Project Management and Planning
|
|
- Myrtle Sanders
- 7 years ago
- Views:
Transcription
1 Project Management and Planning Project: Is defined as a set of interrelated activities that must be executed in a particular order to complete an entire task. Concerned With: Time of completion Costs Available resources Gantt Chart: First scientific technique for planning a project Two Modern Techniques fixed. CPM - Critical Path Method - Developed by Kelly & Walker (1959) - Activity Times are PERT - Program Evaluation & Review Technique - Booze, Allen, Hamilton & US Navy ( 1959). Activity times are probabilistic. - Both used widely in large complex projects. - Construction industry - widely used (80%) - One time large projects - Spaceship construction Requirements for Projects 1. Well defined activities Install Roof weeks Install Ducts for A/C & Heating weeks. Some Activities may be started & finished independently 3. Some activities may require completion of other activities Roof can be installed Truss is built. 4. If an activity is started, it must be completed without interruption
2 Network Representation of a Project Examples (i) Project and activities represented by a network Network is a graph showing each activity to be performed, its predecessor & successor Activity: Represented by an arrow - generally needs some resource for its performance - Use letters Nodes: Activities end or start at points called nodes Represented by circles/ Use numbers Event: A point in time Dummy Activity: Uses no resources & is used for showing precedence requirements only 1 A B 3 (ii) When A is started it must be finished. Needs two nodes. B cannot be started before A is finished. 1 A B
3 Two activities cannot start and end at same nodes. Use dummy activity. We must use one of the following: 1 A B 3 1 B A 3 Precedence; Both B and A need to No precedence; B starts after and A Start after 1 Starts after 1 ****************************************** Establishment of Critical Path Critical Path: Minimum time needed for completion of project. Method: Sequence of activities with no slack time - Add times of all these activities Slack: Is determined by finding earliest/latest start and finish times. Earliest Starting Time: Earliest time an activity can be started when all preceding activities are completed as quickly as possible. Earliest Finish Time: EF = ES + t, (t = time for an activity) Latest Starting Time: Latest time when an activity can be started (for finishing project in appropriate time) Latest Finish Time: LF = LS + t or LS = LF - t We first develop a network diagram. Then we find ES, EF moving forward in the network and LS, LF by moving backward in the network.
4 Then Slack = LS - ES or Slack = LF - EF Example Activity Predecessor Time A * 0 B A C B 4 D C 6 E C 3 F C 5 G D,E,F 5 H G 7 First draw a network flow diagram. A,0 1 B, C,4 D,6 3 G,8 4 7 H,7 8 9 E,3 6 F,5 5 At each node, one or more activities can start or finish. In Forward Pass, we start at a node and find ES and EF time for each activity (a) ES for activity starting at a node is EF. This is maximum of all ES that End at this node.
5 (b) EF for activity is (ES + time) Forward Pass Calculations Node 1: Only A starts and none ends A: ES = 0 EF = ES+ t = = 0 Node : B starts and A ends B: ES = EF for A = 0 EF = ES + t = 0 + = Node 3: C starts and B ends C: ES = EF for B = EF = + 4 = 6 Node 4: D, E, F start and C ends. EF for all is 6 D: EF = = 1 E: EF = = 9 F: EF = = 11 Nodes 5 and 6 are Dummy nodes Node 7 : G starts and D, E, and F end. As more than one activities end, we must Use maximum EF as ES for G ES for G = Maximum of {EF for D, E, F} = 1 EF for G = ES + time = = 0 Node 8: H starts and G ends EF for H = = 7 Node 9: None starts and H ends. End of the project. Backward Pass
6 We move back from the last node to the first node for finding LS and LF Recall LF = latest finish time for an activity And LS = LF - time of activity Node 9 H ends /None starts H; LF = Project completion time = 7 LS = 7-7 = 0 Node 8 G ends/ H starts G; LF = LS for H = 0 LS = 0-8 = 1 Node 7 D, E, F end / G starts. D; LF = LS for G = 1 LS = 1-3 = 9 E; LF = LS for G = 1 LS = 1-6 = 6 F; LF = LS for G = 1 LS = 1-5 = 7 Node 6 & 5 These are Dummy Nodes Node 4 D, E, F end/ E starts C; LF = Minimum LS {D, E, F} = Minimum {9, 6,7} = 6 LS = 6-4 = Node 3 B ends /E starts B; LF= LS for C = LS = - = 0 Node A ends/b starts A; LF = LS for B = 0 LS = 0-0 = 0 Node 1 A ends/none starts Done
7 Alternate Way of writing ES, EF, LS, and LF: We write the times on the network flow diagram for each activity in a box as shown. ************************************************* Slack for each activity: Difference between LS and ES or LF and EF Slack = LS - ES or Slack = LF - EF Using LS and ES, slack for each activity is shown below: Activity ES LS Slack Critical Path A * B * C 0 * D * E F 6 7 1
8 G * H * Activities on the Critical Path have no Slack Critical Path: A, B, C, D, G, H Critical Path Time: = 7 All other paths take less time Example: A, B, C, E, G, H = 4 days Estimating activity time We have assumed, so far, that the time for completing an activity is known for sure. This may not be true in real life. Time for completion of an activity is uncertain and follows some probability function. We are interested in finding probabilities for completion of a project. One commonly used probability function for activity time is Beta distribution. The parameters for Beta distribution can be estimated relatively easily. Estimates of most likely, optimistic and pessimistic times are needed. Example: Most likely time (m) = 6 days Optimistic time (a) Pessimistic time (b) = 3 days = 15 days We can use normal distribution for finding various probabilities. Mean for Normal = {a + 4m + b)}/{6} = {3 + 4(6) + (15)}/{6} = 7days Standard Deviation = {b - a}/{6} = {15-3}/{6} = days
9 Project Completion Time A project consists of many activities, each of which approximately follow a normal distribution with known mean and standard deviation. For project completion time, we need to consider only activities on the Critical Path. Let t i = mean completion time of the ith activity s i = variance of completion time of ith activity Then Mean completion time of project = T m = t i Variance of completion time = s = s i Determination of Probability of Completion Time for a Project Let us suppose that the mean completion time of a project is 7 days and variance is 36 days. The probability that the project can be completed in 9 days or more can be calculated using the normal distribution. Let x be completion time z = (x - Mean)/(standard Deviation) = (9-7)/ (6) = Using Normal tables P(x>9) = P(z>0.333) = This means that there is 37.07% chance that project will finish in more than 9 days. Generally, there is penalty for not completing a project in time. If it is so, one may consider
10 assigning extra resources to some of the activities to make sure that project will finish in time. But this extra cost must be balanced against the possibility of incurring An Example 3 J,9 B,1 A,8 1 D,3 4 E,1 I,7 6 8 C,7 5 H, K,6 7 L,10 Find ES, LS, EF, and LF Find Slack Critical Path: A, E, K, and L Critical Path time is = 36 days (i) Find probability that project will take 34 days or less. T m = t i = = 36 days
11 s = s i = = Activity Predecessor a m b t i s i A * B * C * D A E A F A G C,F H C,F I B,D J B K E,G,I L H,K ( 34 36) / ( ) z = (x - mean)/(s) = = P { x < 34 } = P { z < } = % Only % chance that project can be completed in 34 days or less.
12 (ii) Find probability that project will be completed in 39 days or more. ( 39 36) / ( ) z = = 1.14 P { x > 39} = P { z > 1.14} = 11% Only 11% chance that project will take 39 days or more. TIME COST TRADEOFF It may be possible to reduce time needed to complete an activity by utilizing more resources (workers, machinery etc.) ---- This will result in extra costs (labor, overtime, etc.). These are increases in direct costs. Indirect costs such as supervisory, management, other overhead may be reduced because of reduced time for completing the project. In addition, there may be savings due to avoidance of penalty costs. MINIMUM COST schedule is obtained by balancing the two costs.
13 Procedure Let NT NC CT CC = normal time = completion time of an activity with normal allocation of resources = normal cost = cost associated with NT = crash time = shortest possible completion time of an activity with extra resources. = crash cost = cost/day associated with CT (assumed linear) 1. Prepare network diagram. Find ES, LS, EF, LF, slack, critical path and normal time (normal cost)schedule 3. Determine direct cost of decreasing activity time by one unit for all the activities on the critical path ---- choose activity with minimum direct cost. 4. Weigh it against the decrease in indirect cost by one unit. 5. If Indirect cost reduction > direct cost; reduce the activity by time one unit.
14 CAUTION: Make sure that critical path does not change. 6. Go step # 3 and repeat till minimum cost schedule is obtained. An Example A,3 C, D,4 4 F,3 1 G,4 H, B,4 E,4 3 Activity Normal Time Crash Time Crash Cost/Day A 3 $00 B 4 $150 C * D 4 3 $300 E 4 3 $450 F 3 1 $50 G 4 $0 H 4 3 $300 Critical Path is A, D, G, H Normal Time for critical path = = 15 days
15 I. Minimum direct cost activity on the critical path is A (00/day) Savings/day = 500 We use extra resources and reduce activity time of A by one day (3 to days) Critical path time = 14 days Savings = = 300 Note: Critical path is still the same II Minimum direct cost activity is G (Note: A cannot be reduced) We can take days out of G Savings = (500) - (0) = 560 Critical path time is 1 days All other paths also take 1 days. This means if one day is reduced on one path it must be reduced on all the other paths. III Use minimum direct cost activity Take 1 day out of B; cost is 150 Take 1 day out of H; cost is 300 Savings = ( ) = 50 Critical path is 11 days IV Take 1 day out of B; cost is 150 Reduce D by 1 day; cost is 300 Reduce F by 1 day; cost is 50 Total cost is 700; more than savings of 500/day V Optimal (Minimum cost) critical path time is 11 days with total savings of or $910
16
Operational Research. Project Menagement Method by CPM/ PERT
Operational Research Project Menagement Method by CPM/ PERT Project definition A project is a series of activities directed to accomplishment of a desired objective. Plan your work first..then work your
More informationProject Planning and Scheduling
Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination
More informationProject Management Chapter 3
Project Management Chapter 3 How Project Management fits the Operations Management Philosophy Operations As a Competitive Weapon Operations Strategy Project Management Process Strategy Process Analysis
More informationNetwork Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration
Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Prof. M. Rammohan Rao Former Dean Professor Emeritus Executive Director, Centre for Analytical
More informationME 407 Mechanical Engineering Design Spring 2016
ME 407 Mechanical Engineering Design Spring 2016 Project Planning & Management Asst. Prof. Dr. Ulaş Yaman Acknowledgements to Dieter, Engineering Design, 4 th edition Ullman, The Mechanical Design Process,
More informationCISC 322 Software Architecture. Project Scheduling (PERT/CPM) Ahmed E. Hassan
CISC 322 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan Project A project is a temporary endeavour undertaken to create a "unique" product or service A project is composed of a number
More informationCambridge International AS and A Level Computer Science
Topic support guide Cambridge International AS and A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains
More informationPROJECT COMPLETION PROBABILITY AFTER CRASHING PERT/CPM NETWORK
PROJECT COMPLETION PROBABILITY AFTER CRASHING PERT/CPM NETWORK M Nazrul, ISLAM 1, Eugen, DRAGHICI 2 and M Sharif, UDDIN 3 1 Jahangirnagar University, Bangladesh, islam_ju@yahoo.com 2 Lucian Blaga University
More informationProject Scheduling: PERT/CPM
Project Scheduling: PERT/CPM CHAPTER 8 LEARNING OBJECTIVES After completing this chapter, you should be able to: 1. Describe the role and application of PERT/CPM for project scheduling. 2. Define a project
More informationThe work breakdown structure can be illustrated in a block diagram:
1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as
More information10 Project Management with PERT/CPM
10 Project Management with PERT/CPM 468 One of the most challenging jobs that any manager can take on is the management of a large-scale project that requires coordinating numerous activities throughout
More informationB. 2-4-6 D. 3-4-5 E. 3-5-7 F. 5-7-9
Lesson 01 Project Management Solutions #1: The network diagram for a project is shown below, with three time estimates (optimistic, most likely, and pessimistic) for each activity. Activity times are in
More informationScheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
More informationProject Management SCM 352. 2011 Pearson Education, Inc. publishing as Prentice Hall
3 Project Management 3 SCM 35 11 Pearson Education, Inc. publishing as Prentice Hall Boeing 787 Dreamliner Delays are a natural part of the airplane supply business. They promise an unreasonable delivery
More informationNetwork Calculations
Network Calculations The concepts and graphical techniques described in this week s readings form the basis of the tools widely used today to manage large projects. There is no way of simplifying the tasks
More informationPROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM)
PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM) Project Evaluation Review Technique (PERT) and Critical Path Method (CPM) are scheduling techniques used to plan, schedule, budget
More information22 Project Management with PERT/CPM
hil61217_ch22.qxd /29/0 05:58 PM Page 22-1 22 C H A P T E R Project Management with PERT/CPM One of the most challenging jobs that any manager can take on is the management of a large-scale project that
More information8. Project Time Management
8. Project Time Management Project Time Management closely coordinated Two basic approaches -bottom-up (analytical) -top-down (expert judgement) Processes required to ensure timely completion of the project
More informationProject Scheduling: PERT/CPM
Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times (as in exercises 1, 2, 3 and 5 in the handout) and considering Time-Cost Trade-Offs (as in exercises 4 and 6 in the handout). This
More informationPROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT)
PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT) ABSTRACT Category: Planning/ Monitoring - Control KEYWORDS Program (Project) Evaluation and Review Technique (PERT) (G) is a project management tool used
More informationProject Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
More informationNetwork analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition:
Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition: 1. Activity : It is a particular work of a project which consumes some resources (in ) & time. It is shown as & represented
More informationMECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor (hefny@cs.queensu.ca and surgenor@me.queensu.ca) Winter : Lecture # Project Time Management Homework Discussion Homework
More informationtechnical tips and tricks
technical tips and tricks Performing critical path analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the
More informationChapter 4: Project Time Management
Chapter 4: Project Time Management Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
More informationLecture 26 CPM / PERT Network Diagram
Lecture 26 CPM / PERT Network Diagram 26.1 Introduction to CPM / PERT Techniques CPM (Critical Path Method) was developed by Walker to solve project scheduling problems. PERT (Project Evaluation and Review
More informationBasic Concepts. Project Scheduling and Tracking. Why are Projects Late? Relationship between People and Effort
Basic s Project Scheduling and Tracking The process of building a schedule for any case study helps really understand how it s done. The basic idea is to get across to break the software project into well-defined
More informationScheduling. Anne Banks Pidduck Adapted from John Musser
Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart
More informationChapter-6. Developing a Project Plan
MGMT 4135 Project Management Chapter-6 Where we are now Developing the Project Network Why? Graphical representation of the tasks to be completed Logical sequence of activities Determines dependencies
More informationProject Management DISCUSSION QUESTIONS
3 C H A P T E R Project Management DISCUSSION QUESTIONS. There are many possible answers. Project management is needed in large construction jobs, in implementing new information systems, in new product
More informationChapter 11 Monte Carlo Simulation
Chapter 11 Monte Carlo Simulation 11.1 Introduction The basic idea of simulation is to build an experimental device, or simulator, that will act like (simulate) the system of interest in certain important
More informationChapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072
Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define
More informationProject and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking
More informationProject Scheduling and Gantt Charts
Project Scheduling and Gantt Charts Siddharth Gangadhar Dr. Prasad Kulkarni Department of Electrical Engineering & Computer Science Lab Presentation siddharth@ku.edu prasadk@ku.edu 4 November 2015 2015
More informationChapter 11: PERT for Project Planning and Scheduling
Chapter 11: PERT for Project Planning and Scheduling PERT, the Project Evaluation and Review Technique, is a network-based aid for planning and scheduling the many interrelated tasks in a large and complex
More informationGoals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management
Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute
More informationScheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org
Planning and Managing Software Projects 2011-12 Class 9 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides
More informationPriori ty ... ... ...
.Maintenance Scheduling Maintenance scheduling is the process by which jobs are matched with resources (crafts) and sequenced to be executed at certain points in time. The maintenance schedule can be prepared
More informationScheduling Resources and Costs
Student Version CHAPTER EIGHT Scheduling Resources and Costs McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Gannt Chart Developed by Henry Gannt in 1916 is used
More informationSE351a: Software Project & Process Management
SE351a: Software Project & Process Management W8: Software Project Planning 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa SE351 Roadmap Introduction to Software Project Management Project Management
More informationProject Management Glossary
Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project
More informationAppendix A of Project Management. Appendix Table of Contents REFERENCES...761
Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity
More informationChapter 6: Project Time Management
CIS 486 Managing Information Systems Projects Fall 2003 (Chapter 6), PhD jwoo5@calstatela.edu California State University, LA Computer and Information System Department Chapter 6: Project Time Management
More informationUse project management tools
Use project management tools Overview Using project management tools play a large role in all phases of a project - in planning, implementation, and evaluation. This resource will give you a basic understanding
More informationChapter 2: Project Time Management
Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.
More informationProject management: a simulation-based optimization method for dynamic time-cost tradeoff decisions
Rochester Institute of Technology RIT Scholar Works Theses Thesis/Dissertation Collections 2009 Project management: a simulation-based optimization method for dynamic time-cost tradeoff decisions Radhamés
More informationA. O. Odior Department of Production Engineering University of Benin, Edo State. E-mail: waddnis@yahoo.com
2012 Cenresin Publications www.cenresinpub.org APPLICATION OF PROJECT MANAGEMENT TECHNIQUES IN A CONSTRUCTION FIRM Department of Production Engineering University of Benin, Edo State. E-mail: waddnis@yahoo.com
More informationPERT/CPM. Network Representation:
- 1 - PERT/CPM PERT Program Evaluation & Review Technique It is generally used for those projects where time required to complete various activities are not known as a priori. It is probabilistic model
More informationApplication Survey Paper
Application Survey Paper Project Planning with PERT/CPM LINDO Systems 2003 Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) are two closely related techniques for monitoring
More informationIntroduction to Project Management
L E S S O N 1 Introduction to Project Management Suggested lesson time 50-60 minutes Lesson objectives To be able to identify the steps involved in project planning, you will: a b c Plan a project. You
More informationChapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False
Chapter 1.7 Project Management Part I: Objective type questions and answers 1. Project financing is one of the step of project management- State True or False 2. Proposed new technologies, process modifications,
More information12 Network Scheduling Techniques
Page 671 12 Network Scheduling Techniques 12.0 Introduction Management is continually seeking new and better control techniques to cope with the complexities, masses of data, and tight deadlines that are
More informationMarch 30, 2007 CHAPTER 4
March 30, 07 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE Chapter Outline 4.1 Background What was the cause of the desperation that lead to the development of the Program Evaluation and Review
More informationONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS
ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS Chapter 3 of Systems Analysis and Design in a Changing World explains the techniques and steps required to build a project schedule
More informationCPM-200: Principles of Schedule Management
CPM-: Principles of Schedule Management Lesson B: Critical Path Scheduling Techniques Instructor Jim Wrisley IPM Fall Conference PMI-College of Performance Management Professional Education Program Copyright
More informationProject Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps
Project Planning What are you going to do in the project? Lecture Objectives To discuss the tasks in planning a project To describe the tools that can be used for developing a project plan To illustrate
More informationNetwork Planning and Analysis
46 Network Planning and Analysis 1. Objective: What can you tell me about the project? When will the project finish? How long will the project take (project total duration)? 2. Why is this topic Important
More informationCRITICAL PATH METHOD (CEE 320 VDC SEMINAR)
CRITICAL PATH METHOD (CEE 320 VDC SEMINAR) 4 February 2009 Jesse Santiago & Desirae Magallon Overview Background & History CPM Defined The CPM approach Definitions Class Exercise Background & History Developed
More informationProject Time Management
Project Time Management By Augsburg College 1 Learning Objectives Understand the importance of project schedules and good project time management Define activities as the basis for developing project schedules
More informationModule 11. Software Project Planning. Version 2 CSE IIT, Kharagpur
Module 11 Software Project Planning Lesson 29 Staffing Level Estimation and Scheduling Specific Instructional Objectives At the end of this lesson the student would be able to: Identify why careful planning
More information7. PROJECT MANAGEMENT
7. PROJECT MANAGEMENT Syllabus Definition and scope of project, Technical design, Financing, Contracting, Implementation and performance monitoring. Implementation plan for top management, Planning Budget,
More informationDeming s 14 Points for TQM
1 Deming s 14 Points for TQM 1. Constancy of purpose Create constancy of purpose for continual improvement of products and service to society, allocating resources to provide for long range needs rather
More informationTime Management. Part 5 Schedule Development. Richard Boser
Time Management Part 5 Schedule Development Richard Boser 6.5 Schedule Development Inputs Organizational Process Assets Scope Statement Activity List Activity Attributes Network Diagrams Resource Req ms
More informationModule 3: The Project Planning Stage
Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you
More informationTest Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead
More informationProject Scheduling by PERT/CPM
Project Scheduling by PERT/PM Reference ooks: nderson, Sweeney, and Williams, N INTROUTION TO MNGEMENT SIENE, QUNTITTIVE PPROHES TO EISION MKING, th edition, West Publishing ompany,99 Hamdy. Taha, OPERTIONS
More informationA UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST
A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST Priti Singh Astt. Prof.-MCA Department OCM, Bhopal preitisingh@rediffmail.com Florentin Smarandache Chair of Department of Mathematics
More informationUnit 1: Project Planning and Scheduling
Unit : Project Planning and Scheduling Objective Ð To provide a brief introduction to project planning and scheduling. The critical area where project management meets system development. ackground Most
More informationEgypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014
Project Management Six Session Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Mohamed Khalifa, 2014 All Rights 1 7. Scheduling 2 7. Scheduling 7.1 Scheduling techniques 7.3 Critical path method
More informationTest Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen + Antworten October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 1 All the following Statements about a WBS are true except that it a. Provides a framework for
More informationCollaborative Scheduling using the CPM Method
MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines
More informationMnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Schedule Float Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar
More informationNotes on the Critical Path Method for project planning and management.
E90 Engineering Design Notes on the Critical Path Method for project planning and management. CPM models any project by a network of blocks or circles called NODES that are connected by lines called ARROWS.
More informationNetwork analysis and building construction: Implications for timing and costing of activities
Journal of Civil Engineering and Construction Technology Vol. 2(5), pp. 90-100, May 2011 Available online at http://www.academicjournals.org/jcect ISSN 2141-2634 2011 Academic Journals Full Length Research
More informationEdExcel Decision Mathematics 1
EdExcel Decision Mathematics 1 Notes and Examples Critical Path Analysis Section 1: Activity networks These notes contain subsections on Drawing an activity network Using dummy activities Analysing the
More informationGuidance on Critical Path Analysis
Guidance on Critical Path Analysis OCR GCE in Applied Business Unit F248 (Unit 9): Strategic Decision Making As part of the assessment for Unit F248 Strategic Decision-Making the examination may contain
More informationInformation Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project
More informationCRASHING PERT NETWORKS: A SIMULATION APPROACH
CRASHING PERT NETWORKS: A SIMULATION APPROACH Wayne A. Haga Assistant Professor of Computer Information Systems Metropolitan State College of Denver P.O. Box 173362, Campus Box 45 Denver, CO 80217-3362
More informationSWEN 256 Software Process & Project Management
SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end
More informationChapter 6 (part 1) Project Time Management. (Project Scheduling)
Chapter 6 (part 1) Project Time Management. (Project Scheduling) 1 Objectives Understand the process of project decomposition into activities Understand the level of details required for activities Understand
More informationNetwork diagrams in context
PM Network diagrams in context SOW CHARTER SCOPE DEFINITION WBS circulation, negotiation, translation WBS WP à activities ----- estimation Time Cost GANTT PERT AOA AON - - - - - - - - - - - planning, resource
More informationANALYSIS OF PROJECT PLANNING USING CPM AND PERT
ANALYSIS OF PROJECT PLANNING USING CPM AND PERT Rogelio Acuña Spring 2010 In Partial Fulfillment of Math 4395-Senior Project Department of Computer and Mathematical Sciences Faculty Advisor: Dr. Timothy
More informationImportance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
More informationPROJECT PROPOSAL: PROJECT BLUE ZUMA
PROJECT PROPOSAL: PROJECT BLUE ZUMA To: From: CC: Dr. Edward J Glantz Alex Bok (ayb5041@psu.edu) Mark Randall Date: February 28 th, 2008 The following documents are detailed reports on our project proposal
More informationProject Scheduling & Tracking
Project Scheduling & Tracking Traditional Techniques: Work Breakdown Structure (WBS) Gantt Charts Precedence Diagrams Earned Value Planning It is the mark of an instructed mind to rest satisfied with the
More informationLearning Objectives. Learning Objectives (continued) Importance of Project Schedules
Chapter 6: Project Time Management Information Technology Project Management, Fifth Edition Learning Objectives Understand the importance of project schedules and good project time management Define activities
More informationMnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Schedule Updates Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions
More informationReview on Using Packages to Enhance the Teaching of Critical Path Networks
Review on Using Packages to Enhance the Teaching of Critical Path Networks Harry S Ku Abstract The aim of this paper is to review a published paper, Using computer software packages to enhance the teaching
More informationLecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition
Lecture 6: Project Time Management By: Prof. Lili Saghafi Information Technology Project Management, Fifth Edition Learning Objectives 2 Understand the importance of project schedules and good project
More informationProject Management 1. PROJECT MANAGEMENT...1 2. PROJECT ANALYSIS...3
Project Management What is a project? How to plan a project? How to schedule a project? How to control a project? 1. PROJECT MNGEMENT...1 2. PROJECT NLYSIS...3 3 PROJECT PLNNING...8 3.1 RESOURCE LLOCTION...8
More informationTopic: The easiest way to calculate Critical Path, Total Float, Free Float, Early Start, Early Finish, Late Start, and Late Finish.
Hot Topics & hallenges Time Management Topic: The easiest way to calculate ritical Path, Total Float, Free Float, Early, Early, Late, and Late. Presenter: Sohel khter, PMP, N,ISMS PMP and Six Sigma instructor,
More informationPrecedence Diagram Method. CSTM 462 Planning & Scheduling
Precedence Diagram Method CSTM 462 Planning & Scheduling Precedence Diagramming Method (PDM) PDM is more flexible than AON or AOA networks because PDM allows the overlapping of concurrent activities.
More informationCritical Path Analysis & PERT Charts (taken from www.business.com.
Critical Path Analysis & PERT Charts (taken from www.business.com. - Planning and scheduling more complex projects Critical Path Analysis and PERT are powerful tools that help you to schedule and manage
More informationApplication of Critical Path Method scheduling to research plan and management of graduate students research project in engineering education
OPEN ACCESS Engineering Leaders Conference 2014 Application of Critical Path Method scheduling to research plan and management of graduate students research project in engineering education M.O. Daramola
More informationProf. Olivier de Weck
ESD.36 System Project Management + Lecture 9 Probabilistic Scheduling Instructor(s) Prof. Olivier de Weck Dr. James Lyneis October 4, 2012 Today s Agenda Probabilistic Task Times PERT (Program Evaluation
More informationPROJECT MANAGEMENT Critical Path Method-- Program, Evaluation & Review Technique (CPM/PERT)
PROJECT MANAGEMENT Critical Path Method-- Program, Evaluation & Review Technique (CPM/PERT) 1 Introduction to Project Management Many people and organizations today have a new or renewed interest in project
More informationA Generalized PERT/CPM Implementation in a Spreadsheet
A Generalized PERT/CPM Implementation in a Spreadsheet Abstract Kala C. Seal College of Business Administration Loyola Marymount University Los Angles, CA 90045, USA kseal@lmumail.lmu.edu This paper describes
More informationTable of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose
1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing
More information專 案 管 理 實 務 嘉 義 縣 政 府 學 分 班 : 管 理 實 務 專 題 2006 中 正 大 學 企 管 系 助 理 教 授 周 瑞 生
專 案 管 理 實 務 嘉 義 縣 政 府 學 分 班 : 管 理 實 務 專 題 2006 中 正 大 學 企 管 系 助 理 教 授 周 瑞 生 講 師 介 紹 > 學 歷 台 灣 大 學 學 士 台 灣 大 學 碩 士 美 國 德 州 大 學 奧 斯 汀 校 區 工 程 專 案 管 理 博 士 中 華 民 國 土 木 工 程 大 地 工 程 水 土 保 持 工 程 專 門 技 術 人 員 高
More informationpm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
More information