Generation Interconnection Facilities Study Report. For. PJM Generation Interconnection Request Queue Position R11. South River

Size: px
Start display at page:

Download "Generation Interconnection Facilities Study Report. For. PJM Generation Interconnection Request Queue Position R11. South River"

Transcription

1 Generation Interconnection Facilities Study Report For PJM Generation Interconnection Request Queue Position R11 South River May 2012

2 Transmission Owner Facilities Study Summary Description of Project Gateway Energy Center, LLC, (developer) has proposed the addition of 440 MW of natural gas generation to be injected near the present South River 230 kv Substation. The 440 MW will be a capacity resource. The plant will interconnect with Jersey Central Power & Light (JCP&L), a FirstEnergy Company; at a new three-breaker ring bus configured switching station. Additionally, a new six-breaker ring bus substation will be installed for the South River R11 project at a location where the 230 kv line is looped into the South River Generation complex. Based on the project scope defined in this study, the projected in-service date for this facility is June This study assumes that engineering and siting work begins on December 1, 2011 to meet the facility in-service date. A Project Kickoff meeting must occur by November 15, 2011 to begin engineering on the required date. Amendments to the System Impact Study data or System Impact Study Results None. Interconnection Customer s Submitted Milestone Schedule 6/1/2013 Project Commercial Operation Scope of Customer s Work The developer will construct facilities including the natural gas generation facility, the generator step-up (GSU) transformer, high side circuit breakers and the connection line to the new 230 kv three-breaker ring bus. The interconnection point will be located at the point where the customer-owned facilities connect to the FE-owned disconnect switch, as shown in the attached one-line diagram, shown in Attachment B. Fully rated fault interrupting circuit breakers owned by the developer are required on the high side of the GSU s, between the position on the ring bus and the generating station. The direct connection facilities include line terminal equipment on FirstEnergy s side of the point of interconnection. This typically includes a dead-end structure that is considered radial equipment from the terminal to the point of interconnection. The remainder of the ring bus switching-station is a network upgrade because of system through-flow. Description of Facilities Included in the Facilities Study The new South River Junction six breaker ring bus will interconnect the Red Oak, Raritan River, Parlin, Atlantic, and South River Substations. It is proposed that the R11 project be connected via a new 230 kv three breaker ring bus. It is to be constructed between the South River Substation and the South River Junction Substation. The loop for the R11 Substation is estimated to extend approximately 0.1 miles. The developer is responsible for constructing all of the facilities on its side of the point of interconnection, which will be located at the point where the customer-owned facilities connect to the FE-owned disconnect switch at the R11 Interconnection Substation, as shown in the attached one-line diagram, shown in Attachment B. PJM Interconnection All rights reserved. 1 PJMDOCS-# v3

3 Required reinforcements to be constructed by FirstEnergy: Direct Connection Network Upgrades PJM Network Upgrade N1666: New loop structure in 230 kv line to connect the transmission line to the new interconnection substation located adjacent to the transmission line right-of-way. Approximately 200 feet of 230 kv transmission line extending from the South River Junction South River 230 kv Line to the generation plant interconnection substation. PJM Network Upgrade N1256: Design and construction of a new 230 kv three breaker ring bus for interconnection to the customer supplied R11 generation substation along with fiber communications. Non Direct Connection Network Upgrade PJM Network Upgrade N1667: New loop structures in 230 kv lines to connect the transmission lines to the South River Junction 6 position substation located adjacent to the transmission line right-of-way. Approximately 200 feet per line of 230 kv transmission line extending from the T1034, G1047, P1030, and K1025 Lines to the new 230 kv six breaker ring bus substation. PJM Network Upgrade N1257: Design and construction of a new 230 kv six breaker ring bus called South River Junction that interconnects the T1034, G1047, P1030, and K1025 transmission lines along with fiber communications. PJM Network Upgrade N1266: South River - Replace 230kV Line Relaying on T and P lines. PJM Network Upgrade N1267: Red Oak - Replace T1034 and G1047 RFL 9300 Relays with SEL-311L s. PJM Network Upgrade N1268: Raritan River - Replace T1034 and G1047 RFL 9300 Relays with SEL-311L s. PJM Network Upgrade N1668: Parlin - Replace primary and backup relaying on 230 kv line G1047 to the South River Junction substation. PJM Network Upgrade N1669: Atlantic - Replace 230 kv line P1030 relaying and separate primary and backup line relaying. PJM Network Upgrade N0907: Raritan River - Replace drop loop conductors on G kV Transmission Line with bundled 1590 kcmil ACSR cables. Raritan River Replace 6 existing breakers with 230kV, 3000A, 63kA circuit breakers. o PJM Network Upgrade N1036: Replace breaker G1047E o PJM Network Upgrade N1037: Replace breaker G1047F o PJM Network Upgrade N1038: Replace breaker T1034E PJM Interconnection All rights reserved. 2 PJMDOCS-# v3

4 o PJM Network Upgrade N1039: Replace breaker T1034F o PJM Network Upgrade N1046: Replace breaker I1023E o PJM Network Upgrade N1047: Replace breaker I1023F Red Oak Replace 4 existing breakers with o PJM Network Upgrade N1042: Replace breaker MT1 o PJM Network Upgrade N1043: Replace breaker MT2 o PJM Network Upgrade N1044: Replace breaker MT3 o PJM Network Upgrade N1045: Replace breaker MT4 The estimated costs above and below are in 2011 dollars and do not include taxes or effects from Contribution In Aid of Construction. Specific detailed protection requirements are provided as Attachment A. PJM Interconnection All rights reserved. 3 PJMDOCS-# v3

5 Total Costs of Transmission Owner Facilities included in Facilities Study Direct Connection Network Upgrades PJM Network Upgrade Number N1666 $ 368,600 PJM Network Upgrade Number N1256 $ 6,011,600 Non-Direct Connection Network Upgrades PJM Network Upgrade Number N1667 $ 1,398,800 PJM Network Upgrade Number N1257 $ 10,733,900 PJM Network Upgrade Number N1266 $ 648,800 PJM Network Upgrade Number N1267 $ 565,600 PJM Network Upgrade Number N1268 $ 335,500 PJM Network Upgrade Number N1668 $ 273,100 PJM Network Upgrade Number N1669 $ 695,200 PJM Network Upgrade Number N0907 $ 137,400 PJM Network Upgrade Numbers N1036, N1037, N1038, N1039, N1046, N1047 $ 2,193,800 PJM Network Upgrade Numbers N1042, N1043, N1044, N1045 $ 500,000 PJM Network Upgrade Number N1265 $ 132,000 Total $ 23,994,301 Summary of Milestone Schedules for Completion of Work Included in Facilities Study A proposed 19-month construction schedule is estimated to complete construction and the associated activities listed below from the date of a fully executed Interconnection Construction Service Agreement. This schedule assumes that all issues covered by the Environmental, Real Estate, and Permitting section of this document are resolved. A more detailed construction schedule with milestones will be developed for the Interconnection Construction Service Agreement. This study assumes that engineering and siting work begins on December 1, 2011 to meet the facility in-service date. A Project Kickoff meeting must occur by November 15, 2011 to begin engineering on the required date. Construction should not begin until after all applicable permits have been obtained. Activity Start Month End Month Preliminary Engineering 1 1 Permits & Real Estate 7 14 Detailed Engineering 2 17 Equipment Procurement Delivery 3 18 Below Grade Construction Above Grade Construction Testing & Commissioning PJM Interconnection All rights reserved. 4 PJMDOCS-# v3

6 Transmission Owner Facilities Study Results Transmission Lines New/Upgraded 1. R11 Interconnect Substation Transmission Line Loop PJM Network Upgrade N1666 The existing 230 kv transmission line will be sectionalized at the new JCP&L Interconnection Substation at a site to be selected by the developer with agreement from JCP&L. This study assumes that the new substation will be located adjacent to the JCP&L 230 kv line right-of-way (see Attachment E) and the substation dead-end structures will each be within one span of the line. The estimated costs shown in this study are typical for this type of design. The actual costs will be determined by the final substation and loop locations. The estimated cost for this work is $ 368,600 and could be completed as noted in the Summary of Proposed Schedule for Completion of Work on page 4 of this Facility Study Report. 2. South River Junction Transmission Line Loop PJM Network Upgrade N1667 The existing 230 kv transmission line will be sectionalized at the new JCP&L Interconnection Substation at a site to be selected by the developer with agreement from JCP&L. This study assumes that the new substation will be located adjacent to the JCP&L 230 kv line right-of-way (see Attachment E) and the substation dead-end structures will each be within one span of the line. The estimated costs shown in this study are typical for this type of design. The actual costs will be determined by the final substation and loop locations. The estimated cost for this work is $ 1,398,800 and could be completed as noted in the Summary of Proposed Schedule for Completion of Work on page 4 of this Facility Study Report. Substation/Switchyard Facilities New/Upgraded 1. JCP&L Interconnection Substation PJM Network Upgrade N1256 JCP&L will design, furnish and install the following for the new three-breaker 230 kv ring bus substation including but not limited to the following: Three 230 kv, 3000 ampere, 63 ka interrupting power circuit breakers Six 230 kv, 3000 ampere, three-pole, manually group operated disconnect switches Nine surge arresters for application on a 230 kv system Nine 230 kv capacitor voltage transformers One 230 kv power VT for station service One 230kV, 3000A, MOAB disconnect switch 230 kv bus and conductor with associated structures and foundations. One 230 kv, 3000 ampere, three-pole, motor operated disconnect switch PJM Interconnection All rights reserved. 5 PJMDOCS-# v3

7 Five pre-wired relay panels Prefabricated building with battery and charger and all JCP&L relaying and controls per the Protection Requirements provided as Attachment A. SCADA RTU Fiber communications equipment Substation fencing, ground grid and stoning. Gateway Energy Center, LLC will be responsible for providing the rough graded site for the interconnect substation and providing/maintaining the access road to the interconnect substation. The estimated cost for this work is $6,011,600 and could be completed as noted in the Summary of Proposed Schedule for Completion of Work on page 4 of this Facility Study Report. 2. JCP&L Six Breaker Substation (South River Junction) PJM Network Upgrade N1257 JCP&L will design, furnish and install the following for the new six-breaker 230 kv ring bus substation including but not limited to the following: Six 230 kv, 4000 ampere, 63 ka interrupting power circuit breakers Twelve 230 kv, 4000 ampere, three-pole, manually group operated disconnect switches Eighteen surge arresters for application on a 230 kv system Eighteen 230 kv capacitor voltage transformers One 230 kv power VT for station service 230 kv bus and conductor with associated structures and foundations. One 230 kv 3000 ampere Wave Trap Eight pre-wired relay panels Prefabricated building with battery and charger and all JCP&L relaying and controls per the Protection Requirements provided as Attachment A. SCADA RTU Fiber communications equipment Substation fencing, ground grid and stoning. Gateway Energy Center, LLC will be responsible for providing the rough graded site for the interconnect substation and providing/maintaining the access road to the interconnect substation. The estimated cost for this work is $10,733,900 and could be completed as noted in the Summary of Proposed Schedule for Completion of Work on page 4 of this Facility Study Report. 3. Raritan River Substation PJM Network Upgrade N1036, N1037, N1038, N1039, N1046, N1047 Replace six breakers I1023E, I1023F, T1034E, T1034F G1047E and G1047F at the Raritan River Substation with 230 kv 3000A, 63 ka circuit breakers. PJM Interconnection All rights reserved. 6 PJMDOCS-# v3

8 The estimated cost for this work is $ 2,193,800 and could be completed as noted in the Summary of Proposed Schedule for Completion of Work on page 4 of this Facility Study Report. 4. Red Oak Substation PJM Network Upgrade N1042, N1043, N1044, N1045 The estimated cost for this work is $ 500, South River Substation PJM Network Upgrade N1266 Replacement of the primary and backup relaying on 230kV T1034 and P1030 lines to support PJM R11 project. The estimated cost for this work is $648,800 and could be completed as noted in the Summary of Proposed Schedule for Completion of Work on page 4 of this Facility Study Report. 6. Parlin Substation PJM Network Upgrade N1668 Replacement of the primary and backup relaying on 230 kv line G1047 to the South River Junction substation. The estimated cost for this work is $273,100 and could be completed as noted in the Summary of Proposed Schedule for Completion of Work on page 4 of this Facility Study Report. 7. Raritan River Substation PJM Network Upgrade N0907 Replacement of the drop loop conductor on the G kV Transmission Line with bundled 1590 cable. The estimated cost for this work is $137,400 and could be completed as noted in the Summary of Proposed Schedule for Completion of Work on page 4 of this Facility Study Report. 8. Atlantic Substation PJM Network Upgrade N1669 Replacement of the 230 kv line P1030 relaying and separate primary and backup line relaying. The estimated cost for this work is $695,200 and could be completed as noted in the Summary of Proposed Schedule for Completion of Work on page 4 of this Facility Study Report. 9. Red Oak Substation PJM Network Upgrade N1267 Replacement of the T1034 and G1047 RFL 9300 Relays with SEL-311L s. The estimated cost for this work is $565,600 and could be completed as noted in the Summary of Proposed Schedule for Completion of Work on page 4 of this Facility Study Report. PJM Interconnection All rights reserved. 7 PJMDOCS-# v3

9 10. Raritan River Substation PJM Network Upgrade N1268 Replacement of the T1034 and G1047 RFL 9300 Relays with SEL-311L s. The estimated cost for this work is $335,500 and could be completed as noted in the Summary of Proposed Schedule for Completion of Work on page 4 of this Facility Study Report. 11. Interconnecting Customer Generation Substation PJM Network Upgrade n1265 Engineering Oversight and Commissioning Support of the Interconnection Customer s generation substation including support of protective relay installation. The estimated cost for this work is $132,000 and could be completed as noted in the Summary of Proposed Schedule for Completion of Work on page 4 of this Facility Study Report. The estimated costs above are in 2011 dollars and do not include taxes or effects from Contribution In Aid of Construction. Metering & Communications Gateway Energy Center, LLC, shall install, own, operate, test and maintain the necessary revenue metering equipment. The FirstEnergy Revenue Metering Requirements may be found in the FirstEnergy Requirements for Transmission Connected Facilities document located at the following links: es.html. Gateway Energy Center, LLC shall also provide JCP&L with dial-up communication to the revenue meter. Assuming JCP&L is installing the Interconnection Substation, JCP&L will provide the telecommunication circuits for the SCADA RTU and the telephone in the JCP&L Interconnection Substation. Assuming JCP&L is installing the Interconnection Substation, JCP&L will also provide the telecommunication circuits for the SCADA RTU and the telephone in the JCP&L South River Junction Substation. Gateway Energy Center, LLC will be responsible for designing, furnishing and installing a SCADA RTU in their generation substation and obtaining the telecommunication circuits from the RTU to the JCP&L Data Center. These requirements are in addition to any metering required by PJM. Fiber Optic Communication Channels Fiber optic communication is required between the South River, the South River Junction, the Red Oak, the Raritan River, and the R11 Interconnection Substations to be used for line protection, direct transfer trip and other communication as detailed in Attachment A. Existing PJM Interconnection All rights reserved. 8 PJMDOCS-# v3

10 fiber optic cable will be utilized for this communication and extended to the two new substations. FirstEnergy will own and maintain the cable. Environmental, Real Estate and Permitting Issues The following are possible environmental, real estate and permitting issues: The JCP&L Substations will involve NJ BPU notification, local board approvals, and stormwater control plans with the NJ DEP and/or county conservation district. Included in these procedures is the applicable threatened and endangered species evaluation. These activities are the responsibility of the developer to the extent that they are providing the rough graded site to FE. The construction permit for work following the rough grading will be obtained by FE. Environmental, Real Estate and NJ BPU notification durations can vary, some up to 12 months and must be completed prior to the start of construction which can add to the critical path schedule. It is assumed there will be no significant social impacts, ecological impacts, property owner opposition, or elected official opposition to the project. If the developer owns the project property, in fee title, JCP&L will require a fee property transfer for the substation sites which may require subdivision approval, together with permanent access rights to and from the sub, as well as a permanent easement for the transmission line tap to the sub. The subdivision process is to be completed by and at the expense of the developer. If the developer leases the project property, then the developer will be required to obtain fee property from the underlying fee property owner, on behalf of JCP&L, for the substation sites, together with permanent access rights to and from the sub, as well as a permanent easement for the transmission line tap to the sub. All property rights must be surveyed and metes and bounds descriptions prepared for incorporation into JCP&L s document forms, for transfer of title. The line work siting estimate is a preliminary conceptual estimate. On the ground evaluations of the routes as well as a detailed review of local zoning issues is required for a more definitive estimate. It is assumed that all existing right-of-way are valid and that there is no need for any new right-of-ways. The underlying assumptions for the line siting estimate is that no appeal filings of local zoning issues to the New Jersey Board of Public Utilities will be required for any aspect of the project. Wetland issues and erosion and sedimentation control issues are not included in this estimate. PJM Interconnection All rights reserved. 9 PJMDOCS-# v3

11 It is assumed that the developer will provide the rough graded sites/property and access roads to a public road, for the South River Junction Substation as well as the R11 Interconnection Substation. 7. Summary of Results of Study The facilities work is described in the above project details and on the attachments. An estimated cost summary in 2011 dollars and excluding taxes or effects from Contribution In Aid of Construction is: PJM Interconnection All rights reserved. 10 PJMDOCS-# v3

12 Engineering Material & Equipment Construction & Testing Total Network Upgrade N1666: R11 Interconnect Substation Transmission $ 29,500 $ 183,500 $ 155,600 $ 368,600 Line Loop Network Upgrade N1256: JCP&L Three Breaker Ring Bus $ 663,600 $ 2,681,200 $ 2,666,800 $ 6,011,600 Interconnecting Substation Network Upgrade N1667: South River Junction Transmission Line $ 50,000 $ 728,900 $ 619,900 $ 1,398,800 Loop Network Upgrade N1257: South River Junction Six Breaker Ring $ 1,019,200 $ 5,434,000 $ 4,280,700 $ 10,733,900 Bus Substation Network Upgrade N1266: Relay upgrade at South River $ 148,500 $ 153,200 $ 347,100 $ 648,800 Network Upgrade N1267: Relay upgrade at Red Oak $ 103,700 $ 123,000 $ 338,900 $ 565,600 Network Upgrade N1268: Relay upgrade at Raritan River $ 51,600 $ 78,800 $ 205,100 $ 335,500 Network Upgrade N1668: Relay upgrade at Parlin Substation $ 40,200 $ 35,900 $ 197,000 $ 273,100 Network Upgrade N1669: Relay upgrade at Atlantic Substation $ 147,100 $ 212,800 $ 335,300 $ 695,200 Network Upgrade N0907: Raritan River G1047 Drop Loop $ 24,100 $ 20,700 $ 92,600 $ 137,400 Conductor Replacement Network Upgrade N1036, N1037, N1038, N1039, N1046, N1047: $ 316,200 $ 1,128,200 $ 749,400 $ 2,193,800 Replace 6 Breakers: Raritan River Network Upgrade N1042, N1043, N1044, N1045: Replace 4 $ 72,067 $ 257,134 $ 170,800 $ 500,000 Breakers: Red Oak PJM Network Upgrade n1265: Engineering Oversight and $ 41,500 $ 0 $ 90,500 $ 132,000 Commissioning $ 2,707,267 $ 11,037,334 $ 10,249,700 $ 23,994,301 The estimated costs above are in 2011 dollars and do not include taxes or effects from Contribution In Aid of Construction. PJM Interconnection All rights reserved. 11 PJMDOCS-# v3

13 Assumptions/Qualifiers The accomplishment of the work on the FE system to support the estimated costs and proposed schedule is dependent on the following: Obtaining the necessary transmission line outages. Transmission line outages are typically not granted from June to September. No equipment delivery, environmental or regulatory delays. The FE/JCP&L schedule provides for 8 months of permitting activity. The completion date could be affected if the permitting would extend any longer. No permitting or real estate delays. If the project is contested or rejected at the local level, significant legal and siting costs may be required to appeal to the BPU - possibly exceeding $1,000, which is not included in the cost estimates in this report. No extreme weather. No force majeure. The three breaker ring bus and six breaker ring bus estimates are based upon typical estimates because detailed site and interconnection information was not received from the developer. In the event, Gateway Energy Center, LLC selects the Option To Build, they must utilize an approved FE A/E & Construction Contractor. FE will then act in an oversight capacity reviewing all design information & site construction (estimated cost for engineering support to be provided by FE). Information Required for Interconnection Service Agreement The following table summarizes the total estimated costs according to FERC criteria. The estimated costs are in 2011 dollars. The taxes are a CIAC (Contribution in Aid of Construction) Federal Income Tax Gross Up charge. This tax may or may not be charged based on whether or not this project meets the eligibility requirements of IRS Notice Direct Charges Labor $ 10,519,867 Direct Charges Material $ 7,623,962 Indirect Charges Labor $ 2,669,010 Indirect Charges Material $ 3,151,462 Total without taxes $ 23,994,302 PJM Interconnection All rights reserved. 12 PJMDOCS-# v3

14 Attachment A R11 Detailed Protection Requirements JCP&L Protection Short Circuit Analysis Short Circuit Values Fault values for the South River Junction Substation location are: Three phase = 39,044 A Single line to ground = 42,052 A Z1 = j % Z0 = j % Impedances are given on a 100 MVA and 230 kv bases. Fault values are from the current PJM Short Circuit Case for the R11 generation project. The faults provided are bolted, symmetrical values for normal system conditions. Future increases in fault currents are possible and it is the customer s responsibility to upgrade their equipment and/or protective equipment coordination when necessary. General Connection Requirements All proposed generation interconnection points and load-serving delivery points must comply with the technical requirements detailed in the FirstEnergy Requirements for Transmission Connected Facilities document. Relay Communications Channels Two independent fiber optic communications channels (<100m each) are required between the FirstEnergy owned R11 Generation Three-Breaker substation and the R11 Generation substation to be used for relay communications. Two independent fiber optic communications channels (~600m each) are required between the FirstEnergy owned R11 Interconnection Three-Breaker substation and the FirstEnergy owned South River Junction (R11) interconnecting substation to be used for relay communications. Two independent fiber optic communications channels (~0.65 miles each) are required between the existing FirstEnergy owned South River substation and the FirstEnergy owned South River Junction (R11) interconnecting substation to be used for relay communications. Two independent fiber optic communications channels (~0.65 miles each) are required between the existing FirstEnergy owned South River substation and the FirstEnergy owned R11 Interconnection Three-Breaker substation to be used for relay communications. PJM Interconnection All rights reserved. 13 PJMDOCS-# v3

15 Generator 230 kv Substation Connection Requirements Protection Requirements The attached one-lines (Attachments C and D) provide an overall view of the FE owned interconnection substations and the R11 Generation substation and South River Junction substation. The 230 kv intertie breaker(s) shall have two sets (6 total) of 3000:5 A MR, C800 CTs with a thermal factor of at least 2.0 available on the plant side of the breaker(s) to be used for protection of the intertie line. Additional CTs required for the protection of plant equipment to be determined by developer. The 230 kv breakers shall have two independent trip coils. A 230 kv three phase potential source (CVT or equivalent) is required for line exit relaying. Faults within any 230 kv piece of equipment must be detected by two independent high-speed zones of protection. Bus protection shall consist of primary and backup current differential or a high-impedance voltage differential scheme. Transformer protection shall consist of a primary current differential scheme and a backup current scheme, preferably differential, utilizing separate current transformers and an independent transformer neutral overcurrent relay. Backup protection shall be completely independent from the primary protection; including separate current transformers, potential transformer windings (where applicable) and DC control circuits. A separate tripping path energizing separate breaker trip coils is required for primary and backup relaying. A breaker failure relay (such as SEL-501 or SEL-352) shall be utilized on all 230 kv circuit breakers. Any protective relay trip of a 230 kv breaker shall initiate the failure to trip scheme for that breaker. The re-trip feature for the BFT scheme shall be utilized and trip the 230 kv circuit breaker. The 230 kv breaker failure scheme shall operate a hand reset lockout relay which shall trip and block close all electrically adjacent circuit breakers. Tripping of the breakers at the R11 Interconnection Three Breaker Substation shall be accomplished via the fiber optic cables and the tie line protective relays (DTT). All primary relaying is required to be connected CTs on the inner bushing looking through the breaker in to the protected equipment. All backup relaying is required to be connected CTs on the outer bushing looking through the breaker in to the protected equipment. The protection should trip the associated breakers, initiate breaker failure-to-trip schemes and reclosing schemes where applicable. The relaying system shall have a reliable source of DC power independent from the AC system or immune to AC system disturbance or loss (for example - DC battery and charger) to assure proper operation of the protection scheme. All relays, relay schemes, and relay settings that include 230 kv voltages or currents, or trip any 230 kv circuit breakers shall require the review and approval of FirstEnergy. FirstEnergy will complete detailed relay coordination studies to identify off-site relay setting changes required due to this generation interconnection. This may result in additional individual PJM Interconnection All rights reserved. 14 PJMDOCS-# v3

16 relay replacements being required. These relay replacements will be done at the cost of the developer. The customer is solely responsible for protecting its own equipment in such a manner that electrical faults or other disturbances on the FE system do not damage its equipment. Metering Requirements A revenue metering installation is required for this installation. Requirements are outlined in FirstEnergy s Requirements for Transmission Connected Facilities document. Operational metering is also required for this generation connection. These requirements are also outlined in FirstEnergy s Requirements for Transmission Connected Facilities document. These requirements are in addition to any metering required by PJM. FE System Modifications R11 Interconnection Substation The R11 Interconnection 230 kv Substation shall be a three breaker ring bus. The 230 kv breakers shall be rated 3000 amperes continuous, 63kA interrupting; and shall have two sets of 3000:5 A MR, C800 CTs per bushing with a thermal factor of at least 2.0. A 230 kv three phase potential device (CVT or equivalent) is required for all three positions around the ring bus. The potential device shall have dual secondary windings with a 2000/1200:1 ratio. The protection for the 230 kv (R11G) line to the R11 Generation Substation shall consist of: SEL-387L with fiber optic interface (Primary Line) SEL-311L with fiber optic interface (Backup Line) SATEC meter In addition the customer owned R11 Generation Substation shall consist of: SEL-387L with fiber optic interface (Primary Line) SEL-311L with fiber optic interface (Backup Line) The protection for the 230 kv (T1034-3) line to South River shall consist of: SEL-387L with fiber optic interface (Primary Line) SEL-311L with fiber optic interface (Backup Line) SATEC meter PJM Interconnection All rights reserved. 15 PJMDOCS-# v3

17 The protection for the 230 kv (T1034-2) line to South River Junction shall consist of: (2) SEL-387L with fiber optic interface (Primary and Backup Line) SATEC meter Reclosing initiated by either the T or T line relaying SEL-279H-2 (reclose the T1034-2/T breaker) Each breaker shall utilize a SEL-352 relay and associated lockout relay for breaker failure-to-trip protection. As per PRC-002-RFC-01, a digital fault recorder shall be installed with a minimum of 32 analog and 64 digital channels. The DFR shall be connected to a GPS time clock. All relays to be connected to a SEL-2020 for remote relay communication. South River Junction Substation The South River Junction 230 kv Substation shall be a six breaker ring bus. The 230 kv breakers shall be rated 4000 amperes continuous, 63kA interrupting; and shall have two sets of 3000:5 A MR, C800 CTs per bushing with a thermal factor of at least 2.0. A 230 kv three phase potential device (CVT or equivalent) is required for each line exit position. The potential devices shall have dual secondary windings with a 2000/1200:1 ratio. The protection for the 230 kv (T1034) line to Red Oak-Raritan River shall consist of: SEL-311L with fiber optic interface (Primary Line) SEL-311C with fiber optic interface (Backup Line) SATEC meter The protection for the 230 kv (G1047-2) line to Red Oak-Raritan River shall consist of: SEL-311L with fiber optic interface (Primary Line) SEL-311C with fiber optic interface (Backup Line) SATEC meter The protection for the 230 kv (G1047-3) line to Parlin shall consist of: SEL-387L with fiber optic interface (Primary Line) SEL-311L with fiber optic interface (Backup Line) SATEC meter The protection for the 230 kv (P1030) line to Atlantic shall consist of: PJM Interconnection All rights reserved. 16 PJMDOCS-# v3

18 SEL-321 (Primary Line) SEL-311C (Backup Line) SATEC meter RFL-9785 Carrier RFL-9780 Dual Channel Transfer Trip Transmitter RFL-9780 Dual Channel Transfer Trip Receiver Wave trap and line tuning unit is also required The protection for the 230 kv (P1030-2) line to South River shall consist of: SEL-387L with fiber optic interface (Primary Line) SEL-311L with fiber optic interface (Backup Line) SATEC meter The protection for the 230 kv (T1034-2) line to the R11 Interconnection Substation shall consist of: (2) SEL-387L with fiber optic interface (Primary and Backup Line) SATEC meter Reclosing initiated by either the T1034 or G line relaying SEL-279H-2 (reclose the T1034/G breaker) Reclosing initiated by either the T or P line relaying SEL-279H-2 (reclose the T1034-2/P breaker) Reclosing initiated by either the P1030 or G line relaying SEL-279H-2 (reclose the P1030/G breaker) Each breaker shall utilize a SEL-352 relay and associated lockout relay for breaker failure-to-trip protection. As per PRC-002-RFC-01, a digital fault recorder shall be installed with a minimum of 48 analog and 96 digital channels. The DFR shall be connected to a GPS time clock. All relays to be connected to a SEL-2020 for remote relay communication. PJM Interconnection All rights reserved. 17 PJMDOCS-# v3

19 South River Substation (Revisions) The protection for the 230 kv (T1034-3) line to the R11 Interconnection Substation shall consist of: Replace the RFL-9300 relay with a SEL-387L relay with fiber optic interface (Primary Line) Replace the SEL-311C relay with a SEL-311L relay with fiber optic interface (Backup Line) The protection for the 230 kv (P1030-2) line to South River Junction Substation shall consist of: Remove the existing P1030 relays, consisting of: MDAR, KD-10, IRQ-8, TD-5, SGR-51, carrier, transfer trip, SBC relays for breakers PA and PB, and the CVE relays for breakers PA and PB. Add: SEL-387L with fiber optic interface (Primary Line) SEL-311L with fiber optic interface (Backup Line) SATEC meter SEL-279H (reclosing of PB breaker only initiated by P1030 line relaying) (2) SEL-352 (PA & PB Stuck Breaker Protection and Breaker Close Supervision) All relays to be connected to SEL-2020, which is to be connected to a GPS time clock. Parlin Substation (Revisions) The protection for the 230 kv (G1047-3) line to the South River Junction Substation shall consist of: Replace the RFL-9300 relay with a SEL-387L relay with fiber optic interface (Primary Line) Replace the SEL-311C relay with a SEL-311L relay with fiber optic interface (Backup Line) All relays to be connected to SEL-2020, which is to be connected to a GPS time clock. Atlantic Substation (Revisions) The protection for the 230 kv (P1030) line to the South River Junction Substation shall consist of: Remove the existing P1030 relays, consisting of: (3) KD-4, KD-41, KA, KRD, IRD, TD, SGR, carrier, transfer trip and the breaker failure relays for breakers HP & SH. PJM Interconnection All rights reserved. 18 PJMDOCS-# v3

20 Add: SEL-321 (Primary Line) SEL-311C (Backup Line) SEL-279H SATEC meter RFL-9785 Carrier RFL-9780 Dual Channel Transfer Trip Transmitter RFL-9780 Dual Channel Transfer Trip Receiver (2) SEL-352 (HP & SH Stuck Breaker Protection and Breaker Close Supervision) Raritan River Substation (Revisions) The protection for the 230 kv (T1034) line to the R11 Interconnection Substation shall consist of: Replace the RFL-9300 relay with a SEL-311L relay with fiber optic interface (Primary Line) The protection for the 230 kv (G1047) line to the R11 Interconnection Substation shall consist of: Replace the RFL-9300 relay with a SEL-311L relay with fiber optic interface (Primary Line) Red Oak Substation (Revisions) The protection for the 230 kv (T1034) line to the R11 Interconnection Substation shall consist of: Replace the RFL-9300 relay with a SEL-311L relay with fiber optic interface (Primary Line) The protection for the 230 kv (G1047) line to the R11 Interconnection Substation shall consist of: Replace the RFL-9300 relay with a SEL-311L relay with fiber optic interface (Primary Line) All relays to be connected to SEL-2020, which is to be connected to a GPS time clock. PJM Interconnection All rights reserved. 19 PJMDOCS-# v3

21 Attachment B R11 Protection One-Line Diagram PJM Interconnection All rights reserved. 20 PJMDOCS-# v3

22 Attachment C R11 Interconnection Substation Relay Sketch PJM Interconnection All rights reserved. 21 PJMDOCS-# v3

23 Attachment D Junction Relay Sketch PJM Interconnection All rights reserved. 22 PJMDOCS-# v3

24 Attachment E Typical Interconnection Substation Location Plan PJM Interconnection All rights reserved. 23 PJMDOCS-# v3

25 Attachment F Generation Connection Requirements The proposed interconnection facilities must be designed in accordance with the FirstEnergy Requirements for Transmission Connected Facilities located at: The Interconnection Customer will also be responsible for following the requirements of the FirstEnergy Wholesale Generation Interconnection (WGI) Manual and the FE Approved Vendors and Contractors documents which are also located at the above link. The following is an excerpt taken from the FirstEnergy Requirements for Transmission Connected Facilities document Reactive Power The Facility s minimum requirement, except for wind-powered and other nonsynchronous generation, shall be the provision of a reactive power capability sufficient to maintain a composite power delivery for the Facility at the Interconnection Point at a power factor between 0.95 leading (absorbingvars) and 0.90 lagging (producing VARs). This reactive requirement applies to both the initial installation as well as to any incremental change in unit MW capability. FE will coordinate with the Connecting Party to identify the optimal generator step-up transformer tap to make such a capability available when demanded. Design Requirements The generation owner is responsible for specifying appropriate equipment and facilities such that the parallel generation is compatible with the FirstEnergy Transmission System. The generation owner is also responsible for meeting any applicable federal, state, and local codes. Design Criteria Facilities owned and operated by FirstEnergy (FE) and JCP&L, its operating company, shall comply with the applicable FE technical requirements and standards posted on the PJM website per the PJM Tariff, the PJM transmission and Substation Design Subcommittee Technical Requirements, the PJM Relay Philosophy Design Standards and the following criteria. Where there are different requirements for the same criterion, the more restrictive shall apply. General Design Requirements System phasing (counter clockwise) (FE)/X-Y-Z (JCP&L) System frequency: 60 hertz Elevation, AMSL: 2254 feet Isokeraunic level: 40 Maximum ambient temperature: 40 degrees C Minimum ambient temperature: -40 degrees C PJM Interconnection All rights reserved. 24 PJMDOCS-# v3

26 Maximum conductor operating temperature: Per PJM Document Outdoor Substation Conductor Ratings dated 10/19/04 Wind Loading (no ice): Per ASCE 7-98, Fig. 6-1 Wind coincident with 13 mm radial ice 64 km/h (40 mph) Ice loading Substations (no wind): 25 mm Seismic zone: Per ASCE 7-98, Fig (a) and (b). Equipment qualification per IEEE Voltage and Current Ratings 230 kv System Nominal phase-to-phase: 230 kv Maximum phase-to-phase: 242 kv Basic impulse level (BIL): 900 kv Minimum continuous current carrying capacity: 2000 A Design fault current (equipment & bus): 40 ka Single Contingency (breaker or relay failure) clearing time: 45 cycles Clearances and Spacing 230 kv System Recommended rigid bus center-to-center phase spacing: 132 Minimum phase-to-phase, metal-to-metal distance: 89 Recommended phase-to-ground: 80 Minimum phase-to-ground: 71 Minimum vertical clearance from live parts to grade: 12-9 Minimum horizontal clearance from live parts: 8-3 Minimum conductor clearance above roads, streets, and other areas subject to truck traffic: 23-0 Minimum conductor clearance above spaces and ways subject to pedestrian or restricted traffic: 20-2 Minimum bottom of insulator to top of foundation: 8-6 PJM Interconnection All rights reserved. 25 PJMDOCS-# v3

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114. Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position X1-114 Sandyston January 2012 Preface The intent of the System Impact Study is to determine

More information

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055 Generation Interconnection Feasibility Study Report-Web Version For PJM Generation Interconnection Request Queue Position Z1-055 South Bend Generation Project March 2014 PJM Interconnection 2014. All rights

More information

Hyperlinks are Inactive

Hyperlinks are Inactive Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Course No: E02-010 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education

More information

TRANSMISSION AND SUBSTATION PROJECTS

TRANSMISSION AND SUBSTATION PROJECTS TRANSMISSION AND SUBSTATION PROJECTS OPERATING COMPANY: EMI CUSTOMER: WARREN POWER, LLC EJO # MS0010 SCOPE DOCUMENT FOR 340 MW, IPP PROJECT at VICKSBURG, MS WITH INTERCONNECTION AT BAXTER WILSON 500kV

More information

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F TABLE OF CONTENTS Appendix F - Electrical Engineering Design Criteria F.1 Introduction...F-1 F.2 Codes and Standards...F-1 F.3 Switchyard and Transformers...F-1

More information

Digital Energy ITI. Instrument Transformer Basic Technical Information and Application

Digital Energy ITI. Instrument Transformer Basic Technical Information and Application g Digital Energy ITI Instrument Transformer Basic Technical Information and Application Table of Contents DEFINITIONS AND FUNCTIONS CONSTRUCTION FEATURES MAGNETIC CIRCUITS RATING AND RATIO CURRENT TRANSFORMER

More information

INTRODUCTION TO SYSTEM PROTECTION. Hands-On Relay School 2012

INTRODUCTION TO SYSTEM PROTECTION. Hands-On Relay School 2012 INTRODUCTION TO SYSTEM PROTECTION Hands-On Relay School 2012 CONGRATULATIONS On choosing the field of system protection. It is an exciting, challenging profession. System protection has changed considerably

More information

January 23, 2015. Minimum Design Standards Task Force

January 23, 2015. Minimum Design Standards Task Force Minimum Transmission Design Standards for Competitive January 23, 2015 Minimum Design Standards Task Force Revision History Date or Version Number 12/17/2014 Revision IR 1/23/2015 Revision 1 Author Change

More information

SPECIFICATION COG-2007

SPECIFICATION COG-2007 Cleco Power LLC SPECIFICATION COG-2007 FOR PARALLEL OPPERATION OF CUSTOMER-OWNED GENERATION ON CLECO S ELECTRICAL SYSTEM Revised: March 7, 2014 CONTENTS ITEM NO. TITLE PAGE NO. 1.0 Scope 3 2.0 Policy On

More information

PG&E Transmission Interconnection Handbook. Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

PG&E Transmission Interconnection Handbook. Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES PURPOSE This section provides substation design information for Load Entities interconnected at transmission voltage

More information

TERMS AND CONDITIONS

TERMS AND CONDITIONS Virginia Electric and Power Company TERMS AND CONDITIONS XXIV. GENERATOR INTERCONNECTION STANDARD Electric generator interconnection service includes only the ability to interconnect an electric generator

More information

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering Title 20 PUBLIC SERVICE COMMISSION Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES Chapter 02 Engineering Authority: Public Utility Companies Article, 2-121, 5-101 and 5-303, Annotated Code of Maryland.

More information

Teleprotection Schemes and Equipment. James W. Ebrecht Young Power Equipment Scottsdale, AZ

Teleprotection Schemes and Equipment. James W. Ebrecht Young Power Equipment Scottsdale, AZ * Teleprotection Schemes and Equipment James W. Ebrecht Young Power Equipment Scottsdale, AZ Teleprotection Schemes And Equipment ~ ~ Relay Relay Teleprotection Communications channel Teleprotection Protection

More information

Transmission Protection Overview

Transmission Protection Overview Transmission Protection Overview 2012 Hands-On Relay School Brian Smyth Schweitzer Engineering Laboratories Pullman, WA Transmission Line Protection Objective General knowledge and familiarity with transmission

More information

Submit shop drawings for equipment provided under this section Shop drawings shall indicate:

Submit shop drawings for equipment provided under this section Shop drawings shall indicate: Section 16435 - SWITCHBOARDS Introduction Part 1 - General Reference The work under this section is subject to requirements of the Contract Documents including the General Conditions, Supplementary Conditions,

More information

Q140 Cluster Addendum

Q140 Cluster Addendum Cluster Addendum 1. INTRODUCTION This Interconnection Customer (IC), submitted a Small Generator Interconnection Request (IR) to Arizona Public Service Company (APS) for their proposed project, located

More information

Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process

Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process Presented by: Marianne Mannschreck Date: Welcome A Look at the Net Energy Metering

More information

Technical Specification Of Substation Protection & Control System with IEC 61850 BHEL s Perspective

Technical Specification Of Substation Protection & Control System with IEC 61850 BHEL s Perspective Technical Specification Of Substation Protection & Control System with IEC 61850 BHEL s Perspective India Core Events 2008 September 24 th 2008 1 Background Stability & Reliability Data Storage Communication

More information

QUESTIONS and ANSWERS RFB 745-15-9894, Metal Clad Switchgear and Power Control Room

QUESTIONS and ANSWERS RFB 745-15-9894, Metal Clad Switchgear and Power Control Room QUESTIONS and ANSWERS RFB 745-15-9894, Metal Clad Switchgear and Power Control Room 1) When you click on the UTHSCSA Drawing the site takes you to the E-1 drawing no other. Will there be other drawings

More information

ECE 586b Course Project Report. Auto-Reclosing

ECE 586b Course Project Report. Auto-Reclosing ECE 586b Course Project Report Auto-Reclosing Srichand Injeti May 5, 2008 Department Of Electrical and computer Engineering University Of Western Ontario, London Ontario Table of contents 1. Introduction...1

More information

Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System

Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System Prepared By: Transmission Planning Unit Baltimore Gas & Electric Company Table of Contents 1. INTRODUCTION

More information

Colorado Springs Utilities Interconnection Guidelines For Transmission to Transmission Interconnections Version 1 12/04/2007

Colorado Springs Utilities Interconnection Guidelines For Transmission to Transmission Interconnections Version 1 12/04/2007 Colorado Springs Utilities Interconnection Guidelines For Transmission to Transmission Interconnections Version 1 12/04/2007 I.INTRODUCTION AND GENERAL POLICY 5 A. INTRODUCTION...5 B. THE COLORADO SPRINGS

More information

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz)

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz) 24 1. NETWORK CONFIGURATIONS definition Standard IEC 38 defines voltage ratings as follows: - Low voltage () For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690

More information

Local Back-up Protection for an Electric Power System

Local Back-up Protection for an Electric Power System MULTILIN GER-3178 GE Power Management Local Back-up Protection for an Electric Power System LOCAL BACK UP PROTECTION FOR AN ELECTRIC POWER SYSTEM J. BERDY TABLE OF CONTENTS Transmission Line Back-Up Protection...............................................

More information

Short Circuit Current Calculations

Short Circuit Current Calculations Introduction Several sections of the National Electrical Code relate to proper overcurrent protection. Safe and reliable application of overcurrent protective devices based on these sections mandate that

More information

Requirements for the Attachment of Communication Cable Facilities on PPL Poles

Requirements for the Attachment of Communication Cable Facilities on PPL Poles Page 99 of 137 Requirements for the Attachment of Communication Cable Facilities on Replaces: URS-3002 URS-3004 URS-101C-304 A-157649 Page 100 of 137 Reference Notes for Drawings: General 1. The term communication

More information

Substation Automation and Smart Grid

Substation Automation and Smart Grid GE Energy Substation Automation and Smart Grid John D. McDonald, P.E. GM, T&D Marketing IEEE PES Past President IEEE Division VII Director IEEE Fellow The Smart Grid POWERING POTENTIA L Current Situation

More information

Power Plant Electrical Distribution Systems

Power Plant Electrical Distribution Systems PDH Course E184 Power Plant Electrical Distribution Systems Gary W Castleberry, PE 2008 PDH Center 2410 Dakota Lakes Drive Herndon, VA 20171-2995 Phone: 703-478-6833 Fax: 703-481-9535 www.pdhcenter.com

More information

2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1. 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std.

2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1. 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std. 2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std. Relays) Part 1 General 1.1 CONDITIONS AND REQUIREMENTS: A. Refer to

More information

AORC Technical meeting 2014

AORC Technical meeting 2014 AORC Technical meeting 2014 http : //www.cigre.org C4-1012 Alarm System Improvement in the Northern Region Dispatching Center of Thailand Mr. Manu PONGKAEW, Mr. Phathom TIPSUWAN Electricity Generating

More information

RELIABILITY PLANNING CRITERIA

RELIABILITY PLANNING CRITERIA RELIABILITY PLANNING CRITERIA Version 4.0 01/20/2016 Date Rev. No. Individual Making Edits REVISION HISTORY Reason / Comments 07/01/2013 1 J. Johnson Initial document 06/06/2014 2 R. Chapman Document review;

More information

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation Basis of Design This section applies to the design relating to low voltage switchboards. Design Criteria UW Class N1 facilities main switchboards shall be rear accessible. The main, tie and feeder breakers

More information

16 West Coast Regional Plan

16 West Coast Regional Plan 16 West Coast Regional Plan 16.1 Regional overview 16.2 West Coast transmission system 16.3 West Coast demand 16.4 West Coast generation 16.5 West Coast significant maintenance work 16.6 Future West Coast

More information

PJM Merchant Transmission Request. Queue #R75. Mitchell Shepler Hill 138 Kv Feasibility / System Impact Study

PJM Merchant Transmission Request. Queue #R75. Mitchell Shepler Hill 138 Kv Feasibility / System Impact Study PJM Merchant Transmission Request Queue #R75 Mitchell Shepler Hill 138 Kv Feasibility / System Impact Study 413038v1a March 2007 PJM Interconnection 2007. All rights reserved. Preface The intent of the

More information

PSEG-LONG ISLAND SMART GRID SMALL GENERATOR INTERCONNECTION SCREENING CRITERIA FOR OPERATING IN PARALLEL WITH LIPA S DISTRIBUTION SYSTEM

PSEG-LONG ISLAND SMART GRID SMALL GENERATOR INTERCONNECTION SCREENING CRITERIA FOR OPERATING IN PARALLEL WITH LIPA S DISTRIBUTION SYSTEM PSEG-LONG ISLAND SMART GRID SMALL GENERATOR INTERCONNECTION SCREENING CRITERIA FOR OPERATING IN PARALLEL WITH LIPA S DISTRIBUTION SYSTEM PSEG-LI SGSGIP DG Screening Criteria 5-29-14 Table of Contents I.

More information

TRANSMISSION Field Services (January 30, 2014)

TRANSMISSION Field Services (January 30, 2014) TRANSMISSION Field Services (January 30, 2014) Vice President Transmission Field Services The Vice President - Transmission Region Operations is responsible for the safe, reliable, cost-effective, and

More information

PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS

PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS TESTS ON TRANSFORMERS 1. IR Values a) For 33/11 KV Power Transformer 2500 V megger is to be need. b) Power Transformer neutral Earthing is

More information

Step Voltage Regulators

Step Voltage Regulators Step Voltage Regulators Don Wareham Field Application Engineer Today s Agenda Introduction Voltage Regulator theory Voltage Regulator application considerations Installation and proper bypassing Wrap-up/questions

More information

Secondary Unit Substations

Secondary Unit Substations 14 SWITCHGEAR Secondary Unit Substations Overview Siemens offers a wide variety of unit substation designs to meet customer requirements. A unit substation consists of one or more transformers mechanically

More information

6. The estimated costs here do not include any applicable ITCC tax

6. The estimated costs here do not include any applicable ITCC tax General Notes and Clarifications: 1. The following estimated costs are based on past experiences and are intended to provide an order of magnitude of the total project cost given the major system components.

More information

David Payne, P.E. Associate Director February 18, 2014

David Payne, P.E. Associate Director February 18, 2014 David Payne, P.E. Associate Director February 18, 2014 Overview of Texas A&M University State's first public institution of higher education, was opened on Oct. 4, 1876 as the Agricultural and Mechanical

More information

TABLE OF CONTENTS 1.0 INTRODUCTION... 2 1.1 PURPOSE... 2 1.2 DEVIATION... 2 4.0 INTERTIE PROTECTION REQUIREMENTS... 4

TABLE OF CONTENTS 1.0 INTRODUCTION... 2 1.1 PURPOSE... 2 1.2 DEVIATION... 2 4.0 INTERTIE PROTECTION REQUIREMENTS... 4 Page: 1 of 14 KEY BULLETIN POINTS: THIS GUIDE OUTLINES MINIMUM REQUIREMENTS FOR CONNECTION OF CUSTOMER-OWNED EMERGENCY AND STANDBY (ESG) TO THE GEORGIA POWER COMPANY (GPC) DISTRIBUTION SYSTEM. THESE ARE

More information

N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS

N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS 14:8-4.1 Scope This subchapter sets forth net metering requirements that apply to electric power suppliers, basic generation service providers

More information

Generation and Transmission Interconnection Process

Generation and Transmission Interconnection Process PJM Manual 14A Generation and Transmission Interconnection Process Revision: 18 Effective Date: January 28, 2016 Prepared by Planning Division Generation Interconnection Department PJM 2016 Table of Contents

More information

LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems

LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems A. General This Net Metering Standard for Customer-Owned Grid Connected Electric Generating Systems sets forth the

More information

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003 F R C C FRCC Standards Handbook FRCC Automatic Underfrequency Load Shedding Program Revision Date: July 2003 FRCC Underfrequency Load Shedding Program Modification and Approval Process Requests to modify

More information

Part 1 System Modeling & Studies for Existing Systems

Part 1 System Modeling & Studies for Existing Systems Part 1 System Modeling & Studies for Existing Systems Operation Technology, Inc. Copyright 2009 Result of rapid release of energy due to an arcing fault between two conductors. Bus voltages > 208V Temperatures

More information

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD HOLLAND CLIFF HEWITT ROAD 230 KV TRANSMISSION LINE PROJECT ELECTRIC ALTERNATIVE EVALUATION STUDY BLACK & VEATCH CORPORATION B&V Project 146026(G)

More information

ABB PSPS Erich Steinmann; Generator control-2013

ABB PSPS Erich Steinmann; Generator control-2013 ABB PSPS Erich Steinmann; Generator control-2013 GENERATOR CONTROL THE MODULAR SOLUTION FOR GENERATORS To make sure that power is efficiently converted into electric energy, it is necessary to supervise

More information

HV Substation Design: Applications and Considerations

HV Substation Design: Applications and Considerations HV Substation Design: Applications and Considerations Dominik Pieniazek, P.E. IEEE CED Houston Chapter October 2-3, 2012 Agenda Substation Basics Electrical Configuration Physical Design Protection and

More information

FINAL. Alternative Evaluation. for the. Proposed Burlington-Wray 230-kilovolt Transmission Project

FINAL. Alternative Evaluation. for the. Proposed Burlington-Wray 230-kilovolt Transmission Project FINAL Alternative Evaluation for the Proposed Burlington-Wray 230-kilovolt Transmission Project Prepared by Tri-State Generation and Transmission Association, Inc. 1100 W. 116th Avenue Westminster, Colorado

More information

Unified requirements for systems with voltages above 1 kv up to 15 kv

Unified requirements for systems with voltages above 1 kv up to 15 kv (1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements apply to

More information

How To Get A Power Line Extension

How To Get A Power Line Extension GUIDELINES FOR COMMERCIAL ELECTRIC SERVICE HOOKUP 1 Steps to Commercial Service Pay the Design Deposit Commercial Buildings: Up to 1, sq ft = $1,. 1, 5, sq ft = $2,. Over 5, sq ft = $3,. Commercial jobs

More information

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China ELECTRIC POWER DISTRIBUTION SYSTEMS F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China Keywords: Distribution system planning, Load characteristics, Subtransmission Lines, Distribution

More information

Power products and systems. Intelligent solutions for power distribution Zone concept

Power products and systems. Intelligent solutions for power distribution Zone concept Power products and systems Intelligent solutions for power distribution Zone concept Securing continuous power supply ABB is one of the world's leading power and automation technology companies whose products,

More information

Treasure Valley Electric Plan - Community Advisory Committee

Treasure Valley Electric Plan - Community Advisory Committee Treasure Valley Electric Plan - Community Advisory Committee What is a transmission line and why are they necessary? A transmission line is used to conduct electricity between two points. Without high

More information

101 BASICS SERIES LEARNING MODULE 3: FUNDAMENTALS OF ELECTRICAL DISTRIBUTION. Cutler-Hammer

101 BASICS SERIES LEARNING MODULE 3: FUNDAMENTALS OF ELECTRICAL DISTRIBUTION. Cutler-Hammer 101 BASICS SERIES LEARNING MODULE 3: FUNDAMENTALS OF ELECTRICAL DISTRIBUTION Cutler-Hammer WELCOME Welcome to Module 3, Fundamentals of Electrical Distribution. If you have successfully completed Module

More information

Current Limiting Protector For Systems rated 2.8-38kV and continuous currents through 5000A.

Current Limiting Protector For Systems rated 2.8-38kV and continuous currents through 5000A. Current Limiting Protector For Systems rated 2.8-38kV and continuous currents through 5000A. Arc Flash and Arc Blast reduction Network protection SCADA adaptable Indoor/outdoor application Professional

More information

ENERGY NETWORKS ASSOCIATION. Electricity Industry EMF Measurement Protocol for High Field Areas

ENERGY NETWORKS ASSOCIATION. Electricity Industry EMF Measurement Protocol for High Field Areas ENERGY NETWORKS ASSOCIATION Electricity Industry EMF Measurement Protocol for High Field Areas Contents 1 Introduction 1.1 Background 1.2 High Field Areas 2 High Field Area - Generation Businesses 2.1

More information

Effective: September 10, 2006 Vermont Attachment 1 to Rule 5.500 Public Service Board Page 1 of 6

Effective: September 10, 2006 Vermont Attachment 1 to Rule 5.500 Public Service Board Page 1 of 6 Public Service Board Page 1 of 6 STANDARD APPLICATION FOR INTERCONNECTION OF GENERATION RESOURCES IN PARALLEL TO THE ELECTRIC SYSTEM OF: (Interconnecting Utility) Preamble and Instructions: An owner of

More information

Selecting Current Transformers Part 1 By Darrell G. Broussard, P.E.

Selecting Current Transformers Part 1 By Darrell G. Broussard, P.E. By Darrell G. Broussard, P.E. Introduction: As engineers, we are aware that electrical power systems have grown. How much have they grown? When was the last time you specified a 2400-volt system, a 4160-volt

More information

SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL

SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL 1.1 SUMMARY A. This section describes the requirements for the installation of Power Monitors and associated

More information

Primary-Side Transformer Protection

Primary-Side Transformer Protection Primary-Side Transformer Protection Peter J. Meyer, S&C Electric Company, Chicago, Illinois Presented at the Doble Life of a Transformer Seminar; Laguna Beach, California February 21 25, 2005 INTRODUCTION

More information

Understanding Power Factor and How it Affects Your Electric Bill. Presented by Scott Peele PE

Understanding Power Factor and How it Affects Your Electric Bill. Presented by Scott Peele PE Understanding Power Factor and How it Affects Your Electric Bill Presented by Scott Peele PE Understanding Power Factor Definitions kva, kvar, kw, Apparent Power vs. True Power Calculations Measurements

More information

Engineering innovation

Engineering innovation Eaton's Electrical Engineering Services & Systems Solutions Focus Seamless Solutions for Reliable, Efficient and Safe Power Systems Engineering innovation Progressive solutions for today s power systems

More information

ABB ! CAUTION. Type COQ Negative Sequence Generator Relay. (50/60 Hertz) 41-161J. Instruction Leaflet

ABB ! CAUTION. Type COQ Negative Sequence Generator Relay. (50/60 Hertz) 41-161J. Instruction Leaflet ABB Instruction Leaflet 41-161J Effective: May 1997 Supersedes I.L. 41-161H Dated July 1984 ( ) Denotes Change Since Previous Issue Type COQ Negative Sequence Generator Relay (50/60 Hertz)! CAUTION Before

More information

When power interruptions happen.

When power interruptions happen. When power interruptions happen. We know it s never a good time to have your power go out, so we work all year pruning trees and investing in our system to cut down on problems before they start. Outage

More information

Grounding of Electrical Systems NEW CODE: Grounding and Bonding

Grounding of Electrical Systems NEW CODE: Grounding and Bonding Grounding of Electrical Systems NEW CODE: Grounding and Bonding Presented By Scott Peele PE Grounding of Electrical Systems Outline Defining the Terms Why should I Ground? Types of Grounding Systems Separately

More information

Type SA-1 Generator Differential Relay

Type SA-1 Generator Differential Relay ABB Automation Inc. Substation Automation and Protection Division Coral Springs, FL 33065 Instruction Leaflet 41-348.11C Effective: November 1999 Supersedes I.L. 41-348.11B, Dated August 1986 ( ) Denotes

More information

Guidelines for Generation, Tie-Line, and Substation Interconnections

Guidelines for Generation, Tie-Line, and Substation Interconnections Guidelines for Generation, Tie-Line, and Substation Interconnections Otter Tail Power Company compiled this document with input from others. Otter Tail Power Company gratefully acknowledges permission

More information

100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center. 598 N. Buth Rd 3215 Arrowhead Rd

100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center. 598 N. Buth Rd 3215 Arrowhead Rd 100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center Introduction Roger Hedding Steven Schoenherr, P.E. ABB Inc. Minnesota Power 598 N. Buth Rd 3215 Arrowhead Rd Dousman,

More information

Scope of Restoration Plan

Scope of Restoration Plan RWG Area Restoration Review Worksheet (10/28/09) EOP-006-02 Directory 8 EOP-005 NYSRG Rule G Text Restoration Plan Requirement R1.Each Reliability Coordinator shall have a Reliability Coordinator Area

More information

Appendix F: TELEMETERING AND TRANSFER TRIP FOR TRANSMISSION GENERATION ENTITIES

Appendix F: TELEMETERING AND TRANSFER TRIP FOR TRANSMISSION GENERATION ENTITIES Appendix F: TELEMETERING AND TRANSFER TRIP FOR TRANSMISSION GENERATION ENTITIES Table of Contents APPENDIX F: TELEMETERING AND TRANSFER TRIP FOR TRANSMISSION GENERATION ENTITIES... 1 F.0. NOTIFICATION...

More information

THE COMMISSIONING PROCESS FOR NEW SUBSTATION EQUIPMENT & PROTECTION SCHEMES ON THE BULK ELECTRIC SYSTEM. Lawrence P. Hayes FirstEnergy Corp.

THE COMMISSIONING PROCESS FOR NEW SUBSTATION EQUIPMENT & PROTECTION SCHEMES ON THE BULK ELECTRIC SYSTEM. Lawrence P. Hayes FirstEnergy Corp. THE COMMISSIONING PROCESS FOR NEW SUBSTATION EQUIPMENT & PROTECTION SCHEMES ON THE BULK ELECTRIC SYSTEM Lawrence P. Hayes FirstEnergy Corp. ABSTRACT This paper discusses the various aspects, considerations,

More information

Arc Terminator Active Arc-Resistant Switchgear

Arc Terminator Active Arc-Resistant Switchgear Arc Terminator Active Arc-Resistant Switchgear Increasing safety and productivity by extinguishing internal arcing faults within the switchgear. The Square D Arc Terminator from Schneider Electric offers

More information

CUSTOMER REQUIREMENTS AT POWER SUBSTATIONS

CUSTOMER REQUIREMENTS AT POWER SUBSTATIONS CUSTOMER REQUIREMENTS AT POWER SUBSTATIONS Customer Handout Date Aug 2, 2010 Version 1.0 File Name Customer Requirements At Power Substations Document Id Outside Plant Engineering 1 Table Of Contents 1.0

More information

DRTS 33. The new generation of advanced test equipments for Relays, Energy meters, Transducers and Power quality meters

DRTS 33. The new generation of advanced test equipments for Relays, Energy meters, Transducers and Power quality meters The new generation of advanced test equipments for Relays, Energy meters, Transducers and Power quality meters Testing all relay technologies: electromechanical, solid state, numerical and IEC61850 Manual

More information

Table of Contents. TransformerIQ FAQs 1

Table of Contents. TransformerIQ FAQs 1 [12/12] FAQs Table of Contents FAQ 1. What size transformer will TransformerIQ monitor?... 2 FAQ 2. Are there different TransformerIQ versions?... 2 FAQ 3. How are the units powered?... 2 FAQ 4. What is

More information

Telemetry system for cathodic protection equipment of underground metal pipelines

Telemetry system for cathodic protection equipment of underground metal pipelines RECOMMENDATION PCRA 009 June 2010 Rev. 0 Committee for Cathodic Protection and Associated Coatings Telemetry system for cathodic protection equipment of underground metal pipelines DISCLAIMER: The present

More information

How the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse

How the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse How the National Grid System Operates Chris Gorman Lead Account Executive Syracuse 2 Parts of the Electric System Parts of the Electric System 1. Generating Station: Produces Electricity. 2. Transmission

More information

PA PUC AERS & Metropolitan Edison Company Site Visit

PA PUC AERS & Metropolitan Edison Company Site Visit PA PUC AERS & Metropolitan Edison Company Site Visit October 26, 2010 Scott Lowry Director-Operation Services, Met-Ed Andrew Zulkosky Manager-Engineering, Met-Ed Curt Christenson Manager-York Customer

More information

CONSULTATION PAPER FOR PROPOSED MODIFICATIONS TO THE TRANSMISSION CODE

CONSULTATION PAPER FOR PROPOSED MODIFICATIONS TO THE TRANSMISSION CODE CONSULTATION PAPER FOR PROPOSED MODIFICATIONS TO THE TRANSMISSION CODE Closing date for submission of representations: 30 th Sep 2014, 5 pm 18 AUG 2014 ENERGY MARKET AUTHORITY 991G Alexandra Road #01-29

More information

ATTACHMENT G. Network Operating Agreement

ATTACHMENT G. Network Operating Agreement ATTACHMENT G Network Operating Agreement 1. PURPOSE OF NETWORK OPERATING AGREEMENT The purpose of this Agreement is to identify contractual requirements related to Network Integration Transmission Service

More information

DIMENSIONING OF CURRENT TRANSFORMERS FOR PROTECTON APPLICATION

DIMENSIONING OF CURRENT TRANSFORMERS FOR PROTECTON APPLICATION ÿþ üûúùø öõöôùóùõò CT Dimensioning DIMENSIONING OF CURRENT TRANSFORMERS FOR PROTECTON APPLICATION Application note GER3973 1 CT Dimensioning ÿþ üûúùø öõöôùóùõò GER-3973 Application note ÿþ üûúùø öõöôùóùõò

More information

Addendum #2 Contract UK-11-13

Addendum #2 Contract UK-11-13 Addendum #2 Contract UK-11-13 Utilities Kingston Purchase and Replacement of Switchgear at Kingston Hydro Substation MS11 March 25, 2011 Delivered to: All RFP recipients Total number of pages: Nine (9)

More information

Reyrolle Protection Devices. 7PG17 - XR Intertripping, Interposing, Supervision and Special Purpose Relays. Answers for energy

Reyrolle Protection Devices. 7PG17 - XR Intertripping, Interposing, Supervision and Special Purpose Relays. Answers for energy Reyrolle Protection Devices 7PG17 - XR Intertripping, Interposing, Supervision and Special Purpose Relays. Answers for energy Siemens Protection Devices Limited 2 7PG17 XR101 & XR102 Intertripping Relay

More information

Minimizing Impact of Electric Utility Outages with Backup Generation

Minimizing Impact of Electric Utility Outages with Backup Generation Minimizing Impact of Electric Utility Outages with Backup Generation Introduction of the Speaker Michael Dempsey, PE Senior Electrical Engineer Carter & Burgess, Inc. Energy & Power Solutions Facility

More information

COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011

COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011 COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011 I. Background The Solar Alliance is a group of approximately 30 of the largest photovoltaic (PV) solar development and

More information

Pilot-wire differential relay for lines with two or more terminals

Pilot-wire differential relay for lines with two or more terminals Pilot-wire differential relay for lines with two or more terminals Page 1 Issued: March 2003 Revision: A Data subject to change without notice Pilot-wire differential relay with RXHL 401 Features Phase

More information

Customer Substation Manual 08/05/02

Customer Substation Manual 08/05/02 Customer Substation Manual Table of Contents Section Page 2 of 85 Description 0 Preface 010.00 General 010.10 Information Required for the Review of New Customer Substations 010.20 New Customer Substation

More information

STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK

STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK This statement is effective from 1 April 2010 This statement is approved by the Gas and Electricity

More information

Typical Data Requirements Data Required for Power System Evaluation

Typical Data Requirements Data Required for Power System Evaluation Summary 66 Carey Road Queensbury, NY 12804 Ph: (518) 792-4776 Fax: (518) 792-5767 www.nepsi.com sales@nepsi.com Harmonic Filter & Power Capacitor Bank Application Studies This document describes NEPSI

More information

INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION

INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION February 2013 NOTE: If conflict exists between St. Thomas Energy s Conditions of Service and this document, the Conditions

More information

Generator Stator Protection, under/over voltage, under /over frequency and unbalanced loading. Ramandeep Kaur Aujla S.NO 250447392

Generator Stator Protection, under/over voltage, under /over frequency and unbalanced loading. Ramandeep Kaur Aujla S.NO 250447392 1 Generator Stator Protection, under/over voltage, under /over frequency and unbalanced loading By Ramandeep Kaur Aujla S.NO 250447392 ES 586b: Theory and applications of protective relays Department of

More information

Design Criteria Additions Related To PJM IPP R02 project

Design Criteria Additions Related To PJM IPP R02 project Design Criteria Additions Related To PJM IPP R02 project GENERAL DESCRIPTION OF THE PPL ELECTRIC UTILTIES 500 KV SYSTEM Existing System: This document describes the design details of the EXISTING 500 kv

More information

Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems

Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems This Agreement is made and entered into this day of, 20, ( Effective Date ) by and between the Orlando Utilities Commission

More information

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV 1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled

More information