1 Engineer's Estimate DiPaolo Company 4350 DiPaolo Center Glenview, IL Stark Excavating, Inc W. Washington Street Bloomington, IL Rowe Construction 1523 N. Cottage Avenue Bloomington, IL Base Bid Schedule (Water) 1 6-Inch Diameter Water Main, Open Cut, DIP, Backfill Method 4, per Lineal Foot 457 LF $90 $41,130 $77 $35,189 $100 $45,700 $54 $24, Inch Diameter DIP Water Main, Open Cut With 12 Casing, Backfill Method 4, per Lineal Foot 22 LF $165 $3,630 $200 $4,400 $143 $3,146 $89 $1, Inch Diameter Water Main, Open Cut, DIP, Backfill Method 4, per Lineal Foot 3,574 LF $100 $357,400 $75 $268,050 $95 $339,530 $82 $292, Inch Diameter Water Main, Open Cut, DIP, Backfill Method 4, Country Club Place and Mercer Avenue, per Lineal Foot 3,523 LF $90 $317,070 $55 $193,765 $73 $257,179 $84 $295, Inch Diameter DIP Water Main, Open Cut With 16 Casing, Backfill Method 4, per Lineal Foot 481 LF $190 $91,390 $203 $97,643 $204 $98,124 $116 $55, Inch Diameter DIP Water Main, Open Cut With 16 Casing, Backfill Method 4, Country Club Place and Mercer Avenue, per Lineal Foot 288 LF $180 $51,840 $224 $64,512 $185 $53,280 $116 $33, Inch Diameter Water Main, Open Cut, DIP, Backfill Method 2, per Lineal Foot 100 LF $95 $9,500 $95 $9,500 $127 $12,700 $89 $8, Inch Diameter Water Main, Open Cut, DIP, Backfill Method 4, per Lineal Foot 1,451 LF $165 $239,415 $114 $165,414 $125 $181,375 $99 $143, Inch Diameter DIP Water Main, Open Cut With 24 Casing, Backfill Method 4, per Lineal Foot 118 LF $300 $35,400 $310 $36,580 $322 $37,996 $160 $18, Inch Diameter DIP Water Main, Horizontal Directional Drill, per Lineal Foot 416 LF $300 $124,800 $132 $54,912 $185 $76,960 $202 $83, Inch Diameter DIP Water Main, Bore and Jack With 24" Casing, per Lineal Foot 115 LF $550 $63,250 $488 $56,120 $500 $57,500 $484 $55, Inch Service Tap and Connection, per Each 143 EA $2,200 $314,600 $1,620 $231,660 $2,500 $357,500 $1,649 $235, Inch Service Tap and Connection, per Each 17 EA $3,300 $56,100 $2,800 $47,600 $2,400 $40,800 $2,312 $39, Inch Service Tap and Connection, per Each 2 EA $4,400 $8,800 $3,000 $6,000 $5,000 $10,000 $7,350 $14, Connection to Existing Water Main With Tapping Sleeve and Valve, per Each 10 EA $5,500 $55,000 $3,500 $35,000 $3,500 $35,000 $3,820 $38, Connection to Existing Water Main, per Each 9 EA $7,700 $69,300 $5,000 $45,000 $7,500 $67,500 $5,214 $46, Inch Gate Valve and Box, per Each 2 EA $1,000 $2,000 $900 $1,800 $860 $1,720 $1,313 $2, Inch Gate Valve and Box, per Each 27 EA $1,600 $43,200 $1,300 $35,100 $1,300 $35,100 $1,680 $45, Inch Gate Valve and Box, per Each 10 EA $2,600 $26,000 $2,300 $23,000 $2,500 $25,000 $2,835 $28, Fire Hydrant Assembly, per Each 23 EA $3,800 $87,400 $4,550 $104,650 $7,900 $181,700 $6,161 $141, Reuse/Reconnect Fire Hydrant Assembly, per Each 3 EA $1,000 $3,000 $2,400 $7,200 $4,400 $13,200 $2,730 $8, Abandonment of Existing Water Main, Valves, Hydrants, Service Connections, Lump Sum 1 LS $30,000 $30,000 $111,000 $111,000 $50,000 $50,000 $44,100 $44, Surface Replacement, Pavement, 4'-7' Trench, per Lineal Foot 6,165 LF $55 $339,075 $32 $197,280 $73 $450,045 $38 $237, Surface Replacement, Portland Cement Panel, per Panel 18 EA $400 $7,200 $700 $12,600 $1,600 $28,800 $1,897 $34, Granular Trench Stabilization 20 Ton $20 $400 $60 $1,200 $200 $4,000 $26 $ Mobilization and Demobilization, Lump Sum 1 LS $50,000 $50,000 $9,500 $9,500 $100,000 $100,000 $87,802 $87, Traffic Control Complete, Lump Sum 1 LS $90,000 $90,000 $22,000 $22,000 $35,000 $35,000 $50,981 $50, General Cost Items, Lump Sum 1 LS $150,000 $150,000 $96,000 $96,000 $145,000 $145,000 $118,613 $118,613 Page 1 of 5
2 Total Base Bid (Water ) Amount $2,670,000 $1,972,675 $2,743,855 $2,188,747 Base Bid Schedule (Sewer) Depth Class, Backfill Method 4, per Lineal Foot 1,383 LF $150 $207,450 $103 $142,449 $115 $159,045 $179 $246, Inch Diameter Sanitary Sewer, Open Cut, 12'-15' Depth Class, Backfill Method 4, per Lineal Foot 1,901 LF $170 $323,170 $129 $245,229 $143 $271,843 $189 $359, Inch Diameter Sanitary Sewer, Open Cut, 12'-15' and Mercer Avenue, per Lineal Foot 400 LF $140 $56,000 $133 $53,200 $100 $40,000 $189 $75, Inch Diameter Sanitary Sewer, Open Cut, 15'-18' Depth Class, Backfill Method 4, per Lineal Foot 786 LF $210 $165,060 $174 $136,764 $181 $142,266 $200 $156, Inch Diameter Sanitary Sewer, Open Cut, 6'-9' Depth Class, Backfill Method 2, per Lineal Foot 34 LF $65 $2,210 $90 $3,060 $116 $3,944 $221 $7, Inch Diameter Sanitary Sewer, Open Cut, 9'-12' Depth Class, Backfill Method 2, per Lineal Foot 101 LF $80 $8,080 $100 $10,100 $87 $8,787 $231 $23, Inch Diameter Sanitary Sewer, Open Cut, 9'-12' and Mercer Avenue, per Lineal Foot 90 LS $115 $10,350 $110 $9,900 $143 $12,870 $231 $20, Inch Diameter Sanitary Sewer, Open Cut, 12'-15' Depth Class, Backfill Method 4, per Lineal Foot 34 LF $165 $5,610 $175 $5,950 $170 $5,780 $242 $8, Inch Diameter Sanitary Sewer, Open Cut, 12'-15' Depth Class, Backfill Method 4, per Lineal Foot 621 LF $190 $117,990 $169 $104,949 $209 $129,789 $257 $159, Inch Diameter Sanitary Sewer, Open Cut, 9'-12' and Mercer Avenue, per Lineal Foot 311 LF $150 $46,650 $153 $47,583 $160 $49,760 $268 $83, Inch Diameter Sanitary Sewer, Open Cut, 12'-15' Depth Class, Backfill Method 4, per Lineal Foot 602 LF $200 $120,400 $185 $111,370 $189 $113,778 $278 $167, Inch Diameter Sanitary Sewer, Open Cut, 12'-15' and Mercer Avenue, per Lineal Foot 1,555 LF $170 $264,350 $161 $250,355 $189 $293,895 $278 $432, Inch Diameter Sanitary Sewer, Open Cut, 15'-18' Depth Class, Backfill Method 4, per Lineal Foot 703 LF $230 $161,690 $225 $158,175 $228 $160,284 $294 $206, Inch Diameter Sanitary Sewer, Open Cut, 15'-18' and Mercer Avenue, per Lineal Foot 573 LF $195 $111,735 $195 $111,735 $221 $126,633 $294 $168, Inch Diameter Sanitary Sewer, Open Cut, 18'-21' Depth Class, Backfill Method 4, per Lineal Foot 783 LF $275 $215,325 $282 $220,806 $265 $207,495 $305 $238, Inch Diameter Sanitary Sewer, Open Cut, 21'+ Depth Class, Backfill Method 4, per Lineal Foot 212 LF $330 $69,960 $380 $80,560 $308 $65,296 $315 $66, Inch Diameter Sanitary Sewer, Open Cut, 21'+ and Mercer Avenue, per Lineal Foot 257 LF $285 $73,245 $344 $88,408 $285 $73,245 $315 $80, Inch Diameter Sanitary Sewer, Open Cut, 9'-12' Depth Class, Backfill Method 2, per Lineal Foot 255 LF $165 $42,075 $150 $38,250 $162 $41,310 $326 $83,003 Page 2 of 5
3 19 30-Inch Diameter Sanitary Sewer, Open Cut, 9'-12' Depth Class, Backfill Method 4, per Lineal Foot 516 LF $190 $98,040 $195 $100,620 $250 $129,000 $326 $167, Inch Diameter Sanitary Sewer, Open Cut, 12'-15' Depth Class, Backfill Method 4, per Lineal Foot 859 LF $205 $176,095 $198 $170,082 $255 $219,045 $336 $288, Inch Diameter Sanitary Sewer, Bore and Jack with 42" Casing, per Lineal Foot 259 LF $700 $181,300 $567 $146,853 $1,000 $259,000 $1,365 $353, Inch Diameter Sanitary Manhole, 9'-12' Depth Class, per Each 1 EA $8,000 $8,000 $6,000 $6,000 $10,000 $10,000 $22,890 $22, Inch Diameter Sanitary Manhole, 9'-12' Depth Class, per Each 1 EA $5,700 $5,700 $7,000 $7,000 $9,000 $9,000 $10,500 $10, Inch Diameter Sanitary Manhole, 12'-15' Depth Class, per Each 9 EA $6,600 $59,400 $6,500 $58,500 $7,000 $63,000 $11,550 $103, Inch Diameter Sanitary Drop Manhole, 12'-15' Depth Class, per Each 5 EA $6,800 $34,000 $7,600 $38,000 $8,800 $44,000 $14,700 $73, Inch Diameter Sanitary Manhole, 15'-18' Depth Class, per Each 2 EA $7,200 $14,400 $7,500 $15,000 $7,800 $15,600 $12,600 $25, Inch Diameter Sanitary Drop Manhole, 15'-18' Depth Class, per Each 6 EA $7,500 $45,000 $8,500 $51,000 $9,800 $58,800 $15,750 $94, Inch Diameter Sanitary Manhole, 18'-21' Depth Class, per Each 1 EA $7,600 $7,600 $10,000 $10,000 $8,500 $8,500 $16,800 $16, Inch Diameter Sanitary Manhole, 21'+ Depth Class, per Each 1 EA $8,800 $8,800 $10,000 $10,000 $9,700 $9,700 $17,850 $17, Inch Diameter Sanitary Drop Manhole, 21'+ Depth Class, per Each 2 EA $9,100 $18,200 $11,000 $22,000 $14,700 $29,400 $18,900 $37, Inch Diameter Sanitary Manhole, 6'-9' Depth Class, per Each 2 EA $4,000 $8,000 $4,200 $8,400 $4,800 $9,600 $6,300 $12, Inch Diameter Sanitary Manhole, 9'-12' Depth Class, per Each 7 EA $4,400 $30,800 $4,500 $31,500 $5,000 $35,000 $6,825 $47, Inch Diameter Sanitary Manhole, 12'-15' Depth Class, per Each 4 EA $5,400 $21,600 $5,100 $20,400 $5,300 $21,200 $7,350 $29, Inch Diameter Sanitary Drop Manhole, 12'-15' Depth Class, per Each 2 EA $5,500 $11,000 $6,500 $13,000 $5,600 $11,200 $8,400 $16, Inch Diameter Sanitary Manhole, 15'-18' Depth Class, per Each 4 EA $5,800 $23,200 $6,500 $26,000 $6,300 $25,200 $8,925 $35, Inch Diameter Sanitary Manhole, 18'-21' Depth Class, per Each 1 EA $6,100 $6,100 $6,500 $6,500 $7,000 $7,000 $9,450 $9, Inch Diameter Storm Sewer, Open Cut, 6'-9' Depth Class, Backfill Method 2, per Lineal Foot 141 LF $60 $8,460 $65 $9,165 $70 $9,870 $97 $13, Inch Diameter Storm Sewer, Open Cut, 6'-9' and Mercer Avenue, per Lineal Foot 471 LF $100 $47,100 $83 $39,093 $115 $54,165 $139 $65, Inch Diameter Storm Sewer, Open Cut, 9'-12' and Mercer Avenue, per Lineal Foot 418 LF $120 $50,160 $102 $42,636 $120 $50,160 $180 $75, Inch Diameter Storm Sewer, Open Cut, 9'-12' Depth Class, Backfill Method 4, per Lineal Foot 52 LF $120 $6,240 $100 $5,200 $130 $6,760 $189 $9, Inch Diameter Storm Sewer, Open Cut, 9'-12' Depth Class, Backfill Method 4, per Lineal Foot 45 LF $100 $4,500 $100 $4,500 $170 $7,650 $221 $9,923 Page 3 of 5
4 42 12-Inch Diameter Storm Sewer, Open Cut, 6'-9' Depth Class, Backfill Method 4, per Lineal Foot 41 LF $60 $2,460 $100 $4,100 $66 $2,706 $33 $1, Inch Diameter Storm Manhole, 6'-9' Depth Class, per Each 4 EA $5,200 $20,800 $4,300 $17,200 $3,400 $13,600 $3,442 $13, Inch Diameter Storm Manhole, 9'-12' Depth Class, per Each 2 EA $6,100 $12,200 $4,500 $9,000 $3,400 $6,800 $4,561 $9, Sanitary Lateral Connection, per Each 146 EA $1,700 $248,200 $3,800 $554,800 $2,900 $423,400 $6,182 $902, Storm Sewer Inlets, per Each 2 EA $3,300 $6,600 $2,000 $4,000 $1,500 $3,000 $0 $0 47 Abandonment of Existing Sewer, Manholes and Laterals, Lump Sum 1 LS $100,000 $100,000 $70,000 $70,000 $97,000 $97,000 $63,242 $63, Surface Replacement, Pavement 6'-9' Trench, per Lineal Foot 34 LF $80 $2,720 $34 $1,156 $75 $2,550 $77 $2, Surface Replacement, Pavement 9'-12' Trench, per Lineal Foot 1,383 LF $100 $138,300 $38 $52,554 $76 $105,108 $60 $83, Surface Replacement, Pavement 12'-15' Trench, per Lineal Foot 2,597 LF $130 $337,610 $37 $96,089 $77 $199,969 $61 $157, Surface Replacement, Pavement 15'-18' Trench, per Lineal Foot 1,487 LF $150 $223,050 $47 $69,889 $100 $148,700 $60 $89, Surface Replacement, Pavement 18'-21' Trench, per Lineal Foot 783 LF $165 $129,195 $53 $41,499 $101 $79,083 $62 $48, Surface Replacement, Pavement 21'+ Trench, per Lineal Foot 212 LF $175 $37,100 $58 $12,296 $107 $22,684 $62 $13, Connect to Existing Sanitary Sewers, per Each 6 EA $3,300 $19,800 $1,800 $10,800 $5,000 $30,000 $5,985 $35, Connect to Existing Storm Sewers, per Each 8 EA $3,300 $26,400 $1,500 $12,000 $2,000 $16,000 $1,836 $14, Surface Replacement, Sod along Baseball Field, per Lineal Foot 678 LF $18 $12,204 $72 $48,816 $12 $8,136 $63 $42, Tree Removal, per Each 2 EA $500 $1,000 $550 $1,100 $400 $800 $368 $ Bloomington Country Club Irrigation Restoration 1 LS $25,000 $25,000 $5,300 $5,300 $10,000 $10,000 $18,480 $18, Granular Trench Stabilization 20 Ton $20 $400 $60 $1,200 $200 $4,000 $44 $ Mobilization and Demobilization, Lump Sum 1 LS $90,000 $90,000 $28,000 $28,000 $100,000 $100,000 $150,238 $150, Traffic Control Complete, Lump Sum 1 LS $160,000 $160,000 $4,700 $4,700 $45,000 $45,000 $50,771 $50, General Cost Items, Lump Sum 1 LS $270,000 $270,000 $194,787 $194,787 $229,000 $229,000 $73,636 $73,636 Total Base Bid (Sewer) Amount $4,740,000 $3,899,578 $4,546,406 $5,897,427 Total Base Bid (Transportation) Amount 1 $1,970,000 $1,970,000 $1,352,255 $1,736,288 $1,533,903 Additive Alternate No. 1 Schedule (Water) Total Base Bid $9,380,000 $7,224,508 $9,026,549 $9,620, Inch Diameter Water Main, Open Cut, DIP, Backfill Method 4, per Lineal Foot 442 LF $100 $44,200 $92 $40,664 $98 $43,316 $82 $36, Inch Diameter DIP Water Main, Open Cut With 16 Casing, Backfill Method 4, per Lineal Foot 28 LF $190 $5,320 $250 $7,000 $212 $5,936 $116 $3, Inch Service Tap and Connection, per Each 20 EA $2,200 $44,000 $2,600 $52,000 $3,000 $60,000 $1,733 $34,650 4 Connection to Existing Water Main With Tapping Sleeve and Valve, per Each 2 EA $5,500 $11,000 $4,000 $8,000 $4,500 $9,000 $5,460 $10,920 5 Connection to Existing Water Main, per Each 2 EA $7,700 $15,400 $4,000 $8,000 $3,500 $7,000 $6,510 $13,020 Page 4 of 5
5 6 8-Inch Gate Valve and Box, per Each 2 EA $1,600 $3,200 $1,250 $2,500 $1,800 $3,600 $1,680 $3,360 7 Fire Hydrant Assembly, per Each 3 EA $3,800 $11,400 $4,300 $12,900 $9,000 $27,000 $6,642 $19,927 8 Surface Replacement, Pavement, 4'-7' Trench, per Lineal Foot 470 LF $55 $25,850 $34 $15,980 $74 $34,780 $40 $18,969 Additive Alternate No. 1 (Water) Bid Amount $160,000 $147,044 $190,632 $140,280 Additive Alternate No. 1 Schedule (Sewer) Depth Class, Backfill Method 4, per Lineal Foot 1,075 LF $150 $161,250 $113 $121,475 $115 $123,625 $152 $163, Inch Diameter Sanitary Manhole, 9'-12' Depth Class, per Each 4 EA $4,400 $17,600 $5,000 $20,000 $4,800 $19,200 $6,615 $26,460 3 Sanitary Lateral Connection, per Each 25 EA $1,700 $42,500 $3,500 $87,500 $2,300 $57,500 $3,887 $97,167 4 Surface Replacement, Pavement 9'-12' Trench, per Lineal Foot 1,075 LF $100 $107,500 $38 $40,850 $78 $83,850 $60 $64,973 Additive Alternate No. 1 (Sewer) Bid Amount $330,000 $269,825 $284,175 $352,269 Total Additive Alternate No. 1 Bid Amount $490,000 $416,869 $474,807 $492,548 Additive Alternate No. 2 Schedule (Sewer) Depth Class, Backfill Method 4, per Lineal Foot 624 LF $150 $93,600 $102 $63,648 $150 $93,600 $156 $97, Inch Diameter Sanitary Manhole, 9'-12' Depth Class, per Each 2 EA $4,400 $8,800 $5,500 $11,000 $5,500 $11,000 $8,033 $16, Inch Diameter Storm Sewer, Open Cut, 6'-9' Depth Class, Backfill Method 4, per Lineal Foot 334 LF $105 $35,070 $104 $34,736 $124 $41,416 $132 $44, Inch Diameter Storm Sewer, Open Cut, 6'-9' Depth Class, Backfill Method 4, per Lineal Foot 323 LF $100 $32,300 $108 $34,884 $120 $38,760 $139 $44, Inch Diameter Storm Manhole, 6'-9' Depth Class, per Each 3 EA $4,000 $12,000 $4,500 $13,500 $3,800 $11,400 $8,516 $25,547 6 Sanitary Lateral Connection, per Each 14 EA $1,700 $23,800 $3,400 $47,600 $1,500 $21,000 $4,515 $63,210 7 Storm Sewer Inlets, per Each 2 EA $3,300 $6,600 $2,100 $4,200 $1,300 $2,600 $1,806 $3,612 8 Surface Replacement, Pavement 6'-9' Trench, per Lineal Foot 25 LF $80 $2,000 $34 $850 $100 $2,500 $58 $1,458 9 Surface Replacement, Pavement 9'-12' Trench, per Lineal Foot 624 LF $100 $62,400 $38 $23,712 $102 $63,648 $42 $25, Connect to Existing Storm Sewers, per Each 2 EA $3,300 $6,600 $1,050 $2,100 $1,800 $3,600 $6,720 $13,440 Additive Alternate No. 2 (Sewer) Bid Amount $280,000 $236,230 $289,524 $335,846 Total Additive Alternate No. 2 Bid Amount $280,000 $236,230 $289,524 $335,846 Total Base Bid + Additive Alternates $10,150,000 $7,877,607 $9,790,880 $10,448,472 Page 5 of 5
VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL
VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL I/We hereby agree to furnish to the Village of Lombard all necessary materials, equipment, and labor, to complete the North Industrial
More informationSpecial Specification 7021 Water Main and Sewer Line Replacements
Special Specification 7021 Water Main and Sewer Line Replacements 1. DESCRIPTION Furnish, install, or replace water pipe, water valves, water meters and boxes, water service connections, fire hydrant assemblies,
More informationSECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
More informationHow to Do a Water & Sewer System Inventory - Capital Improvements Plan
Table of Contents Background, Objective and Method... 2 Capital Outlay - Water System... 3 Capital Outlay - Sewer System... 4 Summary... 4 Water Exhibit... 5 Sewer Exhibit....6 w w w. c a v a n a u g h
More informationFY08 SEWER POINT REPAIRS BID TABULATION
6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "
More informationFY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation
644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING
More informationSANITARY SEWER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix D
SANITARY SEWER PROJECT COST ESTIMATES & LOCATION MAPS Appendix D RIVERDALE CITY CAPITAL FACILITIES PLAN SANITARY SEWER Engineer's Cost Estimate January 2009 Project Name: Riverdale Road - Rumbi Grill -
More informationSTORM WATER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix F
STORM WATER PROJECT COST ESTIMATES & LOCATION MAPS Appendix F RIVERDALE CITY CAPITAL FACILITIES PLAN STORM DRAINAGE Engineer's Cost Estimate January 2009 Project Name: 4400 South Street - Piping and Collection
More informationCD i -STREETS- Detail #
-STREETS- Detail # 3000 Vertical Curb, Gutter and Sidewalk 3010 Low-Profile Curb, Gutter and Sidewalk 3020 Rolled Curb, Gutter and Sidewalk 3030 Separated Sidewalk, Curb & Gutter 3040 Sidewalk Staged Construction
More informationLos Angeles County Department Of Public Works. Land Development Division. Bond Calculation Sheets
Los Angeles County Department Of Public Works Land Development Division Bond Calculation Sheets Effective July 1, 2015 COUNTY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS LAND DEVELOPMENT DIVISION ROADS COST
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS
San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS 854.1 DESCRIPTION: This item shall govern sanitary sewer laterals installed in accordance with these
More informationTABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth
TABLE OF CONTENTS NO. MP-1 MP-2 MP-3 MP-4 MP-4.01 MP-4.02 MP-4.03 MP-5 MP-5.01 MP-5.02 MP-5.03 MP-5.04 MP-5.05 MP-5.06 MP-5.07 MP-5.08 MP-5.11 MP-5.12 MP-5.13 MP-5.14 MP-5.15 MP-5.16 MP-5.18 MP-5.19 MP-5.20
More informationSECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.
SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings
More informationDemo Existing Curb Demo Existing Asphalt Roadway Demo Asphalt Saw Cutting Protection Fence - 4 Snow Fence with T posts
SECTION 00300 BID FORM S For additions and deletions to the Contract, the following unit prices shall be applicable for the specific items listed. Unit Prices shall be complete, in place including required
More informationGOUVEIA ENGINEERING. Pre-Bid Conference Meeting Minutes. City of Los Banos. Henry Miller Area Storm Drain and L Street Waterline
GOUVEIA ENGINEERING Pre-Bid Conference Meeting Minutes City of Los Banos Henry Miller Area Storm Drain and L Street Waterline Conference held at Intersection of West I Street and L Street, in Los Banos
More informationLS 2540 SEWER LATERALS AND INSPECTION TEES
LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal
More informationUNIT PRICE LIST January 2009
UNIT PRICE LIST January 2009 1 INTRODUCTION The purpose of the Unit Price List is to provide a resource for the preparation of cost estimates for subdivisions and permit projects and should be used only
More informationNew Road 11.0m Asphalt 23m ROW
New Road 11.0m Asphalt 23m ROW Granular A - 150 mm sq. m. $5.35 $69.53 Granular B - 300 mm sq. m. $7.35 $95.54 Concrete Curb and Gutter m. $44.67 $89.34 HL3 Asphalt - 40 mm sq. m. $7.66 $84.23 HL 4 or
More informationSECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.
SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price
More informationPROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS
C PROJECT ESTIMATE ASSUMPTIONS AND EXCLUSIONS In support of the alternatives development process, preliminary cost estimates were prepared for each of the three Candidate Build Alternatives. The cost estimates
More information32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.
SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and
More informationA. Structures Quantity Item Price Cost @ $3,500 EA
PRINCE WILLIAM COUNTY Department of Development Services Land Development Division UNIT PRICE LIST (Performance Bonds, Landscaping Escrows, and Siltation & Erosion Control Escrows) Revised: November 17,
More informationCITY OF ANN ARBOR PUBLIC SERVICES PLAN REVIEW CHECKLIST
CITY OF ANN ARBOR PUBLIC SERVICES PLAN REVIEW CHECKLIST NOTE: The following list shall only be used as a guide and shall not be used in lieu of the specifications found in the CITY OF ANN ARBOR PUBLIC
More informationStorm Sewer Trenchless Upgrade Alternatives and Recommendations
Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for
More informationFDOT Specifications List
FDOT Specifications List TABLE OF CONTENTS DIVISION II CONSTRUCTION DETAILS CLEARING CONSTRUCTION SITE 110 Clearing and Grubbing... 152 EARTHWORK AND RELATED OPERATIONS 120 Excavation and Embankment...
More informationWATER & SEWER LINE REPLACEMENT PROJECT Downtown Tempe Neighborhoods
WATER & SEWER LINE REPLACEMENT PROJECT Downtown Tempe Neighborhoods NEIGHBORHOOD MEETING Wednesday, February 10, 2016 6:00 7:00 p.m. Childsplay, 900 S. Mitchell Drive, Tempe, AZ Neighborhood Meeting Welcome,
More informationClose-Out Documents... 9
Water and Sanitary Sewer Service Connection Requirements Service Connection Requirements... 1 Application for Services... 2 Water Meter Application... 2 Wet Tap/Tie-in Connection Requirements... 3 Meter
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS
ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located
More informationWILDCAT CANYON ROAD SPECIFICATION NO. 16-11001 SLIDE REPAIR BIDDER'S PROPOSAL (continued)
BIDDER'S PROPOSAL (continued) Item Estimated No. Description Quantity Unit Unit Cost Total Cost BASE BID 1 Traffic Control 1 LS $ $ 2 Construction Area Signs 1 LS $ $ 3 Excavation Safety 1 LS $ $ 4 Reset
More informationDESCRIPTION OF WORK:
DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works
More informationEXHIBIT "A. Technical Specifications for Water and Sewer Service Lines
EXHIBIT "A Technical Specifications for Water and Sewer Service Lines Water and Sewer Line Bedding and Backfill: Drawings show cross-section of trench, pipe laid on top of 6" min. bedding material, bedding
More informationPipe Bursting. Case Study at Zeeland, MI Collections Seminar September 6, 2012. Presentation Agenda. What is Pipe Bursting? What is Pipe Bursting?
Pipe Bursting Case Study at Zeeland, MI Collections Seminar September 6, 2012 By: Brian Hannon, PE and John Racek, PE Presentation Agenda What is Pipe Bursting? History of Pipe Bursting Types of Pipe Bursting
More informationA. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.
PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,
More informationSection 402. STORM SEWERS
402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide
More informationCONSTRUCTION PERMIT REQUIREMENTS
CONSTRUCTION PERMIT REQUIREMENTS Any work to be done in the City right-of-way (ROW), in a utility easement, and certain work on private property, requires an Engineering Inspection Permit from the Department
More informationSECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or
More informationSECTION 02400 - STORM DRAIN SYSTEM
SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And
More informationSTANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF MANITOWOC, WISCONSIN SECTION 400 SEWER AND WATER CONSTRUCTION
STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF MANITOWOC, WISCONSIN SECTION 400 SEWER AND WATER CONSTRUCTION Section Number Title 401 GENERAL 402 AMENDMENTS TO WSWS PART I - GENERAL CONDITIONS
More informationBeacon Hill Sewer District Standard Specifications
Beacon Hill Sewer District Standard Specifications Residential Gravity Side Sewer Including Design Criteria and Standard Construction Drawings Residential Gravity Side Sewer Design Criteria 1. Provisions
More informationCITY OF COOS BAY CITY COUNCIL Agenda Staff Report
CITY OF COOS BAY CITY COUNCIL Agenda Staff Report MEETING DATE August 4, 2015 AGENDA ITEM NUMBER TO: Mayor Shoji and City Councilors FROM: Aaron Real, Engineering Technician THROUGH: Jim Hossley, Public
More information3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.
The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:
More informationReference Guide for Obtaining Permits and Utility Services For New Construction
Reference Guide for Obtaining Permits and Utility Services For New Construction (Revised 04-2012) Table of Contents City Offices Telephone Numbers...1 Application for Utilities...2 Building Permits New
More informationAPPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT
APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI 48473 810-635-4464 Fee Received: $ Date: / / Receipt No: Demolition Permit (including Right of
More informationSTORM DRAIN DESIGN AND CONSTRUCTION STANDARDS & SPECIFICATIONS 400 SERIES
CITY OF PETALUMA STORM DRAIN DESIGN AND CONSTRUCTION STANDARDS & SPECIFICATIONS 400 SERIES AUGUST 1999 Revised 10/98 City of Petaluma Petaluma, California STORM DRAIN INSTALLATION DETAIL
More informationMONETARY GUARANTY PROCEDURE PACKAGE FREDERICK COUNTY, VIRGINIA
MONETARY GUARANTY PROCEDURE PACKAGE FREDERICK COUNTY, VIRGINIA Department of Planning and Development 107 North Kent Street, Suite 202 Winchester, Virginia 22601 Phone: (540) 665-5651 Fax: (540) 665-6395
More informationCity of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014
City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014 Section Subsection Name Date Modification Division 1 All subsections General Provisions
More informationSECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING
SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent
More informationSEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,
More informationLet Us Give Utilities the Respect that they Deserve.
Water & Sewer Utilities Miscellaneous Design and Plan Preparation Guidelines Issued by: Ray Mowla, P.E. Jefferson Parish Department of Engineering, Utilities Section The purpose of issuing these miscellaneous
More informationTechnical Memorandum Cost Criteria for 2010 System Capacity Plan
2010 SASD SEWER SYSTEM CAPACITY PLAN UPDATE Technical Memorandum Cost Criteria for 2010 System Capacity Plan PREPARED BY: My Huynh DATE: September 13, 2011 REVIEWED BY: Sonny Lunde INTRODUCTION This Technical
More informationBidding and Contract Requirements:
CITY OF LAREDO, TEXAS WATER UTILITIES DEPARTMENT 24-INCH TRANSMISSION MAIN ADDENDUM 7 June 10, 2016 To Bidder of Record: The following changes, additions, and/or deletions are hereby made a part of the
More informationDESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES
SECTION INCLUDES Domestic Water Fire Water Service Water Well Sanitary Sewer Storm Drains Foundation Drainage RELATED SECTIONS 03 30 00 Concrete 21 00 00 Fire Suppression - Sprinklers 22 00 00 Plumbing
More informationLOGAN TOWNSHIP MUNICIPAL UTILITIES AUTHORITY DESIGN, CONSTRUCTION, INSPECTION AND TESTING MANUAL
LOGAN TOWNSHIP MUNICIPAL UTILITIES AUTHORITY DESIGN, CONSTRUCTION, INSPECTION AND TESTING MANUAL February 2010 LOGAN TOWNSHIP UTILITIES AUTHORITY INSPECTION AND TESTING PROCEDURE TABLE OF CONTENTS SECTION
More informationPipe Bursting Water Lines with Confidence
North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 Paper MM-T4-03 Pipe Bursting Water Lines with Confidence Tracy Weaver, Portland Utilities
More informationARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS. for (PVC) SANITARY SEWER MAIN CONSTRUCTION
ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS for (PVC) SANITARY SEWER MAIN CONSTRUCTION VI(A).1 General VI(A).2 Materials and Equipment VI(A).3 Installation of Sanitary Sewer Mains VI(A).4 Laying of
More informationSTANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY
STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY Approved and adopted as Official Document Number 800576 this 10th day of December, 1980 Donald R. Boyd, P.E., Director Water
More informationSECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains
More informationWater and Sewer Service Line Policy
Water and Sewer Service Line Policy Effective beginning May 17, 2004 (Amended March 16, 2009) Water Service Line Policy General Statement The City of Arlington does not install or participate in water
More informationAPPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0
More informationDIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant
More informationCITY OF NAPLES PURCHASING DIVISION CITY HALL, 735 8 TH STREET SOUTH NAPLES, FLORIDA 34102 PH: 239-213-7100 FX: 239-213-7105 ADDENDUM NUMBER 1
CITY OF NAPLES PURCHASING DIVISION CITY HALL, 735 8 TH STREET SOUTH NAPLES, FLORIDA 34102 PH: 239-213-7100 FX: 239-213-7105 ADDENDUM NUMBER 1 NOTIFICATION DATE: BID TITLE: BID NUMBER: BID OPENING DATE
More informationSECTION 02221 SELECTIVE DEMOLITION
SECTION 02221 PART 1 -GENERAL 1.01 DESCRIPTION This section includes all material, labor, machinery and supervision required to demolish and remove the following items where applicable and as noted on
More informationHow To Install An Overhead Sewer
Village of Broadview Flood Control Assistance Program Village of Broadview 2350 S. 25 th Avenue, Broadview, IL 60155 INTRODUCTION The Village of Broadview is served by combined sewers which carry sewage
More informationSUMMARY OF PUBLIC WORK STANDARD SPECIFICATION REVISIONS 2016
SUMMARY OF PUBLIC WORK STANDARD SPECIFICATION REVISIONS 2016 102.5 Bid Deposits The City of Madison bid deposit form is required for all bids unless a Biennial Bid Bond is on file or check deposit is used.
More informationWATER, SEWER AND TRAFFIC IT S ALL ABOUT THE FLOW
North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 TA-T3-02 WATER, SEWER AND TRAFFIC IT S ALL ABOUT THE FLOW Mark Oberschmidt, P.E., Stantec,
More information12/8/2014. Brought To You By: This webcast is sponsored by NASSCO with the support of IPBA.
Brought To You By: This webcast is sponsored by NASSCO with the support of IPBA. 1 Pipe Bursting A Mature and Diverse Trenchless Technology December 10, 2014 1:00 3:00 pm Eastern How to Participate Today
More informationSERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS
1001 SOUTH LEECHBURG HILL LEECHBURG, PA 15656 Phone: 724-845-9355 Fax: 724-845-1186 SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS 1. General
More informationSECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES
SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with
More informationSECTION 4Aggegate Subbase
The contractor shall moist-cure the completed Lime Treated Subbase for a minimum of days before allowing any traffic on the compacted surface. The contractor shall be responsible for repairing any damages
More informationSection 02415. Installation of pipe and casing for sanitary sewer by methods of augering.
ITY OF PRLN UGRING PIP OR SING FOR SWRS Section 02415 UGRING PIP OR SING FOR SWRS 1.0 G N R L 1.01 STION INLUS Installation of pipe and casing for sanitary sewer by methods of augering. References to Technical
More information1.3.2 Method of construction and restoration of existing water service connections. This shall include:
1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting
More informationSECTION 02100 SITE PREPARATION
SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division
More informationWHEREAS, the Village of Villa Park is a municipal corporation duly organized. WHEREAS, the Village of Villa Park has received a proposal from IMS
' RESOLUTION NO. t,3-3t Q A RESOLUTION AUTHORIZING ACCEPTANCE OF PROPOSAL FROM IMS INFRASTRUCTURE MANAGEMENT SERVICES FOR THE PAVEMENT CONDITION EVALUATION OF SELECTED VILLAGE STREETS WHEREAS, the Village
More informationSEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER
Village of Shorewood, Wisconsin SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER Prepared By: Thomas A. Zoulek, P.E., LEED A.P. Vice President Mid City Plumbing & Heating
More informationFIBER-OPTIC CABLE PLAN CHECK
Engineering Division 201 North Broadway, Escondido, CA 92025 (760) 839-4651, FAX (760) 839-4597 FIBER-OPTIC CABLE PLAN CHECK To: Date: Project: Project No. Address: Check No. Attn: Via: The attached plans
More information8.01 STORM SEWERS, CATCH BASIN LEADS, AND EXTENSIONS
8.01 STORM SEWERS, CATCH BASIN LEADS, AND EXTENSIONS 8.01.01 Description This work shall consist of installing lines of storm sewer pipe of the required inside diameter, and the necessary appurtenances,
More informationSECTION 802 GRAVITY SEWER PIPE
SECTION 802 GRAVITY SEWER PIPE 802-1 DESCRIPTION: This Work shall consist of furnishing all labor, materials, equipment, and incidentals required to remove and dispose of existing gravity sewer pipe if
More informationSUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.
SUBDRAINS AND FOOTING DRAIN COLLECTORS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subdrains B. Subdrain Cleanouts and Outlets C. Footing Drain Collectors D. Storm Sewer Service and Connections 1.02 DESCRIPTION
More informationWater Main Lining A Sustainable Alternative to Open Cut Replacement
Water Main Lining A Sustainable Alternative to Open Cut Replacement Sean O Dell, PE Baxter & Woodman, Inc. B&W Client Seminar, Crystal Lake May 1, 2014 Agenda Why, What, When, Where, Who, How Reduction
More informationCITY ENGINEERS ASSOCIATION OF MINNESOTA
CITY ENGINEERS ASSOCIATION OF MINNESOTA STANDARD SPECIFICATIONS 2600 Trench Excavation and Backfill/Surface Restoration 2611 Water Main and Service Line Installation 2621 Sanitary Sewer and Storm Sewer
More informationITD Pipe Materials Selection & Specification Procedures. July 2011
ITD Pipe Materials Selection & Specification Procedures July 2011 INTRODUCTION: This technical memorandum is written as a guide to the selection of compliant pipe materials and the elimination of non-compliant
More informationSewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE
1.0 GENERAL 1.1 DESCRIPTION This section addresses the procedures to be employed for pipe bursting existing water/sewer pipelines, as identified on the drawings, and replacing with new Restrained Joint
More informationCHAPTER 1181 Improvements
139 CHAPTER 1181 Improvements 1181.01 Performance bond; 1181.07 Street name signs. construction plans; 1181.08 Street lighting. improvements. 1181.09 Improvements bond. 1181.02 Monuments. 1181.10 Maintenance
More informationSECTION 02401 SHEETING, SHORING AND BRACING
SECTION 02401 SHEETING, SHORING AND BRACING This section should be edited to reflect soil conditions specific to the project site and the recommendations of a Geotechnical Engineer licensed in the State
More informationSANITARY GRAVITY SEWER LINE TESTING. B. Section 02732 CCTV Inspection of Gravity Sewer Lines
PART 1 GENERAL 1.1 SECTION INCLUDES A. Low Pressure Air Test B. Deflection Test 1.2 RELATED SECTIONS A. Section 02730 Sanitary Gravity Sewer Lines B. Section 02732 CCTV Inspection of Gravity Sewer Lines
More informationPART B SPECIAL PROVISIONS
PART B SPECIAL PROVISIONS SPECIFICATIONS FOR SANITARY SEWER REHABILITATION GRIZZLY PEAK BOULEVARD, FOREST LANE, CRESTON ROAD BACKLINES, LATHAM LANE, BRET HARTE LANE, LE CONTE AVENUE, EUCLID AVENUE, LE
More informationW. REYNOLDS ST. (SR 574) SEWER LINE REPLACEMENT BID NO. 10-91345-003 Addendum 3a
PROPOSAL AND BID FORM W. REYNOLDS ST. (SR 574) SEWER LINE REPLACEMENT Pursuant to and in compliance with your Invitation to Bid dated February 9, 2010, the Instructions to Bidders, Special Conditions and
More informationWATER & WASTEWATER SYSTEM DESIGN. Technical Design Manuals 1 & 2
WATER & WASTEWATER SYSTEM DESIGN Technical Design Manuals 1 & 2 April 2016 Table of Contents 1. Introduction... 1 A. Policy... 1 I. Potable Water... 1 II. Sanitary Sewer... 2 III. Reclaimed Water... 2
More informationCLEANING, INSPECTION, AND TESTING OF SEWERS
CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and
More informationSECTION 33 41 00 REINFORCED CONCRETE PIPE. A. The following is a list of SPECIFICATIONS, which may be related to this section:
SECTION 33 41 00 REINFORCED CONCRETE PIPE PART 1 GENERAL 1.01 SECTION INCLUDES A. This section includes construction of reinforced concrete pipe for storm drainage, culverts, and sanitary sewer, including
More informationSTANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS
STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for cleaning and lining existing cast iron and ductile iron water mains
More informationWastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects
Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental
More informationINSTALLATION OF INSITUFORM LINER
PART 1 GENERAL 1.1 SCOPE: A. This item shall include all work and materials to install, insert a flexible polyester felt liner saturated with a thermo-setting resin into the existing sewer line for rehabilitation
More informationTechnical Specifications For Sewing Enveilment Plans
Appendix B Clean Water Nashville Overflow Abatement Program GUIDANCE FOR DESIGN CONVEYANCE PIPELINES Version 2.0 April 2014 Table of Contents Section 1 General Information... 1 Section 2 Gravity and Pressure
More information550 PIPE CULVERTS, SEWERS AND DRAINS
551.01 550 PIPE CULVERTS, SEWERS AND DRAINS 551 GENERAL 551.01 Description 551.02 Materials 551.03 Excavation 551.04 Protection of Excavation 551.05(a) Bedding for Rigid Pipe 551.05(b) Bedding for Non-Rigid
More informationSanitary Sewer Mains and Services
Sewer Title Sanitary Sewer Mains and Services STitle Sewer Table of Contents "CORRECTIVE PERIOD & INSPECTION FOR SANITARY SEWERS & SERVICES"... 1 1. TERM OF GUARANTEE... 1 2. CONTRACTOR LICENSE AND PERMITS...
More informationSECTION 5: SANITARY SEWER SYSTEM DESIGN
SECTION 5: SANITARY SEWER SYSTEM DESIGN 5.01 GENERAL Sanitary sewer improvements shall be designed to serve the ultimate level of City development as defined in the General Plan and the Wastewater Facilities
More informationRiverside County Transportation Department Summary of Bids
Bids Open: 2 pm Date: Wednesday, March 4, 2015 BASE BID SCHEDULE 1 - Rudell Road Reconstruction Project NO. CODE CONTRACT PROJECT No. B3-0470 and C4-0069 COUNTY'S ESTIMATE 1 All American Asphalt Corona,
More informationThe checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:
Page 1 of 6 Section 1. PURPOSE This policy is an Engineering checklist of the Local Review Program for sanitary sewer improvement projects by the Bedford Regional Water Authority ( Authority ). Section
More informationCITY OF SAN ANTONIO. Issued By: Transportation and Capital Improvements Date Issued: February 10, 2016 ID NO.: 23-01472-05-03
CITY OF SAN ANTONIO Issued By: Transportation and Capital Improvements Date Issued: February 10, 2016 ID NO.: 23-01472-05-03 (010) FORMAL INVITATION FOR BIDS (IFB) to CONTRACT 2016-2017 TASK ORDER CONTRACT
More information