Michael B. Gilbert, P.E. Vice President

Size: px
Start display at page:

Download "Michael B. Gilbert, P.E. Vice President"

Transcription

1 Vice President Mr. Gilbert has over 35 years of experience in the area of geotechnical engineering. Much of his experience has been specifically focused on tunneling projects. He has served as the lead tunnel designer and coordinated the efforts of engineers, geologists, technicians, and subcontractors in various aspects of project investigations, design, and construction inspection for tunnel projects, including highway, mass transit, water supply and sanitation, and also has extensive geotechnical experience with pipeline and foundation design. Tunnels Lead Geotechnical/Tunnel Engineer: NLTN PP03 - Project Preparation Technical Assistance Facility Subproject for Ho Chi Minh City Environmental Sanitation Project, Phase to Present. Mr Gilbert is the lead for the on-going tunnel design. Project consists of 8 km of 3200mm RCP tunnel that will be microtunneled along the Saigon River bank in HCMC. There are 18 separate jacked segments including a maximum drive length of 1030 m in soft clay. Lead Tunnel Engineer; Canaos By-Pass Experience Highlights Tunnel in Bogotá Columbia 2013 to present Over 308,700 lf of soft ground tunnels Mr Gilbert is the lead tunnel designer for this project that involves connecting the 4,200 mm Over 39,900 lf of hard rock tunnels ID ITC Tunnel and the 3,200 mm Emergency Over 149,900 lf of Microtunnels Tunnel underground. Because of contract and land issues both tunnels were terminated underground. The owner now wants to connect these two tunnels with a final terminal point in the WWTP site. Tunnels are in soft rock and will require hand mined excavation using air spades and rib and lagging support with a shotcrete final lining. Education M.S. - Civil Engineering, Northeastern University, 1977 B.S. - Civil Engineering, Northeastern University, 1973 Registration Professional Engineer: Maine (1979), Massachusetts, Illinois, Minnesota, Missouri, Nebraska, Tennessee and Washington Lead Tunnel/Geotechnical Engineer: Raw Water Intake Tunnel, Kingsport TN 2013 to Present Mr Gilbert is the lead tunnel designer for the geotechnical exploration program and tunnel design. Explorations for this 1100 lf 8-ft horseshoe tunnel included a 600 ft horizontal drilled hole parallel to the tunnel alignment to take advantage of the site topography. Currently the design is at 90% and will allow the contractor to either use drill and blast or roadheader for excavation. Rock consists of limestone and claystone with a well-defined fault zone. The strength of the limestone is an issue with roadheader excavation which would result in a larger cross section than is required for operational use. Technical Lead for Evaluation of Alternative Alignments of Thames Tideway Tunnel, London England, 2013 Mr. Gilbert provided the technical lead in evaluation of alternatives for tunnel drive length and location of shaft sites for the 7200mm ID tunnel with a long drive length of 7km and the feasibility of increasing drive lengths to 12km. Lead Geotechnical/Tunnel Engineer, Suffolk County Sewer Outfall, New York City, New York, 2009 to Present. Mr. Gilbert is the lead geotechnical/ tunnel engineer for the explorations and design of this outfall replacement tunnel under South Bay Cove from the

2 Bergin Point wastewater treatment plant. Work involves both land and marine borings to locate the tunnel vertical alignment. The tunnel is currently in final design and will be lf and 12 feet in diameter. Ground conditions transition from sand to clay. The lining system will be gasketed precast concrete segmental lining with a prestressed cable to address surge loads. Launch and exit shafts were both designed with groundfreezing as the SOE because of limited site space and environmental issues. Lead Geotechnical/Tunnel Engineer, WASA CSO Tunnels, Washington DC, 2007 to 2009 Mr. Gilbert served as the lead geotechnical engineer for the advanced feasibility design of approximately 18 miles of 15- and 23-feet inside diameter (ID) combined sewer overflow (CSO) tunnels in the nation s capital. The project involved design and implementation of an exploration program of 71 borings including marine borings in the Anacostia River. Borings drilled in this phase of the program provided sufficient subsurface data to make geotechnical recommendations on the various tunnel alignment options and to develop preliminary costs for the selected alignment. Technical Reviewer, Harbor Siphon Tunnel, New York, New York, 2005 to Mr. Gilbert provided technical review of subsurface geotechnical conditions being encountered during the marine explorations for this siphon tunnel. The 10,000-lf tunnel spans the entrance channel to New York City Harbor and will have a 12-foot outside diameter (OD) with a 72-inch pipeline. It will connect Staten Island and Brooklyn with an emergency water supply to replace an existing service that will be removed when the channel is dredged to a deeper depth. Soil conditions range from very soft, silty clays to medium dense sand and gravel. Mr. Gilbert also provided guidance on the ground freezing design for the shafts at the tunnel termini. Chief Geotechnical Engineer, Brightwater Tunnel, King County, Washington, 2002 to As chief geotechnical engineer, Mr. Gilbert oversaw the geotechnical program for the design of this 13-mile soft ground tunnel project. It included 5 deep shafts, including one that was supported by ground freezing, and over 3,000 lf of microtunneling. This work included overseeing the geotechnical investigation; laboratory testing; and preparing the geotechnical data, interpretative, and baseline reports for three separate tunnel contracts. Tunnels range in size from 14-feet to 20-feet OD. Influent tunnels will transport sewerage to the treatment plant and effluent water to a new outfall into Puget Sound. All tunnels excavated in soft ground with as much as 450 feet below the ground surface and 220 feet of water pressure head. Tunnels ranging in size from 15- to 19-feet ID are all completed. Technical Reviewer, Oakwood Combined Sewer Overflow (CSO) Control Facility and Pump Station Design, Detroit, Michigan. Mr. Gilbert performed a design review of the completed pump station slurry wall support system, which is about 65 feet deep. The bottom of the excavation comes to within about 10 feet of rock. The excavation made use of slurry wall construction and successfully controlled the artesian pressure in the underlying rock. The review included slurry wall construction, dewatering, and rock pressure grouting. Technical Review of the Connection Tunnels to the CSO Phase II Facilities Planning, Fall River, Massachusetts, 2007 to 2009 Mr. Gilbert was responsible for providing geologic and geotechnical engineering interpretation and cost estimates for five drop shaft and connection tunnels to the recently completed 20-foot diameter CSO tunnel. These connection tunnels were all excavated using drill and blast in granite with minimal support

3 consisting of rock bolts and in one tunnel ribs and shotcrete. Tunnels ranged in length from 75 to 500 lf and had cross-sections of 10- to 12-feet in width and heights of 8- to 12- feet. Lead Tunnel Engineer, Ellis Avenue Tunnels, Fountain Valley, California, 2005 to 2007 Mr. Gilbert recommended that two tunnels be excavated, rather than two different size microtunnels. This eliminated most of the traffic issues and provided an economy with regards to the TBM mobilization. Bids showed a cost savings of $5 million with rib and lagging. The project was completed on time with change orders of less than four percent. Lead Tunnel/Geotechnical Engineer, Myers Park High School Tunnel, Charlotte, North Carolina,2007 to Mr. Gilbert completed the exploration and design of this 8- foot diameter rock tunnel. The alignment goes directly under the high school campus for a distance of 2,423 lf of tunnel. The design included preparation of a GBR to cover issues in both alignments. Tunnels are currently under construction. Geotechnical Tunnel Consultant, North Carolina Sewer Project, Charlotte, North Carolina, 2006 to Mr. Gilbert completed design of two 98-inch OD rock tunnels in Charlotte, North Carolina, with one common main tunnel shaft that will form a Y connection. A 64-inch water main was installed in a 700-foot long tunnel and 48-inch main in the 1,700 lf tunnel section. One leg of the tunnel crossed under two highways and the second transverse under the apron to Charlotte Airport runway. The initial lining support types that were designed consist of light rock bolts, pattern rock bolts and ribs and lagging where the overlaying rock is decomposed and will not support rock bolts. Tunnel construction has been completed. Lead Geotechnical Engineer, Tunnel Design, L-73 Tunnel, Woodbury, Minnesota, 2003 to 2005 Mr. Gilbert completed the design and provided consultation to Metropolitan Council Environmental Services (MCES) during the construction for this 8,080 lf tunnel, which has an 8-foot bored diameter, is feet deep and included three main shafts up to 75 feet deep. Geotechnical data, interpretative and baseline reports were prepared for the contractors to use as a basis for bidding. The tunnel conditions ranged from loose to medium dense sand below the groundwater to a rock tunnel in the St. Peter Sandstone except for additional boulders. Lead Tunnel Engineer, Deer Creek Tunnel, St. Louis, Missouri, 2003 to As lead tunnel designer, Mr. Gilbert oversaw the final design of the tunnel alignment and lining design for this 7,100-foot, 20-foot OD in limestone rock tunnel. As the lead on the tunnel design, CDM Smith selected the vertical alignment of the tunnel in consultation with the hydraulics designers, established criteria for the horizontal alignment, developed rock loads on the lining, designed the final lining, and prepared the GBR and tunnel cost estimates. Support consists of rock bolts as function of the rock quality. The final lining will be cast-in-place concrete. Senior Geotechnical Engineer, Tunnel Design, Central Artery Project Immersed Tube Tunnel Crossing of Fort Point Channel Contract, Massachusetts. Mr. Gilbert was responsible for overseeing the geotechnical design performed by both in-house staff and by a geotechnical subconsultant for the Central Artery/Tunnel, Fort Point Channel Crossing, Design Contract D009B for the Massachusetts Highway Department. Geotechnical designs included a 55-foot deep casting basin for construction of Immersed Tube Tunnels, 65-foot diameter cellular cofferdam, dredging in the Fort Point Channel to

4 within five feet of the twin 24-foot non-reinforced concrete lined Massachusetts Bay Transportation Authority (MBTA) Red Line Tunnels, over $800,000 of instrumentation hardware to monitor these tunnels, drilled shafts to support the ITT in place, settlement analyses, dewatering and recharge systems and geotechnical instrumentation. Geotechnical Project Manager, Inter-Island Tunnel, Massachusetts Water Resources Authority (MWRA), Boston, Massachusetts For MWRA s Inter-Island Tunnel project (DP-5), Mr. Gilbert was responsible for investigations that consisted of a multimilliondollar exploration program for the connecting tunnel between the Nut Island and Deer Island treatment facilities and preparation of an environmental design summary report (EDSR) and GDR for the tunnel. The tunnel is 5 miles long with a finished diameter of 11.5 feet and will be a minimum of 70 feet below the top of the rock. Two shafts, each more than 275 feet deep, connect the tunnel to the wastewater treatment facilities. The tunnel rock structure was mapped during construction. Geotechnical Project Engineer, Caisson Design Pump Station, Detroit, Michigan Mr. Gilbert was responsible for exploration and design associated with major additions to the existing wastewater treatment plant (WWTP) in Detroit, Michigan. The additions consisted of a major pump station that was designed as a 150-foot diameter caisson sunk in the soft clay to final grade. The caisson was on piles to rock to stop it at design grade. Design also included two 20-foot diameter tunnels located between two pile supported aeration tanks and making a live connection to a surcharged 15-foot concrete lined tunnel with wood lugging. The connection consisted of seven 5-foot diameter stub tunnels to the new pump station. Chief of Geotechnical Section, International Sewer Project, Alexandria, Egypt Mr. Gilbert was responsible for a long-term assignment that included geotechnical design, specification preparation, and technical support during bid for design of two primary treatment plants, five pumping stations, 27 kilometers (km) of pipe-jacked soft-ground tunnels, 3 km of precast concrete liner plate tunnel through the center of Alexandria's business district, and more than 150 km of gravity sewer pipe ranging in diameter from 150 to 2,800 millimeters. He was also responsible for reviewing contractor shop drawings for gravity sewer pipes and five major pump stations, including major dewatering and slurry wall construction. Project Engineer, Outfall Sewer Design, MCUA Outfall Sewer, New Jersey. Mr. Gilbert was the engineer responsible for designing an 11-foot, one-pass pre-cast segmented tunnel. This project involved designing a lining for the various soil conditions anticipated and developing tunnel specifications, including geotechnical instrumentation. Geotechnical Project Manager, District Heating Hot Water Tunnel - St. Paul, Minnesota. Mr. Gilbert provided geologic and geotechnical engineering for the design and construction of two, 30-inch insulated high-pressure hot water mains for district heating throughout the business district of St. Paul. This project included design and construction of a 400-foot-long, 12-foot-high cathedral-shaped tunnel through the St. Peter Sandstone. The tunnel was constructed using a hydraulic lance to cut the stone. Geotechnical Project Manager, Sewer Tunnel Design, Greenwich, Connecticut. Mr. Gilbert was responsible for the construction of a 600-foot-long, 6-foot-diameter drill and blast tunnel in gneiss. This project involved monitoring vibrations and air pressures

5 due to blasting. The 350-foot main tunnel also included a 250-foot-long branch tunnel to form a "Y." All of the work was done in a residential section of the town. Microtunnels Tunnel Review and Benchmark Study BHP Billion Seawater Intake and Discharge Chile Lead reviewer of a benchmarking study for a total of four 2-meter ID open water microtunnels; two for intake both 527 m and two discharge both 317m in length. All four tunnels are proposed to be excavated in Diorite. This marine project includes one launch shaft for all four drives, the tunnels and ocean shafts for wet retrievals of the MTBM. The report benchmarked the key tunnel parameters including tunnel size, length, open water depth, rock cover and method of tunneling. The geotechnical conditions were also evaluated; including rock strength, abrasion and evaluation of the geological setting as a reason for the low rock compressive strength. A risk register was prepared and also a comparison of the costs developed by the design engineering firm was compared to our database of similar projects. Tunnel Design Technical Lead, M St. Tunnels Washington, District of Columbia. As part of the project team for the Division E M Street Diversion Sewer Project of the DC Clean Rivers Projects for DC Water, Washington D.C., MR. Gilbert performed the technical tunnel design lead for two tunnels : 1014 lf of 48-in and 1313 lf of 108-in sewer. Design was performed and specifications developed to allow the bidders to select the method of tunneling (microtunnel or conventional), ground modification and lining support systems. Lead Tunnel Design, Tingey St. Microtunnel, Washington, District of Columbia. As the technical lead for the tunnel design of this design/build project Mr. Gilbert is in charge of the design of this 72-in RCP microtunnel that is approximately 1200 lf in length. Extensive 3D modeling using FLAC 3D was performed to evaluate effect of jacking loads on the brick lined Tiber Creek Tunnel which is in very poor conditions. Design also required ground modification consisting of permeation grouting to protect the East Side Interceptor sewer and jet grout columns to support the Tingey St sewer in soft clay and miscellaneous fill. Technical Lead, Narragansett Bay Commission CSO Control Facilities Program Phase II, Providence, Rhode Island, 2011 to Mr. Gilbert was the technical lead for the design of the geotechnical and microtunneling aspects of the project. This project originally conceived as open cut was finally designed as 8,200 feet of tunnel with a 48-inch RCP carrier pipe. Tunneling will be in silty sand below the groundwater table. Lead Tunnel Design The South Interceptor and Mather Interceptor Project, Sacramento, California Mr. Gilbert was the lead tunnel design for the project that consisted of 15,000 linear feet of pipes varying from 54- to 72-inches. Tunnel design was based on pipe jacking technique using digger shield type excavation machine. The project also included design and construction of several deep shafts. Technical Review, Replacement of the Existing water Siphons between Brooklyn and Staten Island, New York City, New York, 2008 to Mr. Gilbert reviewed various aspects of this project including geotechnical investigation, GBR/GDR/GIR reports, structural design of TBM launch and receiving shafts using ground freezing technique, and design of two trenchless crossings using microtunneling techniques to install 84-inch diameter casing pipes under Staten Island Rail Road tracks.

6 Lead Tunnel Design, Tollgate Relief Interceptors, Aurora, Colorado, 2008 to Mr. Gilbert led the microtunnel design of the North and South Tollgate Interceptor projects. The South contract consisted of 6,000 linear feet (lf) of pipeline, including more than 1,000 lf of 54-inch microtunneling in soft rock, mixed-face, and loose- to medium-dense alluvium soils. The North contract consisted of 10,000 lf of pipeline. Approximately 4,500 lf required microtunneling using a 54-inch minimum-sized casing and as much as 9,800 lf could be tunneled. As part of the contract documents, both a geotechnical data report (GDR) and geotechnical baseline report (GBR) were prepared for each contract. Currently the South Tollgate work is completed and more than 75 percent of the North Tollgate tunnel work is completed. Technical Review for the Arlington Interceptor Pipeline and Tunnels, Arlington, Virginia, 2009 to Mr. Gilbert provided technical review of the subsurface conditions and methods of tunneling for this 60-inch gravity sewer under Arlington National Cemetery in Virginia. Tunneling will involve subsurface conditions ranging from mixed face of silty sand overlying gneiss and loose sands overlying organic silt deposits. Tunnels ranged in length from 500 to 1,000 feet using microtunneling. Lead Tunnel Engineer, RMMA SER 2278 Water Main Project, Austin, Texas, 2007 to 2008 This project included three trenchless crossings: two 48-inches jack and bore each about 125 feet in length in soft ground and a 60-inch crossing under US-290 that is 475 lf in length in limestone. The design included development of a GDR and a GBR for all trenchless crossings and plans and specifications for the trenchless work. Lead Tunnel Engineer, I-270 Tunnel Crossing St. Louis, Missouri. Mr. Gilbert was responsible design and construction of a 48-inch-diameter jacked casing with water main installed across I-270 in fill and fine sand and silt. The project was prepared in fast-track mode and completed within the schedule required by Missouri American Water Company. Lead Tunnel/Geotechnical Engineer, Bliss Run Tunnel, Columbus, Ohio 2005 Mr. Gilbert completed the exploration and design of this 7-feet microtunnel in saturated silty sand. This 370-foot tunnel was used as an alternative to open cut to avoid disruption to traffic and commercial businesses. Technical challenges included the design of a grouting system to stabilize the bedding of an existing 36-inch sewer line that was successfully crossed, with less than 2 feet of clearance in addition to the grouting required for face stability during advancement. Lead Tunnel Engineer, Intake and Rock Tunnel Design, Table Rock, Greenville, South Carolina, 2004 to Mr. Gilbert completed the design and construction of the Table Rock Tunnel and intake. The tunnel was designed as a 5-foot-diameter, rock tunnel under the 60-foot high earth filled Table Rock Dam. The design included the preparation of plans, specifications, geotechnical data report (GDR) and GBR. The tunnel ties into a new intake structure located about 100 feet out into the reservoir. The exploration program consisted of two phases of drilling and geophysical survey to help identify the interface between highly weathered rock and sound rock. The location of the tunnel was based on identifying a zone that would allow for the tunnel and connecting intake to be excavated in sound rock. Tunnel Consultant, Replacement Sewer, Pueblo Canyon, Arizona, 2003 to Mr. Gilbert revised the tunnel specifications for the replacement of 12,000 lf of the Pueblo Canyon sewer. The project involved 35 separate microtunnel segments totaling 9,000 lf of

7 trenchless construction in loose sand and Tuff. Work was successfully completed in the allotted time schedule due to Mr. Gilbert s modifications to the specifications that allowed the contractor to use various trenchless techniques that were acceptable to the line and grade tolerances without damaging the existing Hoodoos (a formation of stacked boulders). He made recommendations that required both microtunneling and jack and bore methods. The contractor succeeded in installing over 9,000 lf of sewer by tunneling in a 120-day period, beating the schedule and thunderstorms by one week. Technical Specialist, South Central Hillsborough Intertie, Tampa Bay, Florida Mr. Gilbert provided tunnel assistance by reviewing shop drawings for all tunneling submittals for this sewer project. Tunnel crossings included 8- to 10-foot ID tunneled crossings using various techniques, including compressed air, open shield with sand shelves, and pipe ramming. Ground control was attained by dewatering and compressed air. Geotechnical Project Manager, Instrumentation System Design Oakwood Beach Water Pollution Control Plant, Staten Island, New York As the geotechnical project manager for the West Branch Interceptor Contracts 6B-3 at the Oakwood Beach Water Pollution Control Plant, Mr. Gilbert was responsible for designing a geotechnical instrumentation system to monitor performance of 4.5 miles of 8-foot ID tunnel with conventional precast concrete segmental lining. The project included making predictions on ground movement and pipe stresses due to tunneling activities such as grouting, back graveling, dewatering using ejector wells, and jacking the shield against the lining to advance the heading. He also designed, installed, and monitored an instrumentation system and monitored construction activities. He analyzed the collected data and prepared a report summarizing the performance of the tunnel lining. Geotechnical Project Manager, Contract 6B1 Instrumentation System Design Oakwood Beach Water Pollution Control Project, Staten Island, New York Mr. Gilbert was responsible for designing the geotechnical instrumentation system to monitor performance of 1.5 miles of 60-inch OD tunnel installed by microtunneling method for the Oakwood Beach Water Pollution Control Project, West Branch Interceptor. This was one of the first major applications of Hobas Pipe. The results of the instrumentation were used by the Bureau of Sewers for future tunnel work in the city. The project included making predictions of ground movement and pipe stresses due to jacking loads and soil loads. Construction procedures such as grouting, dewatering, and resulting disturbance to the soil were considered in the analysis of the data and preparing a report summarizing overall pipe performance. Tunnel Rehabilitation Technical Specialist, Tunnel Rehabilitation, Situate Aqueduct, Providence, Rhode Island, Mr. Gilbert was responsible for providing technical guidance during the inspection, evaluation, report presentation and development of a cost estimate for the rehabilitation of the Situate Aqueduct. This is a horseshoe-shaped rock tunnel over 6 miles long that was constructed in 1920 for the Providence, Rhode Island, Water Board. Recommendations resulting from the inspection included a means of accessing the tunnel for the repairs that included reactivating the abandoned and filled tunnel shaft used during the original construction.

8 Technical Specialist, Tunnel Rehabilitation, Catskill/Delaware Aqueduct, New York City, 2007 to Mr. Gilbert performed a review of the inspection and rehabilitation recommendations of this tunnel. The inspection team performed an internal physical inspection of a 2.5-mile section of the Catskill Aqueduct, constructed in about 1910 was to be pressurized to convey additional raw water to the new disinfection facility. The tunnel is generally concrete-lined and varied in shape from a 17-foot-diameter circular tunnel to a 17- by 13-foot horseshoe-shaped tunnel. The tunnel inspection included a preliminary inspection to confirm the tunnel geometry and general condition. This phase included coordinating two to three teams inside the tunnel at the same time to map the tunnel over a 2-day period. Mapping by each four-person team included identifying all significant cracks, infiltration and defects, as well as structures and previous repairs over the length of the tunnel. Technical Lead, Inspection and Rehabilitation of Heroes Tunnel, New Haven, Connecticut, 2007 to Mr. Gilbert reviewed the inspection results and recommendations of a multi-disciplinary field inspection that included geophysical testing ground penetration and ultrasonic measurements as well as visual inspection with hammer sounding to determine the integrity of the 2-foot-thick tunnel liner, shaft structure, and the masonry façade. The final report provided state-of-the-art methods for stopping or minimizing water leakage through tunnel lining and ventilations shafts and for repairing the damaged concrete. Horizontal Directional Drilling Technical Lead Geotechnical/Tunnel Engineer, HDD Crossing of Raritan River, New Jersey, 2009 to Mr. Gilbert served as the technical lead for the design of this 24- inch water main that set a record for length of fpvc at 5,350 lf in length. Exploration program consisted of both land and marine borings to develop the subsurface profile and used to set the vertical alignment of the water main in soil and to avoid an interface of with the rock. Technical Lead, Horizontal Directional Drilling (HDD) Milwaukee Gas Pipeline, Michigan, 2009 to The entire pipeline was designed within existing municipal or state right-of-way and was comprised of 9 miles of HDD and 4 miles of open cut construction. Mr. Gilbert was the technical lead for the geotechnical and trenchless crossings including all HDD work. Technical Review Horizontal Directional Drilling (HDD) Union Road, Spring Valley, New York, 2011 to Mr. Gilbert performed a technical review of data developed from a subsurface exploration and laboratory testing programs. Laboratory testing program included both soil and rock testing. He reviewed the design of the vertical alignment of the HDD profile, for the design of the 16-inch-diameter HDPE (750-ft long) forcemain, drawings and specifications for the HDD portion of the work. Technical Review, Horizontal Directional Drilling (HDD) Bees Ferry Road Design and Relocation of Sanitary Sewer Force Main, Charleston, South Carolina, 2011 to Mr. Gilbert reviewed design of the 10- and 12-inch-diameter fpvc (420-ft long) and the 36-inch-diameter fpvc (810-ft long) forcemains. Technical Review, Horizontal Directional Drilling (HDD) Dravo Forcemain, Louisiana, 2010 to Mr. Gilbert performed technical review of the vertical

9 alignment of the HDD profiles, for the design of the 30-inch diameter fpvc (650-ft long) and 36-inch diameter (630-ft long) forcemains, and for plans and specifications for the HDD portion of the work. Technical Review, Horizontal Directional Drilling (HDD) Governors Island, New York New York 2010 to 2012 Mr. Gilbert performed a technical review of proposed HDD works including design a 2,200 ft long, 12-inch diameter forcemain, plans and specifications. Technical Review, Horizontal Directional Drilling (HDD) Kings Highway HDD, Suffolk, Virginia 2011 to 2012 Mr. Gilbert performed a review of Geotechnical Data Report, plans and specifications for HDD river crossing or a 2,100 ft long, 16-inch-diameter forcemain. Senior Geotechnical Engineer, Horizontal Directional Drilling (HDD) Wareham, Massachusetts, 2012 Mr. Gilbert did a technical review of a HDD design for 4-inch-diameter, 575-ft long HDPE forcemain including plans and specifications. Publications Avolio, G. and M. Gilbert. Geotechnical Investigation for Soft Ground Tunnel in Alexandria, Egypt RETC, Vol. 1, Ch. 3, New Orleans, Louisiana, 1987 Gilbert, M., V.J. Perrone, and L. Maday Exploration Decision Analyses for Brightwater Tunnels RETC, Section 9, Ch. 64, Seattle, Washington, 2005 Bachand, M.L. and M.B. Gilbert Innovative Solution: A combined tunnel option for wastewater applications. ASCE Pipeline Conference Proceedings, Houston, Texas, June Haß, H. and M.B. Gilbert Support of the Leipzig City - Tunnel Extension Using a Tie-Back Supported Freeze Wall RETC Conference Proceedings, Section 3, p 197, Toronto, Canada, June Gwildis, U.G. and M.B. Gilbert Comparison of Risk Management Strategies for Microtunneling American Society for Trenchless Technologies Conference Proceedings, San Diego, California, April Newby, J., M. Gilbert, and L. Maday. Establishing Geotechnical Baseline Values for Deep Soft Ground Tunnels North American Tunnel Conference Proceedings, Track 3, Session 4, San Francisco, California, June Gilbert, M. and S. Dentz. L-73 Tunnel Woodbury Minnesota North American Tunnel Conference Proceedings, Track 4, Session 2, San Francisco California, June Short Tunnels = High Risk?: Pipeline Construction Involving Open Cut and Tunnel Segments Gilbert, M and Schultz, M. Part14 p 881 RETC, Las Vegas NV, June 2009 Wawrzyniak C. and Gilbert, M. Tunnels of the High Speed Railway System in Germany Proceeding of Seminar Tunnels of the World Planning, Design and Construction March 29-30, 2010 ASCE Met Infrastructure Group, Brooklyn NY Gilbert, M., Wesley, J. and Nyirenda, S. Tunneling to Preserve Tollgate Creek Proceeding of North American Tunnel Conference, Track x Session X4, Portland OR, June 2010.

10 Gilbert, M., Schultz, M., Wright, B. and Kelly, K. Risk Issues Associated with New Outfall Tunnel Under Great South Bay in Suffolk County, New York Part 6, p 374, Proceeding of RETC, San Francisco CA, June 2011 Haß H, Löffler, M, Michael Gilbert, M. Tunnel Boring Machine Rescue Projects, Section 3 Ground Treatment p 743 Proceedings of NAT, Indianapolis IN June 2012 Gilbert, M, Bernardeau F, Schultz M. Design-Build Tunneling Project in Urban Setting with Fast-track Engineering and Ground Modifications p.---- Part p, Proceeding of RETC, Washington DC, June 2013 Presentations Gilbert, M. Salinity Influence on Frozen Soils Strength. Presentation of paper by: Helmut Haß, Regine Jagow-Klaff and Rudolf Wernecke at the ASCE, 13th International Conference on Cold Regions Engineering Session C7: Frozen Soil Strength, University of Maine Orono, Maine, July 23-26, Gwildis, U.G. and M.B. Gilbert. Comparison of Risk Management Strategies for Microtunneling. American Society for Trenchless Technologies Proceedings, San Diego California

Dewatering - Time and Cost Relief by way of Trenchless Construction

Dewatering - Time and Cost Relief by way of Trenchless Construction North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 TA-T3-04 Dewatering - Time and Cost Relief by way of Trenchless Construction Jenn Stillman,

More information

P.O. Box 416 Winlock WA 98596 360-880-8804 http://jstridpe.com julius10@mac.com

P.O. Box 416 Winlock WA 98596 360-880-8804 http://jstridpe.com julius10@mac.com P.O. Box 416 Winlock WA 98596 360-880-8804 http://jstridpe.com julius10@mac.com Education: B.S., Mining Engineering, South Dakota School of Mines, 1980 Registration: Registered Engineer Washington State,

More information

WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598

WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598 Lessons Learned from Large Diameter Sanitary Sewer Pipe Bursting Project: Conversion of Abandoned Gravity Sewer Main Into Upsized Sanitary Force Main South San Francisco, CA Kent Von Aspern,* Collins Orton**

More information

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska APPENDIX B Geotechnical Engineering Report GEOTECHNICAL ENGINEERING REPORT Preliminary Geotechnical Study Upper Southeast Salt Creek Sanitary Trunk Sewer Lincoln Wastewater System Lincoln, Nebraska PREPARED

More information

Tunnelling & Underground. Specialists

Tunnelling & Underground. Specialists Tunnelling & Underground Specialists Mined Tunnels Excavation at Ayer Rajah Avenue, Singapore Introduction Amberg & TTI Engineering Pte Ltd (AETTI) was established in Singapore in 2002 by Amberg Engineering

More information

TUNNELING UNDER AUSTIN PROTECTING THE ENVIRONMENT, AND PRESERVING THE PEACE

TUNNELING UNDER AUSTIN PROTECTING THE ENVIRONMENT, AND PRESERVING THE PEACE TUNNELING UNDER AUSTIN PROTECTING THE ENVIRONMENT, AND PRESERVING THE PEACE Reynaldo Cantu, Pervez Jameel, Susan Kelly Brown and Caldwell 9011 Mountain Ridge Drive, Suite 100 Austin, TX 78759 ABSTRACT

More information

C O N S U L T A N T S RESUME

C O N S U L T A N T S RESUME C O N S U L T A N T S RESUME Ed Bove, P.E. SUMMARY OF EXPERIENCE Mr. Bove possesses 28 years experience in the civil engineering field. He has been involved with investigation, design, analysis, and quality

More information

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com

More information

SECTION 02401 SHEETING, SHORING AND BRACING

SECTION 02401 SHEETING, SHORING AND BRACING SECTION 02401 SHEETING, SHORING AND BRACING This section should be edited to reflect soil conditions specific to the project site and the recommendations of a Geotechnical Engineer licensed in the State

More information

BUTE Department of Construction Management and Technology

BUTE Department of Construction Management and Technology BUTE Department of Construction Management and Technology 02.10.2012 Definition 1: Foundation: The structure, that transmits the load of the building to the soil Definition 2: Load bearing soil (strata):

More information

LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD

LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD www.norcalpug.com LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD Bob Fisher and Lance Stracner Ameron Protective Lining J.R. Pipeline Co Inc. Abstract: The

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified. Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

More information

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation

More information

FY08 SEWER POINT REPAIRS BID TABULATION

FY08 SEWER POINT REPAIRS BID TABULATION 6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "

More information

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS Vince Luongo Petrifond Foundation Co., Ltd. PROJECT DESCRIPTION The York Durham Sanitary System (YDSS) Interceptor in the Town of Richmond Hill located

More information

Collection Systems Technology Fact Sheet Sewers, Conventional Gravity

Collection Systems Technology Fact Sheet Sewers, Conventional Gravity United States Environmental Protection Agency Collection Systems Technology Fact Sheet Sewers, Conventional Gravity DESCRIPTION Sewers are hydraulic conveyance structures that carry wastewater to a treatment

More information

RESUME Lee A. Knuppel, P.E.

RESUME Lee A. Knuppel, P.E. RESUME Lee A. Knuppel, P.E. OFFICE: EDUCATION: LEE A. KNUPPEL AND ASSOCIATES, Inc. 7770 Cooper Road, Suite 7 Montgomery, Ohio 45242 (513) 793-4222 Graduate: UCLA, Los Angeles, CA M.S. in Civil Engineering,

More information

Sewer systems: Failures and rehabilitation

Sewer systems: Failures and rehabilitation Water Utility Journal 8: 17-24, 2014. 2014 E.W. Publications Sewer systems: Failures and rehabilitation C. N. Damvergis Hellenic Association of Hydraulic Works and Water Resources Management Consulting

More information

Technical Memorandum Cost Criteria for 2010 System Capacity Plan

Technical Memorandum Cost Criteria for 2010 System Capacity Plan 2010 SASD SEWER SYSTEM CAPACITY PLAN UPDATE Technical Memorandum Cost Criteria for 2010 System Capacity Plan PREPARED BY: My Huynh DATE: September 13, 2011 REVIEWED BY: Sonny Lunde INTRODUCTION This Technical

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam

Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam Education Master of Business Administration University of Houston, 1985 Bachelor of Science, Civil Engineering University

More information

CHALLENGES IN LINING A 100 YR OLD BRICK SEWER

CHALLENGES IN LINING A 100 YR OLD BRICK SEWER North American Society for Trenchless Technology 2007 No-Dig Conference & Exhibition San Diego, California April 15-20, 2007 CHALLENGES IN LINING A 100 YR OLD BRICK SEWER Brad Jenson 1, Keith Hanks 2,

More information

Repair or Replacement - Band-Aids vs. Surgery

Repair or Replacement - Band-Aids vs. Surgery Repair or Replacement - Band-Aids vs. Surgery Using RCP for the Replacement of Failed or Undersized Culverts www.concrete-pipe.org Introduction and Background Our Nation s infrastructure owners are facing

More information

Specifications for Residential Property Owners Connection to New Public Sewer

Specifications for Residential Property Owners Connection to New Public Sewer Specifications for Residential Property Owners Connection to New Public Sewer Spalding Tract property owners are required to connect to the community sewer system when construction is complete and the

More information

Rehabilitation or Replacement? That Is The Question

Rehabilitation or Replacement? That Is The Question Rehabilitation or Replacement? That Is The Question Chris L. Windley PE Greg Anderson, PE 94th Annual Conference November 18, 2014 Overview Project Background Existing Sewer Condition Flow Projections

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

Sewer Rehabilitation Design Requirements

Sewer Rehabilitation Design Requirements Sanitary Sewer Overflow (SSO) Control and Wastewater Facilities Program Sewer Rehabilitation Design Requirements City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted by Prepared

More information

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Abstract The United States Virgin Islands Waste Management Authority

More information

C-2 Construction, Inc. - NAICS Codes

C-2 Construction, Inc. - NAICS Codes C-2 Construction, Inc. - NAICS Codes 212313 - Crushed and Broken Granite Mining and Quarrying This U.S. industry comprises: (1) establishments primarily engaged in developing the mine site, and/or mining

More information

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM Swaminathan Srinivasan, P.E., M.ASCE H.C. Nutting/Terracon David Tomley, P.E., M.ASCE KZF Design Delivering Success for

More information

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 SECTION B1: PREPARATION GUIDE B1.1 INTRODUCTION... B1-1

More information

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains

More information

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation 644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING

More information

Cost Estimating Procedures for Raw Sewage Overflow Control Program

Cost Estimating Procedures for Raw Sewage Overflow Control Program Raw Sewage Overflow Control Program April 23, 2004 Raw Sewage Overflow Control Program City of Indianapolis Department of Public Works Table of Contents Section Page 1.0 Introduction... 1 2.0 General Project

More information

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or

More information

The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11 Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;

More information

BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD DIRECT TESTIMONY OF STEPHEN J. FURTEK

BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD DIRECT TESTIMONY OF STEPHEN J. FURTEK BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD Re Application of the Philadelphia Water Department for Increased Rates and Related Charges Fiscal Years 2017-2018 DIRECT TESTIMONY OF STEPHEN

More information

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Stephen W. Lacz 1, M. ASCE, P.E. and Richard C. Wells 2, F. ASCE, P.E. 1 Senior Professional, Trigon Kleinfelder, Inc., 313 Gallimore

More information

Member Nation Report 2010 from Denmark.

Member Nation Report 2010 from Denmark. Member Nation Report 2010 from Denmark. The has during the year 2010 arranged 6 member meetings including two technical site visits. The first technical site visit covered the 5.3 km long Leipzig City

More information

Emerging Technologies in Wastewater Collection Systems

Emerging Technologies in Wastewater Collection Systems Keville Enterprises Emerging Technologies in Wastewater Collection Systems Douglas McCutchen, CCM Brian Karmasin, P.E., BCEE CMAA Annual Conference Oct 2008 San Francisco, California Today s s Presentation

More information

Section 2100-Trenching and Tunneling

Section 2100-Trenching and Tunneling SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial

More information

Pipe Bursting. Case Study at Zeeland, MI Collections Seminar September 6, 2012. Presentation Agenda. What is Pipe Bursting? What is Pipe Bursting?

Pipe Bursting. Case Study at Zeeland, MI Collections Seminar September 6, 2012. Presentation Agenda. What is Pipe Bursting? What is Pipe Bursting? Pipe Bursting Case Study at Zeeland, MI Collections Seminar September 6, 2012 By: Brian Hannon, PE and John Racek, PE Presentation Agenda What is Pipe Bursting? History of Pipe Bursting Types of Pipe Bursting

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located

More information

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) 1 Intent: The intent of trenchless sewer pipe Insertion is to rehabilitate the existing sewer

More information

Flowtite Jacking Pipe

Flowtite Jacking Pipe U.S. COMPOSITE PIPE SOUTH, LLC. MEMBER OF KTI PIPE GROUP OF COMPANIES Flowtite Jacking Pipe 18585 Samuels Rd. Zachary, La. 70791 PH. 225-658-6166 Fax 225-658-0947 www.flowtitepipe.com Flowtite GRP Pipe

More information

How to Design and Build a Fence/G traverse Bridge or Graffiti Project

How to Design and Build a Fence/G traverse Bridge or Graffiti Project Outline Project Location Project Description Project History Site Constraints Geotechnical Investigation & Soil Profile Foundation Design Process Photos Project Location Project Limits: The Grand River

More information

construction management Customized Approach, Global ExpErience, Innovative Delivery

construction management Customized Approach, Global ExpErience, Innovative Delivery program and construction management Customized Approach, Global ExpErience, Innovative Delivery Proven Solutions for Smooth, Successful Project Delivery Capital projects, by their nature, can be highly

More information

Monterey Regional Water Pollution Control Agency. Sewer System Management Plan

Monterey Regional Water Pollution Control Agency. Sewer System Management Plan Monterey Regional Water Pollution Control Agency Sewer System Management Plan March 31, 2013 Sewer System Management Plan Introduction I. Goals II. Organization III. Legal Authority IV. Operation and Maintenance

More information

DEPARTMENT OF ENVIRONMENTAL QUALITY

DEPARTMENT OF ENVIRONMENTAL QUALITY PROJECT IDENTIFICATION DEPARTMENT OF ENVIRONMENTAL QUALITY City of Burton Sanitary Sewer Collection System Improvements State Revolving Fund (SRF) Environmental Assessment April 2015 Applicant: Authorized

More information

COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY

COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY Revised: April 2014 Village of Wilmette, Illinois NPDES CSO Permit No. ILM580012 Chapter 1 Introduction This Operational and Maintenance

More information

GOWANUS EXPRESSWAY TUNNEL PRIMER

GOWANUS EXPRESSWAY TUNNEL PRIMER GOWANUS EXPRESSWAY TUNNEL PRIMER T he New York State Department of Transportation is currently studying the replacement of the Gowanus Expressway with a tunnel. This investigation involves looking at a

More information

See Appendix A for additional information, or contact ASTM directly.

See Appendix A for additional information, or contact ASTM directly. DEFINITIONS Wherever used in these specification guidelines, the following words and terms have the meanings indicated. AREAWAY: A paved surface, serving as an entry area to a basement or subsurface portion

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,

More information

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

Storm Sewer Trenchless Upgrade Alternatives and Recommendations Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for

More information

SECTION 7 UNDERDRAIN SERVICE

SECTION 7 UNDERDRAIN SERVICE SECTION 7 UNDERDRAIN SERVICE ARTICLE I USE OF THE PUBLIC UNDERDRAIN SYSTEM 7.100 The purpose of the District s underdrain system is to provide a method for conveying ground water from around building foundations

More information

District of Columbia State Data Center Quarterly Report Summer 2007

District of Columbia State Data Center Quarterly Report Summer 2007 District of Columbia State Data Center Quarterly Report Summer 2007 Commuting to Work: Bike? Walk? Drive? Introduction by Joy Phillips Robert Beasley In 2005, 45 percent of District residents drove to

More information

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit

More information

GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER

GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER Professional Experience: Pride and Passion in the Art of Structural Engineering since 1979. Professional Registration: Professional

More information

Earthquake damage in wastewater systems and postearthquake repair methods; limitation and practice

Earthquake damage in wastewater systems and postearthquake repair methods; limitation and practice Earthquake damage in wastewater systems and postearthquake repair methods; limitation and practice M. R. Zare 1, S. Wilkinson 2, R. Potangaroa 3 1. PhD candidate, University of Auckland, Auckland, New

More information

MLGW s Average Residential Utility Bill Ranks the Lowest

MLGW s Average Residential Utility Bill Ranks the Lowest MLGW s Average Residential Utility Bill Ranks the Lowest Each year, MLGW strives to deliver the highest quality service at the lowest possible rates. One way that we measure our performance is to examine

More information

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection

More information

Meeting the Challenge of Pipeline Emergency Repair

Meeting the Challenge of Pipeline Emergency Repair Meeting the Challenge of Pipeline Emergency Repair Michael R. McReynolds, PE, SE 1 Tao Peng, PE, SE 2 ABSTRACTS The Metropolitan Water District of Southern California (MWD) is the nation s largest provider

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

Oakland Macomb Interceptor Drain Rehabilitation State Revolving Fund Project Plan Overview. Public Meeting June 10, 2009

Oakland Macomb Interceptor Drain Rehabilitation State Revolving Fund Project Plan Overview. Public Meeting June 10, 2009 State Revolving Fund Project Plan Overview Public Meeting June 10, 2009 What is the OMI? The OMI is the Oakland Macomb Interceptor Sewer. The OMI transports much of the sanitary sewage from Oakland and

More information

After the Flush. Safe disposal of our wastewater is a valued and complex, not-for-profit municipal service.

After the Flush. Safe disposal of our wastewater is a valued and complex, not-for-profit municipal service. After the Flush Published: July 14, 2011 Sewage or wastewater is something we rarely think or talk about. The wastewater from our toilets, showers, washing machines and dishwashers quickly departs our

More information

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth

More information

Type of Sewer Systems. Solomon Seyoum

Type of Sewer Systems. Solomon Seyoum Type of Sewer Systems Solomon Seyoum 0 Learning objectives Upon completion of this lecture, the participants will be able to differentiate between types of sewer systems and discuss different aspects of

More information

Section 02415. Installation of pipe and casing for sanitary sewer by methods of augering.

Section 02415. Installation of pipe and casing for sanitary sewer by methods of augering. ITY OF PRLN UGRING PIP OR SING FOR SWRS Section 02415 UGRING PIP OR SING FOR SWRS 1.0 G N R L 1.01 STION INLUS Installation of pipe and casing for sanitary sewer by methods of augering. References to Technical

More information

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental

More information

Beacon Hill Sewer District Standard Specifications

Beacon Hill Sewer District Standard Specifications Beacon Hill Sewer District Standard Specifications Residential Gravity Side Sewer Including Design Criteria and Standard Construction Drawings Residential Gravity Side Sewer Design Criteria 1. Provisions

More information

Environmental Impairment Liability Application 2

Environmental Impairment Liability Application 2 1. Applicant/Parent Company Date Needed: Applicant/Parent Company Address: Effective Date: Phone Number: Website: _ 2. Requested Coverages: Proposed Limits/Retention Onsite Cleanup/3rd Party Liability

More information

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe 1. GENERAL The following supplemental sewer main specifications are intended to address the installation of high-density polyethylene

More information

Letty Arvide-Gomar, PE

Letty Arvide-Gomar, PE Letty Arvide-Gomar, PE Outline DIP History and Applications Corrosion Issues Internal Cleaning Technologies Rehabilitation Options DIP History and Applications Corrosion Issues Internal Cleaning Technologies

More information

District of Columbia Water and Sewer Authority George S. Hawkins, General Manager

District of Columbia Water and Sewer Authority George S. Hawkins, General Manager District of Columbia Water and Sewer Authority George S. Hawkins, General Manager FLOODING ISSUES IN BLOOMINGDALE AND LeDROIT PARK A DC Water Presentation Given to the Mayor s Task Force on the Prevention

More information

GLOSSARY OF TERMINOLOGY

GLOSSARY OF TERMINOLOGY GLOSSARY OF TERMINOLOGY AUTHORIZED PILE LENGTHS - (a.k.a. Authorized Pile Lengths letter) Official letter stating Engineer's recommended length of concrete piles to be cast for construction of foundation.

More information

Sanitary Sewer Master Plan

Sanitary Sewer Master Plan , Illinois Sanitary Sewer Master Plan EXECUTIVE SUMMARY Prepared by September 9, 2010 1670 South Taylorville Road Decatur, Illinois 62521 www.bgmengineering.com Sanitary Sewer Master Plan A. SCOPE OF STUDY

More information

Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses

Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses They also give the community a built-in re-entry system for future monitoring and repair. BY BRETT HANES According to

More information

Coast Trunk Sewer Rehabilitation Project for the Orange County Sanitation District

Coast Trunk Sewer Rehabilitation Project for the Orange County Sanitation District Coast Trunk Sewer Rehabilitation Project for the Orange County Sanitation District Paul F. Wilson 1 and Robert J. Warren 2 1 1525 Faraday Ave, Suite 290, Carlsbad, California, USA 92008; e-mail: pwilson@pirnie.com.

More information

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair Eric M. Klein, P. E., Rummel, Klepper & Kahl, LLP, Baltimore, Maryland Kenneth B. Andromalos, P. E., Brayman Environmental,

More information

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent

More information

SECTION 02400 - STORM DRAIN SYSTEM

SECTION 02400 - STORM DRAIN SYSTEM SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And

More information

City of Friendswood FY 2010 Capital Improvements Program - Water & Sewer Projects 5-Year CIP

City of Friendswood FY 2010 Capital Improvements Program - Water & Sewer Projects 5-Year CIP City of Friendswood FY 2010 Capital Improvements Program - Water & Sewer Projects 5-Year CIP PROJECT ESTIMATED COST ESTIMATED COUNCIL IDENTIFIED FUNDING SOURCES STRATEGIC COMPLETION INITIATIVES FM 2351/Beamer

More information

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TN 5.14 February 2010 Introduction It may be at times necessary, in an aging infrastructure, to rehabilitate drainage and sanitary lines

More information

Section 402. STORM SEWERS

Section 402. STORM SEWERS 402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide

More information

2010 Allocations to States of Volume Cap for Qualified School Construction Bonds

2010 Allocations to States of Volume Cap for Qualified School Construction Bonds 2010 Allocations to States of Volume Cap for Qualified School Construction Bonds Total Dollar Allocation by State/ State/Territory Territory Alabama 140,453,000 Alaska 28,163,000 Arizona 171,115,000 Arkansas

More information

Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1

Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1 Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1 The Montgomery County Dept. of Environmental Protection, in cooperation with the Dept. of Permitting Services and the Washington

More information

Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle

Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle EPB-TBM Face Support Control in the Metro do Porto Project, Portugal S. Babendererde, Babendererde Engineers LLC, Kent, WA; E. Hoek, Vancouver,

More information

Executive Director, Engineering & Construction Services Director, Purchasing & Materials Management Division

Executive Director, Engineering & Construction Services Director, Purchasing & Materials Management Division PW8.5 STAFF REPORT ACTION REQUIRED Contract Award Request for Proposal No. 9117-15-7122 Engineering Services for the Detailed Design, Services During Construction, and Post-Construction Services for an

More information

How To Design A Combined Sewer And Storage Tunnel

How To Design A Combined Sewer And Storage Tunnel IWA Publishing 2015 Water Practice & Technology Vol 10 No 2 282 doi: 10.2166/wpt.2015.033 New tunnel system to eliminate sanitary sewer overflows and control combined sewer overflows in Hartford, Connecticut

More information

CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST

CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST 1 Permeability is a measure of the ease in which water can flow through a soil volume. It is one of the most important geotechnical parameters. However,

More information

BRIDGES ARE relatively expensive but often are

BRIDGES ARE relatively expensive but often are Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the

More information

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

1.3.2 Method of construction and restoration of existing water service connections. This shall include: 1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting

More information

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples Prof. V.S.Raju (Formerly: Director, IIT Delhi & Professor and Dean, IIT Madras) Email: rajuvs_b@yahoo.com

More information

Annular Space Grouting of Slipline Products

Annular Space Grouting of Slipline Products Annular Space Grouting of Slipline Products by David Gellings(, M.APWA & John Jurgens(, M.WWCPA Traditional methods of using neat cement slurries, (Portland cement and water, cement with fly ash or cement

More information

Special Specification 7021 Water Main and Sewer Line Replacements

Special Specification 7021 Water Main and Sewer Line Replacements Special Specification 7021 Water Main and Sewer Line Replacements 1. DESCRIPTION Furnish, install, or replace water pipe, water valves, water meters and boxes, water service connections, fire hydrant assemblies,

More information

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, Storm Drain Installation, of these Standard Provisions. SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and

More information

SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER

SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER Village of Shorewood, Wisconsin SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER Prepared By: Thomas A. Zoulek, P.E., LEED A.P. Vice President Mid City Plumbing & Heating

More information

EXECUTIVE SUMMARY. Salini Impregilo / Healy / GLF Joint Venture

EXECUTIVE SUMMARY. Salini Impregilo / Healy / GLF Joint Venture EXECUTIVE SUMMARY statement of qualifications chesapeake bay bridge and tunnel district EXECUTIVE SUMMARY With extensive international tunneling and marine design and construction experience, Salini Impregilo/Healy/GLF

More information