1 CONSTRUCTION MANAGEMENT SERVICES for the new REPLACEMENT NORTH DORCHESTER HIGH SCHOOL Dorchester County Public Schools December 9, 2015 Dorchester County Public Schools is intending to engage the services of a Construction Management at Risk (CMR) firm to oversee and manage the construction of the new North Dorchester High School facility. The selected CMR will manage the bidding, and oversee the construction and closeout of the new facility. Additionally, once the replacement facility is constructed and occupied, the CMR oversee the efficient and effective removal of the existing facility, restoration of the site and closeout of the project. At this time the County intends to have the firm provide these services under the CM-At Risk project delivery method. As such, the CMR will act as the County s construction entity while holding all trade contracts not held by the County. Interested firms are asked to complete the attached CMR Selection Questionnaire and return it, along with all requested attachments, to the County by 3 pm on December 17, This successful submission of this information constitutes prequalification. Please submit 6 copies of the information. Please do not contact any parties other than as noted below: Chris Hauge Dorchester County Public Schools 700 Glasgow Street Cambridge, MD Ph , ext 1009 Project Description The Dorchester County Board of Education and County Council intend to build a replacement facility to support the approved education specifications and high school program at a replacement North Dorchester High School. The new (approximately 117,500 sf) facility will be built on the site currently occupied by the existing facility, at 5875 Cloverdale Road, Hurlock, MD, The new facility will be located adjacent to the existing high school a top existing sports facilities. The existing facility will be demolished and site restored per the approved plans and specifications. Currently the design development documents are complete and being reviewed by state funding authorities. The new facility will house instructional and multiple use spaces for the County s approved high school program of study and education specifications. The work includes providing support to maintain instructional, athletic and community use programing, all required temporary and permanent amenities while the new facility is

2 under construction. Upon completion of the replacement facility, the existing facility will be demolished, recycled and the balance of the site work completed along with complete restoration of the site. The County is currently estimating the construction costs to be in the range of $35,000,000-40,000,000, pending completion of design. Currently funding applications have been submitted for review and approval by both local and state funding authorities. Currently the project has State planning approval, and is supported by the Dorchester County Council and the State of Maryland s Public School Construction Program for construction funding to become available in FY2017 and proceed through FY2020. This project will be funded over multiple fiscal years. Proposed Project Schedule Schematic Design submitted to MD IAC Complete Design Development to MD DGS Complete Select Construction Manager January 2016 Construction Documents to MD DGS Spring 2016 Bidding Spring 2016 Begin Construction (Construction Funding Available) July 1, 2016 Complete Replacement School Construction Phase June 2018 Occupancy July 2018 Demolition/Site Restoration Complete July 2019 Warranty/Project Closeout Complete July 2020 Project Design Team Hord Coplan Macht DMS Morabito Gipe Associates Nyikos Associates Educational Planning Systems Architect, Landscape Architect Civil Engineer Structural Mechanical, Electrical, Plumbing Engineer Food Service Technology Project Steering Committee Dr. Henry V. Wagner, Jr.; Superintendent of Schools Mr. C. Dwayne Abt; Assistant Superintendent for Administration Dr. Lorenzo Hughes; Assistant Superintendent for Instruction Ms. Lynn Sorrels; Principal, North Dorchester High School Mr. Chris Hauge; School Facilities Engineer Mr. Sam Slacum; Energy and Projects Manager Proposed Selection Process Schedule Advertise for CM s Qualifications December, 2015 Questionnaires & Technical Proposals due December 17, 2015

3 Short-listed firms notified December 30, 2015 Oral Presentations & Fees due January 14, 2016 Recommendation to Superintendent January 15, 2016 Board Approval of CM Recommendation January 21, 2016 CM Notice-to-Proceed* January 22, 2016 *Contract will require Maryland IAC approval. Final NTP will be issued pending final state approval. Selection Process The selection process will be a two step process in accordance with the regulations of the State of Maryland s Public School Construction Program. The objective is to have a competitive selection process, based on qualifications, experience and price. In order to be considered pre-qualified, all interested firms will respond to the questionnaire and technical response requirements. This first submission will be reviewed and scored by the project steering committee. The project steering committee will select firms for interview and fee submission based on the first submission. The quality of the submission and the information contained therein, will be the sole determining factor in being short-listed. Upon selection and notification of being short-listed, interviews will be scheduled with the project steering committee as noted. Additionally, short-listed firms will be asked to submit a fee at the time of the interview. Specific details on the basis of the fee, including a detailed list of reimbursable expenses, will be provided to the short-listed firms. Short-listed firms will be provided copies of the Educational Specifications, site plan and current architectural plans. Upon review of the second submissions, the project steering committee will make a recommendation to the Superintendent of Schools for Board action. The Board will act on the Superintendent s recommendation. The Board will then formally engage in a Contract with the successful CM. The intended form of Contract will be the AIA A121 CMc 2003 and AGC 565 Standard Form of Agreement Between Owner and Construction Manager where Construction Manager is Also the Constructor, including Amendment #1 to A121. AIA A General Conditions of the Contract for Construction will also be used on this project. Six copies of completed questionnaire and technical proposal shall be submitted to: Dorchester County Public School-Construction Manager Search Operations Department 700 Glasgow Street Cambridge, MD 21613

4 Attn: Chris Hauge The submissions will then be distributed to the six other steering committee members for evaluation. See selection process above for further detail on how this process will proceed.

5 Selection Questionnaire (Up to 20 Points) Name of Firm: Address of Firm: Principal Owner s name & title: Telephone Number: Fax: MD Business License: Number of years in business as Construction Manager: Number of years in business as General Contractor (if applicable): Bonding Capacity: Name and address of Surety: Have you ever failed to complete a project, or been terminated for cause by an owner (as a GC, a CMA, or a CMR)?. If so, provide explanation. Ability to Self-perform Work (list trades) Number of MD public high school projects on occupied sites; total and last 5 years For each project, provide in list format name of project, county, completion date; construction cost; role in project (e.g. GC, CMA, CMR); & contact info. for owner s representative/project manager. Number of MD high school projects on occupied sites on Eastern Shore; total and last 5 years For each project, provide same information as requested above.

6 Technical Proposal (Up to 200 points) Please answer the following questions, in order, not to exceed 20 pages. Note that for certain questions, a minimum number of points required per question are indicated. Failure to achieve that required minimum number of points indicated may result in the firm not being short-listed, regardless of the total points achieved. : 1. Why should DCPS hire your firm for CMR services for the Construction phase for the Replacement North Dorchester High School? (Up to 10 pts) 2. Describe, in detail, the scope of services to be provided during bidding, construction and closeout. Refer to the list of services noted below that are expected by DCPS as a point of departure. (Up to 5 pts) 3. Critical to the success of this project will be the CMR s ability to maintain a project delivery and execution plan that is reflective of the local and state cash flow projections that are established for the project. What is your teams experience in this regard? Describe your teams approach to this requirement for this project. (Up to 25 pts, minimum of 20 points required to be selected) 4. Describe, in detail, the staffing plan for this project. What staff members will be assigned to this project, including title/role and responsibilities? Indicate if they will be full or part-time, on-site, office, or both. Be specific as how and when the staff will be involved, for Bidding, Pre-Occupancy Construction and Post- Occupancy Construction and Closeout phases. Provide resumes for each. Note that proposed key personnel cannot be changed without express agreement by the Owner. List any other firms who will be involved as your consultants, such as cost estimator, envelope consultant, etc. (Up to 15 pts) 5. Describe similar public education projects that you have provided CMR project delivery (construction) services for (up to three, one page per project), including project name, county, construction cost including change orders, owner info, architect info, MBE plan and participation achieved, contractual role as CMR, and detail description of services provided. (Up to 30 pts, up to 10 points per project, minimum 20 points required to be selected) 6. Indicate your experience and knowledge working with the State of Maryland agencies and their various submittal requirements, forms, standards, etc. (Up to 10 pts, minimum 5 points required to be selected) 7. Describe your understanding and experience in gaining Minority Business Enterprise (MBE) participation. Discuss proposed strategies for achieving maximum, responsible results in achieving this goal. Provide documentation of efforts from projects on Eastern Shore in the last 5 years. (Up to 5 pts) 8. Indicate your experience in delivering similar projects on occupied sites, and your specific concept for managing the Replacement of North Dorchester High School site (subject to modification after contract award and completion of design). (Up to 30 pts, up to 15 points per project, minimum 20 points required to be selected)

7 9. Describe your experience in various LEED s sustainable practices, such as installing Variable Refrigerant Flow HVAC Systems, clean-up, re-cycling, waste disposal, IAQ protection, etc. (Up to 20 pts) 10. In the context of experience in the last 5 years and the Construction Management at Risk contract model, document your team s experience in delivering successful, occupied school replacement projects on the Eastern Shore relative to overall quality, shared savings and schedule deadline(s). (Up to 50 pts, up to 25 points per project, minimum 25 points required to be selected)

8 Scope of Services The following is a list of the minimum scope of services expected by DCPS. Refer to question #2 above to elaborate on the list relative to your firm s experience on past similar projects. Be sure to indicate any additional services or scope you feel is applicable to this project. Bidding Services 1. Design team interaction, including: a. Attendance at design team meetings as needed. b. Constructability reviews as needed. c. Advice on materials & methods. d. Code & life safety input. e. Phasing. 2. Participate in Value-Engineering tasks, including offering strategies and methods used successfully in the past and revision of estimates as needed. 3. Development and updating of Project Schedule 4. Provide Guaranteed Maximum Price (GMP) to Owner based on 80% or better CD s. 5. Assist Architect with coordinating various permit activities 6. Project Manual coordination w/ architect (front-end, contracts, bonds, etc.) 7. Create bid packaging strategies / methods for sub-trades, such as number of bid packages, ability to eliminate scope gaps and redundancy in packaging, and write bid package sections for inclusion in Project Manual. 8. Direct and conduct bidding phase activities, such as scheduling of pre-bid meetings and bid openings, document distribution, compiling and assisting Owner/Architect in responding to bidder questions, distributing addenda 9. Oversee bid evaluations and scope reviews, and advise Owner on best course of action. Pre-Occupancy Construction phase activities (Per AIA Contract A121 CMc & General Conditions A201): 1. Maintain, monitor and update schedule, and enforce compliance. 2. Execute project delivery strategy that supports ongoing school district activities while maintaining a safe environment for the public, school district staff, students, etc. 3. Hold, manage and coordinate all trade subcontracts and ensure compliance with project documents and requirements. 4. Provide supervision while any work is occurring on site. 5. Provide monthly updates to Owner (including attendance at monthly Board meetings, identification of constraints, progress photographs, updated schedule, etc.). 6. Conduct separate biweekly progress meetings for owner and subcontractors.

9 7. Process monthly pay applications 8. Shop drawing & submittal processing 9. Review RFI s and other clarifications, respond when possible before forwarding to architect and/or Owner. 10. Address non-performing trades or sub-trades (schedule, inferior quality, etc.) 11. Maintain quality control 12. Coordinate commissioning activities 13. Project completion / close-out 14. Assistance with Owner Fit-out Post-Occupancy Construction activities 1. Site phasing 2. Building Demolition 3. Building Material Recycling 4. Site Restoration 5. Warranty responsibilities 6. Project training, hand-over 7. Coordination of move-in activities Other 1. Capability and capacity to successfully address any challenge that arises in a timely manner to ensure timely delivery of the owner s project.

Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho

Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho REQUEST FOR QUALIFICATIONS Independent School District No. 1, Lewiston, Idaho ( District ) is seeking responses from individuals

More information

IDALIA SCHOOL DISTRICT RJ-3 REQUEST FOR QUALIFICATIONS (RFQ) CONSTRUCTION MANAGEMENT/GENERAL CONTRACTING (CM/GC) SERVICES DECEMBER 14, 2011

IDALIA SCHOOL DISTRICT RJ-3 REQUEST FOR QUALIFICATIONS (RFQ) CONSTRUCTION MANAGEMENT/GENERAL CONTRACTING (CM/GC) SERVICES DECEMBER 14, 2011 IDALIA SCHOOL DISTRICT RJ-3 REQUEST FOR QUALIFICATIONS (RFQ) CONSTRUCTION MANAGEMENT/GENERAL CONTRACTING (CM/GC) SERVICES DECEMBER 14, 2011 PROJECT: New PK-12 School Facility Idalia, Colorado Idalia School

More information

REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES PIERSON ELEMENTARY REPLACEMENT SCHOOL PROJECT NO. 164519

REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES PIERSON ELEMENTARY REPLACEMENT SCHOOL PROJECT NO. 164519 REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES FOR PIERSON ELEMENTARY REPLACEMENT SCHOOL PROJECT NO. 164519 School Board of Volusia County Florida Facilities Services 3750 Olson Drive, Daytona Beach

More information

REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES PINE TRAIL ELEMENTARY HVAC, CEILING & LIGHTING PROJECT NO. 164514

REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES PINE TRAIL ELEMENTARY HVAC, CEILING & LIGHTING PROJECT NO. 164514 REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES FOR PINE TRAIL ELEMENTARY HVAC, CEILING & LIGHTING PROJECT NO. 164514 Contact: Mr. Tom Brown, Senior Construction Project Manager Facilities Services,

More information

NOTICE TO CM/GC Companies

NOTICE TO CM/GC Companies NOTICE TO CM/GC Companies Facilities and Construction Management Jefferson County School District R-1 (Jeffco) is pre-qualifying Construction Manager/General Contractors for CM/GC services for a new K-6

More information

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR)

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR) REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR) For the Project: CITY OF KATY NEW KATY FIRE STATION #2 Issued: August 13, 2015 Katy Fire Station #2 August 13, 2015 Page 1 of 17 Request

More information

Construction Management At-Risk

Construction Management At-Risk Oconee County Schools P.O. Box 146, 34 School Street Watkinsville, GA 30677 706-769-5130 706-769-3513 REQUEST FOR PROPOSALS ISSUE DATE: March 10, 2016 RFP REF: Construction Management At-Risk Construction

More information

Request of Qualification Proposal for Construction Management Services

Request of Qualification Proposal for Construction Management Services Request of Qualification Proposal for Construction Management Services Dated June 10, 2014 Table of Contents Overview 3 Introduction 4 Scope of Construction Managers Services 4 Submission of Qualifications

More information

Eanes Independent School District

Eanes Independent School District EANES INDEPENDENT SCHOOL DISTRICT 601 Camp Craft Road Austin, Texas 78746 Request for Qualifications Construction Manager at Risk Services Eanes Independent School District Construct a District Operations

More information

Request for Qualifications. Owner s Project Manager. Design and Construction of a New School Facility. K~8 Charter School

Request for Qualifications. Owner s Project Manager. Design and Construction of a New School Facility. K~8 Charter School Request for Qualifications Owner s Project Manager Design and Construction of a New School Facility K~8 Charter School 26 Madeira Avenue New Bedford, MA 02746 REQUEST FOR QUALIFICATIONS (RFQ) Issued: 4/16/2014

More information

Executive Office for Administration & Finance. Request for Qualifications For Construction Management Services

Executive Office for Administration & Finance. Request for Qualifications For Construction Management Services Executive Office for Administration & Finance Request for Qualifications For Construction Management Services Massachusetts State Project (Project Number) (Full Project Name and Location), Massachusetts

More information

Revised Work Scope Dated April 23 rd, 2015

Revised Work Scope Dated April 23 rd, 2015 Revised Work Scope Dated April 23 rd, 2015 2.4 SCOPE OF SERVICES The following combines the Scope of Services included in RFQ No. 671 dated March 12, 2015 and the Invitation to Interview letter dated March

More information

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Request for Qualifications (CM at Risk Contract) Administration of Project: School District Board + OFCC Project Name Groveport Madison High School Response Deadline 10/17/2014 4:00pm local time Project

More information

Construction Management Services Delmar School District RFP No. DSD16001-CONSTR_MAN

Construction Management Services Delmar School District RFP No. DSD16001-CONSTR_MAN Construction Management Services Delmar School District RFP No. DSD16001-CONSTR_MAN The Delmar School District (DSD) is seeking the professional services of a Construction Management (CM) firm for the

More information

Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive

Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86

More information

REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office

REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office REQUEST FOR PROPOSALS (RFP) - Construction Management Services From: Germantown School District Project: Germantown School District Addition & Renovations to Rockfield Elementary School N132 W18473 Rockfield

More information

Request for Qualifications & Proposal. Architectural Team. Lake County School District R-1. On-Call Services. For

Request for Qualifications & Proposal. Architectural Team. Lake County School District R-1. On-Call Services. For Request for Qualifications & Proposal Architectural Team For Lake County School District R-1 On-Call Services Provided by: Submittal Deadline: April 23, 2015 Time: 5:00 PM 1.0 Introduction On behalf of

More information

COMMUNITY LIBRARY (SUNBURY) RFP for Construction Manager at Risk

COMMUNITY LIBRARY (SUNBURY) RFP for Construction Manager at Risk Project Name: Addition to Community Library (Sunbury) Project Location: 44 Burrer Drive, Sunbury, Ohio 43074 Owner: Community Library Board of Trustees Address: 44 Burrer Drive, Sunbury, Ohio 43074 Project

More information

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER / GENERAL CONTRACTOR (CM/GC SERVICES)

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER / GENERAL CONTRACTOR (CM/GC SERVICES) REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER / GENERAL CONTRACTOR (CM/GC SERVICES) Return Completed Qualifications To: Twin Falls School District No. 411 Administrative Office 201 Main Avenue West Twin

More information

GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES

GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES Greenburgh Central School District No. 7 ( The District ) invites proposals to perform construction management

More information

Construction Management Standards of Practice

Construction Management Standards of Practice Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388

More information

Shawnee County ATTN: Bill Kroll 200 SE 7 th Street, Rm B-30 Topeka, KS 66603 Phone 785.251-4490 Bill.Kroll@snco.us

Shawnee County ATTN: Bill Kroll 200 SE 7 th Street, Rm B-30 Topeka, KS 66603 Phone 785.251-4490 Bill.Kroll@snco.us SECTION I Shawnee County is requesting qualifications/proposals for the renovation of 2600 SW East Circle Drive, Topeka, Kansas 66606 which will be utilized by the Shawnee County Health Agency per the

More information

Hunt Construction Group, Inc. LEVEL 1 DESIGN BUILD SPECIALTY CONTRACTOR PREQUALIFICATION DOCUMENTS FOR:

Hunt Construction Group, Inc. LEVEL 1 DESIGN BUILD SPECIALTY CONTRACTOR PREQUALIFICATION DOCUMENTS FOR: Hunt Construction Group, Inc. LEVEL 1 DESIGN BUILD SPECIALTY CONTRACTOR PREQUALIFICATION DOCUMENTS FOR: San Diego State University Basketball Practice Facility Project Number: 03400200 October 2013 San

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services

More information

REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT

REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT ADVERTISEMENT: REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT The WALTON COUNTY SCHOOL DISTRICT will receive

More information

BOARD POLICY DJA: PROFESSIONAL/TECHNICAL SERVICE CONTRACTS

BOARD POLICY DJA: PROFESSIONAL/TECHNICAL SERVICE CONTRACTS CARROLL COUNTY PUBLIC SCHOOLS ADMINISTRATIVE REGULATIONS BOARD POLICY DJA: PROFESSIONAL/TECHNICAL SERVICE CONTRACTS Administrative Procedures For Appointment of Architectural, Engineering and Construction

More information

Construction Manager at Risk

Construction Manager at Risk Request for Qualifications (RFQ) Construction Manager at Risk Beaufort County Jail and Sheriff s Office Jim Chrisman, Assistant County Manager/Finance Officer Beaufort County Government Beaufort County

More information

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES ISSUED BY: INGLEWOOD UNIFIED SCHOOL DISTRICT Issued: November 20, 2015 Due: December 18, 2015 SCHEDULE OF EVENTS INGLEWOOD UNIFIED SCHOOL

More information

Mid Michigan Community College

Mid Michigan Community College Mid Michigan Community College REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT/CONSTRUCTOR SERVICES PART 1 -- GENERAL INSTRUCTIONS A. PROJECT DESCRIPTION Mid Michigan Community College (the "Owner")

More information

REQUEST FOR QUALIFICATIONS RFQ NO. 001-09

REQUEST FOR QUALIFICATIONS RFQ NO. 001-09 REQUEST FOR QUALIFICATIONS RFQ NO. 001-09 COAST COMMUNITY COLLEGE DISTRICT Facilities & Planning Department 1370 Adams Avenue, Costa Mesa, CA 92626 Telephone (714) 438-4673 Fax (714) 438-4893 The is inviting

More information

Adrian Public Schools

Adrian Public Schools Adrian Public Schools A. Instructions REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES PART 1 -- GENERAL INSTRUCTIONS Qualified firms are invited to submit proposals to Adrian Public Schools (the

More information

REQUEST FOR QUALIFICATIONS ARCHTECTURAL SERVICE FEBRUARY 20, 2015 JACKSONVILLE PUBLIC SCHOOL DISTRICT 117

REQUEST FOR QUALIFICATIONS ARCHTECTURAL SERVICE FEBRUARY 20, 2015 JACKSONVILLE PUBLIC SCHOOL DISTRICT 117 Introduction The Board of Education for Jacksonville School District 117 is soliciting Statements of Interest and Qualifications pursuant to 50 ILCS 510/0.01 from qualified firms to provide comprehensive

More information

REQUEST FOR QUALIFICATIONS/REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES Various Projects RFQ/RFP No. 15-16-02

REQUEST FOR QUALIFICATIONS/REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES Various Projects RFQ/RFP No. 15-16-02 Banning Unified School District 161 West Williams Street, Banning, CA 92220 (951) 922-2706 phone (951) 922-0227 fax January 12, 2016 REQUEST FOR QUALIFICATIONS/REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT

More information

CONSTRUCTION MANAGEMENT AT RISK A NEW CONSTRUCTION DELIVERY METHOD For PUBLIC SCHOOLS

CONSTRUCTION MANAGEMENT AT RISK A NEW CONSTRUCTION DELIVERY METHOD For PUBLIC SCHOOLS CONSTRUCTION MANAGEMENT AT RISK A NEW CONSTRUCTION DELIVERY METHOD For PUBLIC SCHOOLS Senate Bill 914, ratified by the General Assembly December 6, 2001, made more changes to the public bidding and construction

More information

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Administration of Project: School District Board + OFCC Project Name Wellington New K-8 EM/MS Response Deadline

More information

GEORGETOWN PUBLIC SCHOOLS REQUEST FOR PROPOSALS. Perley Elementary School Roof Replacement Project DESIGN SERVICES

GEORGETOWN PUBLIC SCHOOLS REQUEST FOR PROPOSALS. Perley Elementary School Roof Replacement Project DESIGN SERVICES GEORGETOWN PUBLIC SCHOOLS REQUEST FOR PROPOSALS Perley Elementary School Roof Replacement Project DESIGN SERVICES The Georgetown School Committee seeks proposals for Design Services in connection with

More information

REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES

REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES Big Rapids Public Schools Building Program 2005 OWNER Big Rapids Public Schools 21034 15-Mile Road Big Rapids, Michigan 49307 PHONE: (231) 796-2627

More information

The purpose of the policy is to establish guidelines for the administration of the School Planning and the School Construction programs.

The purpose of the policy is to establish guidelines for the administration of the School Planning and the School Construction programs. SCHOOL PLANNING/SCHOOL CONSTRUCTION PROGRAMS Effective: August 14, 2014 I. Policy Statement The Board of Education is responsible for providing safe, engaging and supportive educational and work environments

More information

REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER

REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER RFP #2016-02 REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES FOR SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER RELEASE DATE: January 29, 2016 DUE DATE: February

More information

Request for Qualifications 2015-162

Request for Qualifications 2015-162 Kitsap County Human Services Department Request for Qualifications 2015-162 Architectural and Project Management Services - Kitsap County Work Release Facility Remodel Response Deadline: November 17, 2015

More information

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 2 1109 S. Marion Avenue, Mail Station 2015 Lake City, Florida 32025-5874

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 2 1109 S. Marion Avenue, Mail Station 2015 Lake City, Florida 32025-5874 ADVERTISEMENT FOR LETTERS OF INTEREST FOR A DESIGN BUILD PROJECT (PROCUREMENT METHOD SHORTLISTING OF PROPOSERS WITH TECHNICAL AND PRICE EVALUATION BY ADJUSTED SCORE) PROCUREMENT NUMBER: E2N44 Financial

More information

This request for qualifications seeks the following type of service providers:

This request for qualifications seeks the following type of service providers: ANNOUNCEMENT REQUEST FOR STATEMENT OF QUALIFICATIONS NOTICE SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES DESIGN AND CONSTRUCTION ARCHITECTURAL SERVICES The San Francisco Unified School District Facilities,

More information

On behalf of Governor Pat Quinn and CDB s Executive Director, Jim Underwood Welcome!

On behalf of Governor Pat Quinn and CDB s Executive Director, Jim Underwood Welcome! On behalf of Governor Pat Quinn and CDB s Executive Director, Jim Underwood Welcome! 1 WHAT CDB IS DOING FOR THE STATE OF ILLINOIS 2 Capital Development Board Created in 1972 Illinois General Assembly

More information

Request for Proposal for Construction Management Services

Request for Proposal for Construction Management Services Request for Proposal for Construction Management Services Moorhead Area Public Schools is soliciting Construction Management Agent of the Owner (CMa) proposals for the construction of a new K-4 elementary

More information

REQUEST FOR QUALIFICATIONS PROJECT / PROGRAM MANAGEMENT CONSULTANT

REQUEST FOR QUALIFICATIONS PROJECT / PROGRAM MANAGEMENT CONSULTANT REQUEST FOR QUALIFICATIONS PROJECT / PROGRAM MANAGEMENT CONSULTANT DUE: January 9, 2015 @ 5:00 PM Lopez Island School District 86 School Road Lopez Island, WA 98261 Contact: Bill Evans, Superintendent

More information

New WMHS Construction Management Firm

New WMHS Construction Management Firm New WMHS Construction Management Firm RFQ Schedule November 5, 2013 Board Meeting Approval to Advertise and use revised RFQ Week December 9, 2013 Ad runs in local papers (Thursday Dec. 12 th ) Week December

More information

COAST COMMUNITY COLLEGE DISTRICT REQUEST FOR PROPOSALS #2013 FOR

COAST COMMUNITY COLLEGE DISTRICT REQUEST FOR PROPOSALS #2013 FOR COAST COMMUNITY COLLEGE DISTRICT REQUEST FOR PROPOSALS #2013 FOR CONSTRUCTION MANAGEMENT SERVICES FOR ORANGE COAST COLLEGE BUSINESS, MATH, COMPUTING CENTER December 14, 2012 PROPOSALS DUE: By 4 p.m. -

More information

ALABAMA STATE DEPARTMENT OF EDUCATION

ALABAMA STATE DEPARTMENT OF EDUCATION ALABAMA STATE DEPARTMENT OF EDUCATION CONSTRUCTION REQUIREMENTS FOR COUNTY AND CITY PUBLIC SCHOOLS PROJECTS TOTALLY FUNDED WITH LOCAL FUNDS AND SUBMITTAL OF ALL PLANS AND SPECIFICATIONS Thomas R. Bice,

More information

Capital Projects Construction Manager At-Risk (CMR) Guaranteed Maximum Price (GMP) Best Value Selection Procedure Manual

Capital Projects Construction Manager At-Risk (CMR) Guaranteed Maximum Price (GMP) Best Value Selection Procedure Manual Page 1 of 21 Connecticut Department of Administrative Services Capital Projects Construction Manager At-Risk (CMR) Guaranteed Maximum Price (GMP) Best Value Selection Procedure Manual Prepared for Capital

More information

CREOL EXPANSION PHASE II UCF-581 Architect/Engineer (A/E) and Construction Manager (CM) Project Fact Sheet

CREOL EXPANSION PHASE II UCF-581 Architect/Engineer (A/E) and Construction Manager (CM) Project Fact Sheet CREOL EXPANSION PHASE II UCF-581 Architect/Engineer (A/E) and Construction Manager (CM) Project Fact Sheet PROJECT DESCRIPTION The project consists of the design and construction of an expansion to the

More information

Construction Management Agency (CMa) Services Request for Qualifications Hermantown Schools ISD #700

Construction Management Agency (CMa) Services Request for Qualifications Hermantown Schools ISD #700 Construction Management Agency (CMa) Services Request for Qualifications Hermantown Schools ISD #700 Response Due: February 21, 2014 4:00 PM Submit to: Brad Johnson, Superintendent Hermantown Schools ISD

More information

For Construction of the Sandy Suburban Improvement District 2013 Pipeline Rehabilitation Project

For Construction of the Sandy Suburban Improvement District 2013 Pipeline Rehabilitation Project DOCUMENTS For Construction of the Sandy Suburban Improvement District 2013 Pipeline Rehabilitation Project February 11, 2013 OWNER Sandy Suburban Improvement District 8855 South 700 West Sandy, UT 84070

More information

BALTIMORE CITY PUBLIC SCHOOLS MATERIALS MANAGEMENT DEPARTMENT

BALTIMORE CITY PUBLIC SCHOOLS MATERIALS MANAGEMENT DEPARTMENT BALTIMORE CITY PUBLIC SCHOOLS MATERIALS MANAGEMENT DEPARTMENT Contract No. RFP-15010 Request for Proposals On-Call Architectural, Engineering & Construction Management Consultant Services for. Proposals

More information

Request for Proposal No. RFP02658. Project Construction Management Services. for. Capital Levy BTA IV Project: Ingraham High School Classroom Addition

Request for Proposal No. RFP02658. Project Construction Management Services. for. Capital Levy BTA IV Project: Ingraham High School Classroom Addition Seattle Public Schools Contracting Services 2445 Third Avenue South Seattle, WA 98134 Telephone: (206) 252-0566 Fax: (206) 743-3018 contractingservices@seattleschools.org Request for Proposal No. RFP02658

More information

Request for Qualifications (RFQ NO. 1415-3) CONSTRUCTION MANAGEMENT/OWNERS REPRESENTATIVE SERVICES APRIL 16, 2015

Request for Qualifications (RFQ NO. 1415-3) CONSTRUCTION MANAGEMENT/OWNERS REPRESENTATIVE SERVICES APRIL 16, 2015 NORWALK-LA MIRADA UNIFIED SCHOOL DISTRICT Request for Qualifications (RFQ NO. 1415-3) CONSTRUCTION MANAGEMENT/OWNERS REPRESENTATIVE SERVICES APRIL 16, 2015 Norwalk-La Mirada Unified School District Purchasing

More information

CULVER CITY UNIFIED SCHOOL DISTRICT PREQUALIFICATION INFORMATION FOR PROSPECTIVE CONTRACTORS. May 21, 2015

CULVER CITY UNIFIED SCHOOL DISTRICT PREQUALIFICATION INFORMATION FOR PROSPECTIVE CONTRACTORS. May 21, 2015 I. BACKGROUND AND OVERVIEW PREQUALIFICATION INFORMATION FOR PROSPECTIVE CONTRACTORS May 21, 2015 The Culver City Unified School District ( District ), is prequalifying contractors to perform construction

More information

AIA Contract Documents, by Family as of 10/20/2015

AIA Contract Documents, by Family as of 10/20/2015 A101 2007 A101 1997 Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum A101 2007 SP A102 2007 A111 1997 A103 2007 A114 2001 Agreement Between Owner and Contractor, for

More information

GENERAL CONTRACTOR PRE-QUALIFICATION 2014 - FOR PERIOD ENDING DEC 2017

GENERAL CONTRACTOR PRE-QUALIFICATION 2014 - FOR PERIOD ENDING DEC 2017 APPLICATION for PRE QUALIFICATION GENERAL CONSTRUCTION CONTRACTORS Construction Projects up to $3,000,000 Prequalified General Contractors will be invited to submit bids for various Renovation and Construction

More information

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name RH-Renovations Summer 2013 Response Deadline 1/03/13

More information

Solicitation Information 10 May 2012

Solicitation Information 10 May 2012 Solicitation Information 10 May 2012 RFP # 7449715 Title: Service Desk Software Submission Deadline: 13 June 2012 @ 11:00 AM (Eastern Time) Questions concerning this solicitation must be received by the

More information

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Request for Qualifications (CM at Risk Contract) Administration of Project: Local Higher Education Project Name FAES- Student Success Center Response Deadline 03/04/2013 4:30 pm local time Project Location

More information

Minnesota Power PRE QUALIFICATION QUESTIONNAIRE. Engineering, Procurement and Construction of a 10 MW Solar PV Power Plant

Minnesota Power PRE QUALIFICATION QUESTIONNAIRE. Engineering, Procurement and Construction of a 10 MW Solar PV Power Plant Minnesota Power PRE QUALIFICATION QUESTIONNAIRE Engineering, Procurement and Construction of a 10 MW Solar PV Power Plant December 1, 2014 CONTRACTOR s NAME: Project Description: Minnesota Power is developing,

More information

**NOTICE OF REQUEST FOR INFORMATION** Posted/Mailed: 03/25/2010 HILLSBOROUGH COMMUNITY COLLEGE IS ACCEPTING SEALED SUBMISSIONS FOR THE FOLLOWING:

**NOTICE OF REQUEST FOR INFORMATION** Posted/Mailed: 03/25/2010 HILLSBOROUGH COMMUNITY COLLEGE IS ACCEPTING SEALED SUBMISSIONS FOR THE FOLLOWING: **NOTICE OF REQUEST FOR INFORMATION** Posted/Mailed: 03/25/2010 HILLSBOROUGH COMMUNITY COLLEGE IS ACCEPTING SEALED SUBMISSIONS FOR THE FOLLOWING: Hillsborough Community College (HCC), on behalf of the

More information

AIA Contract Documents, by Series as of 10/20/2015

AIA Contract Documents, by Series as of 10/20/2015 A101 2007 A101 1997 A101 2007 SP Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum Standard Form of Agreement Between Owner and Contractor, for use

More information

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Shideler Hall Renovation Response Deadline 12/20/13

More information

TOWN OF MILFORD REQUEST FOR QUALIFICATIONS DESIGNER SERVICES FOR LIBRARY ROOF REPLACEMENT

TOWN OF MILFORD REQUEST FOR QUALIFICATIONS DESIGNER SERVICES FOR LIBRARY ROOF REPLACEMENT TOWN OF MILFORD REQUEST FOR QUALIFICATIONS DESIGNER SERVICES FOR LIBRARY ROOF REPLACEMENT The Milford Board of Library Trustees, as the Awarding Authority, invites the submission of qualifications by responsible

More information

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Campus Elevator Upgrades Response Deadline 9/03/13

More information

REQUEST FOR PROPOSAL MECHANICAL, ELECTRICAL, PLUMBING ENGINEERING SERVICES VARIOUS BUILDING RENOVATIONS AND NEW CONSTRUCTION

REQUEST FOR PROPOSAL MECHANICAL, ELECTRICAL, PLUMBING ENGINEERING SERVICES VARIOUS BUILDING RENOVATIONS AND NEW CONSTRUCTION REQUEST FOR PROPOSAL For MECHANICAL, ELECTRICAL, PLUMBING ENGINEERING SERVICES For VARIOUS BUILDING RENOVATIONS AND NEW CONSTRUCTION CITY OF ROCHESTER November 2009 TABLE OF CONTENTS GENERAL INFORMATION

More information

B. Capital Improvement Program (CIP) All capital improvement projects listed as part of the Board s annual approved capital budget.

B. Capital Improvement Program (CIP) All capital improvement projects listed as part of the Board s annual approved capital budget. PROCUREMENT OF ARCHITECTURAL/ENGINEERING AND CONSTRUCTION MANAGEMENT SERVICES Effective: November 6, 2008 I. Policy Statement The Board of Education recognizes the ongoing need to procure professional

More information

Life of a Project. Phase General Activities Specific Activities Notes Expected Time Frame

Life of a Project. Phase General Activities Specific Activities Notes Expected Time Frame 1.0 Inception 1.1 Project Request from Client / User 1.2 Assignment 1.3 1.4 1.5 1.6 1.7 1.8 Preliminary Project Charter Submit Project Charter to Obtain internal project number Initial Project Authorization

More information

Request for Qualifications

Request for Qualifications Greenville One Building Up Fit State Project H12-9905-JM Greenville, South Carolina Request for Qualifications to provide Construction Management At-Risk Services Caution: The only official source for

More information

GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES

GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES REQUEST FOR QUALIFICATIONS GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES NEW DINING HALL MONTANA STATE UNIVERSITY Bozeman, Montana PPA NO. 15-0103 Campus Planning, Design & Construction Plew Building

More information

Carmel Unified School District. Prequalification Application For Bleacher and Pressbox Replacement Project at Carmel High School

Carmel Unified School District. Prequalification Application For Bleacher and Pressbox Replacement Project at Carmel High School Carmel Unified School District Prequalification Application For Bleacher and Pressbox Replacement Project at Carmel High School January 4, 2016 1 NOTICE REGARDING PREQUALIFICATION FOR BLEACHER AND PRESSBOX

More information

AVOIDING RISK AND SAVING MONEY ON YOUR MODERNIZATION PROJECT

AVOIDING RISK AND SAVING MONEY ON YOUR MODERNIZATION PROJECT AVOIDING RISK AND SAVING MONEY ON YOUR MODERNIZATION PROJECT Presented by Craig Misso, Ontario-Montclair School District Chris Lawrence, HMC GROUP Barbara Gadbois of Gibbs, Giden, Locher & Turner, LLP

More information

REQUEST FOR QUALIFICATIONS. 2013 Concrete Rehabilitation Program. Various Locations within the City of Centennial PROJECT NO.

REQUEST FOR QUALIFICATIONS. 2013 Concrete Rehabilitation Program. Various Locations within the City of Centennial PROJECT NO. REQUEST FOR QUALIFICATIONS 2013 Concrete Rehabilitation Program Various Locations within the City of Centennial PROJECT NO. 2013-RFQ-13-01-01 Request for Qualifications due: Date: Friday, January 11, 2013

More information

Westside'Community'Schools' Request'for'Qualifications' 'Construction'Manager'at'Risk'(CMR)' 'Community'Conference'Center' October'12,'2015'

Westside'Community'Schools' Request'for'Qualifications' 'Construction'Manager'at'Risk'(CMR)' 'Community'Conference'Center' October'12,'2015' Westside'Community'Schools' Request'for'Qualifications' 'Construction'Manager'at'Risk'(CMR)' 'Community'Conference'Center' October'12,'2015' NOTICE' In' accordance' with' Westside' Community' Schools'

More information

FABENS INDEPENDENT SCHOOL DISTRICT FABENS, TEXAS. REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES (CM @ Risk) FOR

FABENS INDEPENDENT SCHOOL DISTRICT FABENS, TEXAS. REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES (CM @ Risk) FOR FABENS INDEPENDENT SCHOOL DISTRICT FABENS, TEXAS REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES (CM @ Risk) FOR A New High School Competition Gym RFP No. 052015-036 PROPOSALS ARE DUE 10:00

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Prepared & Issued by: Middleton-Cross Plains Area School District 7106 South Avenue Middleton, Wisconsin 53562 January 9, 2012 Request for Proposal

More information

School Construction Projects

School Construction Projects The process of educating young people seems to be continually developing. New insights regarding how students most effectively receive retain and gain understanding of information and principles affect

More information

NORTH COLONIE CENTRAL SCHOOL DISTRICT 91 FIDDLERS LANE LATHAM, NEW YORK 12110-5349 INVITATION FOR CONSTRUCTION MANAGEMENT PROPOSALS

NORTH COLONIE CENTRAL SCHOOL DISTRICT 91 FIDDLERS LANE LATHAM, NEW YORK 12110-5349 INVITATION FOR CONSTRUCTION MANAGEMENT PROPOSALS NORTH COLONIE CENTRAL SCHOOL DISTRICT 91 FIDDLERS LANE LATHAM, NEW YORK 12110-5349 INVITATION FOR CONSTRUCTION MANAGEMENT PROPOSALS The North Colonie Central School District invites your firm to submit

More information

Doniphan-Trumbull Public School BP 902.05 Page 1 of 6 CONSTRUCTION MANAGEMENT AT RISK SCHOOL CONSTRUCTION ALTERNATIVE

Doniphan-Trumbull Public School BP 902.05 Page 1 of 6 CONSTRUCTION MANAGEMENT AT RISK SCHOOL CONSTRUCTION ALTERNATIVE Page 1 of 6 CONSTRUCTION MANAGEMENT AT RISK SCHOOL CONSTRUCTION ALTERNATIVE The school district adopts this policy in the event it resolves to use the construction management at risk (CM at risk) construction

More information

CONTRACTOR QUALIFICATION APPLICATION for

CONTRACTOR QUALIFICATION APPLICATION for BOARD OF WATER COMMISSIONERS 1600 WEST 12TH AVENUE DENVER, COLORADO 80204 CONTRACTOR QUALIFICATION APPLICATION for South Boulder Diversion Canal Access Bridge for Ralston Landslide Repair General Contractor

More information

Tel: (617) 727-4050 Fax: (617) 727-5363. OWNER S PROJECT MANAGER GUIDELINES M.G.L. c. 149, 44A1/2

Tel: (617) 727-4050 Fax: (617) 727-5363. OWNER S PROJECT MANAGER GUIDELINES M.G.L. c. 149, 44A1/2 The Commonwealth of Massachusetts Executive Office for Administration and Finance Division of Capital Asset Management One Ashburton Place Boston, Massachusetts 02108 Tel: (617) 727-4050 Fax: (617) 727-5363

More information

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES. Part I: Qualifications Information

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES. Part I: Qualifications Information REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES A. General Information Part I: Qualifications Information The Tacoma School District is soliciting Qualifications for onsite

More information

Ambulatory Electronic Health Record Equipment/System (EHR) Project Infrastructure Upgrade

Ambulatory Electronic Health Record Equipment/System (EHR) Project Infrastructure Upgrade Consultant Submittal Guidelines Ambulatory Electronic Health Record Equipment/System (EHR) Project Infrastructure Upgrade University of Kentucky Project Scope: $2,000,000 INTRODUCTION The University of

More information

Request for Qualification (RFQ) For Architectural Services. McCormick, South Carolina

Request for Qualification (RFQ) For Architectural Services. McCormick, South Carolina Request for Qualification (RFQ) For Architectural Services McCormick, South Carolina 1 REQUEST FOR QUALIFICATIONS (RFQ) FOR ARCHITECTURAL SERVICES TABLE OF CONTENTS I. PURPOSE OF RFQ... II. SITES DESCRIPTION..

More information

Liability and LEED. Wednesday, March 10, 2010

Liability and LEED. Wednesday, March 10, 2010 Liability and LEED Wednesday, March 10, 2010 Liability & LEED Project Team Contract Stylings LEED Considerations Contract Considerations Coverage Considerations 1 1 The Project Team LEED project accreditation

More information

Project Management Manual for Design and Construction Projects. (Revised August 2010)

Project Management Manual for Design and Construction Projects. (Revised August 2010) Project Management Manual for Design and Construction Projects (Revised August 2010) Table of Contents 1. Overview...5 1.1 Introduction... 6 1.2 Design and Construction Process... 7 1.3 Project Delegation

More information

State of North Carolina Prequalification for First Tier Subcontractors under CM at Risk

State of North Carolina Prequalification for First Tier Subcontractors under CM at Risk NC General Statute 143.128.1.c states, The construction manager at risk shall contract directly with the public entity for all construction; shall publicly advertise as prescribed in G.S. 143 129; and

More information

Corrected Form: Revised Attachment 7B Cost Proposal Distribution Exhibits A1 and A2 Attached

Corrected Form: Revised Attachment 7B Cost Proposal Distribution Exhibits A1 and A2 Attached ADDENDUM #1 RFP: 500 16 Design Build Maintenance & Operations Complex The following changes to the Request for Proposal and clarifications are provided based on questions received and must be added/considered

More information

REQUEST FOR QUALIFICATIONS (RFQ) FOR CONSTRUCTION MANAGEMENT SERVICES

REQUEST FOR QUALIFICATIONS (RFQ) FOR CONSTRUCTION MANAGEMENT SERVICES REQUEST FOR QUALIFICATIONS (RFQ) FOR CONSTRUCTION MANAGEMENT SERVICES (Construction Manager At-Risk) FOR PROJECTS IN THE CENTER UNIFIED SCHOOL DISTRICT April 7, 2005 The ( District ) is seeking Statements

More information

CONSTRUCTION CONTRACT NO. T-333.59F001-3-02

CONSTRUCTION CONTRACT NO. T-333.59F001-3-02 SPECIAL PREQUALIFICATION PROCESS FOR PLYMOUTH MEETING MAINTENANCE FACILITY RELOCATION AND CONSTRUCTION MILEPOST 332.5 EASTBOUND PLYMOUTH TOWNSHIP, MONTGOMERY COUNTY PENNSYLVANIA TURNPIKE COMMISSION CONSTRUCTION

More information

CONSTRUCTION & DESIGN AGREEMENTS FOR OWNERS. Presented by ALEXANDER F. FERRINI, III

CONSTRUCTION & DESIGN AGREEMENTS FOR OWNERS. Presented by ALEXANDER F. FERRINI, III CONSTRUCTION & DESIGN AGREEMENTS FOR OWNERS Basics for Projects of All Sizes Presented by ALEXANDER F. FERRINI, III Why do I need an agreement? Why do I need an agreement? Why do I need an agreement? Design

More information

REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES. PASSENGER SCREENING CHECKPOINT CONSOLIDATION PROJECT PROJECT No.

REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES. PASSENGER SCREENING CHECKPOINT CONSOLIDATION PROJECT PROJECT No. REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES PASSENGER SCREENING CHECKPOINT CONSOLIDATION PROJECT PROJECT No. FY15-805-67 Manchester-Boston Regional Airport is soliciting Proposals from qualified

More information

RESOLUTION NO. 2012-11

RESOLUTION NO. 2012-11 RESOLUTION NO. 2012-11 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF GARIBALDI ACTING AS CONTRACT REVIEW BOARD APPROVING A REQUEST FOR PROPOSAL DOCUMENT AND SAMPLE CONTRACT FOR THE GARIBALDI FIRE STATION

More information

Owner s project control review. 2014 Baker Tilly Virchow Krause, LLP

Owner s project control review. 2014 Baker Tilly Virchow Krause, LLP Owner s project control review 2014 Baker Tilly Virchow Krause, LLP About Baker Tilly > Established in 1931 > One of the top 20 largest accounting and advisory firms in the United States according to Accounting

More information

EXHIBIT A SCOPE OF SERVICES CONSTRUCTION MANAGEMENT TEAM POSITIONS AND REQUIREMENTS

EXHIBIT A SCOPE OF SERVICES CONSTRUCTION MANAGEMENT TEAM POSITIONS AND REQUIREMENTS EXHIBIT A SCOPE OF SERVICES CONSTRUCTION MANAGEMENT TEAM POSITIONS AND REQUIREMENTS 1.0 SCOPE OF SERVICES 1.1 General Information LAUSD requires construction management services to manage and expedite

More information

PRE BID MEETING AGENDA

PRE BID MEETING AGENDA PRE BID MEETING AGENDA Project Name: UCHC Academic Bldg. Addition & Renovation Meeting Location: UCHC, Farmington, CT Campus Project #: 901729 Meeting Date: December 10, 2014 1. Team Introductions: Construction

More information

CAPITAL PROGRAM SERVICES Capital Improvement Program

CAPITAL PROGRAM SERVICES Capital Improvement Program TABLE OF CONTENTS CAPITAL PROGRAM SERVICES Capital Improvement Program SEPTEMBER 2012 MONTHLY REPORT PROGRAM OVERVIEW Project Management & Quality Management Design and Bidding Controls MWSBE Bond Progress

More information

GLENVIEW SCHOOL DISTRICT 34

GLENVIEW SCHOOL DISTRICT 34 GLENVIEW SCHOOL DISTRICT 34 Request for Qualifications Construction Manager December 19, 2013 GLENVIEW, ILLINOIS 1 GLENVIEW SCHOOL DISTRICT 34 1401 Greenwood Road Glenview, Illinois 60026 847-998-5000

More information