Extending Power Cable Life an Additional 40 Years Richard K. Brinton & Glen J. Bertini Novinium, Inc.
|
|
|
- Mervin Dorsey
- 10 years ago
- Views:
Transcription
1 Extending Power Cable Life an Additional 40 Years Richard K. Brinton & Glen J. Bertini Novinium, Inc. Abstract: For more than 20 years, cable rejuvenation has been used at electric utilities to extend power cable life. Most cable rejuvenation has been carried out in residential subdivisions. However, with the latest improvements in injection fluids, industrial customers are beginning to adopt cable rejuvenation for chemical, industrial, and power plants as an insurance policy against power cable failures. For about one-half the cost of replacement, power cable life can be extended up to 40 years. INTRODUCTION Cables injected (Km) Estimated Annual Power Cable Injection Rates If only we could do for humans what can now be done for medium voltage power cables. Imagine that as you approached the end of your life, you could drink a magic elixir and within a week you could perform at your peak in every way for another 40 years. That is precisely what rejuvenation fluid does for power cables but is not magic it is chemistry and physics. You have another option: you can replace the aging plant power cables with new cable. The new cable will perform reliably, but installing it will disrupt the plant, take a lot longer, squander scarce world resources, and cost 2 to 5- times more, which must ultimately be reflected in your production costs. Rejuvenation is a safer, faster and better alternative. From 1984 through 2008, over 80 million feet of medium voltage power cables were rejuvenated as shown in Figure 1. As demonstrated by [5], injection is typically less than onehalf the cost of replacement, and cable rehabilitation economics almost always favor rejuvenation over replacement. Undoubtedly, the favorable economics of rejuvenation fueled the rapid growth in rejuvenation depicted in Figure 1. How successful has rejuvenation been for circuit owners that have injected cables? According to [6], of the over 80 million feet of cable rejuvenated, less than 1% of the cable has failed. In a soon to be published paper, recent improvements in fluid formulations have dropped the failure rate to less than 0.5% for the most advanced fluid and injection techniques. In addition to having an attractive cost profile, cable rejuvenation also saves time. At an industrial plant, it takes less than one day to inject even long lengths of medium voltage cables, and typically only a couple of hours for most cables. What is the cost of a failure in your plant? Many industrial plants were constructed between 1965 and From the time of construction until now, the medium Figure 1. Cumulative injection compiled from dozens of industry sources including [1], [2], [3] and [4] demonstrate the growing importance of injection technology. voltage power cables have worked without failure. However, many industrial plants of this vintage are facing failures that could shut down the plant for an extended period, or at least shut down a line for a day or two. Failure costs vary widely in industrial facilities. On the low end, there may be a cable that runs 20 meters from switchgear to a motor through a lightly loaded, easily accessible cable tray, where the cables are not interlaced with other cables. This cable should be easy and inexpensive to remove and then install a replacement cable. Its failure should not cause the failure of adjacent cables. However, this is not typical in industrial plant settings. Power cable runs of up to 750 meters are common. The cable paths are not straight. Cable might be in conduit, or interlaced with other cables in one or more cable trays on different levels. The cable trays might not be accessible. The conduit may have collapsed, preventing the cable from being easily pulled out. Where cable is buried, additional problems can occur. Many times new buildings are constructed over the original path of the cable. The impact of a failure can be a significant economic event. In one aluminum smelter, the cost of a one hour power outage to the line was about $250,000. If it extended over an hour, the cost rose to over $100,000,000, because the aluminum solidified and the plant had to be rebuilt from the ground up. Think about what a power cable failure in your plant might cause in downtime, repair cost, lost production value, and environmental damage. Page 1
2 Vented Water Tree Electric Tree Figure 2. Water trees initiate from defects (dirt) in the insulation. When water trees grow large enough, an electric tree is formed (see inset). After an electrical tree is formed, cable failure usually follows. What Causes Medium Voltage Power Cable Failures? Medium voltage cables fail due to a phenomenon called water trees. Water trees can grow from the inside of the cable out, from the outside of the cable in, or from defects within the insulation. As they grow, they look like trees or bushes. Figure 2 shows how water trees grow until they can no longer hold the voltage stress and an electric tree is formed. Once an electrical tree is formed, the cable usually fails within two weeks. Figure 3 provides an overview of cable aging and failure mechanisms (rectangles) and the mechanisms by which cable rejuvenation (rounded rectangles) interfere with aging and failure. It is not the purpose of this paper to recite the work of countless others to explain the mechanisms of water treeing and how those water trees ultimately lead to failure. Instead, we briefly review the process described by Figure 3. Manufacturing Defects while not absolutely required for water tree growth, they certainly accelerate the growth and propagation of water trees and hence the longest water trees in any section of cable are quite likely to involve some imperfection. AC stress, Ions, and Water are the three requirements for the growth of water trees (see Figure 2). In general, reductions in any of these three elements retard water tree growth. Local high-density space charge and electrical fields are the inevitable consequence of large water trees and are exacerbated by transient over-voltage events such as switching, failure, lightning, and off-line cable testing. Figure 3. Cable aging, failure and rejuvenation mechanisms. UV emission is a consequence of space charges returning to their ground state. Ultraviolet photons are emitted, which have sufficient energy to destroy polyethylene bonds and spawn damaging free radicals. Hot electron acceleration is a consequence of very high local fields created around some dielectric imperfections including space charges. Hot electrons can break polyethylene bonds and create free radicals. Thermo-mechanical stress causes the halo visible in most aged cables, which are exposed to water and a 24-hour temperature cycle and is described in [7]. As the cable warms, the solubility of water in polyethylene increases substantially and more water rapidly diffuses into the cable from the surrounding soil. As the temperature of the cable falls, the solubility of water decreases and water cannot permeate out of the cable quickly enough to avoid supersaturation. Driven by thermodynamic forces, the supersaturated water seeks its liquid state and condenses to the micro-voids of the halo. Void formation is caused by UV photons and hot electrons created primarily through the water tree process and by the thermo-mechanical stress. PD (partial discharges) manifest in voids, which are large enough for the gas within the voids to be ionized by the electrical field. The PD inception voltage is greater than the extinction voltage, because once the gas within the void becomes ionized; the PD is more easily sustained. Failure results as partial discharges erode the wall of the void in which they occur. The erosion of each discharge in a PE void increases the size of the void and hence decreases the partial discharge inception and extinction voltages for that void. This self-acceleration means that any PD occurring at operating voltages in polyethylene is likely to lead to rapid failure. Page 2
3 What is Cable Rejuvenation? Cable rejuvenation introduces silicone fluid into medium voltage power cable strands. The fluid migrates into the conductor shield and the insulation. Injection fluids modify the chemistry of the insulation and the physics of the cable to extend the reliable life of the cable circuit. What Problems does Cable Rejuvenation Solve? Problems You Face Declining cable reliability Spending more than $10/ft to solve power cable reliability problems Insufficient maintenance budget for cable failures Table 1. Problems and outcomes. Rejuvenation Outcomes Achieved Same reliability as new cable in a fraction of the time 50% cost reduction Shift cost of cable failures from O&M $ to CAPX $ What applications for fluid injection in power cables have proven to be successful? HMWPE, XLPE, TR-XLPE, EPR, butyl-rubber insulation Single phase cables (conductors generally 4/0 or smaller) Feeder cables (3 conductors generally larger than 4/0) Network cables Transmission cables Submarine cables It is not possible to inject: Solid conductor cable Strand blocked cable Paper-lead cables How Does Rejuvenation solve the cable failure model? Figure 3 shows seven rejuvenation mechanisms (as rounded rectangles) along with arrows, which indicate the steps of the aging and failure process, which are interfered with by each rejuvenation mechanism. The seven rejuvenation mechanisms are described below. Ingredient Isolauryl alcohol Tolylethylmethyldimethoxysilane Dodecylbenzenesulfonic acid Cyanobutylmethyldimethoxysilane Tinuvin 123 Tinuvin 1130 Geranylacetone Ferrocene Irgastab Cable KV10 Purpose Short term Medium term silane Condensation catalyst Long term silane; Stress grading HALS UV stabilizer UVA stabilizer Voltage stabilizer PD suppression; UVA stabilizer Antioxidant Table 2. A summary of the ingredients utilized by the cable rejuvenation process. (Tinuvin and Irgastab are registered trademarks of Ciba Specialty Chemicals.) MICRO-VOID FILLING Not to be confused with voids, which can be imaged with an optical microscope, micro-voids are on a much smaller scale. These micro-voids are usually chemical imperfections in the polyethylene and are characterized by the presence of bonded oxygen, often carboxyl-groups, which have an affinity for water relative to non-treed PE. The silanes react with and displace (see DRYING) water at oxidized PE sites within the water trees. The replacement of conducting ionic water with a silicone dielectric increases the dielectric strength of the insulation. DRYING There are two drying effects. The first, the chemical reaction of silanes with water, is the most widely reported in past literature, but is the less important of the two drying effects. Much more important than the transient chemical drying is the ability of the treatment to reduce the reentry of water. To this end, materials, which have an improved affinity for polyethylene, provide superior water repellent capability. STRESS GRADING The inclusion of high dielectric constant layers to grade the electric field within cables and cable components is widely practiced and well understood. Cable rejuvenation provides stress grading on a micro-scale inside the voids. VOLTAGE STABILIZATION The voltage stabilizing effects of ketones are due to keto-enol-tautomerism and were first demonstrated by [8] and later in [9]. Tautomers provide a stable receptor for hot electrons. The enol form of the tautomer absorbs much of the energy of hot electrons and converts to the transition forms and a free proton. These resonant transition forms delocalize the excess negative charge. The theory is that a hot electron is first captured, then thermalized, and finally released. Page 3
4 UV STABILIZATION Rejuvenation technology includes components, which absorb photons in the 275 to 400 nm range. These are called ultra violet absorbers or UVA for short. Specifically Tinuvin 1130 and ferrocene provide the appropriate absorption. Tinuvin 1130 and ferrocene are each quite soluble in PE, but diffuse slowly. Their beneficial UVA effects persist for over 4 decades in most applications. In addition to the UVA component, a hindered amine light stabilizer, or HALS component, is included. HALS are free radical scavengers that trap radicals before subsequent reaction leads to polymer degradation. As demonstrated in [10], HALS are self regenerative. After quenching a free radical, the HALS regenerate and can then quench another free radical. UVA and HALS enjoy a chemical synergy. Since UVA materials attenuate UV emissions, there will always be some UV photons, which damage the polymer, and this is the case where the HALS comes to the rescue. However, by itself, a HALS would be overwhelmed, if 100% of the UV photons damaged polymer bonds. Together, UVA and HALS provide greater UV stability than either one alone. ANTIOXIDATION Antioxidants are included in virtually all modern cable compound formulations. While originally deployed to prevent oxidation during the extrusion process, it has been shown in [11] that antioxidants also slow the growth of water trees. It has also been demonstrated in [12] that the presence of antioxidants increases the electrical tree inception voltage. KV10, a sulfur containing phenolic antioxidant, has been demonstrated to slow the growth of water trees by a factor of four. This class of sulfur containing phenolic antioxidants has been shown to increase electrical tree initiation voltage by up to 75% at just 0.2% w. KV10 enjoys a very high solubility in polyethylene, and because of its high molecular weight of 424.7, a very low diffusion rate. The combination of high solubility and low diffusivity yields a very low sweat out or exudation as was shown in [11]. PD SUPPRESSION There are several mechanism involved in the suppression of partial discharges or PDs. First as described previously, local stress reduction though stress grading increases the partial discharge inception and extinction voltages. As described in [13], a free electron, sometimes from cosmic rays, is a necessary precursor to the initiation of a PD. Therefore, a second suppression mechanism is provided by the electron affinity of the previously described voltage stabilizer (geranylacetone) described in [8] and [9], and the electron accepting ferrocene as shown in [14]. Third and fourth mechanisms are also provided by the ferrocene. The presence of ferrocene is designed to prevent the inception of partial discharges. This is accomplished by rendering the walls of large voids partially conductive when voltages exceed a threshold well below typical inception voltages in a manner analogous to the electronic activation of a transistor. Once the walls are partially conductive, the e- field all but disappears. In the event that a PD does occur, a small portion of the ferrocene is consumed and simultaneously raises the pressure in the void and releases an oxygen scavenger, namely atomic iron. These effects act to quickly snuff out incipient partial discharges and mitigate the damage normally incurred when a discharge occurs. How are cables injected in the field? Rejuvenation Injection Process De-energize, test & ground cable (A-B) Pinpoint all splices; vacuum-excavate Remove all splices, terminations & connectors Position new connectors, injection adaptors & new splices flush Figure 4. Overview of injection process. What is the Business Case for Injection? Swage injection adaptors & connectors Inject sub-segments at moderate pressure feed tank x 2 flush Engineering experts now believe the nation is entering a period that could be marked by a dramatic increase in power cable failures unless considerably more is spent on addressing old and deteriorated cables in industrial plants. Cable rejuvenation is at a minimum one-half the cost of replacement. More typically it is 1/3 to 1/5 the cost of replacement. Factors that increase the cost advantages of injection are: Copper conductors vs. aluminum conductors Direct buried cables or collapsed conduits Longer cable runs Unknown cable routes Cable routes with many turns Interlaced cables in cable trays Cable tray inaccessibility The time to inject a cable is significantly less than the time to replace a cable. Typically once the cable ends are replaced, injection takes from 1-12 hours depending on the cable length and the strand compaction. Runs of 100 meters can be injected in less than one hour. Cables of 600 meters could take 12 hours. Cable replacement for runs of 100 meters could take up to a day and runs of 600 meters could take up to 3 days or more, depending on accessibility. Page 4
5 The space, accessibility, and equipment required for cable rejuvenation is considerably less than for cable replacement. No lifting or heavy pulling equipment is required, only small tanks of fluid on either end of the cable are utilized. Because rejuvenation is typically less than one-half the cost of replacement, you can extend the life of at least twice as much cable with the same budget. New cables and rejuvenated cables today both have an expected life of 40 more years. Once an older vintage cable is over 20 years old, there is a definite risk of cable failure. Cable rejuvenation can be like buying an insurance policy, once this point in time is reached in a cable s life. With rejuvenation, cable life can be extended another 40 failure-free years. Where has cable rejuvenation been used for industrial plants cables? Terra Industries, Oklahoma This anhydrous ammonia plant in Woodward, OK was built in 1975 and the cables are now 34 years old. The plant has eight 3-phase, 5 kv, 1000 kcm, EPR insulated cables feeding the plant. In 2007, there was a cable failure on one phase of one cable. Terra was concerned that an additional failure could shut down the plant. Consequently, the plant wanted to insure that the cables did not fail. Each cable was about 200 meters long and ran from the incoming power line pole, then underground across the parking lot, and into the switchgear from underneath. Three of eight cables were injected during plant operations in January The last cable in the first half was not injected, because excavating the cable fault could have caused damage to other live cables encased in the same concrete slurry. The injection of these three cables took 3 days out of 7 days onsite. Three phases of each cable were injected at one time. In addition to replacing the terminations, the rejuvenation crew carried out proactive preventative maintenance by installing new arrestors for the plant. Mark Jensen, Engineering Manager, said, We were very impressed with the rejuvenation process. The people were knowledgeable and worked efficiently. They found problems with our terminations and solved them. We liked the fact that the injection did not leave any smell in our plant. All chemical preparation was done outside. When they came inside everything was sealed. We were disappointed that we could not repair the faulted cable, but the risk was too great to the other live cables. Based on the success of this project, we plan to inject the remaining four 3-phase cables next year after the weather cools down and the plant electric load is lower. In January 2009, during a plant shutdown, the remaining four 3-phase cables were injected. Because of the success of these cable injection projects, the plant is considering injecting additional cables. When complete, all medium voltage cables will last another 40 years. Power Plant, Texas In September 2008, Hurricane Ike struck the Texas coast and the storm surge that followed resulted in flooding at a power plant near the coast and most of the plant was underwater. Two weeks after the storm, when disconnecting a motor, plant personnel found water running out of one of the cables. After many years in operation, the cable ends were no longer sealed. It was important to remove this salt water from the cable strands before restarting the plant. Cable rejuvenation was selected for this work, because the work could be completed in days vs. the weeks that it would have taken to replace the cables. The schedule advantage was the key decision factor in selecting injection in order to maintain the plant restart date. Rejuvenation injection adaptors were also an important decision factor, because the in injection adapters permanently seal the ends of the cable. If a future storm surge ever flooded this plant, no salt water will get into the treated and sealed cable strands. First, a survey was carried out. Cables to be treated were identified and the required parts and equipment were ordered. Two days later the equipment, fluid, and personnel were onsite and had begun work to restore the cables. Over the next 14 days, over 25,000 feet of cable were rejuvenated. The cost of the rejuvenation was about 1/3 the cost of buying and pulling in new cables, and much less plant labor was required to complete the work. Rejuvenation also provided a significant schedule advantage over pulling in new cables. Because the plant knew very little about cable rejuvenation before this project, there were many skeptics at the plant about this process. After treatment and before plant startup, the cables were tested. The results were exceptionally good better than new cable, and 100 times better than the last test on the cables before the storm. After this project, the plant said that cable rejuvenation would be part of their regular decision process in the future. How can cable rejuvenation help industrial plants reduce their carbon footprint? For every meter of cable injected 16 grams of silicon fluid are used 195 grams of aluminum are saved Page 5
6 484 grams of copper are saved 963 grams of plastic are saved Diesel fuel-1.09 gal/meter is eliminated for: Transporting the cable, factory to site Taking bigger construction equipment to the site Drilling, trenching, or using a backhoe What impact can rejuvenation have on your plant? Was your plant built before 1985? If so, have any of the medium voltage power cables failed? If not yet, what would be the impact of a cable failure on your plant? SUMMARY As medium voltage cables age past 20 years, they will begin to fail and cause plant outages. These outages can cause a major disruption to plant operations, depending on the cable location. One solution is cable replacement before failure. Another solution is cable rejuvenation. Cable rejuvenation is almost always the most cost effective rehabilitation strategy. In addition, the time and disruption required to implement this solution are much lower. With the 40-year cable life extension provided by rejuvenation, more and more industrial plants are choosing to rejuvenate. REFERENCES 1. Tarpey, "Cost Effective Solution to URD Reliability: Cable Rehabilitation, Pennsylvania Electric Association T&D Committee Meeting, May 8, Bertini & Chatterton, Dielectric Enhancement Technology, IEEE Electrical Insulation Magazine, March/April 1994-Vol.10, No.2, pp Bertini, "Failures in Silicone-Treated German Cables Due to an unusual Methanol-Aluminum Reaction", ICC meeting Minutes, October, , p Bertini, "Injection Supersaturation in Underground Electrical Cables", U.S. Patent 6,162, Bertini, Advancements in Cable Rejuvenation Technology, IEEE/PES 1999 Summer Meeting, Reliability Centered Maintenance, July 21, Chatterton, A New Generation Cable Restoration Fluid, oral presentation IEEE/ICC/SubA, Nov. 28, Bertini, Molecular Thermodynamics of Water in Direct- Buried Power Cables, IEEE Electrical Insulation Magazine, Nov. /Dec Wartusch, Increased voltage endurance of polyolefin insulating materials by means of voltage stabilizers, IEEE Wartusch, et al Polymer-based electrical insulation and electrical conductor insulated therewith, U.S. Pat. 4,897, Step et al, Mechanism of Polymer Stabilization by Hindered-Amine Light Stabilizers (HALS). Model Investigations of the Interaction of Peroxy Radicals with HALS, Amines, and Amino Ethers, Macromolecules 1994, v. 27, pp Matey & Labbe, Exploring the Water Treeing Inhibition Effect of Antioxidants for XLPE Insulation, Jicable 07, 7 th International Conf. on Insulated Power Cables, pp Sekii et al, Effects of Antioxidants on Electrical Tree Generation in XLPE, 2001 IEEE 7 th Int l Conf. on Solid Dielectrics, June 25-29, pp Boggs, Diagnostic Techniques for Medium and High Voltage Cable, 2003 Spring ICC, Subcommittee A. 14. Gubin et al, Redox Properties of Cyclopentadienylmetal Compounds Ferrocene, Ruthenocene, Osmocene, J. Organometallic Chem., v. 30 (1971), pp AUTHORS Richard K. Brinton is the Vice President of Business Development of Novinium. He has been responsible for introducing cable rejuvenation to utilities around the world. Brinton has over 30 years experience in business development in the Americas, Europe, Asia, and Australia. He has focused his career on the worldwide introduction of new technologies and has gained worldwide experience in industrial processes, machine tools, robotics, and construction. Mr. Brinton holds a B.S. in Industrial Engineering and a B.A. Liberal Arts from the Pennsylvania State University, is a Senior Member of the IEEE, and is a licensed professional engineer. Glen J. Bertini is the President, CEO and Chairman of Novinium, Inc. He has spent the last two decades working with cable rejuvenation technology beginning with its development at Dow Corning in 1985 and continuing through its commercialization and growth to over 80 million feet of cable rejuvenated so far. Mr. Bertini was employed by Dow Corning, a silicon chemical manufacturer, as a development engineer, where he was part of a small team that developed and commercialized the first cable rejuvenation products. Mr. Bertini has over 40 articles published on the subject of cable rejuvenation technology, holds 23 patents, and has 7 more pending. Mr. Bertini holds a B.S. in Chemical Engineering from Michigan Technological University, is an IEEE Fellow, a voting member of the ICC, and a licensed professional engineer. Page 6
Total System Reliability - Extending the Life of Electrical Cable Systems
Total System Reliability - Extending the Life of Electrical Cable Systems Wayne J. Chatterton, Ph.D. Technical Applications Manager UtilX Corporation 2 Cable Installation History Medium Voltage Underground
Cable Failure, Diagnostics and. Steven Boggs
Cable Failure, Diagnostics and Rejuvenation Steven Boggs The History PE Cables The Zeigler catalyst was invented in 1953 and mass production of HDPE started in the late 1950 s. Chemically cross linked
A Power Cable Reliability Solution
A Power Cable Reliability Solution IEEE Insulated Conductors Committee Subcommittee C October 30, 2006 Benjamin Lanz Some of the technologies referenced herein are patented and proprietary IMCORP technology.
How To Test For Safety On A Power Cable
T H E M A G A Z I N E O F 7 x 2 4 E X C H A N G E I N T E R N AT I O N A L A Green Approach to Building a Superior Data Center S P R I N G 0 9 BUILD FOR TODAY. EXPAND ON DEMAND. Modularity in the data
TAN δ (DELTA) CABLE TESTING OVERVIEW AND ANSWERS TO FREQUENTLY ASKED QUESTIONS. What Is Tan δ, Or Tan Delta?
TAN δ (DELTA) CABLE TESTING OVERVIEW AND ANSWERS TO FREQUENTLY ASKED QUESTIONS What Is Tan δ, Or Tan Delta? Tan Delta, also called Loss Angle or Dissipation Factor testing, is a diagnostic method of testing
On-line PD Monitoring Makes Good Business Sense
On-line PD Monitoring Makes Good Business Sense An essential tool for asset managers to ensure reliable operation, improve maintenance efficiency and to extend the life of their electrical assets. Executive
IEEE POWER ENGINEERING SOCIETY CHICAGO CHAPTER THE OKONITE COMPANY WEDNESDAY JANUARY 11, 2006 JIM FITZGERALD ENGINEERING LINGO
IEEE POWER ENGINEERING SOCIETY CHICAGO CHAPTER THE OKONITE COMPANY WEDNESDAY JANUARY 11, 2006 JIM FITZGERALD ENGINEERING LINGO WHEN YOU HEAR AN ENGINEER SAY A NUMBER OF DIFFERENT APPROACHES ARE BEING IMPLEMENTED
HIGH- AND EXTRA-HIGH-VOLTAGE GLOBAL CABLE SYSTEM SOLUTIONS Rely On Our Experience... Experience Our Capabilities
HIGH- AND EXTRA-HIGH-VOLTAGE GLOBAL CABLE SYSTEM SOLUTIONS Rely On Our Experience... Experience Our Capabilities RELY ON OUR EXPERIENCE... EXPERIENCE OUR CAPABILITIES For close to half a century, Silec
SUITABILITY OF DIFFERENT TEST VOLTAGES FOR ON-SITE TESTING OF XLPE CABLE SYSTEMS
SUITABILITY OF DIFFERENT TEST VOLTAGES FOR ON-SITE TESTING OF XLPE CABLE SYSTEMS Michael Hensel HIGHVOLT Prüftechnik Dresden GmbH 2 3 Content 1 Introduction Test parameters and their significance Differences
Why Buy HVI VLF Products?
Very Low Frequency AC Hipots AC testing of cables and electrical apparatus is now easier than ever. Since the introduction of the High Voltage, Inc. line of portable and affordable VLF hipots, there is
WIRE AND CABLE ENGINEERING GUIDE
DC Hi Pot Testing Excerpt from PRYSMIAN S WIRE AND CABLE ENGINEERING GUIDE (FOR INFORMATIONAL PURPOSES ONLY) Page 1 of 6 DC HIGH POTENTIAL TESTING DC Hi-Pot testing can be applied as a withstand test (a
Stephen G. Whitley, Senior Vice President & Chief Operating Officer
Peter T. Brandien Vice President, System Operations To: Stephen G. Whitley, Senior Vice President & Chief Operating Officer From: Peter T. Brandien Re: Discussion of Cable Technologies Under Evaluation
Introduction: Background of the OIT Test:
The Effect of Hindered Phenol Stabilizers on Oxygen Induction Time (OIT) Measurements, and The Use of OIT Measurements to Predict Long Term Thermal Stability Philip Jacoby, Vice President of Technology,
PRODUCT / APPLICATION INFORMATION
Abstract This paper will discuss performance life testing and stability testing used for self-regulating heating cables. It will show how the techniques were developed and evolved from the 970 s to the
ComEd Grid Renewal Terence R. Donnelly
ComEd Grid Renewal Terence R. Donnelly Executive Vice President and Chief Operating Officer September 23, 2013 COMED S GRID MODERNIZATION VISION ComEd will fulfill the promise of grid modernization for
MOBILE SYSTEM FOR DIAGNOSIS OF HIGH VOLTAGE CABLES (132KV/220KV) VLF-200 HVCD
MOBILE SYSTEM FOR DIAGNOSIS OF HIGH VOLTAGE CABLES (132KV/220KV) VLF-200 HVCD VERY LOW FREQUENCY (VLF) - PARTIAL DISCHARGES AND TANGENT DELTA HV/EHV POWER CABLES DIAGNOSTIC AND ON-SITE FIELD TESTING WITH
Multi-pollutant control solutions for coal based power plants
Multi-pollutant control solutions for coal based power plants By Luca Mancuso and Hans Janssen Content SOx control Wet Scrubbers Open towers Dual Flow Tray Technology Semi-Dry SDA CFB Scrubbers Dust control
SPACE CHARGE ACCUMULATION UNDER THE EFFECTS OF TEMPERATURE GRADIENT ON SOLID DIELECTRIC DC CABLE
ISBN 978--658-9 Proceedings of the 6 th International Symposium on High Voltage Engineering Copyright c 9 SAIEE, Innes House, Johannesburg SPACE CHARGE ACCUMULATION UNDER THE EFFECTS OF TEMPERATURE GRADIENT
BC Hydro will submit its further report by September 16, 2008 as requested in the BCUC's letter of July 21, 2008.
BChydro Joanna Sofield Chief Regulatory Officer Phone: (604) 623-4046 Fax: (604) 623-4407 [email protected] August 5,2008 Ms. Erica M. Hamilton Commission Secretary British Columbia Utilities
Fault location on power cables. Fault location on power cables
Fault location on power cables Fault location on power cables Contents: 1. Introduction 2. Construction of power cables 3. Cable faults 01. Introduction Fault location on communication and power cables
E-Highway2050 WP3 workshop April 15 th, 2014 Brussels
E-Highway2050 WP3 workshop April 15 th, 2014 Brussels High voltage underground and subsea cable technology options for future transmission in Europe Ernesto Zaccone, Chairman Europacable High Voltage Systems
CTI TECHNICAL BULLETIN Number 9: A publication of the Cable Tray Institute
CTI TECHNICAL BULLETIN Number 9: A publication of the Cable Tray Institute Cable Tray Wiring Systems Have Many Cost Advantages Cost is usually a major consideration in the selection of a wiring system.
1.3.2 Method of construction and restoration of existing water service connections. This shall include:
1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting
Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components
Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Course No: E02-010 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education
On-Line Partial Discharge Testing. Skip Hicks Director - New Business Development
On-Line Partial Discharge Testing Skip Hicks Director - New Business Development What Is Partial Discharge? According the the International Electrotechnical Commission (IEC) International Standard 60270,
GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables
Engineering Department SEPTEMBER, 2007 GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables General Requirements This section applies to all public and private utilities,
STABILOY BRAND FEEDER SOLUTIONS ASSISTED LIVING FACILITIES
STABILOY BRAND FEEDER SOLUTIONS ASSISTED LIVING FACILITIES Introduction General Cable understands that assisted living facilities require complex building designs that must address a wide range of systems
How To Make A High Co 2 Gas Blend
ECONOMICAL OPTION FOR CO 2 / METHANE SEPARATION IN PRODUCED GAS CONTAINING A HIGH CO 2 FRACTION F. Patrick Ross, P.E. TPR Consulting 9907 Sagecourt Drive Houston, Texas 77089 (713) 870-9208 [email protected]
APPLICATION ORIENTED DESIGN OF CABLES
APPLICATION ORIENTED DESIGN OF CABLES Mrs. Rohini Bhattacharyya, Dubai cables Ltd.P. O. Box 11529,Dubai. [email protected] Mr. Nawaf Ahmad Al Mohaideb Dubai Cables Ltd. P. O. Box 11529, Dubai. [email protected]
CONSTRUCTION STANDARD ELECTRIC OPERATIONS ORGANIZATION
Page 1 of 11 ****This Standard Supercedes BECo CS2.13-2.3 & ComElectric OH Construction Manual, System Grounding Section, drawings CGND, GRDSUM, and C2**** 1.0 Bill of Materials GROUNDING AND BONDING POLE-MOUNTED
Forms of Energy. Freshman Seminar
Forms of Energy Freshman Seminar Energy Energy The ability & capacity to do work Energy can take many different forms Energy can be quantified Law of Conservation of energy In any change from one form
STABILOY BRAND FeeDeR SOLuTIONS
STABILOY BRAND Feeder Solutions DATA CENTER Introduction General Cable understands that data centers depend heavily on a steady, reliable and scalable source of power. That is why our STABILOY Brand aluminum
Cable Condition Monitoring to Improve Reliability
Cable Condition Monitoring to Improve Reliability by Hilary Marazzato, Ken Barber, Mark Jansen, and Graeme Barnewall Olex Australia Page 1-1 - Cable Condition Monitoring of Improve Reliability Hilary Marazzato,
STABILOY BRAND FeeDeR SOLuTIONS
STABILOY BRAND Feeder Solutions DATA CENTER Introduction General Cable understands that data centers depend heavily on a steady, reliable and scalable source of power. That is why our STABILOY Brand aluminum
University of Iowa Main Power Plant 2008 Flood Preparations, Event, & Recovery
University of Iowa Main Power Plant 2008 Flood Preparations, Event, & Recovery Yellow Alert for Mayflower Residence hall Peak at 31.5 feet Power Plant floods from steam tunnel and shuts down 1993 Flood
F05D Meeting on Damped AC Voltage Testing
October 28 th, 2008 from 03.30-5.30 pm in San Antonio, TX Agenda F05D Damped AC Voltage Testing 1 Agenda F05D Damped AC Voltage Testing Welcome: Introduction On-site testing voltages e.g. IEC 60060-3 High
Grounding of Electrical Systems NEW CODE: Grounding and Bonding
Grounding of Electrical Systems NEW CODE: Grounding and Bonding Presented By Scott Peele PE Grounding of Electrical Systems Outline Defining the Terms Why should I Ground? Types of Grounding Systems Separately
Considering UNDERGROUND. tampaelectric.com
Considering UNDERGROUND Electric Service? tampaelectric.com INTRODUCTION The majority of Tampa Electric s customers receive their electric service through overhead construction, which is the standard type
Cable Selection for Medium Voltage Capacitor Banks and Harmonic Filter Banks
Cable Selection for Medium Voltage Capacitor Banks and Harmonic Filter Banks Introduction This document presents the fundamental aspects of cable and conductor selection for connecting pad mounted shunt
Network Standard Advice No. 1420C 9/6/2011
Network Standard Advice No. 1420C 9/6/2011 TO: Customers, Service Providers and Ausgrid Staff. Advisory Note on Changes to the Use of 11kV Cable Types. Introduction This Network Standard Advice (NSA) provides
EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION INTERNATIONAL ELECTROTECHNICAL COMMISSION
EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION INTERNATIONAL ELECTROTECHNICAL COMMISSION EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION 1 EFFICIENT ELECTRICAL ENERGY TRANSMISSION
DDX 7000 & 8003. Digital Partial Discharge Detectors FEATURES APPLICATIONS
DDX 7000 & 8003 Digital Partial Discharge Detectors The HAEFELY HIPOTRONICS DDX Digital Partial Discharge Detector offers the high accuracy and flexibility of digital technology, plus the real-time display
Session Five: Modern XLPE Materials for Extruded Energy Cable Systems
Session Five: Modern XLPE Materials for Extruded Energy Cable Systems Abstract Hakan Lennartsson Senior Technical Service Manager, Borouge Hong Kong Pte. Ltd. The first medium voltage cables using extruded
Governor s Two-Storm Panel: Distribution Infrastructure Hardening Options and Recommendations
Governor s Two-Storm Panel: Distribution Infrastructure Hardening Options and Recommendations Dana Louth, CL&P VP - Infrastructure Hardening December 14, 2011 0 Topics for today s presentation Review of
Linking sustainable ideas to real-world results
Linking sustainable ideas to real-world results Prysmian Group, members of: Prysmian Group 700 Industrial Drive, Lexington, SC 29072 Tel: 1-800-845-8507 www.prysmianusa.com 137 Commerce Drive R.R. #3 Prescott,
Q: PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. A: Gerry Sheerin. Sheerin Technical, 25 Eastville Avenue, Toronto, Ontario Canada
DIRECT TESTIMONY OF GERRY SHEERIN, P. ENG ON BEHALF OF PIEDMONT ENVIRONMENTAL COUNCIL BEFORE THE STATE CORPORATION COMMISSION OF VIRGINIA CASE NOS. PUE-00-0001 AND PUE-00-000 1 1 1 1 1 1 1 1 1 Q: PLEASE
Condition Monitoring of equipment to improve quality of supply to customers by averting failures
Condition Monitoring of equipment to improve quality of supply to customers by averting failures Author & presenter: Patrick O Halloran BTECH Manager Technology Services at City Power Johannesburg Abstract
CATHODIC PROTECTION SYSTEM DESIGN
CATHODIC PROTECTION SYSTEM DESIGN Presented By DENIS L ROSSI P.E. CORROSION ENGINEER New England C P Inc. Corrosion Fundamentals What is corrosion? It is defined as the degradation or deterioration of
Underground Cable Temperature Monitoring in the Real World
Underground Cable Temperature Monitoring in the Real World Executive Summary Background Brain Storming Possible Causes to Duct Bank Over Heating Mitigating Duct Bank Overheating DTS Installation for Duct
Voltage Detection and Indication by Electric Field Measurement
Voltage Detection and Indication by Electric Field Measurement William McNulty, P.E. Technical Director Voltage Detection and Indication by Electric Field Measurement William McNulty, P.E. HD Electric
National Science Foundation Funds Request
University Corporation for Atmospheric Research National Science Foundation Funds Request 1. (NSF USE ONLY) 2. FACILITY NAME & LOCATION 3. PROJECT NAME 4. UCAR TRACKING NUM. NCAR Mesa Lab 15KV FEEDER REPLACEMENT
Troubleshooting accelerometer installations
Troubleshooting accelerometer installations Accelerometer based monitoring systems can be tested to verify proper installation and operation. Testing ensures data integrity and can identify most problems.
CHEMISTRY STANDARDS BASED RUBRIC ATOMIC STRUCTURE AND BONDING
CHEMISTRY STANDARDS BASED RUBRIC ATOMIC STRUCTURE AND BONDING Essential Standard: STUDENTS WILL UNDERSTAND THAT THE PROPERTIES OF MATTER AND THEIR INTERACTIONS ARE A CONSEQUENCE OF THE STRUCTURE OF MATTER,
WHAT IS INFRARED (IR) THERMOGRAPHY
WHAT IS INFRARED (IR) THERMOGRAPHY IR Thermography is the technique of producing pictures called from the invisible thermal radiation that objects emit. This is a non-contact means of identifying electrical
environment briefing02
PRODUCED BY THE SAFETY, HEALTH & ENVIRONMENT GROUP OF THE ENERGY NETWORKS ASSOCIATION - JULY 2006 environment briefing02 transporting electricity Overhead Lines or Underground Cables? Introduction The
Top Drive Service Loops. Conventional, Enhanced and Superior Solutions for Drilling Applications
Top Drive Service Loops Conventional, Enhanced and Superior Solutions for Drilling Applications Linking the future As the worldwide leader in the cable industry, Prysmian Group believes in the effective,
Hendrix Spacer Cable
Hendrix Spacer Cable What is Spacer Cable? Covered Conductor Withstands temporary branch contact Eliminates temporary faults Protects wildlife Less clearance issues Compact Configuration Multiple Circuits
THE USE OF AFTER-INSTALLATION COMMISSIONING TESTS TO ASSURE MV POWER CABLE SYSTEMS MEET MANUFACTURERS STANDARDS
THE USE OF AFTER-INSTALLATION COMMISSIONING TESTS TO ASSURE MV POWER CABLE SYSTEMS MEET MANUFACTURERS STANDARDS Stefaan JESPERS (1), Massimo VANOSSI (2), Marco GREEN (3), Benjamin Lanz (4) 1 Cegelec, Brussels,
Solar Pool Heating Proposal
Solar Pool Heating Proposal Swim More with SunCatcher page 1 SunCatcher pool solar heating panels Many thanks for the opportunity to submit our proposal to enhance your swimming pool investment. Our current
A Look at Accelerated Photostability Testing for Packaged Food and Drinks
A Look at Accelerated Photostability Testing for Packaged Food and Drinks By Dr. Oliver Rahäuser and Dr. Artur Schönlein Atlas Material Testing Technology GmbH Vogelsbergstr. 22, 63589 Linsengericht-Altenhaßlau,
ICM Project Underground Infrastructure and Cable
EB 0 00 Tab Schedule B ( pages) ICM Project Underground Infrastructure and Cable Handwell Replacement Segment (THESL) EB 0 00 Tab Schedule B I EXECUTIVE SUMMARY. Project Description 0 The handwell replacement
Development of a 500-kV DC XLPE Cable System
by Satoru Maruyama *, Noboru Ishii *, Michihiro Shimada *, Shinji Kojima * 2, Hideo Tanaka * 3, Mitsumasa Asano * 4, Tetsuya Yamanaka * 4, and Shin ichi Kawakami * 4 This paper describes development work
HYDROCARBON REMOVAL FROM AMINES DEMONSTRATED EXPERIENCE ABSTRACT
HYDROCARBON REMOVAL FROM AMINES DEMONSTRATED EXPERIENCE Technical Article Presented at Gas Processors Association Annual Convention San Antonio, Texas, USA, March 16, 2005 By Gary L. Lawson, PE (Presenter)
Power Voltage Transformers for Air Insulated Substations. THE PROVEN POWER.
Power Voltage Transformers for Air Insulated Substations THE PROVEN POWER. Introduction Trench Power Voltage Transformers (Power VTs) combine the attributes of an inductive voltage transformer with the
Chapter 3: Water and Life
Name Period Chapter 3: Water and Life Concept 3.1 Polar covalent bonds in water result in hydrogen bonding 1. Study the water molecules at the right. On the central molecule, label oxygen (O) and hydrogen
Mixing Sodium and Lead Battery Technologies in Telecom Applications
Mixing Sodium and Lead Battery Technologies in Telecom Applications Paul Smith Shanon Kolasienski Technical Marketing Manager Application Engineer GE Critical Power GE Energy Storage Plano, TX 75074 Schenectady,
Distributed Temperature Monitoring of Energy Transmission and Distribution Systems
1 m 40000m0 range 61850 IEC spatial resolution Distributed Temperature Monitoring of Energy Transmission and Distribution Systems Ensuring a Reliable Supply of Electrical Power for Today s World www.en-sure.pro
electrical services WWW.AU.SGS.COM/INDUSTRIAL
electrical services WWW.AU.SGS.COM/INDUSTRIAL OUR PROFILE SGS offers a full range of electrical engineering services covering the commissioning test of new plant as well as the maintenance and continual
RVH/BCH Data Centres Proposals for Surge Protection and Ventilation
REPORT Proposals for Surge Protection and Ventilation BELFAST HEALTH AND SOCIAL CARE TRUST ROYAL GROUP OF HOSPITALS GROSVENOR ROAD BELFAST BT12 6BA Rev. 01 6th September 2013 Table of Contents 1.0 Ventilation
NEW HIGH PERFORMANCE, ENVIRONMENTALLY FRIENDLY MV POWER CABLE INSULATIONS
P (Brown). P This NEW HIGH PERFORMANCE, ENVIRONMENTALLY FRIENDLY MV POWER CABLE INSULATIONS Mark EASTER, General Cable, (USA), [email protected] Elisenda CASALS, General Cable, Spain, [email protected]
Chemical Bonds. Chemical Bonds. The Nature of Molecules. Energy and Metabolism < < Covalent bonds form when atoms share 2 or more valence electrons.
The Nature of Molecules Chapter 2 Energy and Metabolism Chapter 6 Chemical Bonds Molecules are groups of atoms held together in a stable association. Compounds are molecules containing more than one type
World Leader in HV Testing Technology
World Leader in HV Testing Technology Cable Fault Locators w/tdr Oil/Fluid Dielectric Testers Very Low Frequency AC Technology W/TD & PD Diagnostics Portable AC Hipots ---------------------------------
Standard Operating Procedures for Flood Preparation and Response
Standard Operating Procedures for Flood Preparation and Response General Discussion Hurricanes, tropical storms and intense thunderstorms support a conclusion that more severe flooding conditions than
The optimum material solution for Low Voltage energy cables
The optimum material solution for Low Voltage energy cables About Borealis and Borouge Borealis is a leading provider of innovative solutions in the fields of polyolefins, base chemicals and fertilizers.
MiCAFIL. 1 RIP Technology. Bushings. Z. Zic 09/2003
MiCAFIL 1 RIP Technology Z. Zic 09/2003 )XQFWLRQRI+LJK9ROWDJH%XVKLQJ Uncontrolled (natural) electrical field Capacity-controlled electrical field %XVKLQJV0DLQ,QVXODWLRQ6\VWHPV 7\SH 0DLQ,QVXODWLRQ +RXVLQJFRYHU
All Wires and Cables Are Not Created Equal
All Wires and Cables Are Not Created Equal When comparing life cycle costs for wires and cables in wind systems, consider the specific applications, cost per failure and dielectric losses to determine
Cable Solutions for Servo and Variable Frequency Drives (VFD)
Cable Solutions for Servo and Variable Frequency Drives (VFD) Electric drive systems with continuous torque and speed control are widespread today. They allow an optimal adjustment of the drive with respect
Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage:
Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016 * Garage construction requires permits (electrical, building) * Permits must be applied for at the time. * Dial
DISTRIBUTION PIPING MATERIALS: BUILDING HYDRONIC SYSTEM MANAGEMENT. Jim Riley, Texas A&M University February 10, 2015
DISTRIBUTION PIPING MATERIALS: BUILDING HYDRONIC SYSTEM MANAGEMENT Jim Riley, Texas A&M University February 10, 2015 Piping at Texas A&M 2 History of Distribution Piping at Texas A&M Concrete reinforced
KALPANA INDUSTRIES LTD. TECHNICAL DATA SHEET
1 KALPANA INDUSTRIES LTD. TECHNICAL DATA SHEET KI XL - 03 / KI-SC 10 TWO COMPONENT AMBIENT CURABLE POLYETHYLENE COMPOUND FOR INSULATION OF LOW VOLTAGE POWER CABLE DESCRIPTION : KI polyethylene compound
THE STABILOY BRAND ADVANTAGE UNLOCKING THE SECRETS OF ALUMINUM A LOOK AT THE ADVANTAGES OF ALUMINUM ALLOY OVER COPPER
THE STABILOY BRAND ADVANTAGE UNLOCKING THE SECRETS OF ALUMINUM A LOOK AT THE ADVANTAGES OF ALUMINUM ALLOY OVER COPPER Ever Wonder Why There s No Copper in the Air? Since the early 1900s, aluminum and aluminum
Single Phase UPS Management, Maintenance, and Lifecycle
Single Phase UPS Management, Maintenance, and Lifecycle White Paper 210 Revision 0 by Justin Solis Executive summary How long will my battery last? and what is the best practice for maintaining my UPS?
Cable Consulting International
Cable Consulting International Brian Gregory BSc, CEng, MIEEE, FIEE Technical Director www.cableconsulting.net Alan Williams BSc, CEng, MIEE Senior Consultant 1 FEASIBILITY STUDY for 500 kv AC UNDERGROUND
Underground Commercial Electric Service
Underground Commercial Electric Service SCANA Corporation 2013 Revised: June 2013 Table of Contents SECTION PAGE I. Specification and Requirements 2 A. General B. Definition of Terms C. Company and Developer
CHAPTER 7: REMEDIATION TECHNOLOGIES FOR CONTAMINATED GROUNDWATER
CHAPTER 7: REMEDIATION TECHNOLOGIES FOR CONTAMINATED GROUNDWATER There are a number of technologies that are being use to remediate contaminated groundwater. The choice of a certain remediation technology
DISCUSSION OF CROSS-LINKED POLYETHYLENE INSULATED CABLES FOR UNDERGROUND PORTIONS OF THE MIDDLETOWN-NORWALK 345 kv PROJECTS.
DISCUSSION OF CROSS-LINKED POLYETHYLENE INSULATED CABLES FOR UNDERGROUND PORTIONS OF THE MIDDLETOWN-NORWALK 345 kv PROJECTS December 20, 2004 David W. Forrest Rachel I. Mosier 1. EXECUTIVE SUMMARY CL&P
MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING
Training Title MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING Training Duration 5 days Training Date MV, HV and EHV Switchgear Testing & Commissioning 5 20 24 Apr $3,750 Dubai, UAE In any of the 5 star
Underground Storage Tanks
Underground Storage Tanks An Informational and Guidance Document for the University Community. Please contact Yale Environmental Health and Safety for latest Regulatory Requirements. A typical UST installation
WIRE AND CABLE ENGINEERING GUIDE
Excerpt From Prysmian s WIRE AND CABLE ENGINEERING GUIDE Page 1 of 8 CABLE TESTING Testing represents an integral part in the life of a cable. A cable will be subjected to multiple tests in its lifetime
TECHNICAL SERVICE DEPARTMENT Technical Service Bulletin 1-800-432-8373. Anode Rods, Cathodic Protection and the Porcelain (glass) Lining
Corrosion can be defined as the destructive attack of a metal by an electrochemical reaction with its environment. Steel exposed to moisture and oxygen will rust and corrode. Corrosion is defined as the
METER REQUIREMENTS GENERAL REQUIREMENTS SECTION D
12 - ELECTRIC SERVICE HANDBOOK SECTION D METER REQUIREMENTS This chapter gives you information on Central Lincoln s metering requirements. It's divided into three sections: General requirements This section
Extend the Life of Existing Switchgear
Extend the Life of Existing Switchgear January 2011/1910DB1002 by Hal Theobald, Product Manager Schneider Electric USA, Inc. Make the most of your energy SM Summary Introduction... p 3 Maintenance Requirements...
ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F
ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F TABLE OF CONTENTS Appendix F - Electrical Engineering Design Criteria F.1 Introduction...F-1 F.2 Codes and Standards...F-1 F.3 Switchyard and Transformers...F-1
Insulation Resistance Testing of Low Voltage Cables in the Field
Insulation Resistance Testing of Low Voltage Cables in the Field Table of Contents 1. Background...3 1.1. Before Making Measurements...3 1.2. How to Apply the Temperature Correction Factor...4 1.2.1. Calculation...4
Transient and Lightning Protection for the Water Industries
Transient and Lightning Protection for the Water Industries Mike Nager Phoenix Contact [email protected] 5 th ISA Water/Wastewater Automatic Controls Division Symposium (WWAC) August 3-5, Orlando,
CHEMICAL DETERMINATION OF EVERYDAY HOUSEHOLD CHEMICALS
CHEMICAL DETERMINATION OF EVERYDAY HOUSEHOLD CHEMICALS Purpose: It is important for chemists to be able to determine the composition of unknown chemicals. This can often be done by way of chemical tests.
W-2. Stranding Comparison
Wire Knowledge W-1 W-2 Stranding Comparison Conductor Coatings/Coverings PURPOSE To facilitate stripping of components applied over the conductor To prevent compound fall-in Improve solderability Prevent
Environmental Benefits of Pervious Concrete
Environmental Benefits of Pervious Concrete Concrete Can Be Recycled When the time comes to demolish a concrete structure or pavement, the material need not be wasted. It can be crushed and used as aggregate,
EVALUATION OF ON-SITE DIELECTRIC RESPONSE METHODS FOR NON- DESTRUCTIVE TESTING OF WATER TREED MV XLPE CABLES
EVALUATION OF ON-SITE DIELECTRIC RESPONSE METHODS FOR NON- DESTRUCTIVE TESTING OF WATER TREED MV XLPE CABLES Sverre Hvidsten*, Peter Werelius**, Jørgen Christensen*** * SINTEF Energy Research (SEfAS),
REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING
REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING Revised October, 2013 TABLE OF CONTENTS 1.0 INTRODUCTION... 3 2.0 REQUIRED DRAWINGS... 3 2.1 Site Plan... 3