PJM Generator Interconnection Request. Queue #F04 Somerset 115 kv 30 MW. Queue #I04 Somerset-Allegheny (Pride/Stonycreek) 115 kv 45 MW (Energy Only)
|
|
- Oswin Summers
- 7 years ago
- Views:
Transcription
1 PJM Generator Interconnection Request Queue #F04 Somerset 115 kv 30 MW Queue #I04 Somerset-Allegheny (Pride/Stonycreek) 115 kv 45 MW (Energy Only) Facilities Study Report December 2004 #295423
2 SCOPE Description of Project: Keystone Wind Power L.L.C. has proposed installation of a 30MW wind powered generating facility to be installed in Brothers Valley and Somerset Townships, Somerset County, Pennsylvania (Queue position F04). The generating facility will consist of induction generator wind turbines each with a generating capacity of KW. The plant is proposed to be in service December 31, Stonycreek WindPower, LLC has proposed a 45 MW wind turbine generating station consisting of forty wind turbine generators (Queue position I04). The plant will be utilizing the Vestas 1.8MW machines. The generating station is to be located in Stonycreek and Somerset Townships, Somerset County Pennsylvania. The generating plant, originally scheduled to be in service March 31, 2003, is now scheduled to be in service September 30, The interconnection of both projects will be at 34.5 kv to a new kv substation (Pride a.k.a. Stonycreek) being designed and constructed by the Somerset REC under the delivery point agreement with FirstEnergy (FE). Under that agreement, FE will take ownership of the 115 kv portion of the substation that conveys power across the transmission system. FE will design and install the transmission line tap to the new substation and modify the protective relaying at the Allegheny and Somerset Substations. The Pride Substation Project (The Facility -- also called Stonycreek Substation) is a new delivery point for the Somerset Rural Electric Cooperative, which replaces and eliminates the existing Somerset White Horse Delivery Point. The new substation will serve Somerset s consumers and provide direct connection for two- (2) new wind turbine generating facilities. The two new generators, Keystone WindPower L.L.C. proposes a new 30 MW facility and Stonycreek WindPower L.L.C. a new 45 MW facility. Somerset proposes to tap Pennsylvania Electric Company s (Penelec s) 115 kv transmission line between Penelec Somerset Substation and Penelec Allegheny Substation approximately two miles east of the Penelec Somerset Substation. The substation site is located approximately three miles east of Somerset, Pennsylvania on the north side of State route 31. It is directly across route 31 from the Waste Management landfill site. The Keystone WindPower LLC, under PJM Generator Interconnection Request Queue #F04, and the Stonycreek WindPower LLC, under PJM Generator Interconnection Request Queue #I04, wind turbines will be connected to the transmission system via the low voltage side of the 115/34.5 kv transformers to be installed at the Pride Substation. Somerset REC s consumers will be connected to the transmission system via a 12.5 MVA, 24.9/34.5 kv transformer (and one spare) connected to the low voltage side of the 115/34.5 kv transformers. The new wind farms consisting of 45 MW and 30 MW will have a total connected capacity of 75 MW. Ammendments to System Impact Study None.
3 Substation Interconnection Milestone Schedule: Substation in-service: 18 months after execution of the Interconnection Agreement Initial operation (first synchronization): 18 months after execution of the Interconnection Agreement Commercial operation date: 18 1/2 months after execution of the Interconnection Agreement These estimates of time for construction appear to have been shortened. Apparently the substation can be constructed by the fall of Stoneycreek Windpower (I04) Milestone Schedule July 1, 2005 Initial project energization September 30, 2005 Commercial operation date Keystone Wind Power (F04) Milestone Schedule Close Financing April 2005 Purchase of major equipment April/May 2005 Start of Construction May 2005 First Energization October 2005 Project Completion December 2005 Facility Study Result Work to be completed by Somerset REC Pride (Stonycreek) 115/34.5 kv Substation: The substation portion of work is to be completed by Somerset REC in accordance with RUS guidelines, the one-line diagrams, and the site plan. The following description, ratings and design criteria shall be used to build the substation. Description: The substation shall be construction as a double-end transformer substation consisting of 115 kv line breakers with provisions for a third 115 kv breaker tie position, 115 kv power transformers, 115 kv fault interrupters, 115 kv metering instrument transformers, and 115 kv power line carrier and relaying potential transformers. The Penelec Somerset Substation to Penelec Allegheny Substation 115 kv transmission line will be looped into and out of the substation by FirstEnergy. The 115 kv breaker positions shall be equipped with breaker disconnect and bypass switches. The substation shall be constructed utilizing galvanized structural steel. Installation of 115 kv fault interrupters and 34.5 kv transformer bus breakers shall provide a means of isolating the power transformers for emergencies, operation and maintenance activities.
4 All sources of generation will be connected to the 34.5 kv buses with circuit breakers. A 34.5 kv bus-tie breaker shall be installed. Somerset REC will take delivery from 34.5 kv Bus #2. A relay control house shall be provided to house the relay switchboards, SCADA RTUs, ac and dc panelboards, communications equipment, and 125 Vdc battery system. Ratings/Design Criteria: GSU Power Transformers: three phase units, 115 to 34.5 kv, rated 40/53/66//74 65 degrees C with LTC in 115 kv windings. 115 kv is 550 kv kv is 200 kv. Quantity: 2 Distribution Power Transformers: three phase units, 34.5 kv to 24.9 kv, rated 10/ degrees C kv is 200 kv BIL kv is 150 kv. Quantity: 2 (one spare) Capacitor banks: 34.5 kv, rating/type to be determined. Quantity: 2 Circuit breakers: 115 kv, 2000 A, 550 kv BIL, 40 ka interrupting, SF6 insulated, 4 sets of current transformers (two sets per bushing), Quantity: 2 (structure and switches provided for future 3 rd breaker) Circuit breakers: 34.5 kv, 2000 A, 200 kv BIL, 20 ka interrupting, Vacuum, Quantity: 3 (two bus breakers and one tie breaker) Circuit breakers: 34.5 kv, 1200 A, 200 kv BIL, 20 ka interrupting, Vacuum, Quantity: 6 Fault interrupters: 115 kv, 1200 A 550 kv BIL, 25 ka, Quantity: 2 Group disconnect switch: 115 kv, 1200 A, 550 BIL, 43.5 ka (3 sec), manually operated Group disconnect switch: 34.5 kv, 2000 A, 200 BIL, 100 ka, manually operated Group disconnect switch: 25 kv, 1200 A, 150 BIL, 61 ka, manually operated Disconnect switch: 34.5 kv, 2000 A, 200 BIL, 43.5 ka (3 sec), manually operated Disconnect switch: 34.5 kv, 1200 A, 200 BIL, 38 ka (3 sec), manually operated Disconnect switch: 25 kv, 1200 A, 150 BIL, 38 ka (3 sec), manually operated Regulator bypass: 25 kv, 1200 A, 150 kv BIL, 61 ka (mom.), manually operated Tandem disconnect switch: 25 kv, 1200 A, 150 BIL, 38 ka (3 sec), manually operated Reclosers: 34.5 kv, 560 A, 200 kv BIL, Quantity: 2 Recloser: 25 kv, 560 A, 150 kv BIL, Quantity: 2 Regulator: 333 kva, 25 kv, 150 kv BIL, Quantity: 3
5 CCVT: 115 kv, 550 kv BIL, Quantity: 2 Line trap: 2000 A, Quantity: 2 Protection Requirements: The attached one line diagrams provide details of the relay requirements for the Pride substation. The 115 kv high side of the substation will contain, at minimum, two 115kV circuit breakers, two 115 kv fault interrupters, two 115kV-34.5kV (wye grounded delta wye grounded) transformers, and 115 kv metering instrument transformers. Each 115 kv line exit shall be equipped with a line trap, capacitor voltage transformer, line tuner and carrier set. Minimum protective relaying requirements for this substation installation include primary and backup relays plus a breaker failure relay and an intertie relay. The 115kV breakers shall be purchased with four sets (12 total) of 2000:5 A MR C800 CTs. The 115 kv circuit breaker primary line relays shall be an SEL-321 and SEL-311B for directional ground and phase distance protection. SEL-352 breaker failure relays shall be utilized on the 115kV circuit breakers. The source for the breaker failure fault detector and line relays shall be CTs on the bus side of the 115kV circuit breakers. Any protective trip of this breaker shall initiate the failure to trip scheme. The intertie relay shall be an SEL-351, including 27, 59, 81, 67V and 67N elements. The source for the intertie relay shall be CTs on the 115 kv side of the kv transformers. The CT inputs shall be paralleled from both transformers. The transformer primary protective relay shall be an SEL-587. The transformer backup protective relay shall be an SEL-551 (backup, non-directional) or SEL-351 (backup, directional) digital relays for the transformer high side and the 51G function for the transformer low side. (Note: Directional relays used if required for relay coordination). The transformer primary and backup relaying trips through independent lockout relays. 115 kv bus protection shall be provided by two SEL-387 relays for redundant 115 kv bus protection with inputs from the line side of the two line breakers and the high side of each transformer. These relays shall trip both of the 115 kv line breakers and the 115 kv transformer fault interrupters and 34.5 kv bus circuit breakers kv bus protection shall be provided by two SEL-387 relays with inputs from the source side of the 34.5 kv bus breaker, from the 34.5 kv bus tie breaker, and from the rest of the 34.5 kv circuit breakers connected to that 34.5 kv bus. Each of these relays shall trip its associated 34.5 kv bus and 34.5 kv bus-tie breaker and all other bus-connected 34.5 kv breakers. All required relays shall be utility grade devices. The relaying system shall have a 125 Vdc battery system. Direct Transfer Trip Equipment:
6 Direct Transfer Trip over Class A leased telephone lines from both Somerset and Allegheny substations is to be acquired and maintained for Direct Transfer Trip communications. Receipt of DTT from FirstEnergy shall trip all generation connected to Pride substation. Loss of the DTT channel shall also trip generation connected to Pride substation. Special Relay Requirement: Since stability problems occur as a result of the loss of the Pride Somerset 115kV line for fault clearing, it is, therefore, recommended that the I04 project generators shall be tripped without intentional time delay whenever the Pride Somerset 115kV line becomes unavailable, and should not be reconnected to the 115 kv system till the line is back in service. Metering Requirements: Revenue metering is to be measured by 115 kv instrument transformers installed on the high voltage side of the kv transformers located within 115 kv bus differential zone between the 115 kv fault interrupters and 115/34.5 kv transformers. Metering shall also be provided between each of the 34.5 kv breaker and the 34.5 kv interconnection lines for the generation feeders and between the 34.5 kv breaker and REC s 34.5/24.9 kv transformers. SCADA Requirements: Monitoring should be provided via a SCADA RTU for the 34.5 kv breakers on the generation feeders. Pride (Stonycreek) 115/34.5 kv Substation cost estimate: The estimated cost of the substation is $2.52 million. Work to be done by FirstEnergy Design Criteria Facilities owned and operated by FirstEnergy shall comply with the FirstEnergy Requirements for Transmission Connected Facilities. The FE 115 kv system design shall be based upon the following criteria: General Design Requirements System frequency: 60 hertz Elevation, AMSL: 2254 feet Isokeraunic level: 40 Maximum ambient temperature: 40 degrees C Minimum ambient temperature: -40 degrees C Maximum conductor operating temperature: 100 degrees C Wind Loading (round shapes): 25 psf Ice loading Substations (no wind): 1 inch
7 Seismic zone: Per ASCE 7-98, per Fig (a) and (b). Equipment qualification per IEEE Voltage and Current Ratings Nominal phase-to-phase: 115 kv Maximum phase-to-phase: 121 kv Basic impulse level (BIL): 550 kv Maximum continuous current carrying capacity: 2000 A Design fault current: 40 ka Maximum fault clearing time: 15 cycles Clearances and Spacing Recommended rigid bus center-to-center phase spacing: 84 Minimum phase-to-phase, metal-to-metal distance: 53 Recommended phase-to-ground: 45 Minimum phase-to-ground: 42 Minimum vertical clearance from live parts to grade: 11-7 Minimum horizontal clearance from live parts: 6-1 Minimum conductor clearance above roads in switchyard: 20-2 Minimum bottom of insulator to top of foundation: 8-6 Transmission Lines New/Upgraded 1. Allegheny Somerset 115 kv Line Design, furnish and install a loop (in/out) tap to the new Pride (a.k.a. Stonycreek) Substation. The estimate assumes the substation will be located at the base of an existing transmission line structure. The estimated cost for this work is $70,000 and could be completed in 8 months (6 months for engineering and permitting, 3 months for material and 2 months for construction). Permitting may be required with the PaPUC. Substations New/Upgraded 1. Pride (a.k.a. Stonycreek) Substation. Provide design review and interconnection coordination (transmission line, interconnection metering and SCADA) of the Somerset REC designed and constructed substation. Provide design review and interconnection coordination (interconnection metering and SCADA) for the FE required telemetry of the wind turbine 34.5 kv connections at the Somerset REC substation. The costs of the activities associated with the FE-REC delivery point are assumed to be outside the scope of the PJM interconnection. The estimated cost for the FirstEnergy activities
8 associated with the wind turbine interconnection is $13,000 and would be completed to support the REC s schedule. 2. Allegheny Substation Design, furnish and install the following additions and modifications at the Allegheny 115 kv Substation: New control and relaying on the present Somerset 115 kv line associated with the addition of the new Pride (a.k.a. Stonycreek) Substation. The existing Somerset 115kV exit shall become the new Pride 115kV exit. New line relaying and carrier equipment is required for this exit. A new wave trap and tuning equipment is also required. The existing circuit breaker and line CCPD shall be used. A Direct Transfer Trip (DTT) transmitter is to be installed and DTT is to be keyed to Pride substation for any protective trip of the Pride exit at Allegheny, for a breaker open condition or for a BFT operation on the Allegheny 115kV bus. The estimated cost for this work is $180,000 and could be completed in 8 months (6 months for engineering, 3 months for material and 2 months for construction). There should be no permitting requirements.
9 3. Somerset Substation Design, furnish and install the following additions and modifications at the Allegheny 115 kv Substation: New control and relaying on the present Somerset 115 kv line associated with the addition of the new Pride (a.k.a. Stonycreek) Substation. The existing Allegheny 115kV exit shall become the new Pride 115kV exit. New line relaying and carrier equipment is required for this exit. The existing circuit breaker and line CCPD shall be used. A Direct Transfer Trip (DTT) transmitter is to be installed and DTT is to be keyed to Pride substation for any protective trip of the Pride exit at Somerset, for a breaker open condition or for a BFT operation on the Somerset #1 115kV bus. The estimated cost for this work is $155,000 and could be completed in 8 months (6 months for engineering, 3months for material and 2 months for construction). There should be no permitting requirements. Summary Results of the Study FE can meet the Somerset REC schedule of in-service 18 months after a CSA is signed. A cost summary in 2004 dollars and excluding taxes or CIAC is: 115 kv Transmission Line Tap $70,000 Allegheny Substation Modifications $180,000 Somerset Substation Modifications $155,000 Wind Turbine Interconnection Activity $13,000 Total $418,000 A proposed milestone schedule for this work based upon months from a signed CSA is: Qualifiers Activity Start Month End Month Detailed Engineering 0 6 Equipment Procurement Delivery 3 5 Construction 7 8 Testing & Commissioning 8 8 The accomplishment of the work on the FirstEnergy system to support the costs and schedule is dependent on the following:
10 The developer/somerset REC providing dedicated communication circuits for direct transfer trip relaying from FE s Allegheny and Somerset Substations, for SCADA communication to the transmission system control center, and for dialup access to revenue metering. Obtaining approval from PJM for the necessary outages. No equipment delivery, environmental or regulatory delays. No contractor problems. No force majeure. Interconnection Service Agreement Information The following table summarizes the total costs according to FERC criteria. The costs are in 2004 dollars and do not include taxes or CIAC. Network Facilities Direct Charges Labor $76,900 Direct Charges Material $153,000 Indirect Charges Labor $113,000 Indirect Charges Material $30,300 Return (12%) $44,800 Total $418,000
11 ATTACHMENTS Somerset REC Pride Substation One-Line and Protective Relay Diagram
12
13
Generation Interconnection Facilities Study Report. For. PJM Generation Interconnection Request Queue Position R11. South River
Generation Interconnection Facilities Study Report For PJM Generation Interconnection Request Queue Position R11 South River May 2012 Transmission Owner Facilities Study Summary Description of Project
More informationGeneration Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.
Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position X1-114 Sandyston January 2012 Preface The intent of the System Impact Study is to determine
More informationHyperlinks are Inactive
Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)
More informationELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F
ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F TABLE OF CONTENTS Appendix F - Electrical Engineering Design Criteria F.1 Introduction...F-1 F.2 Codes and Standards...F-1 F.3 Switchyard and Transformers...F-1
More informationQUESTIONS and ANSWERS RFB 745-15-9894, Metal Clad Switchgear and Power Control Room
QUESTIONS and ANSWERS RFB 745-15-9894, Metal Clad Switchgear and Power Control Room 1) When you click on the UTHSCSA Drawing the site takes you to the E-1 drawing no other. Will there be other drawings
More informationGeneration Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055
Generation Interconnection Feasibility Study Report-Web Version For PJM Generation Interconnection Request Queue Position Z1-055 South Bend Generation Project March 2014 PJM Interconnection 2014. All rights
More informationSPECIFICATION COG-2007
Cleco Power LLC SPECIFICATION COG-2007 FOR PARALLEL OPPERATION OF CUSTOMER-OWNED GENERATION ON CLECO S ELECTRICAL SYSTEM Revised: March 7, 2014 CONTENTS ITEM NO. TITLE PAGE NO. 1.0 Scope 3 2.0 Policy On
More informationINTRODUCTION TO SYSTEM PROTECTION. Hands-On Relay School 2012
INTRODUCTION TO SYSTEM PROTECTION Hands-On Relay School 2012 CONGRATULATIONS On choosing the field of system protection. It is an exciting, challenging profession. System protection has changed considerably
More informationTransmission Protection Overview
Transmission Protection Overview 2012 Hands-On Relay School Brian Smyth Schweitzer Engineering Laboratories Pullman, WA Transmission Line Protection Objective General knowledge and familiarity with transmission
More informationFundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components
Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Course No: E02-010 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education
More information2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1. 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std.
2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std. Relays) Part 1 General 1.1 CONDITIONS AND REQUIREMENTS: A. Refer to
More informationAORC Technical meeting 2014
AORC Technical meeting 2014 http : //www.cigre.org C4-1012 Alarm System Improvement in the Northern Region Dispatching Center of Thailand Mr. Manu PONGKAEW, Mr. Phathom TIPSUWAN Electricity Generating
More informationLEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems
LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems A. General This Net Metering Standard for Customer-Owned Grid Connected Electric Generating Systems sets forth the
More informationSubmit shop drawings for equipment provided under this section Shop drawings shall indicate:
Section 16435 - SWITCHBOARDS Introduction Part 1 - General Reference The work under this section is subject to requirements of the Contract Documents including the General Conditions, Supplementary Conditions,
More informationPG&E Transmission Interconnection Handbook. Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES
Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES PURPOSE This section provides substation design information for Load Entities interconnected at transmission voltage
More informationDavid Payne, P.E. Associate Director February 18, 2014
David Payne, P.E. Associate Director February 18, 2014 Overview of Texas A&M University State's first public institution of higher education, was opened on Oct. 4, 1876 as the Agricultural and Mechanical
More informationECE 586b Course Project Report. Auto-Reclosing
ECE 586b Course Project Report Auto-Reclosing Srichand Injeti May 5, 2008 Department Of Electrical and computer Engineering University Of Western Ontario, London Ontario Table of contents 1. Introduction...1
More informationTERMS AND CONDITIONS
Virginia Electric and Power Company TERMS AND CONDITIONS XXIV. GENERATOR INTERCONNECTION STANDARD Electric generator interconnection service includes only the ability to interconnect an electric generator
More information6. The estimated costs here do not include any applicable ITCC tax
General Notes and Clarifications: 1. The following estimated costs are based on past experiences and are intended to provide an order of magnitude of the total project cost given the major system components.
More informationVariable Frequency Drives - a Comparison of VSI versus LCI Systems
Variable Frequency Drives - a Comparison of VSI versus LCI Systems Introduction TMEIC is a leader in the innovative design and manufacture of large ac variable f requency drive systems. TMEIC has been
More informationTHE COMMISSIONING PROCESS FOR NEW SUBSTATION EQUIPMENT & PROTECTION SCHEMES ON THE BULK ELECTRIC SYSTEM. Lawrence P. Hayes FirstEnergy Corp.
THE COMMISSIONING PROCESS FOR NEW SUBSTATION EQUIPMENT & PROTECTION SCHEMES ON THE BULK ELECTRIC SYSTEM Lawrence P. Hayes FirstEnergy Corp. ABSTRACT This paper discusses the various aspects, considerations,
More informationFRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003
F R C C FRCC Standards Handbook FRCC Automatic Underfrequency Load Shedding Program Revision Date: July 2003 FRCC Underfrequency Load Shedding Program Modification and Approval Process Requests to modify
More informationJanuary 23, 2015. Minimum Design Standards Task Force
Minimum Transmission Design Standards for Competitive January 23, 2015 Minimum Design Standards Task Force Revision History Date or Version Number 12/17/2014 Revision IR 1/23/2015 Revision 1 Author Change
More informationTeleprotection Schemes and Equipment. James W. Ebrecht Young Power Equipment Scottsdale, AZ
* Teleprotection Schemes and Equipment James W. Ebrecht Young Power Equipment Scottsdale, AZ Teleprotection Schemes And Equipment ~ ~ Relay Relay Teleprotection Communications channel Teleprotection Protection
More informationFor a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz)
24 1. NETWORK CONFIGURATIONS definition Standard IEC 38 defines voltage ratings as follows: - Low voltage () For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690
More informationANCILLARY EQUIPMENT AND ELECTRICAL EQUIPMENT Power Supply Systems and Electrical Equipment for Desalination Plants - Y.M. Hamud and A.H.
POWER SUPPLY SYSTEMS AND ELECTRICAL EQUIPMENT FOR DESALINATION PLANTS Y.M. Hamud and A.H. Anwar Abu Dhabi Water and Electricity Authority, Abu Dhabi, UAE Keywords : Electrical System, Network for Desalination,
More informationHow To Choose A Transformer
Consider open loop MV network as an example source 1 source 2 NC NC NC or NO main MV switchboard A B Detail design of substation NC NC NC NO NC NC switchboard 1 switchboard 2 switchboard 3 MV MV MV LV
More informationSecondary Unit Substations
14 SWITCHGEAR Secondary Unit Substations Overview Siemens offers a wide variety of unit substation designs to meet customer requirements. A unit substation consists of one or more transformers mechanically
More informationTitle 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering
Title 20 PUBLIC SERVICE COMMISSION Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES Chapter 02 Engineering Authority: Public Utility Companies Article, 2-121, 5-101 and 5-303, Annotated Code of Maryland.
More informationGreen Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process
Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process Presented by: Marianne Mannschreck Date: Welcome A Look at the Net Energy Metering
More informationPower Plant Electrical Distribution Systems
PDH Course E184 Power Plant Electrical Distribution Systems Gary W Castleberry, PE 2008 PDH Center 2410 Dakota Lakes Drive Herndon, VA 20171-2995 Phone: 703-478-6833 Fax: 703-481-9535 www.pdhcenter.com
More informationPA PUC AERS & Metropolitan Edison Company Site Visit
PA PUC AERS & Metropolitan Edison Company Site Visit October 26, 2010 Scott Lowry Director-Operation Services, Met-Ed Andrew Zulkosky Manager-Engineering, Met-Ed Curt Christenson Manager-York Customer
More informationCustomer Substation Manual 08/05/02
Customer Substation Manual Table of Contents Section Page 2 of 85 Description 0 Preface 010.00 General 010.10 Information Required for the Review of New Customer Substations 010.20 New Customer Substation
More informationUNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation
Basis of Design This section applies to the design relating to low voltage switchboards. Design Criteria UW Class N1 facilities main switchboards shall be rear accessible. The main, tie and feeder breakers
More informationSOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD
SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD HOLLAND CLIFF HEWITT ROAD 230 KV TRANSMISSION LINE PROJECT ELECTRIC ALTERNATIVE EVALUATION STUDY BLACK & VEATCH CORPORATION B&V Project 146026(G)
More informationStep Voltage Regulators
Step Voltage Regulators Don Wareham Field Application Engineer Today s Agenda Introduction Voltage Regulator theory Voltage Regulator application considerations Installation and proper bypassing Wrap-up/questions
More informationPSEG-LONG ISLAND SMART GRID SMALL GENERATOR INTERCONNECTION SCREENING CRITERIA FOR OPERATING IN PARALLEL WITH LIPA S DISTRIBUTION SYSTEM
PSEG-LONG ISLAND SMART GRID SMALL GENERATOR INTERCONNECTION SCREENING CRITERIA FOR OPERATING IN PARALLEL WITH LIPA S DISTRIBUTION SYSTEM PSEG-LI SGSGIP DG Screening Criteria 5-29-14 Table of Contents I.
More informationSWITCH YARD OPERATION IN THERMAL POWER PLANT(KaTPP Jhalawar Rajasthan)
From the SelectedWorks of Radhey Shyam Meena Winter July 12, 2012 SWITCH YARD OPERATION IN THERMAL POWER PLANT(KaTPP Jhalawar Rajasthan) RADHEY SHYAM MEENA, Er. Available at: http://works.bepress.com/radhey_meena/5/
More informationHow the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse
How the National Grid System Operates Chris Gorman Lead Account Executive Syracuse 2 Parts of the Electric System Parts of the Electric System 1. Generating Station: Produces Electricity. 2. Transmission
More informationEffective: September 10, 2006 Vermont Attachment 1 to Rule 5.500 Public Service Board Page 1 of 6
Public Service Board Page 1 of 6 STANDARD APPLICATION FOR INTERCONNECTION OF GENERATION RESOURCES IN PARALLEL TO THE ELECTRIC SYSTEM OF: (Interconnecting Utility) Preamble and Instructions: An owner of
More informationRule 5.500 Fast Track Analysis for National Life Insurance Co.
Rule 5.500 Fast Track Analysis for National Life Insurance Co. For a 500 kw Solar array to be located at 155 Northfield Street in Montpelier, Vermont Green Mountain Power Pam Allen Date: 5/31/13 SECTION
More informationEngineering innovation
Eaton's Electrical Engineering Services & Systems Solutions Focus Seamless Solutions for Reliable, Efficient and Safe Power Systems Engineering innovation Progressive solutions for today s power systems
More informationFIT TIER 2 Application
FIT TIER 2 Application Application Information The below information Auto-Fills from your registration information: Building Permit Application Date: Project Completion Date: Name: Address: City: State:
More informationDigital Energy ITI. Instrument Transformer Basic Technical Information and Application
g Digital Energy ITI Instrument Transformer Basic Technical Information and Application Table of Contents DEFINITIONS AND FUNCTIONS CONSTRUCTION FEATURES MAGNETIC CIRCUITS RATING AND RATIO CURRENT TRANSFORMER
More informationPrimary and Secondary Electrical Distribution Systems
Primary and Secondary Electrical Distribution Systems Critical Facilities Round Table 12th Quarterly Membership Meeting June 2, 2006 David D. Roybal. P.E. Eaton Electrical Cutler-Hammer Products Utility
More informationPower Voltage Transformers for Air Insulated Substations. THE PROVEN POWER.
Power Voltage Transformers for Air Insulated Substations THE PROVEN POWER. Introduction Trench Power Voltage Transformers (Power VTs) combine the attributes of an inductive voltage transformer with the
More informationTRANSMISSION AND SUBSTATION PROJECTS
TRANSMISSION AND SUBSTATION PROJECTS OPERATING COMPANY: EMI CUSTOMER: WARREN POWER, LLC EJO # MS0010 SCOPE DOCUMENT FOR 340 MW, IPP PROJECT at VICKSBURG, MS WITH INTERCONNECTION AT BAXTER WILSON 500kV
More informationDead Tank Circuit Breaker 72PM40-C Proven reliability through common platforms
Dead Tank Circuit Breaker 72PM40-C Proven reliability through common platforms ABB innovations for changing demands ABB (www.abb.com) is a leader in power and automation technologies that enables utility
More informationColorado Springs Utilities Interconnection Guidelines For Transmission to Transmission Interconnections Version 1 12/04/2007
Colorado Springs Utilities Interconnection Guidelines For Transmission to Transmission Interconnections Version 1 12/04/2007 I.INTRODUCTION AND GENERAL POLICY 5 A. INTRODUCTION...5 B. THE COLORADO SPRINGS
More informationRequest for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP
Grid Interconnection & Contract Development Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP Submittal Instructions Prior to submitting your application and
More informationSWITCHGEAR SOLUTIONS FOR MISSION CRITICAL APPLICATIONS. Presented by SAI Advanced Power Solutions
SWITCHGEAR SOLUTIONS FOR MISSION CRITICAL APPLICATIONS POWER DISTRIBUTION RACKS IN A MISSION CRITICAL SYSTEM MODULES IN A MISSION CRITICAL SYSTEM UPS Convertor Main Inverter Load Battery BPC UPS & BATTERY
More information100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center. 598 N. Buth Rd 3215 Arrowhead Rd
100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center Introduction Roger Hedding Steven Schoenherr, P.E. ABB Inc. Minnesota Power 598 N. Buth Rd 3215 Arrowhead Rd Dousman,
More information26 3213.13 Diesel Engine Driven Generators Page 1 of 6
Last Update: December 8, 2014 A. Description of System Consultant s Handbook Page 1 of 6 1. Provide a diesel engine driven electric generating unit, factory assembled, tested and certified to operate at
More informationDiscussion on Class I & II Terminology. IEEE PES Transformers Committee Fall Meeting 2011 Boston, MA
Discussion on Class I & II Terminology IEEE PES Transformers Committee Fall Meeting 2011 Boston, MA What is Class I & II? C57.12.00 2010 is the only document we have that defined these terms. 5.10 Insulation
More informationUnified requirements for systems with voltages above 1 kv up to 15 kv
(1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements apply to
More informationDesign of electrical power system for a 1000MW nuclear power generating station
Design of electrical power system for a 1000MW nuclear power generating station K Raja, K Yesunadam Dept. of Electrical & Electronics Engineering, Lingaya s Institute of Management & Technology, Vijayawada,
More informationAchieving Operational Efficiencies through On-Line Substation Monitoring. Vince Polsoni Powerstream Inc. Manager Station Sustainment EDIST 2016
Achieving Operational Efficiencies through On-Line Substation Monitoring Vince Polsoni Powerstream Inc. Manager Station Sustainment EDIST 2016 1 Agenda Maintenance Monitoring Equipment CMMS Data Historian
More information-1- PSEG-LI Update of LIPA SGIP Full Docw-NYISO reqmts above 10 MW 10-27-14
PSEG-Long Island Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA s Radial Distribution Systems -1- PSEG-LI Update of LIPA
More informationN.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS
N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS 14:8-4.1 Scope This subchapter sets forth net metering requirements that apply to electric power suppliers, basic generation service providers
More informationPart 1 System Modeling & Studies for Existing Systems
Part 1 System Modeling & Studies for Existing Systems Operation Technology, Inc. Copyright 2009 Result of rapid release of energy due to an arcing fault between two conductors. Bus voltages > 208V Temperatures
More information261000 Medium Voltage Electrical Distribution
Sections Included In This Standard: 1.1 General 1.2 Underground Cable 1.3 Medium Voltage Switches 1.4 Transformers 1.5 Electrical Manholes 1.6 Switch Vaults 1.7 Distribution Switchgear/Switchboards This
More informationHow To Get A Power Line Extension
GUIDELINES FOR COMMERCIAL ELECTRIC SERVICE HOOKUP 1 Steps to Commercial Service Pay the Design Deposit Commercial Buildings: Up to 1, sq ft = $1,. 1, 5, sq ft = $2,. Over 5, sq ft = $3,. Commercial jobs
More informationAUSTIN ENERGY INTERCONNECTION GUIDE FOR CUSTOMER-OWNED POWER PRODUCTION FOR FACILITIES UP TO 10MW A INTERCONNECTION CLASSIFICATIONS...
AUSTIN ENERGY INTERCONNECTION GUIDE FOR CUSTOMER-OWNED POWER PRODUCTION FOR FACILITIES UP TO 10MW TABLE OF CONTENTS PAGE INTRODUCTION... 4 A INTERCONNECTION CLASSIFICATIONS... 5 B. APPLICATION PROCESS
More informationDesign Criteria Additions Related To PJM IPP R02 project
Design Criteria Additions Related To PJM IPP R02 project GENERAL DESCRIPTION OF THE PPL ELECTRIC UTILTIES 500 KV SYSTEM Existing System: This document describes the design details of the EXISTING 500 kv
More informationABB PSPS Erich Steinmann; Generator control-2013
ABB PSPS Erich Steinmann; Generator control-2013 GENERATOR CONTROL THE MODULAR SOLUTION FOR GENERATORS To make sure that power is efficiently converted into electric energy, it is necessary to supervise
More informationResidential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems
Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems This Agreement is made and entered into this day of, 20, ( Effective Date ) by and between the Orlando Utilities Commission
More informationDistributed Generation and the Impact on a Distribution System. Brian Lassiter Technical Sales Engineer
Distributed Generation and the Impact on a Distribution System Brian Lassiter Technical Sales Engineer Company Overview Founded in 1989 in Abilene, TX Industry leader in Engineering and Operations Utility
More informationPower products and systems. Intelligent solutions for power distribution Zone concept
Power products and systems Intelligent solutions for power distribution Zone concept Securing continuous power supply ABB is one of the world's leading power and automation technology companies whose products,
More informationTABLE OF CONTENTS 1.0 INTRODUCTION... 2 1.1 PURPOSE... 2 1.2 DEVIATION... 2 4.0 INTERTIE PROTECTION REQUIREMENTS... 4
Page: 1 of 14 KEY BULLETIN POINTS: THIS GUIDE OUTLINES MINIMUM REQUIREMENTS FOR CONNECTION OF CUSTOMER-OWNED EMERGENCY AND STANDBY (ESG) TO THE GEORGIA POWER COMPANY (GPC) DISTRIBUTION SYSTEM. THESE ARE
More informationCONSULTATION PAPER FOR PROPOSED MODIFICATIONS TO THE TRANSMISSION CODE
CONSULTATION PAPER FOR PROPOSED MODIFICATIONS TO THE TRANSMISSION CODE Closing date for submission of representations: 30 th Sep 2014, 5 pm 18 AUG 2014 ENERGY MARKET AUTHORITY 991G Alexandra Road #01-29
More informationPRODUCT GUIDE. SL Medium Voltage IEC Vacuum Contactors
PRODUCT GUIDE SL Medium Voltage IEC Vacuum Contactors Table of Contents 1 Overview Introduction....................................................2 Features........................................................2
More informationLightning Arresters P30027 18 KVA P30038 10 KVA. Description & Installation
Lightning Arresters P30027 18 KVA P30038 10 KVA Description & Installation Printed in USA 09/11 TO330 Rev. B Table of Contents Page 1.0 SCOPE 2 2.0 PRODUCT OVERVIEW 2 2.1 Intended Uses 2 2.2 Lightning
More informationType SA-1 Generator Differential Relay
ABB Automation Inc. Substation Automation and Protection Division Coral Springs, FL 33065 Instruction Leaflet 41-348.11C Effective: November 1999 Supersedes I.L. 41-348.11B, Dated August 1986 ( ) Denotes
More informationUnitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva
Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva Issued: August 2009 SIZED UP TO 100 KVA TABLE OF CONTENTS 1.0 Introduction... 1 1.1 Applicability... 1 1.2 Definitions...
More informationMEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS
MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS Meher Capacitors offers reliable and innovative products and solutions in the fields of Reactive Power Compensation, Power Quality and Energy
More informationRELIABILITY PLANNING CRITERIA
RELIABILITY PLANNING CRITERIA Version 4.0 01/20/2016 Date Rev. No. Individual Making Edits REVISION HISTORY Reason / Comments 07/01/2013 1 J. Johnson Initial document 06/06/2014 2 R. Chapman Document review;
More information4.1.1 Generator Owner 4.1.2 Transmission Owner that owns synchronous condenser(s)
A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure
More informationFederal Wage System Job Grading Standards for Electric Power Controlling, 5407. Table of Contents
Federal Wage System Job Grading Standards for Electric Power Controlling, 5407 Table of Contents WORK COVERED... 2 WORK NOT COVERED...2 TITLES... 2 GRADE LEVELS... 2 SPECIAL ADDITIONAL RESPONSIBILITIES...
More informationAppendix F: TELEMETERING AND TRANSFER TRIP FOR TRANSMISSION GENERATION ENTITIES
Appendix F: TELEMETERING AND TRANSFER TRIP FOR TRANSMISSION GENERATION ENTITIES Table of Contents APPENDIX F: TELEMETERING AND TRANSFER TRIP FOR TRANSMISSION GENERATION ENTITIES... 1 F.0. NOTIFICATION...
More informationAddendum #2 Contract UK-11-13
Addendum #2 Contract UK-11-13 Utilities Kingston Purchase and Replacement of Switchgear at Kingston Hydro Substation MS11 March 25, 2011 Delivered to: All RFP recipients Total number of pages: Nine (9)
More information3. TYPES OF SERVICE AVAILABLE. 3.1 Scope
3. TYPES OF SERVICE AVAILABLE 3.1 Scope UI supplies 60 hertz, alternating current with different voltage and ampere ratings. Not all voltage and ampere ratings are available throughout the entire service
More informationTechnical Specification Of Substation Protection & Control System with IEC 61850 BHEL s Perspective
Technical Specification Of Substation Protection & Control System with IEC 61850 BHEL s Perspective India Core Events 2008 September 24 th 2008 1 Background Stability & Reliability Data Storage Communication
More informationSECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL
SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL 1.1 SUMMARY A. This section describes the requirements for the installation of Power Monitors and associated
More informationOVR-3SP Recloser with PCD Control Style Guide 1VAL263901-SG March 30, 2009 Revision B
OVR-3SP Recloser with PCD Control Style Guide 1VAL263901-SG March 30, 2009 Revision B The OVR-3SP three-phase recloser style guide aids in the proper selection of your OVR-3SP style number. The OVR-3SP
More informationAMFA-27 AMFA-29. Operator s Manual & Installation Instructions. Rev. 2.5
AMFA-27 AMFA-29 Operator s Manual & Installation Instructions Rev. 2.5 Date: 17 July, 2010 Permanently-connected, utility Interactive, single-phase, inverters Model AMFA-27 WIND TURBINE INVERTER (240 VAC
More informationTable of Contents. TransformerIQ FAQs 1
[12/12] FAQs Table of Contents FAQ 1. What size transformer will TransformerIQ monitor?... 2 FAQ 2. Are there different TransformerIQ versions?... 2 FAQ 3. How are the units powered?... 2 FAQ 4. What is
More informationTA Kahraman Yumak ELK412 - Distribution of Electrical Energy Lab. Notes v1.0 2013 Spring web.itu.edu.tr/yumakk. Distance Protection
Distance Protection Announcement: You are not supposed to prepare a pre-report. But there will be an oral examination, so you are strongly advised to study this note regarding to the pre-study questions
More informationGuidelines for Generation, Tie-Line, and Substation Interconnections
Guidelines for Generation, Tie-Line, and Substation Interconnections Otter Tail Power Company compiled this document with input from others. Otter Tail Power Company gratefully acknowledges permission
More informationOVR Three-Phase Recloser and PCD Control Style Guide 1VAL264001-SG October 13, 2009 Revision F
OVR Three-Phase Recloser and PCD Control Style Guide 1VAL264001-SG October 13, 2009 Revision F The OVR three-phase recloser style guide aids in the proper selection of your OVR three-phase style number.
More informationAdvanced Protection of Distribution Networks with Distributed Generators
Date:- 8 10 March 2011 Venue: University of Manchester EES-UETP Course title Advanced Protection of Distribution Networks with Distributed Generators Peter Crossley Director of the Joule Centre School
More informationNFPA 70E 2012 Rolls Out New Electrical Safety Requirements Affecting Data Centers
NFPA 70E 2012 Rolls Out New Electrical Safety Requirements Affecting Data Centers A market position paper from the experts in Business-Critical Continuity TM Executive Summary Electrocutions are the fourth
More informationTransmission Planning Standards for the Baltimore Gas & Electric Company Transmission System
Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System Prepared By: Transmission Planning Unit Baltimore Gas & Electric Company Table of Contents 1. INTRODUCTION
More information16 West Coast Regional Plan
16 West Coast Regional Plan 16.1 Regional overview 16.2 West Coast transmission system 16.3 West Coast demand 16.4 West Coast generation 16.5 West Coast significant maintenance work 16.6 Future West Coast
More informationInterconnection of Generators to EDI s Distribution System
Interconnection of Generators to EDI s Distribution System May 22, 2002 This document sets forth the guidelines for connecting a power producing facility to the Alberta Interconnected Electric System through
More informationCustomer Low-Voltage Switchboards Service Cable Terminal Compartment Arrangements and Clearances
Page 50 of 100 Customer Low-Voltage Switchboards Service Cable Terminal Compartment Arrangements and Clearances (Replaces A-190556) THIS CUSTOMER REFERENCE SPECIFICATION (CRS) IS PART OF THE RULES FOR
More informationSOLARCARE SERIES PRODUCT AND APPLICATION GUIDE
SOLARCARE SERIES PRODUCT AND APPLICATION GUIDE for solar energy management LEATEC Delivering Solutions for Energy Management SOLAR ENERGY DATA CENTER BUILDING 4 to8 String Monitoring with 0.% Accuracy
More information2012 San Francisco Colloquium
2012 San Francisco Colloquium http : //www.cigre.org HVDC and Power Electronic Systems for Overhead Line and Insulated Cable Applications B4-8 Trans Bay Cable A Breakthrough of VSC Multilevel Converters
More informationMinimizing Impact of Electric Utility Outages with Backup Generation
Minimizing Impact of Electric Utility Outages with Backup Generation Introduction of the Speaker Michael Dempsey, PE Senior Electrical Engineer Carter & Burgess, Inc. Energy & Power Solutions Facility
More information