PJM Merchant Transmission Request. Queue #R75. Mitchell Shepler Hill 138 Kv Feasibility / System Impact Study

Size: px
Start display at page:

Download "PJM Merchant Transmission Request. Queue #R75. Mitchell Shepler Hill 138 Kv Feasibility / System Impact Study"

Transcription

1 PJM Merchant Transmission Request Queue #R75 Mitchell Shepler Hill 138 Kv Feasibility / System Impact Study v1a March 2007 PJM Interconnection All rights reserved.

2 Preface The intent of the feasibility study is to determine a plan, with ballpark cost and construction time estimates, to connect the subject merchant transmission upgrade to the PJM network at a location specified by the Interconnection Customer. As a requirement for interconnection, the Interconnection Customer may be responsible for the cost of constructing: Network Upgrades, which are facility additions, or upgrades to existing facilities, that are needed to maintain the reliability of the PJM system. All facilities required for interconnection of a merchant transmission upgrade must be designed to meet the technical specifications (on PJM web site) for the appropriate transmission owner. In some instances an interconnection customer may not be responsible for 100% of the identified network upgrade cost because other transmission network uses, e.g. another generation interconnection or merchant transmission upgrade, may also contribute to the need for the same network reinforcement. The possibility of sharing the reinforcement costs with other projects may be identified in the feasibility study, but the actual allocation will be deferred until the impact study is performed. The Feasibility Study estimates do not include the feasibility, cost, or time required to obtain property rights and permits for construction of the required facilities. The project developer is responsible for the right of way, real estate, and construction permit issues. For properties currently owned by Transmission Owners, the costs may be included in the study. PJM Interconnection All rights reserved.

3 General Reliant Energy Electric Solutions, LLC has proposed a project to upgrade the Mitchell Shepler Hill 138 kv circuit. The circuit is to be reconductored with miles of 954 ACSR. The proposed in-service date for this merchant transmission project is January 1, This Merchant Transmission Feasibility Study assesses the practicality and cost of incorporating the transmission facility into the PJM system. This study was limited to short-circuit analyses as well as load flow analyses of probable contingencies. PJM has provided preliminary estimates of the type, scope, cost, and lead time for construction of facilities. If the interconnection customer elects to pursue the System Impact Study, a more comprehensive analysis will be performed. Attachment Facilities The proposed reconductored 138 kv transmission line will terminate at existing facilities. The total project cost is estimated to be $ 3,000,000 in 2007 dollars. This estimate does not include tax gross up. This project will require 26 months to complete from the date of receipt of a signed Construction Service Agreement (CSA). Delays could be based on weather, equipment lead-time, and availability of outages to perform the work. NETWORK UPGRADES The study indicates no network upgrades are needed for the project. PJM Interconnection All rights reserved. 3

4 Network Impacts Project #R75 was evaluated for compliance with reliability criteria for summer peak conditions in Potential network impacts were as follows: Generator Deliverability No problems were identified Multiple Facility Contingency No problems were identified Contribution to Previously Identified Overloads No significant contributions to previously overloaded facilities were identified New System Reinforcements None identified. Contribution to Previously Identified System Reinforcements None identified. Short Circuit No overdutied breakers were found. IDRs at Elrama 138 kv 0 MW The incremental MW-injection is limited by the Mitchell-Uninon J. 138 kv line for the tower outage of 138 kv lines Mitchell-Charleroi and Mitchell-Dry Run. PJM Interconnection All rights reserved. 4

5 Elrama (DL) * Approximately 4 miles ACSR ACSR * AP Mitchell Union Jct PJM Queue P56 Dry Run AP Reconductor Mitchell Shepler Hill Jct. 138 kv circuit. Smithton Shepler Hill Jct 138 kv Belmont Charleroi AP SOURCE CAD FILE REVIEWED APPROVED DATE Allegheny Power P L A N MITCHELL SHEPLER HILL JCT. RECONDUCTOR 138 kv LINE FOR RELIANT ENERGY ELECTRIC SOLUTIONS MERCHANT TRANSMISSION CHARLEROI SERVICE CENTER DRAWN CHKD SCALE AUTHORIZATION NS REV Figure 1 PJM Interconnection All rights reserved. 5

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055 Generation Interconnection Feasibility Study Report-Web Version For PJM Generation Interconnection Request Queue Position Z1-055 South Bend Generation Project March 2014 PJM Interconnection 2014. All rights

More information

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114. Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position X1-114 Sandyston January 2012 Preface The intent of the System Impact Study is to determine

More information

Generator Interconnection and Deliverability Study Methodology Technical Paper

Generator Interconnection and Deliverability Study Methodology Technical Paper Generator Interconnection and Deliverability Study Methodology Technical Paper July 2, 2013 Generator Interconnection and Deliverability Study Methodology Table of Contents Introduction... 1 Section One:

More information

Generation and Transmission Interconnection Process

Generation and Transmission Interconnection Process PJM Manual 14A Generation and Transmission Interconnection Process Revision: 18 Effective Date: January 28, 2016 Prepared by Planning Division Generation Interconnection Department PJM 2016 Table of Contents

More information

Q140 Cluster Addendum

Q140 Cluster Addendum Cluster Addendum 1. INTRODUCTION This Interconnection Customer (IC), submitted a Small Generator Interconnection Request (IR) to Arizona Public Service Company (APS) for their proposed project, located

More information

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD HOLLAND CLIFF HEWITT ROAD 230 KV TRANSMISSION LINE PROJECT ELECTRIC ALTERNATIVE EVALUATION STUDY BLACK & VEATCH CORPORATION B&V Project 146026(G)

More information

Emera Maine Proposed Potential Transmission Projects. Line Identification Line 75 - KR Sub. Estimated Cost $201,464 $0 $3,200,000

Emera Maine Proposed Potential Transmission Projects. Line Identification Line 75 - KR Sub. Estimated Cost $201,464 $0 $3,200,000 L75 & BW3 Rebuild ROW Phase I Keene Rd. Expansion for Oakfield Wind KR Transformer Addition Line Identification Line 75 - KR Sub Location Bangor Chester Chester Estimated Cost $201,464 $0 $3,200,000 Voltage

More information

Control Number : 37897. Item Number : 9. Addendum StartPage: 0

Control Number : 37897. Item Number : 9. Addendum StartPage: 0 Control Number : 37897 Item Number : 9 Addendum StartPage: 0 PROJECT NO. 37897 PUC PROCEEDING RELATING TO PUBLIC UTILITy/^OI^IMISSIO^ RESOURCE AND RESERVE ^CL_^ ADEQUACY AND SHORTAGE OF TEXAS PRICING COMMENTS

More information

Section 4: Integrating Public Policy Drivers

Section 4: Integrating Public Policy Drivers Public Policy Drivers Section : Integrating Public Policy Drivers PJM DE DC IL IN KY MD MI NJ NC OH PA TN VA WV Section.0: The Role of Public Policy in the RTEP Process Figure.1: Public Policy Drivers

More information

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003 F R C C FRCC Standards Handbook FRCC Automatic Underfrequency Load Shedding Program Revision Date: July 2003 FRCC Underfrequency Load Shedding Program Modification and Approval Process Requests to modify

More information

Updated SYSTEM IMPACT STUDY OF NEW ENGLAND AREA

Updated SYSTEM IMPACT STUDY OF NEW ENGLAND AREA CROSS SOUND CABLE PROJECT 330MW HVdc INTERCONNECTION BETWEEN NEW HAVEN, CONNECTICUT AND SHOREHAM, NY Updated SYSTEM IMPACT STUDY OF NEW ENGLAND AREA Subordinate Status Removal and Amendment of Approved

More information

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering Title 20 PUBLIC SERVICE COMMISSION Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES Chapter 02 Engineering Authority: Public Utility Companies Article, 2-121, 5-101 and 5-303, Annotated Code of Maryland.

More information

COMMONWEALTH OF VIRGINIA LRK,'S UNCE AT RICHMOND, SEPTEMBER 7,2012 TRUL CE.. P 112 : 51 APPLICATION OF FINAL ORDER

COMMONWEALTH OF VIRGINIA LRK,'S UNCE AT RICHMOND, SEPTEMBER 7,2012 TRUL CE.. P 112 : 51 APPLICATION OF FINAL ORDER COMMONWEALTH OF VIRGINIA STATE CORPORATION COMMISSION LRK,'S UNCE AT RICHMOND, SEPTEMBER 7,2012 TRUL CE.. P 112 : 51 APPLICATION OF VIRGINIA ELECTRIC AND POWER COMPANY For approval and certification of

More information

TRANSMISSION ALTERNATIVES CONSIDERED

TRANSMISSION ALTERNATIVES CONSIDERED EB-00-0 Tab Page of TRANSMISSION ALTERNATIVES CONSIDERED In determining the proposed facilities, Hydro One and the West GTA LDCs investigated six options to address the two needs identified in this Application

More information

16 West Coast Regional Plan

16 West Coast Regional Plan 16 West Coast Regional Plan 16.1 Regional overview 16.2 West Coast transmission system 16.3 West Coast demand 16.4 West Coast generation 16.5 West Coast significant maintenance work 16.6 Future West Coast

More information

BPA Network Open Season 2013 Cluster Study

BPA Network Open Season 2013 Cluster Study BPA Network Open Season 2013 Cluster Study Customer Meeting January 15, 2014 Topics for Discussion Cluster Study TSR Overview Cluster Study Areas Incremental TTC Needed Cluster Study Areas Preliminary

More information

Houston Region Import Capacity Project

Houston Region Import Capacity Project Houston Region Import Capacity Project July 25, 2013 Prepared by: CenterPoint Energy Transmission Planning Executive Summary 3 1. Introduction 5 2. Methodology and Study Assumptions 7 2.1 Case Description

More information

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment March 20, 2009 Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Table of Contents:

More information

FINAL. Alternative Evaluation. for the. Proposed Burlington-Wray 230-kilovolt Transmission Project

FINAL. Alternative Evaluation. for the. Proposed Burlington-Wray 230-kilovolt Transmission Project FINAL Alternative Evaluation for the Proposed Burlington-Wray 230-kilovolt Transmission Project Prepared by Tri-State Generation and Transmission Association, Inc. 1100 W. 116th Avenue Westminster, Colorado

More information

TDI's NYC Merchant CHPE Transmission Project with POI at Astoria (NYISO Queue #305) Deliverability Analysis

TDI's NYC Merchant CHPE Transmission Project with POI at Astoria (NYISO Queue #305) Deliverability Analysis R103-11 TDI's NYC Merchant CHPE Transmission Project with POI at Astoria (NYISO Queue #305) Deliverability Analysis Prepared for Transmission Developers, Inc. Submitted by: Larry Eng, Staff Consultant

More information

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 SHE Transmission 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 Summary This paper presents SHE Transmission s views and approach on the impact of transmission losses on the transmission

More information

Deliverability Testing

Deliverability Testing Deliverability Testing Henry Chao Vice President System & Resource Planning New York Independent System Operator New York State Reliability Council Executive Committee Meeting September 12, 2008 Definition

More information

FRCC Coordination Procedure. Title: FRCC Reliability Coordinator Contingency Analysis Monitoring Criteria

FRCC Coordination Procedure. Title: FRCC Reliability Coordinator Contingency Analysis Monitoring Criteria A. Purpose: The FRCC Reliability Coordinator (RC) Contingency Analysis (CA) application is essential to maintaining the reliability of the FRCC Bulk Electric System. The application has the capability

More information

Section 4: Scheduling Philosophy & Tools

Section 4: Scheduling Philosophy & Tools Welcome to the Scheduling Philosophy & Tools section of the PJM Manual for Scheduling Operations. In this section you will find the following information: A description of the PJM OI s scheduling philosophy

More information

Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives. Final Report

Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives. Final Report Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives (Required per CPUC Decision No. C10-1328) Final Report (Submitted with Public Service s 2011 ERP) Executive Summary The objective

More information

Millennium Pipeline Company, LLC Response to New York State Energy Highway RFI

Millennium Pipeline Company, LLC Response to New York State Energy Highway RFI Millennium Pipeline Company, LLC Response to New York State Energy Highway RFI www.millenniumpipeline.com One Blue Hill Plaza, 7th Floor Post Office Box 1565 Pearl River, N Y 10965 845.620.1300 Voice 845.620.1320

More information

Rocky Mountain Power Transmission Five Year Study Findings Meeting

Rocky Mountain Power Transmission Five Year Study Findings Meeting Rocky Mountain Power Transmission Five Year Study Findings Meeting Study Areas for 2009 Goshen Idaho Study Area encompasses parts of Bingham, Bonneville, Butte, Clark, Fremont, Jefferson, Lemhi, Madison

More information

Memorandum. This memorandum requires Board action. Executive Summary

Memorandum. This memorandum requires Board action. Executive Summary California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: July 8, 2014 Re: Decision on the Delaney-Colorado

More information

Potomac Electric Power Company 1900 Pennsylvania Ave., N.W. Washington, D.C. 20068

Potomac Electric Power Company 1900 Pennsylvania Ave., N.W. Washington, D.C. 20068 Section 11 PEPCO'S EARLY PLANNING FOR A PHASED COAL GASIFICATION COMBINED-CYCLE PLANT Steven Scherer, P.E. Potomac Electric Power Company 1900 Pennsylvania Ave., N.W. Washington, D.C. 20068 PEPCO'S EARLY

More information

AGREEMENT FOR PRELIMINARY ENGINEERING DESIGN MISO PROJECT J233

AGREEMENT FOR PRELIMINARY ENGINEERING DESIGN MISO PROJECT J233 SA 2507 INTERSTATE POWER AND LIGHT COMPANY E&P AGREEMENT VERSION 1.0.0 EFFECTIVE 3/1/2013 AGREEMENT FOR PRELIMINARY ENGINEERING DESIGN MISO PROJECT J233 Agreement for Preliminary Engineering Design - MISO

More information

PJM Interconnection LLC Regional Transmission Organization (RTO)

PJM Interconnection LLC Regional Transmission Organization (RTO) PJM Interconnection LLC Regional Transmission Organization (RTO) ComEd Generator Interconnection Meeting October 2015 William Patzin PJM Infrastructure Coordination October 2015 PJM 2013 Nine Major North

More information

SOUTH CAROLINA. Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard)

SOUTH CAROLINA. Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard) SOUTH CAROLINA Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard) 1. Overview: This Standard contains the requirements, in addition

More information

Cross-Tie Transmission Line. Ravikanth Varanasi Principal Transmission Planner

Cross-Tie Transmission Line. Ravikanth Varanasi Principal Transmission Planner Cross-Tie Transmission Line Ravikanth Varanasi Principal Transmission Planner Overview ~213 mile 500-kV transmission line between PacifiCorp s proposed Clover 500 kv substation with NV Energy s Robinson

More information

AAPG 2011 Annual Convention & Exhibition April 10, 2011

AAPG 2011 Annual Convention & Exhibition April 10, 2011 Generator Transmission Grid Interconnection Guidelines AAPG 2011 Annual Convention & Exhibition April 10, 2011 Hala Ballouz, B.Sc., M.Sc. TAMU, P.E. President, Electric Power Engineers, Inc. Partner &

More information

IESO Supply Deliverability Guidelines

IESO Supply Deliverability Guidelines PUBLIC IMO_GDL_0021 IESO Supply Deliverability Guidelines Issue 3.0 This document is to be used to evaluate long-term system adequacy and connection assessments Public Disclaimer The posting of documents

More information

The Economic Impact of Dominion Capital Expenditure Projects

The Economic Impact of Dominion Capital Expenditure Projects The Economic Impact of Dominion Capital Expenditure Projects Prepared for Dominion Virginia Power October 22, 2015 1309 E Cary Street, Richmond, VA 23219 1025 Huron Road East, Cleveland, OH 44115 chmuraecon.com

More information

Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach

Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach READ AND DELETE For best results with this template, use PowerPoint 2003 10 November 2015 Background and Importance of ICA Definition:

More information

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION FEASIBILITY STUDY FOR PROPOSED XXXXXXXX GENERATION ON THE SIERRA BLANCA-FARMER 69 KV LINE

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION FEASIBILITY STUDY FOR PROPOSED XXXXXXXX GENERATION ON THE SIERRA BLANCA-FARMER 69 KV LINE EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION FEASIBILITY STUDY FOR PROPOSED XXXXXXXX GENERATION ON THE SIERRA BLANCA-FARMER 69 KV LINE El Paso Electric Company System Planning Department April

More information

Pennsylvania Summer Reliability

Pennsylvania Summer Reliability A. Reliability Enhancement Programs In 2015, Pennsylvania Power Company s ( Penn Power or Company ) reliability plan incorporates projects and programs to enhance overall reliability. The plan is structured

More information

SUMMARY OF CAPITAL EXPENDITURES

SUMMARY OF CAPITAL EXPENDITURES Filed: May, EB--00 Page of SUMMARY OF CAPITAL EXPENDITURES.0 SUMMARY OF CAPITAL BUDGET The proposed capital expenditures result from a rigorous business planning and work prioritization process that reflects

More information

Load Dispatcher (Class Code 5223) Task List

Load Dispatcher (Class Code 5223) Task List A. Load Dispatching, General Load Dispatcher (Class Code 5223) Task List 1. Prior to work shift speaks to Load Dispatcher(s), reviews hardcopy and computer logs, and looks at the dispatcher's diagram board

More information

PUBLIC SERVICE COMMISSION OF MARYLAND TEN-YEAR PLAN (2012 2021) OF ELECTRIC COMPANIES IN MARYLAND

PUBLIC SERVICE COMMISSION OF MARYLAND TEN-YEAR PLAN (2012 2021) OF ELECTRIC COMPANIES IN MARYLAND PUBLIC SERVICE COMMISSION OF MARYLAND TEN-YEAR PLAN (2012 2021) OF ELECTRIC COMPANIES IN MARYLAND Prepared for the Maryland Department of Natural Resources In compliance with Section 7-201 of the Maryland

More information

Tehachapi Renewable Transmission Project (TRTP)

Tehachapi Renewable Transmission Project (TRTP) SM Tehachapi Renewable Transmission Project (TRTP) February 2009 Why We Are Here Today Provide background on SCE s commitment to renewable energy Discuss the operational and economic importance of the

More information

HYDRO ONE LIMITED REPORTS FOURTH QUARTER 2015 RESULTS

HYDRO ONE LIMITED REPORTS FOURTH QUARTER 2015 RESULTS HYDRO ONE LIMITED REPORTS FOURTH QUARTER 2015 RESULTS Quarterly results reflect a number of timing, unusual and unseasonal weather related items while core operations remain strong; Board declares first

More information

Microgrid Building block for Smart Cities

Microgrid Building block for Smart Cities Microgrid Building block for Smart Cities Shay Bahramirad, Ph.D. Manager of Smart Grid & Technology December 2014 COMED OVERVIEW 1 The service territory covers 11,400 mi 2 in Northern Illinois Serving

More information

Item 8: Houston Import RPG Project

Item 8: Houston Import RPG Project : Houston Import RPG Project Jeff Billo Manager, Transmission Planning Board of Directors Meeting April 8, 2014 Study Overview ERCOT has determined that there will be a need for additional import capacity

More information

BOUNDLESS ENERGY, LLC S RESPONSE TO THE REQUEST FOR INFORMATION BY THE NEW YORK ENERGY HIGHWAY

BOUNDLESS ENERGY, LLC S RESPONSE TO THE REQUEST FOR INFORMATION BY THE NEW YORK ENERGY HIGHWAY Background BOUNDLESS ENERGY, LLC S RESPONSE TO THE REQUEST FOR INFORMATION BY THE NEW YORK ENERGY HIGHWAY On April 11, 2012, the New York Energy Highway Task Force (Task Force) issued a request for information

More information

Transmission Related Station Power Use at Substations

Transmission Related Station Power Use at Substations Transmission Related Station Power Use at Substations BUSINESS PRACTICE This Business Practice identifies the cost responsibility for energy consumption at substations by American Transmission Company

More information

DUKE ENERGY INDIANA. Preparation for Summer 2007. Presentation to Indiana Utility Regulatory Commission

DUKE ENERGY INDIANA. Preparation for Summer 2007. Presentation to Indiana Utility Regulatory Commission DUKE ENERGY INDIANA Preparation for Summer 2007 Presentation to Indiana Utility Regulatory Commission May 30, 2007 Overview of Presentation 2006 Duke Energy Indiana accomplishments/challenges Summer 2007

More information

NTTG Study Plan for the 2014-2015 Public Policy Consideration Scenario

NTTG Study Plan for the 2014-2015 Public Policy Consideration Scenario NTTG Study Plan for the 2014-2015 Public Policy Consideration Scenario Table of Contents NTTG Study Plan for the 2014-2015 Public Policy Consideration Scenario Table of Contents... 2 1. Executive Summary...

More information

APPENDIX 7 TO LGIP INTERIM INTERCONNECTION SYSTEM IMPACT STUDY AGREEMENT

APPENDIX 7 TO LGIP INTERIM INTERCONNECTION SYSTEM IMPACT STUDY AGREEMENT APPENDIX 7 TO LGIP INTERIM INTERCONNECTION SYSTEM IMPACT STUDY AGREEMENT THIS AGREEMENT is made and entered into this day of, 20 by and between, a organized and existing under the laws of the State of,

More information

PJM LMP Market Overview

PJM LMP Market Overview PJM LMP Market Overview Andrew Ott Senior Vice President, Markets June 10, 2010 PJM as Part of the Eastern Interconnection 6,038 substations KEY STATISTICS PJM member companies 600+ millions of people

More information

Economic Impact Analysis of PSE&G s Capital Expenditure Program

Economic Impact Analysis of PSE&G s Capital Expenditure Program Economic Impact Analysis of PSE&G s Capital Expenditure Program Submitted to: PSE&G June 2014 Joseph J. Seneca, Michael L. Lahr, Will Irving Contents Introduction... 1 Project Expenditure Data... 2 Methodology...

More information

2015 Highlights. Operating Committee January 21, 2016

2015 Highlights. Operating Committee January 21, 2016 2015 Highlights Operating Committee January 21, 2016 Health & Safety Overview Alignment with improvements to incident reporting process and software (e.g. Catsweb) Improvement of safety culture and accountability

More information

Electric Power 2005 in Chicago. Dr. Aiham Alsammarae Minister Of Electricity Iraq

Electric Power 2005 in Chicago. Dr. Aiham Alsammarae Minister Of Electricity Iraq Electric Power 2005 in Chicago Dr. Aiham Alsammarae Minister Of Electricity Iraq IRAQ s ELECTRICAL SYSTEM (STATUS & FUTURE PLAN) April. 2005 IRAQ s ELECTRICAL SYSTEM A QUICK HISTORICAL REVIEW Electricity

More information

FORM EIA-411 INSTRUCTIONS COORDINATED BULK POWER SUPPLY AND DEMAND PROGRAM REPORT

FORM EIA-411 INSTRUCTIONS COORDINATED BULK POWER SUPPLY AND DEMAND PROGRAM REPORT PURPOSE REQUIRED RESPONDENTS RESPONSE DUE DATE METHODS OF FILING RESPONSE Form EIA-411 collects information about regional electricity supply and demand projections for a ten-year advance period and information

More information

131 FERC 61,157 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER GRANTING WAIVER. (Issued May 25, 2010)

131 FERC 61,157 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER GRANTING WAIVER. (Issued May 25, 2010) 131 FERC 61,157 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Marc Spitzer, Philip D. Moeller, and John R. Norris. Hudson Transmission Partners,

More information

Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System

Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System Prepared By: Transmission Planning Unit Baltimore Gas & Electric Company Table of Contents 1. INTRODUCTION

More information

Generation Interconnection Facilities Study Report. For. PJM Generation Interconnection Request Queue Position R11. South River

Generation Interconnection Facilities Study Report. For. PJM Generation Interconnection Request Queue Position R11. South River Generation Interconnection Facilities Study Report For PJM Generation Interconnection Request Queue Position R11 South River May 2012 Transmission Owner Facilities Study Summary Description of Project

More information

345 kv Brazos Valley Connection Project FAQs

345 kv Brazos Valley Connection Project FAQs 345 kv Brazos Valley Connection Project FAQs Overview 1. Who is CenterPoint Energy Houston Electric, LLC? CenterPoint Energy Houston Electric, LLC (CenterPoint Energy) is an electric utility that maintains

More information

Kyrgyzstan: Power Generation & Transmission

Kyrgyzstan: Power Generation & Transmission Kyrgyzstan: Power Generation & Transmission October, 2010 Author: Artyom Zozulinsky, Business & Commercial Assistant, US Embassy Bishkek Contents SUMMARY... 2 POWER SECTOR OVERVIEW... 2 Infrastructure...

More information

ASSET MANAGEMENT STRATEGY Approved

ASSET MANAGEMENT STRATEGY Approved Approved Document TP.TG 01.01 30/10/2014 Approved Transpower New Zealand Limited 2014. All rights reserved. Page 1 of 25 C O P Y R I G H T 2014 T R A N S P O W E R N E W Z E A L A N D L I M I T E D. A

More information

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION'^^ j E DIRECT TESTIMONY RAJESH GUPTA PROJECT MANAGER, ENTERGY SERVICES, INC.

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION'^^ j E DIRECT TESTIMONY RAJESH GUPTA PROJECT MANAGER, ENTERGY SERVICES, INC. BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION'^^ j E s : D IN THE MATTER OF THE APPLICATION OF ENTERGY ARKANSAS, INC. FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED TO CONSTRUCT AND OPERATE

More information

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date

More information

Cyber Infrastructure for the Smart Grid

Cyber Infrastructure for the Smart Grid Cyber Infrastructure for the Smart Grid Dr. Anurag K. Srivastava, Dr. Carl Hauser, and Dr. Dave Bakken Smart Grid Use Cases: Part 2 SGIC Xcel Energy SG Xcel Energy A public Service company of Colorado

More information

Preliminary Feasibility Assessment For. The Rio Tinto Alcan to BCH Transfer Limit of 460 MW. With 50% Series Compensation on Both KMO KIT lines

Preliminary Feasibility Assessment For. The Rio Tinto Alcan to BCH Transfer Limit of 460 MW. With 50% Series Compensation on Both KMO KIT lines Preliminary Feasibility Assessment For The Rio Tinto Alcan to BCH Transfer Limit of 460 MW With 50% Series Compensation on Both KMO KIT lines Report : ASP2010-T001 July 2010 Asset Strategy & Planning,

More information

Comments of Louisiana Energy Users Group and Texas Industrial Energy Consumers. MISO South Market Congestion Planning Study. September 18, 2015

Comments of Louisiana Energy Users Group and Texas Industrial Energy Consumers. MISO South Market Congestion Planning Study. September 18, 2015 Comments of Louisiana Energy Users Group and Texas Industrial Energy Consumers On MISO South Market Congestion Planning Study September 18, 2015 In response to the MISO Staff s September 11, 2015 request

More information

Sudbury to Hudson Transmission Reliability Project

Sudbury to Hudson Transmission Reliability Project Hudson Light & Power Sudbury to Hudson Transmission Reliability Project Sudbury, Massachusetts Board of Selectmen Presentation February 2, 2016 Revised on Page 12 to show Project Open House dates in Sudbury

More information

ITP Evaluation Process Plan Cross-Tie Transmission Line

ITP Evaluation Process Plan Cross-Tie Transmission Line ITP Evaluation Process Plan Cross-Tie Transmission Line The goal of the coordinated Interregional Transmission Project (ITP) evaluation process is to achieve consistent planning assumptions and technical

More information

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2 2.0

More information

Financing New High Voltage Transmission Lines in Nepal Using HTLS Conductors Surendra Rajbhandari, Nepal Electricity Authority Zhang Lei, ADB South

Financing New High Voltage Transmission Lines in Nepal Using HTLS Conductors Surendra Rajbhandari, Nepal Electricity Authority Zhang Lei, ADB South Financing New High Voltage Transmission Lines in Nepal Using HTLS Conductors Surendra Rajbhandari, Nepal Electricity Authority Zhang Lei, ADB South Asia Energy Division Asia Clean Energy Forum June 2015

More information

Electrical System Studies

Electrical System Studies Electrical System Studies INTRODUCTION s experienced professionals provide electrical systems planning and design services to improve the safety and the reliability of electric power systems. The planning,

More information

Chapter 7 - Appendix A

Chapter 7 - Appendix A Chapter 7 - Appendix A Transmission and Distribution Supplemental Information Table 7A.1 MTEP Transmission Projects in Missouri 1 Project Approved Project Title Project Description Category Estimated Cost

More information

SPP Notification to Construct

SPP Notification to Construct SPP-NTC-200365 SPP Notification to Construct January 12, 2016 Mr. John Fulton Southwestern Public Service Company P.O. Box 1261 Amarillo, TX 79105 RE: Notification to Construct for Transmission Service

More information

E N G I N E E R I N G

E N G I N E E R I N G Purpose If the customer s proposed project proceeds to Gate 1 of the Integrated Customer Solutions (ICS) process (see the ICS Process and Proposal Submission Guide), the customer must prepare a Load Displacement

More information

2014 Solicitation DGS Request for Proposals & ADGS Request for Information Conference. July 1, 2014

2014 Solicitation DGS Request for Proposals & ADGS Request for Information Conference. July 1, 2014 2014 Solicitation DGS Request for Proposals & ADGS Request for Information Conference July 1, 2014 Overview of the Conference Introduction Conference Agenda DGS and ADGS Overview RFP/RFI Schedule The DGS

More information

Texas Demand Response Programs Cirro Energy Services an NRG Energy Company

Texas Demand Response Programs Cirro Energy Services an NRG Energy Company Texas Demand Response Programs Cirro Energy Services an NRG Energy Company April 04, 2014 Fazil Shaikh, Sales Manager Melissa Karner, Energy Consultant Outline Introduction ERCOT Resource Adequacy and

More information

Integrating Renewable Electricity on the Grid. A Report by the APS Panel on Public Affairs

Integrating Renewable Electricity on the Grid. A Report by the APS Panel on Public Affairs Integrating Renewable Electricity on the Grid A Report by the APS Panel on Public Affairs 2 Integrating Renewable Electricity on the Grid Executive Summary The United States has ample renewable energy

More information

PJM Overview of Markets. Georgian Delegation PUCO Office April 11, 2013

PJM Overview of Markets. Georgian Delegation PUCO Office April 11, 2013 PJM Overview of Markets Georgian Delegation PUCO Office April 11, 2013 1 Agenda Introduction Energy Markets Locational Marginal Pricing - LMP Two Settlement - Day Ahead / Real time Ancillary Services Capacity

More information

Energy Storage Market Overview MADRI 3/3/2015 John Fernandes Policy & Market Development Manager

Energy Storage Market Overview MADRI 3/3/2015 John Fernandes Policy & Market Development Manager Energy Storage Market Overview MADRI 3/3/2015 John Fernandes Policy & Market Development Manager Storage Technologies 2 Over 100 Energy Storage Technologies Background to the Market Flywheels Thermal ES

More information

Updated: November 30, 2007 Date: 30-Nov-07 SUMMARY OF DISCOUNTED CASH FLOW CALCULATIONS EB-2007-0050 Project # Exhibit B Tab 4 Schedule 4 page 1 of 5

Updated: November 30, 2007 Date: 30-Nov-07 SUMMARY OF DISCOUNTED CASH FLOW CALCULATIONS EB-2007-0050 Project # Exhibit B Tab 4 Schedule 4 page 1 of 5 Date: 30-Nov-07 SUMMARY OF DISCOUNTED CASH FLOW CALCULATIONS Project # page 1 of 5 Facility Name: Bruce to Milton Reinforcement Project Scope: 500kV Line and related station modifications In-Service Date

More information

Treasure Valley Electric Plan - Community Advisory Committee

Treasure Valley Electric Plan - Community Advisory Committee Treasure Valley Electric Plan - Community Advisory Committee What is a transmission line and why are they necessary? A transmission line is used to conduct electricity between two points. Without high

More information

Calculating the Business Case for Demand Response

Calculating the Business Case for Demand Response Calculating the Business Case for Demand Response Whether for regional transmission systems, integrated utilities, or load serving retailers, there are many direct and indirect benefits financial, regulatory,

More information

TRANSMISSION BUSINESS PERFORMANCE

TRANSMISSION BUSINESS PERFORMANCE Filed: 0-0- Tx 0-0 Rates Tab Schedule Page of TRANSMISSION BUSINESS PERFORMANCE.0 INTRODUCTION 0 Hydro One is focused on the strategic goals and performance targets in the area of safety, customer satisfaction,

More information

Fixed Income Investor Meeting

Fixed Income Investor Meeting Fixed Income Investor Meeting James F. Pearson Senior Vice President and Chief Financial Officer NYSE, New York, NY May 20, 2015 Forward-Looking Statement Forward-Looking Statements: This Presentation

More information

CITY AND COUNTY OF SAN FRANCISCO

CITY AND COUNTY OF SAN FRANCISCO CITY AND COUNTY OF SAN FRANCISCO Mayor Gavin Newsom City Attorney Dennis Herrera Supervisor Michela Alioto-Pier Supervisor David Chiu Supervisor Sophenia Maxwell General Manager Edward Harrington May 8,

More information

Convergence of Wholesale And Retail Markets: The Texas Experience

Convergence of Wholesale And Retail Markets: The Texas Experience Convergence of Wholesale And Retail Markets: The Texas Experience 1 COMMISSIONER KENNETH W. ANDERSON, JR. PUBLIC UTILITY COMMISSION OF TEXAS PRESENTATION FOR HARVARD ELECTRICITY POLICY GROUP JUNE 12, 2014

More information

Enabling End Users to see Real Time Price Signals and Manage their Own Electricity Costs via the PJM Demand Side Response Program Delaware DNREC

Enabling End Users to see Real Time Price Signals and Manage their Own Electricity Costs via the PJM Demand Side Response Program Delaware DNREC Enabling End Users to see Real Time Price Signals and Manage their Own Electricity Costs via the PJM Demand Side Response Program Delaware DNREC Joe Polidoro, Sr. Engineer PJM Interconnection, LLC 610-666-4693

More information

Operating Security Standards

Operating Security Standards Version 1.1 Prishtina December 2009 TABLE OF CONTENTS 1 Introduction... 1 2 Definitions... 1 2.1 General...1 2.1.2 Kosovo Transmission System...1 2.1.3 Circuit...2 2.1.4 The N-1 Criterion...2 2.1.5 Normal

More information

Schedule 19 POWER PURCHASES FROM COGENERATION AND SMALL POWER PRODUCTION QUALIFYING FACILITIES

Schedule 19 POWER PURCHASES FROM COGENERATION AND SMALL POWER PRODUCTION QUALIFYING FACILITIES I. APPLICABILITY & AVAILABILITY This Schedule is applicable to any Cogenerator or Small Power Producer (Qualifying Facility), as defined in the Public Utility Regulatory Policies Act of 1978 (PURPA), which

More information

How To Operate The Williston Uvls

How To Operate The Williston Uvls WND Winter Operating Guide 2012/2013 1 WND Operating Study Using EQ-890-2012WIN- FINAL.sav developed through the 890 process Got load updates from MDU, Central Power, UM G&T Made several topology updates

More information

PJM Renewable Integration Study

PJM Renewable Integration Study GE Energy Consulting PJM Renewable Integration Study Executive Summary Report Revision 03 Prepared for: PJM Interconnection, LLC. Prepared by: General Electric International, Inc. February 28, 2014 Legal

More information

TERMS AND CONDITIONS

TERMS AND CONDITIONS Virginia Electric and Power Company TERMS AND CONDITIONS XXIV. GENERATOR INTERCONNECTION STANDARD Electric generator interconnection service includes only the ability to interconnect an electric generator

More information

Applicability and Eligibility

Applicability and Eligibility Application for Resource Adequacy Deliverability Status for a Distributed Generation Resource Interconnected or Seeking Interconnection to the Distribution Facilities of an Investor-Owned Utility Participating

More information

New York Independent System Operator (NYISO)

New York Independent System Operator (NYISO) New York Independent System Operator (NYISO) 2010 ISO/RTO Metrics Report 196 Section 5 NYISO Performance Metrics and Other Information The New York Independent System Operator ( NYISO ) is a not-for-profit

More information

PJM Overview and Wholesale Power Markets. John Gdowik PJM Member Relations

PJM Overview and Wholesale Power Markets. John Gdowik PJM Member Relations PJM Overview and Wholesale Power Markets John Gdowik PJM Member Relations PJM s Role Ensures the reliability of the high-voltage electric power system Coordinates and directs the operation of the region

More information

D.3 South Minneapolis Electric Distribution Delivery System Long-Term Study

D.3 South Minneapolis Electric Distribution Delivery System Long-Term Study D.3 South Minneapolis Electric Distribution Delivery System Long-Term Study Xcel Energy April 2009 Hiawatha Project SOUTH MINNEAPOLIS ELECTRIC DISTRIBUTION DELIVERY SYSTEM LONG-TERM STUDY Scott Zima Distribution

More information

National Regulatory Conference May 20, 2015. The Role of Natural Gas in Electric Generation

National Regulatory Conference May 20, 2015. The Role of Natural Gas in Electric Generation National Regulatory Conference May 20, 2015 The Role of Natural Gas in Electric Generation Chairman Edward S. Finley, Jr. North Carolina Utilities Commission www.ncuc.net North Carolina fully regulates

More information

Jason B. Keyes Keyes & Fox, LLP Kansas Solar Round Table Topeka, Kansas March 3, 2009

Jason B. Keyes Keyes & Fox, LLP Kansas Solar Round Table Topeka, Kansas March 3, 2009 Net Metering and Interconnection of Solar Energy Facilities Jason B. Keyes Keyes & Fox, LLP Kansas Solar Round Table Topeka, Kansas March 3, 2009 What IREC Does Participate in state utility commission

More information

Superconducting and Solid-State Electronic Fault Current Limiter Technologies The shift from demonstration projects to Business-as-Usual solutions

Superconducting and Solid-State Electronic Fault Current Limiter Technologies The shift from demonstration projects to Business-as-Usual solutions Superconducting and Solid-State Electronic Fault Current Limiter Technologies The shift from demonstration projects to Business-as-Usual solutions Dr. Detlev Kirsten & Herbert Piereder Solid State SSFCL

More information