PROJECT COMPLETION PROBABILITY AFTER CRASHING PERT/CPM NETWORK
|
|
- Iris Webster
- 4 years ago
- Views:
Transcription
1 PROJECT COMPLETION PROBABILITY AFTER CRASHING PERT/CPM NETWORK M Nazrul, ISLAM 1, Eugen, DRAGHICI 2 and M Sharif, UDDIN 3 1 Jahangirnagar University, Bangladesh, 2 Lucian Blaga University of Sibiu, Romania, 3 Jahangirnagar University, Bangladesh, ABSTRACT: This paper analyzed a mathematical model for estimating the project completion probability after crashing PERT/CPM network. Here we reduced the pessimistic of the activities on critical path to reduce the expected project completion which increase the probability of the project completion on or before the scheduled. Some additional cost is required for the activities along critical path to speed-up the project. The increment of the estimate cost decreases the pessimistic of the activities along critical path and indirectly decreases the total expected project duration. The approach has been modelled in mathematical and algorithmic aspects and finally presented with a numerical example. 1. INTRODUCTION CPM/PERT or Network Analysis as the technique is somes called, developed along two parallel streams, one industrial and the other military. CPM was the discovery of M. R. Walker of E. I. Du Pont de Nemours & Co. and J. E. Kelly of Remington Rand, circa The computation was designed for the UNIVAC-I computer. The first test was made in 1958, when CPM was applied to the construction of a new chemical plant. In March 1959, the method was applied to maintenance shut-down at the Du Pont works in Louisville, Kentucky. Unproductive was reduced from 125 to 93 hours. PERT was devised in 1958 for the POLARIS missile program by the Program Evaluation Branch of the Special Projects office of the U. S. Navy, helped by the Lockheed Missile Systems division and the Consultant firm of Booz-Allen & Hamilton. The calculations were so arranged so that they could be carried out on the IBM Naval Ordinance Research Computer (NORC) at Dahlgren, Virginia. Project crashing is a method for shortening the project duration by reducing the of one or more of the critical project activities to less than its normal. The object crashing is to reduce project duration while minimizing the cost of crashing. Fulkerson (191) and Premachandra (1992) reformulate the problem of crashing PERT network as a linear program, reducing the required to find the optimal solution. Moore et al. (1978) reformulate the problem using goal programming. Goal programming is a modification of linear programming that can solve problems with multiple objectives. This allows goals in addition to cost minimization to be added to the problem. Foldes and Sourmis (1993) present a reformulation of crashing networks when the cost- tradeoff is represented by non-linear, non-differentiable convex function. T Wei Peng at al (2010) analyzed numerical results of crashing CPM/PERT network to the increase of the probability or percentage of completing the project on or before the completion by reducing pessimistic of critical activities. Crashing PERT networks was investigated by a number of researchers, such as Cho and Yum (1997), Ghaleb and Adnan (2001), Johnson and Schou (1990), Keefer and Verdini (1993), Saman (1991). There exist and example in Nicholas & Steyn (2008). that the probability that project will be finished before the expected duration are 1%-50%, while probability that project will be finished after the expected duration are 50%- 99%. The concept of crashing in CPM is applied to PERT networks in order to reduce the project duration of the project, and also to increase the probability of completing the project on or before completion with the additional amounts of money that will be invested to activities on the critical path. 2. PERT FOR PROJECT COMPLETION PROBABILITY PERT is a management technique to estimate the probability that a project will be finished on normal. According to the traditional PERT technique the probability of a certain project meeting a specific schedule can be described as follows: = = Here, is the number of standard deviations of the due date or target date lies from the mean or expected date. is the normal expected which is equal to the sum of normal expected s of activities on critical path. That means if,,, are the expected s of critical path activities, then =,=1,2,,. is the due date or targeted date of completion and is the project standard deviation which is written as = = h = and for each are measured by the following formulae = and = 59
2 The estimates,, are defined as follows: Optimistic (a): the minimum possible required to accomplish a task, assuming everything proceeds better than is normally expected Most likely (m): the best estimate of the required to accomplish a task, assuming everything proceeds as normal Pessimistic (b): the maximum possible required to accomplish a task, assuming everything goes wrong. 3. PROJECT COMPLETION PROBABILITY TO MEET THE DESIRED DURATION Concept of project crashing requires the investment of extra budget to minimize the duration so that the project can meet the targeted date. The delay of the activities on critical path makes the delay of the whole project. So, if we can finish the critical path activities before their normal estimated s, the project will be finished on or before the targeted. For this, the extra budget will be invested for the activities along the critical path. The increasing of budget in critical path activities will minimize the total project duration and will increase the probability of the project completion on or before the targeted date. Activity -cost relationship: Activity cost Crash cost Normal cost Crash Normal Activity duration Figure 1. Linear and cost trade-off for an 4. MATHEMATICAL ASPECT Suppose that the amount of money invested in each critical path is where =1,2,, and is the number of activities on the critical path. The total extra invested money is and then it can be written as = To minimize expected project duration to and project standard deviation to, we reduce the pessimistic of critical activities to. Then the mathematical models for new and stand =. The new expected for critical path activities, = +4 + /. The decreasing of pessimistic of the critical path activities depends on the increasing of cost for each on critical path. Therefore, it means that the decrease in both expected and variance of the activities will be a function and of the additional investment. Then the new pessimistic and variance of the activities for the critical path activities will be = and = with 0 Combining all the constraints from (7), (8), (9) and (10) along with the function (), we get the following mathematical model Time Model and 0 =. /. = +4 + = = After reducing the expected, the probability of the project completion on or before the targeted increased to. Then the mathematical form of the objective function can be written as =.= For getting the increased probability we have to decrease the project duration and to decrease the project standard deviation, which can be written as and < < Combining all the constraints from (12), (13), (10) and (8) along with the probability function (11), we get the following mathematical model Probability Model s/t < and 0 =.= < 5. ALGORITHMIC ASPECT Input: Allocate extra resources in order to reduce the for each critical. Output: Maximum value of the probability of the completion of Project within the deadline. Scheduling Steps Step 1: Determine the activities along the critical path. Step 1.1. Estimate optimistic, most likely and pessimistic for each. Step 1.2. Calculate expected for each. Use the following formula for duration. = +4+ 0
3 Step 1.3. Calculate Earliest Start, Earliest Finisf, Latest Start and Latest Finish for each by the following rules: Forward Pass: Set earliest start zero for all activities which have no predecessors. Earliest finish is equal to the sum of earliest start and duration of the. To calculate the ES of activities with immediate predecessors set the maximum of the EF of all predecessors to the. The project completion is equal to the maximum of the earliest finish of all activities. Backward Pass: The latest finish of activities with no successors are set equal to the project completion. Calculate of an by subtracting the duration from it s. To calculate of activities with successors set the minimum of of all successors to the. Step 1.4. Calculate slack for all the activities by one of the following rules: Rule 1. = Rule 2. = Step 1.5. Sort the activities with zero slack. These are critical activities and the path containing these activities is critical path. Step 2: Calculate the project completion by adding the s of all critical activities. Step 3: Determine the Project Completion Probability Step 3.1. Calculate the variance of all critical activities by the following formula = Step 3.2. Sum the variances of all critical activities for the project variance. Step 3.3. Find the project standard deviation. Use the following formula in this step: = Step 3.4. Use the following formula to calculate the probability of the project completion within the deadline Crashing Steps = Step 4: Fix an amount of resources and distribute it to all the critical activities. Step 5: Reduce the pessimistic for all critical activities. Step : Recall the scheduling steps to calculate a new value of. Step 7: Continue the process until become maximum.. NUMERICAL ASPECT We consider a hypothetical project with 12 activities. Optimistic (a), Most likely (m), Pessimistic (b) and immediate predecessor of each of the project is given in the following table: Table 1. a, b, m and immediate predecessors of the12 activities. Activity Immediate Predecessors ,, 7 10,, , 4 7 8, 1 2 4, We use PERT probabilistic method to calculate expected, earliest start, latest start and variance of each and tabulated in the table 2. 1
4 Table 2. Values of t, ES, LS and variance of 12 activities using PERT method. Activity Project network showing the critical path: Expected Earliest Start Latest Start Slack Variance The activities with slack 0 are on the critical path of the network which is indicated with bold line. Expected project completion date 2 1 = =8.7 days. It means that, there is a 50% chance that the entire project will be completed in less than the expected 8.7 days and a 50% chance that it will exceed 8.7 days. Project variance 5 ac9 7 2 ES=2 ac4 ES=40 LS=2 ac1 ac LS=40 10 ac2 4 ac8 ac ac ac3 ac5 ac7 ES=55 EF=8.7 LS=55 3 LF= ac12 =8.7 Figure 2. Critical path on PERT network = = 12.32=3.51 Probability to meet the normal : To find the probability that the project will be completed on or before 70 days deadline, we need to determine the value of Z = = = From the standard normal table, we find the probability Thus there is a 4.8% chance that the project will be completed in 70 days. Probability to meet the targeted : To find the probability that the project will be finished on or before 5 days deadline without any extra investment, the value of is = = = From the standard normal table, we find the probability Thus there is only 14.9% chance that the project will be completed in 5 days within the same budget. According to the new approach presented in this paper, we invest approximately 10000, and extra budgets for the critical path activities to show how the probability of project completion increases. As a result we reduce to for each critical, shown in following tables: Table 3. Estimation of b, t and v after increased the budget amount M= Critical From the Table 3, =. =8.0 and = 9.7=3.1 =.= = =
5 Table 4. Estimation of b, t and v after increased the budget amount M= Critical From the above Table 4, =. =7.44 and = 7.8=2.80 =.= = = Table 5. Estimation of b, t and v after increased the budget amount M= Critical From the Table 5, =. =.88 And =.01=2.45 =.= = 5.88 = Increasing of the probability that the project will be finished within 5 days is shown in the following table: Table. The probability that the project will be completed in 5 days when M= {0,10000,20000,30000}. No. M % The results are shown in the following graph: % of probability CONCLUSIONS We estimated the probability that the project will be completed in the targeted for different cases. If we invest the extra budgets approximately 10000, and for the activities along the critical path, the expected of the project decreases to 8.0 days, 7.44 days and.88 days respectively. And the probability that the project will be finished within the targeted 5 days increases from 14.9% to 1.0%, 19.22% and 22.0%.The project completion probability within the targeted date can be expressed as the following composite relations =, = and =h Where, is the number of standard deviations, is the project completion, is the pessimistic for each critical path and is the extra cost invested for each such. REFERENCES 1. Cho, J. G. & Yum, B. J. (1997). An Uncertainty Important Measure of Activities in PERT Networks. Int. J Port Res.. 2. Fulkerson, D. R. (191). A network flow computation for project cost curve. Management Science, 7(2), Foldes, S. & Sourmis F. (1993). PERT and crashing revisited: Mathematical generalizations. European Journal of Operational Research, 4, Ghaleb Y. A. & Adnan M. M. (2001). Crashing PERT network using mathematical programming. International Journal of Project Management 19(2001): Johnson G. A. & Schou C. D. (1990). Expediting projects in PERT with stochastic estimates. Project Management Journal 21(20: Keefer D. L. & Verdini W. A. (1993). Better estimation of PERT parameters. Management Science 39(9): Moore, L. J. et al., (1978). Analysis of a multi-criteria project crashing model. AIIE Transactions, 10(2), Nicholas J. M. & Steyn H. (2008). Project Management for Business, Engineering and Technology. Principles and Practice, Pearson Education, Inc. 9. Premachandra, I. M. (1992). A goal programming model for crashing in project networks. International Journal of Operations Management, 13(), Peng, T. W., M. Mamat and Dasril Y. (2010). An Improvement of Numerical Result of Crashing CPM/PERT Network. Journal of Science and Technology 2(10): Saman M. (1991). Crashing in PERT Network. M. Sc. Thesis submitted at the Faculty of Graduate Studies, University of Jordan, Amman-Jordan. 12. Ten Wei Peng, Mustafa Mamat, Yosza Dasril (2010). An Improvement of Numerical Result of Crashing CPM/PERT Network. Journal of Science and Technology, Vol 2, No 1 (2010) Crash cost Figure 3. A typical project completion probability-cost graph for an. 3
Operational Research. Project Menagement Method by CPM/ PERT
Operational Research Project Menagement Method by CPM/ PERT Project definition A project is a series of activities directed to accomplishment of a desired objective. Plan your work first..then work your
CISC 322 Software Architecture. Project Scheduling (PERT/CPM) Ahmed E. Hassan
CISC 322 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan Project A project is a temporary endeavour undertaken to create a "unique" product or service A project is composed of a number
Network Calculations
Network Calculations The concepts and graphical techniques described in this week s readings form the basis of the tools widely used today to manage large projects. There is no way of simplifying the tasks
CRASHING PERT NETWORKS: A SIMULATION APPROACH
CRASHING PERT NETWORKS: A SIMULATION APPROACH Wayne A. Haga Assistant Professor of Computer Information Systems Metropolitan State College of Denver P.O. Box 173362, Campus Box 45 Denver, CO 80217-3362
Project Management SCM 352. 2011 Pearson Education, Inc. publishing as Prentice Hall
3 Project Management 3 SCM 35 11 Pearson Education, Inc. publishing as Prentice Hall Boeing 787 Dreamliner Delays are a natural part of the airplane supply business. They promise an unreasonable delivery
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Project Planning and Scheduling
Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination
Scheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
Project Scheduling: PERT/CPM
Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times (as in exercises 1, 2, 3 and 5 in the handout) and considering Time-Cost Trade-Offs (as in exercises 4 and 6 in the handout). This
Cambridge International AS and A Level Computer Science
Topic support guide Cambridge International AS and A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains
22 Project Management with PERT/CPM
hil61217_ch22.qxd /29/0 05:58 PM Page 22-1 22 C H A P T E R Project Management with PERT/CPM One of the most challenging jobs that any manager can take on is the management of a large-scale project that
10 Project Management with PERT/CPM
10 Project Management with PERT/CPM 468 One of the most challenging jobs that any manager can take on is the management of a large-scale project that requires coordinating numerous activities throughout
Project Management Chapter 3
Project Management Chapter 3 How Project Management fits the Operations Management Philosophy Operations As a Competitive Weapon Operations Strategy Project Management Process Strategy Process Analysis
A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST
A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST Priti Singh Astt. Prof.-MCA Department OCM, Bhopal preitisingh@rediffmail.com Florentin Smarandache Chair of Department of Mathematics
Project Scheduling: PERT/CPM
Project Scheduling: PERT/CPM CHAPTER 8 LEARNING OBJECTIVES After completing this chapter, you should be able to: 1. Describe the role and application of PERT/CPM for project scheduling. 2. Define a project
Basic Concepts. Project Scheduling and Tracking. Why are Projects Late? Relationship between People and Effort
Basic s Project Scheduling and Tracking The process of building a schedule for any case study helps really understand how it s done. The basic idea is to get across to break the software project into well-defined
March 30, 2007 CHAPTER 4
March 30, 07 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE Chapter Outline 4.1 Background What was the cause of the desperation that lead to the development of the Program Evaluation and Review
Project management: a simulation-based optimization method for dynamic time-cost tradeoff decisions
Rochester Institute of Technology RIT Scholar Works Theses Thesis/Dissertation Collections 2009 Project management: a simulation-based optimization method for dynamic time-cost tradeoff decisions Radhamés
Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072
Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking
Application of Critical Path Method scheduling to research plan and management of graduate students research project in engineering education
OPEN ACCESS Engineering Leaders Conference 2014 Application of Critical Path Method scheduling to research plan and management of graduate students research project in engineering education M.O. Daramola
PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT)
PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT) ABSTRACT Category: Planning/ Monitoring - Control KEYWORDS Program (Project) Evaluation and Review Technique (PERT) (G) is a project management tool used
Project Scheduling and Gantt Charts
Project Scheduling and Gantt Charts Siddharth Gangadhar Dr. Prasad Kulkarni Department of Electrical Engineering & Computer Science Lab Presentation siddharth@ku.edu prasadk@ku.edu 4 November 2015 2015
The work breakdown structure can be illustrated in a block diagram:
1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as
CPM-200: Principles of Schedule Management
CPM-: Principles of Schedule Management Lesson B: Critical Path Scheduling Techniques Instructor Jim Wrisley IPM Fall Conference PMI-College of Performance Management Professional Education Program Copyright
Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration
Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Prof. M. Rammohan Rao Former Dean Professor Emeritus Executive Director, Centre for Analytical
PERT/CPM. Network Representation:
- 1 - PERT/CPM PERT Program Evaluation & Review Technique It is generally used for those projects where time required to complete various activities are not known as a priori. It is probabilistic model
ME 407 Mechanical Engineering Design Spring 2016
ME 407 Mechanical Engineering Design Spring 2016 Project Planning & Management Asst. Prof. Dr. Ulaş Yaman Acknowledgements to Dieter, Engineering Design, 4 th edition Ullman, The Mechanical Design Process,
Chapter 4: Project Time Management
Chapter 4: Project Time Management Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
8. Project Time Management
8. Project Time Management Project Time Management closely coordinated Two basic approaches -bottom-up (analytical) -top-down (expert judgement) Processes required to ensure timely completion of the project
Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition:
Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition: 1. Activity : It is a particular work of a project which consumes some resources (in ) & time. It is shown as & represented
Scheduling Resources and Costs
Student Version CHAPTER EIGHT Scheduling Resources and Costs McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Gannt Chart Developed by Henry Gannt in 1916 is used
PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM)
PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM) Project Evaluation Review Technique (PERT) and Critical Path Method (CPM) are scheduling techniques used to plan, schedule, budget
Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen + Antworten October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 1 All the following Statements about a WBS are true except that it a. Provides a framework for
ANALYSIS OF PROJECT PLANNING USING CPM AND PERT
ANALYSIS OF PROJECT PLANNING USING CPM AND PERT Rogelio Acuña Spring 2010 In Partial Fulfillment of Math 4395-Senior Project Department of Computer and Mathematical Sciences Faculty Advisor: Dr. Timothy
Project Management DISCUSSION QUESTIONS
3 C H A P T E R Project Management DISCUSSION QUESTIONS. There are many possible answers. Project management is needed in large construction jobs, in implementing new information systems, in new product
Chapter 11: PERT for Project Planning and Scheduling
Chapter 11: PERT for Project Planning and Scheduling PERT, the Project Evaluation and Review Technique, is a network-based aid for planning and scheduling the many interrelated tasks in a large and complex
A Generalized PERT/CPM Implementation in a Spreadsheet
A Generalized PERT/CPM Implementation in a Spreadsheet Abstract Kala C. Seal College of Business Administration Loyola Marymount University Los Angles, CA 90045, USA kseal@lmumail.lmu.edu This paper describes
Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead
Chapter 2: Project Time Management
Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
Scheduling. Anne Banks Pidduck Adapted from John Musser
Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart
Project Management 1. PROJECT MANAGEMENT...1 2. PROJECT ANALYSIS...3
Project Management What is a project? How to plan a project? How to schedule a project? How to control a project? 1. PROJECT MNGEMENT...1 2. PROJECT NLYSIS...3 3 PROJECT PLNNING...8 3.1 RESOURCE LLOCTION...8
Application Survey Paper
Application Survey Paper Project Planning with PERT/CPM LINDO Systems 2003 Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) are two closely related techniques for monitoring
Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org
Planning and Managing Software Projects 2011-12 Class 9 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides
MECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor (hefny@cs.queensu.ca and surgenor@me.queensu.ca) Winter : Lecture # Project Time Management Homework Discussion Homework
Chapter 6: Project Time Management
CIS 486 Managing Information Systems Projects Fall 2003 (Chapter 6), PhD jwoo5@calstatela.edu California State University, LA Computer and Information System Department Chapter 6: Project Time Management
Project Time Management
Project Time Management By Augsburg College 1 Learning Objectives Understand the importance of project schedules and good project time management Define activities as the basis for developing project schedules
A. O. Odior Department of Production Engineering University of Benin, Edo State. E-mail: waddnis@yahoo.com
2012 Cenresin Publications www.cenresinpub.org APPLICATION OF PROJECT MANAGEMENT TECHNIQUES IN A CONSTRUCTION FIRM Department of Production Engineering University of Benin, Edo State. E-mail: waddnis@yahoo.com
Chapter 11 Monte Carlo Simulation
Chapter 11 Monte Carlo Simulation 11.1 Introduction The basic idea of simulation is to build an experimental device, or simulator, that will act like (simulate) the system of interest in certain important
Project Management Glossary
Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project
Quantitative Risk Analysis with Microsoft Project
Copyright Notice: Materials published by Intaver Institute Inc. may not be published elsewhere without prior written consent of Intaver Institute Inc. Requests for permission to reproduce published materials
Network Planning and Analysis
46 Network Planning and Analysis 1. Objective: What can you tell me about the project? When will the project finish? How long will the project take (project total duration)? 2. Why is this topic Important
Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014
Project Management Six Session Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Mohamed Khalifa, 2014 All Rights 1 7. Scheduling 2 7. Scheduling 7.1 Scheduling techniques 7.3 Critical path method
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS
ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS Chapter 3 of Systems Analysis and Design in a Changing World explains the techniques and steps required to build a project schedule
technical tips and tricks
technical tips and tricks Performing critical path analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the
APPLYING PERT AND CRITICAL PATH METHOD IN HUMAN RESOURCE TRAINING
APPLYING PERT AND CRITICAL PATH METHOD IN HUMAN RESOURCE TRAINING Eugen ROT RESCU * Abstract: The subject of the article is referring to the modelling and simulating of the formation of human resources
Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project
MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Schedule Float Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar
Collaborative Scheduling using the CPM Method
MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines
Managing Information Systems Project Time and Resources
06-Avison-45664:06-Avison-45664 7/29/2008 7:18 PM Page 153 6 Managing Information Systems Project Time and Resources Themes of Chapter 6 What is project time management? What characteristics define an
Unit 1: Project Planning and Scheduling
Unit : Project Planning and Scheduling Objective Ð To provide a brief introduction to project planning and scheduling. The critical area where project management meets system development. ackground Most
SE351a: Software Project & Process Management
SE351a: Software Project & Process Management W8: Software Project Planning 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa SE351 Roadmap Introduction to Software Project Management Project Management
Learning Objectives. Learning Objectives (continued) Importance of Project Schedules
Chapter 6: Project Time Management Information Technology Project Management, Fifth Edition Learning Objectives Understand the importance of project schedules and good project time management Define activities
12 Network Scheduling Techniques
Page 671 12 Network Scheduling Techniques 12.0 Introduction Management is continually seeking new and better control techniques to cope with the complexities, masses of data, and tight deadlines that are
Time Management. Part 5 Schedule Development. Richard Boser
Time Management Part 5 Schedule Development Richard Boser 6.5 Schedule Development Inputs Organizational Process Assets Scope Statement Activity List Activity Attributes Network Diagrams Resource Req ms
Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition
Lecture 6: Project Time Management By: Prof. Lili Saghafi Information Technology Project Management, Fifth Edition Learning Objectives 2 Understand the importance of project schedules and good project
CRITICAL PATH METHOD (CEE 320 VDC SEMINAR)
CRITICAL PATH METHOD (CEE 320 VDC SEMINAR) 4 February 2009 Jesse Santiago & Desirae Magallon Overview Background & History CPM Defined The CPM approach Definitions Class Exercise Background & History Developed
Appendix A of Project Management. Appendix Table of Contents REFERENCES...761
Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity
EdExcel Decision Mathematics 1
EdExcel Decision Mathematics 1 Notes and Examples Critical Path Analysis Section 1: Activity networks These notes contain subsections on Drawing an activity network Using dummy activities Analysing the
Deming s 14 Points for TQM
1 Deming s 14 Points for TQM 1. Constancy of purpose Create constancy of purpose for continual improvement of products and service to society, allocating resources to provide for long range needs rather
CRASHING-RISK-MODELING SOFTWARE (CRMS)
International Journal of Science, Environment and Technology, Vol. 4, No 2, 2015, 501 508 ISSN 2278-3687 (O) 2277-663X (P) CRASHING-RISK-MODELING SOFTWARE (CRMS) Nabil Semaan 1, Najib Georges 2 and Joe
BPEL disadvantage: more time to product BPEL advantage: better reusability, analysis
Modeling Page 1 To BPEL or not to BPEL? 5:56 PM To BPEL or not to BPEL? BPEL disadvantage: more time to product BPEL advantage: better reusability, analysis Modeling Page 2 A tale of two strategies 5:57
Systems Analysis and Design
Systems Analysis and Design Slides adapted from Jeffrey A. Hoffer, University of Dayton Joey F. George, Florida State University Joseph S. Valacich, Washington State University Modern Systems Analysis
PROJECT MANAGEMENT: PERT AND CPM
14 Chapter PROJECT MANAGEMENT: PERT AND CPM CHAPTER OUTLINE 14.1 Introduction 14.2 A Typical Project: The Global Oil Credit Card Operation 14.3 The Critical Path Meeting the Board s Deadline 14.4 Variability
Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose
1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing
PMP : Project Management Professional Study Guide Kim Heldman
SYBEX Sample Chapter PMP : Project Management Professional Study Guide Kim Heldman Chapter 7: Creating the Project Plan Copyright 2002 SYBEX Inc., 1151 Marina Village Parkway, Alameda, CA 94501. World
Chapter 6 (part 1) Project Time Management. (Project Scheduling)
Chapter 6 (part 1) Project Time Management. (Project Scheduling) 1 Objectives Understand the process of project decomposition into activities Understand the level of details required for activities Understand
Project Scheduling by PERT/CPM
Project Scheduling by PERT/PM Reference ooks: nderson, Sweeney, and Williams, N INTROUTION TO MNGEMENT SIENE, QUNTITTIVE PPROHES TO EISION MKING, th edition, West Publishing ompany,99 Hamdy. Taha, OPERTIONS
Critical Path Analysis
Chapter 13 Critical Path Analysis Basic Concepts Activity An activity is any portion of a project which consumes time or resources and has a definable beginning and ending. For example, laying of pipe
Prof. Olivier de Weck
ESD.36 System Project Management + Lecture 9 Probabilistic Scheduling Instructor(s) Prof. Olivier de Weck Dr. James Lyneis October 4, 2012 Today s Agenda Probabilistic Task Times PERT (Program Evaluation
Notes on the Critical Path Method for project planning and management.
E90 Engineering Design Notes on the Critical Path Method for project planning and management. CPM models any project by a network of blocks or circles called NODES that are connected by lines called ARROWS.
Research on Task Planning Based on Activity Period in Manufacturing Grid
Research on Task Planning Based on Activity Period in Manufacturing Grid He Yu an, Yu Tao, Hu Da chao Abstract In manufacturing grid (MG), activities of the manufacturing task need to be planed after the
MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Schedule Updates Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions
B. 2-4-6 D. 3-4-5 E. 3-5-7 F. 5-7-9
Lesson 01 Project Management Solutions #1: The network diagram for a project is shown below, with three time estimates (optimistic, most likely, and pessimistic) for each activity. Activity times are in
7. PROJECT MANAGEMENT
7. PROJECT MANAGEMENT Syllabus Definition and scope of project, Technical design, Financing, Contracting, Implementation and performance monitoring. Implementation plan for top management, Planning Budget,
專 案 管 理 實 務 嘉 義 縣 政 府 學 分 班 : 管 理 實 務 專 題 2006 中 正 大 學 企 管 系 助 理 教 授 周 瑞 生
專 案 管 理 實 務 嘉 義 縣 政 府 學 分 班 : 管 理 實 務 專 題 2006 中 正 大 學 企 管 系 助 理 教 授 周 瑞 生 講 師 介 紹 > 學 歷 台 灣 大 學 學 士 台 灣 大 學 碩 士 美 國 德 州 大 學 奧 斯 汀 校 區 工 程 專 案 管 理 博 士 中 華 民 國 土 木 工 程 大 地 工 程 水 土 保 持 工 程 專 門 技 術 人 員 高
Scheduling 8.1 BACKGROUND
5426ch08.qxd_jt 9/19/02 10:39 AM Page 379 C H A P T E R 8 Scheduling The previous chapter initiated our discussion of project implementation. In this and the following three chapters, we continue with
Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur
Module 11 Software Project Planning Lesson 29 Staffing Level Estimation and Scheduling Specific Instructional Objectives At the end of this lesson the student would be able to: Identify why careful planning
Simulator for Optimization of Software Project Cost and Schedule
Journal of Computer Science 4 (12): 1030-1035, 2008 ISSN 1549-3636 2008 Science Publications Simulator for Optimization of Software Project Cost and Schedule 1 P.K. Suri and 2 Bharat Bhushan 1 Department
Chapter-6. Developing a Project Plan
MGMT 4135 Project Management Chapter-6 Where we are now Developing the Project Network Why? Graphical representation of the tasks to be completed Logical sequence of activities Determines dependencies
Project Management Dr. James A. Bednar
Project Management Dr. James A. Bednar jbednar@inf.ed.ac.uk http://homepages.inf.ed.ac.uk/jbednar SAPM Spring 2006: Project Management 1 Project Management A project is a temporary endeavour to produce
Should I Resource Load My Schedule?
Should I Resource Load My Schedule? th Annual International Integrated Program Management Conference November -, Copyright All Rights Reserved The Goals Of Project Management: to make the most effective
Cost & Time and Also Minimum Project Duration Using Alternative Method
International Review of Applied Engineering Research. ISSN 2248-9967 Volume 4, Number 5 (2014), pp. 403-412 Research India Publications http://www.ripublication.com/iraer.htm Cost & Time and Also Minimum
Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University
Object-Oriented Analysis and Design with the Unified Process John W. Satzinger Southwest Missouri State University Robert B. Jackson Brigham Young University Stephen D. Burd University of New Mexico ALL
PROJECT MANAGEMENT Critical Path Method-- Program, Evaluation & Review Technique (CPM/PERT)
PROJECT MANAGEMENT Critical Path Method-- Program, Evaluation & Review Technique (CPM/PERT) 1 Introduction to Project Management Many people and organizations today have a new or renewed interest in project
SYSTEMS ANALYSIS AND DESIGN DO NOT COPY
Systems Analysis and Design in a Changing World, Fourth Edition -488-6-5 Copyright 7 Thomson Course Technology. All rights reserved. FOURTH EDITION SYSTEMS ANALYSIS AND DESIGN IN A C HANGING W ORLD John
MANAGING OVER ALLOCATION OF RESOURCE IN STEEL INDUSTRIES USING PROJECT MANAGEMENT SOFTWARE
MANAGING OVER ALLOCATION OF RESOURCE IN STEEL INDUSTRIES USING PROJECT MANAGEMENT SOFTWARE Harshlata Rewaskar 1, D.K.Shukla 2 1 M Tech (4th Semester) 2 M Tech, Mumbai, India harshlatar@gmail.com Abstract
Schedule Risk Analysis Simulator using Beta Distribution
Schedule Risk Analysis Simulator using Beta Distribution Isha Sharma Department of Computer Science and Applications, Kurukshetra University, Kurukshetra, Haryana (INDIA) ishasharma211@yahoo.com Dr. P.K.