Guidance on Critical Path Analysis
|
|
|
- Ashley Moody
- 9 years ago
- Views:
Transcription
1 Guidance on Critical Path Analysis OCR GCE in Applied Business Unit F248 (Unit 9): Strategic Decision Making As part of the assessment for Unit F248 Strategic Decision-Making the examination may contain questions concerning critical path analysis. Candidates are likely to be asked one or more of the following: 1. To complete a network diagram from data given in a gantt chart or table 2. To complete a network diagram by filling-in the EST and LFT entries for the remaining nodes 3. To calculate the float time for a given activity 4. To determine the shortest time in which a project can be completed 5. To identify a critical path 6. To analyse a network diagram 7. To evaluate the usefulness of critical path as a decision-making tool. All questions require the candidate to have a sound understanding of the mechanics of critical path analysis in order to access the available marks. In the examination the network diagram will be presented according to common convention: Nodes will be labelled by number and tasks by letter. Nodes will be shown as circles and elapsed time by arrows. The EST (earliest start time for an activity) is to be positioned in the top right quadrant of the node and the LFT (latest finish time) in the bottom right quadrant. In the notation diagram which follows (units in days): The node number is 3. The earliest start time for the following tasks is day 16. The latest finish time for the preceding tasks is day 21. The task which follows node 3 is labelled task D and will take 6 days.
2 days In the examination the network diagram itself will vary in composition depending on the number, dependence and concurrency of tasks in the project being illustrated. In all cases, however, candidates should be taught to begin by inserting the EST for each task into the appropriate node working in order from left to right. Only when the final node is reached should candidates insert the LFT entries, this time working in order from right to left. The shortest length of time that a project can be completed by is shown in the final node (farthest right). The critical path can be identified by following the path where the EST and LFTs are the same. The formula for calculating the total float for a task is: LFT at end of task duration of task EST at start of task. Worked example: Racoons Restaurant has decided to carry out some market research to find out existing customers and local residents attitudes to the proposed extension of its opening hours. The tasks involved are shown in the table below. Task Description Order/Logic Duration A Plan primary research To be completed first 1 week B Prepare postal questionnaire Start when A is complete 3 weeks C Prepare survey Start when A is complete 2 weeks D Post questionnaires and wait for replies Start when B is complete 3 weeks E Send surveys and wait for replies Start when C is complete 3 weeks F Analyse results Start when D and E are complete 4 weeks
3 Network diagram: Required: (a) Complete the network diagram by inserting the EST (earliest start time) and LFT (latest finish time) for each node on the diagram. (b) Calculate the total float for task C. (c) Identify the critical path. (d) Identify the shortest length of time it can take to complete this market research.
4 Method: (a) (i) First enter the ESTs for all nodes from left to right beginning with node 1. (ii) Then enter the LFTs for all nodes from right to left beginning with node 6.
5 (b) Formula for total float for activity C is LFT at end of task C duration of task C EST at start of task C. EST at start of task C Duration of task C LFT at end of task C Total float for activity C is, therefore: = 1 week (c) The network diagram shows that all nodes have equal EST and LFTs apart from node 4. The critical path is, therefore, A B D F (d) The shortest length of time it can take to complete the market research is shown in the final node, node 6. Shortest time to completion = 11 weeks
Project Planning and Scheduling
Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination
Programmes. Unit 3: P lanning construction work processes and efficient use of resources in construction and the built environment.
Unit : P lanning construction work processes and efficient use of resources in construction and the. Links This topic links to: HNC in Construction and the Built Environment Unit : LO; HNC Unit 15: LO.
Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management
Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute
Use project management tools
Use project management tools Overview Using project management tools play a large role in all phases of a project - in planning, implementation, and evaluation. This resource will give you a basic understanding
Leaving Certificate Technology. Project Management. Student Workbook
Leaving Certificate Technology Project Management Student Workbook Project Management Student notes Introduction Project management is the name given to a number of techniques used in industry to manage
Critical Path Analysis & PERT Charts (taken from www.business.com.
Critical Path Analysis & PERT Charts (taken from www.business.com. - Planning and scheduling more complex projects Critical Path Analysis and PERT are powerful tools that help you to schedule and manage
02 Project planning. There are two approaches to identifying the components of a project: productbased and work- or activity-based.
C H A P T E R T W O 02 Project planning LEARNING OUTCOMES When you have completed this chapter you should be able to demonstrate an understanding of the following: project deliverables and intermediate
Operational Research. Project Menagement Method by CPM/ PERT
Operational Research Project Menagement Method by CPM/ PERT Project definition A project is a series of activities directed to accomplishment of a desired objective. Plan your work first..then work your
Chapter 2: Project Time Management
Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.
Precedence Diagram Method. CSTM 462 Planning & Scheduling
Precedence Diagram Method CSTM 462 Planning & Scheduling Precedence Diagramming Method (PDM) PDM is more flexible than AON or AOA networks because PDM allows the overlapping of concurrent activities.
Leaving Certificate Technology. Project Management. Teacher Notes
Leaving Certificate Technology Project Management Teacher Notes 1 Project Management This is the first of three key topics that form Project and Quality Management in the Technology Syllabus core. These
A GUIDE TO NETWORK ANALYSIS by MICHAEL C GLEN
Introduction A GUIDE TO NETWORK ANALYSIS by MICHAEL C GLEN The core technique available to Project Managers for planning and controlling their projects is Network Analysis. This short guide will provide
Cambridge International AS and A Level Computer Science
Topic support guide Cambridge International AS and A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
CRITICAL PATH ANALYSIS AND GANTT CHARTS
CRITICAL PATH ANALYSIS AND GANTT CHARTS 1. An engineering project is modelled by the activity network shown in the figure above. The activities are represented by the arcs. The number in brackets on each
Time Planning and Control
TOBIC 4 TIM SCLD NTWORK 1 June 3013 Time Planning and Control Time-Scaled Network G404 NGINRING MNGMNT 1 TOBIC 4 TIM SCLD NTWORK 1 June 3013 Processes of Time Planning and Control 1. Visualize and define
Notes on the Critical Path Method for project planning and management.
E90 Engineering Design Notes on the Critical Path Method for project planning and management. CPM models any project by a network of blocks or circles called NODES that are connected by lines called ARROWS.
25Project management
5Project management A Activity 5.1 (page ) 1 Verify the ESTs above by working through the diagram from left to right, taking the longest route, in days, to each node. Node 1 3 5 7 8 EST 0 0 + 8 = 8 0 +
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking
Project Time Management
Project Time Management By Augsburg College 1 Learning Objectives Understand the importance of project schedules and good project time management Define activities as the basis for developing project schedules
technical tips and tricks
technical tips and tricks Performing critical path analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the
Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072
Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define
BCS THE CHARTERED INSTITUTE FOR IT BCS HIGHER EDUCATION QUALIFICATIONS. BCS Level 5 Diploma in IT APRIL 2013 IT PROJECT MANAGEMENT EXAMINERS REPORT
BCS THE CHARTERED INSTITUTE FOR IT BCS HIGHER EDUCATION QUALIFICATIONS BCS Level 5 Diploma in IT APRIL 2013 IT PROJECT MANAGEMENT EAMINERS REPORT Section A A1 a) Name FOUR criteria by which a project can
Systems Analysis and Design
Systems Analysis and Design Slides adapted from Jeffrey A. Hoffer, University of Dayton Joey F. George, Florida State University Joseph S. Valacich, Washington State University Modern Systems Analysis
Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps
Project Planning What are you going to do in the project? Lecture Objectives To discuss the tasks in planning a project To describe the tools that can be used for developing a project plan To illustrate
Network Calculations
Network Calculations The concepts and graphical techniques described in this week s readings form the basis of the tools widely used today to manage large projects. There is no way of simplifying the tasks
Chapter 6: Project Time Management
CIS 486 Managing Information Systems Projects Fall 2003 (Chapter 6), PhD [email protected] California State University, LA Computer and Information System Department Chapter 6: Project Time Management
EdExcel Decision Mathematics 1
EdExcel Decision Mathematics 1 Notes and Examples Critical Path Analysis Section 1: Activity networks These notes contain subsections on Drawing an activity network Using dummy activities Analysing the
Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration
Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Prof. M. Rammohan Rao Former Dean Professor Emeritus Executive Director, Centre for Analytical
ME 407 Mechanical Engineering Design Spring 2016
ME 407 Mechanical Engineering Design Spring 2016 Project Planning & Management Asst. Prof. Dr. Ulaş Yaman Acknowledgements to Dieter, Engineering Design, 4 th edition Ullman, The Mechanical Design Process,
Scheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
Lecture 26 CPM / PERT Network Diagram
Lecture 26 CPM / PERT Network Diagram 26.1 Introduction to CPM / PERT Techniques CPM (Critical Path Method) was developed by Walker to solve project scheduling problems. PERT (Project Evaluation and Review
Review on Using Packages to Enhance the Teaching of Critical Path Networks
Review on Using Packages to Enhance the Teaching of Critical Path Networks Harry S Ku Abstract The aim of this paper is to review a published paper, Using computer software packages to enhance the teaching
Project Scheduling: PERT/CPM
Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times (as in exercises 1, 2, 3 and 5 in the handout) and considering Time-Cost Trade-Offs (as in exercises 4 and 6 in the handout). This
Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur
Module 11 Software Project Planning Lesson 29 Staffing Level Estimation and Scheduling Specific Instructional Objectives At the end of this lesson the student would be able to: Identify why careful planning
Chapter-6. Developing a Project Plan
MGMT 4135 Project Management Chapter-6 Where we are now Developing the Project Network Why? Graphical representation of the tasks to be completed Logical sequence of activities Determines dependencies
A Generalized PERT/CPM Implementation in a Spreadsheet
A Generalized PERT/CPM Implementation in a Spreadsheet Abstract Kala C. Seal College of Business Administration Loyola Marymount University Los Angles, CA 90045, USA [email protected] This paper describes
CSSE 372 Software Project Management: Software Project Scheduling
CSSE 372 Software Project Management: Software Project Scheduling Shawn Bohner Office: Moench Room F212 Phone: (812) 877-8685 Email: [email protected] Examination #1 Results Average Score 82.70% Median
Priori ty ... ... ...
.Maintenance Scheduling Maintenance scheduling is the process by which jobs are matched with resources (crafts) and sequenced to be executed at certain points in time. The maintenance schedule can be prepared
PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM)
PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM) Project Evaluation Review Technique (PERT) and Critical Path Method (CPM) are scheduling techniques used to plan, schedule, budget
ECDL / ICDL Project Planning Syllabus Version 1.0
ECDL / ICDL Project Planning Syllabus Version 1.0 Purpose This document details the syllabus for ECDL / ICDL Project Planning. The syllabus describes, through learning outcomes, the knowledge and skills
Microsoft Project 2010
Tutorial 1: Planning a Project Microsoft Project 2010 In Tutorial Section 1.1 you will: Learn project management terminology Understand the benefits of project management Explore the Project 2010 window
Scheduling. Anne Banks Pidduck Adapted from John Musser
Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart
MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration
SECTION 01 311 NETWORK ANALYSIS SCHEDULE Part 1.1 DESCRIPTION A. Scope: Provide projected network analysis schedules for the entire Work and revise periodically. This type of schedule is acceptable for
MECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor ([email protected] and [email protected]) Winter : Lecture # Project Time Management Homework Discussion Homework
Project Scheduling: PERT/CPM
Project Scheduling: PERT/CPM CHAPTER 8 LEARNING OBJECTIVES After completing this chapter, you should be able to: 1. Describe the role and application of PERT/CPM for project scheduling. 2. Define a project
A Short Introduction to Project Management
2003 January April SFWR ENG 2B03 Slides 08 0 A Short Introduction to Project Management SFWR ENG 2B03 2003 Robert L. Baber 2003 January April SFWR ENG 2B03 Slides 08 1 Why Project Management? Why manage
Critical Path Analysis
Chapter 13 Critical Path Analysis Basic Concepts Activity An activity is any portion of a project which consumes time or resources and has a definable beginning and ending. For example, laying of pipe
CRITICAL PATH METHOD (CEE 320 VDC SEMINAR)
CRITICAL PATH METHOD (CEE 320 VDC SEMINAR) 4 February 2009 Jesse Santiago & Desirae Magallon Overview Background & History CPM Defined The CPM approach Definitions Class Exercise Background & History Developed
Basic CPM Calculations
Overview Core Scheduling Papers: #7 Basic CPM Calculations Time Analysis calculations in a Precedence Diagramming Method (PDM) Critical Path Method (CPM) network can be done in a number of different ways.
Gantt Chart/Diagram Excel Template User Guide
Gantt Chart/Diagram Excel Template User Guide Excel-based simple Gantt Chart Template This Excel-based template allows a Gantt chart to be easily and quickly developed. As the project progresses, the chart
ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS
ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS Chapter 3 of Systems Analysis and Design in a Changing World explains the techniques and steps required to build a project schedule
Basic Concepts. Project Scheduling and Tracking. Why are Projects Late? Relationship between People and Effort
Basic s Project Scheduling and Tracking The process of building a schedule for any case study helps really understand how it s done. The basic idea is to get across to break the software project into well-defined
Decision Mathematics D1 Advanced/Advanced Subsidiary. Tuesday 5 June 2007 Afternoon Time: 1 hour 30 minutes
Paper Reference(s) 6689/01 Edexcel GCE Decision Mathematics D1 Advanced/Advanced Subsidiary Tuesday 5 June 2007 Afternoon Time: 1 hour 30 minutes Materials required for examination Nil Items included with
Chapter 4: Project Time Management
Chapter 4: Project Time Management Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
A-1. Chapter 1. Project planning. Chapter 1. Festo Didactic Mechatronics
A-1 Project planning A-2 Mechatronics specialists are responsible for the complete service life of an industrial machine, from the initial planning phase through to its disassembly and disposal. This cycle
Work Breakdown Structure & Schedules
A Work Breakdown Structure (WBS) identifies tasks and deliverables associated with a project. Resources are identified for each item within the WBS that facilitates budgeting as well as assignment of responsibilities.
Large Scale Systems Design G52LSS
Large Scale Systems esign 52LSS Lecture 6 Project Scheduling With PRT Project Scheduling PRT iagrams onstructing Pert iagrams Learning outcomes: describe the purpose and steps of project scheduling within
Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose
1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing
Unit 1: Project Planning and Scheduling
Unit : Project Planning and Scheduling Objective Ð To provide a brief introduction to project planning and scheduling. The critical area where project management meets system development. ackground Most
PERT/CPM. Network Representation:
- 1 - PERT/CPM PERT Program Evaluation & Review Technique It is generally used for those projects where time required to complete various activities are not known as a priori. It is probabilistic model
Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University
Object-Oriented Analysis and Design with the Unified Process John W. Satzinger Southwest Missouri State University Robert B. Jackson Brigham Young University Stephen D. Burd University of New Mexico ALL
SYSTEMS ANALYSIS AND DESIGN DO NOT COPY
Systems Analysis and Design in a Changing World, Fourth Edition -488-6-5 Copyright 7 Thomson Course Technology. All rights reserved. FOURTH EDITION SYSTEMS ANALYSIS AND DESIGN IN A C HANGING W ORLD John
ECDL / ICDL Project Planning Project Management Software Level 2. Syllabus Version 1.0 (UK)
ECDL / ICDL Project Planning Project Management Software Level 2 Syllabus Version 1.0 (UK) Purpose This document details the syllabus for ECDL / ICDL Project Planning. The syllabus describes, through learning
SE351a: Software Project & Process Management
SE351a: Software Project & Process Management W8: Software Project Planning 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa SE351 Roadmap Introduction to Software Project Management Project Management
10 Project Management with PERT/CPM
10 Project Management with PERT/CPM 468 One of the most challenging jobs that any manager can take on is the management of a large-scale project that requires coordinating numerous activities throughout
Project Management Glossary
Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project
Project Management Fact Sheet: Developing a Gantt Chart
Project Management Fact Sheet: Developing a Gantt Chart March 2006 What is a Gantt Chart? The Gantt Chart is a horizontal bar chart. It shows the project activities and tasks in sequential order with the
Project Scheduling. Introduction
Project Scheduling Introduction In chapter, the O and ON networks were presented, also the time and cost of individual activities based were calculated. Yet, however, we do not know how long is the total
Software Engineering. Pert and Gantt exercises. Lecturer: Giuseppe Santucci
Software Engineering Pert and Gantt exercises Lecturer: Giuseppe Santucci Degree of freedom! I.3a 3 3 I. I. 3 I.3b I.3c I.4 Exercise s goals. Draw a PERT network (AON) representing a project s characteristics.
Learning Objectives. Learning Objectives (continued) Importance of Project Schedules
Chapter 6: Project Time Management Information Technology Project Management, Fifth Edition Learning Objectives Understand the importance of project schedules and good project time management Define activities
Information Technology Solutions
Connecting People, Process Information & Data Network Systems Diagnostic Testing Information Technology Solutions Getting started in Workflow Designer Prior Learning 1. While it helps to have some knowledge
Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org
Planning and Managing Software Projects 2011-12 Class 9 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides
Time Management. Part 5 Schedule Development. Richard Boser
Time Management Part 5 Schedule Development Richard Boser 6.5 Schedule Development Inputs Organizational Process Assets Scope Statement Activity List Activity Attributes Network Diagrams Resource Req ms
Appendix A of Project Management. Appendix Table of Contents REFERENCES...761
Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity
Critical Path Method (CPM)
Project Management Templates (CPM) http://spreadsheetml.com/projectmanagement/criticalpathanalysis.shtml Copyright (c) 2009-2010, ConnectCode All Rights Reserved. ConnectCode accepts no responsibility
Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition
Lecture 6: Project Time Management By: Prof. Lili Saghafi Information Technology Project Management, Fifth Edition Learning Objectives 2 Understand the importance of project schedules and good project
Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False
Chapter 1.7 Project Management Part I: Objective type questions and answers 1. Project financing is one of the step of project management- State True or False 2. Proposed new technologies, process modifications,
LECTURE 5: SOFTWARE PROJECT MANAGEMENT. Software Engineering Mike Wooldridge
LECTURE 5: SOFTWARE PROJECT MANAGEMENT Mike Wooldridge 1 Introduction The software crisis of the 1960s and 1970s was so called because of a string of high profile software project failures: over budget,
Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project
Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project Project Example Overview Microsoft Project, in addition to scheduling calculations,
The work breakdown structure can be illustrated in a block diagram:
1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as
Topic: The easiest way to calculate Critical Path, Total Float, Free Float, Early Start, Early Finish, Late Start, and Late Finish.
Hot Topics & hallenges Time Management Topic: The easiest way to calculate ritical Path, Total Float, Free Float, Early, Early, Late, and Late. Presenter: Sohel khter, PMP, N,ISMS PMP and Six Sigma instructor,
Aras Corporation. 2005 Aras Corporation. All rights reserved. Notice of Rights. Notice of Liability
Aras Corporation 2005 Aras Corporation. All rights reserved Notice of Rights All rights reserved. Aras Corporation (Aras) owns this document. No part of this document may be reproduced or transmitted in
Graphical Project Planning Techniques: An Overview of Gantt, PERT, and CPM Charts Prepared for groups in ECE480 1/6/02, D. Grover
Introduction/Purpose Graphical Project Planning Techniques: An Overview of Gantt, PERT, and CPM Charts Prepared for groups in ECE480 1/6/02, D. Grover The purpose of this brief tutorial is to present an
Project Management Chapter 3
Project Management Chapter 3 How Project Management fits the Operations Management Philosophy Operations As a Competitive Weapon Operations Strategy Project Management Process Strategy Process Analysis
Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project
SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS
SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
Scheduling Best Practices
In a continuing series of articles on specific aspects of critical path method (CPM) scheduling, Warner examines various facets of the process of preparing, analyzing and utilizing schedules in project
Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6)
Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6) CONSTRUCTION DIVISION (SCHEDULING & CONTRACTS) 1. INTRODUCTION To establish standards and consistent scheduling practices
A Computer Application for Scheduling in MS Project
Comput. Sci. Appl. Volume 1, Number 5, 2014, pp. 309-318 Received: July 18, 2014; Published: November 25, 2014 Computer Science and Applications www.ethanpublishing.com Anabela Tereso, André Guedes and
SCT AND MCAS MIRAMAR FOTS SOUTHERN CALIFORNIA TRACON
1-5 CONSTRUCTION SCHEDULES 1-5.1 General, Network Analysis System (NAS).- 1-5.1.1 Applicable documents.- The Publication listed below forms a part of this specification and is applicable to the extent
Earned Value Analysis Exercise
Earned Value Analysis Exercise www.spmbook.com Author: Adolfo Villafiorita Revision: 2 (205-02-06) Given the following project plan: ID Task Immediate Predecessor (*) Expected Duration (days) Budget ($)
A. O. Odior Department of Production Engineering University of Benin, Edo State. E-mail: [email protected]
2012 Cenresin Publications www.cenresinpub.org APPLICATION OF PROJECT MANAGEMENT TECHNIQUES IN A CONSTRUCTION FIRM Department of Production Engineering University of Benin, Edo State. E-mail: [email protected]
CRITICAL PATH METHOD (CPM) SCHEDULES
96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without
Level 3 Project management software (PM 7574-326)
Level 3 Project management software (PM 7574-326) ITQ (QCF) Assignment guide for Candidates Assignment A www.cityandguilds.com January 2012 Version 1.0 About City & Guilds City & Guilds is the UK s leading
Devising new Software Project Risk Management Model: MARUNA
Devising new Software Project Risk Management Model: MARUNA Bekim Fetaji South East European University, Computer Sciences, Ilindenska bb, 00 Tetovo, Macedonia Abstract The focus of this research is the
CPM-200: Principles of Schedule Management
CPM-: Principles of Schedule Management Lesson B: Critical Path Scheduling Techniques Instructor Jim Wrisley IPM Fall Conference PMI-College of Performance Management Professional Education Program Copyright