Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Size: px
Start display at page:

Download "Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003"

Transcription

1 Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

2 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead c. Float d. lack e. None of the above 2

3 Question 7 - Answer Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead c. Float d. lack e. None of the above For example, in a finish-to-start dependency with a 10-day lag, the successor activity cannot Start until 10 days after the predecessor has finished. PMI 1996, 164 3

4 Question 8 Milestones are not - a. Activities of zero duration b. Significant events in the project life cycle c. Measures of achievement for expenditures of money or time d. Set by project stakeholders e. Best utilized when denoting Start and finish of all activities 4

5 Question 8 - Answer Milestones are not - a. Activities of zero duration b. Significant events in the project life cycle c. Measures of achievement for expenditures of money or time d. Set by project stakeholders e. Best utilized when denoting Start and finish of all activities Because milestones represent significant project events, a milestone for the Start and finish of every activity would be excessive. PMI 1996, 70 5

6 Question 9 The network diagram - a. Illustrates project team member communication b. Identifies the scheduled Start and end dates of key activities and administrative tasks c. Displays the logical relationships between project activities d. Provides Information on schedule performance e. None of the above 6

7 Question 9 The network diagram - a. Illustrates project team member communication b. Identifies the scheduled Start and end dates of key activities and administrative tasks c. Displays the logical relationships between project activities d. Provides Information on schedule performance e. None of the above The project activities (work packages) are connected by lines of precedence indicating their logical relationships, or dependencies. PMI 1996, 64 7

8 Question 10 Activity A has a duration of 3 days and begins on the morning of Monday the 4th. The successor activity, B, has a finish-to-start relationship with A. The finish-to-start relationship has 3 days of lag, and activity B has a duration of 4 days. Sunday is a non workday. What can be determined from these dates? a. The total duration of both activities is 7 days b. Calendar time between Start of A to the finish of B is 11 days c. The finish date of B is Wednesday the 13 th d. a and b e. a, b, and c 8

9 Question 10 Activity A has a duration of 3 days and begins on the morning of Monday the 4th. The successor activity, B, has a finish-to-start relationship with A. The finish-to-start relationship has 3 days of lag, and activity B has a duration of 4 days. Sunday is a non workday. What can be determined from these dates? a. The total duration of both activities is 7 days b. Calendar time between Start of A to the Start of B is 11 days c. The finish date of B is Wednesday the 13 th d. a and b e. a, b, and c 9

10 Question 10 a and b The duration of A, which is 3, is added to the duration of B, which is 4, for a total of 7. The 3 days between the activities is lag and not duration. The lag is a constraint and must be taken into account as part of the network calculations, but it does not consume resources. The total time by the calendar is 11 days as counted from the morning of Monday the 4th. The lag occurs over Thursday, Friday, and Saturday. Sunday is A nonworkingday, so activity B does not Start until Monday the 11th. Therefore, the calendar time is 11 days and activity B ends on Thursday the 14th. 10

11 Question 11 In project time management, fast tracking means - a. Reducing the duration of critical path activities to shorten project duration b. Reducing project duration by redefining logical relationships c. Using only the best resources to accomplish work as quickly as possible d. Coordination efforts with other projects to reduce administrative friction e. Using state-of-the-art Software to measure project progress 11

12 Question 11 In project time management, fast tracking means - a. Reducing the duration of critical path activities to shorten project duration b. Reducing project duration by redefining logical relationships c. Using only the best resources to accomplish work as quickly as possible d. Coordination efforts with other projects to reduce administrative friction e. Using state-of-the-art Software to measure project progress The objective of fast-tracking is to redefine the logic in a project to accomplish activities in parallel as start-to-start, rather than finish-tostart, relationships. PMI 1996, 68 12

13 Question 12 The primary outcome of performing a forward pass on a network diagram is determination of the - a. Earliest time each activity in the network can Start and finish b. Amount of resource required to complete the project c. Project's total float d. a and b e. a, b, and c 13

14 Question 12 The primary outcome of performing a forward pass on a network diagram is determination of the - a. Earliest time each activity in the network can Start and finish b. Amount of resource required to complete the project c. Project's total float d. a and b e. a, b, and c A forward pass Starts with the earliest Start date of the first activity and calculates early Start and finish times for each activity. 14

15 Question 13 Unlike bar charts, milestone charts show - a. Scheduled Start or completion of major deliverables and key events b. Activity Start and end dates c. Expected durations d. Dependencies e. Logical relationships and critical path 15

16 Question 13 Unlike bar charts, milestone charts show - a. Scheduled Start or completion of major deliverables and key events b. Activity Start and end dates c. Expected durations d. Dependencies e. Logical relationships and critical path Milestones are Singular points in time, such as Start or completion of a significant activity or group of activities. PMI 1996, 70 16

17 Question 14 An activity has an early Start date of the 10th and a late Start date of the 19th. The activity also has a duration of 4 days. There are no non workdays. From the Information given, what can be concluded about the activity? a. Total float for the activity is 9 days b. The early finish date of the activity is the end of the day on the 13th c. The late finish date is the 25th d. The total calendar time to complete the activity is 4 days e. a and b 17

18 Question 14 An activity has an early Start date of the 10th and a late Start date of the 19th. The activity also has a duration of 4 days. There are no non workdays. From the Information given, what can be concluded about the activity? a. Total float for the activity is 9 days b. The early finish date of the activity is the end of the day on the 13th c. The late finish date is the 25th d. The total calendar time to complete the activity is 4 days e. a and b Total float is computed by subtracting the early Start date from the late Start date. The early finish date is computed by adding the duration to the early Start date. 18

19 Question 15 Which tool provides a basis to identify the work that must be scheduled? a. Ishikawa diagram b. WBS c. Budget d. Master schedule e. Gantt chart 19

20 Question 15 Which tool provides a basis to identify the work that must be scheduled? a. Ishikawa diagram b. WBS c. Budget d. Master schedule e. Gantt chart The WBS provides an important foundation for constructing a realistic schedule because it identifies all the work that must be accomplished. PMI 1996, 54-56, 61 20

21 Question 16 In project time management, crashing means a. Reducing project duration by redefining logical relationships b. Reducing Computer network downtime for schedule risk modeling c. Applying additional resources to all project activities d. Randomly applying resources to critical path activities e. Applying additional resources to critical path activities by priority 21

22 Question 16 In project time management, crashing means a. Reducing project duration by redefining logical relationships b. Reducing Computer network downtime for schedule risk modeling c. Applying additional resources to all project activities d. Randomly applying resources to critical path activities e. Applying additional resources to critical path activities by priority When applying additional resources to reduce project duration, the emphasis is on those activities whose cost of crashing will gain the most time for the cost incurred. PMI 1996, 68 22

23 Question 17 The following activities are in a network diagram Activity Predecessor Duration A Excavating none 5 B Pouring foundation A 2 C Installing outside plumbing A 6 D Framing B 8 E Installing inside plumbing D 2 F Wiring D 3 In the network outlined above, which Statements are true? I. Installing outside plumbing is on the critical path. II. Installing inside plumbing has a day of slack. III. Pouring foundation is on the critical path. a. I b. II and III c. I and II d. I and III e. I, II and III 23

24 Question 17 In the network outlined above, which Statements are true? I. Installing outside plumbing is on the critical path. II. Installing inside plumbing has a day of slack. III. Pouring foundation is on the critical path. a. I b. II and III c. I and II d. I and III e. I, II and III Path A-B-D-E = 17 days Path A-B-D-F = 18 days = Critical path Path A-C = 11 days Activity E, installing inside plumbing, has 1 day of slack: 18 days -17 days = 1 day. Activity B, pouring foundation, is on the critical path. 24

25 Question 17 Start ES EF 1 6 Duration=5 Task A 1 6 LS LF ES EF 6 8 Duration=2 Task B 6 8 LS LF ES EF 8 16 Duration=8 Task D 8 16 LS LF ES 16 EF 18 Duration=2 Task E LS LF Finish ES EF Duration=3 Task F LS LF ES EF 6 12 Duration=6 Task C LS LF 25

26 Question 18 Each of the following Statements about risk avoidance is true except that it - a. Focuses on eliminating the elements that are creating the risk b. Includes making the decision not to bid a project in which the risk exposure is believed to be too high c. Accepts the consequences of the risk event should it occur d. Includes adopting an alternative, lower-risk technology path e. Includes leaving the risk with the customer when the customer is in the best position to mitigate the risk 26

27 Question 18 Each of the following Statements about risk avoidance is true except that it - a. Focuses on eliminating the elements that are creating the risk b. Includes making the decision not to bid a project in which the risk exposure is believed to be too high c. Accepts the consequences of the risk event should it occur d. Includes adopting an alternative, lower-risk technology path e. Includes leaving the risk with the customer when the customer is in the best position to mitigate the risk Accepting the consequences of the risk event is categorized as risk acceptance. With this response development approach, the project team takes no action to reduce the probability of the risk's occurring. 27

28 Question 19 In a proactive approach to project risk management, the amount of a contingency reserve should be based on a. Standard allowance b. Percentages based on past experience c. The sum total of the most likely probability and impact of the various risk items d. A set amount allocated to each item proportionately e. An allowance of 10% for each phase in the project life cycle 28

29 Question 19 In a proactive approach to project risk management, the amount of a contingency reserve should be based on a. Standard allowance b. Percentages based on past experience c. The sum total of the most likely probability and impact of the various risk items d. A set amount allocated to each item proportionately e. An allowance of 10% for each phase in the project life cycle After appropriate allowances have been determined, allocations should be made to the major functional areas of responsibility. With the other approaches, the funds are often depleted before the end of the project because of the temptation for others to use the reserve fund for purposes other than risk management. 29

30 Question 20 Risk mitigation involves a. Using performance and payment bonds b. Eliminating a specific threat by eliminating the cause c. Avoiding the schedule risk inherent in the project d. Assigning the risk to a subcontractor e. Reducing the expected monetary value of a risk event by reducing the probability of occurrence 30

31 Question 20 Risk mitigation involves a. Using performance and payment bonds b. Eliminating a specific threat by eliminating the cause c. Avoiding the schedule risk inherent in the project d. Assigning the risk to a subcontractor e. Reducing the expected monetary value of a risk event by reducing the probability of occurrence An example of mitigation is using proven technology to lessen the probability that the product of the project will not work or reducing the risk event value through buying Insurance, or both. PMI 1996,

32 Question 21 On a typical project, when are risks highest and impacts (amount at stake) lowest? a. When the resource histogram peaks b. During the concept phase c. At or near completion of the project d. During the implementation phase e. When the project manager is replaced 32

33 Question 21 On a typical project, when are risks highest and impacts (amount at stake) lowest? a. When the resource histogram peaks b. During the concept phase c. At or near completion of the project d. During the implementation phase e. When the project manager is replaced Risks are highest at the beginning of a project because the project faces an uncertain future, and impacts are lowest then because Investments in human and material resources are small. 33

34 Question 22 All the following are examples of external risks except - a. Regulatory considerations b. Natural hazards c. Inflation d. Contract type e. Taxation 34

35 Question 22 All the following are examples of external risks except - a. Regulatory considerations b. Natural hazards c. Inflation d. Contract type e. Taxation External risks are those events over which the project manager has no control or influence. PMI 1996,

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Test Fragen + Antworten October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 1 All the following Statements about a WBS are true except that it a. Provides a framework for

More information

Project Time Management

Project Time Management Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

More information

Scheduling Glossary Activity. A component of work performed during the course of a project.

Scheduling Glossary Activity. A component of work performed during the course of a project. Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the

More information

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes

More information

Chapter 2: Project Time Management

Chapter 2: Project Time Management Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.

More information

Project Management Glossary

Project Management Glossary Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project

More information

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define

More information

CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012

CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 King Saud University College of Computer & Information Sciences Department of Computer Science CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 1- Decomposing

More information

Collaborative Scheduling using the CPM Method

Collaborative Scheduling using the CPM Method MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines

More information

Time Management. Part 5 Schedule Development. Richard Boser

Time Management. Part 5 Schedule Development. Richard Boser Time Management Part 5 Schedule Development Richard Boser 6.5 Schedule Development Inputs Organizational Process Assets Scope Statement Activity List Activity Attributes Network Diagrams Resource Req ms

More information

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Project Management Six Session Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Mohamed Khalifa, 2014 All Rights 1 7. Scheduling 2 7. Scheduling 7.1 Scheduling techniques 7.3 Critical path method

More information

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Schedule Float Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

Precedence Diagram Method. CSTM 462 Planning & Scheduling

Precedence Diagram Method. CSTM 462 Planning & Scheduling Precedence Diagram Method CSTM 462 Planning & Scheduling Precedence Diagramming Method (PDM) PDM is more flexible than AON or AOA networks because PDM allows the overlapping of concurrent activities.

More information

Chapter 4: Project Time Management

Chapter 4: Project Time Management Chapter 4: Project Time Management Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes

More information

Chapter-6. Developing a Project Plan

Chapter-6. Developing a Project Plan MGMT 4135 Project Management Chapter-6 Where we are now Developing the Project Network Why? Graphical representation of the tasks to be completed Logical sequence of activities Determines dependencies

More information

Project Planning and Scheduling

Project Planning and Scheduling Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination

More information

8. Project Time Management

8. Project Time Management 8. Project Time Management Project Time Management closely coordinated Two basic approaches -bottom-up (analytical) -top-down (expert judgement) Processes required to ensure timely completion of the project

More information

Basic CPM Calculations

Basic CPM Calculations Overview Core Scheduling Papers: #7 Basic CPM Calculations Time Analysis calculations in a Precedence Diagramming Method (PDM) Critical Path Method (CPM) network can be done in a number of different ways.

More information

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761 Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity

More information

Project Management Dr. James A. Bednar

Project Management Dr. James A. Bednar Project Management Dr. James A. Bednar jbednar@inf.ed.ac.uk http://homepages.inf.ed.ac.uk/jbednar SAPM Spring 2006: Project Management 1 Project Management A project is a temporary endeavour to produce

More information

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Planning and Managing Software Projects 2011-12 Class 9 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides

More information

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Schedule Updates Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions

More information

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project

More information

CRITICAL PATH METHOD (CPM) SCHEDULES

CRITICAL PATH METHOD (CPM) SCHEDULES 96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without

More information

ME 407 Mechanical Engineering Design Spring 2016

ME 407 Mechanical Engineering Design Spring 2016 ME 407 Mechanical Engineering Design Spring 2016 Project Planning & Management Asst. Prof. Dr. Ulaş Yaman Acknowledgements to Dieter, Engineering Design, 4 th edition Ullman, The Mechanical Design Process,

More information

Introduction to Project Management

Introduction to Project Management L E S S O N 1 Introduction to Project Management Suggested lesson time 50-60 minutes Lesson objectives To be able to identify the steps involved in project planning, you will: a b c Plan a project. You

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Project Time Management

Project Time Management Project Time Management By Augsburg College 1 Learning Objectives Understand the importance of project schedules and good project time management Define activities as the basis for developing project schedules

More information

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of

More information

PMP Exam Preparation Answer Key

PMP Exam Preparation Answer Key Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.

More information

Operational Research. Project Menagement Method by CPM/ PERT

Operational Research. Project Menagement Method by CPM/ PERT Operational Research Project Menagement Method by CPM/ PERT Project definition A project is a series of activities directed to accomplishment of a desired objective. Plan your work first..then work your

More information

Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management

Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute

More information

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa Project Creation and Gantt Chart Design Using Microsoft Project R. Baker The University of Tampa What is Microsoft Project? Microsoft Project is a software package designed help managers manage a variety

More information

Scheduling. Anne Banks Pidduck Adapted from John Musser

Scheduling. Anne Banks Pidduck Adapted from John Musser Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart

More information

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Prof. M. Rammohan Rao Former Dean Professor Emeritus Executive Director, Centre for Analytical

More information

MODEL SCHEDULING SPECIFICATION

MODEL SCHEDULING SPECIFICATION MODEL SCHEDULING SPECIFICATION Introduction (Not part of the specification) Before implementation, we recommend that your contract and this provision be reviewed and modified to ensure compatibility with

More information

Dashboards and Reporting for Program Management

Dashboards and Reporting for Program Management MnDOT Project Management Office Presents: Dashboards and Reporting for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will

More information

The work breakdown structure can be illustrated in a block diagram:

The work breakdown structure can be illustrated in a block diagram: 1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as

More information

Unit 4: Time Management (PMBOK Guide, Chapter 6)

Unit 4: Time Management (PMBOK Guide, Chapter 6) (PMBOK Guide, Chapter 6) The questions on this topic focus heavily on scheduling techniques, network diagrams, Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or may

More information

Chapter 6: Project Time Management

Chapter 6: Project Time Management CIS 486 Managing Information Systems Projects Fall 2003 (Chapter 6), PhD jwoo5@calstatela.edu California State University, LA Computer and Information System Department Chapter 6: Project Time Management

More information

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules Chapter 6: Project Time Management Information Technology Project Management, Fifth Edition Learning Objectives Understand the importance of project schedules and good project time management Define activities

More information

PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM)

PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM) PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM) Project Evaluation Review Technique (PERT) and Critical Path Method (CPM) are scheduling techniques used to plan, schedule, budget

More information

PMI Lexicon of Project Management Terms

PMI Lexicon of Project Management Terms Project Management Institute PMI Lexicon of Project Management Terms Version 3.0 Published by: Project Management Institute, Inc. 14 Campus Boulevard Newtown Square, Pennsylvania 19073-3299 USA Phone:

More information

Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition

Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition Lecture 6: Project Time Management By: Prof. Lili Saghafi Information Technology Project Management, Fifth Edition Learning Objectives 2 Understand the importance of project schedules and good project

More information

WORK PROGRAM GUIDELINES

WORK PROGRAM GUIDELINES Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment

More information

U.S. Department of Veterans Affairs. Facilities Management. Critical Path Method. Guidelines for Preparation of CPM Schedule Volume I

U.S. Department of Veterans Affairs. Facilities Management. Critical Path Method. Guidelines for Preparation of CPM Schedule Volume I VA U.S. Department of Veterans Affairs Facilities Management Critical Path Method design DECEMBER 2012 Volume I Design Manual for & TABLE OF CONTENTS, Volume I 1. INTRODUCTION... 3 1.1. Purpose and Scope...

More information

The Project Planning Process Group

The Project Planning Process Group 3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity

More information

Systems Analysis and Design

Systems Analysis and Design Systems Analysis and Design Slides adapted from Jeffrey A. Hoffer, University of Dayton Joey F. George, Florida State University Joseph S. Valacich, Washington State University Modern Systems Analysis

More information

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E. Memorandum To: Thru: Jeff Jasper, P.E. Director, Division of Design Rachel Mills, P.E. Technical Support TEBM, Division of Construction From: Jeremiah Littleton, P.E. Division of Construction Date: June

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS Chapter 3 of Systems Analysis and Design in a Changing World explains the techniques and steps required to build a project schedule

More information

Cambridge International AS and A Level Computer Science

Cambridge International AS and A Level Computer Science Topic support guide Cambridge International AS and A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains

More information

MECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management

MECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor (hefny@cs.queensu.ca and surgenor@me.queensu.ca) Winter : Lecture # Project Time Management Homework Discussion Homework

More information

Develop Project Charter. Develop Project Management Plan

Develop Project Charter. Develop Project Management Plan Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs

More information

Project management Project Management

Project management Project Management Project management Project Management Dr. James A. Bednar jbednar@inf.ed.ac.uk http://homepages.inf.ed.ac.uk/jbednar A project is a temporary endeavour to produce a unique product, service, or result (PMI

More information

Module 3: The Project Planning Stage

Module 3: The Project Planning Stage Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you

More information

Information Technology Project Management

Information Technology Project Management Information Technology Project Management by Jack T. Marchewka Power Point Slides by Jack T. Marchewka, Northern Illinois University Copyright 2006 John Wiley & Sons, Inc. all rights reserved. Reproduction

More information

Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them

Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them Sponsored by Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them Joseph A. Lukas PMP, CSM, CCP, PE White Paper 1-888-762-3683 www.pmcentersusa.com Joe Lukas & PM Centers USA, LLC

More information

PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE

PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE A. General. The progress schedule required for this project is the critical path method schedule (CPM schedule). The Contractor shall designate

More information

CPM-200: Principles of Schedule Management

CPM-200: Principles of Schedule Management CPM-: Principles of Schedule Management Lesson B: Critical Path Scheduling Techniques Instructor Jim Wrisley IPM Fall Conference PMI-College of Performance Management Professional Education Program Copyright

More information

Project Time Management

Project Time Management CHAPTER 8 Project Time Management The project scope identifies the objectives of the project, what activities will be performed, and some of the activities that are not included in the project. The scope

More information

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10) CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements

More information

Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur

Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur Module 11 Software Project Planning Lesson 29 Staffing Level Estimation and Scheduling Specific Instructional Objectives At the end of this lesson the student would be able to: Identify why careful planning

More information

SWEN 256 Software Process & Project Management

SWEN 256 Software Process & Project Management SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end

More information

Earned Value Analysis Exercise

Earned Value Analysis Exercise Earned Value Analysis Exercise www.spmbook.com Author: Adolfo Villafiorita Revision: 2 (205-02-06) Given the following project plan: ID Task Immediate Predecessor (*) Expected Duration (days) Budget ($)

More information

Frequently Asked Questions in Project Management

Frequently Asked Questions in Project Management Frequently Asked Questions in Project Management 1. Question: What is Project Management? Answer: Project Management is the collection and application of skills, knowledge, processes, and activities to

More information

An Introduction to the Management Principles of Scheduling

An Introduction to the Management Principles of Scheduling College of Engineering VDOT-VT Partnership for Project Scheduling Charles Edward Via, Jr. Department of Civil and Environmental Engineering 200 Patton Hall (0105) Blacksburg, Virginia 24061 540/231-0923

More information

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT 6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity

More information

CISC 322 Software Architecture. Project Scheduling (PERT/CPM) Ahmed E. Hassan

CISC 322 Software Architecture. Project Scheduling (PERT/CPM) Ahmed E. Hassan CISC 322 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan Project A project is a temporary endeavour undertaken to create a "unique" product or service A project is composed of a number

More information

Chapter 6. (PMBOK Guide)

Chapter 6. (PMBOK Guide) Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:

More information

State of Michigan (SOM) August 2013. Department of Technology, Management & Budget

State of Michigan (SOM) August 2013. Department of Technology, Management & Budget State of Michigan (SOM) PROJECT MANAGEMENT KEY TERMS, DEFINITIONS AND ACRONYMS August 2013 Department of Technology, Management & Budget Table of Contents Table of Contents Key Terms, Definitions, and

More information

CSSE 372 Software Project Management: Software Project Scheduling

CSSE 372 Software Project Management: Software Project Scheduling CSSE 372 Software Project Management: Software Project Scheduling Shawn Bohner Office: Moench Room F212 Phone: (812) 877-8685 Email: bohner@rose-hulman.edu Examination #1 Results Average Score 82.70% Median

More information

The Plan s Journey From Scope to WBS to Schedule

The Plan s Journey From Scope to WBS to Schedule The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)

More information

Network Calculations

Network Calculations Network Calculations The concepts and graphical techniques described in this week s readings form the basis of the tools widely used today to manage large projects. There is no way of simplifying the tasks

More information

PROJECT MANAGEMENT GLOSSARY OF TERMS

PROJECT MANAGEMENT GLOSSARY OF TERMS PROJECT MANAGEMENT GLOSSARY OF TERMS Contents A...3 B...4 C...4 D...10 E...11 F...12 G...14 H...15 I...15 J...15 K...15 L...15 M...17 N...18 O...18 P...19 Q...26 R...27 S...30 T...34 U...36 V...36 W...37

More information

Software Project Management

Software Project Management Software Project Management Project: unique process, consisting of a set of coordinated and controlled activities with start and finish dates, undertaken to achieve an objective conforming to specific

More information

www.pmworldjournal.net Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP

www.pmworldjournal.net Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP PMBOK Guide 5 th Edition and MS Project 2010: A Practical Step-by-Step Approach 1. Abstract By Satya Narayan Dash, PMP, CSM, MCP Project Management Body of Knowledge (PMBOK) Guide, from PMI, comes with

More information

Introduction to Project Management ECE 480. Erik Goodman

Introduction to Project Management ECE 480. Erik Goodman Introduction to Project Management ECE 480 Erik Goodman What is Project Management? a method for organizing tasks a structured framework to help a group work productively tools to aid in task sequencing,

More information

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose 1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing

More information

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain * TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited

More information

SCHEDULING AND TIME MANAGEMENT. Project Management and Leadership 2015D, PhD, PMP

SCHEDULING AND TIME MANAGEMENT. Project Management and Leadership 2015D, PhD, PMP SCHEDULING AND TIME MANAGEMENT Project Management and Leadership 2015D, PhD, PMP Our PROGRAMME: 1. INTRODUCTION TO PROJECT MANAGEMENT 2. STARTING A PROJECT 3. WORK MOTIVATION 4. COMMUNICATION 5: TEAMS

More information

CRITICAL PATH METHOD (CEE 320 VDC SEMINAR)

CRITICAL PATH METHOD (CEE 320 VDC SEMINAR) CRITICAL PATH METHOD (CEE 320 VDC SEMINAR) 4 February 2009 Jesse Santiago & Desirae Magallon Overview Background & History CPM Defined The CPM approach Definitions Class Exercise Background & History Developed

More information

Unit 1: Project Planning and Scheduling

Unit 1: Project Planning and Scheduling Unit : Project Planning and Scheduling Objective Ð To provide a brief introduction to project planning and scheduling. The critical area where project management meets system development. ackground Most

More information

SE351a: Software Project & Process Management

SE351a: Software Project & Process Management SE351a: Software Project & Process Management W8: Software Project Planning 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa SE351 Roadmap Introduction to Software Project Management Project Management

More information

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones

More information

Network Planning and Analysis

Network Planning and Analysis 46 Network Planning and Analysis 1. Objective: What can you tell me about the project? When will the project finish? How long will the project take (project total duration)? 2. Why is this topic Important

More information

PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7

PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7 PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7 Duration: 03 days INTRODUCTION This course provides hands-on training for Primavera s web-based solution. Participants will create a project, add activities

More information

PROJECT PROPOSAL: PROJECT BLUE ZUMA

PROJECT PROPOSAL: PROJECT BLUE ZUMA PROJECT PROPOSAL: PROJECT BLUE ZUMA To: From: CC: Dr. Edward J Glantz Alex Bok (ayb5041@psu.edu) Mark Randall Date: February 28 th, 2008 The following documents are detailed reports on our project proposal

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Performing critical path analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the

More information

Introduction to Project Management

Introduction to Project Management Introduction to Project Management Chapter 6 Managing Project Scheduling Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 6-1 What is Project

More information

Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University

Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University Object-Oriented Analysis and Design with the Unified Process John W. Satzinger Southwest Missouri State University Robert B. Jackson Brigham Young University Stephen D. Burd University of New Mexico ALL

More information

SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...

More information

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT PROJECT RISK MANAGEMENT http://www.tutorialspoint.com/pmp-exams/project_risk_management.htm Copyright tutorialspoint.com Here is a list of sample questions which would help you to understand the pattern

More information

SYSTEMS ANALYSIS AND DESIGN DO NOT COPY

SYSTEMS ANALYSIS AND DESIGN DO NOT COPY Systems Analysis and Design in a Changing World, Fourth Edition -488-6-5 Copyright 7 Thomson Course Technology. All rights reserved. FOURTH EDITION SYSTEMS ANALYSIS AND DESIGN IN A C HANGING W ORLD John

More information

02 Project planning. There are two approaches to identifying the components of a project: productbased and work- or activity-based.

02 Project planning. There are two approaches to identifying the components of a project: productbased and work- or activity-based. C H A P T E R T W O 02 Project planning LEARNING OUTCOMES When you have completed this chapter you should be able to demonstrate an understanding of the following: project deliverables and intermediate

More information

This is Project Time Management, chapter 8 from the book Beginning Project Management (index.html) (v. 1.0).

This is Project Time Management, chapter 8 from the book Beginning Project Management (index.html) (v. 1.0). This is Project Time Management, chapter 8 from the book Beginning Project Management (index.html) (v. 1.0). This book is licensed under a Creative Commons by-nc-sa 3.0 (http://creativecommons.org/licenses/by-nc-sa/

More information

Developing Critical Path Method Scheduling (CPM)

Developing Critical Path Method Scheduling (CPM) Developing Critical Path Method Scheduling (CPM) Pretest 1. An activity which is on critical path has a planned duration of 5 days. What is the total float for the activity? a. 0 b. 1 c. 2 d. 3 Pretest

More information

PMBOK GLOSSARY. Activity Duration Estimating. Estimating the number of work periods which will be needed to complete individual activities.

PMBOK GLOSSARY. Activity Duration Estimating. Estimating the number of work periods which will be needed to complete individual activities. PMBOK GLOSSARY Accountability Matrix. See responsibility assignment matrix. Activity. An element of work performed during the course of a project. An activity normally has an expected duration, an expected

More information

Abar Solutions Petroleum Consultancy & Training Qualified From KPC Training & Consulting Services Provider. Code Period Language Start End Location

Abar Solutions Petroleum Consultancy & Training Qualified From KPC Training & Consulting Services Provider. Code Period Language Start End Location Training Course : Project Management Skills & Estimation Development Training Course For One Week In Canada, Montreal, Hyatt Regency Montreal Which Be Held As Under Details : Tel. : 00965 22610021 99600277,

More information

Metadata-Based Project Management System. A Case Study at M-Files Corporation. Iulia Adomnita

Metadata-Based Project Management System. A Case Study at M-Files Corporation. Iulia Adomnita Metadata-Based Project Management System. A Case Study at M-Files Corporation Iulia Adomnita University of Tampere School of Information Sciences Computer Science M.Sc. Thesis Supervisors: Timo Poranen,

More information