Seismic Certification Requirements For Hospital Facilities

Size: px
Start display at page:

Download "Seismic Certification Requirements For Hospital Facilities"

Transcription

1 New Seismic Compliance Requirements for Hospitals Special Seismic Certification Preapproval Program Rebroadcast of June 17, 2010 Web Seminar

2 Welcome & Program Overview

3 Roger Richter Roger Richter is Senior Vice President for Professional Services, at California Hospital Association where he represents the members interests on energy, facilities, environmental and disaster planning issues for California hospitals and health systems. Mr. Richter serves as a liaison with state regulatory agencies, including the Office of Statewide t Health Planning and Development, Hospital Building Safety Board, California Buildings Standards Commission, State Fire Marshal, Cal/OSHA, Cal EPA, Emergency Medical Services Authority, California Department of Public Health, California Energy Commission and the California Public Utilities Commission. 3

4 Acknowledgments Special thanks to: Office of Statewide Health Planning and Development California Society for Healthcare Engineering American Institute of Architects, American Institute of Architects, California Council

5 Chris Tokas Chris Tokas MS, SE, is a supervising structural engineer for the Office of Statewide Health Planning and Development. Mr. Tokas has 25 years of experience in structural engineering and design, with special emphasis in the areas of seismic evaluation, analysis, and retrofit. He has designed and managed seismic upgrade projects for a wide variety of public, private and institutional clients and on a wide variety of structures. Mr. Tokas has been involved in all phases of seismic risk reduction programs, including development of criteria, evaluation of existing structural capacity, schematic design, and preparation p of construction documents. 5

6 Office of Statewide t Health Planning & Development Facilities Development Division The Building Department for California s Hospitals Update on the CBC 2010 Requirements Presented by Chris Tokas, MS, SE 6

7 Drivers of Change Earthquake Lessons Learned 7

8 Special Seismic Certification is Also Known As (AKA) Seismic Certification of Nonstructural Components (IBC 2009 Section and the CBC 2010 Section 1708A.4) Special Certification for Designated Seismic System (ASCE 7-05 Section ) 8

9 Codes and Standards Relationship 9

10 What is Designated Seismic System? Any Component or System with Importance Factor (I p )i is Greater than 1.0 is called Designated Seismic System (CBC 2010 Section 1702A) 10

11 Nonstructural Component Importance Factor Component Importance (I p ) is either 1.0 or 1.5 (ASCE 7-05 Section ) Component Importance (I p ) is 1.5 if: Component is required to function for life-safety Component contain hazardous materials Components is in essential facilities and its failure could impair the continued operation of the facility 11

12 Intent of Building Code Provide reasonable assurance of seismic performance that will: 1. Avoid serious injury and life loss, 2. Avoid loss of function in critical facilities, 3. Minimize structural and nonstructural repair costs where practical to do so. 12

13 Statutory Mandate for OSHPD HOSPITAL FACILITIES SEISMIC SAFETY ACT 1983 (HSSA 83) Hospital buildings that house patients who have less than the capacity of normally healthy persons to protect themselves must be reasonably capable of providing services to the public after a disaster 13

14 Seismic Performance of Nonstructural Components Damage to nonstructural components can result in: Significant economic losses Cost of building contents exceeds building cost Temporary partial/total loss of operation/functionality Injuries and Loss of Life Past Emphasis: Life Safety and Position Retention only Present Focus: Maintaining Functionality 14

15 Special Certification for Designated Seismic Systems Section of ASCE 7-05 Special Certification is required for Designated Seismic Systems assigned to Seismic i Design Categories C through F as follows: Active mechanical and electrical equipment that are required to function following the Design Earthquake Components containing hazardous contents 15

16 Seismic Certification of Nonstructural Components CBC 2010 Section 1708A.4: The registered design professional shall state the applicable seismic certification requirements for nonstructural components and designated seismic systems on the construction documents. CONT D 16

17 CBC 2010 Section 1708A.4 Seismic Certification of Nonstructural t Components The manufacturer of each designated seismic system components subject to the provisions of ASCE 7 Section shall test or analyze the component and its mounting system or anchorage and submit a certificate of compliance for review and acceptance by the registered design professional responsible for the design of the designated seismic system and for approval by the building official. CONT D 17

18 CBC 2010 Section 1708A.4 Certification shall be based on: An actual test on a shake table, Seismic Certification of Nonstructural Components By three-dimensional shock tests, By an analytical method using dynamic characteristics and forces, By the use of experience data (i.e., historical data demonstrating acceptable seismic performance), or By more rigorous analysis providing for equivalent safety. 18

19 Seismic Certification by Analysis 19

20 Seismic Certification by Analysis Seismic Certification of Tanks by Analysis Using ASME BPVC Tanks (without vibration isolators) designed by: 1. A registered design professional in accordance with ASME Boiler and Pressure Vessel Code, 2007 (BPVC 2007); and, 2. Satisfying the force and displacement requirements of Sections and of ASCE 7-05 having an importance factor, I = 1.5; and, 3. Reviewed and approved by OSHPD Shall be considered to satisfy the Special Seismic Certification requirements on the basis of ASCE 7-05 Section

21 Seismic Certification by Analysis Seismic Certification of Tanks by Analysis Using ASCE 7-05 Chapter 15 Tanks Classified as Nonbuilding Structures in ASCE 7-05 shall be considered to satisfy Special Seismic Certification requirements if all of the following conditions are satisfied: 1. Tank design is in accordance ASCE 7-05 Chapter 15 with R = 0 = C d = 1, and 2. Attachments and Supports are designed in accordance with ASCE 7-05 Chapter 15 with R, 0, and C d values provided therein, and 3. Tank design is reviewed and approved by OSHPD. 21

22 Seismic Certification by Analysis For a product line with multiple products analysis is too time consuming. Active and Energized components must be qualified by test or experience data. Analyzing a custom 40-units HVAC product line will be similar to designing 40-hospital buildings. Same HVAC product line can be qualified by just two shake table test. Shake Table test is not a destructive test, hence tested unit may be installed and used 22

23 ASCE/SEI 7-05 Referenced Seismic Qualification Testing Protocol 23

24 AC-156 Seismic Qualification by Shake Table Testing of Nonstructural Components Companion Document to 2009 IBC/ASCE 7-05 Acceptance Criteria published by ICC Evaluation Services First published in 2000, latest version 2007 Provides testing protocol and test spectra definition iti Test Spectra is tied directly to F p force equation Acceptance Criteria tied to I p factor. For I p = 1.5, Equipment to remain functional following the test 24

25 Translating Building Code Requirement to Test Protocol 25

26 Seismic Simulation Test Results and Acceptance Criteria Example 26

27 Seismic Simulation Test Results and Acceptance Criteria Acceptance Criteria Account for post event pass/fail criteria Post event functionality for critical facilities Photo by: Philip Caldwell 27

28 Seismic Simulation Test Results and Acceptance Criteria Account for post event pass/fail criteria Ip= 1.5 Post test functionality verified Photo by: Philip Caldwell 28

29 Seismic Certification by Experience Requirements for Qualification by Experience Data (for OSHPD) Characterization of experience motions as measured by instruments t Verification of post-earthquake Functionality and Structural Integrity Equipment must be of equal or better construction Project seismic demand must be less than Certification basis Requires maintenance of data base for continuous evaluation of the performance of installed equipment experiencing new earthquake 29

30 HOSPITAL FACILITIES SEISMIC SAFETY ACT 1983 (HSSA 83) Hospitals housing patients less able to protect themselves; Legislative intent It is the intent of the Legislature that hospital buildings that house patients who have less than the capacity of normally healthy persons to protect themselves, and that must be reasonably capable of providing services to the public after a disaster. In order to accomplish this purpose, the office shall propose proper building standards for earthquake resistance based upon current knowledge 30

31 CBC 2010, Section 1708A.4 List of Systems Requiring Special Seismic Certification: 1. Emergency and standby power systems including generators, turbines, fuel tanks, and automatic transfer switches. 2. Elevator equipment (excluding elevator cabs). 31

32 CBC 2010, Section 1708A.4 List of Equipment and Components Requiring Special Seismic Certification: 3. Components with hazardous contents (excluding pipes, ducts, and underground tanks). 4. Smoke control fans. 5. Exhaust fans New addition in the CBC 2010 to Ensure That Pressurization in Building will not Interfere with Opening or Closing of Exit Doors. 6. Switchgear. 7. Motor control centers. 8. X-Ray machines in fluoroscopy rooms. 9. CT (Computerized Tomography) Scanners New addition in the CBC 2010 to Ensure that Stroke/Head Injury Patients and Trauma Center/Emergency Rooms will have Adequate Access to Imaging (Virtually all Manufacturer s of CT scanners will have scanners with special seismic certification by July, 2010) 32

33 CBC 2010, Section 1708A.4 List of Equipment and Components Requiring Special Seismic Certification: 10.Air conditioning units. 11. Air handling units. 12.Chillers. 13.Cooling Towers (excluding Cooling Towers designed as nonbuilding structures). 14. Transformers. 15.Electrical substations. 16.UPS (Inverters) and associated batteries. 17.Distribution panels including electrical panelboards, 18.Control panels including fire alarm, fire suppression, preaction, and auxiliary or remote power supplies. 33

34 CBC 2010, Section 1708A.4 Components Exempt from Special Seismic Certification: 1. Equipment and components installed in nonconforming buildings unless the equipment or component provides a service/system or utility to conforming buildings, or building is designated as SPC 3 or higher. 1. Equipment and components weighing not more than 20lbs. supported directly on structures (and not mounted on other equipment or components) with supports and attachments in accordance with a SCE 7 Chapter 13 as modified by Section 1615A. 34

35 CBC 2010, Section 1708A.4 Special Seismic Certification for OSHPD 2 and 3 Buildings: Special Seismic Certification is required for Designated Seismic System (components with importance factor equal to 1.5). Typical components that require special seismic certification in OSHPD 2 & 3 buildings include: Emergency generators Automatic transfer switches Smoke control fans Medical gas systems Fire alarm panels 35

36 CBC 2010 Section 1708A.4/ASCE 7-05 Section : 2 Special Seismic i Certification Special Seismic Certification for Designated Seismic System, ASCE/SEI 7-05 Section and CBC 2010 Section 1708A.4 Analysis Testing Experience Data ASCE/SEI7-05 Sections 13.3, 13.4, 13.5, & 13.6 ASCE/SEI 7-05 Section ASCE/SEI 7-05 Section Project Specific Submittal to OSHPD OSHPD Special Seismic Certification Preapproval (OSP) 36

37 OSHPD Special Seismic Certification Preapproval (OSP) OSP requirements of a product line with similar structural configuration: Testing of at least two units (typically the smallest & largest units), and Verification of similarities il iti for interpolated t units (CBC 2010 Section 1708A.4). 37

38 Special Seismic Certification By a Single Test One dynamic test is Acceptable when: A single product is certified NOT a product line with more than one product with variations; and, Manufacturing process is ISO 9001 certified 38

39 OSP Requirements (Continued) OSHPD strongly recommends: The Owner and his California licensed structural engineer meet and review the proposed test plan with OSHPD prior to any testing to ensure that there will be no issues with the OSP approval when submitted. 39

40 Statutory OSHPD Review Requirements Hospitals housing patients less able to protect themselves; Legislative Intent (a) It is the intent of the Legislature that hospital buildings that house patients who have less than the capacity of normally healthy persons to protect themselves, and that must be reasonably capable of providing services to the public after a disaster, shall be designed and constructed t to resist, insofar as practical, the forces generated by earthquakes, gravity, and winds. In order to accomplish this purpose, the office shall propose proper building standards for earthquake resistance based upon current knowledge, and provide an independent d review of the design and construction of hospital buildings. 40

41 Regulatory OSHPD Approval Requirements CBC A.3 Enforcement Agency Approval. In addition to requirements of California Code of Regulations (C.C.R.) Title 24, Parts 1 & 2, any aspect of project design, construction, quality assurance, or quality control programs for which this code requires approval by the design professional, are also subject to approval by the enforcement agency. 41

42 Is Third Party Review Subject to OSHPD Review and Approval? Yes Required by Statutet t Required by the CBC 2010 Section 1601A.3 42

43 No Can the Analysis be Bookended Similar to Testing? Analysis is only good for the unit analyzed limited variations and/or grouping may be acceptable i.e. analysis of the smallest and largest buildings (under OSHPD jurisdiction) can t be used for permitting all OSHPD buildings (of a given structural t configuration). However, testing of a few connections to verify an analysis methodology can justify all connections of similar configurations 43

44 What R p Can be Used for Special Seismic Certification? R p = 1.0 & I p = 1.5 for Special Seismic Certification by Analysis (Attachments design can use R p in ASCE 7), Since Functionality can t be Verified by Analysis R p/i p = 1.0 for Special Seismic Certification by Shake Table Test. Both Structural Integrity and Functionality shall be maintained after shake table test. 44

45 Why is R p based on the AC-156 Requirements? ASCE 7-05 does not provide R p values for special seismic certification of active electrical and mechanical equipment, since it does not provide analysis as an option for special certification of active mechanical and electrical equipment. ICC-ES AC 156 requires R p/i p = 1 for Shake Table Test. Require Post-Test Structural Integrity for Ip = 1 Require Post-Test Structural Integrity and Functionality for Ip = 1.5 Critical equipment and components should remain essentially elastic for post-earthquake functionality 45

46 Can the Active Mechanical & Electrical Equipment get an OSP by analysis alone? No Active and energized components must be certified by shake table testing or experience data. ONLY connecting elements, attachments, and supports can be justified by supporting analysis for active and energized components 46

47 Does the Design need to comply with the CBC 2010 for OSP? Yes All components shall be designed in accordance with the CBC requirements Both demand and capacity shall be based on the CBC and referenced material standards. Stability and local affects shall be part of the design as required by the code. The CBC does not permit 1/3 rd allowable stress increase for most materials, including steel and concrete. 47

48 OSHPD Special Seismic Certification Preapproval (OSP) at OSHPD Website OSHPD Special Seismic Certification Preapproval (OSP) Requirements and Application form is available at: List of Equipment and Components with OSHPD Special Seismic Certification Preapproval (OSP) is available at: Approval/special_seismic_cert_pre-approval.html 48

49 Progress in OSHPD Special Seismic Certification Preapproval (OSP) More than seventy Special Seismic Certification Pre-Approvals to date (OSP Program started in July, 09). 10,000 Equipment Currently processing on average more than three (3) new OSP s per week Most Categories have Multiple Pre-approvals 49

50 Options When No Equipment with Special Seismic Certification is Available Differ the Special Seismic Certification and Require the Manufacturer to Provide the Certification Certification must be complete prior to installation. Emergency Waiver OSHPD may waive the requirements for emergency replacements 50

51 Yes Does HVAC Unit for CT Scanner Room Require Special Seismic Certification for the CBC 2007? The CBC 2007 Section 1708A.5 require special seismic certification of all equipment with importance factor (I p ) of 1.5. The CBC 2010 will require CT Scanners to have special seismic certification (Every Manufacturer of CT scanners are expected to have qualified scanners by July, 2010) If CT Scanners are out of service, that room can be converted to another service following earthquake provided all support equipment are functional. All rooms may become essential after an earthquake. Loss of equipment such as acid filled UPS batteries may create a hazardous materials situation, which may affect other functions in the hospital. 51

52 Closing Comments Thank you for viewing the web seminar. For questions regarding seismic issues, contact Roger Richter at (916) or Other questions, please contact Liz Mekjavich at (916) or

Facilities Development Division. The Building Department for California s Hospitals

Facilities Development Division. The Building Department for California s Hospitals OSHPD Special Seismic Certification Preapproval (OSP) Preapproval of Special Seismic Certification by OSHPD is a voluntary program for Equipment Manufacturers! Facilities Development Division The Building

More information

AT&T Internet Data Center Site Specification Chicago Area (Lisle, IL)

AT&T Internet Data Center Site Specification Chicago Area (Lisle, IL) AT&T Internet Data Center Site Specification Chicago Area (Lisle, IL) Site Biography Market Area: Chicago, IL Location: Lisle, IL 60532 Address: 4513 Western Avenue CLLI,POP, NPA/NXX Code: LSLEILAA, EQLAILAA

More information

Key Considerations for Selecting Server Cabinets for Seismic Areas

Key Considerations for Selecting Server Cabinets for Seismic Areas Key Considerations for Selecting Server Cabinets for Seismic Areas Protect Up to 1500 of Critical Network Equipment without Sacrificing Flexibility Planning a data center in a seismically active area requires

More information

The Fundamentals of Seismic Compliance and Heating, Ventilation and Air-Conditioning Systems (HVAC)

The Fundamentals of Seismic Compliance and Heating, Ventilation and Air-Conditioning Systems (HVAC) Carrier Engineering Newsletter Volume 1, Issue 2 The Fundamentals of Seismic Compliance and Heating, Ventilation and Air-Conditioning Systems (HVAC) Earthquakes are a real problem and not just in California

More information

SUBJECT CAN: 2-108. Temporary Systems, Utilities and Equipment. Effective: 4/09/2013. CODE SECTION 2010 California Building Code (CBC)

SUBJECT CAN: 2-108. Temporary Systems, Utilities and Equipment. Effective: 4/09/2013. CODE SECTION 2010 California Building Code (CBC) Facilities Development Division Office of Statewide Health Planning and Development 400 R Street, Suite 200 Sacramento, CA 95811 (916) 440-8300 700 N. Alameda Street, Suite 2-500 Los Angeles, CA 90012

More information

AT&T Internet Data Center Site Specification Washington-DC Area (Ashburn, VA)

AT&T Internet Data Center Site Specification Washington-DC Area (Ashburn, VA) AT&T Internet Data Center Site Specification Washington-DC Area (Ashburn, VA) Site Biography Market Area: Washington, DC Area Location: Ashburn, VA 20147-6011 Address: All deliveries should be sent to

More information

How To Visit An Internet Data Center

How To Visit An Internet Data Center AT&T Internet Data Center Site Specification Atlanta Area (Lithia Springs, GA) Site Biography Market Area: Atlanta and surrounding areas (Georgia, Alabama, Tennessee, Florida, North and South Carolina

More information

AT&T Internet Data Center Site Specification - Phoenix Area (Mesa, AZ)

AT&T Internet Data Center Site Specification - Phoenix Area (Mesa, AZ) AT&T Internet Data Center Site Specification - Phoenix Area (Mesa, AZ) Site Biography Market Area: Phoenix, Mesa, Tempe, Chandler, Scottsdale, AZ Location: Mesa, AZ 85201 Address: 1301 University Blvd.

More information

Earthquakes and Data Centers

Earthquakes and Data Centers 7x24 Exchange Fall Symposium September 11, 2013 Hilton Bellevue Andrew W. Taylor, Ph.D., S.E., FACI Earthquake Hazards 2 September 11, 2013 1 Cascadia Earthquake Sources Figure Credit: Craig Weaver, Pacific

More information

AT&T Internet Data Center Site Specification San Diego Koll (San Diego, CA)

AT&T Internet Data Center Site Specification San Diego Koll (San Diego, CA) AT&T Internet Data Center Site Specification San Diego Koll (San Diego, CA) Site Biography Market Area: San Diego, CA Location: San Diego, CA 92121 Address: 5732 Pacific Center Blvd CLLI,POP, NPA/NXX Code:

More information

ELECTRICAL EMERGENCY SYSTEM PLAN REVIEW OVERVIEW OF CODE REQUIREMENTS

ELECTRICAL EMERGENCY SYSTEM PLAN REVIEW OVERVIEW OF CODE REQUIREMENTS ELECTRICAL EMERGENCY SYSTEM PLAN REVIEW What to Look for during Plan Review OVERVIEW OF CODE REQUIREMENTS First determine the type of emergency power system; is the system designed for Emergency or Legally

More information

AT&T Internet Data Center Site Specification Dallas Area (Allen, Tx)

AT&T Internet Data Center Site Specification Dallas Area (Allen, Tx) AT&T Internet Data Center Site Specification Dallas Area (Allen, Tx) Site Biography Market Area: Dallas and Fort Worth Areas of Texas Location: Allen, Tx 75013 Address: 900 Ventura Drive CLLI, POP, NPA/NXX

More information

The State Fire Marshal's Office and the VDH/Office of Licensure and Certification. Generator Testing in Nursing Facilities

The State Fire Marshal's Office and the VDH/Office of Licensure and Certification. Generator Testing in Nursing Facilities Generator Testing in Nursing Facilities Introduction Recent emergencies and natural disasters have emphasized the need to ensure that nursing facilities have an adequate EPSS in place should the loss of

More information

Seismic Assessment of Engineering Systems in Hospitals A Challenge for Operational Continuity

Seismic Assessment of Engineering Systems in Hospitals A Challenge for Operational Continuity Seismic Assessment of Engineering Systems in Hospitals A Challenge for Operational Continuity S.R. Uma GNS Science, Lower Hutt. G.J. Beattie Building Research Association of New Zealand, Porirua. 2010

More information

RESIDENTIAL PHOTOVOLTAIC SUBMITTAL REQUIREMENTS

RESIDENTIAL PHOTOVOLTAIC SUBMITTAL REQUIREMENTS DEVELOPMENT AND RESOURCE MANAGEMENT DEPARTMENT BUILDING AND SAFETY SERVICES 2600 Fresno Street, Third Floor Fresno, California 93721-3604 (559) 621-8082 FAX (559) 498-4357 RESIDENTIAL PHOTOVOLTAIC SUBMITTAL

More information

Prepared For San Francisco Community College District 33 Gough Street San Francisco, California 94103. Prepared By

Prepared For San Francisco Community College District 33 Gough Street San Francisco, California 94103. Prepared By Project Structural Conditions Survey and Seismic Vulnerability Assessment For SFCC Civic Center Campus 750 Eddy Street San Francisco, California 94109 Prepared For San Francisco Community College District

More information

Facilities Maintenance Standards rev 9-1-2015

Facilities Maintenance Standards rev 9-1-2015 Facilities Maintenance Standards rev 9-1-2015 Purpose The purpose of these standards is to outline the minimum requirements for maintaining state owned facilities and infrastructures in a manner that will

More information

Guidelines for doing Mechanical & Electrical work At the University of New Mexico

Guidelines for doing Mechanical & Electrical work At the University of New Mexico Guidelines for doing Mechanical & Electrical work At the University of New Mexico {Revised on 04/14/2015 @ LHC} Table of Contents Cover letter...2 Contractor Information: Performing Work at the University

More information

INSPECTION AND TESTING OF EMERGENCY GENERATORS

INSPECTION AND TESTING OF EMERGENCY GENERATORS INSPECTION AND TESTING OF EMERGENCY GENERATORS Certification requirements NFPA 101(00), Sec. 7.9.2.3 requires that emergency generators be installed, tested and maintained in accordance with NFPA 110,

More information

Fire Alarm System Plans Submittal Guidelines For New and Existing Systems

Fire Alarm System Plans Submittal Guidelines For New and Existing Systems Fire Alarm System Plans Submittal Guidelines For New and Existing Systems SCOPE The Temecula Fire Prevention Bureau (TFPB) has established the following requirements for the submittal of all fire alarms,

More information

National Archives and Records Administration (NARA) Facility Standards for Federal Records Storage Facilities

National Archives and Records Administration (NARA) Facility Standards for Federal Records Storage Facilities National Archives and Records Administration (NARA) Facility Standards for Federal Records Storage Facilities A quick overview of what Federal Records Officers need to know about: What the Records Storage

More information

Rhode Island State Fire Marshal Fire Protection Systems Narrative Reports. What is a Narrative Report?

Rhode Island State Fire Marshal Fire Protection Systems Narrative Reports. What is a Narrative Report? RHODE ISLAND DIVISION OF STATE FIRE MARSHAL 1951 Smith Street, North Providence, RI 02911 Telephone: (401) 383-7717 Fax: (401) 383-8879 John E. Chartier, EFO, CFI State Fire Marshal Rhode Island State

More information

Recommended Product Specifications Fuel Day Tank System Tramont UTRS Fuel Day Tank

Recommended Product Specifications Fuel Day Tank System Tramont UTRS Fuel Day Tank Recommended Product Specifications Fuel Day Tank System Tramont UTRS Fuel Day Tank This specification describes requirements for a Diesel Fuel Day Tank System consisting of one or more fuel tanks, an Electronic

More information

NeuStar Ultra Services Physical Security Overview

NeuStar Ultra Services Physical Security Overview NeuStar Ultra Services Physical Security Overview Mission-critical network operations must have the highest standards of quality, security and reliability. NeuStar Ultra Services currently locates its

More information

AT&T Internet Data Center Site Specification New York III (Secaucus, NJ)

AT&T Internet Data Center Site Specification New York III (Secaucus, NJ) AT&T Internet Data Center Site Specification New York III (Secaucus, NJ) Site Biography Market Area: New York City, New Jersey, Upstate NY and Lower Connecticut Location: Secaucus, NJ 07094 Address: 15

More information

The ACI 562 Repair Code

The ACI 562 Repair Code The ACI 562 Repair Code Code Requirements for Evaluation, Repair and Rehabilitation of Concrete Buildings by Keith Kesner 1 Chair ACI 562 Lawrence Kahn 2 Former Chair ACI 562 1. Associate WDP & Associates,

More information

ASME QRO Certification Program

ASME QRO Certification Program ASME QRO Certification Program ASME QRO Certification For Operators of Resource Recovery Facilities Applicant Information Table of Contents Table of Contents Page QRO Certification Overview...1 Types of

More information

SEISMIC EVALUATION OF HOSPITAL PIPING SYSTEMS

SEISMIC EVALUATION OF HOSPITAL PIPING SYSTEMS 13 th World Conference on Earthquake Engineering Vancouver, B.C., Canada August 1-6, 2004 Paper No. 1081 SEISMIC EVALUATION OF HOSPITAL PIPING SYSTEMS Elliott GOODWIN 1, Emmanuel MARAGAKIS 2, Ahmad ITANI

More information

Winnipeg Fire Department Fire Prevention Branch

Winnipeg Fire Department Fire Prevention Branch Winnipeg Fire Department Fire Prevention Branch Manitoba Fire Code Life-Safety Equipment Maintenance Requirements The Fire Prevention Branch of the Winnipeg Fire Department has prepared this document of

More information

General Fire Code Requirements Within Commercial Tenant Spaces

General Fire Code Requirements Within Commercial Tenant Spaces FIRE DEPARTMENT in cooperation with Scope: General Fire Code Requirements Within Commercial Tenant Spaces This handout is designed to assist owners, architects, contractors and others in understanding

More information

FLORIDA ATLANTIC UNIVERSITY FIRE ALARM SYSTEM INSTALLATION MANUAL

FLORIDA ATLANTIC UNIVERSITY FIRE ALARM SYSTEM INSTALLATION MANUAL FLORIDA ATLANTIC UNIVERSITY FIRE ALARM SYSTEM INSTALLATION MANUAL January, 2003 Environmental Health and Safety Florida Atlantic University 777 Glades Rd. Boca Raton, FL 33431 Phone: 561-297-3129 Fax:

More information

SECTION 8 Industrial Facilities Field Investigation

SECTION 8 Industrial Facilities Field Investigation SECTION 8 Industrial Facilities Field Investigation Types of Data to Be Collected and Recorded Warehouses, manufacturing facilities, energy-producing facilities, and factories should be inspected for performance

More information

Appendix B. 2010 Florida Building Code Building Section 423.25 Public Shelter Design Criteria

Appendix B. 2010 Florida Building Code Building Section 423.25 Public Shelter Design Criteria Appendix B 2010 Florida Building Code Building Section 423.25 Public Shelter Design Criteria 423.25 Public shelter design criteria. 423.25.1 New facilities. New educational facilities for school boards

More information

ABSTRACT DCMCCT PROJECT OVERVIEW

ABSTRACT DCMCCT PROJECT OVERVIEW Title: Case Study of the Austin Energy Dell Regional Children s Medical Center of Central Texas Packaged Hybrid CHP Energy Plant in Austin, Texas Authors: Mr. Ed Mardiat, Burns & McDonnell Mr. Jim Teigen,

More information

26 3213.13 Diesel Engine Driven Generators Page 1 of 6

26 3213.13 Diesel Engine Driven Generators Page 1 of 6 Last Update: December 8, 2014 A. Description of System Consultant s Handbook Page 1 of 6 1. Provide a diesel engine driven electric generating unit, factory assembled, tested and certified to operate at

More information

Safety, Health and Accessibility Design Guidelines For Architects, Engineers and Design Firms

Safety, Health and Accessibility Design Guidelines For Architects, Engineers and Design Firms Safety, Health and Accessibility Design Guidelines For Architects, Engineers and Design Firms U.S. Department of the Interior Bureau of Indian Affairs Division of Safety and Risk Management Introduction

More information

SECTION 13850 (28 31 00) FIRE DETECTION AND ALARM SYSTEM

SECTION 13850 (28 31 00) FIRE DETECTION AND ALARM SYSTEM SECTION 13850 (28 31 00) FIRE DETECTION AND ALARM SYSTEM ENGINEERING SPECIFICATION INTELLIGENT REPORTING FIRE DETECTION SYSTEM PART 1 GENERAL 1.1 DESCRIPTION A. This specification includes the furnishing,

More information

EXPRESS PERMITS (No Plan Check Required)

EXPRESS PERMITS (No Plan Check Required) EXPRESS PERMITS (No Plan Check Required) Following are the lists of different types of construction for which an express permit can be issued. Express permits can be issued where work does not require

More information

Energy-efficient data center achieves 2N reliability; MTU Onsite Energy generator sets provide critical backup

Energy-efficient data center achieves 2N reliability; MTU Onsite Energy generator sets provide critical backup Press Release Contact: Gary Mason Tognum America Inc. Phone: +1 248 560 8480 E-mail: gary.mason@tognum.com Agency contact: Robert E. Sheldon, APR Creative Communications Consultants, Inc. Phone: +1 210

More information

ISO IEC 27002 2005 (17799 2005) INFORMATION SECURITY AUDIT TOOL

ISO IEC 27002 2005 (17799 2005) INFORMATION SECURITY AUDIT TOOL 9.1 USE SECURITY AREAS TO PROTECT FACILITIES 1 GOAL Do you use physical methods to prevent unauthorized access to your organization s information and premises? 2 GOAL Do you use physical methods to prevent

More information

DELAWARE STATE FIRE MARSHAL FIRE ALARM SYSTEM CERTIFICATE OF INSTALLATION

DELAWARE STATE FIRE MARSHAL FIRE ALARM SYSTEM CERTIFICATE OF INSTALLATION Phone System Owner Phone System Engineered by: of Record Drawings: of System Manuals: of Test Reports: System Installer 1. GENERAL INFORMATION Phone Delaware License No: Certificate Holder No. System Supplier

More information

2012 Michigan Rehabilitation Code for Existing Buildings ISBN: 978-1-60983-208-7

2012 Michigan Rehabilitation Code for Existing Buildings ISBN: 978-1-60983-208-7 2012 Michigan Rehabilitation Code for Existing Buildings First Printing: June 2014 ISBN: 978-1-60983-208-7 COPYRIGHT 2014 by INTERNATIONAL CODE COUNCIL, INC. ALL RIGHTS RESERVED. This 2012 Michigan Rehabilitation

More information

AFTER THE BIG ONE, WILL CRITICAL COUNTY SERVICES SURVIVE?

AFTER THE BIG ONE, WILL CRITICAL COUNTY SERVICES SURVIVE? AFTER THE BIG ONE, WILL CRITICAL COUNTY SERVICES SURVIVE? SUMMARY There is a 67% probability that Southern California will be hit by a magnitude 6.7 or larger earthquake in the next 30 years according

More information

Maintaining Fire Protection Systems

Maintaining Fire Protection Systems Maintaining Fire Protection Systems Fire continues to be a major threat to your business and your personal safety. Each year several thousand people are injured or killed by fires and billions of dollars

More information

ALBERTA FIRE CODE SAFETY EQUIPMENT MAINTENANCE REQUIREMENTS

ALBERTA FIRE CODE SAFETY EQUIPMENT MAINTENANCE REQUIREMENTS ALBERTA FIRE CODE SAFETY EQUIPMENT MAINTENANCE REQUIREMENTS In this document are the fire safety equipment maintenance requirements that are found in Division B of the Alberta Fire Code (AFC 2006) for

More information

EXETER TOWNSHIP DRY OR WET CHEMICAL FIRE SUPPRESSION SYSTEMS

EXETER TOWNSHIP DRY OR WET CHEMICAL FIRE SUPPRESSION SYSTEMS DRY OR WET CHEMICAL FIRE SUPPRESSION SYSTEMS POLICY STATEMENT This policy applies to NEW Dry or Wet chemical fire suppression systems. The Authority Having Jurisdiction will not waive major criteria in

More information

Fire Alarm Systems Certification

Fire Alarm Systems Certification Fire Alarm Systems Certification The skills and knowledge listed under each task are suggestive of those involved in that task, but are not intended to constitute an exhaustive listing. 2.1 Submittal Preparation

More information

Fire Pump Plan Review March 2010

Fire Pump Plan Review March 2010 Fire Pump Plan Review March 2010 Date of Review: / / Permit Number: Business/Building Name: Address of Project: Designer Name: Designer s Phone: Contractor: Contractor s Phone: Occupancy Classification:

More information

HOW TO EVALUATE BUILDINGS AND DETERMINE RETROFIT COSTS

HOW TO EVALUATE BUILDINGS AND DETERMINE RETROFIT COSTS David Bell PJHM Architects, Inc. Young Nam Daniel Traub Thornton Tomasetti how to evaluate buildings and determine retrofit costs HOW TO EVALUATE BUILDINGS AND DETERMINE RETROFIT COSTS Presented by: David

More information

SINGLE-FAMILY EARTHQUAKE (SEISMIC) RETROFITS

SINGLE-FAMILY EARTHQUAKE (SEISMIC) RETROFITS CITY OF BEAVERTON Community Development Department Building Division 12725 SW Millikan Way / PO Box 4755, Beaverton, OR 97076 Phone: (503) 526-2493 Fax: (503) 526-2550 General Information (503) 526-2222

More information

SECTION 16721 FIRE ALARM AND DETECTION SYSTEM

SECTION 16721 FIRE ALARM AND DETECTION SYSTEM 1. GENERAL 1.1. Related Documents: 1.2. Scope: 1.1.1. The general provisions of the Contract, including General and Supplementary Conditions and General Requirements apply to the work specified in this

More information

CAN/ULC S1001-11 Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning

CAN/ULC S1001-11 Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning CAN/ULC S1001-11 Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning Presentation To: Canadian Fire Alarm Association (CFAA) Alberta Technical Seminar

More information

APEC CAPABILITIES PROJECT MANAGEMENT / SUPPORT

APEC CAPABILITIES PROJECT MANAGEMENT / SUPPORT PROJECT MANAGEMENT / SUPPORT Capital Cost Savings Construction Monitoring and Assistance In-Plant Production Assistance In-Plant Maintenance Assistance Procurement Assistance Project Cost Estimating o

More information

Location. Central Business District. Ataturk Airport IFC. Sabiha Gökçen Airport

Location. Central Business District. Ataturk Airport IFC. Sabiha Gökçen Airport Welcome Zenium Istanbul One provides 12,000 square metres of high specification technical space across three purpose-built data centers. It is Turkey s first wholesale data center offering; the data halls

More information

527 CMR: BOARD OF FIRE PREVENTION REGULATIONS

527 CMR: BOARD OF FIRE PREVENTION REGULATIONS 527 CMR 31.00: CARBON MONOXIDE ALARMS Section 31.01: Purpose and Scope 31.02: Definitions 31.03: General Installation Provisions 31.04: Specific Installation Provisions 31.05: Carbon Monoxide Protection:

More information

CyberFortress Data Center at Innovation Park Infrastructure and Topology Guide. Innovation Park Charlotte. NC 28262. DRAFT V0.

CyberFortress Data Center at Innovation Park Infrastructure and Topology Guide. Innovation Park Charlotte. NC 28262. DRAFT V0. Innovation Park Charlotte. NC 28262 DRAFT V0.1 Page 2 CyberFortress Data Center at Innovation Park BECO South purchased Innovation Park in March 2010 and immediately launched a dramatic top-to-bottom $30M

More information

inimi ing damage and repair osts to manufa tured omes during an eart ua e

inimi ing damage and repair osts to manufa tured omes during an eart ua e inimi ing damage and repair osts to manufa tured omes during an eart ua e Prepared for T e Department of Housing and Urban Development Offi e of Poli y Development and eesear by t e National Conferen e

More information

G. Michele Calvi IUSS Pavia

G. Michele Calvi IUSS Pavia CONVEGNO SISMA ED ELEMENTI NON STRUTTURALI Approcci, Stati Limite e Verifiche Prestazionali Bologna 24 ottobre 2014 PROGETTO DI ELEMENTI NON STRUTTURALI SOGGETTI AD AZIONI SISMICHE G. Michele Calvi IUSS

More information

PLAN REVIEW GUIDE FOR FIRE ALARM

PLAN REVIEW GUIDE FOR FIRE ALARM PLAN REVIEW GUIDE FOR FIRE ALARM PROJECT NAME: PERMIT # PROJECT ADDRESS: CONTACT PERSON: PHONE Fire alarm system installation information shall be provided on the appropriate architectural and electrical

More information

CITY OF PHILADELPHIA DEPARTMENT OF LICENSES AND INSPECTIONS ANNUAL CERTIFICATION FOR FIRE ALARM SYSTEMS

CITY OF PHILADELPHIA DEPARTMENT OF LICENSES AND INSPECTIONS ANNUAL CERTIFICATION FOR FIRE ALARM SYSTEMS CITY OF PHILADELPHIA DEPARTMENT OF LICENSES AND INSPECTIONS ANNUAL CERTIFICATION FOR FIRE ALARM SYSTEMS PROPERTY ADDRESS (BRT Address Required) TESTING CONTRACTOR (Name and Address) License No. ANNUAL

More information

TELECOMMUNICATION SYSTEM HAZARD MITIGATION STRATEGIC PLANNING

TELECOMMUNICATION SYSTEM HAZARD MITIGATION STRATEGIC PLANNING TELECOMMUNICATION SYSTEM HAZARD MITIGATION STRATEGIC PLANNING A.K. Tang 1 1 President, L&T Engineering and Project Management Consultant, Mississauga. Canada Email: alexktang@mac.com ABSTRACT: Telecommunication

More information

NEW JERSEY CENTER OF EXCELLENCE

NEW JERSEY CENTER OF EXCELLENCE Overview NEW JERSEY Page 1 The Plant (CUP) provides electricity via a cogeneration system, chilled water for environmental cooling, steam for heating, and compressed air primarily for HVAC control Serves

More information

Arc Terminator Active Arc-Resistant Switchgear

Arc Terminator Active Arc-Resistant Switchgear Arc Terminator Active Arc-Resistant Switchgear Increasing safety and productivity by extinguishing internal arcing faults within the switchgear. The Square D Arc Terminator from Schneider Electric offers

More information

Prime Power Services, Inc. Georgia, Carolinas 800 741 0128. NFPA 110 Standards for Emergency & Stand by Generators June 1, 2010

Prime Power Services, Inc. Georgia, Carolinas 800 741 0128. NFPA 110 Standards for Emergency & Stand by Generators June 1, 2010 Prime Power Services, Inc. Georgia, Carolinas 800 741 0128 NFPA 110 Standards for Emergency & Stand by Generators June 1, 2010 NFPA Disclaimer The views and opinions expressed in this seminar are purely

More information

UCLA Policy 811: Environmental Health and Safety

UCLA Policy 811: Environmental Health and Safety UCLA Policy 811: Environmental Health and Safety Issuing Officer: Assistant Vice Chancellor, General Services Responsible Dept: Environment, Health & Safety Effective Date: September 5, 2007 Supersedes:

More information

MOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION

MOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION MOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION Fire Pump Plan Review 2009 International Fire Code and NFPA 20 Date of Review / / BLD201 - Project Address: Project Name: Contractor s Business

More information

NATIONAL FIRE ALARM AND SIGNALING CODE

NATIONAL FIRE ALARM AND SIGNALING CODE GAP.11.1.1.0 A Publication of Global Asset Protection Services LLC NATIONAL FIRE ALARM AND SIGNALING CODE INTRODUCTION National Fire Protection Association (NFPA) documents describe a level of fire protection

More information

University Design Standard. Fire Alarm Systems

University Design Standard. Fire Alarm Systems University Design Standard Fire Alarm Systems 1.0 Overview This document provides Virginia Tech s standards for the design and installation of fire alarm systems and equipment in new construction, retrofit

More information

Butch Browning State Fire Marshal, Bobby Jindal Governor - Licensing Requirements

Butch Browning State Fire Marshal, Bobby Jindal Governor - Licensing Requirements LOUISIANA DEPARTMENT OF PUBLIC SAFETY AND CORRECTIONS OFFICE OF STATE FIRE MARSHAL, CODE ENFORCEMENT AND BUILDING SAFETY H. Butch Browning State Fire Marshal Bobby Jindal Governor Licensing Law and Rules

More information

Canadian Regulatory Compliance for Stationary Battery Systems North American Update

Canadian Regulatory Compliance for Stationary Battery Systems North American Update Canadian Regulatory Compliance for Stationary Battery Systems North American Update ComplianceKnowledgeCenter.com What is Compliance? In general: compliance means conforming to a rule, such as: a specification,

More information

DESIGN CRITERIA. Determination of earthquake demand. Building importance level. Component categories SEISMICALLY RESILIENT NON-STRUCTURAL ELEMENTS

DESIGN CRITERIA. Determination of earthquake demand. Building importance level. Component categories SEISMICALLY RESILIENT NON-STRUCTURAL ELEMENTS FACT SHEET 2 NZS 4219:2009 Seismic performance of engineering systems in buildings requires the arrangement and layout of engineering systems within a building to allow for earthquake actions. NZS 4219:2009

More information

National Competency Based Skill Training Refrigeration and Air-conditioning Mechanic Logbook

National Competency Based Skill Training Refrigeration and Air-conditioning Mechanic Logbook National Competency Based Skill Training Refrigeration and Air-conditioning Mechanic Logbook Trainee:... Training Provider:... Year:... Trainee Contact no:... Competency Based Skill Training Logbook Introduction

More information

NIST Disaster Resilience Framework

NIST Disaster Resilience Framework NIST Disaster Resilience Framework Communication and Information Systems Presenter: David Mizzen Applied Research Associates Chapter Goals Provide guidance to: 1. Understand potential vulnerabilities/damage

More information

Building Code of New York State

Building Code of New York State Welcome Christopher R. Paolini, P.E., Sr. Vice President CME Associates, Inc. 6035 Corporate Drive East Syracuse, New York 13057 (315) 701-0522 (315) 701-0526 (Fax) cpaolini@cmeassociates.com 1 Building

More information

Welcome UST Owners & Operators!!

Welcome UST Owners & Operators!! Welcome UST Owners & Operators!! Underground Storage Tank Owner & Operator Workshop Presented By: Kern County Environmental Health CUPA Kern County Environmental Health Phone: (661) 862-8740 Email: hazmatprogram@co.kern.ca.us

More information

UL Fire Door Inspection Service. UL Fire Alarm Certification Program. A valuable but misunderstood resource for jurisdictions

UL Fire Door Inspection Service. UL Fire Alarm Certification Program. A valuable but misunderstood resource for jurisdictions 2013 Issue 2 2 A Strong Foundation 3 Introducing UL Fire Door Inspection Service 6 Enhanced UL Marks Coming Your Way Soon UL Fire Alarm Certification Program A valuable but misunderstood resource for jurisdictions

More information

ENGINEERING-BASED EARTHQUAKE RISK MANAGEMENT

ENGINEERING-BASED EARTHQUAKE RISK MANAGEMENT ENGINEERING-BASED EARTHQUAKE RISK MANAGEMENT MRP Engineering Newsletter February 2012 The world recently experienced several major earthquakes, which caused severe local impacts and major worldwide repercussions.

More information

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES A. The Owner will contract separately and directly for the majority of the commissioning work

More information

BUILDING OCCUPANCY RESUMPTION PROGRAM

BUILDING OCCUPANCY RESUMPTION PROGRAM BUILDING OCCUPANCY RESUMPTION PROGRAM Revised JANUARY 2011 CITY AND COUNTY OF SAN FRANCISCO DEPARTMENT OF BUILDING INSPECTION EMERGENCY OPERATIONS PLAN For any questions regarding this program, please

More information

ENVIRONMENTAL HEALTH & SAFETY 6 East Dr., Amherst MA 01002-5000

ENVIRONMENTAL HEALTH & SAFETY 6 East Dr., Amherst MA 01002-5000 AMHERST COLLEGE ENVIRONMENTAL HEALTH & SAFETY 6 East Dr., Amherst MA 01002-5000 Michael Zlogar April 11, 2001 Assistant Fire Chief Amherst Fire Department 68 North Pleasant St. Amherst, MA 01004 FIRE ALARM

More information

Published in the Official State Gazette (BOE) number 166 of July 10th 2009 [1]

Published in the Official State Gazette (BOE) number 166 of July 10th 2009 [1] Nuclear Safety Council Instruction number IS-22, of July 1st 2009, on safety requirements for the management of ageing and long-term operation of nuclear power plants Published in the Official State Gazette

More information

Cx for Enhanced Healthcare Project Delivery. Presentation Format. Project features and timeline

Cx for Enhanced Healthcare Project Delivery. Presentation Format. Project features and timeline Cx for Enhanced Healthcare Project Delivery Rick Staley Sr. Construction Manager PH&S Joe Webb Construction Manager PH&S Richard Beam Director, Energy Management Services PH&S Todd McGuire, PE - Sr. Project

More information

Building Permit Application

Building Permit Application Building Permit Application Administrative Use Only PARENT PERMIT NUMBER (Required if part of another project) PERMITTEE: PERMITTEE ADDRESS: E-MAIL ADDRESS: ARCHITECT/ENGINEER: PHONE: PHONE: ARCHITECT/ENGINEER

More information

Director of Operations. Lattice Communications & Industrial Energy Applications

Director of Operations. Lattice Communications & Industrial Energy Applications Director of Operations Lattice Communications & Industrial Energy Applications The Case for Remote Monitoring How confident are you that your generator will be available when you need it? How can you be

More information

SECTION 26 05 49 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

SECTION 26 05 49 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS SECTION 26 05 49 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes seismic restraints and other earthquake-damage-reduction measures for electrical

More information

ISSUE BRIEF. Understanding the Hospital Planning, Design, and Construction Process. Introduction. Background. Phase 1: Project Definition and Planning

ISSUE BRIEF. Understanding the Hospital Planning, Design, and Construction Process. Introduction. Background. Phase 1: Project Definition and Planning Understanding the Hospital Planning, Design, and Construction Process Introduction California s acute care hospitals are an essential health care resource that serve a wide range of patients during times

More information

FIRE ALARM AND DETECTION SYSTEMS SECTION 16721

FIRE ALARM AND DETECTION SYSTEMS SECTION 16721 PART 1 - GENERAL 1.01 WORK INCLUDED FIRE ALARM AND DETECTION SYSTEMS SECTION 16721 A. Provide a complete fully addressable, power limited, fire detection and evacuation system. The system shall be connected

More information

State of Iowa Electrician Licensing Program Brian Young Interim Executive Secretary Of The Electrical Examining Board Division Of The State Fire Marshal s Office Iowa Code 103 Electrician Licensing & Inspections

More information

POSITION STATEMENT THE ENGINEER AND THE ENGINEERING TECHNICIAN DESIGNING FIRE PROTECTION SYSTEMS. July 28, 2008

POSITION STATEMENT THE ENGINEER AND THE ENGINEERING TECHNICIAN DESIGNING FIRE PROTECTION SYSTEMS. July 28, 2008 SOCIETY OF FIRE PROTECTION ENGINEERS (SFPE) NATIONAL SOCIETY OF PROFESSIONAL ENGINEERS (NSPE) NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES (NICET) POSITION STATEMENT THE ENGINEER AND

More information

2012 Ontario Building Code Changes Affecting Fire Alarm Systems

2012 Ontario Building Code Changes Affecting Fire Alarm Systems 2012 Ontario Building Code Changes Affecting Fire Alarm Systems CFAA Annual Technical Seminar May 31, 2013 Ken Baird VP Systems www.lrifire.com LRI 2010 Developments in Life Safety Introduction Code Development

More information

2015 C&I HVAC RETROFIT APPLICATION FOR PRESCRIPTIVE REBATES

2015 C&I HVAC RETROFIT APPLICATION FOR PRESCRIPTIVE REBATES 2015 C&I HVAC RETROFIT APPLICATION FOR PRESCRIPTIVE REBATES WELCOME TO THE POWER MOVES C&I HVAC RETROFIT PROGRAM. We look forward to working with you. If you have questions after reading this application,

More information

HERNANDO COUNTY FIRE ALARM GUIDELINES

HERNANDO COUNTY FIRE ALARM GUIDELINES HERNANDO COUNTY FIRE ALARM GUIDELINES To be used for all commercial building fire alarm system plan review. The procedures set forth in this document are the minimum requirements necessary to ensure a

More information

This is a Master s degree level apprenticeship which includes academic learning combined workplace learning and training.

This is a Master s degree level apprenticeship which includes academic learning combined workplace learning and training. Power Engineer Degree Apprenticeship The UK s energy sector is integral to the prosperity and stability of the UK economy as a whole, delivering an absolutely fundamental service for all its citizens.

More information

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F TABLE OF CONTENTS Appendix F - Electrical Engineering Design Criteria F.1 Introduction...F-1 F.2 Codes and Standards...F-1 F.3 Switchyard and Transformers...F-1

More information

BT300 HVAC Drives Conventional Bypass (C-Bypass) Options

BT300 HVAC Drives Conventional Bypass (C-Bypass) Options BT300 HVAC Drives Conventional Bypass (C-Bypass) Options Description The BT300 Conventional Bypass is a companion package for the family of BT300 HVAC Drives. For information on the family of BT300 HVAC

More information

SECTION THREE CONSTRUCTION CODES

SECTION THREE CONSTRUCTION CODES SECTION THREE CONSTRUCTION CODES CHAPTER 36: Construction Codes in Michigan Purpose and Applicability of Regulations Manufacturing facilities and other businesses must be designed according to code in

More information

Energy Design Resources Commissioning Plan Outline Template

Energy Design Resources Commissioning Plan Outline Template IMPORTANT NOTICE: This sample document is provided for instructional purposes only. CCC is not rendering advice concerning any commission project or practices. This document is neither approved nor intended

More information

APPLICATION PACKAGE FOR LISTING AS A WATER AND/OR WASTEWATER INFRASTRUCTURE PROVIDER FOR DESIGNERS, CONSTRUCTORS

APPLICATION PACKAGE FOR LISTING AS A WATER AND/OR WASTEWATER INFRASTRUCTURE PROVIDER FOR DESIGNERS, CONSTRUCTORS APPLICATION PACKAGE FOR LISTING AS A WATER AND/OR WASTEWATER INFRASTRUCTURE PROVIDER FOR DESIGNERS, CONSTRUCTORS (Major & minor works) TO THE MANAGING NEW DEVELOPMENTS PROCESS For information regarding

More information