Storm Water Runoff Detention Basin Design Medrum Building, University of Utah

Size: px
Start display at page:

Download "Storm Water Runoff Detention Basin Design Medrum Building, University of Utah"

Transcription

1 Storm Water Runoff Detention Basin Design Medrum Building, University of Utah CVEEN 4410 Engineering Hydrology, Spring 2012 Submitted by

2 Executive Summary Urbanization has a significant impact on the hydrologic cycle. The removal of natural vegetation and construction of large sections of impervious areas decrease infiltration and increase the total volume of storm water runoff. In addition the peak runoff discharge rate increases in intensity and timing. If these effects are not addressed, flooding of urban areas will occur which can be costly and dangerous for area residents. Also increased intensity of peak discharge negatively affects natural waterways, decreasing water quality in the process. Water quality is also degraded due to the storm water gathering pollutants off the urban impervious surfaces and then transporting it to water bodies were the storm water enters untreated. In an attempt to mitigate the negative effects of urbanization on the hydrology of a watershed storm water control methods are used. This report provides the analysis of the watershed which has its outlet 100 feet downstream of the MCE Building on the University of Utah Campus. By determining the pre-development hydrologic conditions a design can be provided that will account for the effects of urbanization. For this project a detention basin is proposed. The basin will detain the storm water runoff and then release it at rates that will be equal to or less than the pre-development peak discharge rates. This report consists of 4 sections: the pre-development watershed analysis, an in-depth analysis of an impervious urban structure within the watershed, the post-development watershed analysis, and the detention basin design. Also included are Appendices which provided detailed information on the analysis methods used. The final product is a design which accomplishes the stated goal of mimicking the pre-development hydrology within the urban environment.

3 Table of Contents Executive Summary Introduction Problem Description Goals & Objectives Pre-Development Watershed Analysis Purpose of Analysis Pre-development Watershed Properties Time of Concentration Peak Discharge via the Rational Method Predicted Hydrographs via HEC-HMS Building Drainage Parameters, MCE Case Study Purpose of Analysis Roof Properties Time of Concentration Peak Discharge via the Rational Method Predicted Hydrographs via HEC-HMS Summary of Roof Hydrologic Parameters Post-Development Watershed Analysis Purpose of Analysis Post-development Watershed Properties Time of Concentration Peak Discharge via the Rational Method Predicted Hydrographs via HEC-HMS Detention Basin Design Required Detention Basin Size Detention Basin Design Outlet Structure Design Pipe Requirements for Detention Basin Inflow/Outflow Summary and Conclusions References P a g e

4 Appendices A. SCS Curve Number Method B. Salt Lake City Precipitation Data C. Time of Concentration Method D. Time of Concentration Calculation Pre-Development Watershed E. Rational Method F. HEC-HMS Method G. HEC-HMS Analysis Pre-Development Watershed H. HEC-HMS Analysis MCE Building Case Study I. HEC-HMS Analysis Post-Development Watershed J. HEC-HMS Analysis Detention Basin P a g e

5 List of Figures and Tables Figure 1: Developed versus Natural Hydrograph... 8 Figure 2: Watershed Map with Sub-Areas... 9 Figure 3: Watershed Total Area Calculation Figure 4: Sub-Watershed Area Calculations Table 1: Table 2-2d from USDA TR55 guide Figure 5: Historical Photo of the Area Figure 6: USDA Soil Survey Table 2: Curve Number Detail Summary Table 3: Table 3-1 from USDA TR55 guide (USDA, 1986) Table 4: SCS Method Detail Summary Table 5: Runoff Coefficients Table 6: Rational Method Peak Discharge Rates Table 7: Comparison of Peak Discharge Rates from the Rational Method and HEC-HMS Figure 7: MCE Roof Architectural Plan Table 8: MCE Roof, Area Summary Table 9: Table 2-2a from USDA TR55 guide Table 10: Runoff Coefficient Detail Summary Table 11: Time of Concentration Worksheet Table 12: Peak Discharge for Each Sub-Watershed Table13: Peak Discharge Entire Roof Section Table 14: Roof Hydrologic Parameters Figure 8: Post-development sub-watersheds Figure 9: Post-Development Watershed Area Calculations Table 15: Post-Development Watershed Curve Number Detailed Summary Table 16: Post-Development Watershed Manning s Roughness Coefficients Table 17: SCS Method Detailed Summary Table 18: Time of Concentration Worksheet Table 19: Peak Discharge for Each Sub-Watershed Table 20: Peak Discharge for Entire Post-Development Watershed Table 21: Comparison of Peak Discharge Rates from the Rational Method and HEC-HMS Figure 10: Detention Basin Location P a g e

6 Figure 11: Conceptual Drawing of Detention Basin Design (NOTE: drawing not to scale) Figure 12: Example of an Outlet Structure Figure 13: Conceptual Drawing of Outlet Structure Design (NOTE: drawing not to scale) Table 22: Inflow and Outflow Pipe Diameter Requirements Figure 14: Chart for Estimating Velocity from TR-55 (USDA, 1986) Figure 15: Time of Concentration Worksheet from TR55 Guide Figure 16: Time of Concentration, Path Lengths for Area 2 and Area Figure 17: Time of Concentration, Path Length for Area Table 23: Runoff Coefficients Figure 18: HEC-HMS Standard View Screen Figure 19: HEC-HMS Watershed Model Table 24: HEC-HMS Results, 5 year, 25 year, & 100 year storms Figure 20: 5 year storm hydrograph Figure 21: 25 year storm hydrograph Figure 22: 100 year storm hydrograph Figure 23: HEC-HMS Watershed Model for MCE Rooftop Table 25: HEC-HMS Results, 5 year, 25 year, & 100 year storms Figure 24: 5 year storm hydrograph Figure 25: 25 year storm hydrograph Figure 26: 100 year storm hydrograph Figure 27: HEC-HMS Watershed Model Table 26: HEC-HMS Results, 5 year, 25 year, & 100 year storms Figure 28: 5 year storm hydrograph Figure 29: 25 year storm hydrograph Figure 30: 100 year storm hydrograph Figure 31: HEC-HMS Watershed Model Table 27: HEC-HMS Results, 100-year storm Figure 32: Detention Basin Storage Table and Volume Graph Vs. Time Figure 33: Outlet Structure, Flow from 4 levels of Orifices P a g e

7 1. Introduction Runoff is part of the hydrologic cycle, which also includes precipitation, infiltration, evaporation, transpiration, and ground water flow. The control of runoff in developed areas must be addressed so that damage from flooding does not occur. Engineers are tasked with developing designs to control storm water runoff. The first step of this design is to perform hydrologic analysis to determine the direct runoff, which is equal to the net precipitation over a watershed area. The definition of a watershed is a contiguous area that drains to an outlet, such that precipitation that falls within the watershed runs off through that single outlet. (Bedient, pg. 8). Net precipitation is the difference between total rain volume and the discharge volume. The difference in these values includes losses to interception, depression storage, infiltration, evaporation, and transpiration. It is the discharge volume, or direct runoff, which must be managed with effective drainage design measures. 1.2 Problem Description The Meldrum Civil Engineering (MCE) Building is located on the University of Utah Campus in Salt Lake City, Utah. The watershed that contributes runoff to the MCE Building must be analyzed, so a point 100 feet downstream, or west, of the MCE Building will be the point of analysis for this design. State-of-the-art hydrologic analysis methods are utilized to design containment and processing of storm water runoff that results from the contributing watershed at this point of analysis. 1.3 Goals & Objectives The goal of this design is to provide the necessary parameters for construction of a detention basin that will control storm water runoff at the point of analysis. A detention basin is a storm water management tool used to capture and temporarily detain storm water to prevent excessive discharge or flooding. In order to develop the detention basin design several steps will be taken including a pre-development watershed analysis, the analysis of drainage parameters for buildings within the watershed, and a post-development analysis. The results of these steps will provide the data necessary to design the detention basin for this system. 2. Pre-Development Watershed Analysis The first step in designing a detention basin to control runoff from the watershed area with an outlet at the MCE building was to determine the boundaries of this watershed and the predevelopment conditions. The boundaries of the watershed are decided by determining the area 7 P a g e

8 that drains to the point of analysis, which it the point 100 feet downstream of the MCE building. Pre-development conditions describe the area prior to any development of the land for human use. This is also referred to as the natural condition of the area. 2.1 Purpose of Analysis The urbanization of areas leads to decreased infiltration of precipitation due to the replacement of natural vegetation with impervious surfaces such as rooftops, parking lots, and roadways. Runoff travel times decrease as the natural vegetation is replaced by impervious surfaces and interception due to vegetation and natural depression storage is removed. These modifications of the natural landscape cause increased peak discharge rates and a larger overall volume of runoff. A hydrograph is a graph which plots runoff discharge over time. The effect of urbanization is a post-development direct runoff (DRO) hydrograph that peaks higher and more quickly than the pre-development DRO hydrograph (see Figure 1). The purpose of pre-development watershed analysis is so that in the final design drainage systems can be created that match peak discharge flows from the developed area to what they were prior to development. In other words, to create a drainage management system in the form of a detention basin that forces the post-development hydrograph peak to be less than or equal to the pre-development hydrograph peak, per local ordinances. Because the goal of the design is to mimic hydrological pre-development conditions, it is necessary to determine what those pre-development conditions were. Figure 1: Developed versus Natural Hydrograph 8 P a g e

9 2.2 Pre-development Watershed Properties The watershed area, with the point of discharge 100 feet west of the MCE building, was delineated using a combination of a raised-relief map and Google earth maps. This watershed was divided into 3 sub-watersheds because of differences in geographical conditions of the area resulting in variations in types of vegetation. The division into sub-watersheds results in a more accurate analysis due to the fact that different surface conditions lead to different runoff amounts and runoff travel times, which will be seen in following calculations. The most important factor in determining volume of runoff is the surface area over which precipitation collects. The area of this watershed and sub-watersheds were calculated to be 311 acres overall; 162 acres for area 1, 64 acres for area 2, and 85 acres for area 3. See figures 2 through 4 for detail. Figure 2: Watershed Map with Sub-Areas 9 P a g e

10 Figure 3: Watershed Total Area Calculation Figure 4: Sub-Watershed Area Calculations Pre-development characteristics of this area, a critical aspect of the analysis, were determined. These characteristics include assigned values for curve number, roughness coefficients, and runoff coefficients, which are necessary to estimate peak discharge, DRO hydrographs, and total volume of runoff. According to the USDA guide TR-55 (USDA,1986), the runoff curve number (CN) is based on soil types, plant cover, amount of impervious areas, interception, and surface storage. Table 2-2d (USDA,1986) in this guide was used to determine the curve number for the watershed (see Table 1). The pre-development cover type was determined from historical photos (Figure 5) and current satellite imagery of non-developed sections found using Google Earth. Using a soil classification of C (from USDA soil surveys, see Figure 6), a cover type of oak aspen, and hydrologic condition of poor, the curve number was found to be 74 for subwatersheds 2 and 3. For sub-watershed 1, soil C, a cover type of sagebrush with grass, and hydrologic condition of poor, suggests the curve number to be approximately 80. Using a 10 P a g e

11 weighted average, the curve number for the total watershed is 77. See Table 2 for a summary of the characteristic details. Table 1: Table 2-2d from USDA TR55 guide Figure 5: Historical Photo of the Area 11 P a g e

12 Figure 6: USDA Soil Survey Table 2: Curve Number Detail Summary Sub-Watersheds Cover Type Hydrologic Condition Soil Group Curve Number Area (acres) Area 1 Sagebrush/Grass Poor C Area 2 Oak Aspen Poor C Area 3 Oak Aspen Poor C Total Watershed Area = 311 Weighted Average = [(162 * 80) + (64 * 74) + (85 * 74)] / 311 Curve Number for Watershed = 77 Manning s roughness coefficients (n) are used in calculating the time it takes for water to flow through the watershed, which is referred to as time of concentration. They are related to the vegetation of the surface area up to 0.1 foot off the ground. These values are listed in table 3-1 in the TR-55 guide (see Table 3). For area 1 the coefficient is 0.15 (short grass) and for areas 2 and 3 the coefficient is 0.40 (light underbrush). 12 P a g e

13 Table 3: Table 3-1 from USDA TR55 guide (USDA, 1986) The SCS runoff curve number method is used to estimate volume of runoff in inches. See Appendix A for a detailed description of this method. Using the weighted curve number values determined (see Table 2) with the SCS runoff curve number method, runoff may be calculated using the following equations: Q = (P 0.2S) 2 / (P + 0.8S) Equation 1 S = 1000/CN 10 Equation 2 I a = 0.2S Equation 3 Where: Q = runoff (in) P = rainfall (in) S = potential maximum retention after runoff begins (in) I a = initial abstraction (in) The rainfall values are obtained from the NOAA Atlas 14 website, using the closest monitoring station, the Salt Lake City Zoo (see Appendix B). These values, for a 24-hour storm duration, are 1.96 inches for a 5 year storm, 2.59 inches for a 25 year storm, and 3.16 for a 100 year storm. Using the equations above, S = inches and I a = inches. Q = inches for a 5 year 13 P a g e

14 storm, inches for a 25 year storm, and inches for a 100 year storm. See Table 4 for a detailed summary of results. Table 4: SCS Method Detail Summary CN P (in) S (in) I a (in) Q (in) C 24 hour, 5 year storm hour, 25 year storm hour, 100 year storm The runoff coefficient (C) is defined as the ratio of runoff to precipitation. Estimated values of C are used with the Rational Method to estimate peak discharge. The runoff volumes (Q) and the precipitation values (I a ) from Table 4 were used to calculated the C values. The average runoff coefficient for this area is the ratio of the average of the calculated Q values to the average of the I a values, which equals Detailed results are included in Table 4. The calculated C values were compared with values that have been empirically derived. Table 5 provides these values. This comparison provides concurrence that the runoff coefficients calculated in Table 4 are within the average range. Table 5: Runoff Coefficients 14 P a g e

15 2.3 Time of Concentration Time of concentration (t c ) is the time required for water to flow from the most hydraulically distant point in a watershed to the watershed outlet, which in this analysis is the MCE building. Time of concentration is necessary information for calculating the peak discharge using the rational method, and is also necessary for specifying lag-time data associated with SCS methods utilized by the HEC-HMS program; results of both methods are discussed in more detail in subsequent sections of this report. The roughness coefficients determined earlier (Table 3) as well as the slope of the watershed for the anticipated flow path, which was determined using Google Maps, are used for these calculations. The TR-55 guide (USDA, 1986) provides a worksheet to calculate time of concentration which includes a summation of travel time values corresponding to sheet flow, shallow concentrated flow, and channel flow. For this watershed the time of concentration for the entire watershed was determined to be 0.97 hours. See Appendix C for a complete description of the method used to estimate times of concentration and Appendix D for details of calculations for the pre-development watershed. 2.4 Peak Discharge via the Rational Method The rational method is used to determine peak discharge rates (Q p) by relating rainfall to runoff. The formula for this method is Q p = CiA, where C = runoff coefficient, i = intensity of rainfall of chosen frequency for a duration equal to the time of concentration (in/hr), and A = area of the watershed (acres). See Appendix E for a complete explanation of this method. Because the time of concentration for this watershed is just under one hour (0.97 hours), the NOAA Atlas 14 (see Appendix B) 1 hour storm data was used in this calculation. These values are.714 inches for the 5 year storm, 1.18 for the 24 year storm, and 1.77 for the 100 year storm. The peak discharge rates for this watershed were determined to be 48 cfs for the 5-year storm, 113 cfs for the 25-year storm, and 206 for the 100-year storm. See table 6 for detail of calculations. Table 6: Rational Method Peak Discharge Rates A (acres) i (in/hr) C Q p (cfs) 5 year Storm year Storm year Storm Predicted Hydrographs via HEC-HMS HEC-HMS was used to model three storms; 5-year, 25-year, and 100-year. See Appendix F for a complete discussion of HEC-HMS methods. Complete results of these analyses are listed in appendix G. The peak discharge rates for the watershed, which is listed as the discharge for the MCE Building, are as follows: 5 year storm equals 65 cfs, 25 year storm equals cfs, 100 year storm equals cfs. See Table 7 for these results in comparison to results obtained with the Rational Method. 15 P a g e

16 While the Rational Method and HEC-HMS are both widely used and well accepted methods for use in watershed analysis and the design of storm water systems, each has its limitations. The rational method is more accurate when used for smaller, semi-urbanized areas. Because of the degree of detail and ability to adjust over time, HEC-HMS provides more accurate results for larger watersheds. Because of this the results from HEC-HMS are assumed to more accurate for this case and will be used in further calculations for this project. Table 7: Comparison of Peak Discharge Rates from the Rational Method and HEC-HMS Q p (cfs) Rational Method HEC-HMS 5 year Storm year Storm year Storm Building Drainage Parameters, MCE Case Study The next step, after the analysis of the pre-development watershed, is to perform an analysis of the drainage parameters for the buildings within the watershed. Although the most accurate method would be to perform this analysis on every building that falls within the drainage area, a less time intensive and still appropriately accurate technique is to perform a case study of one building. For this design that building will be the MCE building, specifically, the recent addition to the northwest corner for which plans are readily available (see Figure 7). Figure 7: MCE Roof Architectural Plan 16 P a g e

17 3.1 Purpose of Analysis As with the analysis of the pre-development watershed, time of concentration, peak discharge, total volume of runoff, and the runoff hydrograph for the building rooftop area must be determined. Once these values are established then assumptions can be made for other surfaces within the post-development watershed. As stated, the post-development watershed could be broken into hundreds of sub-watersheds and analysis could be performed on each. However in addition to the impractical time requirements, this would not necessarily provide any more accurate results. By providing an in depth analysis of one rooftop, necessary parameters can be established for use in similar impervious areas within the developed watershed. With this information educated assumptions can be made that result in accurate estimates of postdevelopment peak discharge and DRO hyrdrographs Roof Properties The total area of the recent addition to the MCE roof is 7076 square feet, or acres. This area is broken into 5 sub-watersheds due to the fact that there are 5 drains and associated sloped drainage areas on this section of roof. The area of each sub-watershed is listed in Table 8. Also included in this table are values of longest drainage path for each sub-watershed and the slope of each sub-watershed. These values will be used later calculations to determine time of concentration. Table 8: MCE Roof, Area Summary Area #1 Area #2 Area #3 Area #4 Area #5 Total square feet acres t c path length (ft) slope As with the pre-development watershed several characteristics of the roof area must be established in order to determine other factors needed for the analysis. Again these characteristics include assigned values for curve number, roughness coefficients, and runoff coefficient which are all used later in calculations which estimate the peak discharge and total volume of runoff. Using table 2.2a from the TR-55 guide (USDA, 1986), the curve number (CN) was determined to be 98 (see Table 9). 17 P a g e

18 Table 9: Table 2-2a from USDA TR55 guide The Manning s roughness coefficient (n), used to calculate time of concentration, was determined from table 3-1 in the TR55 guide (see Table 3 in this report). For a smooth surface such as a rooftop this value is As with the pre-development analysis, the SCS runoff curve number method was used (see Appendix A for a detailed description of this method). These calculations were performed using the curve number of 98, equations 1, 2, and 3, and the rainfall values in Appendix B for a 5 year, 25 year, and 100 year storm. See Table 10 for a detail summary of results. The runoff coefficient (C), which is the ratio of runoff to precipitation, is used to calculate peak discharge in the rational method. This value was calculated using the runoff and precipitation values obtained with the SCS method. The average runoff coefficient value for the three storms was Again this value was compared to the tabulated values in Table 5 which validated the results. 18 P a g e

19 3.3 Time of Concentration Table 10: Runoff Coefficient Detail Summary CN P (in) S (in) I a (in) Q (in) C 24 hour, 5 year storm hour, 25 year storm hour, 100 year storm Time of concentration (t c ) was calculated for each sub-watershed and for the overall watershed (see Appendix C for detailed description of method). Because of the relatively short distances from the most hydraulically remote point to the drain outlet in each of the roof sub-watersheds, all flow is considered sheet flow. A modified version of the worksheet provided in the TR55 guide was used. The total time of concentration was calculated to be hours, or 4.2 minutes. See Table 11 for detail of calculations. Table 11: Time of Concentration Worksheet Worksheet 3: Time of Concentration (T c ) or travel time (T t ) Project: MCE Rooftop Location: University of Utah Sheet Flow Segment ID #1 #2 #3 #4 #5 1 Surface descriptions (table 3-1) Smooth Surface Smooth Surface Smooth Surface Smooth Surface Smooth Surface 2 Manning's roughness coefficient, n (table 3-1) Flow length, L (total L 300 ft) ft Two-year 24-hour rainfall, P 2 in Land slope, s ft/ft T t = (nl) 0.8 Compute T t hr = P s Peak Discharge via the Rational Method The Rational Method was used to calculate peak discharge values for the sub-watersheds and overall roof area. See appendix E for a complete explanation of this method. The inputs to this method include the area calculations listed in Table 6, the rainfall values obtained from the NOAA Atlas-14 website as specified by the time of concentration, and the runoff coefficients as determined previously. The peak discharge rates for each of the sub-watersheds are tabulated in Table 12. The peak discharge rates for the entire roof section are 0.4 cfs for the 5-year storm, 0.7 cfs for the 25-year storm, and 1.0 cfs for the 100-year storm. See Table 13 for detail of results. 19 P a g e

20 Table 12: Peak Discharge for Each Sub-Watershed Sub-Watershed #1 A (acres) i (in/hr) C Q p (cfs) 5 year Storm year Storm year Storm Sub-Watershed #2 A (acres) i (in/hr) C Q p (cfs) 5 year Storm year Storm year Storm Sub-Watershed #3 A (acres) i (in/hr) C Q p (cfs) 5 year Storm year Storm year Storm Sub-Watershed #4 A (acres) i (in/hr) C Q p (cfs) 5 year Storm year Storm year Storm Sub-Watershed #5 A (acres) i (in/hr) C Q p (cfs) 5 year Storm year Storm year Storm Table13: Peak Discharge Entire Roof Section A (acres) i (in/hr) C Q p (cfs) 5 year Storm year Storm year Storm P a g e

21 3.5 Predicted Hydrographs via HEC-HMS HEC-HMS was used to model the system for the three SCS design storms of 5, 25, and 100 years. This was done in order obtain peak discharge rates and produce direct runoff hydrographs. See Appendix F for a complete discussion of this program. Results of this analysis and runoff hydrographs for each storm are included in appendix H. The peak discharge for the sub-watershed and entire roof section were comparable, although higher than what was found with the Rational Method. These values are as follows: 5 year storm equals cfs, 25 year storm equals cfs, and 100 year storm equals cfs. Because the Rational Method was specifically designed for small, urban watershed those results determined in the previous section are more accurate than the results obtained from HEC-HMS. 3.6 Summary of Roof Hydrologic Parameters A final tabulation of all results of the MCE roof top analysis was compiled. These results will be used in further analysis of the developed area. The accuracy of the information obtained is critical to the success of the detention basin design. See Table 14 for a summary of these parameters. Table 14: Roof Hydrologic Parameters Curve Number Roughness Coefficient Surface Area (ft 2 ) Surface Slope Time of Concentration Area # Area # Area # Area # Area # P a g e

22 4. Post-Development Watershed Analysis The post-development watershed consists of the previously established geographic area which contributes runoff to the point of analysis, which is the point 100 feet downstream of the MCE building. The difference in this analysis, versus the pre-development watershed analysis, is that in the post-development watershed the human modified landscape is considered. The existing urbanized area with all the buildings, parking lots, roads, and other built land features are taken into account in the determination of estimated peak discharge and DRO hydrographs. 4.1 Purpose of Analysis As stated in the previous section, time of concentration, peak discharge, total volume of runoff, and the runoff hydrograph for the post-development watershed must be determined. This information is needed in order to establish the necessary design parameters for the detention basin that will adjust for the differences between the resultant pre and post urbanization hydrographs. This analysis provides the information necessary to reach the ultimate goal of the detention basin design, which is to reduce peak discharge of the post-development watershed to equal or less than the rate of the pre-development watershed. 4.2 Post-development Watershed Properties As with the pre-development watershed, the post-development watershed was divided into subwatersheds. The sub-watersheds were determined using google maps. The delineations were made based on the groupings of relatively similar types of land cover. For example, areas with a higher percentage of impervious surfaces were separated from areas with a lower percentage of impervious surfaces. In order to not need to treat every rooftop, parking lot, sidewalk, etc. as an individual watershed, groupings were made of similar surfaced areas so that weighted curve numbers could be assigned. Figure 8 shows the sub-watersheds, numbered 1 through 10. For each of these sub-watersheds the area was calculated (see Figure 9). The area in acres for each sub-watershed is listed in Table P a g e

23 Figure 8: Post-development sub-watersheds Figure 9: Post-Development Watershed Area Calculations 23 P a g e

24 As with the pre-development watershed, certain characteristics of the areas were determined, including curve number values, roughness coefficients, and runoff coefficients. The curve numbers were determined using Table 2-2a from the TR-55 guide (USDA, 1983), which can be found in Table 9 in this report. These values were weighted for each area in order to determine an appropriate curve number for each sub-watershed. See Table 15 for details of this determination and the resulting curve numbers for each area. Table 15: Post-Development Watershed Curve Number Detailed Summary Sub-Watersheds Cover Type Percentage Hydrologic Condition Soil Group Curve Number for Cover/Condition Area 1 Lawns, Parks, etc. 50% Fair C 79 Paved, Roofs, Streets, etc. 50% N/A C 98 Area 2 Lawns, Parks, etc. 35% Fair C 79 Paved, Roofs, Streets, etc. 65% N/A C 98 Area 3 Lawns, Parks, etc. 90% Fair C 79 Paved, Roofs, Streets, etc. 10% N/A C 98 Area 4 Lawns, Parks, etc. 10% Fair C 79 Paved, Roofs, Streets, etc. 90% N/A C 98 Area 5 Lawns, Parks, etc. 15% Fair C 79 Paved, Roofs, Streets, etc. 85% N/A C 98 Area 6 Lawns, Parks, etc. 45% Fair C 79 Paved, Roofs, Streets, etc. 55% N/A C 98 Area 7 Area 8 Area 9 Area 10 Sagebrush/Grass 100% Poor C 80 Sagebrush/Grass 100% Poor C 80 Oak Aspen 100% Poor C 74 Oak Aspen 100% Poor C 74 Weighted Curve Number for Area Area (acres) Total Watershed Area = 311 Weighted Average = [(6.58 * 89)+(32.17 * 91)+(26.28 * 81)+(27.73 * 96)+(23.71 * 95)+(22.67 * 89)+(8.44 * 80)+ (14.68 * 80)+(64.21 * 74)+ (84.79 * 74) ] / 311 Curve Number for Watershed = 82 The Manning s roughness coefficients for each sub-watershed area were also determined. These values are taken from TR-55 (USDA, 1983) (see Table 3) and will be used to calculate time of concentration. These values were weighted as with the curve numbers. A tabulation of the results is found in Table P a g e

25 Table 16: Post-Development Watershed Manning s Roughness Coefficients Sub-Watersheds Surface Description Percentage Coefficient for Surface Type Weighted Coefficient for Area Area 1 Area 2 Area 3 Area 4 Area 5 Area 6 Cultivated Soils Cultivated Soils Cultivated Soils Cultivated Soils Cultivated Soils Cultivated Soils 50% 35% 90% 10% 15% 45% Smooth Surface Smooth Surface Smooth Surface Smooth Surface Smooth Surface Smooth Surface 50% 65% 10% 90% 85% 55% Area 7 Area 8 Area 9 Area 10 Short Grass 100% 0.15 Short Grass 100% 0.15 Light Underbrush 100% 0.4 Light Underbrush 100% The SCS runoff curve number method was used to estimate volume of runoff in inches. See Appendix A for a complete description of this method. The weighted curve number values from Table 14 and precipitation values from NOAA Atlas 14, used in the pre-development SCS method calculations, were used. The calculations produced the following results: S = inches, I a = inches, and Q = inches for a 5-year storm, inches for a 25-year storm, and inches for a 100-year storm. See Table 17 for a detailed summary of results. Table 17: SCS Method Detailed Summary CN P (in) S (in) I a (in) Q (in) C 24 hour, 5 year storm hour, 25 year storm hour, 100 year storm The runoff coefficient (C), which is used in the Rational Method to determine peak discharge, was calculated using the results obtained from the SCS Method. The runoff coefficient is the ratio of runoff to precipitation. The average runoff coefficient for the 5, 25, and 100-year storms is See Table 17 for detailed results. This value was compared to runoff coefficients that have been empirically derived (see Table 5). This comparison provides concurrence that the runoff coefficients calculated in Table 17 are within the average range. 25 P a g e

26 4.3 Time of Concentration Time of concentration, the time required for water to flow from the most hydraulically distant point in a watershed to the watershed outlet, was calculated for the post-development watershed. See Appendix C for a complete description of this method. A modified version of the TR-55 (USDA, 1986) worksheet was used to calculate the travel time for each sub-watershed area and the total time of concentration for the entire watershed. The time of concentration for the total watershed was determined to be 0.90 hours or 54 minutes. See Table 18 for detail of calculations. This decrease in time of concentration from the pre-development value is not significant when considered for the entire watershed. However, when a comparison is made of just the valley area, which is the developed portion of the watershed, the time of concentration decreases by 28%, which is a drop from 13.6 minutes to 9.8 minutes. Worksheet 3: Time of Concentration (T c ) or travel time (T t ) Project: MCE Building Location: University of Utah Table 18: Time of Concentration Worksheet Sheet Flow Segment ID #1 #2 #3 #4 #5 #6 #7 / #8 #9 / #10 1 Surface descriptions (table 3-1) Light Underbrush 2 Manning's roughness coefficient, n (table 3-1) Flow length, L (total L 300 ft) ft Two-year 24-hour rainfall, P 2 in Land slope, s ft/ft T t = (nl) Compute T t hr = P s 0.4 Shallow Concentrated Flow Segment ID #1 #2 #3 #4 #5 #6 #7 / #8 #9 / #10 7 Surface description (paved or unpaved) Paved Paved Unpaved Paved Paved Paved Unpaved Unpaved 8 Flow length, L ft Watercourse slope, s ft/ft Average velocity, V (figure 3-1) ft/s T t = L Compute T t hr = V Watershed T c (Total of T t from 6 and 11) Peak Discharge via the Rational Method The rational method, which is Q p = CiA, was used to determine the peak discharge rates (Q p ) for the developed watershed. See Appendix E for a description of the method. The runoff coefficient values (C) from Table 17 were used with the area values (A) from Table 15. The precipitation value (i) was obtained from the NOAA Atlas-14 table in Appendix B. Because the time of concentration was 50 minutes the precipitation value was determined by interpolating. The peak discharge rates for each of the sub-watersheds are tabulated in Table 19. The peak discharge rates for the entire watershed are 79.3 cfs for the 5-year storm, cfs for the 25- year storm, and cfs for the 100-year storm. See Table 20 for detail of results. 26 P a g e

27 Table 19: Peak Discharge for Each Sub-Watershed Sub-Watershed #1 A (acres) i (in/hr) C Q p (cfs) 5 year Storm year Storm year Storm Sub-Watershed #2 A (acres) i (in/hr) C Q p (cfs) 5 year Storm year Storm year Storm Sub-Watershed #3 A (acres) i (in/hr) C Q p (cfs) 5 year Storm year Storm year Storm Sub-Watershed #4 A (acres) i (in/hr) C Q p (cfs) 5 year Storm year Storm year Storm Sub-Watershed #5 A (acres) i (in/hr) C Q p (cfs) 5 year Storm year Storm year Storm Sub-Watershed #6 A (acres) i (in/hr) C Q p (cfs) 5 year Storm year Storm year Storm Sub-Watershed #7 A (acres) i (in/hr) C Q p (cfs) 5 year Storm year Storm year Storm Sub-Watershed #8 A (acres) i (in/hr) C Q p (cfs) 5 year Storm year Storm year Storm Sub-Watershed #9 A (acres) i (in/hr) C Q p (cfs) 5 year Storm year Storm year Storm Sub-Watershed #10 A (acres) i (in/hr) C Q p (cfs) 5 year Storm year Storm year Storm P a g e

28 Table 20: Peak Discharge for Entire Post-Development Watershed A (acres) i (in/hr) C Q p (cfs) 5 year Storm year Storm year Storm Predicted Hydrographs via HEC-HMS HEC-HMS was again used to model the system for the three SCS design storms of 5, 25, and 100 years. This was done to obtain peak discharge rate and direct runoff hydrographs. See Appendix F for detailed information about HEC-HMS and Appendix I for results of this analysis. The peak discharge rates for the watershed are as follows: 5 year storm equals 189 cfs, 25 year storm equals 278 cfs, 100 year storm equals 363 cfs. See Table 21 for these results in comparison to results obtained with the Rational Method. The peak discharge rates obtained using HEC-HMS are higher than those obtained with the Rational Method. As stated, the Rational Method is more accurate when used for smaller, semi-urbanized areas. Because most of this watershed is not yet developed, and because of the size, HEC-HMS is assumed to produce more accurate results. In addition, designing for the HEC-HMS produced values is a more conservative approach to take in sizing the detention basin. Table 21: Comparison of Peak Discharge Rates from the Rational Method and HEC-HMS Q p (cfs) Rational Method HEC-HMS 5 year Storm year Storm year Storm P a g e

29 5. Detention Basin Design In order to adjust for the effects of urbanization on this watershed and account for the effects of the built impervious surfaces on the natural hydrologic cycle, a detention basin is proposed. The detention basin will temporarily detain storm water, and then release this storm water at a determined rate in order to adjust for the quicker and more intense peak of the urbanized hydrograph (see Figure 1). The detention basin will modify the outflow of storm water. The peak discharge of the post-development watershed will be reduced to equal or less than the peak discharge of the pre-development watershed. 5.1 Required Detention Basin Size Using the following equation the approximate size of the detention basin was determined: V s = (Q pa - Q pb ) * (t ca ) Equation 4 Where: V s = Storage volume (ft 3 ) Q pa = Post-development peak discharge (cfs) Q pb = Pre-development peak discharge (cfs) t ca = Post-development time of concentration (seconds) The peak discharge rates used were values from HEC-HMS for the 100 year storm (see Tables 7 and 22). The result was a detention basin 480,911 ft 3 or acre-feet. A model was created in HEC-HMS with a detention basin of acre-feet. Through trial and error, and using the detention basin and outlet structure as designed (see section 5.2 and 5.3), it was found that the actual volume required was 9.27 acre-feet. At this volume the detention basin almost filled during the 100-year storm event. Through the outlet structure the detained water was able to drain at a maximum rate of 215 cfs. This peak discharge matches the peak discharge of the predevelopment watershed. See Appendix J for HEC-HMS inputs and results. 5.2 Detention Basin Design For reasons of aesthetics the detention basin has been designed as an oval that will mimic the shape of a natural water body. The basin will be 6 feet deep with a slope of 0.44 at the ends and 0.16 on the sides. At the necessary volume, the required surface area is 85,872 ft 2. See Figure 10 for an image showing where the detention basin will be located. Figure 11 provides a conceptual drawing of the detention basin with interior and exterior dimensions. 29 P a g e

30 Figure 10: Detention Basin Location Figure 11: Conceptual Drawing of Detention Basin Design (NOTE: drawing not to scale) 30 P a g e

31 5.3 Outlet Structure Design The outlet structure is designed to be constructed of concrete. It will be 6 feet tall and 5 foot by 5 foot wide. There will be 36 orifices total distributed equally on 3 sides. Each orifice will be 8.2 inches wide by 12 tall. The top of the structure will be open with a grate in case of storm events greater than the 100-year storm. See Figure 12 for an example of a similar outlet structure. See Figure 13 for a conceptual drawing of the structure for this project with dimensions. Figure 12: Example of an Outlet Structure Figure 13: Conceptual Drawing of Outlet Structure Design (NOTE: drawing not to scale) 31 P a g e

32 5.4 Pipe Requirements for Detention Basin Inflow/Outflow Manning s equation for pipe flow was used to calculate the required inflow and outflow pipe diameters for the detention basin. The equation is: d = [3.208 * n/k n * Q p /(S o 1/2 )] 3/8 Equation 5 Where: d = diameter (feet) n = Manning s roughness coefficient K n = constant, 1.49 for U.S. Customary Units Q p = peak discharge (cfs) S o = slope The recommended pipe is reinforced concrete pipe (RCP) which has a roughness coefficient of The minimum recommended slope is The peak discharge values used are for the 100-year storm. The results of these calculations show that a 7 foot diameter pipe is needed for the inflow and a 6 foot diameter pipe is needed for the outflow. See detailed results in Table 22. Table 22: Inflow and Outflow Pipe Diameter Requirements For Detention Basin Inflow For Detention Basin Outflow Q p : 363 cfs Q p : 215 cfs n: n: K: 1.49 K: 1.49 S o : 0.50% S o : 0.50% d: feet d: feet 6. Summary and Conclusions The purpose of this design is to provide a measure in which the natural hydrology that existed in the pre-developed watershed can be returned to the urbanized watershed. The method selected in order to accomplish this goal is a detention basin. The information gathered provided data from which the pre-development peak discharge rates for various storms could be determined. A specific pervious area, the MCE rooftop, within the watershed was analyzed in detail. This provided confirmation of assumptions, which were then used to make generalizations for the post-development watershed so that peak discharge rates could be estimated. With this information a detention basin and outlet structure have been designed which will temporarily detain storm water runoff and allow it to drain at the pre-development peak rate. Through the installation of this detention basin the goal to return the post-development watershed to predevelopment hydrological conditions will be achieved. 32 P a g e

33 References Huber, W.C., Bedient, P.B., Vieux, B.E., (2007), Hydrology and Floodplain Analysis, Place: Publisher. United States Department of Agriculture, Technical Release 55 (TR-55), Urban Hydrology for Small Watersheds, June 1986 National Oceanic and Atmospheric Administration s (NOAA) National Weather Service, Atlas 14 Point Precipitation Frequency Estimates, 33 P a g e

34 Appendix A SCS Curve Number Method The SCS Curve Number Method was developed by the United State Department of Agriculture (USDA) Natural Resources Conservation Service. The agency was formerly known as the Soil Conservation Service or SCS. It is a method that is widely used for the predication of direct runoff from storms. It is an empirical method developed by the USDA through the monitoring and analysis of runoff from systems. It is a simple method to use and provides rough estimates of the volume of runoff and infiltration. The first step in this method is the identification of the appropriate curve number for the area to be analyzed. The curve number is based on soil types, plant cover, amount of impervious areas, interception, and surface storage. Curve numbers range from 30 to 98. Low numbers represent lower runoff potential and more permeable surfaces while high numbers represent higher runoff potential and more impervious surfaces. The TR55 guide published by the USDA includes a set of four tables (Tables 2.2a through 2.2d) that are used to determine the curve number once the other parameters have been determined. The next step in this method is to determine the rainfall value. The selection of this value depends on the duration and magnitude of design storm selected. Precipitation data is collected by the National Oceanic and Atmospheric Administration (NOAA) and is available online at With values for the curve number and rainfall the calculations can be made. The equations are as follows: Q = (P 0.2S) 2 / (P + 0.8S) Equation 1 S = 1000/CN 10 Equation 2 I a = 0.2S Equation 3 Where: Q = runoff (in) P = rainfall (in) S = potential maximum retention after runoff begins (in) I a = initial abstraction (in) The results from these equations are an estimated volume of runoff in inches (Q), an estimated volume for initial abstractions in inches (I a ), and an estimated volume for potential maximum retention in inches (S). 34 P a g e

35 Appendix B Salt Lake City Precipitation Data 35 P a g e

36 Appendix C Time of Concentration Method Time of concentration (t c ) is defined as the time required for water to flow from the most hydraulically remote point in a watershed to the watershed outlet. It is an important parameter is determining the response of a watershed to storm events. Time of concentration is dependent on several factors including slope, distance, and surface conditions. The method of segments is used to calculate time of concentration. This method consists of the summation of three types of flow; sheet flow, shallow concentrated flow, and channel flow. Sheet flow consists of the first 300 feet or less from the most remote point. The necessary variables required to perform this calculation are the Manning s roughness coefficient, which can be found in Table 3-1 in the USDA TR-55 guide, the flow length, the two year, 24 hour rainfall value for the area, and the land slope. With these values the following equation is used to compute the time for this first section of flow. T = (0.007 * (n * L) 0.8 ) / (P * s 0.4 ) Where: T = time (hours) n = Manning s roughness coefficients L = Flow length (ft) P 2 = Two-year 24-hour rainfall (in) s = Land slope (ft/ft) The next section of flow is shallow concentrated flow. The first step in this determining this value is to determine the velocity of flow. This is done using the surface description of paved or unpaved, the flow length, and the watercourse slope. From these variables the velocity can be determined using figure 3-1 in the TR-55 guide (see Figure 14). Then the time is calculated using the following equation: T = L / (3600 * V) Where: T = time (hours) L = Flow length (ft) V = Velocity (ft/s) 36 P a g e

37 Figure 14: Chart for Estimating Velocity from TR-55 (USDA, 1986) The next section is channel flow, which may or may not be relevant to every watershed. In the situation that channel flow does occur the velocity must again be determined. In this case it is determined by using the Manning s equation for open channel flow. This equation is as follows: V = (1.49 * r 2/3 * s 1/2 ) / (n) Where: V = Velocity (ft/s) r = Hydraulic radius (ft) s = Channel slope (ft/ft) n = Manning s roughness coefficient 37 P a g e

38 Once the velocity is determined the time is calculated using the following equation: T = L / (3600 * V) Where: T = time (hours) L = Flow length (ft) V = Velocity (ft/s) The total of the 3 calculated times are added together and this is the time of concentration for the watershed. This method is detailed in the USDA TR55 guide. The guide also provides a worksheet that can be used as a tool in organizing the calculations. See Figure 15 for a example of the Time of Concentration Worksheet included in the TR55 guide. Figure 15: Time of Concentration Worksheet from TR55 Guide 38 P a g e

39 Appendix D Time of Concentration Calculation Pre-Development Watershed 39 P a g e

40 Figure 16: Time of Concentration, Path Lengths for Area 2 and Area 3 Figure 17: Time of Concentration, Path Length for Area 1 40 P a g e

41 Appendix E Rational Method The Rational Method is used to determine the peak discharge rate for a watershed. Peak discharge is the highest rate of runoff resulting from a precipitation event. This value is important to know for planning in order to avoid damage from flooding, to size storm water management facilities, and to determine the effects of urbanization on the hydrology of a watershed. The Rational Method provides a simple and quick method to calculate an approximate peak discharge value. Following is the Rational Method equation: Q p = CiA where C = runoff coefficient i = intensity of rainfall (in/hr) A = area of the watershed (acres). The runoff coefficient is the ratio of runoff to rainfall. There are charts available were these coefficients can be obtained for various types of vegetation and cover (see Table 5 and Table 23 below). The coefficient can also be calculated if runoff and rainfall values are available. The rainfall intensity needs to be selected for the storm duration that is the same time as the time of concentration (see Appendix C for time of concentration method). The rainfall intensity can be found at the NOAA Atlas-14 website. The area of the watershed needs to be in acres. This method is very useful but does have some limitations. The method was developed for small (100 acres or less) watersheds that are undergoing urbanization. Because of this the results are not accurate when used for larger watersheds. The method assumes that rainfall intensity is uniform over watershed and over duration of the storm event. It also assumes that runoff is invariant with time, meaning that soil conditions do not change with time. Table 23: Runoff Coefficients 41 P a g e

42 Appendix F HEC-HMS Method HEC-HMS is a computer program designed for modeling hydrologic systems. It is a free program that was developed by the United States Army Corps of Engineers (USACE). According to the USACE web page the primary goal of HEC is to support the nation in its water resources management responsibilities by increasing the Corps technical capability in hydrologic engineering and water resources planning and management. An additional goal is to provide leadership in improving the state-of-the-art in hydrologic engineering and analytical methods for water resources planning. ( The following statement from the USACE web page sums up the program uses and capabilities: The Hydrologic Modeling System (HEC-HMS) is designed to simulate the precipitationrunoff processes of dendritic watershed systems. It is designed to be applicable in a wide range of geographic areas for solving the widest possible range of problems. This includes large river basin water supply and flood hydrology, and small urban or natural watershed runoff. Hydrographs produced by the program are used directly or in conjunction with other software for studies of water availability, urban drainage, flow forecasting, future urbanization impact, reservoir spillway design, flood damage reduction, floodplain regulation, and systems operation. The program is a generalized modeling system capable of representing many different watersheds. A model of the watershed is constructed by separating the hydrologic cycle into manageable pieces and constructing boundaries around the watershed of interest. Any mass or energy flux in the cycle can then be represented with a mathematical model. In most cases, several model choices are available for representing each flux. Each mathematical model included in the program is suitable in different environments and under different conditions. Making the correct choice requires knowledge of the watershed, the goals of the hydrologic study, and engineering judgment. The program features a completely integrated work environment including a database, data entry utilities, computation engine, and results reporting tools. A graphical user interface allows the seamless movement between the different parts of the program. Program functionality and appearance are the same across all supported platforms. ( In order to use the HEC-HMS program information about the watershed must be gathered prior to modeling the system. This information includes geographical areas in square miles, curve numbers which are based on soil types, plant cover, amount of impervious areas, interception, and surface storage (see Appendix A), initial abstractions which are calculated using the SCS Method (Appendix A), and time of concentration the watershed or each sub-watershed (see Appendix C). Once this and other general information about the watershed is known a model can be created in HEC-HMS. Next meteorological data must be entered for the types of storm 42 P a g e

43 events that are to be analyzed. This information can be found at the NOAA Atlas-14 website from tables or Intensity Duration Frequency (IDF) curves. The next step is to enter simulation control specifications which determine the duration of the model event and the time steps the program will use. With these steps completed a simulation can be performed. Various results can be obtained from simulation runs including peak discharge rates and total volume of runoff. The program produces hyetographs which graph precipitation intensity over time and hydrographs which graph outflow over time, in addition to many other graphs that can be used for hydrologic planning. Storm water management devices such as detention basins or reservoirs can also be modeled in the system. The results of this analysis can be useful in infrastructure design and the construction of storm water management devices. The main limitation of HEC-HMS is that it is a complex program that takes training and practice to use. Using HEC-HMS to calculate a peak discharge rate is much more complicated and time consuming than using the Rational Method (see Appendix E). The other limitation to consider is that the program was designed to model larger watersheds and does not perform as well for small scale urban watersheds. Figure 18: HEC-HMS Standard View Screen 43 P a g e

44 Appendix G HEC-HMS Analysis Pre-Development Watershed Figure 19: HEC-HMS Watershed Model Table 24: HEC-HMS Results, 5 year, 25 year, & 100 year storms 44 P a g e

45 Figure 20: 5 year storm hydrograph Figure 21: 25 year storm hydrograph Figure 22: 100 year storm hydrograph 45 P a g e

46 Appendix H HEC-HMS Analysis MCE Building Case Study Figure 23: HEC-HMS Watershed Model for MCE Rooftop Table 25: HEC-HMS Results, 5 year, 25 year, & 100 year storms 46 P a g e

47 Figure 24: 5 year storm hydrograph Figure 25: 25 year storm hydrograph Figure 26: 100 year storm hydrograph 47 P a g e

48 Appendix I HEC-HMS Analysis Post-Development Watershed Figure 27: HEC-HMS Watershed Model Table 26: HEC-HMS Results, 5 year, 25 year, & 100 year storms 48 P a g e

49 Figure 28: 5 year storm hydrograph Figure 29: 25 year storm hydrograph Figure 30: 100 year storm hydrograph 49 P a g e

50 Appendix J HEC-HMS Analysis Detention Basin Figure 31: HEC-HMS Watershed Model Table 27: HEC-HMS Results, 100-year storm 50 P a g e

51 Figure 32: Detention Basin Storage Table and Volume Graph Vs. Time Figure 33: Outlet Structure, Flow from 4 levels of Orifices 51 P a g e

Travel Time. Computation of travel time and time of concentration. Factors affecting time of concentration. Surface roughness

Travel Time. Computation of travel time and time of concentration. Factors affecting time of concentration. Surface roughness 3 Chapter 3 of Concentration and Travel Time Time of Concentration and Travel Time Travel time ( T t ) is the time it takes water to travel from one location to another in a watershed. T t is a component

More information

CHAPTER 2 HYDRAULICS OF SEWERS

CHAPTER 2 HYDRAULICS OF SEWERS CHAPTER 2 HYDRAULICS OF SEWERS SANITARY SEWERS The hydraulic design procedure for sewers requires: 1. Determination of Sewer System Type 2. Determination of Design Flow 3. Selection of Pipe Size 4. Determination

More information

Computing Stormwater Runoff Rates and Volumes

Computing Stormwater Runoff Rates and Volumes New Jersey Stormwater Best Management Practices Manual February 2004 C H A P T E R 5 Computing Stormwater Runoff Rates and Volumes This chapter discusses the fundamentals of computing stormwater runoff

More information

Basic Hydrology. Time of Concentration Methodology

Basic Hydrology. Time of Concentration Methodology Basic Hydrology Time of Concentration Methodology By: Paul Schiariti, P.E., CPESC Mercer County Soil Conservation District What is the Time of Concentration? The time it takes for runoff to travel from

More information

The Rational Method. David B. Thompson Civil Engineering Deptartment Texas Tech University. Draft: 20 September 2006

The Rational Method. David B. Thompson Civil Engineering Deptartment Texas Tech University. Draft: 20 September 2006 The David B. Thompson Civil Engineering Deptartment Texas Tech University Draft: 20 September 2006 1. Introduction For hydraulic designs on very small watersheds, a complete hydrograph of runoff is not

More information

APPENDIX B DESIGN GUIDELINES FOR APPROVED TREATMENT METHODS

APPENDIX B DESIGN GUIDELINES FOR APPROVED TREATMENT METHODS APPENDIX B DESIGN GUIDELINES FOR APPROVED TREATMENT METHODS PLANTER BOXES 1. Determine the impervious area contributing flow to the planter box (see Chapter 4.2). 2. Assumption: Typical soil infiltration

More information

Rational Method Hydrologic Calculations with Excel. Rational Method Hydrologic Calculations with Excel, Course #508. Presented by:

Rational Method Hydrologic Calculations with Excel. Rational Method Hydrologic Calculations with Excel, Course #508. Presented by: Rational Method Hydrologic Calculations with Excel, Course #508 Presented by: PDH Enterprises, LLC PO Box 942 Morrisville, NC 27560 www.pdhsite.com Calculation of peak storm water runoff rate from a drainage

More information

URBAN DRAINAGE CRITERIA

URBAN DRAINAGE CRITERIA URBAN DRAINAGE CRITERIA I. Introduction This division contains guidelines for drainage system design and establishes a policy for recognized and established engineering design of storm drain facilities

More information

10/4/2012. 40 slide sample of Presentation. Key Principles to Current Stormwater Management

10/4/2012. 40 slide sample of Presentation. Key Principles to Current Stormwater Management 40 slide sample of Presentation Please contact mhoalton@pacewater.com if you would like the complete presentation Key Principles to Current Stormwater Management Distributed Control Measures Integrated

More information

TENNESSEE GAS PIPELINE COMPANY, L.L.C.

TENNESSEE GAS PIPELINE COMPANY, L.L.C. TENNESSEE GAS PIPELINE COMPANY, L.L.C. HYDROLOGIC & HYDRAULIC CALCULATIONS FOR WATERBODIES CROSSED BY CONNECTICUT PIPELINE EXPANSION PROJECT CONNECTICUT LOOP Submitted by: Tennessee Gas Pipeline Company,

More information

Stormwater Drainage Design for Parking Lots

Stormwater Drainage Design for Parking Lots PDHonline Course C201 (4 PDH) Stormwater Drainage Design for Parking Lots 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088 www.pdhonline.org www.pdhcenter.com

More information

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth

More information

CHAPTER 3 STORM DRAINAGE SYSTEMS

CHAPTER 3 STORM DRAINAGE SYSTEMS CHAPTER 3 STORM DRAINAGE SYSTEMS 3.7 Storm Drains 3.7.1 Introduction After the tentative locations of inlets, drain pipes, and outfalls with tail-waters have been determined and the inlets sized, the next

More information

Sample DEQ Plan Submitter s Checklist for Stormwater Management Plans

Sample DEQ Plan Submitter s Checklist for Stormwater Management Plans APPENDIX IV Version: February 2, 2015 Sample DEQ Plan Submitter s Checklist for Stormwater Management Plans Please fill in all blanks and please reference the plan sheets/pages where the information may

More information

CITY OF CHARLOTTE STORM WATER SERVICES CREDIT APPLICATION INSTRUCTION MANUAL

CITY OF CHARLOTTE STORM WATER SERVICES CREDIT APPLICATION INSTRUCTION MANUAL CITY OF CHARLOTTE STORM WATER SERVICES CREDIT APPLICATION INSTRUCTION MANUAL March 2008 A note to recipients of the Charlotte-Mecklenburg Storm Water Services Credit Application Manual: This is the second

More information

STORMWATER MANAGEMENT CHECKLIST

STORMWATER MANAGEMENT CHECKLIST STORMWATER MANAGEMENT CHECKLIST *This checklist must be completed and part of the Land Disturbing Permit submittal for review if the acreage disturbed is one (1) acre or more: I. SUPPORTING DATA Narrative

More information

Estimating Storm Water Runoff

Estimating Storm Water Runoff PDHonline Course H119 (2 PDH) Estimating Storm Water Runoff Instructor: John Poullain, PE 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088 www.pdhonline.org

More information

1800 Washington Boulevard, Baltimore, MD 21230-1718 www.mde.maryland.gov 410-537-3000 800-633-6101 TTY Users 800-735-2258 Larry Hogan, Governor Boyd

1800 Washington Boulevard, Baltimore, MD 21230-1718 www.mde.maryland.gov 410-537-3000 800-633-6101 TTY Users 800-735-2258 Larry Hogan, Governor Boyd ENVIRONMENTAL SITE DESIGN (ESD) REDEVELOPMENT EXAMPLES OCTOBER 2010 1800 Washington Boulevard, Baltimore, MD 21230-1718 www.mde.maryland.gov 410-537-3000 800-633-6101 TTY Users 800-735-2258 Larry Hogan,

More information

C.3 Workshop Track 2: Sizing Calculations and Design Considerations for LID Treatment Measures

C.3 Workshop Track 2: Sizing Calculations and Design Considerations for LID Treatment Measures C.3 Workshop Track 2: Sizing Calculations and Design Considerations for LID Treatment Measures Jill Bicknell, P.E., EOA, Inc. Santa Clara Valley Urban Runoff Pollution Prevention Program Presentation Overview

More information

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW9 June 2015 SW9.01 Purpose This Chapter provides information for the design of open channels for the conveyance of stormwater in the City of Fort Wayne.

More information

Fort Dodge Stormwater Master Planning. Prepared By: Ralph C. Stark, Jr., P.E., C.F.M. Joel N. Krause, P.E., C.F.M.

Fort Dodge Stormwater Master Planning. Prepared By: Ralph C. Stark, Jr., P.E., C.F.M. Joel N. Krause, P.E., C.F.M. Fort Dodge Stormwater Master Planning Prepared By: Ralph C. Stark, Jr., P.E., C.F.M. Joel N. Krause, P.E., C.F.M. Project Location Project Background Flooding History Localized flooding and storm sewer

More information

Storm Drainage Systems 11.9-1

Storm Drainage Systems 11.9-1 Storm Drainage Systems 11.9-1 11.9 Gutter Flow Calculations 11.9.1 Introduction Gutter flow calculations are necessary in order to relate the quantity of flow (Q) in the curbed channel to the spread of

More information

STORM DRAINS CHAPTER 7

STORM DRAINS CHAPTER 7 CHAPTER 7 Chapter 7 - Storm Drains A storm drain is a drainage system that conveys water or stormwater, consisting of two or more pipes in a series connected by one or more structures. Storm drains collect

More information

Shooks Run Drainage Study Basic Terminology

Shooks Run Drainage Study Basic Terminology Shooks Run Drainage Study Basic Terminology PREPARED FOR: PREPARED BY: City of Colorado Springs CH2M DATE: April 9, 2015 Introduction This document is intended to provide an introduction to Colorado Springs

More information

Chapter 5.0. Stormwater Credits for Innovative Site Planning

Chapter 5.0. Stormwater Credits for Innovative Site Planning Chapter 5.0 Stormwater Credits for Innovative Site Planning Chapter 5. Stormwater Credits...Introduction 5.0 Stormwater Credits In Maryland, there are many programs at both the State and local level that

More information

City of Atlanta. Department of Watershed Management. Post-Development Stormwater Management Ordinance Summary of Revisions

City of Atlanta. Department of Watershed Management. Post-Development Stormwater Management Ordinance Summary of Revisions City of Atlanta Department of Watershed Management Post-Development Stormwater Management Ordinance Summary of Revisions Cory Rayburn, CPESC Environmental Program Manager crayburn@atlantaga.gov Stormwater

More information

Post Construction Stormwater Management Checklist Program

Post Construction Stormwater Management Checklist Program Post Construction Stormwater Management Checklist Program Anahid Damerau, CPESC, CPSWQ Christopher Smith, P.E. Department of Environmental Protection Stormwater Section Watershed Management Program The

More information

Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010

Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010 Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010 Background What are permeable interlocking concrete pavements (PICP)?

More information

Storm Drainage Design and Technical Criteria Manual. City of Brookings, SD

Storm Drainage Design and Technical Criteria Manual. City of Brookings, SD Storm Drainage Design and Technical Criteria Manual City of Brookings, SD May, 2006 City of Brookings Storm Drainage Manual Ecological Resource Consultants, Inc. Storm Drainage Design and Technical Criteria

More information

Micromanagement of Stormwater in a Combined Sewer Community for Wet Weather Control The Skokie Experience

Micromanagement of Stormwater in a Combined Sewer Community for Wet Weather Control The Skokie Experience Micromanagement of Stormwater in a Combined Sewer Community for Wet Weather Control The Skokie Experience Robert W. Carr 1 * and Stuart G. Walesh 2 1 Water Resources Modeling, LLC, 4144 S. Lipton Ave,

More information

Flash Flood Science. Chapter 2. What Is in This Chapter? Flash Flood Processes

Flash Flood Science. Chapter 2. What Is in This Chapter? Flash Flood Processes Chapter 2 Flash Flood Science A flash flood is generally defined as a rapid onset flood of short duration with a relatively high peak discharge (World Meteorological Organization). The American Meteorological

More information

APPENDIX F. RESIDENTIAL WATER QUALITY PLAN: ALLOWABLE BMP OPTIONS

APPENDIX F. RESIDENTIAL WATER QUALITY PLAN: ALLOWABLE BMP OPTIONS APPENDIX F. RESIDENTIAL WATER QUALITY PLAN: ALLOWABLE BMP OPTIONS The following section provides descriptions, advantages, limitations, and schematics of allowable best management practices (BMPs) for

More information

H. Khalid Jamil 9367 Verain Street San Diego, CA, 92129 (858) 663-9200

H. Khalid Jamil 9367 Verain Street San Diego, CA, 92129 (858) 663-9200 OFFSITE DRAINAGE REPORT Ramona Assisted Living 1236 "D" Street Ramona, CA 92065 re~*7lb3 Prepared for H. Khalid Jamil 9367 Verain Street San Diego, CA, 92129 (858) 663-9200 July 1 1, 2008 Daniel Tobar,

More information

CHAPTER 5 HYDROLOGIC ANALYSIS AND DESIGN

CHAPTER 5 HYDROLOGIC ANALYSIS AND DESIGN CHAPTER 5 HYDROLOGIC ANALYSIS AND DESIGN Chapter Organization 5.1 Introduction... 5-1 5.2 Hydrologic Analysis Methods... 5-1 5.3 Curve Number Method... 5-2 5.3.1 NRCS Curve Number Method Theory... 5-2

More information

ARTICLE II STORM DRAINAGE. (From Ordinance No. 1987-17; August 4, 1987; Sections III through VIII)

ARTICLE II STORM DRAINAGE. (From Ordinance No. 1987-17; August 4, 1987; Sections III through VIII) ARTICLE II STORM DRAINAGE (From Ordinance No. 1987-17; August 4, 1987; Sections III through VIII) SECTION 2.1 Standard Provisions Standard Provisions All construction for storm drainage in the development

More information

Riprap-lined Swale (RS)

Riprap-lined Swale (RS) Riprap-lined Swale (RS) Practice Description A riprap-lined swale is a natural or constructed channel with an erosion-resistant rock lining designed to carry concentrated runoff to a stable outlet. This

More information

APPENDIX D INLET CAPACITY AND SPACING. The capacity and spacing design of storm drainage inlets are presented in detail in this Appendix.

APPENDIX D INLET CAPACITY AND SPACING. The capacity and spacing design of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 3-D- PPENDIX D INET CPCITY ND SPCING.0 Introduction The capacity and spacing design of storm drainage inlets are presented in detail in this ppendix. 2.0 Design Recurrence Interval and Spread

More information

SECTION 108 - INLETS 108.1 INLET LOCATIONS

SECTION 108 - INLETS 108.1 INLET LOCATIONS Greene County Design Standards -Adopted April 5, 1999 SECTION 108 - INLETS SECTION 108 - INLETS 108.1 INLET LOCATIONS 108.2 INLET INTERCEPTION CAPACITIES 108.2.1 Clogging Factors 108.3 INTERCEPTION AND

More information

Permeable Pavement Treatment Capacity

Permeable Pavement Treatment Capacity Permeable Pavement Treatment Capacity April 20 2011 This investigation will analyze the pollutant removal capacity of various types of permeable paving techniques. Daniel Sullivan Joseph Fleury Contents

More information

Outlet stabilization structure

Outlet stabilization structure Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural

More information

PRECIPITATION AND EVAPORATION

PRECIPITATION AND EVAPORATION PRECIPITATION AND EVAPORATION OBJECTIVES Use historical data to analyze relationships between precipitation, evaporation and stream flow in the San Antonio River Basin TOPICS Water cycle Precipitation

More information

Storm Water Runoff. Managing. A Self-Assessment Guide for Wisconsin Businesses. Storm water runoff is coming. This guide provides businesses

Storm Water Runoff. Managing. A Self-Assessment Guide for Wisconsin Businesses. Storm water runoff is coming. This guide provides businesses Managing Storm Water Runoff A Self-Assessment Guide for Wisconsin Businesses Storm water runoff is coming under increasing scrutiny as both a source of pollutants to our lakes and streams, and as a cause

More information

A plan for conversion of stormwater to groundwater recharge on the Utah Valley University main campus, Orem, Utah

A plan for conversion of stormwater to groundwater recharge on the Utah Valley University main campus, Orem, Utah Hydrology Days 2013 A plan for conversion of stormwater to groundwater recharge on the Utah Valley University main campus, Orem, Utah Dylan B. Dastrup, Gabriela R. Ferreira, Daniel Zacharias, Daniel H.

More information

Retention/Irrigation. Design Considerations. Soil for Infiltration Area Required Slope Environmental Side-effects

Retention/Irrigation. Design Considerations. Soil for Infiltration Area Required Slope Environmental Side-effects Description Retention/irrigation refers to the capture of stormwater runoff in a holding pond and subsequent use of the captured volume for irrigation of landscape of natural pervious areas. This technology

More information

SUSTAINABLE URBAN DRAINAGE SYSTEMS

SUSTAINABLE URBAN DRAINAGE SYSTEMS overflow can lead into a permeable conveyance system to increase further the benefit and reduce the need for pipe systems. Pollutant removal rates have been shown to be high, with some pollutants being

More information

City of West Linn Public Works Design Standards 2010. Table of Contents

City of West Linn Public Works Design Standards 2010. Table of Contents City of West Linn Public Works Design Standards Table of Contents SECTION TWO STORM DRAIN REQUIREMENTS... 1 2.0000 STORM DRAINS... 1 2.0010 General Design Requirements...1 2.0011 Site Drainage Plans...2

More information

Module 6 : Quantity Estimation of Storm Water. Lecture 6 : Quantity Estimation of Storm Water

Module 6 : Quantity Estimation of Storm Water. Lecture 6 : Quantity Estimation of Storm Water 1 P age Module 6 : Quantity Estimation of Storm Water Lecture 6 : Quantity Estimation of Storm Water 2 P age 6.1 Factors Affecting the Quantity of Stormwater The surface run-off resulting after precipitation

More information

Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. CIVL 1112 Detention Ponds - Part 1 1/12

Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. CIVL 1112 Detention Ponds - Part 1 1/12 CIVL 1112 - Part 1 1/12 The water cycle, also known as the hydrologic cycle, describes the continuous movement of water on, above and below the surface of the Earth. The water cycle, also known as the

More information

Ruissellement du Bassin Précipitation Abstractions Hydrogramme Flux de Base. Superposition Routage

Ruissellement du Bassin Précipitation Abstractions Hydrogramme Flux de Base. Superposition Routage HEC-1 Leçon 11 This lesson will focus on how WMS can be used to develop HEC-1 modeling parameters and not on the fundamental hydrologic principles simulated by HEC-1. 1 Vue D Emsemble Utilisés Couramment

More information

Burnsville Stormwater Retrofit Study

Burnsville Stormwater Retrofit Study Burnsville Stormwater Retrofit Study Prepared for City of Burnsville June 2006 4700 West 77 th Street Minneapolis, MN 55435-4803 Phone: (952) 832-2600 Fax: (952) 832-2601 Burnsville Stormwater Retrofit

More information

DESIGN OF STORM WATER DETENTION POND

DESIGN OF STORM WATER DETENTION POND Yunnan Chuxiong Urban Environment Improvement Project (RRP PRC 45507) DESIGN OF STORM WATER DETENTION POND A. Background 1. Chuxiong Yi Autonomous Prefecture (Chuxiong prefecture) is located at about 160

More information

1.7.0 Floodplain Modification Criteria

1.7.0 Floodplain Modification Criteria 1.7.0 Floodplain Modification Criteria 1.7.1 Introduction These guidelines set out standards for evaluating and processing proposed modifications of the 100- year floodplain with the following objectives:

More information

Permeable Interlocking Concrete Pavements

Permeable Interlocking Concrete Pavements Permeable Interlocking Concrete Pavements Program 000003 Revised 1-29-08 Permeable Interlocking Concrete Pavements This program is registered with the AIA/CES and ASLA CPE for continuing education professional

More information

Pollution Control NEW! NEW! Stormwater Attenuation Systems Sustainable Urban Drainage Solutions for Domestic & Commercial Applications. klargester.

Pollution Control NEW! NEW! Stormwater Attenuation Systems Sustainable Urban Drainage Solutions for Domestic & Commercial Applications. klargester. Pollution Control NEW! NEW! Stormwater Attenuation Systems Sustainable Urban Drainage Solutions for Domestic & Commercial Applications klargester.com Stormwater Attenuation Systems Sustainable Urban Drainage

More information

MODULE 2 RULES RELATING RULES RELA

MODULE 2 RULES RELATING RULES RELA MODULE 2 RULES RELATING TO STORM DRAINAGE STANDARDS MODULE 2 RULES RELATING TO STORM DRAINAGE STANDARDS 1 RULES RELATING TO STORM DRAINAGE STANDARDS Sections that underwent revision 1-11 PURPOSE 1-2 MODIFICATIONS

More information

Next Generation Flood Alert in Houston

Next Generation Flood Alert in Houston Next Generation Flood Alert in Houston Philip B. Bedient Civil and Environmental Eng., Rice University Houston, TX Major Causes of Urban Flooding (Excess Water that Inundates) Highly Developed (urbanized)

More information

CHAPTER 7 STORM WATER DESIGN

CHAPTER 7 STORM WATER DESIGN CITY OF BOULDER DESIGN AND CONSTRUCTION STANDARDS CHAPTER 7 STORM WATER DESIGN TABLE OF CONTENTS Section Page 7.01 GENERAL...4 (A) INTENT... 4 (B) STORM WATER AND GREENWAYS MASTER PLANS... 4 (C) REFERENCE

More information

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection

More information

8.1.3 General Design Guidelines. The following guidelines shall be used when designing inlets along a street section:

8.1.3 General Design Guidelines. The following guidelines shall be used when designing inlets along a street section: . Introduction Presented in this chapter are the criteria and methodology for design and evaluation of storm sewer inlets located in Town of Castle Rock. The review of all planning submittals will be based

More information

CHAPTER 17: STORM SEWER STANDARDS. 17.00 Introduction. 17.01 Administration. 17.02 Standards 17.1

CHAPTER 17: STORM SEWER STANDARDS. 17.00 Introduction. 17.01 Administration. 17.02 Standards 17.1 CHAPTER 17: STORM SEWER STANDARDS 17.00 Introduction 17.01 Administration 17.02 Standards 17.1 17.00 INTRODUCTION The purpose of this chapter is to provide guidance for the design and construction of storm

More information

CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE

CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE 1008 STORM DRAINAGE (3/24/05) 1008.01 PURPOSE To minimize the amount of stormwater runoff resulting from development utilizing nonstructural controls where possible, maintain and improve water quality,

More information

Follow the Drop. Activity Overview Students observe and collect information about water runoff on their school property. Objective Students will:

Follow the Drop. Activity Overview Students observe and collect information about water runoff on their school property. Objective Students will: Follow the Drop Activity Overview Students observe and collect information about water runoff on their school property. Objective Students will: Practice observation and investigative skills Survey and

More information

3.4 DRAINAGE PLAN. 3.4.1 Characteristics of Existing Drainages. 3.4.2 Master Drainage System. Section 3: Development Plan BUTTERFIELD SPECIFIC PLAN

3.4 DRAINAGE PLAN. 3.4.1 Characteristics of Existing Drainages. 3.4.2 Master Drainage System. Section 3: Development Plan BUTTERFIELD SPECIFIC PLAN 3.4 DRAINAGE PLAN This section describes the existing onsite drainage characteristics and improvements proposed within this Specific Plan. Following this description, drainage plan development standards

More information

Watershed Modeling System

Watershed Modeling System Watershed Modeling System WMS v8.0 MARICOPA COUNTY TUTORIALS TABLE OF CONTENTS 1 MARICOPA COUNTY: NFF AND HEC-1... 1-1 1.1 OBJECTIVES... 1-1 1.2 DELINEATING THE WATERSHED... 1-1 1.3 BUILDING THE NFF SIMULATION...

More information

6-1 Introduction. 1. Storm drain that does not require pressure testing. 2. Lateral that does not require pressure testing.

6-1 Introduction. 1. Storm drain that does not require pressure testing. 2. Lateral that does not require pressure testing. Chapter 6 Storm Drains 6-1 Introduction A storm drain (storm sewer) is a network of pipes that conveys surface drainage from a surface inlet or through a manhole, to an outfall. Storm drains are defined

More information

BLACK/HARMONY/FAREWELL CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT

BLACK/HARMONY/FAREWELL CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT Harmony Creek subwatershed Harmony Creek subwatershed BLACK/HARMONY/FAREWELL CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT April 2011 TABLE OF CONTENTS 1.0 INTRODUCTION...

More information

LYNDE CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT

LYNDE CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT Whitby CLOCA Whitby CLOCA LYNDE CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT June 2008 TABLE OF CONTENTS 1.0 INTRODUCTION... 3 2.0 STUDY AREA AND SCOPE... 4 3.0 METHODOLOGY...

More information

Stormwater Management Functional Servicing Report

Stormwater Management Functional Servicing Report Stormwater Management Functional Servicing Report Part of Lot 12, Concession 10 Township of Cavan Monaghan Ian Cameron Rural Subdivision Engage Project No. 14016 Engage Engineering Ltd. January 7, 2015

More information

Appendix 3 Water-Harvesting Earthworks Calculations

Appendix 3 Water-Harvesting Earthworks Calculations Appendix 3 Water-Harvesting Earthworks Calculations List of Equations and Other Information Box A3.1. Abbreviations, Conversions, and Constants for English and Metric Measurement Units Equation 1. Catchment

More information

APPENDIX A: STORMWATER MANAGEMENT CHECKLIST

APPENDIX A: STORMWATER MANAGEMENT CHECKLIST APPENDIX A: STORMWATER MANAGEMENT CHECKLIST The first thing that applicants and designers must do before beginning a project is to make sure they are familiar with the 11 minimum standards listed in Manual

More information

ROSE CREEK WATERSHED HYDROLOGIC, HYDRAULIC, SEDIMENT TRANSPORT, AND GEOMORPHIC ANALYSES TASK 1 EXISTING DATA AND INFORMATION SUMMARY REPORT BACKGROUND

ROSE CREEK WATERSHED HYDROLOGIC, HYDRAULIC, SEDIMENT TRANSPORT, AND GEOMORPHIC ANALYSES TASK 1 EXISTING DATA AND INFORMATION SUMMARY REPORT BACKGROUND ROSE CREEK WATERSHED HYDROLOGIC, HYDRAULIC, SEDIMENT TRANSPORT, AND GEOMORPHIC ANALYSES TASK 1 EXISTING DATA AND INFORMATION SUMMARY REPORT BACKGROUND The Rose Creek Watershed (RCW) consists of three planning

More information

Stormwater Design Guidelines Frequently Asked Questions:

Stormwater Design Guidelines Frequently Asked Questions: 525 Golden Gate, 11th Floor San Francisco, CA 94102 T 415.551.4694 F 415.934.5728 TTY 415.554.3488 Stormwater Design Guidelines Frequently Asked Questions: A. GENERAL INQUIRIES... 2 1. What projects are

More information

Planning, Health and Environment Division

Planning, Health and Environment Division 18 Planning, Health and Environment Division A Planning Guide to Sustainable Drainage Systems Introduction Working in co-operation with the Environment Agency, Severn Trent Water Ltd., the Highway Authority

More information

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations

More information

2011 HYDRAULICS MANUAL

2011 HYDRAULICS MANUAL STATE OF LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT P.O. Box 94245 Baton Rouge, Louisiana 70804-9245 http://www.dotd.la.gov/ HYDRAULICS MANUAL Hydraulics (225) 379-1306 PREFACE The following

More information

ORDINANCE NO. 89-04-09 AN ORDINANCE TO ESTABLISH REGULATIONS AND STANDARDS FOR STORM DRAINAGE FACILITIES

ORDINANCE NO. 89-04-09 AN ORDINANCE TO ESTABLISH REGULATIONS AND STANDARDS FOR STORM DRAINAGE FACILITIES Bill No. 86-13 ORDINANCE NO. 89-04-09 AN ORDINANCE TO ESTABLISH REGULATIONS AND STANDARDS FOR STORM DRAINAGE FACILITIES The Berkeley County Council hereby adopts the following provisions: 1) Definitions

More information

1 in 30 year 1 in 75 year 1 in 100 year 1 in 100 year plus climate change (+30%) 1 in 200 year

1 in 30 year 1 in 75 year 1 in 100 year 1 in 100 year plus climate change (+30%) 1 in 200 year Appendix C1 Surface Water Modelling 1 Overview 1.1 The Drain London modelling was designed to analyse the impact of heavy rainfall events across each London borough by assessing flow paths, velocities

More information

TECHNICAL MEMORANDUM STORM DRAIN SYSTEM DESIGN EVALUATION CRITERIA. For CITY OF YREKA WILLDAN. July 14, 2006

TECHNICAL MEMORANDUM STORM DRAIN SYSTEM DESIGN EVALUATION CRITERIA. For CITY OF YREKA WILLDAN. July 14, 2006 TECHNICAL MEMORANDUM STORM DRAIN SYSTEM DESIGN & EVALUATION CRITERIA For CITY OF YREKA By WILLDAN July 14, 2006-1 - STORM DRAIN SYSTEM DESIGN & EVALUATION CRITERIA I GENERAL Storm drainage improvements

More information

Low Impact Development Checklist

Low Impact Development Checklist New Jersey Stormwater Best Management Practices Manual February 2004 A P P E N D I X A Low Impact Development Checklist A checklist for identifying nonstructural stormwater management strategies incorporated

More information

CHAPTER 4 STORM DRAINAGE SYSTEMS

CHAPTER 4 STORM DRAINAGE SYSTEMS CHAPTER 4 STORM DRAINAGE SYSTEMS 4.1 Overview... 4-1 4.1.1 Introduction... 4-1 4.1.2 Inlet Definition... 4-1 4.1.3 Criteria... 4-1 4.2 Pavement Drainage... 4-2 4.2.1 Introduction... 4-2 4.2.2 Storm Drain

More information

Chapter 4. Flood Risk Assessment

Chapter 4. Flood Risk Assessment Chapter 4 Flood Risk Assessment Chapter Overview Any floodplain management program must be established on a sound technical and scientific basis in order to be effective, whether for flood loss reduction

More information

CHAPTER 5 OPEN CHANNEL HYDROLOGY

CHAPTER 5 OPEN CHANNEL HYDROLOGY 5.4 Uniform Flow Calculations 5.4.1 Design Charts CHAPTER 5 OPEN CHANNEL HYDROLOGY Following is a discussion of the equations that can be used for the design and analysis of open channel flow. The Federal

More information

WETLAND RESTORATION PROGRAM WATER ACT APPROVAL ADMINISTRATIVE GUIDE

WETLAND RESTORATION PROGRAM WATER ACT APPROVAL ADMINISTRATIVE GUIDE WETLAND RESTORATION PROGRAM WATER ACT APPROVAL ADMINISTRATIVE GUIDE May 24, 2005 Table of Contents Introduction...3 Definitions...3 Types of Wetland Restorations...4 Re-Contouring...4 Engineered...4 Water

More information

Lower Raritan Watershed Management Area Stormwater & Flooding Subcommittee Strategy Worksheet LRSW-S3C1

Lower Raritan Watershed Management Area Stormwater & Flooding Subcommittee Strategy Worksheet LRSW-S3C1 Strategy Name: Reduce Existing Potential for Flood Damages LRSW-S3C1. Develop and implement a program to: Minimize flood damages through the use of structural measures. Minimize flood damages through the

More information

Estimating Potential Reduction Flood Benefits of Restored Wetlands

Estimating Potential Reduction Flood Benefits of Restored Wetlands Estimating Potential Reduction Flood Benefits of Restored Wetlands Kenneth W. Potter University of Wisconsin Introduction Throughout the summer of 1993 a recurring question was the impact of wetland drainage

More information

UNIFIED FACILITIES CRITERIA (UFC) LOW IMPACT DEVELOPMENT

UNIFIED FACILITIES CRITERIA (UFC) LOW IMPACT DEVELOPMENT UNIFIED FACILITIES CRITERIA (UFC) LOW IMPACT DEVELOPMENT APPROVED FOR PUBLIC RELEASE; DISTRIBUTION UNLIMITED UNIFIED FACILITIES CRITERIA (UFC) LOW IMPACT DEVELOPMENT Any copyrighted material included in

More information

RAINWATER HARVESTING FOR DRYLANDS - VOLUME 1. By Brad Lancaster, 2006. Appendix 3. Water-Harvesting Calculations

RAINWATER HARVESTING FOR DRYLANDS - VOLUME 1. By Brad Lancaster, 2006. Appendix 3. Water-Harvesting Calculations RAINWATER HARVESTING FOR DRYLANDS - VOLUME 1 By Brad Lancaster, 2006 Appendix 3 Water-Harvesting Calculations List of Equations and Other Information Box A3.1. Abbreviations, Conversions, and Constants

More information

ENGINEERING DESIGN GUIDELINES. for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS

ENGINEERING DESIGN GUIDELINES. for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS ENGINEERING DESIGN GUIDELINES for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS City of Birmingham Department of Planning, Engineering and Permits Engineering Division Office of the City Engineer 2008 TABLE

More information

Hydrologic Modeling using HEC-HMS

Hydrologic Modeling using HEC-HMS Hydrologic Modeling using HEC-HMS Prepared by Venkatesh Merwade School of Civil Engineering, Purdue University vmerwade@purdue.edu April 2012 Introduction The intent of this exercise is to introduce you

More information

Project Manager. Geoff Masotti, P.Eng. T. 905.940.6161 Ext. 254 T. 905.940.6161 416.987.6161

Project Manager. Geoff Masotti, P.Eng. T. 905.940.6161 Ext. 254 T. 905.940.6161 416.987.6161 Rainbow Creek Master Plan Update Study The City of Vaughan june 2014 COLE ENGINEERING GROUP LTD. 70 Valleywood Drive Project Manager. Geoff Masotti, P.Eng. Markham, ON CANADA L3R 4T5 T. 905.940.6161 Ext.

More information

2D Modeling of Urban Flood Vulnerable Areas

2D Modeling of Urban Flood Vulnerable Areas 2D Modeling of Urban Flood Vulnerable Areas Sameer Dhalla, P.Eng. Dilnesaw Chekol, Ph.D. A.D. Latornell Conservation Symposium November 22, 2013 Outline 1. Toronto and Region 2. Evolution of Flood Management

More information

SECTION 5: SANITARY SEWER SYSTEM DESIGN

SECTION 5: SANITARY SEWER SYSTEM DESIGN SECTION 5: SANITARY SEWER SYSTEM DESIGN 5.01 GENERAL Sanitary sewer improvements shall be designed to serve the ultimate level of City development as defined in the General Plan and the Wastewater Facilities

More information

MARSHALL COUNTY STORM DRAINAGE AND SEDIMENT CONTROL ORDINANCE. ralphb [Pick the date]

MARSHALL COUNTY STORM DRAINAGE AND SEDIMENT CONTROL ORDINANCE. ralphb [Pick the date] MARSHALL COUNTY STORM DRAINAGE AND SEDIMENT CONTROL ORDINANCE ralphb [Pick the date] MARSHALL COUNTY, INDIANA STORM DRAINAGE AND SEDIMENT CONTROL ORDINANCE An Ordinance applicable to the County Commissioner

More information

Sanitary Sewer Overflow (SSO) Incident Report Form

Sanitary Sewer Overflow (SSO) Incident Report Form Submit completed form to EHS. Date of SSO spill: Sanitary Sewer Overflow (SSO) Incident Report Form Identify the SSO category (check one): Category 1 SSO Spills of any volume that reach surface water Category

More information

City of La Quinta Public Works Department - Storm Drain Plan Review Checklist

City of La Quinta Public Works Department - Storm Drain Plan Review Checklist Tract or Parcel Project Name PCN Checked By Date City of La Quinta Public Works Department - Storm Drain Plan Review Checklist SUBMITTAL REQUIREMENTS Approved Tentative Tract Map Conditions of Approval

More information

CHAPTER 9 STORM DRAINAGE DESIGN AND STORMWATER QUALITY REGULATIONS

CHAPTER 9 STORM DRAINAGE DESIGN AND STORMWATER QUALITY REGULATIONS June 27, 2011 Chapter 9 Storm Drainage Design and Stormwater Quality Regulations Table of Contents CHAPTER 9 STORM DRAINAGE DESIGN AND STORMWATER QUALITY REGULATIONS Table of Contents Chapter 9 Storm Drainage

More information

From Civil 3D, with Love

From Civil 3D, with Love From Civil 3D, with Love Download the zip file containing the files needed for the exercise. Extract the files to a convenient location on your hard drive before you begin. The files associated with this

More information

5.14 Floodplains and Drainage/Hydrology

5.14 Floodplains and Drainage/Hydrology I-70 East Final EIS 5.14 Floodplains and Drainage/Hydrology 5.14 Floodplains and Drainage/Hydrology This section discusses floodplain and drainage/hydrology resources and explains why they are important

More information

Appendix 4-C. Open Channel Theory

Appendix 4-C. Open Channel Theory 4-C-1 Appendix 4-C Open Channel Theory 4-C-2 Appendix 4.C - Table of Contents 4.C.1 Open Channel Flow Theory 4-C-3 4.C.2 Concepts 4-C-3 4.C.2.1 Specific Energy 4-C-3 4.C.2.2 Velocity Distribution Coefficient

More information

GRAND COUNTY STORM DRAINAGE DESIGN AND TECHNICAL CRITERIA MANUAL. OFFICIALLY ADOPTED: August 1 st, 2006

GRAND COUNTY STORM DRAINAGE DESIGN AND TECHNICAL CRITERIA MANUAL. OFFICIALLY ADOPTED: August 1 st, 2006 GRAND COUNTY STORM DRAINAGE DESIGN AND TECHNICAL CRITERIA MANUAL OFFICIALLY ADOPTED: August 1 st, 2006 TABLE OF CONTENTS CHAPTER TITLE PAGE 1 GENERAL PROVISIONS 1.1 Short Title.. 1 1.2 Jurisdiction 1 1.3

More information