Notes on the Critical Path Method for project planning and management.
|
|
|
- Shavonne Stanley
- 9 years ago
- Views:
Transcription
1 E90 Engineering Design Notes on the Critical Path Method for project planning and management. CPM models any project by a network of blocks or circles called NODES that are connected by lines called ARROWS. These represent ACTIVITIES (processes) and EVENTS (states); one has the option of putting Activities on Arrows or Activities on Nodes - the latter method is simpler, quite similar to the use of Block Diagrams for computer programs, and will be presented here. The chief difference between Block Diagrams and CPM Networks is the inclusion of time and duration information in CPM. The object of CPM modeling is to enable project managers to readily visualize the time and precedence relations among all significant project activities, to discover which sequence(s) of activities are Critical to timely project completion, and to investigate the effects of Crashing (accelerating completion) or Slipping (delaying) activities within the project. Regarding E90, CPM can enable you to determine in advance 1) whether your proposed project can be completed on or before a deadline, or needs to be modified in order to achieve timely completion; 2) which activities absolutely must be begun and completed on schedule to permit timely project completion; 3) the latest possible start and latest completion dates for each project activity; and 4) the effect of potential delays in material or equipment availability on final project completion. A very important additional benefit is a week-by-week indication of total project effort ("manpower loading") that you can use to adjust the scope and/or schedule of your project in advance, so that you will then be able to accomplish it and meet all relevant deadlines without sacrificing either your physical or mental health. As a relevant (and mildly recursive) example of CPM use, consider the "project" of creating a CPM network for your E90 Project and producing a finished CPM Network diagram for your Draft Project Proposal. The main activities involved in this project are: A B C D E F G H (I) Making a list of all significant activities included in your project Estimating the time duration and effort needed to complete each activity Determining the precedence/dependence of each activity with respect to the others Becoming familiar with CPM methodology and conventions Creating an initial network diagram showing the activity interrelations within the task Examining the diagram to discover the Critical Path, determine overall time feasibility and effort schedule Adjusting project scope by adding/modifying/deleting tasks until Spring '00 deadlines can be met within realistic time, effort, material/equipment availability and/or other resource constraints Redrawing and preparing the CPM diagram and notes in final format for inclusion in Draft Proposal Printing the CPM Network diagram and supporting documentation for insertion into Draft Proposal
2 The list above is mostly in precedence order; that is typical for simple projects, but such clear definition can seldom be achieved in one pass for more complex projects. Frequently, one must work backward from the final product specification to determine the prior activities required, and in such cases one must be very careful not to omit any significant activity - one that will require anyone's effort in a timely manner. Here, then is the formal Activities List resulting from completion of Activity A: Project: Creating a CPM Network diagram for a Draft E90 Proposal Activity Action A B C D E F G H (I) Make a list of all significant activities included in project Estimate time duration and effort needed to complete each activity Determine precedence/dependence of each activity Become familiar with CPM methodology and conventions Draw initial network diagram showing activity interrelations Examine diagram to discover Critical Path, determine overall time feasibility and effort schedule Adjust project scope and add/modify/delete tasks until deadlines can be met within time, effort and resource constraints Redraw and prepare CPM diagram and notes in final format for inclusion in Draft Proposal Print CPM Network diagram and supporting documentation for insertion into Draft Proposal Activity (I) is optional, required only if the CPM Network and accompanying notes is created and saved as a separate word processing document. Now we add initial Duration and Effort estimates; duration estimates are in days and effort estimates in hours, reflecting the preference of the typical student worker (you) to fit each activity into an existing daily routine rather than do the entire project at once, or even in big chunks. This distinction between Duration and Effort is NOT part of standard CPM texts, but is highly relevant whenever there is part-time activity involved in a project. Minimum increments of duration and effort are here 1 day and 1 hour respectively; others could have been used.
3 Project: Creating a CPM Network diagram for a Draft E90 Proposal Activity Duration Effort Action A 1d 1h List significant activities B 2d 2h Estimate activity duration and effort C 1d 2h Determine activity precedence D 2d 2h Learn CPM fundamentals E 2d 3h Draw initial network diagram F 2d 4h Examine diagram for Critical Path, feasibility, effort schedule G 0-4d 0-8h Adjust project scope, tasks H 3d 4h Prepare final CPM diagram and notes (I) 1d 1h Print CPM Network and supporting docs Next we add precedence information for each activity. At this stage of a larger project, it might become apparent that some activities should be subdivided on account of the subactivities being more or less independent and/or subject to different precedents. Project: Creating a CPM Network diagram for a Draft E90 Proposal Activity Needs Feeds Duration Effort Action A - B 1d 1h List significant activities B A E 2d 2h Estimate activity duration and effort C A E 1d 2h Determine activity precedence D - E 2d 2h Learn CPM fundamentals E B,C,D F 2d 3h Draw initial network diagram F E G 2d 4h Examine diagram for Critical Path, feasibility, effort schedule G F H 0-4d 0-8h Adjust project scope, tasks H G I 3d 4h Prepare final CPM diagram and notes (I) H - 1d 1h Print CPM Network and supporting documents Note that Activity G may not be required if Activity F indicates no need for adjustments.
4 Now we're ready to draw the initial CPM Network (Activities on Nodes). First, lay out the sequence of activities with arrows indicating precedence. Note the smaller arrow connecting F to G, indicating the optional character of G, and the parallel branch indicating that if G is not required, F must still conclude before H can begin. Precedence arrows can emanate from or arrive at the left (Start) or right (Finish) edge of an activity Node, depending upon whether the preceding activity need only be Started or must be Finished before the dependant activity can Start or Finish We now determine the Earliest Start Time (ES) for each activity by making a "forward pass" through the diagram from Start to Finish, beginning with ES=0 for the first activity in any branch and adding the Duration of each activity to determine ES for each subsequent activity. When multiple branches converge at a node, the latest of the possible ESs prevails. We also determine the Latest Start Time (LS) for each activity by making a "backward pass" from Finish to Start, subtracting the duration of each activity from LS of the subsequent one to determine LS for that activity. When multiple branches emanate from a node, the earliest of the possible LSs prevails. Below we add the Earliest and Latest Start Time information to each activity by writing its ES,LS above the node. In this particular diagram, the smaller arrowhead on the dashed arrow from G to H indicates that H may not require G.
5 Now we're ready to find the Critical Path for this network. Any arrow connecting nodes that each have equal ES and LS values is part of the Critical Path. Nodes having unequal ES and LS values have "Slack" or "Float" time associated with that activity equal to the difference between ES and LS. There is no slack anywhere on a Critical Path - any delay or "slip" in an activity on the Critical Path results in equal slip at the Finish. Thick arrows below denote the Critical Path: Now that we have found the Critical Path, we can note several things about this project: 1) Total duration is 15 days Start to Finish. If the project deadline were less than 15 days distant from today, this project could not be completed on time unless one or more activity durations along the Critical Path were reduced. Such reductions are possible, because activity duration, as distinct from effort, is somewhat discretionary. 2) Activity G is on the Critical Path, even though it might not be required, because one cannot decide whether to eliminate it until Activity F is complete; thus sufficient time must be built into the project schedule. If G turns out not to be necessary, the project can be completed as many as four days sooner, or some vacation days may be enjoyed. 3) Activities C and D each have one day slack; one can start these activities anywhere between their ES and LS without compromising timely project completion.
6 But we're not done yet. Because critical path analysis assumes that time is the critical resource, and because this particular project (preparation of a CPM Network diagram for an E90 proposal) will most probably be the work of one person, it would be prudent to examine an effort schedule as well. Day by Day Activities Summary Day Act s. In Progress Act. Effort Hrs Day s Total Effort Total Hrs to Date 0 A, (D) 1, (0-2) B, (D), (C) 1, (0-2), (0-2) B, (D), (C) 1, (0-2), (0-2) E E F F G G G G H H H I Done This list makes it quite apparent that the Duration of most activities could be reduced at the cost of increased daily Effort. However, that might well conflict with one's other responsibilities and priorities that day a situation that is dangerous to overlook if you are planning an E90 project on a weekly (rather than daily) basis and some weeks are known in advance to include important professional (job seeking), social, familial or institutional obligations.
7 Another very useful project planning tool is a chart showing activities versus time - known in business as a GANTT chart or a Milestone Chart. Here is the one for our project corresponding to the Activities Summary list: Thin lines here indicate optional activity placement (e.g. C requires 1 day between Days 1 and 3). Thick lines indicate activities that are on the Critical Path. A Hardcopy of such a chart readily permits easy comparison of Planned (printed as shown) versus Actual (written in using contrasting color(s)) project activity. Significant deadlines or other milestones can be added using markers along the timeline or at the End of appropriate activities. The Specification, Purchase ordering, Delivery and/or Construction and Availability of important items of equipment, instrumentation or supplies can be included in projects as appropriate Activities. Such things are frequently on a project's Critical Path but are not sufficiently acknowledged by appearance in the CPM Network; naively excluding them is a serious and often risking omission.
8 For the "project" of creating a CPM analysis for an E90 Senior Engineering Design Project, this handout has presented each of the necessary steps in turn. Your CPM analysis for your own E90 project should therefore include: 1) an Activities List written in sufficient detail to enable the reader to understand the scope and output of each activity; 2) a Table of Activities showing Needs/Feeds, Duration and Effort for each Activity; 3) a CPM Network diagram showing ES/LS, Precedence and Duration for each Activity, and clearly indicating the Critical Path; 4) a GANTT or Milestone Chart showing Activities versus Time, and indicating appropriate Deadlines and/or Milestones; and 5) a Bill of Materials and/or Equipment List describing all critical physical resources whose timely availability is mentioned and indicated within the project plan. * * * THE END * * *
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
Chapter 2: Project Time Management
Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.
PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM)
PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM) Project Evaluation Review Technique (PERT) and Critical Path Method (CPM) are scheduling techniques used to plan, schedule, budget
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072
Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define
Project Planning and Scheduling
Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination
The work breakdown structure can be illustrated in a block diagram:
1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as
Scheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
Operational Research. Project Menagement Method by CPM/ PERT
Operational Research Project Menagement Method by CPM/ PERT Project definition A project is a series of activities directed to accomplishment of a desired objective. Plan your work first..then work your
ME 407 Mechanical Engineering Design Spring 2016
ME 407 Mechanical Engineering Design Spring 2016 Project Planning & Management Asst. Prof. Dr. Ulaş Yaman Acknowledgements to Dieter, Engineering Design, 4 th edition Ullman, The Mechanical Design Process,
ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS
ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS Chapter 3 of Systems Analysis and Design in a Changing World explains the techniques and steps required to build a project schedule
Critical Path Analysis & PERT Charts (taken from www.business.com.
Critical Path Analysis & PERT Charts (taken from www.business.com. - Planning and scheduling more complex projects Critical Path Analysis and PERT are powerful tools that help you to schedule and manage
Project Time Management
Project Time Management By Augsburg College 1 Learning Objectives Understand the importance of project schedules and good project time management Define activities as the basis for developing project schedules
Network Calculations
Network Calculations The concepts and graphical techniques described in this week s readings form the basis of the tools widely used today to manage large projects. There is no way of simplifying the tasks
Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management
Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute
Chapter 6: Project Time Management
CIS 486 Managing Information Systems Projects Fall 2003 (Chapter 6), PhD [email protected] California State University, LA Computer and Information System Department Chapter 6: Project Time Management
Chapter 4: Project Time Management
Chapter 4: Project Time Management Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project
Time Management. Part 5 Schedule Development. Richard Boser
Time Management Part 5 Schedule Development Richard Boser 6.5 Schedule Development Inputs Organizational Process Assets Scope Statement Activity List Activity Attributes Network Diagrams Resource Req ms
8. Project Time Management
8. Project Time Management Project Time Management closely coordinated Two basic approaches -bottom-up (analytical) -top-down (expert judgement) Processes required to ensure timely completion of the project
MECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor ([email protected] and [email protected]) Winter : Lecture # Project Time Management Homework Discussion Homework
Cambridge International AS and A Level Computer Science
Topic support guide Cambridge International AS and A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains
Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur
Module 11 Software Project Planning Lesson 29 Staffing Level Estimation and Scheduling Specific Instructional Objectives At the end of this lesson the student would be able to: Identify why careful planning
Unit 1: Project Planning and Scheduling
Unit : Project Planning and Scheduling Objective Ð To provide a brief introduction to project planning and scheduling. The critical area where project management meets system development. ackground Most
Learning Objectives. Learning Objectives (continued) Importance of Project Schedules
Chapter 6: Project Time Management Information Technology Project Management, Fifth Edition Learning Objectives Understand the importance of project schedules and good project time management Define activities
Systems Analysis and Design
Systems Analysis and Design Slides adapted from Jeffrey A. Hoffer, University of Dayton Joey F. George, Florida State University Joseph S. Valacich, Washington State University Modern Systems Analysis
Project Management Glossary
Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project
Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition
Lecture 6: Project Time Management By: Prof. Lili Saghafi Information Technology Project Management, Fifth Edition Learning Objectives 2 Understand the importance of project schedules and good project
Use project management tools
Use project management tools Overview Using project management tools play a large role in all phases of a project - in planning, implementation, and evaluation. This resource will give you a basic understanding
Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University
Object-Oriented Analysis and Design with the Unified Process John W. Satzinger Southwest Missouri State University Robert B. Jackson Brigham Young University Stephen D. Burd University of New Mexico ALL
SYSTEMS ANALYSIS AND DESIGN DO NOT COPY
Systems Analysis and Design in a Changing World, Fourth Edition -488-6-5 Copyright 7 Thomson Course Technology. All rights reserved. FOURTH EDITION SYSTEMS ANALYSIS AND DESIGN IN A C HANGING W ORLD John
A Short Introduction to Project Management
2003 January April SFWR ENG 2B03 Slides 08 0 A Short Introduction to Project Management SFWR ENG 2B03 2003 Robert L. Baber 2003 January April SFWR ENG 2B03 Slides 08 1 Why Project Management? Why manage
Chapter-6. Developing a Project Plan
MGMT 4135 Project Management Chapter-6 Where we are now Developing the Project Network Why? Graphical representation of the tasks to be completed Logical sequence of activities Determines dependencies
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking
Leaving Certificate Technology. Project Management. Student Workbook
Leaving Certificate Technology Project Management Student Workbook Project Management Student notes Introduction Project management is the name given to a number of techniques used in industry to manage
Leaving Certificate Technology. Project Management. Teacher Notes
Leaving Certificate Technology Project Management Teacher Notes 1 Project Management This is the first of three key topics that form Project and Quality Management in the Technology Syllabus core. These
Project Management Chapter 3
Project Management Chapter 3 How Project Management fits the Operations Management Philosophy Operations As a Competitive Weapon Operations Strategy Project Management Process Strategy Process Analysis
Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014
Project Management Six Session Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Mohamed Khalifa, 2014 All Rights 1 7. Scheduling 2 7. Scheduling 7.1 Scheduling techniques 7.3 Critical path method
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps
Project Planning What are you going to do in the project? Lecture Objectives To discuss the tasks in planning a project To describe the tools that can be used for developing a project plan To illustrate
Scheduling. Anne Banks Pidduck Adapted from John Musser
Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart
Basic Concepts. Project Scheduling and Tracking. Why are Projects Late? Relationship between People and Effort
Basic s Project Scheduling and Tracking The process of building a schedule for any case study helps really understand how it s done. The basic idea is to get across to break the software project into well-defined
Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False
Chapter 1.7 Project Management Part I: Objective type questions and answers 1. Project financing is one of the step of project management- State True or False 2. Proposed new technologies, process modifications,
Mastering Microsoft Project 2010
Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project
OVERVIEW. Microsoft Project terms and definitions
PROJECT 2003 DISCLAIMER: This reference guide is meant for experienced Microsoft Project users. It provides a list of quick tips and shortcuts for familiar features. This guide does NOT replace training
Guidance on Critical Path Analysis
Guidance on Critical Path Analysis OCR GCE in Applied Business Unit F248 (Unit 9): Strategic Decision Making As part of the assessment for Unit F248 Strategic Decision-Making the examination may contain
Scheduling Resources and Costs
Student Version CHAPTER EIGHT Scheduling Resources and Costs McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Gannt Chart Developed by Henry Gannt in 1916 is used
Lecture 26 CPM / PERT Network Diagram
Lecture 26 CPM / PERT Network Diagram 26.1 Introduction to CPM / PERT Techniques CPM (Critical Path Method) was developed by Walker to solve project scheduling problems. PERT (Project Evaluation and Review
Time Management II. http://lbgeeks.com/gitc/pmtime.php. June 5, 2008. Copyright 2008, Jason Paul Kazarian. All rights reserved.
Time Management II http://lbgeeks.com/gitc/pmtime.php June 5, 2008 Copyright 2008, Jason Paul Kazarian. All rights reserved. Page 1 Outline Scheduling Methods Finding the Critical Path Scheduling Documentation
Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead
Project Management (CS 3730) Lecture 4 Name:
Ch. 6: Scheduling Project Work 1. Some people think that project management is nothing but scheduling, but scheduling is just one of the tools used to manage jobs and should not be considered the primary
Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org
Planning and Managing Software Projects 2011-12 Class 9 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides
02 Project planning. There are two approaches to identifying the components of a project: productbased and work- or activity-based.
C H A P T E R T W O 02 Project planning LEARNING OUTCOMES When you have completed this chapter you should be able to demonstrate an understanding of the following: project deliverables and intermediate
Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration
Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Prof. M. Rammohan Rao Former Dean Professor Emeritus Executive Director, Centre for Analytical
Collaborative Scheduling using the CPM Method
MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines
Appendix A of Project Management. Appendix Table of Contents REFERENCES...761
Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity
5. Creating a Gantt Chart
5. Creating a Gantt Chart Whilst the network diagram is a useful way to describe how tasks are linked to each other, the Gantt chart is used to display the schedule of a project. The Gantt chart is the
CISC 322 Software Architecture. Project Scheduling (PERT/CPM) Ahmed E. Hassan
CISC 322 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan Project A project is a temporary endeavour undertaken to create a "unique" product or service A project is composed of a number
The principles, processes, tools and techniques of project management
Unit 34: Plan and manage a project. 341 The principles, processes, tools and techniques of project management An industrial project, big or small, must be managed effectively to ensure the project s objectives
CRITICAL PATH METHOD (CPM) SCHEDULES
96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without
Introduction to Project Management ECE 480. Erik Goodman
Introduction to Project Management ECE 480 Erik Goodman What is Project Management? a method for organizing tasks a structured framework to help a group work productively tools to aid in task sequencing,
Chapter 3 Managing the Information Systems (IS) Project
Content Chapter 3 Managing the Information Systems (IS) Project Process of managing IS projects Skills required to be an effective project manager Skills and activities of a project manager during project
7. PROJECT MANAGEMENT
7. PROJECT MANAGEMENT Syllabus Definition and scope of project, Technical design, Financing, Contracting, Implementation and performance monitoring. Implementation plan for top management, Planning Budget,
MS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado
CS 587 Software Project Management Instructor: Dr. Atef Bader MS Project Tutorial MS Project in Labs: Available in Siegal Hall Lab in Main Campus Available in Room 210 Rice Campus Prepared by Milton Hurtado
College of Engineering and Applied Science University of Wisconsin -- Milwaukee
Edward A. Beimborn and W. Anthony Garvey College of Engineering and Applied Science University of Wisconsin -- Milwaukee The Blob Chart:: A Simplified Method of Allocating Resources over Time Edward Beimborn
Programmes. Unit 3: P lanning construction work processes and efficient use of resources in construction and the built environment.
Unit : P lanning construction work processes and efficient use of resources in construction and the. Links This topic links to: HNC in Construction and the Built Environment Unit : LO; HNC Unit 15: LO.
A GUIDE TO NETWORK ANALYSIS by MICHAEL C GLEN
Introduction A GUIDE TO NETWORK ANALYSIS by MICHAEL C GLEN The core technique available to Project Managers for planning and controlling their projects is Network Analysis. This short guide will provide
PROJECT TIME MANAGEMENT
6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity
Project Management Dr. James A. Bednar
Project Management Dr. James A. Bednar [email protected] http://homepages.inf.ed.ac.uk/jbednar SAPM Spring 2006: Project Management 1 Project Management A project is a temporary endeavour to produce
Mastering Microsoft Project 2013
Course 55054: Mastering Microsoft Project 2013 Page 1 of 9 Mastering Microsoft Project 2013 Course 55054: 2 days; Instructor-Led Introduction This two-day, instructor-led course is intended for individuals
Precedence Diagram Method. CSTM 462 Planning & Scheduling
Precedence Diagram Method CSTM 462 Planning & Scheduling Precedence Diagramming Method (PDM) PDM is more flexible than AON or AOA networks because PDM allows the overlapping of concurrent activities.
MSc Project Planning
MSc Project Planning Dr Paul Brunn 4 th February 2009 Project Planning and Control Intro to General Methods Some simple examples How to plan and complete an MSc Dissertation project EPS Graduate Education
Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days
3 Riverchase Office Plaza Hoover, Alabama 35244 Phone: 205.989.4944 Fax: 855.317.2187 E-Mail: [email protected] Web: www.discoveritt.com Mastering Microsoft Project 2013 Course: 55054A Course Length:
NE-50413B Mastering Microsoft Project 2010
NE-50413B Mastering Microsoft Project 2010 Summary Duration Vendor 3 Days Microsoft Audience This course is intended for both novice and experienced Project Managers and project support personnel who need
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
A. O. Odior Department of Production Engineering University of Benin, Edo State. E-mail: [email protected]
2012 Cenresin Publications www.cenresinpub.org APPLICATION OF PROJECT MANAGEMENT TECHNIQUES IN A CONSTRUCTION FIRM Department of Production Engineering University of Benin, Edo State. E-mail: [email protected]
10 Project Management with PERT/CPM
10 Project Management with PERT/CPM 468 One of the most challenging jobs that any manager can take on is the management of a large-scale project that requires coordinating numerous activities throughout
Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen + Antworten October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 1 All the following Statements about a WBS are true except that it a. Provides a framework for
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP [email protected] Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
Project Scheduling: PERT/CPM
Project Scheduling: PERT/CPM CHAPTER 8 LEARNING OBJECTIVES After completing this chapter, you should be able to: 1. Describe the role and application of PERT/CPM for project scheduling. 2. Define a project
CSSE 372 Software Project Management: Software Project Scheduling
CSSE 372 Software Project Management: Software Project Scheduling Shawn Bohner Office: Moench Room F212 Phone: (812) 877-8685 Email: [email protected] Examination #1 Results Average Score 82.70% Median
Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose
1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing
CRITICAL PATH METHOD (CEE 320 VDC SEMINAR)
CRITICAL PATH METHOD (CEE 320 VDC SEMINAR) 4 February 2009 Jesse Santiago & Desirae Magallon Overview Background & History CPM Defined The CPM approach Definitions Class Exercise Background & History Developed
technical tips and tricks
technical tips and tricks Performing critical path analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the
Devising new Software Project Risk Management Model: MARUNA
Devising new Software Project Risk Management Model: MARUNA Bekim Fetaji South East European University, Computer Sciences, Ilindenska bb, 00 Tetovo, Macedonia Abstract The focus of this research is the
Project Scheduling and Gantt Charts
Project Scheduling and Gantt Charts Siddharth Gangadhar Dr. Prasad Kulkarni Department of Electrical Engineering & Computer Science Lab Presentation [email protected] [email protected] 4 November 2015 2015
Applied Software Project Management
Applied Software Project Management Project Schedules http://www.stellman-greene.com 1 What is a project schedule? The project schedule is a calendar that links the tasks to be done with the resources
Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa
Project Creation and Gantt Chart Design Using Microsoft Project R. Baker The University of Tampa What is Microsoft Project? Microsoft Project is a software package designed help managers manage a variety
Review on Using Packages to Enhance the Teaching of Critical Path Networks
Review on Using Packages to Enhance the Teaching of Critical Path Networks Harry S Ku Abstract The aim of this paper is to review a published paper, Using computer software packages to enhance the teaching
SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards...
SECTION 01311 - CONSTRUCTION SCHEDULE B CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement
Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led
Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Course Description This three-day instructor-led course provides students with the knowledge and skills plan and manage projects using Microsoft
Project Management DISCUSSION QUESTIONS
3 C H A P T E R Project Management DISCUSSION QUESTIONS. There are many possible answers. Project management is needed in large construction jobs, in implementing new information systems, in new product
Introduction to Project Management
L E S S O N 1 Introduction to Project Management Suggested lesson time 50-60 minutes Lesson objectives To be able to identify the steps involved in project planning, you will: a b c Plan a project. You
12 Network Scheduling Techniques
Page 671 12 Network Scheduling Techniques 12.0 Introduction Management is continually seeking new and better control techniques to cope with the complexities, masses of data, and tight deadlines that are
Dashboards and Reporting for Program Management
MnDOT Project Management Office Presents: Dashboards and Reporting for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will
In initial planning phases In monitoring and execution phases
Project management What is it? Project management is a framework for a range of tools for helping plan and implement development and change projects. A range of tools exist, including: Gantt charts (bar
Quick Guide Business Process Modeling Notation (BPMN)
Quick Guide Business Process Modeling Notation (BPMN) IDM Technical Team January 2007 Quick Guide: BPMN 2 of 14 The scope of this document is to provide a quick guide to the concepts and usage of the Business
BUSINESS OCR LEVEL 3 CAMBRIDGE TECHNICAL. Cambridge TECHNICALS BUSINESS PROJECT MANAGEMENT CERTIFICATE/DIPLOMA IN K/502/5459 LEVEL 3 UNIT 18
Cambridge TECHNICALS OCR LEVEL 3 CAMBRIDGE TECHNICAL CERTIFICATE/DIPLOMA IN BUSINESS BUSINESS PROJECT MANAGEMENT K/502/5459 LEVEL 3 UNIT 18 GUIDED LEARNING HOURS: 60 UNIT CREDIT VALUE: 10 BUSINESS PROJECT
MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Schedule Float Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar