Scheduling Resources and Costs

Size: px
Start display at page:

Download "Scheduling Resources and Costs"

Transcription

1 Student Version CHAPTER EIGHT Scheduling Resources and Costs McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved.

2 Gannt Chart Developed by Henry Gannt in 1916 is used to determine the timing of individual activities in a project, is a graphical representation of the duration of tasks against the progression of time, The purpose is to place tasks and activities (groups of tasks gathered into broad tasks) as horizontal bars against a time line to show start and end dates for the tasks is a type of bar chart that illustrates a project schedule, illustrates the start and finish dates of the terminal elements and summary elements of a project, Terminal elements and summary elements comprise the work breakdown structure of the project. 8 2

3 Gannt Chart Planning and Scheduling Use a Gantt chart to plan how long a project should take. A Gantt chart lays out the order in which the tasks need to be carried out. Early Gantt charts did not show dependencies between tasks but modern Gantt chart software provides this capability. Monitoring a Project A Gantt chart lets you see immediately what should have been achieved at any point in time. A Gantt chart lets you see how remedial action may bring the project back on course. Most Gantt charts include "milestones" which are not part of a traditional Gantt Chart. However, for representing deadlines and other significant events, it is very useful to include this feature on a Gantt chart. 8 3

4 A Gantt Chart is a Matrix The Gantt chart is constructed with a horizontal axis representing the total time span of the project, broken down into increments (days, weeks, or months). A Gantt chart is a horizontal bar chart to graphically portray WBS task duration. The Gantt chart is constructed with a vertical axis representing the tasks that make up the project. The Gantt chart is constructed with a graph area which contains horizontal bars for each task connecting the period start and period ending symbols. 8 4

5 A Gantt Chart has variants Milestones: important checkpoints or interim goals for a project. Resources: for team projects, it often helps to have an additional column containing numbers or initials which identify who on the team is responsible for the task. Status: the projects progress, the chart is updated by filling in the task's bar to a length proportional to the amount of work finished. Dependencies: an essential concept that some activities are dependent on other activities being completed first. 8 5

6 Guidelines 1. What is the total length of the project? Let that time be the length of the time axis (x-axis). 2. How long is the shortest task? Let that time help you set the divisions on the x-axis. (Use your judgment if you have a few tasks much shorter than most. They ll show up as points in time or vertical lines). 3. What are the tasks of the project? List them sequentially along the y-axis (either by short title or identifying number). Also, you can choose to list your tasks sequentially by starting date or by number. 4. Estimate the duration for each task in your task list. When does the task begin? When does the task end? Represent start date and end date by an empty bar horizontal to the x-axis for each task. The time between start date and end date is the duration of the task. 8 6

7 F:\BİM 405 Project MAnagement_Spring 2012\IME614_ek\HAK_PM_book.pdf 8 7

8 Figure 5-23 A Gantt Chart of a Sample Project

9 Figure 5-24 A Gantt Chart of Sample Project Showing Critical Path, Path Connections, Slack, EST, LST, EFT, and LFT

10 Figure 5-25 A Gantt Chart of a Day Care Project Showing Expected Durations, Critical Path, Milestone, and Resource Requirements

11 Figure 5-26 A Progress Report on a Day Care Project Showing Actual Progress Versus Baseline

12 Basic Gantt Chart 8 12

13 Gantt Chart with Dependencies 8 13

14 Using PERT PERT is used when activity times are uncertain. Decision making under risk ( P for probabilistic) Three time estimates are required for each activity. OPTIMISTIC TIME: Best time if everything goes perfectly REALISTIC TIME: Most likely time PESSIMISTIC TIME: A worst-case situation B + 4M + P Expected Time = In this example, the most likely time is given a weight of 4, and the other two times (pessimistic and optimistic) are each given weights of 1. Software allows you to change these as needed, but the denominator must be the total of the weights given.

15 St. Adolf s Hospital Developing the schedule If the activity times are risky, the project team must make three time estimates for each activity and use PERT. Risky activity times enable the use of a probability distribution and risk assessment. For this sample project the times will be certain. (CPM) Activity slack is the maximum length of time that an activity can be delayed without delaying the entire project. (The difference between the earliest time we can start an activity and the latest time we can start it without delaying the project.) For St. Adolf s we can t go beyond 69 weeks since that is the project length.

16 St. Adolf s Hospital Developing the schedule Earliest Start Time (ES) for an activity is the earliest finish time of the immediately preceding activity. Earliest Finish Time (EF) for an activity is its earliest start time plus how long it takes to do it (estimated duration). Latest Start Time (LS) is the latest you can finish the activity minus the activity s estimated duration. Latest Finish Time (LF) is the latest start time of the activity that immediately follows it. (Latest start and finish times for each activity are computed starting at the project s last activity completion time and working forward.) For simplicity, all projects start at time zero.

17 Earliest Start and Earliest Finish Times Earliest start time I Earliest finish time 0 A 12 F K Start C G Finish B D 19 H J Lew Hofmann 9 E 33 24

18 Earliest Start and Earliest Finish Times Path Time (wks) A-I-K 33 A-F-K 28 A-C-G-J-K 67 B-D-H-J-K 69 B-E-J-K 43 A I The Critical Path takes 69 weeks F K Start C G Finish Critical Path B 0 9 D H J E Lew Hofmann

19 Latest Start and Latest Finish Times (Working from the last activity toward the first activity) I A F K Latest start time Latest finish time Start C G Finish B D H J Lew Hofmann 9 E

20 Node Duration ES LS Slack A B C D E F G H I J K Start Slack is the difference between LS and ES or the EF and LF. A I F K C G Finish Activity Slack Analysis B D H J Lew Hofmann 9 E

21 ANALYZING PROBABILITIES What is the probability that our sample project will finish in 69 weeks as scheduled? 100% (Why?) Because we used CPM! (This means we were certain of all of our activity times.) If we weren t certain, we should have used PERT You can t do risk analysis if you use CPM

22 PERT and PROBABILITIES With PERT s three time-estimates, we get a mean (average) time and a variance for each activity and each path. We also get a project mean time and variance. In order to compute probabilities (assuming a normal distribution) we need the activity means and variances. Most computer packages calculate this for you.

23 Probability of Project Completion The probability of a project being completed by a given date is a function of the mean activity times and variances along the critical path(s). The probability of any specific activity being completed by a given date is a function of the mean activity times and variances along the longest path leading up to that activity. If you have more than one critical path, focus on the path with the greatest variance. A near-critical path may also be a problem, depending on the mean and variance of it s activities.

24 Distributions & Probability A Beta distribution is often used for the three estimates of each activity This allows skewed distributions. Optimistic------Most likely Pessimistic ( ) Normal distributions are needed for probabilities. A distribution of activity-means is a normal distribution, even though each activity time may be a beta distribution.

25 Probability Beta Distribution Each activity may have its three time estimates skewed (Beta Distribution), but the path along which this activities lie has a normal distribution and thus a mean and variance. Optimistic a m b Time Mean Pessimistic

26 Figuring Probabilities Assume a PERT project critical path takes 40 days, and that the variance of this path is You wish to know the probability of the project going over 42 days. Compute the standard deviation of the critical path. (Take the square root of the variance of 2.147) Std. Dev. = POM/QM software gives you the variance of the critical path. Compute the Z value: Z = (absolute time difference) / Std. Dev. In this example, Z = (42 days - 40 days) / = Look up the Z value of in a Normal Distribution table to get the probability of the project taking 42 days. Subtract it from 100% to get the probability of going over 42.

27 Look up the Z value (1.365) in the table of normal distribution. (In this case you need to interpolate between the Z values of.9313 and.9147).9139 or 91.39% is the probability of the project taking up to 42 days. Going over 42 days is thus = 8.61%

28 Length of critical path is 40 weeks Probability of meeting the schedule in 42 weeks is 91.39% Normal distribution: Sum of Variances along critical path = Std. Dev. = weeks Probability of exceeding 42 weeks is 8.61% Project duration (weeks)

29 St. Adolf s Hospital A 69-week Project What is the Probability of it taking 72 weeks? Critical Path Variance Critical Path = B - D - H - J K = 69 weeks T = 72 weeks C = 69 weeks T C 2 = (variances of activities along critical path) z = 2 2 = = z = Z = Look up Z value in normal distribution table P z =.8078 or 80.78% (Probability of it taking 72 weeks)

30 Look up the Z value (0.870) in the table of normal distribution or 80.78% is the probability of the project taking up to 72 wks. Going over 72 weeks would be = 19.22%

31 St. Adolf s Hospital Probability of Completing Project On Time Length of critical path is 69 weeks Probability of taking 72 weeks is or 80.78% Normal distribution: Mean = 69 weeks; = 3.45 weeks Probability of exceeding 72 weeks is or 19.22% Project duration (weeks)

32 The Statistical Distribution of all Possible Times for an Activity

33 Activity Expected Time and Variance T E ( a 4m 6 b) ( b 6 a) Var 2 ( b 6 a) 2

34 95 Percent Level Task will be a or lower 5 percent of the time Task will be b or greater 5 percent of the time ( b a) 3.3

35 90 Percent Level Task will be a or lower 10 percent of the time Task will be b or greater 10 percent of the time ( b a) 2.6

36 The Probability of Completing the Project on Time Z ( ) D 2 =NORMDIST(D,,,TRUE)

37 Figure 5-18 The Statistical Distribution of Completion Times of the Path a-b-d-g-h

38 Completion Time Distribution for Tennis Tournament Critical Path Activities D V A 2 4/36 C 3 4/36 E /36 I 3 36/36 J = /36 = 5.2 = 15-38

39 Probability of Overrun What is the probability of an overrun if a 24 day completion time is promised? Z Z Z X Days P (Time > 24) = =.04 or 4% 15-39

40 The Resource Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit assumption is that resources will be available in the required amounts when needed. Adding new projects requires making realistic judgments of resource availability and project durations. Cost estimates are not a budget until they have been time-phased. 8 40

41 The Resource Problem (cont d) Resource Smoothing (or Leveling) Involves attempting to even out varying demands on resources by using slack (delaying noncritical activities) to manage resource utilization when resources are adequate over the life of the project. Resource-Constrained Scheduling The duration of a project may be increased by delaying the late start of some of its activities if resources are not adequate to meet peak demands. 8 41

42 Types of Project Constraints Technical or Logic Constraints Constraints related to the networked sequence in which project activities must occur. Physical Constraints Activities that cannot occur in parallel or are affected by contractual or environmental conditions. Resource Constraints The absence, shortage, or unique interrelationship and interaction characteristics of resources that require a particular sequencing of project activities Kinds of Resource Constraints People, materials, equipment 8 42

43 Classification of A Scheduling Problem Classification of Problem Using a priority matrix will help determine if the project is time or resource constrained. Time-Constrained Project Must be completed by an imposed date. Time is fixed, resources are flexible: additional resources are required to ensure project meets schedule. Resource-Constrained Project Is one in which the level of resources available cannot be exceeded. Resources are fixed, time is flexible: inadequate resources will delay the project. 8 43

44 Resource Allocation Methods Limiting Assumptions Splitting activities is not allowed once an activity is start, it is carried to completion. Level of resources used for an activity cannot be changed. Risk Assumptions Activities with the most slack pose the least risk. Reduction of flexibility does not increase risk. The nature of an activity (easy, complex) doesn t increase risk. 8 44

45 Resource Allocation Methods (cont d) Time-Constrained Projects Must be completed by an imposed date. Require use of leveling techniques that focus on balancing or smoothing resource demands. Use positive slack (delaying noncritical activities) to manage resource utilization over the duration of the project. Peak resource demands are reduced. Resources over the life of the project are reduced. Fluctuation in resource demand is minimized. 8 45

46 Resource Allocation Methods (cont d) Resource Demand Leveling Techniques for Time-Constrained Projects Advantages Peak resource demands are reduced. Resources over the life of the project are reduced. Fluctuation in resource demand is minimized. Disadvantages Loss of flexibility that occurs from reducing slack. Increases in the criticality of all activities. 8 46

47 Resource Allocation Methods (cont d) Resource-Constrained Projects Resources are limited in quantity or availability. Activities are scheduled using heuristics (rules-of-thumb) that focus on: 1. Minimum slack 2. Smallest (least) duration 3. Lowest activity identification number The parallel method is used to apply heuristics An iterative process starting at the first time period of the project and scheduling period-by-period the start of any activities using the three priority rules. 8 47

48 The Impacts of Resource-Constrained Scheduling Reduces delay but reduces flexibility. Increases criticality of events. Increases scheduling complexity. May make the traditional critical path no longer meaningful. Can break sequence of events. May cause parallel activities to become sequential and critical activities with slack to become noncritical. 8 48

49 Splitting Splitting A scheduling technique use to get a better project schedule and/or increase resource utilization. Involves interrupting work on an activity to employ the resource on another activity, then returning the resource to finish the interrupted work. Is feasible when startup and shutdown costs are low. Is considered the major reason why projects fail to meet schedule. 8 49

50 Multiproject Resource Schedules Multiproject Scheduling Problems 1. Overall project slippage Delay on one project create delays for other projects 2. Inefficient resource application The peaks and valleys of resource demands create scheduling problems and delays for projects. 3. Resource bottlenecks Shortages of critical resources required for multiple projects cause delays and schedule extensions. 8 50

51 Multiproject Resource Schedules (cont d) Managing Multiproject Scheduling: Create project offices or departments to oversee the scheduling of resources across projects. Use a project priority queuing system: first come, first served for resources. Centralize project management: treat all projects as a part of a megaproject. Outsource projects to reduce the number of projects handled internally. 8 51

52 Key Terms Heuristic Planned value (PV) Resource-constrained projects Smoothing Splitting Time-constrained projects Time-phased budget baseline 8 52

Project Management Chapter 3

Project Management Chapter 3 Project Management Chapter 3 How Project Management fits the Operations Management Philosophy Operations As a Competitive Weapon Operations Strategy Project Management Process Strategy Process Analysis

More information

Operational Research. Project Menagement Method by CPM/ PERT

Operational Research. Project Menagement Method by CPM/ PERT Operational Research Project Menagement Method by CPM/ PERT Project definition A project is a series of activities directed to accomplishment of a desired objective. Plan your work first..then work your

More information

Project Planning and Scheduling

Project Planning and Scheduling Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination

More information

The work breakdown structure can be illustrated in a block diagram:

The work breakdown structure can be illustrated in a block diagram: 1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as

More information

Project Time Management

Project Time Management Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

More information

Cambridge International AS and A Level Computer Science

Cambridge International AS and A Level Computer Science Topic support guide Cambridge International AS and A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains

More information

Scheduling Glossary Activity. A component of work performed during the course of a project.

Scheduling Glossary Activity. A component of work performed during the course of a project. Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the

More information

Systems Analysis and Design

Systems Analysis and Design Systems Analysis and Design Slides adapted from Jeffrey A. Hoffer, University of Dayton Joey F. George, Florida State University Joseph S. Valacich, Washington State University Modern Systems Analysis

More information

Chapter 2: Project Time Management

Chapter 2: Project Time Management Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.

More information

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

Resource Allocation and Scheduling

Resource Allocation and Scheduling 90 This section is about the general overview of scheduling and allocating resources. Assigning people and machines to accomplish work (work on tasks). Resource Allocation: Time-Constrained. Assigning

More information

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False Chapter 1.7 Project Management Part I: Objective type questions and answers 1. Project financing is one of the step of project management- State True or False 2. Proposed new technologies, process modifications,

More information

Network Calculations

Network Calculations Network Calculations The concepts and graphical techniques described in this week s readings form the basis of the tools widely used today to manage large projects. There is no way of simplifying the tasks

More information

Collaborative Scheduling using the CPM Method

Collaborative Scheduling using the CPM Method MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines

More information

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Prof. M. Rammohan Rao Former Dean Professor Emeritus Executive Director, Centre for Analytical

More information

CISC 322 Software Architecture. Project Scheduling (PERT/CPM) Ahmed E. Hassan

CISC 322 Software Architecture. Project Scheduling (PERT/CPM) Ahmed E. Hassan CISC 322 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan Project A project is a temporary endeavour undertaken to create a "unique" product or service A project is composed of a number

More information

Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur

Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur Module 11 Software Project Planning Lesson 29 Staffing Level Estimation and Scheduling Specific Instructional Objectives At the end of this lesson the student would be able to: Identify why careful planning

More information

8. Project Time Management

8. Project Time Management 8. Project Time Management Project Time Management closely coordinated Two basic approaches -bottom-up (analytical) -top-down (expert judgement) Processes required to ensure timely completion of the project

More information

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Planning and Managing Software Projects 2011-12 Class 9 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides

More information

Basic Concepts. Project Scheduling and Tracking. Why are Projects Late? Relationship between People and Effort

Basic Concepts. Project Scheduling and Tracking. Why are Projects Late? Relationship between People and Effort Basic s Project Scheduling and Tracking The process of building a schedule for any case study helps really understand how it s done. The basic idea is to get across to break the software project into well-defined

More information

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes

More information

Time Management. Part 5 Schedule Development. Richard Boser

Time Management. Part 5 Schedule Development. Richard Boser Time Management Part 5 Schedule Development Richard Boser 6.5 Schedule Development Inputs Organizational Process Assets Scope Statement Activity List Activity Attributes Network Diagrams Resource Req ms

More information

Scheduling. Anne Banks Pidduck Adapted from John Musser

Scheduling. Anne Banks Pidduck Adapted from John Musser Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart

More information

Chapter 3 Managing the Information Systems (IS) Project

Chapter 3 Managing the Information Systems (IS) Project Content Chapter 3 Managing the Information Systems (IS) Project Process of managing IS projects Skills required to be an effective project manager Skills and activities of a project manager during project

More information

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Schedule Float Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

SE351a: Software Project & Process Management

SE351a: Software Project & Process Management SE351a: Software Project & Process Management W8: Software Project Planning 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa SE351 Roadmap Introduction to Software Project Management Project Management

More information

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS Chapter 3 of Systems Analysis and Design in a Changing World explains the techniques and steps required to build a project schedule

More information

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define

More information

Chapter 4: Project Time Management

Chapter 4: Project Time Management Chapter 4: Project Time Management Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes

More information

Use project management tools

Use project management tools Use project management tools Overview Using project management tools play a large role in all phases of a project - in planning, implementation, and evaluation. This resource will give you a basic understanding

More information

SWEN 256 Software Process & Project Management

SWEN 256 Software Process & Project Management SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end

More information

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose 1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing

More information

Project Scheduling & Tracking

Project Scheduling & Tracking Project Scheduling & Tracking Traditional Techniques: Work Breakdown Structure (WBS) Gantt Charts Precedence Diagrams Earned Value Planning It is the mark of an instructed mind to rest satisfied with the

More information

CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012

CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 King Saud University College of Computer & Information Sciences Department of Computer Science CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 1- Decomposing

More information

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT 6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity

More information

Project Scheduling: PERT/CPM

Project Scheduling: PERT/CPM Project Scheduling: PERT/CPM CHAPTER 8 LEARNING OBJECTIVES After completing this chapter, you should be able to: 1. Describe the role and application of PERT/CPM for project scheduling. 2. Define a project

More information

10 Project Management with PERT/CPM

10 Project Management with PERT/CPM 10 Project Management with PERT/CPM 468 One of the most challenging jobs that any manager can take on is the management of a large-scale project that requires coordinating numerous activities throughout

More information

Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University

Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University Object-Oriented Analysis and Design with the Unified Process John W. Satzinger Southwest Missouri State University Robert B. Jackson Brigham Young University Stephen D. Burd University of New Mexico ALL

More information

SYSTEMS ANALYSIS AND DESIGN DO NOT COPY

SYSTEMS ANALYSIS AND DESIGN DO NOT COPY Systems Analysis and Design in a Changing World, Fourth Edition -488-6-5 Copyright 7 Thomson Course Technology. All rights reserved. FOURTH EDITION SYSTEMS ANALYSIS AND DESIGN IN A C HANGING W ORLD John

More information

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Schedule Updates Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions

More information

Project Time Management

Project Time Management Project Time Management By Augsburg College 1 Learning Objectives Understand the importance of project schedules and good project time management Define activities as the basis for developing project schedules

More information

Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi

Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking

More information

PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM)

PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM) PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM) Project Evaluation Review Technique (PERT) and Critical Path Method (CPM) are scheduling techniques used to plan, schedule, budget

More information

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761 Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity

More information

Deming s 14 Points for TQM

Deming s 14 Points for TQM 1 Deming s 14 Points for TQM 1. Constancy of purpose Create constancy of purpose for continual improvement of products and service to society, allocating resources to provide for long range needs rather

More information

Chapter 11 Monte Carlo Simulation

Chapter 11 Monte Carlo Simulation Chapter 11 Monte Carlo Simulation 11.1 Introduction The basic idea of simulation is to build an experimental device, or simulator, that will act like (simulate) the system of interest in certain important

More information

CSSE 372 Software Project Management: Software Project Scheduling

CSSE 372 Software Project Management: Software Project Scheduling CSSE 372 Software Project Management: Software Project Scheduling Shawn Bohner Office: Moench Room F212 Phone: (812) 877-8685 Email: bohner@rose-hulman.edu Examination #1 Results Average Score 82.70% Median

More information

Leaving Certificate Technology. Project Management. Student Workbook

Leaving Certificate Technology. Project Management. Student Workbook Leaving Certificate Technology Project Management Student Workbook Project Management Student notes Introduction Project management is the name given to a number of techniques used in industry to manage

More information

Project Management DISCUSSION QUESTIONS

Project Management DISCUSSION QUESTIONS 3 C H A P T E R Project Management DISCUSSION QUESTIONS. There are many possible answers. Project management is needed in large construction jobs, in implementing new information systems, in new product

More information

A. O. Odior Department of Production Engineering University of Benin, Edo State. E-mail: waddnis@yahoo.com

A. O. Odior Department of Production Engineering University of Benin, Edo State. E-mail: waddnis@yahoo.com 2012 Cenresin Publications www.cenresinpub.org APPLICATION OF PROJECT MANAGEMENT TECHNIQUES IN A CONSTRUCTION FIRM Department of Production Engineering University of Benin, Edo State. E-mail: waddnis@yahoo.com

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Chapter-6. Developing a Project Plan

Chapter-6. Developing a Project Plan MGMT 4135 Project Management Chapter-6 Where we are now Developing the Project Network Why? Graphical representation of the tasks to be completed Logical sequence of activities Determines dependencies

More information

Project Management SCM 352. 2011 Pearson Education, Inc. publishing as Prentice Hall

Project Management SCM 352. 2011 Pearson Education, Inc. publishing as Prentice Hall 3 Project Management 3 SCM 35 11 Pearson Education, Inc. publishing as Prentice Hall Boeing 787 Dreamliner Delays are a natural part of the airplane supply business. They promise an unreasonable delivery

More information

Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management

Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute

More information

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Test Fragen + Antworten October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 1 All the following Statements about a WBS are true except that it a. Provides a framework for

More information

12 Network Scheduling Techniques

12 Network Scheduling Techniques Page 671 12 Network Scheduling Techniques 12.0 Introduction Management is continually seeking new and better control techniques to cope with the complexities, masses of data, and tight deadlines that are

More information

The Project Planning Process Group

The Project Planning Process Group 3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity

More information

02 Project planning. There are two approaches to identifying the components of a project: productbased and work- or activity-based.

02 Project planning. There are two approaches to identifying the components of a project: productbased and work- or activity-based. C H A P T E R T W O 02 Project planning LEARNING OUTCOMES When you have completed this chapter you should be able to demonstrate an understanding of the following: project deliverables and intermediate

More information

Chapter 6: Project Time Management

Chapter 6: Project Time Management CIS 486 Managing Information Systems Projects Fall 2003 (Chapter 6), PhD jwoo5@calstatela.edu California State University, LA Computer and Information System Department Chapter 6: Project Time Management

More information

Project Scheduling and Gantt Charts

Project Scheduling and Gantt Charts Project Scheduling and Gantt Charts Siddharth Gangadhar Dr. Prasad Kulkarni Department of Electrical Engineering & Computer Science Lab Presentation siddharth@ku.edu prasadk@ku.edu 4 November 2015 2015

More information

Project Management Glossary

Project Management Glossary Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project

More information

7. PROJECT MANAGEMENT

7. PROJECT MANAGEMENT 7. PROJECT MANAGEMENT Syllabus Definition and scope of project, Technical design, Financing, Contracting, Implementation and performance monitoring. Implementation plan for top management, Planning Budget,

More information

5. Creating a Gantt Chart

5. Creating a Gantt Chart 5. Creating a Gantt Chart Whilst the network diagram is a useful way to describe how tasks are linked to each other, the Gantt chart is used to display the schedule of a project. The Gantt chart is the

More information

CRITICAL PATH METHOD (CPM) SCHEDULES

CRITICAL PATH METHOD (CPM) SCHEDULES 96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without

More information

Project Scheduling: PERT/CPM

Project Scheduling: PERT/CPM Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times (as in exercises 1, 2, 3 and 5 in the handout) and considering Time-Cost Trade-Offs (as in exercises 4 and 6 in the handout). This

More information

Unit 4: Time Management (PMBOK Guide, Chapter 6)

Unit 4: Time Management (PMBOK Guide, Chapter 6) (PMBOK Guide, Chapter 6) The questions on this topic focus heavily on scheduling techniques, network diagrams, Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or may

More information

Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps

Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps Project Planning What are you going to do in the project? Lecture Objectives To discuss the tasks in planning a project To describe the tools that can be used for developing a project plan To illustrate

More information

Project Management (CS 3730) Lecture 4 Name:

Project Management (CS 3730) Lecture 4 Name: Ch. 6: Scheduling Project Work 1. Some people think that project management is nothing but scheduling, but scheduling is just one of the tools used to manage jobs and should not be considered the primary

More information

Resources Management

Resources Management Resources Management. Introduction s we have seen in network scheduling, the basic inputs to criticalpath analysis are the individual project activities, their durations, and their dependency relationships.

More information

March 30, 2007 CHAPTER 4

March 30, 2007 CHAPTER 4 March 30, 07 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE Chapter Outline 4.1 Background What was the cause of the desperation that lead to the development of the Program Evaluation and Review

More information

Leaving Certificate Technology. Project Management. Teacher Notes

Leaving Certificate Technology. Project Management. Teacher Notes Leaving Certificate Technology Project Management Teacher Notes 1 Project Management This is the first of three key topics that form Project and Quality Management in the Technology Syllabus core. These

More information

ME 407 Mechanical Engineering Design Spring 2016

ME 407 Mechanical Engineering Design Spring 2016 ME 407 Mechanical Engineering Design Spring 2016 Project Planning & Management Asst. Prof. Dr. Ulaş Yaman Acknowledgements to Dieter, Engineering Design, 4 th edition Ullman, The Mechanical Design Process,

More information

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of

More information

Dashboards and Reporting for Program Management

Dashboards and Reporting for Program Management MnDOT Project Management Office Presents: Dashboards and Reporting for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will

More information

CRITICAL PATH METHOD (CEE 320 VDC SEMINAR)

CRITICAL PATH METHOD (CEE 320 VDC SEMINAR) CRITICAL PATH METHOD (CEE 320 VDC SEMINAR) 4 February 2009 Jesse Santiago & Desirae Magallon Overview Background & History CPM Defined The CPM approach Definitions Class Exercise Background & History Developed

More information

Pearson Education Limited 2003

Pearson Education Limited 2003 156 Activities Activity 9.1 (PP. 357 358) [Project planning exercise] You are required to construct a project plan for the following information system development project. Your objective is to schedule

More information

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project

More information

Module 3: The Project Planning Stage

Module 3: The Project Planning Stage Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you

More information

Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition:

Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition: Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition: 1. Activity : It is a particular work of a project which consumes some resources (in ) & time. It is shown as & represented

More information

PERT/CPM. Network Representation:

PERT/CPM. Network Representation: - 1 - PERT/CPM PERT Program Evaluation & Review Technique It is generally used for those projects where time required to complete various activities are not known as a priori. It is probabilistic model

More information

Review on Using Packages to Enhance the Teaching of Critical Path Networks

Review on Using Packages to Enhance the Teaching of Critical Path Networks Review on Using Packages to Enhance the Teaching of Critical Path Networks Harry S Ku Abstract The aim of this paper is to review a published paper, Using computer software packages to enhance the teaching

More information

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead

More information

A Computer Application for Scheduling in MS Project

A Computer Application for Scheduling in MS Project Comput. Sci. Appl. Volume 1, Number 5, 2014, pp. 309-318 Received: July 18, 2014; Published: November 25, 2014 Computer Science and Applications www.ethanpublishing.com Anabela Tereso, André Guedes and

More information

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain * TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited

More information

Mastering Microsoft Project 2010

Mastering Microsoft Project 2010 Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project

More information

8. COMPUTER TOOLS FOR PROJECT MANAGEMENT

8. COMPUTER TOOLS FOR PROJECT MANAGEMENT 8. COMPUTER TOOLS FOR PROJECT MANAGEMENT The project management is a complex activity that requires among others: Information intercourse referred to the project, information that is in big amounts more

More information

Time Management II. http://lbgeeks.com/gitc/pmtime.php. June 5, 2008. Copyright 2008, Jason Paul Kazarian. All rights reserved.

Time Management II. http://lbgeeks.com/gitc/pmtime.php. June 5, 2008. Copyright 2008, Jason Paul Kazarian. All rights reserved. Time Management II http://lbgeeks.com/gitc/pmtime.php June 5, 2008 Copyright 2008, Jason Paul Kazarian. All rights reserved. Page 1 Outline Scheduling Methods Finding the Critical Path Scheduling Documentation

More information

PMP : Project Management Professional Study Guide Kim Heldman

PMP : Project Management Professional Study Guide Kim Heldman SYBEX Sample Chapter PMP : Project Management Professional Study Guide Kim Heldman Chapter 7: Creating the Project Plan Copyright 2002 SYBEX Inc., 1151 Marina Village Parkway, Alameda, CA 94501. World

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Looking for schedule variances Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart

More information

Introduction to Project Management. What is the Project Management Life Cycle? Common Life Cycle Characteristics

Introduction to Project Management. What is the Project Management Life Cycle? Common Life Cycle Characteristics Introduction to Project Management Chapter 2 The Project Management Life Cycle Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 2-1 What

More information

22 Project Management with PERT/CPM

22 Project Management with PERT/CPM hil61217_ch22.qxd /29/0 05:58 PM Page 22-1 22 C H A P T E R Project Management with PERT/CPM One of the most challenging jobs that any manager can take on is the management of a large-scale project that

More information

The Plan s Journey From Scope to WBS to Schedule

The Plan s Journey From Scope to WBS to Schedule The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)

More information

College of Engineering and Applied Science University of Wisconsin -- Milwaukee

College of Engineering and Applied Science University of Wisconsin -- Milwaukee Edward A. Beimborn and W. Anthony Garvey College of Engineering and Applied Science University of Wisconsin -- Milwaukee The Blob Chart:: A Simplified Method of Allocating Resources over Time Edward Beimborn

More information

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules Chapter 6: Project Time Management Information Technology Project Management, Fifth Edition Learning Objectives Understand the importance of project schedules and good project time management Define activities

More information

Chapter 11: PERT for Project Planning and Scheduling

Chapter 11: PERT for Project Planning and Scheduling Chapter 11: PERT for Project Planning and Scheduling PERT, the Project Evaluation and Review Technique, is a network-based aid for planning and scheduling the many interrelated tasks in a large and complex

More information

Notes on the Critical Path Method for project planning and management.

Notes on the Critical Path Method for project planning and management. E90 Engineering Design Notes on the Critical Path Method for project planning and management. CPM models any project by a network of blocks or circles called NODES that are connected by lines called ARROWS.

More information

CPM-200: Principles of Schedule Management

CPM-200: Principles of Schedule Management CPM-: Principles of Schedule Management Lesson B: Critical Path Scheduling Techniques Instructor Jim Wrisley IPM Fall Conference PMI-College of Performance Management Professional Education Program Copyright

More information

SCHEDULING AND TIME MANAGEMENT. Project Management and Leadership 2015D, PhD, PMP

SCHEDULING AND TIME MANAGEMENT. Project Management and Leadership 2015D, PhD, PMP SCHEDULING AND TIME MANAGEMENT Project Management and Leadership 2015D, PhD, PMP Our PROGRAMME: 1. INTRODUCTION TO PROJECT MANAGEMENT 2. STARTING A PROJECT 3. WORK MOTIVATION 4. COMMUNICATION 5: TEAMS

More information

A GUIDE TO NETWORK ANALYSIS by MICHAEL C GLEN

A GUIDE TO NETWORK ANALYSIS by MICHAEL C GLEN Introduction A GUIDE TO NETWORK ANALYSIS by MICHAEL C GLEN The core technique available to Project Managers for planning and controlling their projects is Network Analysis. This short guide will provide

More information

CPM -100: Principles of Project Management

CPM -100: Principles of Project Management CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP starshaw@starpower.net Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference

More information