PJM Generator Interconnection Request. Queue #F04 Somerset 115 kv 30 MW. Queue #I04 Somerset-Allegheny (Pride/Stonycreek) 115 kv 45 MW (Energy Only)

Size: px
Start display at page:

Download "PJM Generator Interconnection Request. Queue #F04 Somerset 115 kv 30 MW. Queue #I04 Somerset-Allegheny (Pride/Stonycreek) 115 kv 45 MW (Energy Only)"

Transcription

1 PJM Generator Interconnection Request Queue #F04 Somerset 115 kv 30 MW Queue #I04 Somerset-Allegheny (Pride/Stonycreek) 115 kv 45 MW (Energy Only) Facilities Study Report December 2004 #295423

2 SCOPE Description of Project: Keystone Wind Power L.L.C. has proposed installation of a 30MW wind powered generating facility to be installed in Brothers Valley and Somerset Townships, Somerset County, Pennsylvania (Queue position F04). The generating facility will consist of induction generator wind turbines each with a generating capacity of KW. The plant is proposed to be in service December 31, Stonycreek WindPower, LLC has proposed a 45 MW wind turbine generating station consisting of forty wind turbine generators (Queue position I04). The plant will be utilizing the Vestas 1.8MW machines. The generating station is to be located in Stonycreek and Somerset Townships, Somerset County Pennsylvania. The generating plant, originally scheduled to be in service March 31, 2003, is now scheduled to be in service September 30, The interconnection of both projects will be at 34.5 kv to a new kv substation (Pride a.k.a. Stonycreek) being designed and constructed by the Somerset REC under the delivery point agreement with FirstEnergy (FE). Under that agreement, FE will take ownership of the 115 kv portion of the substation that conveys power across the transmission system. FE will design and install the transmission line tap to the new substation and modify the protective relaying at the Allegheny and Somerset Substations. The Pride Substation Project (The Facility -- also called Stonycreek Substation) is a new delivery point for the Somerset Rural Electric Cooperative, which replaces and eliminates the existing Somerset White Horse Delivery Point. The new substation will serve Somerset s consumers and provide direct connection for two- (2) new wind turbine generating facilities. The two new generators, Keystone WindPower L.L.C. proposes a new 30 MW facility and Stonycreek WindPower L.L.C. a new 45 MW facility. Somerset proposes to tap Pennsylvania Electric Company s (Penelec s) 115 kv transmission line between Penelec Somerset Substation and Penelec Allegheny Substation approximately two miles east of the Penelec Somerset Substation. The substation site is located approximately three miles east of Somerset, Pennsylvania on the north side of State route 31. It is directly across route 31 from the Waste Management landfill site. The Keystone WindPower LLC, under PJM Generator Interconnection Request Queue #F04, and the Stonycreek WindPower LLC, under PJM Generator Interconnection Request Queue #I04, wind turbines will be connected to the transmission system via the low voltage side of the 115/34.5 kv transformers to be installed at the Pride Substation. Somerset REC s consumers will be connected to the transmission system via a 12.5 MVA, 24.9/34.5 kv transformer (and one spare) connected to the low voltage side of the 115/34.5 kv transformers. The new wind farms consisting of 45 MW and 30 MW will have a total connected capacity of 75 MW. Ammendments to System Impact Study None.

3 Substation Interconnection Milestone Schedule: Substation in-service: 18 months after execution of the Interconnection Agreement Initial operation (first synchronization): 18 months after execution of the Interconnection Agreement Commercial operation date: 18 1/2 months after execution of the Interconnection Agreement These estimates of time for construction appear to have been shortened. Apparently the substation can be constructed by the fall of Stoneycreek Windpower (I04) Milestone Schedule July 1, 2005 Initial project energization September 30, 2005 Commercial operation date Keystone Wind Power (F04) Milestone Schedule Close Financing April 2005 Purchase of major equipment April/May 2005 Start of Construction May 2005 First Energization October 2005 Project Completion December 2005 Facility Study Result Work to be completed by Somerset REC Pride (Stonycreek) 115/34.5 kv Substation: The substation portion of work is to be completed by Somerset REC in accordance with RUS guidelines, the one-line diagrams, and the site plan. The following description, ratings and design criteria shall be used to build the substation. Description: The substation shall be construction as a double-end transformer substation consisting of 115 kv line breakers with provisions for a third 115 kv breaker tie position, 115 kv power transformers, 115 kv fault interrupters, 115 kv metering instrument transformers, and 115 kv power line carrier and relaying potential transformers. The Penelec Somerset Substation to Penelec Allegheny Substation 115 kv transmission line will be looped into and out of the substation by FirstEnergy. The 115 kv breaker positions shall be equipped with breaker disconnect and bypass switches. The substation shall be constructed utilizing galvanized structural steel. Installation of 115 kv fault interrupters and 34.5 kv transformer bus breakers shall provide a means of isolating the power transformers for emergencies, operation and maintenance activities.

4 All sources of generation will be connected to the 34.5 kv buses with circuit breakers. A 34.5 kv bus-tie breaker shall be installed. Somerset REC will take delivery from 34.5 kv Bus #2. A relay control house shall be provided to house the relay switchboards, SCADA RTUs, ac and dc panelboards, communications equipment, and 125 Vdc battery system. Ratings/Design Criteria: GSU Power Transformers: three phase units, 115 to 34.5 kv, rated 40/53/66//74 65 degrees C with LTC in 115 kv windings. 115 kv is 550 kv kv is 200 kv. Quantity: 2 Distribution Power Transformers: three phase units, 34.5 kv to 24.9 kv, rated 10/ degrees C kv is 200 kv BIL kv is 150 kv. Quantity: 2 (one spare) Capacitor banks: 34.5 kv, rating/type to be determined. Quantity: 2 Circuit breakers: 115 kv, 2000 A, 550 kv BIL, 40 ka interrupting, SF6 insulated, 4 sets of current transformers (two sets per bushing), Quantity: 2 (structure and switches provided for future 3 rd breaker) Circuit breakers: 34.5 kv, 2000 A, 200 kv BIL, 20 ka interrupting, Vacuum, Quantity: 3 (two bus breakers and one tie breaker) Circuit breakers: 34.5 kv, 1200 A, 200 kv BIL, 20 ka interrupting, Vacuum, Quantity: 6 Fault interrupters: 115 kv, 1200 A 550 kv BIL, 25 ka, Quantity: 2 Group disconnect switch: 115 kv, 1200 A, 550 BIL, 43.5 ka (3 sec), manually operated Group disconnect switch: 34.5 kv, 2000 A, 200 BIL, 100 ka, manually operated Group disconnect switch: 25 kv, 1200 A, 150 BIL, 61 ka, manually operated Disconnect switch: 34.5 kv, 2000 A, 200 BIL, 43.5 ka (3 sec), manually operated Disconnect switch: 34.5 kv, 1200 A, 200 BIL, 38 ka (3 sec), manually operated Disconnect switch: 25 kv, 1200 A, 150 BIL, 38 ka (3 sec), manually operated Regulator bypass: 25 kv, 1200 A, 150 kv BIL, 61 ka (mom.), manually operated Tandem disconnect switch: 25 kv, 1200 A, 150 BIL, 38 ka (3 sec), manually operated Reclosers: 34.5 kv, 560 A, 200 kv BIL, Quantity: 2 Recloser: 25 kv, 560 A, 150 kv BIL, Quantity: 2 Regulator: 333 kva, 25 kv, 150 kv BIL, Quantity: 3

5 CCVT: 115 kv, 550 kv BIL, Quantity: 2 Line trap: 2000 A, Quantity: 2 Protection Requirements: The attached one line diagrams provide details of the relay requirements for the Pride substation. The 115 kv high side of the substation will contain, at minimum, two 115kV circuit breakers, two 115 kv fault interrupters, two 115kV-34.5kV (wye grounded delta wye grounded) transformers, and 115 kv metering instrument transformers. Each 115 kv line exit shall be equipped with a line trap, capacitor voltage transformer, line tuner and carrier set. Minimum protective relaying requirements for this substation installation include primary and backup relays plus a breaker failure relay and an intertie relay. The 115kV breakers shall be purchased with four sets (12 total) of 2000:5 A MR C800 CTs. The 115 kv circuit breaker primary line relays shall be an SEL-321 and SEL-311B for directional ground and phase distance protection. SEL-352 breaker failure relays shall be utilized on the 115kV circuit breakers. The source for the breaker failure fault detector and line relays shall be CTs on the bus side of the 115kV circuit breakers. Any protective trip of this breaker shall initiate the failure to trip scheme. The intertie relay shall be an SEL-351, including 27, 59, 81, 67V and 67N elements. The source for the intertie relay shall be CTs on the 115 kv side of the kv transformers. The CT inputs shall be paralleled from both transformers. The transformer primary protective relay shall be an SEL-587. The transformer backup protective relay shall be an SEL-551 (backup, non-directional) or SEL-351 (backup, directional) digital relays for the transformer high side and the 51G function for the transformer low side. (Note: Directional relays used if required for relay coordination). The transformer primary and backup relaying trips through independent lockout relays. 115 kv bus protection shall be provided by two SEL-387 relays for redundant 115 kv bus protection with inputs from the line side of the two line breakers and the high side of each transformer. These relays shall trip both of the 115 kv line breakers and the 115 kv transformer fault interrupters and 34.5 kv bus circuit breakers kv bus protection shall be provided by two SEL-387 relays with inputs from the source side of the 34.5 kv bus breaker, from the 34.5 kv bus tie breaker, and from the rest of the 34.5 kv circuit breakers connected to that 34.5 kv bus. Each of these relays shall trip its associated 34.5 kv bus and 34.5 kv bus-tie breaker and all other bus-connected 34.5 kv breakers. All required relays shall be utility grade devices. The relaying system shall have a 125 Vdc battery system. Direct Transfer Trip Equipment:

6 Direct Transfer Trip over Class A leased telephone lines from both Somerset and Allegheny substations is to be acquired and maintained for Direct Transfer Trip communications. Receipt of DTT from FirstEnergy shall trip all generation connected to Pride substation. Loss of the DTT channel shall also trip generation connected to Pride substation. Special Relay Requirement: Since stability problems occur as a result of the loss of the Pride Somerset 115kV line for fault clearing, it is, therefore, recommended that the I04 project generators shall be tripped without intentional time delay whenever the Pride Somerset 115kV line becomes unavailable, and should not be reconnected to the 115 kv system till the line is back in service. Metering Requirements: Revenue metering is to be measured by 115 kv instrument transformers installed on the high voltage side of the kv transformers located within 115 kv bus differential zone between the 115 kv fault interrupters and 115/34.5 kv transformers. Metering shall also be provided between each of the 34.5 kv breaker and the 34.5 kv interconnection lines for the generation feeders and between the 34.5 kv breaker and REC s 34.5/24.9 kv transformers. SCADA Requirements: Monitoring should be provided via a SCADA RTU for the 34.5 kv breakers on the generation feeders. Pride (Stonycreek) 115/34.5 kv Substation cost estimate: The estimated cost of the substation is $2.52 million. Work to be done by FirstEnergy Design Criteria Facilities owned and operated by FirstEnergy shall comply with the FirstEnergy Requirements for Transmission Connected Facilities. The FE 115 kv system design shall be based upon the following criteria: General Design Requirements System frequency: 60 hertz Elevation, AMSL: 2254 feet Isokeraunic level: 40 Maximum ambient temperature: 40 degrees C Minimum ambient temperature: -40 degrees C Maximum conductor operating temperature: 100 degrees C Wind Loading (round shapes): 25 psf Ice loading Substations (no wind): 1 inch

7 Seismic zone: Per ASCE 7-98, per Fig (a) and (b). Equipment qualification per IEEE Voltage and Current Ratings Nominal phase-to-phase: 115 kv Maximum phase-to-phase: 121 kv Basic impulse level (BIL): 550 kv Maximum continuous current carrying capacity: 2000 A Design fault current: 40 ka Maximum fault clearing time: 15 cycles Clearances and Spacing Recommended rigid bus center-to-center phase spacing: 84 Minimum phase-to-phase, metal-to-metal distance: 53 Recommended phase-to-ground: 45 Minimum phase-to-ground: 42 Minimum vertical clearance from live parts to grade: 11-7 Minimum horizontal clearance from live parts: 6-1 Minimum conductor clearance above roads in switchyard: 20-2 Minimum bottom of insulator to top of foundation: 8-6 Transmission Lines New/Upgraded 1. Allegheny Somerset 115 kv Line Design, furnish and install a loop (in/out) tap to the new Pride (a.k.a. Stonycreek) Substation. The estimate assumes the substation will be located at the base of an existing transmission line structure. The estimated cost for this work is $70,000 and could be completed in 8 months (6 months for engineering and permitting, 3 months for material and 2 months for construction). Permitting may be required with the PaPUC. Substations New/Upgraded 1. Pride (a.k.a. Stonycreek) Substation. Provide design review and interconnection coordination (transmission line, interconnection metering and SCADA) of the Somerset REC designed and constructed substation. Provide design review and interconnection coordination (interconnection metering and SCADA) for the FE required telemetry of the wind turbine 34.5 kv connections at the Somerset REC substation. The costs of the activities associated with the FE-REC delivery point are assumed to be outside the scope of the PJM interconnection. The estimated cost for the FirstEnergy activities

8 associated with the wind turbine interconnection is $13,000 and would be completed to support the REC s schedule. 2. Allegheny Substation Design, furnish and install the following additions and modifications at the Allegheny 115 kv Substation: New control and relaying on the present Somerset 115 kv line associated with the addition of the new Pride (a.k.a. Stonycreek) Substation. The existing Somerset 115kV exit shall become the new Pride 115kV exit. New line relaying and carrier equipment is required for this exit. A new wave trap and tuning equipment is also required. The existing circuit breaker and line CCPD shall be used. A Direct Transfer Trip (DTT) transmitter is to be installed and DTT is to be keyed to Pride substation for any protective trip of the Pride exit at Allegheny, for a breaker open condition or for a BFT operation on the Allegheny 115kV bus. The estimated cost for this work is $180,000 and could be completed in 8 months (6 months for engineering, 3 months for material and 2 months for construction). There should be no permitting requirements.

9 3. Somerset Substation Design, furnish and install the following additions and modifications at the Allegheny 115 kv Substation: New control and relaying on the present Somerset 115 kv line associated with the addition of the new Pride (a.k.a. Stonycreek) Substation. The existing Allegheny 115kV exit shall become the new Pride 115kV exit. New line relaying and carrier equipment is required for this exit. The existing circuit breaker and line CCPD shall be used. A Direct Transfer Trip (DTT) transmitter is to be installed and DTT is to be keyed to Pride substation for any protective trip of the Pride exit at Somerset, for a breaker open condition or for a BFT operation on the Somerset #1 115kV bus. The estimated cost for this work is $155,000 and could be completed in 8 months (6 months for engineering, 3months for material and 2 months for construction). There should be no permitting requirements. Summary Results of the Study FE can meet the Somerset REC schedule of in-service 18 months after a CSA is signed. A cost summary in 2004 dollars and excluding taxes or CIAC is: 115 kv Transmission Line Tap $70,000 Allegheny Substation Modifications $180,000 Somerset Substation Modifications $155,000 Wind Turbine Interconnection Activity $13,000 Total $418,000 A proposed milestone schedule for this work based upon months from a signed CSA is: Qualifiers Activity Start Month End Month Detailed Engineering 0 6 Equipment Procurement Delivery 3 5 Construction 7 8 Testing & Commissioning 8 8 The accomplishment of the work on the FirstEnergy system to support the costs and schedule is dependent on the following:

10 The developer/somerset REC providing dedicated communication circuits for direct transfer trip relaying from FE s Allegheny and Somerset Substations, for SCADA communication to the transmission system control center, and for dialup access to revenue metering. Obtaining approval from PJM for the necessary outages. No equipment delivery, environmental or regulatory delays. No contractor problems. No force majeure. Interconnection Service Agreement Information The following table summarizes the total costs according to FERC criteria. The costs are in 2004 dollars and do not include taxes or CIAC. Network Facilities Direct Charges Labor $76,900 Direct Charges Material $153,000 Indirect Charges Labor $113,000 Indirect Charges Material $30,300 Return (12%) $44,800 Total $418,000

11 ATTACHMENTS Somerset REC Pride Substation One-Line and Protective Relay Diagram

12

13

Generation Interconnection Facilities Study Report. For. PJM Generation Interconnection Request Queue Position R11. South River

Generation Interconnection Facilities Study Report. For. PJM Generation Interconnection Request Queue Position R11. South River Generation Interconnection Facilities Study Report For PJM Generation Interconnection Request Queue Position R11 South River May 2012 Transmission Owner Facilities Study Summary Description of Project

More information

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114. Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position X1-114 Sandyston January 2012 Preface The intent of the System Impact Study is to determine

More information

Hyperlinks are Inactive

Hyperlinks are Inactive Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F TABLE OF CONTENTS Appendix F - Electrical Engineering Design Criteria F.1 Introduction...F-1 F.2 Codes and Standards...F-1 F.3 Switchyard and Transformers...F-1

More information

QUESTIONS and ANSWERS RFB 745-15-9894, Metal Clad Switchgear and Power Control Room

QUESTIONS and ANSWERS RFB 745-15-9894, Metal Clad Switchgear and Power Control Room QUESTIONS and ANSWERS RFB 745-15-9894, Metal Clad Switchgear and Power Control Room 1) When you click on the UTHSCSA Drawing the site takes you to the E-1 drawing no other. Will there be other drawings

More information

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055 Generation Interconnection Feasibility Study Report-Web Version For PJM Generation Interconnection Request Queue Position Z1-055 South Bend Generation Project March 2014 PJM Interconnection 2014. All rights

More information

SPECIFICATION COG-2007

SPECIFICATION COG-2007 Cleco Power LLC SPECIFICATION COG-2007 FOR PARALLEL OPPERATION OF CUSTOMER-OWNED GENERATION ON CLECO S ELECTRICAL SYSTEM Revised: March 7, 2014 CONTENTS ITEM NO. TITLE PAGE NO. 1.0 Scope 3 2.0 Policy On

More information

INTRODUCTION TO SYSTEM PROTECTION. Hands-On Relay School 2012

INTRODUCTION TO SYSTEM PROTECTION. Hands-On Relay School 2012 INTRODUCTION TO SYSTEM PROTECTION Hands-On Relay School 2012 CONGRATULATIONS On choosing the field of system protection. It is an exciting, challenging profession. System protection has changed considerably

More information

Transmission Protection Overview

Transmission Protection Overview Transmission Protection Overview 2012 Hands-On Relay School Brian Smyth Schweitzer Engineering Laboratories Pullman, WA Transmission Line Protection Objective General knowledge and familiarity with transmission

More information

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Course No: E02-010 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education

More information

2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1. 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std.

2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1. 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std. 2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std. Relays) Part 1 General 1.1 CONDITIONS AND REQUIREMENTS: A. Refer to

More information

AORC Technical meeting 2014

AORC Technical meeting 2014 AORC Technical meeting 2014 http : //www.cigre.org C4-1012 Alarm System Improvement in the Northern Region Dispatching Center of Thailand Mr. Manu PONGKAEW, Mr. Phathom TIPSUWAN Electricity Generating

More information

LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems

LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems A. General This Net Metering Standard for Customer-Owned Grid Connected Electric Generating Systems sets forth the

More information

Submit shop drawings for equipment provided under this section Shop drawings shall indicate:

Submit shop drawings for equipment provided under this section Shop drawings shall indicate: Section 16435 - SWITCHBOARDS Introduction Part 1 - General Reference The work under this section is subject to requirements of the Contract Documents including the General Conditions, Supplementary Conditions,

More information

PG&E Transmission Interconnection Handbook. Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

PG&E Transmission Interconnection Handbook. Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES PURPOSE This section provides substation design information for Load Entities interconnected at transmission voltage

More information

David Payne, P.E. Associate Director February 18, 2014

David Payne, P.E. Associate Director February 18, 2014 David Payne, P.E. Associate Director February 18, 2014 Overview of Texas A&M University State's first public institution of higher education, was opened on Oct. 4, 1876 as the Agricultural and Mechanical

More information

ECE 586b Course Project Report. Auto-Reclosing

ECE 586b Course Project Report. Auto-Reclosing ECE 586b Course Project Report Auto-Reclosing Srichand Injeti May 5, 2008 Department Of Electrical and computer Engineering University Of Western Ontario, London Ontario Table of contents 1. Introduction...1

More information

TERMS AND CONDITIONS

TERMS AND CONDITIONS Virginia Electric and Power Company TERMS AND CONDITIONS XXIV. GENERATOR INTERCONNECTION STANDARD Electric generator interconnection service includes only the ability to interconnect an electric generator

More information

6. The estimated costs here do not include any applicable ITCC tax

6. The estimated costs here do not include any applicable ITCC tax General Notes and Clarifications: 1. The following estimated costs are based on past experiences and are intended to provide an order of magnitude of the total project cost given the major system components.

More information

Variable Frequency Drives - a Comparison of VSI versus LCI Systems

Variable Frequency Drives - a Comparison of VSI versus LCI Systems Variable Frequency Drives - a Comparison of VSI versus LCI Systems Introduction TMEIC is a leader in the innovative design and manufacture of large ac variable f requency drive systems. TMEIC has been

More information

THE COMMISSIONING PROCESS FOR NEW SUBSTATION EQUIPMENT & PROTECTION SCHEMES ON THE BULK ELECTRIC SYSTEM. Lawrence P. Hayes FirstEnergy Corp.

THE COMMISSIONING PROCESS FOR NEW SUBSTATION EQUIPMENT & PROTECTION SCHEMES ON THE BULK ELECTRIC SYSTEM. Lawrence P. Hayes FirstEnergy Corp. THE COMMISSIONING PROCESS FOR NEW SUBSTATION EQUIPMENT & PROTECTION SCHEMES ON THE BULK ELECTRIC SYSTEM Lawrence P. Hayes FirstEnergy Corp. ABSTRACT This paper discusses the various aspects, considerations,

More information

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003 F R C C FRCC Standards Handbook FRCC Automatic Underfrequency Load Shedding Program Revision Date: July 2003 FRCC Underfrequency Load Shedding Program Modification and Approval Process Requests to modify

More information

January 23, 2015. Minimum Design Standards Task Force

January 23, 2015. Minimum Design Standards Task Force Minimum Transmission Design Standards for Competitive January 23, 2015 Minimum Design Standards Task Force Revision History Date or Version Number 12/17/2014 Revision IR 1/23/2015 Revision 1 Author Change

More information

Teleprotection Schemes and Equipment. James W. Ebrecht Young Power Equipment Scottsdale, AZ

Teleprotection Schemes and Equipment. James W. Ebrecht Young Power Equipment Scottsdale, AZ * Teleprotection Schemes and Equipment James W. Ebrecht Young Power Equipment Scottsdale, AZ Teleprotection Schemes And Equipment ~ ~ Relay Relay Teleprotection Communications channel Teleprotection Protection

More information

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz)

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz) 24 1. NETWORK CONFIGURATIONS definition Standard IEC 38 defines voltage ratings as follows: - Low voltage () For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690

More information

ANCILLARY EQUIPMENT AND ELECTRICAL EQUIPMENT Power Supply Systems and Electrical Equipment for Desalination Plants - Y.M. Hamud and A.H.

ANCILLARY EQUIPMENT AND ELECTRICAL EQUIPMENT Power Supply Systems and Electrical Equipment for Desalination Plants - Y.M. Hamud and A.H. POWER SUPPLY SYSTEMS AND ELECTRICAL EQUIPMENT FOR DESALINATION PLANTS Y.M. Hamud and A.H. Anwar Abu Dhabi Water and Electricity Authority, Abu Dhabi, UAE Keywords : Electrical System, Network for Desalination,

More information

How To Choose A Transformer

How To Choose A Transformer Consider open loop MV network as an example source 1 source 2 NC NC NC or NO main MV switchboard A B Detail design of substation NC NC NC NO NC NC switchboard 1 switchboard 2 switchboard 3 MV MV MV LV

More information

Secondary Unit Substations

Secondary Unit Substations 14 SWITCHGEAR Secondary Unit Substations Overview Siemens offers a wide variety of unit substation designs to meet customer requirements. A unit substation consists of one or more transformers mechanically

More information

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering Title 20 PUBLIC SERVICE COMMISSION Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES Chapter 02 Engineering Authority: Public Utility Companies Article, 2-121, 5-101 and 5-303, Annotated Code of Maryland.

More information

Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process

Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process Presented by: Marianne Mannschreck Date: Welcome A Look at the Net Energy Metering

More information

Power Plant Electrical Distribution Systems

Power Plant Electrical Distribution Systems PDH Course E184 Power Plant Electrical Distribution Systems Gary W Castleberry, PE 2008 PDH Center 2410 Dakota Lakes Drive Herndon, VA 20171-2995 Phone: 703-478-6833 Fax: 703-481-9535 www.pdhcenter.com

More information

PA PUC AERS & Metropolitan Edison Company Site Visit

PA PUC AERS & Metropolitan Edison Company Site Visit PA PUC AERS & Metropolitan Edison Company Site Visit October 26, 2010 Scott Lowry Director-Operation Services, Met-Ed Andrew Zulkosky Manager-Engineering, Met-Ed Curt Christenson Manager-York Customer

More information

Customer Substation Manual 08/05/02

Customer Substation Manual 08/05/02 Customer Substation Manual Table of Contents Section Page 2 of 85 Description 0 Preface 010.00 General 010.10 Information Required for the Review of New Customer Substations 010.20 New Customer Substation

More information

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation Basis of Design This section applies to the design relating to low voltage switchboards. Design Criteria UW Class N1 facilities main switchboards shall be rear accessible. The main, tie and feeder breakers

More information

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD HOLLAND CLIFF HEWITT ROAD 230 KV TRANSMISSION LINE PROJECT ELECTRIC ALTERNATIVE EVALUATION STUDY BLACK & VEATCH CORPORATION B&V Project 146026(G)

More information

Step Voltage Regulators

Step Voltage Regulators Step Voltage Regulators Don Wareham Field Application Engineer Today s Agenda Introduction Voltage Regulator theory Voltage Regulator application considerations Installation and proper bypassing Wrap-up/questions

More information

PSEG-LONG ISLAND SMART GRID SMALL GENERATOR INTERCONNECTION SCREENING CRITERIA FOR OPERATING IN PARALLEL WITH LIPA S DISTRIBUTION SYSTEM

PSEG-LONG ISLAND SMART GRID SMALL GENERATOR INTERCONNECTION SCREENING CRITERIA FOR OPERATING IN PARALLEL WITH LIPA S DISTRIBUTION SYSTEM PSEG-LONG ISLAND SMART GRID SMALL GENERATOR INTERCONNECTION SCREENING CRITERIA FOR OPERATING IN PARALLEL WITH LIPA S DISTRIBUTION SYSTEM PSEG-LI SGSGIP DG Screening Criteria 5-29-14 Table of Contents I.

More information

SWITCH YARD OPERATION IN THERMAL POWER PLANT(KaTPP Jhalawar Rajasthan)

SWITCH YARD OPERATION IN THERMAL POWER PLANT(KaTPP Jhalawar Rajasthan) From the SelectedWorks of Radhey Shyam Meena Winter July 12, 2012 SWITCH YARD OPERATION IN THERMAL POWER PLANT(KaTPP Jhalawar Rajasthan) RADHEY SHYAM MEENA, Er. Available at: http://works.bepress.com/radhey_meena/5/

More information

How the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse

How the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse How the National Grid System Operates Chris Gorman Lead Account Executive Syracuse 2 Parts of the Electric System Parts of the Electric System 1. Generating Station: Produces Electricity. 2. Transmission

More information

Effective: September 10, 2006 Vermont Attachment 1 to Rule 5.500 Public Service Board Page 1 of 6

Effective: September 10, 2006 Vermont Attachment 1 to Rule 5.500 Public Service Board Page 1 of 6 Public Service Board Page 1 of 6 STANDARD APPLICATION FOR INTERCONNECTION OF GENERATION RESOURCES IN PARALLEL TO THE ELECTRIC SYSTEM OF: (Interconnecting Utility) Preamble and Instructions: An owner of

More information

Rule 5.500 Fast Track Analysis for National Life Insurance Co.

Rule 5.500 Fast Track Analysis for National Life Insurance Co. Rule 5.500 Fast Track Analysis for National Life Insurance Co. For a 500 kw Solar array to be located at 155 Northfield Street in Montpelier, Vermont Green Mountain Power Pam Allen Date: 5/31/13 SECTION

More information

Engineering innovation

Engineering innovation Eaton's Electrical Engineering Services & Systems Solutions Focus Seamless Solutions for Reliable, Efficient and Safe Power Systems Engineering innovation Progressive solutions for today s power systems

More information

FIT TIER 2 Application

FIT TIER 2 Application FIT TIER 2 Application Application Information The below information Auto-Fills from your registration information: Building Permit Application Date: Project Completion Date: Name: Address: City: State:

More information

Digital Energy ITI. Instrument Transformer Basic Technical Information and Application

Digital Energy ITI. Instrument Transformer Basic Technical Information and Application g Digital Energy ITI Instrument Transformer Basic Technical Information and Application Table of Contents DEFINITIONS AND FUNCTIONS CONSTRUCTION FEATURES MAGNETIC CIRCUITS RATING AND RATIO CURRENT TRANSFORMER

More information

Primary and Secondary Electrical Distribution Systems

Primary and Secondary Electrical Distribution Systems Primary and Secondary Electrical Distribution Systems Critical Facilities Round Table 12th Quarterly Membership Meeting June 2, 2006 David D. Roybal. P.E. Eaton Electrical Cutler-Hammer Products Utility

More information

Power Voltage Transformers for Air Insulated Substations. THE PROVEN POWER.

Power Voltage Transformers for Air Insulated Substations. THE PROVEN POWER. Power Voltage Transformers for Air Insulated Substations THE PROVEN POWER. Introduction Trench Power Voltage Transformers (Power VTs) combine the attributes of an inductive voltage transformer with the

More information

TRANSMISSION AND SUBSTATION PROJECTS

TRANSMISSION AND SUBSTATION PROJECTS TRANSMISSION AND SUBSTATION PROJECTS OPERATING COMPANY: EMI CUSTOMER: WARREN POWER, LLC EJO # MS0010 SCOPE DOCUMENT FOR 340 MW, IPP PROJECT at VICKSBURG, MS WITH INTERCONNECTION AT BAXTER WILSON 500kV

More information

Dead Tank Circuit Breaker 72PM40-C Proven reliability through common platforms

Dead Tank Circuit Breaker 72PM40-C Proven reliability through common platforms Dead Tank Circuit Breaker 72PM40-C Proven reliability through common platforms ABB innovations for changing demands ABB (www.abb.com) is a leader in power and automation technologies that enables utility

More information

Colorado Springs Utilities Interconnection Guidelines For Transmission to Transmission Interconnections Version 1 12/04/2007

Colorado Springs Utilities Interconnection Guidelines For Transmission to Transmission Interconnections Version 1 12/04/2007 Colorado Springs Utilities Interconnection Guidelines For Transmission to Transmission Interconnections Version 1 12/04/2007 I.INTRODUCTION AND GENERAL POLICY 5 A. INTRODUCTION...5 B. THE COLORADO SPRINGS

More information

Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP

Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP Grid Interconnection & Contract Development Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP Submittal Instructions Prior to submitting your application and

More information

SWITCHGEAR SOLUTIONS FOR MISSION CRITICAL APPLICATIONS. Presented by SAI Advanced Power Solutions

SWITCHGEAR SOLUTIONS FOR MISSION CRITICAL APPLICATIONS. Presented by SAI Advanced Power Solutions SWITCHGEAR SOLUTIONS FOR MISSION CRITICAL APPLICATIONS POWER DISTRIBUTION RACKS IN A MISSION CRITICAL SYSTEM MODULES IN A MISSION CRITICAL SYSTEM UPS Convertor Main Inverter Load Battery BPC UPS & BATTERY

More information

100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center. 598 N. Buth Rd 3215 Arrowhead Rd

100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center. 598 N. Buth Rd 3215 Arrowhead Rd 100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center Introduction Roger Hedding Steven Schoenherr, P.E. ABB Inc. Minnesota Power 598 N. Buth Rd 3215 Arrowhead Rd Dousman,

More information

26 3213.13 Diesel Engine Driven Generators Page 1 of 6

26 3213.13 Diesel Engine Driven Generators Page 1 of 6 Last Update: December 8, 2014 A. Description of System Consultant s Handbook Page 1 of 6 1. Provide a diesel engine driven electric generating unit, factory assembled, tested and certified to operate at

More information

Discussion on Class I & II Terminology. IEEE PES Transformers Committee Fall Meeting 2011 Boston, MA

Discussion on Class I & II Terminology. IEEE PES Transformers Committee Fall Meeting 2011 Boston, MA Discussion on Class I & II Terminology IEEE PES Transformers Committee Fall Meeting 2011 Boston, MA What is Class I & II? C57.12.00 2010 is the only document we have that defined these terms. 5.10 Insulation

More information

Unified requirements for systems with voltages above 1 kv up to 15 kv

Unified requirements for systems with voltages above 1 kv up to 15 kv (1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements apply to

More information

Design of electrical power system for a 1000MW nuclear power generating station

Design of electrical power system for a 1000MW nuclear power generating station Design of electrical power system for a 1000MW nuclear power generating station K Raja, K Yesunadam Dept. of Electrical & Electronics Engineering, Lingaya s Institute of Management & Technology, Vijayawada,

More information

Achieving Operational Efficiencies through On-Line Substation Monitoring. Vince Polsoni Powerstream Inc. Manager Station Sustainment EDIST 2016

Achieving Operational Efficiencies through On-Line Substation Monitoring. Vince Polsoni Powerstream Inc. Manager Station Sustainment EDIST 2016 Achieving Operational Efficiencies through On-Line Substation Monitoring Vince Polsoni Powerstream Inc. Manager Station Sustainment EDIST 2016 1 Agenda Maintenance Monitoring Equipment CMMS Data Historian

More information

-1- PSEG-LI Update of LIPA SGIP Full Docw-NYISO reqmts above 10 MW 10-27-14

-1- PSEG-LI Update of LIPA SGIP Full Docw-NYISO reqmts above 10 MW 10-27-14 PSEG-Long Island Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA s Radial Distribution Systems -1- PSEG-LI Update of LIPA

More information

N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS

N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS 14:8-4.1 Scope This subchapter sets forth net metering requirements that apply to electric power suppliers, basic generation service providers

More information

Part 1 System Modeling & Studies for Existing Systems

Part 1 System Modeling & Studies for Existing Systems Part 1 System Modeling & Studies for Existing Systems Operation Technology, Inc. Copyright 2009 Result of rapid release of energy due to an arcing fault between two conductors. Bus voltages > 208V Temperatures

More information

261000 Medium Voltage Electrical Distribution

261000 Medium Voltage Electrical Distribution Sections Included In This Standard: 1.1 General 1.2 Underground Cable 1.3 Medium Voltage Switches 1.4 Transformers 1.5 Electrical Manholes 1.6 Switch Vaults 1.7 Distribution Switchgear/Switchboards This

More information

How To Get A Power Line Extension

How To Get A Power Line Extension GUIDELINES FOR COMMERCIAL ELECTRIC SERVICE HOOKUP 1 Steps to Commercial Service Pay the Design Deposit Commercial Buildings: Up to 1, sq ft = $1,. 1, 5, sq ft = $2,. Over 5, sq ft = $3,. Commercial jobs

More information

AUSTIN ENERGY INTERCONNECTION GUIDE FOR CUSTOMER-OWNED POWER PRODUCTION FOR FACILITIES UP TO 10MW A INTERCONNECTION CLASSIFICATIONS...

AUSTIN ENERGY INTERCONNECTION GUIDE FOR CUSTOMER-OWNED POWER PRODUCTION FOR FACILITIES UP TO 10MW A INTERCONNECTION CLASSIFICATIONS... AUSTIN ENERGY INTERCONNECTION GUIDE FOR CUSTOMER-OWNED POWER PRODUCTION FOR FACILITIES UP TO 10MW TABLE OF CONTENTS PAGE INTRODUCTION... 4 A INTERCONNECTION CLASSIFICATIONS... 5 B. APPLICATION PROCESS

More information

Design Criteria Additions Related To PJM IPP R02 project

Design Criteria Additions Related To PJM IPP R02 project Design Criteria Additions Related To PJM IPP R02 project GENERAL DESCRIPTION OF THE PPL ELECTRIC UTILTIES 500 KV SYSTEM Existing System: This document describes the design details of the EXISTING 500 kv

More information

ABB PSPS Erich Steinmann; Generator control-2013

ABB PSPS Erich Steinmann; Generator control-2013 ABB PSPS Erich Steinmann; Generator control-2013 GENERATOR CONTROL THE MODULAR SOLUTION FOR GENERATORS To make sure that power is efficiently converted into electric energy, it is necessary to supervise

More information

Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems

Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems This Agreement is made and entered into this day of, 20, ( Effective Date ) by and between the Orlando Utilities Commission

More information

Distributed Generation and the Impact on a Distribution System. Brian Lassiter Technical Sales Engineer

Distributed Generation and the Impact on a Distribution System. Brian Lassiter Technical Sales Engineer Distributed Generation and the Impact on a Distribution System Brian Lassiter Technical Sales Engineer Company Overview Founded in 1989 in Abilene, TX Industry leader in Engineering and Operations Utility

More information

Power products and systems. Intelligent solutions for power distribution Zone concept

Power products and systems. Intelligent solutions for power distribution Zone concept Power products and systems Intelligent solutions for power distribution Zone concept Securing continuous power supply ABB is one of the world's leading power and automation technology companies whose products,

More information

TABLE OF CONTENTS 1.0 INTRODUCTION... 2 1.1 PURPOSE... 2 1.2 DEVIATION... 2 4.0 INTERTIE PROTECTION REQUIREMENTS... 4

TABLE OF CONTENTS 1.0 INTRODUCTION... 2 1.1 PURPOSE... 2 1.2 DEVIATION... 2 4.0 INTERTIE PROTECTION REQUIREMENTS... 4 Page: 1 of 14 KEY BULLETIN POINTS: THIS GUIDE OUTLINES MINIMUM REQUIREMENTS FOR CONNECTION OF CUSTOMER-OWNED EMERGENCY AND STANDBY (ESG) TO THE GEORGIA POWER COMPANY (GPC) DISTRIBUTION SYSTEM. THESE ARE

More information

CONSULTATION PAPER FOR PROPOSED MODIFICATIONS TO THE TRANSMISSION CODE

CONSULTATION PAPER FOR PROPOSED MODIFICATIONS TO THE TRANSMISSION CODE CONSULTATION PAPER FOR PROPOSED MODIFICATIONS TO THE TRANSMISSION CODE Closing date for submission of representations: 30 th Sep 2014, 5 pm 18 AUG 2014 ENERGY MARKET AUTHORITY 991G Alexandra Road #01-29

More information

PRODUCT GUIDE. SL Medium Voltage IEC Vacuum Contactors

PRODUCT GUIDE. SL Medium Voltage IEC Vacuum Contactors PRODUCT GUIDE SL Medium Voltage IEC Vacuum Contactors Table of Contents 1 Overview Introduction....................................................2 Features........................................................2

More information

Lightning Arresters P30027 18 KVA P30038 10 KVA. Description & Installation

Lightning Arresters P30027 18 KVA P30038 10 KVA. Description & Installation Lightning Arresters P30027 18 KVA P30038 10 KVA Description & Installation Printed in USA 09/11 TO330 Rev. B Table of Contents Page 1.0 SCOPE 2 2.0 PRODUCT OVERVIEW 2 2.1 Intended Uses 2 2.2 Lightning

More information

Type SA-1 Generator Differential Relay

Type SA-1 Generator Differential Relay ABB Automation Inc. Substation Automation and Protection Division Coral Springs, FL 33065 Instruction Leaflet 41-348.11C Effective: November 1999 Supersedes I.L. 41-348.11B, Dated August 1986 ( ) Denotes

More information

Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva

Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva Issued: August 2009 SIZED UP TO 100 KVA TABLE OF CONTENTS 1.0 Introduction... 1 1.1 Applicability... 1 1.2 Definitions...

More information

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS Meher Capacitors offers reliable and innovative products and solutions in the fields of Reactive Power Compensation, Power Quality and Energy

More information

RELIABILITY PLANNING CRITERIA

RELIABILITY PLANNING CRITERIA RELIABILITY PLANNING CRITERIA Version 4.0 01/20/2016 Date Rev. No. Individual Making Edits REVISION HISTORY Reason / Comments 07/01/2013 1 J. Johnson Initial document 06/06/2014 2 R. Chapman Document review;

More information

4.1.1 Generator Owner 4.1.2 Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner 4.1.2 Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

Federal Wage System Job Grading Standards for Electric Power Controlling, 5407. Table of Contents

Federal Wage System Job Grading Standards for Electric Power Controlling, 5407. Table of Contents Federal Wage System Job Grading Standards for Electric Power Controlling, 5407 Table of Contents WORK COVERED... 2 WORK NOT COVERED...2 TITLES... 2 GRADE LEVELS... 2 SPECIAL ADDITIONAL RESPONSIBILITIES...

More information

Appendix F: TELEMETERING AND TRANSFER TRIP FOR TRANSMISSION GENERATION ENTITIES

Appendix F: TELEMETERING AND TRANSFER TRIP FOR TRANSMISSION GENERATION ENTITIES Appendix F: TELEMETERING AND TRANSFER TRIP FOR TRANSMISSION GENERATION ENTITIES Table of Contents APPENDIX F: TELEMETERING AND TRANSFER TRIP FOR TRANSMISSION GENERATION ENTITIES... 1 F.0. NOTIFICATION...

More information

Addendum #2 Contract UK-11-13

Addendum #2 Contract UK-11-13 Addendum #2 Contract UK-11-13 Utilities Kingston Purchase and Replacement of Switchgear at Kingston Hydro Substation MS11 March 25, 2011 Delivered to: All RFP recipients Total number of pages: Nine (9)

More information

3. TYPES OF SERVICE AVAILABLE. 3.1 Scope

3. TYPES OF SERVICE AVAILABLE. 3.1 Scope 3. TYPES OF SERVICE AVAILABLE 3.1 Scope UI supplies 60 hertz, alternating current with different voltage and ampere ratings. Not all voltage and ampere ratings are available throughout the entire service

More information

Technical Specification Of Substation Protection & Control System with IEC 61850 BHEL s Perspective

Technical Specification Of Substation Protection & Control System with IEC 61850 BHEL s Perspective Technical Specification Of Substation Protection & Control System with IEC 61850 BHEL s Perspective India Core Events 2008 September 24 th 2008 1 Background Stability & Reliability Data Storage Communication

More information

SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL

SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL 1.1 SUMMARY A. This section describes the requirements for the installation of Power Monitors and associated

More information

OVR-3SP Recloser with PCD Control Style Guide 1VAL263901-SG March 30, 2009 Revision B

OVR-3SP Recloser with PCD Control Style Guide 1VAL263901-SG March 30, 2009 Revision B OVR-3SP Recloser with PCD Control Style Guide 1VAL263901-SG March 30, 2009 Revision B The OVR-3SP three-phase recloser style guide aids in the proper selection of your OVR-3SP style number. The OVR-3SP

More information

AMFA-27 AMFA-29. Operator s Manual & Installation Instructions. Rev. 2.5

AMFA-27 AMFA-29. Operator s Manual & Installation Instructions. Rev. 2.5 AMFA-27 AMFA-29 Operator s Manual & Installation Instructions Rev. 2.5 Date: 17 July, 2010 Permanently-connected, utility Interactive, single-phase, inverters Model AMFA-27 WIND TURBINE INVERTER (240 VAC

More information

Table of Contents. TransformerIQ FAQs 1

Table of Contents. TransformerIQ FAQs 1 [12/12] FAQs Table of Contents FAQ 1. What size transformer will TransformerIQ monitor?... 2 FAQ 2. Are there different TransformerIQ versions?... 2 FAQ 3. How are the units powered?... 2 FAQ 4. What is

More information

TA Kahraman Yumak ELK412 - Distribution of Electrical Energy Lab. Notes v1.0 2013 Spring web.itu.edu.tr/yumakk. Distance Protection

TA Kahraman Yumak ELK412 - Distribution of Electrical Energy Lab. Notes v1.0 2013 Spring web.itu.edu.tr/yumakk. Distance Protection Distance Protection Announcement: You are not supposed to prepare a pre-report. But there will be an oral examination, so you are strongly advised to study this note regarding to the pre-study questions

More information

Guidelines for Generation, Tie-Line, and Substation Interconnections

Guidelines for Generation, Tie-Line, and Substation Interconnections Guidelines for Generation, Tie-Line, and Substation Interconnections Otter Tail Power Company compiled this document with input from others. Otter Tail Power Company gratefully acknowledges permission

More information

OVR Three-Phase Recloser and PCD Control Style Guide 1VAL264001-SG October 13, 2009 Revision F

OVR Three-Phase Recloser and PCD Control Style Guide 1VAL264001-SG October 13, 2009 Revision F OVR Three-Phase Recloser and PCD Control Style Guide 1VAL264001-SG October 13, 2009 Revision F The OVR three-phase recloser style guide aids in the proper selection of your OVR three-phase style number.

More information

Advanced Protection of Distribution Networks with Distributed Generators

Advanced Protection of Distribution Networks with Distributed Generators Date:- 8 10 March 2011 Venue: University of Manchester EES-UETP Course title Advanced Protection of Distribution Networks with Distributed Generators Peter Crossley Director of the Joule Centre School

More information

NFPA 70E 2012 Rolls Out New Electrical Safety Requirements Affecting Data Centers

NFPA 70E 2012 Rolls Out New Electrical Safety Requirements Affecting Data Centers NFPA 70E 2012 Rolls Out New Electrical Safety Requirements Affecting Data Centers A market position paper from the experts in Business-Critical Continuity TM Executive Summary Electrocutions are the fourth

More information

Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System

Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System Prepared By: Transmission Planning Unit Baltimore Gas & Electric Company Table of Contents 1. INTRODUCTION

More information

16 West Coast Regional Plan

16 West Coast Regional Plan 16 West Coast Regional Plan 16.1 Regional overview 16.2 West Coast transmission system 16.3 West Coast demand 16.4 West Coast generation 16.5 West Coast significant maintenance work 16.6 Future West Coast

More information

Interconnection of Generators to EDI s Distribution System

Interconnection of Generators to EDI s Distribution System Interconnection of Generators to EDI s Distribution System May 22, 2002 This document sets forth the guidelines for connecting a power producing facility to the Alberta Interconnected Electric System through

More information

Customer Low-Voltage Switchboards Service Cable Terminal Compartment Arrangements and Clearances

Customer Low-Voltage Switchboards Service Cable Terminal Compartment Arrangements and Clearances Page 50 of 100 Customer Low-Voltage Switchboards Service Cable Terminal Compartment Arrangements and Clearances (Replaces A-190556) THIS CUSTOMER REFERENCE SPECIFICATION (CRS) IS PART OF THE RULES FOR

More information

SOLARCARE SERIES PRODUCT AND APPLICATION GUIDE

SOLARCARE SERIES PRODUCT AND APPLICATION GUIDE SOLARCARE SERIES PRODUCT AND APPLICATION GUIDE for solar energy management LEATEC Delivering Solutions for Energy Management SOLAR ENERGY DATA CENTER BUILDING 4 to8 String Monitoring with 0.% Accuracy

More information

2012 San Francisco Colloquium

2012 San Francisco Colloquium 2012 San Francisco Colloquium http : //www.cigre.org HVDC and Power Electronic Systems for Overhead Line and Insulated Cable Applications B4-8 Trans Bay Cable A Breakthrough of VSC Multilevel Converters

More information

Minimizing Impact of Electric Utility Outages with Backup Generation

Minimizing Impact of Electric Utility Outages with Backup Generation Minimizing Impact of Electric Utility Outages with Backup Generation Introduction of the Speaker Michael Dempsey, PE Senior Electrical Engineer Carter & Burgess, Inc. Energy & Power Solutions Facility

More information