1 PWC DESIGN MANUAL TABLE OF CONTENTS Preface Introduction Acknowledgment Copies of Manual Contact List Disclaimer Page i-ii iii iv v vi Chapter One - General Requirements for Water and Sewer Extensions I Standard Definitions II Standard Abbreviations III General Requirements IV Submittals and Guidelines V Conceptual Phase 1.13 VI Safety 1.14 Chapter Two - Sanitary Sewer Design Guidelines I General Guidelines 2.1 II Required Permits for Construction 2.2 III Design Capacity and Design Flow IV Details of Design and Construction of Sanitary Sewer Collection Mains V Sanitary Sewer Locations VI Manholes rev 1/05
2 VII Sewers in Relation to Streams and Other Water Bodies VIII Protection of Potable Water Supplies, Storm Sewers and Other Utilities IX Pump Stations and Force Mains Chapter Three - Water Distribution Design Guidelines I General 3.1 II Hydraulic Design and Demand III Water Distribution System IV Cross Connection Prevention Chapter Four - Survey Requirements I General 4.1 II Data for Design 4.1 III Data for Construction 4.1 Chapter Five - Drawing Requirements I General 5.1 II Typical Drawing Set 5.1 III Plan Sheet Requirements (All Drawings) IV Title Sheet 5.3 V Utility Layout Sheet VI Plan/Profile Sheets VII Detail Sheets rev 1/05
3 VIII Record Drawings Checklist IX Standard Checklist Chapter Six - Drafting and CADD Standards I General II Standard Layer List III Standard Abbreviations Chapter Seven - Permits, Encroachments and Easements I Required Permits for Construction II Water and Sewer System Approval Process III Required Sets of Plans and Specifications for Approvals 7.11 IV Examples 7.12?? Final Plans and Permit Submittal Checklist?? PWC Specification Checklist?? PWC Property Questionnaire?? PWC Economic Development Incentive Questionnaire?? PWC Application for Approval of Engineering Plans and Specifications for Water Supply Systems?? PWC Application for Gravity Sewers, Pump Stations, and Force Mains?? PWC Water Permit Issuance Letter?? PWC Sewer Permit Issuance Letter?? Engineer s Certification Water?? Engineer s Certification Sewer?? Final Approval Letter from PWC?? NCDOT Encroachment Drawing?? Aberdeen and Rockfish Railroad Pipeline Crossing Application?? Easement Submittal Checklist?? Standard Easement Drawing?? Blanket Easement Exhibit Chapter Eight - Standard Details. 3 rev 1/05
4 Sewer Details Water Details Miscellaneous Details Erosion Control/Wetland/Drainage Details Miscellaneous Notes Chapter Nine - Technical Specifications Definitions of Terms 1-3 General Conditions Site Clearing Site Clearing (Utility) Grading, Utilities Excavation, Trenching and Backfilling for Utility Systems Erosion Control - General Provisions Temporary Silt Fence Gravel Construction Entrance/Exit Boring and Jacking (Roadways and Railroads) Steel "H" Piles Adjustment of Existing Structures Remove and Replace Pavement (Permanent Patch) Water Distribution Fire Hydrant Painting Sanitary Sewer Systems Sewage Force Mains Watertight Manhole Insert Submersible Pump Lift Station Chain Link Fencing Lawns and Grasses (Utility) Sod Lawns and Grasses (Seeding) Seeding Wetlands Concrete Construction (Utility) Special Coatings (Coal Tar Epoxy Lining Manholes) Special Coatings - Ceramic Epoxy Special Coatings - Cementitious Lining Underground Electrical Crossing Fiber Optic Conduit rev 1/05
5 LIST OF TABLES Chapter 1 Page Chapter 2 Chapter 3 Chapter 4 Table 1 - Required Sets of Plans & Specs for PWC and State Agency Approval 1.12 Table 1 - Guidelines for Determining Domestic Waste Quantities 2.3 Table 2 - Minimum Slopes 2.4 Table 3 - Concrete Pipe & Depth of Cover 2.9 Table 4 - SDR26 PVC Pipe Minimum & Maximum Depth of Cover 2.9 Table 5 - Extra Strength Clay Pipe Minimum & Maximum Depth of Cover 2.10 Table 6 - Ductile Iron Pipe Maximum Depth of Cover 2.10 Table 7 - CCFRMP Maximum Depth of Cover 2.11 Table 1 - DI Mechanical Joint Allowable Deflection 3.6 Table 2 - DI Restrained Joint Allowable Deflection 3.6 Table 3 - DI Push on Joint Allowable Deflection 3.7 Table 4 - C900 PVC Allowable Deflection 3.7 Table 5 - Min. Length DI Pipe Restraint 16" Diameter and Greater 3.13 Exhibit 1 Meter Sizing Form 3.22 Exhibit 1 Water Cut Sheet (Sample) 4.4 Exhibit 2 Sewer Cut Sheet (Sample) rev 1/05
6 Chapter 6 Table 1 Standard Sheet Sizes 6.2 Chapter 7 Table 1 Minimum Easement Widths rev 1/05
The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:
Page 1 of 6 Section 1. PURPOSE This policy is an Engineering checklist of the Local Review Program for sanitary sewer improvement projects by the Bedford Regional Water Authority ( Authority ). Section
More informationFY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation
644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING
More informationDESCRIPTION OF WORK:
DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works
More informationWastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects
Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental
More informationSECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.
SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price
More informationSpecial Specification 7021 Water Main and Sewer Line Replacements
Special Specification 7021 Water Main and Sewer Line Replacements 1. DESCRIPTION Furnish, install, or replace water pipe, water valves, water meters and boxes, water service connections, fire hydrant assemblies,
More informationLos Angeles County Department Of Public Works. Land Development Division. Bond Calculation Sheets
Los Angeles County Department Of Public Works Land Development Division Bond Calculation Sheets Effective July 1, 2015 COUNTY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS LAND DEVELOPMENT DIVISION ROADS COST
More informationSECTION 3 SANITARY SEWER DESIGN
SECTION 3 SANITARY SEWER DESIGN 3.1 GENERAL DESIGN CRITERIA 3.1.1 Requirement for Sanitary Sewer 3.1.2 Design Approval 3.1.3 IEPA Permit Required 3.1.4 Differentiation Between Public and Private Sanitary
More informationTABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth
TABLE OF CONTENTS NO. MP-1 MP-2 MP-3 MP-4 MP-4.01 MP-4.02 MP-4.03 MP-5 MP-5.01 MP-5.02 MP-5.03 MP-5.04 MP-5.05 MP-5.06 MP-5.07 MP-5.08 MP-5.11 MP-5.12 MP-5.13 MP-5.14 MP-5.15 MP-5.16 MP-5.18 MP-5.19 MP-5.20
More informationSANITARY SEWER SPECIFICATIONS
SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,
More informationFY08 SEWER POINT REPAIRS BID TABULATION
6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "
More informationSANITARY SEWER SERVICE CONNECTION INSTRUCTIONS
1 SANITARY SEWER SERVICE CONNECTION INSTRUCTIONS TABLE OF CONTENTS I. Introduction II. General Information and Requirements A. Applying for Sewer connection B. Excavation C. Cutting Concrete and Asphalt
More informationCity of Lubbock Public Works Engineering Design Standards and Specifications
City of Lubbock Public Works Engineering Design Standards and Specifications Department of Public Works Engineering City of Lubbock, Texas January 1, 2012 These Standards and Specifications are general
More informationSECTION 5: SANITARY SEWER SYSTEM DESIGN
SECTION 5: SANITARY SEWER SYSTEM DESIGN 5.01 GENERAL Sanitary sewer improvements shall be designed to serve the ultimate level of City development as defined in the General Plan and the Wastewater Facilities
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS
San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS 854.1 DESCRIPTION: This item shall govern sanitary sewer laterals installed in accordance with these
More informationExhibit A. Rules and Regulations for House Connections and Sewer Extensions
The purpose of this application example is to provide assistance to small and medium sized rural communities in the drafting of documents necessary for the efficient operation of water, wastewater, and
More informationEXHIBIT "A. Technical Specifications for Water and Sewer Service Lines
EXHIBIT "A Technical Specifications for Water and Sewer Service Lines Water and Sewer Line Bedding and Backfill: Drawings show cross-section of trench, pipe laid on top of 6" min. bedding material, bedding
More information3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.
The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:
More informationSECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING
SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS
ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by
More informationSEWER LINE EXTENSION DESIGN CHECKLIST
SEWER LINE EXTENSION DESIGN CHECKLIST SWLE# Utilities Staff Date DISCLAIMER - This checklist is provided to Consulting Engineers for the express purpose of assisting them in compiling design plans for
More informationTechnical Specifications For Sewing Enveilment Plans
Appendix B Clean Water Nashville Overflow Abatement Program GUIDANCE FOR DESIGN CONVEYANCE PIPELINES Version 2.0 April 2014 Table of Contents Section 1 General Information... 1 Section 2 Gravity and Pressure
More informationSECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
More informationVOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10
VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 SECTION B1: PREPARATION GUIDE B1.1 INTRODUCTION... B1-1
More informationCHAPTER 8 CIVIL DESIGN
CHAPTER 8 CIVIL DESIGN A. GENERAL This Chapter includes standards and design considerations for other civil engineering design in structural, drainage and utilities. Design considerations for electrical
More informationARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS. for (PVC) SANITARY SEWER MAIN CONSTRUCTION
ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS for (PVC) SANITARY SEWER MAIN CONSTRUCTION VI(A).1 General VI(A).2 Materials and Equipment VI(A).3 Installation of Sanitary Sewer Mains VI(A).4 Laying of
More informationPART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET
PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET Name of Municipality or Sewer District Name of Project Original Township and Lot Number Name of Engineer of Firm Preparing Plans
More informationAPPENDIX D. (Standard Notes and Signature Blocks)
APPENDIX D (Standard Notes and Signature Blocks) Use this note on all construction plans in Raleigh: ATTENTION CONTRACTORS The Construction Contractor responsible for the extension of water, sewer, and/or
More information2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS
2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS Water system improvements proposed for inclusion into Western s service area shall be designed in accordance with all appropriate AWWA standards, include
More informationSECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or
More informationDIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant
More informationSECTION 5 DRAFTING STANDARDS
SECTION 5 DRAFTING STANDARDS 1 SECTION FIVE TABLE OF CONTENTS Description Page TABLE OF CONTENTS... 5-2 GENERAL... 5-3 DRAFTING STANDARDS... 5-5 DRAFTING MINIMUM REQUIREMENTS HANDOUT... 5-8 2 GENERAL 1.
More informationSECTION 33 31 00.11 GRAVITY SANITARY SEWERS
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit
More informationAPPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0
More information3. Amend the following: Item 410 Traffic Compacted Surface, Type C to Item 446 Cold Patch.
To Prospective Bidders: CITY OF TOLEDO, OHIO PARKSIDE AREA SSO ELIMINATION PHASE 2 GRAVITY RELIEF SEWER NO. 2011 Addendum No. 2 December 8, 2011 Information disclosed and/or questions raised since issuing
More informationDESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES
SECTION INCLUDES Domestic Water Fire Water Service Water Well Sanitary Sewer Storm Drains Foundation Drainage RELATED SECTIONS 03 30 00 Concrete 21 00 00 Fire Suppression - Sprinklers 22 00 00 Plumbing
More informationItem No. Description Estimated Unit Total Unit Total Unit Total Unit Total Quantity Price Amount Price Amount Price Amount Price Amount
Engineer's Estimate DiPaolo Company 4350 DiPaolo Center Glenview, IL 60025 Stark Excavating, Inc. 1805 W. Washington Street Bloomington, IL 61701 Rowe Construction 1523 N. Cottage Avenue Bloomington, IL
More informationCity of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014
City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014 Section Subsection Name Date Modification Division 1 All subsections General Provisions
More information3A-1---------------------------------General Information A. Concepts... 1 B. Conditions... 1
Statewide Urban Design and Specifications Table of Contents Design Manual Chapter 3 Sanitary Sewers Table of Contents TOC Chapter 3 Sanitary Sewers 3A General Information 3A-1---------------------------------General
More informationSeptember 2012 Brunswick County Engineering Department Revision 1.0. Technical Specification 020.01 GRAVITY SANITARY SEWER SYSTEM
1.0 General Technical Specification 020.01 GRAVITY SANITARY SEWER SYSTEM a) It is the intent of this specification to ensure that all gravity sewer system infrastructure constructed within the service
More informationAPPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT
APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI 48473 810-635-4464 Fee Received: $ Date: / / Receipt No: Demolition Permit (including Right of
More informationStandards for Water, Sewer, and Sewage Lift Station Design
Standards for Water, Sewer, and Sewage Lift Station Design February 2015 Edition I. Plan Format Requirements General Requirements Water Line Requirements Sewer Line Requirements II. III. IV. Water Design
More informationSECTION 08000 STORM DRAINAGE TABLE OF CONTENTS
SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING
More informationSECTION 8 WATER SUPPLY SYSTEMS
SECTION 8 WATER SUPPLY SYSTEMS Contents Page 8-1 INTRODUCTION... 1 8-2 INTENT OF WATER SYSTEM IMPROVEMENT STANDARDS... 1 8-3 DEFINITIONS... 1 8-4 APPLICABLE STANDARDS... 1 8-5 IMPROVEMENT AND LANDSCAPE
More informationPipe Bursting. Case Study at Zeeland, MI Collections Seminar September 6, 2012. Presentation Agenda. What is Pipe Bursting? What is Pipe Bursting?
Pipe Bursting Case Study at Zeeland, MI Collections Seminar September 6, 2012 By: Brian Hannon, PE and John Racek, PE Presentation Agenda What is Pipe Bursting? History of Pipe Bursting Types of Pipe Bursting
More informationWATER & SEWER LINE REPLACEMENT PROJECT Downtown Tempe Neighborhoods
WATER & SEWER LINE REPLACEMENT PROJECT Downtown Tempe Neighborhoods NEIGHBORHOOD MEETING Wednesday, February 10, 2016 6:00 7:00 p.m. Childsplay, 900 S. Mitchell Drive, Tempe, AZ Neighborhood Meeting Welcome,
More informationLet Us Give Utilities the Respect that they Deserve.
Water & Sewer Utilities Miscellaneous Design and Plan Preparation Guidelines Issued by: Ray Mowla, P.E. Jefferson Parish Department of Engineering, Utilities Section The purpose of issuing these miscellaneous
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS
ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located
More informationAIR RELEASE, CLEANOUT, AND SEWER MANHOLES
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing
More informationVILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL
VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL I/We hereby agree to furnish to the Village of Lombard all necessary materials, equipment, and labor, to complete the North Industrial
More informationThe work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
More informationGreater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development
7 SPECIFICATIONS There is currently no Irish specification for construction of drainage works, or water supply works. There are several publications that give guidance on drainage works, such as the Building
More informationTownship of Enniskillen. Asset Management Plan
Township of Enniskillen Asset Management Plan 2014 1 TABLE OF CONTENTS Page A. Introduction 3 B. State of Local Infrastructure 4 C. Desired Levels of Service 7 D. Asset Management Strategy 8 E. Financing
More informationCITY OF ANN ARBOR PUBLIC SERVICES PLAN REVIEW CHECKLIST
CITY OF ANN ARBOR PUBLIC SERVICES PLAN REVIEW CHECKLIST NOTE: The following list shall only be used as a guide and shall not be used in lieu of the specifications found in the CITY OF ANN ARBOR PUBLIC
More informationLand Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department
Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth
More informationSECTION 6 SANITARY SEWER MAIN 6.01 SCOPE
6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction
More informationSewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE
1.0 GENERAL 1.1 DESCRIPTION This section addresses the procedures to be employed for pipe bursting existing water/sewer pipelines, as identified on the drawings, and replacing with new Restrained Joint
More informationClose-Out Documents... 9
Water and Sanitary Sewer Service Connection Requirements Service Connection Requirements... 1 Application for Services... 2 Water Meter Application... 2 Wet Tap/Tie-in Connection Requirements... 3 Meter
More informationSECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL. 1.01 Testing - General
SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL 1.01 Testing - General Testing shall be of the type and frequency described in each section and summarized in Item 1 of this section. In addition to
More informationSECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.
SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings
More informationUnit Price Averages Reports
Unit Price Averages Reports 12/7/2015 UNIT PRICE AVERAGES REPORT Disclaimer The information provided in the following Unit Price Averages Report is only for the use of Alberta Infrastructure & Transportation
More informationCITY OF MELISSA MANUAL FOR THE DESIGN OF WATER AND SANITARY SEWER LINES
CITY OF MELISSA MANUAL FOR THE DESIGN OF WATER AND SANITARY SEWER LINES SECTION A NOTES TO ENGINEERS This manual is intended to aid and assist private engineers in the layout and design of sanitary sewers
More informationSEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST
SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST For permanent structures per Delaware SCS Pond Code 378 and Delaware Sediment and Stormwater Regulations KEY PROJECT INFORMATION Item meets standard
More informationA. Structures Quantity Item Price Cost @ $3,500 EA
PRINCE WILLIAM COUNTY Department of Development Services Land Development Division UNIT PRICE LIST (Performance Bonds, Landscaping Escrows, and Siltation & Erosion Control Escrows) Revised: November 17,
More informationConstruction Standards for the City of Bristol, Tennessee. Adopted: January 8, 2002
Construction Standards for the City of Bristol, Tennessee Adopted: January 8, 2002 Addendum to the Subdivision Regulations Adopted by the Bristol Tennessee Municipal/Regional Planning Commission November
More informationWATER MAIN CONSTRUCTION TECHNIQUES DEPARTMENT OF PUBLIC WORKS WATER & WASTEWATER DIVISION
WATER MAIN CONSTRUCTION TECHNIQUES Overview Water Main - Materials Specifications Installation Future? Water Main Materials Material Types There are various material types used for water mains, these include:
More informationElectric Engineering Division FIBER CONDUIT RULES AND REGULATIONS
Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS TABLE OF CONTENTS I. RULES AND REGULATIONS A. TABLE OF CONTENTS... 2 B. TERMS AND DEFINITIONS... 3 C. DEVELOPER S/CONTRACTOR S RESPONSIBILITIES...
More informationMANUAL FOR THE DESIGN OF WATER AND SEWER LINES
SECTION I: GENERAL PROVISIONS 1.01 This manual is intended to aid and assist engineers in the layout and design of sanitary sewers and water lines to definite standards and to obtain uniformity in the
More informationSpecifications for Residential Property Owners Connection to New Public Sewer
Specifications for Residential Property Owners Connection to New Public Sewer Spalding Tract property owners are required to connect to the community sewer system when construction is complete and the
More informationTown House 11265 Center Highway North Huntingdon, PA 15642
APPENDIX C SPECIFICATIONS FOR THE CONSTRUCTION OF BUILDING LATERAL SANITARY SEWERS DECEMBER 2004, INCLUDING AMENDMENTS ADOPTED ON FEBRUARY 6, 2008 AND APRIL 2, 2008; EFFECTIVE ON MAY 1, 2008 Town House
More informationChapter 9 Sanitary Sewers
Chapter 9 Sanitary Sewers S:/Engineering/Design Standards/Chapter 9 12/29/2014 Section 9.1 Topic General Requirements Chapter 9 Sanitary Sewers Page 9-1 9.2 Plan Submittals 9-1 9.3 Determination of Flow
More informationARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application.
ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application. Article II provides rules governing the allowable connection to the City POTW and the construction and inspection of
More informationSTRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.
STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill
More informationTECHNICAL SPECIFICATIONS GRAVITY AND PRESSURE SEWER LINE AND MATERIALS
TECHNICAL SPECIFICATIONS GRAVITY AND PRESSURE SEWER LINE AND MATERIALS Scope of Work Work performed under this contract shall consist of furnishing and installing, complete and ready for service, the sewer
More information3.1 Introduction: Design Responsibility and Applicability of Requirements
SECTION 3 Sewer Design and Construction 3.1 Introduction: Design Responsibility and Applicability of Requirements The design and construction requirements for sewer collection systems included in this
More informationSEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,
More informationEmerging Technologies in Wastewater Collection Systems
Keville Enterprises Emerging Technologies in Wastewater Collection Systems Douglas McCutchen, CCM Brian Karmasin, P.E., BCEE CMAA Annual Conference Oct 2008 San Francisco, California Today s s Presentation
More informationSTANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY
STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY Approved and adopted as Official Document Number 800576 this 10th day of December, 1980 Donald R. Boyd, P.E., Director Water
More informationDESIGN STANDARDS MANUAL
DEPARTMENT OF PUBLIC UTILITIES CITY OF VIRGINIA BEACH, VA DESIGN STANDARDS MANUAL Revised Table of Contents Table of Contents 1 Introduction... 1-1 1.1 Authority... 1-1 1.2 Revisions... 1-1 1.3 Organization
More informationOSU Extension FACT SHEET
OHIO STATE UNIVERSITY EXTENSION! OSU Extension FACT SHEET Ohio State University Extension, 2120 Fyffe Road, Columbus, OH 43210 Shale Oil and Gas Development Fact Sheet Series A Landowner s Guide to Understanding
More informationEngineering Specifications February, 2004 Schedule H to Bylaw 7452, Subdivision Bylaw Page 18
Schedule H to Bylaw 7452, Subdivision Bylaw Page 18 3.4 Sanitary Sewers 3.4.1 Materials 3.4.1.1 The class and type of pipe and fittings, together with required class of bedding and trench widths, shall
More informationSoapstone Sewer Rehabilitation Alternative Concepts Design and Associated Impacts
Soapstone Sewer Rehabilitation Alternative Concepts Design and Associated Impacts Outline Update on Soapstone Emergency Response Provide project background Provide project purpose & need Present proposed
More informationMinimum Design Criteria for the permitting of Gravity Sewers
Minimum Design Criteria for the permitting of Gravity Sewers Adopted by the Division of Water Quality on February 12, 1996 Updated to 15A NCAC 2T Regulations on March 2008 1,400 copies of this document
More informationSECTION 603 SANITARY SEWER FORCE MAINS
SECTION 603 SANITARY SEWER FORCE MAINS 1. GENERAL Pipelines for sanitary sewer force main systems shall conform to the following specifications and shall be installed at the locations indicated on the
More informationThe Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11
Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;
More informationSection 02415. Installation of pipe and casing for sanitary sewer by methods of augering.
ITY OF PRLN UGRING PIP OR SING FOR SWRS Section 02415 UGRING PIP OR SING FOR SWRS 1.0 G N R L 1.01 STION INLUS Installation of pipe and casing for sanitary sewer by methods of augering. References to Technical
More informationCD i -STREETS- Detail #
-STREETS- Detail # 3000 Vertical Curb, Gutter and Sidewalk 3010 Low-Profile Curb, Gutter and Sidewalk 3020 Rolled Curb, Gutter and Sidewalk 3030 Separated Sidewalk, Curb & Gutter 3040 Sidewalk Staged Construction
More informationFDOT Specifications List
FDOT Specifications List TABLE OF CONTENTS DIVISION II CONSTRUCTION DETAILS CLEARING CONSTRUCTION SITE 110 Clearing and Grubbing... 152 EARTHWORK AND RELATED OPERATIONS 120 Excavation and Embankment...
More informationSECTION 33 41 00 REINFORCED CONCRETE PIPE. A. The following is a list of SPECIFICATIONS, which may be related to this section:
SECTION 33 41 00 REINFORCED CONCRETE PIPE PART 1 GENERAL 1.01 SECTION INCLUDES A. This section includes construction of reinforced concrete pipe for storm drainage, culverts, and sanitary sewer, including
More informationASTM C76, Class III, Wall B, except as modified herein. Clean natural sand, ASTM C33. Artificial or manufactured sand will not be permitted.
SECTION 3000 - SANITARY SEWERS 3001 SCOPE. This section applies to sanitary sewer construction and shall consist of furnishing all labor, materials, and equipment for the complete installation of sewers
More informationDIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST
DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST CERTIFICATION 1. Did the engineer submit a certificate of completion utilizing the appropriate page of the issued
More informationSECTION 7 UNDERDRAIN SERVICE
SECTION 7 UNDERDRAIN SERVICE ARTICLE I USE OF THE PUBLIC UNDERDRAIN SYSTEM 7.100 The purpose of the District s underdrain system is to provide a method for conveying ground water from around building foundations
More informationModule 3: Sewer Material Lecture 3: Sewer Material
Module 3: Sewer Material Lecture 3: Sewer Material [NPTEL, IIT Kharagpur, Prof. M.M.Ghangrekar, Department of Civil Engineering Page 1 3.0 SEWER MATERIAL 3.1 Important Factors Considered for Selecting
More informationSECTION 02401 - SANITARY SEWER PIPE
PART 1 - GENERAL 1.1 DESCRIPTION A. The WORK under this Section includes providing all labor, materials, tools and equipment necessary for furnishing and installing sanitary sewer pipe, in accordance with
More informationA. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.
PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,
More informationLS 2540 SEWER LATERALS AND INSPECTION TEES
LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal
More informationSECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE
SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE PART 1: GENERAL 1.01 SECTION INCLUDES PVC pressure pipe and fabricated fittings in nominal sizes 4-inches through 12-inches with cast iron pipe equivalent
More informationCHAPTER 11 STORM DRAINAGE
CHAPTER 11 STORM DRAINAGE SECTION 11 GENERAL 11.1 Scope. The provisions of this chapter shall govern the materials, design, construction and installation of storm drainage. 11.2 Where required. All roofs,
More informationState of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
More informationMonterey Regional Water Pollution Control Agency. Sewer System Management Plan
Monterey Regional Water Pollution Control Agency Sewer System Management Plan March 31, 2013 Sewer System Management Plan Introduction I. Goals II. Organization III. Legal Authority IV. Operation and Maintenance