Term Paved Introduction
ASPHALT PAVEMENT RECYCLING
HOT IN-PLACE RECYCLING THE ENERGY SAVING METHOD ASPHALT PAVEMENT RECYCLING Hot In-Place alt ec cl n The Energy Saving Method! HIGHWAY REHAB CORP Highway Rehab Corp 2258 Route 22 Brewster, NY 10509 Tel
CID STREET INFRASTRUCTURE ASSESSMENT
ABSTRACT An evaluation of the street infrastructure in Foxberry Estates Phase 1, including pavement condition, verification of construction techniques, and subgrade quality. Recommendations and costs for
Decision Matrix for Pavement Preservation. Mike Mamlouk Arizona State University
Decision Matrix for Pavement Preservation Mike Mamlouk Arizona State University Outline 1. Concept of preventive maintenance 2. Effectiveness of treatments 3. Treatment selection 2 Pavement Pavement Preservation
VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL
VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL I/We hereby agree to furnish to the Village of Lombard all necessary materials, equipment, and labor, to complete the North Industrial
700 Life-Cycle Cost Analysis... 700-1
Table of Contents 700 Life-Cycle Cost Analysis... 700-1 701 Introduction... 700-1 701.1 Discount Rate... 700-1 702 Initial Construction... 700-1 703 Future Rehabilitation... 700-1 703.1 Introduction...
Why Maintain Your Asphalt?
Asphalt Maintenance Why Maintain Your Asphalt? Asphalt pavement is basically sand, gravel and glue. The glue used to keep the sand and gravel together is asphalt, a heavy by-product of oil refining. While
Asphaltic Wedge Paving
OFFICIAL NOTICE ADVERTISEMENT FOR BIDS Notice is hereby given by the Town of Oregon, Dane County, Wisconsin, will receive sealed bids for Road Construction as listed in this request until 4:00 P.M., Local
SECTION 311 PLACEMENT AND CONSTRUCTION OF CEMENT TREATED SUBGRADESOIL CEMENT BASE COURSE
PLACEMENT AND CONSTRUCTION OF CEMENT TREATED SUBGRADESOIL CEMENT BASE COURSE 311.1 DESCRIPTION: This item shall consist of a cement treated subgrade base course composed of a mixture of local soil, portland
Transportation Infrastructure Asset Management
2015 NW Region TTAP& BIA Symposium Transportation Infrastructure Asset Management March, 2015 Happy Longfellow, PE [email protected] (206) 394-3649 ASSET MANAGEMENT OVERVIEW What? Why? How? Inventory
For Asset Management
For Asset Management By: Larry Weiss SDLTAP It Begins with Accurate Inventory Inventory of existing system: The Local Roads Needs Study conducted in Aug/Sept of 08 indicated by it s results and from LTAP
Cost Considerations of In-Place Recycling as a Pavement Rehabilitation Alternative Brian Diefenderfer, PhD, PE Alex Apeagyei, PhD, PE
Cost Considerations of In-Place Recycling as a Pavement Rehabilitation Alternative Brian Diefenderfer, PhD, PE Alex Apeagyei, PhD, PE A partnership of the Virginia Department of Transportation and the
Pavement Rehabilitation Using Hot Mix Asphalt. - National Perspective -
Pavement Rehabilitation Using Hot Mix Asphalt - National Perspective - Rehabilitation Process Evaluate Existing Pavement and Conditions Evaluate Options Construct Project Monitor Performance Evaluate Existing
Rural Road Maintenance Handbook Module 16 Rural Road Maintenance Cost Estimate
After fulfilling Module 16, you will be able to: Understand the structure of cost estimating sheets and the steps to establish a cost estimate for rural road maintenance Establish cost estimate Self -
Case Studies - Concrete Overlays
Case Studies - Concrete Overlays Lessons Learned - Concrete Overlays Purdue Road School March 6, 2013 Today s Topic 1. Overlays 2. New Full-depth 3. Pervious 4. Roller Compacted 5. Full Depth Patching
Evaluation of Long-Lasting Perpetual Asphalt Pavement Using Life-Cycle Cost Analysis. Arnar Agustsson Sulton Azamov
Evaluation of Long-Lasting Perpetual Asphalt Pavement Using Life-Cycle Cost Analysis Arnar Agustsson Sulton Azamov Contents 1. Perpetual Asphalt Pavement 2. Scope 3. Methodology 4. Performance 5. Alternatives
Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements
University of Pittsburgh Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements Authors: J. M Vandenbossche S. Sachs August 2013 1. Introduction Bonded concrete overlays of asphalt
Township of Enniskillen. Asset Management Plan
Township of Enniskillen Asset Management Plan 2014 1 TABLE OF CONTENTS Page A. Introduction 3 B. State of Local Infrastructure 4 C. Desired Levels of Service 7 D. Asset Management Strategy 8 E. Financing
SECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway.
Page 1 Revised 3/2/10 See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway. For New/Reconstruction projects: The cross slope of the driving lanes range from 1.5% to
DRAFT MAINTAINING HOUSTON S STREETS REPAIR, REHABILITATION, RECONSTRUCTION. Using the Full Range of Tools for a Challenging Job
MAINTAINING HOUSTON S STREETS REPAIR, REHABILITATION, RECONSTRUCTION Using the Full Range of Tools for a Challenging Job Report To: TTI Committee May 13, 2014 1 Pavement Management - Suggested Treatments
Pavement Management Office
Department of Transportation and Public Works Puerto Rico Pavement Management Office PAVEMENT PRESERVATION SEPPP 1 GOALS AND OBJECTIVES PRHTA has been collecting data for more than twenty (20) years with
Joint Rehabilitation. Driving Forces for Concrete Pavement Joint Repairs
Long Life Concrete Pavement Joint Performance Joint Rehabilitation Gary Fick, Trinity Construction Management Services, Inc. Representing the National CP Tech Center Driving Forces for Concrete Pavement
Summary of FHWA In-Place Recycling Activities
Summary of FHWA In-Place Recycling Activities 2014 International and 7 th Western States In- Place Recycling Conference Lee Gallivan FHWA Asphalt Materials Engineer Office of Asset Management, Pavement,
Paving Capitalization Work Categories and Treatments
Statement of ODOT Infrastructure Capitalization Policy Government Accounting Standards Board (GASB) 34 requires public agencies to capitalize infrastructure assets on their financial statements for periods
Cornell Asset Management Program - Roads & Streets (CAMP-RS) 2014
Cornell Asset Management Program - Roads & Streets (CAMP-RS) 2014 Distributed by: Cornell Local Roads Program CLRP No. 14-01 Table of Contents 1 - Introduction to Cornell Asset Management Roads & Streets
Presentation to NYSAMPO, June 2015 Steve Wilcox, P.E., Director, Maintenance Program Planning Bureau NYSDOT
Presentation to NYSAMPO, June 2015 Steve Wilcox, P.E., Director, Maintenance Program Planning Bureau NYSDOT Comprehensive Asset Management Planning What Is Your Asset Management Organization? What Do You
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains
Asset Management for MAP-21. Gary Lasham, P.E. Jonathan Pollack
Asset Management for MAP-21 Gary Lasham, P.E. Jonathan Pollack Replaced Intermodal Surface Transportation Efficiency Act (ISTEA) MAP-21 is transforming the policy and programmatic framework for investments
The Roads to Recovery. Facts About Transportation Funding and Spending
The Roads to Recovery Facts About Transportation Funding and Spending How Pima County spends transportation money (F.Y. 2014-15 Transportation Budget) 1 Debt Service (1997 bonds): $19.1 million In 1997,
Local Road Assessment and Improvement Drainage Manual
Local Road Assessment and Improvement Drainage Manual Donald Walker, T.I.C. Director, author Lynn Entine, Entine & Associates, editor Susan Kummer, Artifax, design Transportation Information Center University
CITY COUNCIL AGENDA ITEM CITY OF SHORELINE, WASHINGTON
Council Meeting Date: August 11, 2014 Agenda Item: 7(c) CITY COUNCIL AGENDA ITEM CITY OF SHORELINE, WASHINGTON AGENDA TITLE: Motion Authorizing the City Manager to Execute a Contract with Transmap Corporation
CHAPTERS 600 670 PAVEMENT ENGINEERING CHAPTER 600 GENERAL ASPECTS
HIGHWAY DESIGN MANUAL 600-1 May 7, 2012 CHAPTERS 600 670 PAVEMENT ENGINEERING CHAPTER 600 GENERAL ASPECTS Topic 601 - Introduction Pavement engineering involves the determination of the type and thickness
KENTUCKY TRANSPORTATION CABINET POLICY FOR FEDERALLY FUNDED PAVEMENT REHABILITATION AND PREVENTATIVE MAINTENANCE PROJECTS
KENTUCKY TRANSPORTATION CABINET POLICY FOR FEDERALLY FUNDED PAVEMENT REHABILITATION AND PREVENTATIVE MAINTENANCE PROJECTS I. GENERAL The following policy shall apply when the intent of the project is to
Pavement Patching Repair for AC and PCC Pavement Surfaces. Vern Thompson www.crafco.com
Pavement Patching Repair for AC and PCC Pavement Surfaces Vern Thompson www.crafco.com Overview and Objective New Methods For Pavement Patching-Overview What are they How they are applied New Methods Secti
SPECIAL NOTE FOR ASPHALT WATERPROOFING MIX FOR BRIDGE-DECK OVERLAYS AND ADJACENT APPROACHES
SPECIAL NOTE FOR ASPHALT WATERPROOFING MIX FOR BRIDGE-DECK OVERLAYS AND ADJACENT APPROACHES 1. DESCRIPTION. Asphalt Waterproofing Mix (AWM) is a highly elastomeric, polymermodified, impermeable asphalt
Transportation Asset Management Program 2009 Federal Aid PASER Road Survey. August 2009
Transportation Asset Management Program 2009 Federal Aid PASER Road Survey August 2009 WEST MICHIGAN SHORELINE REGIONAL DEVELOPMENT COMMISSION (WMSRDC) The WMSRDC is a regional council of governments representing
Pavement Management Program
Pavement Management Program 2014 Street Maintenance Program Executive Summary 01/21/2014 Presented by Mark Thiel Assistant Director of Public Works Program Overview Start of current program 2005 825.1
Improving Rehabilitation Selection for Pavement Life Cycle Cost Analysis
Improving Rehabilitation Selection for Pavement Life Cycle Cost Analysis ACPA Mid Year Meeting Applying Life Cycle Cost Analysis for Fair Pavement Type Selection Workshop June 24, 2014 Jim Mack, PE, MBA
Final Report Evaluation of I-Pave Low Volume Road Design Software
Final Report Evaluation of I-Pave Low Volume Road Design Software May 2015 Michael I Darter, William R. Vavrik, Dinesh Ayyala 2015 2014 Applied Research Associates, Inc. 1 Objectives 1. Obtain all documentation
The State of Michigan Transportation Asset Management Council 2005 PASER Survey Of Genesee County
The State of Michigan Transportation Asset Management Council 2005 PASER Survey Of Genesee County Prepared by the Genesee County Metropolitan Planning Commission Staff The State of Michigan Transportation
738-B-297 POLYMERIC CONCRETE BRIDGE DECK OVERLAY. (Adopted 02-20-14)
POLYMERIC CONCRETE BRIDGE DECK OVERLAY (Adopted 02-20-14) Description The polymeric concrete bridge deck overlay shall consist of an epoxy polymer that acts together with special aggregate to form an overlay
How To Improve Road Quality
A Customer Service Level Approach for Maine DOT s Asset Management System Jeffrey L. Zavitski, B.A. Senior Implementation Specialist Deighton Associates Limited Chip Getchell, P.E. Director, Work Plan
TAMS 2.1 User s Manual. Utah LTAP Center. Contact: Utah LTAP 4111 Old Main Hill Logan, UT. 84322-4111 800-822-8878 www.utahltap.
TAMS 2.1 User s Manual Utah LTAP Center Contact: Utah LTAP 4111 Old Main Hill Logan, UT. 84322-4111 800-822-8878 www.utahltap.org Table of Contents Introduction 1 Initializing the program... 1 Data Needed
HIGHWAYS DEPARTMENT GUIDANCE NOTES ON THE USE OF WATERPROOFING MEMBRANES ON CONCRETE BRIDGE DECKS
HIGHWAYS DEPARTMENT GUIDANCE NOTES ON THE USE OF WATERPROOFING MEMBRANES ON CONCRETE BRIDGE DECKS Research & Development Division RD/GN/033 June 2008 THE USE OF WATERPROOFING MEMBRANES ON CONCRETE BRIDGE
SECTION 13 REPLACEMENT AND CLEANUP 13.01 SCOPE OF WORK
13.01 SCOPE OF WORK Under this item, the Contractor will restore all lawns, trees, gardens, landscape plantings, sidewalks, ramps, trails, fences, commercial signs, water courses and sand, gravel, dirt,
2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS
2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS GENERAL 10/16/2008 The listed average unit prices are based on the
Unit Price Averages Reports
Unit Price Averages Reports 12/7/2015 UNIT PRICE AVERAGES REPORT Disclaimer The information provided in the following Unit Price Averages Report is only for the use of Alberta Infrastructure & Transportation
SUMMARY: LAND TRANSPORT ASSET MANAGEMENT PLAN
SUMMARY: LAND TRANSPORT ASSET MANAGEMENT PLAN Introduction This Asset Management Plan (AMP) for Land Transport Network 2012 describes in detail how the District s land transport network will be managed
CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS
December 2014 CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Construction Specifications...
4-02 Gravel Base. 4-04 Ballast and Crushed Surfacing
Chapter 4 Bases 4-02 Gravel Base GEN 4-02.1 General Instructions Gravel Base is typically used in the construction of the roadway section and provides support for the pavement. For the pavement to provide
September 1, 2003 CONCRETE MANUAL 5-694.900 CONCRETE PAVEMENT REHABILITATION 5-694.900
September 1, 2003 CONCRETE MANUAL 5-694.900 5-694.901 GENERAL CONCRETE PAVEMENT REHABILITATION 5-694.900 Concrete Pavement Rehabilitation is an extremely valuable tool of the Minnesota Department of Transportation
CONSTRUCTION AND PERFORMANCE OF ULTRATHIN ASPHALT FRICTION COURSE
NCAT Report No. 97-5 CONSTRUCTION AND PERFORMANCE OF ULTRATHIN ASPHALT FRICTION COURSE by Prithvi S. Kandhal Larry Lockett September 1997 CONSTRUCTION AND PERFORMANCE OF ULTRATHIN ASPHALT FRICTION COURSE
TOWN OF NEW HAVEN ROAD PLAN
1 TOWN OF NEW HAVEN ROAD PLAN BACKGROUND The Town of New Haven, Vermont consists of 42 square miles of land and a population of approximately 1400 people. At the start of the 21 st century, it is served
LIFE-CYCLE COST ANALYSIS PROCEDURES MANUAL
LIFE-CYCLE COST ANALYSIS PROCEDURES MANUAL Note to the User To use this manual, the reader must have the life-cycle cost analysis software program RealCost, Version 2.2 California Edition. The program
Concrete Repair. Applications and Procedures
Concrete Repair Applications and Procedures Objectives Identify what surface preparation is needed Identify typical modes of failure and testing methods How to choose the correct material for the repair
Benefits of Preventative Maintenance Pavement Sealers
Pavement Coatings Technology Council WWW.PAVEMENTCOUNCIL.ORG Benefits of Preventative Maintenance Pavement Sealers Introduction Pavement Sealers have been used successfully for around 60 years. Recently,
Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES
Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering Geotechnical Bulletin GB 1 PLAN SUBGRADES Geotechnical Bulletin GB1 was jointly developed by the Offices
APPENDIX B. I. Background Information
APPENDIX B GUIDELINES FOR IDENTIFYING AND REPAIRING LOCALIZED AREAS OF DISTRESS IN AC PAVEMENTS PRIOR TO CAPITAL PREVENTIVE MAINTENANCE OR REHABILITATION REPAIRS I. Background Information A. AC Pavement
I-66 Pavement Rehabilitation
I-66 Pavement Rehabilitation Fall Asphalt Conference Richmond, VA David Shiells, P.E. Virginia Department of Transportation David White Superior Paving Corporation October 2, 2012 Project Location 2 Goal
An Introduction to Highway Maintenance
An Introduction to Highway Maintenance 1. Asset Management Background Asset Management in Practice For Example 2. Carriageways (or roads) Why do roads need maintenance? Age and Weather Wear and Tear Other
NOTICE TO CONTRACTORS. CALL ORDER 700 FEDERAL PROJECT NO. STPD-6-2(122) LOCATION: US-34/US-6,CULBERTSON-McCOOK COUNTIES: HITCHCOCK RED WILLOW
NOTICE TO CONTRACTORS CALL ORDER 700 FEDERAL PROJECT NO. STPD-6-2(122) LOCATION: US-34/US-6,CULBERTSON-McCOOK COUNTIES: HITCHCOCK RED WILLOW The Nebraska Department of Roads will receive sealed bids in
CA-48 TECHNICAL SPECIFICATION
CA-48 TECHNICAL SPECIFICATION SafeLane surface overlay Pavement Substrate A Cargill Deicing Technology Product Providing customers with deicing solutions that save lives and enhance commerce. Helping to
AGREGADOS RECICLADOS MITOS Y REALIDADES
The Production and Use of Recycled Concrete in the USA Thomas Van Dam, Ph.D., P.E., FACI Principal Engineer CTL Group Introduction In the United States, concrete is the most commonly used recycled material
Draft TMH 22 ROAD ASSET MANAGEMENT MANUAL
-- South Africa COTO Committee of Transport Officials Draft TMH 22 ROAD ASSET MANAGEMENT MANUAL M a r c h 2013 C ommittee of Transport Officials Contents Background Process Contents of Manual Quo Vadis
CHAPTER 2 LCCA APPROACHES
2.1 LCCA Basis CHAPTER 2 LCCA APPROACHES When making decisions about pavement design, LCCA: Compares pavement alternatives; and Identifies the best strategy based on current information as well as meeting
Guidelines. Motorcycle and Bicycle Work Zone Safety
Guidelines on Motorcycle and Bicycle Work Zone Safety This document describes work zone conditions that can cause safety concerns for motorcyclists and bicyclists. The document offers recommended practices
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
Infrastructure assets are distinguished from other capital assets because they normally:
4. REPORTING 4.2 Government-Wide Financial Statements 4.2.6 Infrastructure Reporting 4.2.6.10 Governments are required to report all of their capital assets in the statement of net position. Infrastructure
Pavement Management Systems
Pavement Management Systems Presented by Bill Weiss, P.E. Applied Pavement Technology, Inc. (APTech) At the 2015 Municipal Streets Seminar Ames, Iowa Why Pavement Management??? Pavements are expensive
SD95-16-G2. SD Department of Transportation Office of Research. Rural Road Design, Maintenance, and Rehabilitation Guide
SD95-16-G2 SD Department of Transportation Office of Research Rural Road Design, Maintenance, and Rehabilitation Guide Prepared by ERES Consultants, Inc. 505 West University Champaign, IL 61820-3915 September
Cement-Based Pavement Solutions. Full Depth Reclamation with Cement A Useful and Cost Saving Tool
Cement-Based Pavement Solutions October 30, 2013 Concrete Airport Pavement Workshop Atlanta, Georgia Full Depth Reclamation with Cement A Useful and Cost Saving Tool Stan Bland, PE Pavement Applications
Pavement Surface Evaluation and Rating. Manual RATING RATING RATING PASER RATING. Concrete Roads
Pavement Surface Evaluation and Rating PASER Manual Concrete Roads RATING 10 RATING 7 RATING 4 RATING 1 Contents Introduction 2 Rigid pavement performance 2 Pavement conditions and defects 3 Evaluation
Pavement Asset Management Guidance Section 5.3: Condition Surveying and Rating - Drainage
Pavement Asset Management Guidance Section 5.3: Condition Surveying and Rating - Drainage December 2014 Document Information Title Author Description Pavement Asset Management Guidance, Section 5.3: Condition
Greening our Roads. Approach
Greening our Roads Approach To create a Sustainable Future for the world, by achieving Resource Extension economically, by reducing usage of limiting resources and extending life cycle Ensuring Green Roads
MATERIALS DIVISION MEMORANDUM
MATERIALS DIVISION MEMORANDUM GENERAL SUBJECT: Precast Concrete SPECIFIC SUBJECT: Quality Control Plan Review Check list; Approved list Nos. 26 and 34; Precast Repair Manual NUMBER: MD 286-06 DATE: December
The City of Owen Sound Asset Management Plan
The City of Owen Sound Asset Management Plan December 013 Adopted by Council March 4, 014 TABLE OF CONTENTS 1 EXECUTIVE SUMMARY... 1 INTRODUCTION....1 Vision.... What is Asset Management?....3 Link to
Eric Ross Federal Highway Administration Proposed Office of Performance Management
Life-Cycle Cost Analysis a Decision Making Tool Eric Ross Federal Highway Administration Proposed Office of Performance Management FHWA Tools Team Evaluation and Economic Investment Team development and
Preservation, Repair and Rehabilitation of Concrete Bridges, Pavements and Tunnels in Virginia
Preservation, Repair and Rehabilitation of Concrete Bridges, Pavements and Tunnels in Virginia International Concrete Repair Institute Spring Convention Reno, Nevada March 20, 2014 Michael Sprinkel, PE.,
LIFE-CYCLE COST COMPARISON FOR MUNICIPAL ROAD PAVEMENTS
LIFE-CYCLE COST COMPARISON FOR MUNICIPAL ROAD PAVEMENTS HEIN, David K., P.Eng. Applied Research Associates, Inc., 5401 Eglinton Avenue West, Suite 105, Toronto, ON, CANA- DA, M9C 5K6. Tel: 416-621-9555
DEVELOPMENT OF A NATIONAL ROAD ASSET MANAGEMENT SYSTEM FOR THE KINGDOM OF SAUDI ARABIA. Hazim M Abdulwahid Abdullah Al Kahtani Mustafa Abdulaziz
DEVELOPMENT OF A NATIONAL ROAD ASSET MANAGEMENT SYSTEM FOR THE KINGDOM OF SAUDI ARABIA Hazim M Abdulwahid Abdullah Al Kahtani Mustafa Abdulaziz Contents Introduction Methodology Pavement Management System
CLASS II BASE COURSE - Section 302
CLASS II BASE COURSE - Section 302 Class II Base Courses are similar to Class I Base Courses, with the exception that placement on a subgrade layer built in accordance with Specification Section 305 is