1 ME 407 Mechanical Engineering Design Spring 2016 Project Planning & Management Asst. Prof. Dr. Ulaş Yaman Acknowledgements to Dieter, Engineering Design, 4 th edition Ullman, The Mechanical Design Process, 4 th edition
2 Outline Introduction Building a Plan Sample plan Gantt Charts Critical Path Method Review of the Project Planning and Management Report Template R3 Concluding Remarks
3 Introduction Main goal of planningis to have products developed in timely and cost-effective manner. Planning generates a scheme for developing needed information and distributing it to the correct people at the correct time. Figure 5.1, Ullman
4 Building a Plan Project plan is a document that defines the tasks that need to be completed during the design process, keeps project under control. For each task, the plan states objectives personnel requirements time requirements schedule cost
5 Building a Plan There are 5 steps to establish a plan 1. Identify the tasks 2. State the objective for each task 3. Estimate the personnel, time, and other resources needed to meet the objectives 4. Develop a sequence for the tasks 5. Estimate the product development costs
6 Building a Plan Step 1 Identify the tasks As the team understands the problem, the tasks become clearer. Tasks are initially thought of in terms of the activities. The tasks should be made as specific as possible. They should focus on what needs to be achieved rather than the activities. In some industries, the exact tasks to be accomplished are clearly known from the beginning of the project. However, for a totally new product, the tasks may not be so clear.
7 Building a Plan Step 2 State the objective for each task The tasks need to be refined so that the results of the activities are the stated objectives. Each task objective must be Defined as information to be refined or developed and communicated to others (deliverables) Presented in terms of the decisions and the responsible team members Easily understood Specific Feasible
8 Building a Plan Step 3 Estimate resources to meet the objectives For each task, followings should be identified Responsible members Percentage of their time Period Design takes time, often twice as long as the initial estimate Pessimists suggest 1 day 2 weeks
9 Building a Plan Step 3 Estimate resources to meet the objectives Table 5.2, Ullman
10 Building a Plan Step 3 Estimate resources to meet the objectives Time estimation is not easy! It is suggested that it should depend on Optimistic estimate (o) Pessimistic estimate (p) Most-likely estimate (m) Time Estimate
11 Building a Plan Step 3 Estimate resources to meet the objectives Distribution of time across design phases Phase Time Percentages Project planning 3 5 Specification definition Conceptual design Product development Product support 5 10
12 Building a Plan Step 4 Develop a sequence for the tasks Scheduling can be complex The main aim is to have each task done before its results are required. It is important to define the predecessors and successors of each task. Critical Path Method can be used to determine the most efficient sequence of tasks.
13 Gantt Charts Best way to develop a schedule Tasks are plotted against a time scale Personnel requirements are noted Design reviews are shown Task dependencies are important
14 Gantt Chart Software Microsoft Project Microsoft Excel tom splanner teamgantt smartsheet smartdraw
15
16 Building a Plan Step 5 Estimate the product development costs Design costs are about 5% of the manufacturing costs. Salaries constitute most of the project costs. There are extra burdens on companies Cost of buildings Utilities Support personnel General equipment Travel costs
17 Sample plan Developing a Baja car Identify the steps Figure 5.10, Ullman
18 Critical Path Method (CPM) Gantt chart for prototype testing a heat exchanger (Figure 4.14, Dieter)
19 Critical Path Method (CPM) Network logic diagram for heat exchanger prototyping tests (Figure 4.15, Dieter)
20 Critical Path Method (CPM) Definitions and Rules An activity is a time-consuming effort that is required to perform part of a project. An event is the end of one activity and the beginning of another. An event is assumed to consume no time. Every activity in a CPM diagram is separated by two events.
21 Critical Path Method (CPM) Definitions and Rules 1. An activity cannot be started until its tail event is reached. 2. An event cannot be reached until all activities leading to it are complete.
22 Critical Path Method (CPM) Definitions and Rules 3. Sometimes an event is dependent on another event preceding it, even though the two events are not linked together by an activity. A dummy activity (dashed) requires zero time and has zero cost.
23 Critical Path Method (CPM) Definitions and Rules Duration (D): The duration of an activity is the estimated time to complete the activity. Earliest start (ES): The earliest start of an activity is the earliest time when the activity can start. Latest start (LS): The latest time an activity can be initiated without delaying the minimum completion time for the project. Earliest finish time (EF): EF = ES + D Latest finish time (LF): LF = LS + D Total float (TF): The slack between the earliest and latest start times. TF = LS - ES. An activity on the critical path has zero total float.
24 Critical Path Method (CPM) Description of the activities (Table 4.9, Dieter)
25 Critical Path Method (CPM) CPM network for prototype testing of new heat exchanger design (Figure 4.17, Dieter)
26 Critical Path Method (CPM) Calculation of Early Start Times (Table 4.7, Dieter)
27 Critical Path Method (CPM) Calculation of Late Start Times (Table 4.8, Dieter)
28 Critical Path Method (CPM) Critical path: A-D-G-H-J-K Summary of Scheduling Parameters for Prototype Testing Project (Table 4.9, Dieter)
29 In class activity The development of an electronic widget is expected to follow the following steps. Determine the arrow network diagram and determine the critical path by using the CPM technique (Problem 4.11, Dieter)
30 Project Planning and Management Report Template R3 I. Introduction II. Organization of the project A. Explanation of the tasks and their definitions B. Time table (distribution of the workload) C. Timeline (Gantt Chart) III. Summary and Conclusions (risky tasks, backups, tools) Max 6 pages
31 Concluding Remarks Planning is a must. Products developed through 5 phases Discovery Specifications Conceptual design Product development Product support There are 5 planning steps: Identification of the tasks Stating the objectives Estimating resources Developing a sequence Estimating the cost
Project Planning and Scheduling
Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination
Operational Research. Project Menagement Method by CPM/ PERT
Operational Research Project Menagement Method by CPM/ PERT Project definition A project is a series of activities directed to accomplishment of a desired objective. Plan your work first..then work your
Network Calculations
Network Calculations The concepts and graphical techniques described in this week s readings form the basis of the tools widely used today to manage large projects. There is no way of simplifying the tasks
Cambridge International AS and A Level Computer Science
Topic support guide Cambridge International AS and A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Scheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
MECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor (hefny@cs.queensu.ca and surgenor@me.queensu.ca) Winter : Lecture # Project Time Management Homework Discussion Homework
8. Project Time Management
8. Project Time Management Project Time Management closely coordinated Two basic approaches -bottom-up (analytical) -top-down (expert judgement) Processes required to ensure timely completion of the project
MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Schedule Float Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar
Collaborative Scheduling using the CPM Method
MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines
ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS
ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS Chapter 3 of Systems Analysis and Design in a Changing World explains the techniques and steps required to build a project schedule
Chapter 2: Project Time Management
Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
technical tips and tricks
technical tips and tricks Performing critical path analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the
Project Management Glossary
Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project
Project Scheduling & Tracking
Project Scheduling & Tracking Traditional Techniques: Work Breakdown Structure (WBS) Gantt Charts Precedence Diagrams Earned Value Planning It is the mark of an instructed mind to rest satisfied with the
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking
Time Management. Part 5 Schedule Development. Richard Boser
Time Management Part 5 Schedule Development Richard Boser 6.5 Schedule Development Inputs Organizational Process Assets Scope Statement Activity List Activity Attributes Network Diagrams Resource Req ms
B. 2-4-6 D. 3-4-5 E. 3-5-7 F. 5-7-9
Lesson 01 Project Management Solutions #1: The network diagram for a project is shown below, with three time estimates (optimistic, most likely, and pessimistic) for each activity. Activity times are in
MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Schedule Updates Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions
Unit 1: Project Planning and Scheduling
Unit : Project Planning and Scheduling Objective Ð To provide a brief introduction to project planning and scheduling. The critical area where project management meets system development. ackground Most
Use project management tools
Use project management tools Overview Using project management tools play a large role in all phases of a project - in planning, implementation, and evaluation. This resource will give you a basic understanding
CISC 322 Software Architecture. Project Scheduling (PERT/CPM) Ahmed E. Hassan
CISC 322 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan Project A project is a temporary endeavour undertaken to create a "unique" product or service A project is composed of a number
Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration
Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Prof. M. Rammohan Rao Former Dean Professor Emeritus Executive Director, Centre for Analytical
PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM)
PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM) Project Evaluation Review Technique (PERT) and Critical Path Method (CPM) are scheduling techniques used to plan, schedule, budget
Systems Analysis and Design
Systems Analysis and Design Slides adapted from Jeffrey A. Hoffer, University of Dayton Joey F. George, Florida State University Joseph S. Valacich, Washington State University Modern Systems Analysis
SWEN 256 Software Process & Project Management
SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end
Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072
Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define
Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead
Precedence Diagram Method. CSTM 462 Planning & Scheduling
Precedence Diagram Method CSTM 462 Planning & Scheduling Precedence Diagramming Method (PDM) PDM is more flexible than AON or AOA networks because PDM allows the overlapping of concurrent activities.
Chapter-6. Developing a Project Plan
MGMT 4135 Project Management Chapter-6 Where we are now Developing the Project Network Why? Graphical representation of the tasks to be completed Logical sequence of activities Determines dependencies
Module 3: The Project Planning Stage
Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you
Project Management SCM 352. 2011 Pearson Education, Inc. publishing as Prentice Hall
3 Project Management 3 SCM 35 11 Pearson Education, Inc. publishing as Prentice Hall Boeing 787 Dreamliner Delays are a natural part of the airplane supply business. They promise an unreasonable delivery
Notes on the Critical Path Method for project planning and management.
E90 Engineering Design Notes on the Critical Path Method for project planning and management. CPM models any project by a network of blocks or circles called NODES that are connected by lines called ARROWS.
SE351a: Software Project & Process Management
SE351a: Software Project & Process Management W8: Software Project Planning 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa SE351 Roadmap Introduction to Software Project Management Project Management
Appendix A of Project Management. Appendix Table of Contents REFERENCES...761
Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity
CRITICAL PATH METHOD (CEE 320 VDC SEMINAR)
CRITICAL PATH METHOD (CEE 320 VDC SEMINAR) 4 February 2009 Jesse Santiago & Desirae Magallon Overview Background & History CPM Defined The CPM approach Definitions Class Exercise Background & History Developed
CPM-200: Principles of Schedule Management
CPM-: Principles of Schedule Management Lesson B: Critical Path Scheduling Techniques Instructor Jim Wrisley IPM Fall Conference PMI-College of Performance Management Professional Education Program Copyright
Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014
Project Management Six Session Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Mohamed Khalifa, 2014 All Rights 1 7. Scheduling 2 7. Scheduling 7.1 Scheduling techniques 7.3 Critical path method
Dashboards and Reporting for Program Management
MnDOT Project Management Office Presents: Dashboards and Reporting for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will
Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps
Project Planning What are you going to do in the project? Lecture Objectives To discuss the tasks in planning a project To describe the tools that can be used for developing a project plan To illustrate
Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen + Antworten October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 1 All the following Statements about a WBS are true except that it a. Provides a framework for
Project Management Chapter 3
Project Management Chapter 3 How Project Management fits the Operations Management Philosophy Operations As a Competitive Weapon Operations Strategy Project Management Process Strategy Process Analysis
PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT)
PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT) ABSTRACT Category: Planning/ Monitoring - Control KEYWORDS Program (Project) Evaluation and Review Technique (PERT) (G) is a project management tool used
Chapter 4: Project Time Management
Chapter 4: Project Time Management Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management
Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute
The work breakdown structure can be illustrated in a block diagram:
1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as
Should I Resource Load My Schedule?
Should I Resource Load My Schedule? th Annual International Integrated Program Management Conference November -, Copyright All Rights Reserved The Goals Of Project Management: to make the most effective
Network Planning and Analysis
46 Network Planning and Analysis 1. Objective: What can you tell me about the project? When will the project finish? How long will the project take (project total duration)? 2. Why is this topic Important
Project Scheduling. Introduction
Project Scheduling Introduction In chapter, the O and ON networks were presented, also the time and cost of individual activities based were calculated. Yet, however, we do not know how long is the total
PROJECT PROPOSAL: PROJECT BLUE ZUMA
PROJECT PROPOSAL: PROJECT BLUE ZUMA To: From: CC: Dr. Edward J Glantz Alex Bok (ayb5041@psu.edu) Mark Randall Date: February 28 th, 2008 The following documents are detailed reports on our project proposal
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,
Project plan: document used to keep the project under control.
Planning and Scheduling: Basic tools & expectations for the SrD Project [References: The Mechanical Design Process, Ullman, 2003] and Product Design and Development, Ulrich and Eppinger, 2000] Project
Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur
Module 11 Software Project Planning Lesson 29 Staffing Level Estimation and Scheduling Specific Instructional Objectives At the end of this lesson the student would be able to: Identify why careful planning
CRITICAL PATH METHOD (CPM) SCHEDULES
96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without
Chapter 6 (part 1) Project Time Management. (Project Scheduling)
Chapter 6 (part 1) Project Time Management. (Project Scheduling) 1 Objectives Understand the process of project decomposition into activities Understand the level of details required for activities Understand
Lecture 26 CPM / PERT Network Diagram
Lecture 26 CPM / PERT Network Diagram 26.1 Introduction to CPM / PERT Techniques CPM (Critical Path Method) was developed by Walker to solve project scheduling problems. PERT (Project Evaluation and Review
10 Project Management with PERT/CPM
10 Project Management with PERT/CPM 468 One of the most challenging jobs that any manager can take on is the management of a large-scale project that requires coordinating numerous activities throughout
MS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado
CS 587 Software Project Management Instructor: Dr. Atef Bader MS Project Tutorial MS Project in Labs: Available in Siegal Hall Lab in Main Campus Available in Room 210 Rice Campus Prepared by Milton Hurtado
Chapter 6: Project Time Management
CIS 486 Managing Information Systems Projects Fall 2003 (Chapter 6), PhD jwoo5@calstatela.edu California State University, LA Computer and Information System Department Chapter 6: Project Time Management
Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org
Planning and Managing Software Projects 2011-12 Class 9 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides
Basic Concepts. Project Scheduling and Tracking. Why are Projects Late? Relationship between People and Effort
Basic s Project Scheduling and Tracking The process of building a schedule for any case study helps really understand how it s done. The basic idea is to get across to break the software project into well-defined
CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012
King Saud University College of Computer & Information Sciences Department of Computer Science CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 1- Decomposing
Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False
Chapter 1.7 Project Management Part I: Objective type questions and answers 1. Project financing is one of the step of project management- State True or False 2. Proposed new technologies, process modifications,
Basic CPM Calculations
Overview Core Scheduling Papers: #7 Basic CPM Calculations Time Analysis calculations in a Precedence Diagramming Method (PDM) Critical Path Method (CPM) network can be done in a number of different ways.
Chapter 3 Managing the Information Systems (IS) Project
Content Chapter 3 Managing the Information Systems (IS) Project Process of managing IS projects Skills required to be an effective project manager Skills and activities of a project manager during project
Scheduling. Anne Banks Pidduck Adapted from John Musser
Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart
Introduction to Project Management
L E S S O N 1 Introduction to Project Management Suggested lesson time 50-60 minutes Lesson objectives To be able to identify the steps involved in project planning, you will: a b c Plan a project. You
02 Project planning. There are two approaches to identifying the components of a project: productbased and work- or activity-based.
C H A P T E R T W O 02 Project planning LEARNING OUTCOMES When you have completed this chapter you should be able to demonstrate an understanding of the following: project deliverables and intermediate
Programmes. Unit 3: P lanning construction work processes and efficient use of resources in construction and the built environment.
Unit : P lanning construction work processes and efficient use of resources in construction and the. Links This topic links to: HNC in Construction and the Built Environment Unit : LO; HNC Unit 15: LO.
Frequently Asked Questions in Project Management
Frequently Asked Questions in Project Management 1. Question: What is Project Management? Answer: Project Management is the collection and application of skills, knowledge, processes, and activities to
Scheduling Resources and Costs
Student Version CHAPTER EIGHT Scheduling Resources and Costs McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Gannt Chart Developed by Henry Gannt in 1916 is used
Software Project Management. Software Engineering SW Project Management Slide 1
Software Project Management Software Engineering SW Project Management Slide 1 Objectives To introduce software project management and to describe its distinctive characteristics Explain the advantages
Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose
1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing
A. O. Odior Department of Production Engineering University of Benin, Edo State. E-mail: waddnis@yahoo.com
2012 Cenresin Publications www.cenresinpub.org APPLICATION OF PROJECT MANAGEMENT TECHNIQUES IN A CONSTRUCTION FIRM Department of Production Engineering University of Benin, Edo State. E-mail: waddnis@yahoo.com
Project Management DISCUSSION QUESTIONS
3 C H A P T E R Project Management DISCUSSION QUESTIONS. There are many possible answers. Project management is needed in large construction jobs, in implementing new information systems, in new product
Topic: The easiest way to calculate Critical Path, Total Float, Free Float, Early Start, Early Finish, Late Start, and Late Finish.
Hot Topics & hallenges Time Management Topic: The easiest way to calculate ritical Path, Total Float, Free Float, Early, Early, Late, and Late. Presenter: Sohel khter, PMP, N,ISMS PMP and Six Sigma instructor,
CRITICAL-PATH ANALYSIS FOR NETWORK SCHEDULING
CRITICAL-PATH ANALYSIS FOR NTWORK SCHULING From studying this section, you will be able to: - Perform CPM and PM analyses for AOA and AON networks; - Calculate the early / late times that an activity can
The Project Planning Process Group
3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity
Chapter 11 Monte Carlo Simulation
Chapter 11 Monte Carlo Simulation 11.1 Introduction The basic idea of simulation is to build an experimental device, or simulator, that will act like (simulate) the system of interest in certain important
Project Scheduling and Gantt Charts
Project Scheduling and Gantt Charts Siddharth Gangadhar Dr. Prasad Kulkarni Department of Electrical Engineering & Computer Science Lab Presentation siddharth@ku.edu prasadk@ku.edu 4 November 2015 2015
SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards...
SECTION 01311 - CONSTRUCTION SCHEDULE B CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement
HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7?
HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7? This document contains introduction to P2ware Project Manager 7 views (P2ware Project Manager 7 walkthrough) and shows how to create high quality plans
Software Project Management
Software Project Management Project: unique process, consisting of a set of coordinated and controlled activities with start and finish dates, undertaken to achieve an objective conforming to specific
Project Scheduling: PERT/CPM
Project Scheduling: PERT/CPM CHAPTER 8 LEARNING OBJECTIVES After completing this chapter, you should be able to: 1. Describe the role and application of PERT/CPM for project scheduling. 2. Define a project
PROJECT MANAGEMENT Critical Path Method-- Program, Evaluation & Review Technique (CPM/PERT)
PROJECT MANAGEMENT Critical Path Method-- Program, Evaluation & Review Technique (CPM/PERT) 1 Introduction to Project Management Many people and organizations today have a new or renewed interest in project
5. Creating a Gantt Chart
5. Creating a Gantt Chart Whilst the network diagram is a useful way to describe how tasks are linked to each other, the Gantt chart is used to display the schedule of a project. The Gantt chart is the
Leaving Certificate Technology. Project Management. Teacher Notes
Leaving Certificate Technology Project Management Teacher Notes 1 Project Management This is the first of three key topics that form Project and Quality Management in the Technology Syllabus core. These
Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project
EXAM EXEMPLAR QUESTIONS
Level 6 Professional Diploma in Procurement and Supply PD5 - Programme and project management EXAM EXEMPLAR QUESTIONS QUESTIONS AND INDICATIVE ANSWER CONTENT Page 1 of 10 QUALIFICATIONS 2013 QUESTIONS
EdExcel Decision Mathematics 1
EdExcel Decision Mathematics 1 Notes and Examples Critical Path Analysis Section 1: Activity networks These notes contain subsections on Drawing an activity network Using dummy activities Analysing the
Critical Path Analysis
Chapter 13 Critical Path Analysis Basic Concepts Activity An activity is any portion of a project which consumes time or resources and has a definable beginning and ending. For example, laying of pipe
Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule
1 (Image) 2 The process required to manage timely completion of the project. Project time management start with planning by the project management team (not shown as a discrete process). In small project,
Project Time Management
Project Time Management By Augsburg College 1 Learning Objectives Understand the importance of project schedules and good project time management Define activities as the basis for developing project schedules
Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University
Object-Oriented Analysis and Design with the Unified Process John W. Satzinger Southwest Missouri State University Robert B. Jackson Brigham Young University Stephen D. Burd University of New Mexico ALL
CIS Project Management
Topic # 4 CIS Project Management A Correspondence of Positions and Languages/Communications in CIS Analysis, Design, Development and Implementation (Engineering) Industry Correspondence of Positions and
SYSTEMS ANALYSIS AND DESIGN DO NOT COPY
Systems Analysis and Design in a Changing World, Fourth Edition -488-6-5 Copyright 7 Thomson Course Technology. All rights reserved. FOURTH EDITION SYSTEMS ANALYSIS AND DESIGN IN A C HANGING W ORLD John
Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition
Lecture 6: Project Time Management By: Prof. Lili Saghafi Information Technology Project Management, Fifth Edition Learning Objectives 2 Understand the importance of project schedules and good project
7. PROJECT MANAGEMENT
7. PROJECT MANAGEMENT Syllabus Definition and scope of project, Technical design, Financing, Contracting, Implementation and performance monitoring. Implementation plan for top management, Planning Budget,
Basic Project Management & Planning
Basic Project Management & Planning Dr. David K. Potter Director & Don Pether Chair in Engineering and Management em4a03@mcmaster.ca 1 What is Project Management? A set of principles, methods, tools, and