June On behalf of: Harrow Estates Plc

Size: px
Start display at page:

Download "June 2011. On behalf of: Harrow Estates Plc"

Transcription

1 Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model Former Bayer Crop Science Site Hauxton Cambridgeshire June 2011 On behalf of: Harrow Estates Plc Vertase F.L.I. Limited 3000 Aviator Way Manchester Business Park Manchester M22 5TG Tel +44 (0) Fax +44 (0)

2

3 Executive Summary The report has been prepared to reassess the risk assessment with respect to controlled waters at the former BayerScience site, Hauxton following the collection of further data during the ongoing remediation. This report describes the site setting and outlines previous work undertaken to date with respect to the controlled waters risk assessment. It takes on board information gathered during the current remedial works and builds upon previous investigation data to provide a revised conceptual site model for the post remediation conditions that has significantly more certainty with regard to volumes and types of soil material and thus the geometry of restored soil horizons compared to previous models. This assessment follows the previous risk assessment (Further Quantitative Risk Assessment for Risks to Groundwater and Surface Water, Former Bayer Crop Science Site, Hauxton, Cambridgeshire February 2011) and has been adapted to the new post remediation conceptual site model for and expanded to cover all contaminants of concern. This is now a major step towards the final post remediation risk assessment model that was discussed in the remediation method statement. This assessment will now be updated on a continual and ongoing basis with site data from the ongoing validation. An appropriate level of conservatism and variation within parameters has been built in to allow for any future variability in the treated soils at site. Geotechnical and hydrogeolgical parameters for the treated soils have been assessed through laboratory and in-situ testing. These site specific parameters have subsequently been used in the risk assessment model to enable the potential risks from any residual contaminants in the reinstated remediated soils to be assessed. The output from the model represents the maximum concentrations in soils and leachate that would not result in an exceedance of the selected compliance target at the receptor, the Riddy Brook (i.e. the Environment Agency Environmental Quality Standards or equivalent.) These maximum concentrations will be used as such and in most cases material will be treated much below these concentrations to ensure that the risks are minimised further. The actual achieved concentrations post treatment so far can be as much as several orders of magnitude lower than these maximum concentrations. In order to be protective of human health also a set of working targets has been prepared to ensure remediated soils are both acceptable within the controlled waters risk assessment and that of human health. These are presented in separate documents. We will now continue to build on this model and will add further data to the model as we continue to progress with validation and restoration of material. Once material is restored at the site we wil have final residual contaminants of concern concentrations in the reinstated soil materials, updated geotechnical and hydrogeological parameters and fraction organic carbon which will be entered into the models as probability density functions (or PDF s) to represent actual material at the site. The model will be re-run periodically to ensure that no risk to controlled waters remain resulting ultimately in a post remediation model accurately reflecting ground conditions at the site.

4 Table of Contents 1.0 Introduction Limitations Remediation Strategy and Approach to Risk Assessment Environmental Setting Site Description Pre Remediation Conditions Pre-Remediation Ground Conditions Existing Remedial Measures Hydrogeology Hydrology Observed Conditions During Remedial Works Ground Conditions Additional Contaminant Source Hydrogeology Review of Previous Reports Enviros Consulting Part IIA Site Investigation Report for Bayer Crop Science, January Atkins Environment, Remediation of Former Bayer Site, Hauxton, Preliminary Conceptual Model Report August Atkins Environment, Former Bayer Site, Hauxton, Groundwater Modelling Report, June MODFLOW QRA Vertase FLI, Further Quantitative Risk Assessment for Risks to Groundwater and Surface Waters, January Summary of Previous Works Conceptual Site Model Original CSM Post Remediation Site Conditions Ground Conditions Groundwater Flow Through the Site Aquifer Parameters Post Remediation CSM Contaminant Source Pathways Receptor Selection of Risk Assessment Software and Modelling Approach Environment Agency Remedial Targets Methodology Assessment of Risks from Soils Assessment of Risks from Contaminated Groundwater Conceptual Model Comparison of EA RTM and Site Conceptual Site Model Risk Assessment Approach Applicability of EA RTM Risk Assessment Levels Selection of Modelling Software Assessing Risks from Type B and C Soil Material Assessing Risks from Type A Soil Material i

5 7.0 Model Inputs Contaminant Sources Receptors Selection of Screening Criteria Selection of Aquifer Pathway Parameters Level 3a Assessment Aquifer Thickness Dry Bulk Density Mixing Zone Thickness Hydraulic Conductivity Effective Porosity Hydraulic Gradient Groundwater Flow Direction Dispersivity Fraction of Organic Carbon Summary Model Settings Model Correlations Soil Source Parameters Level 1 Assessment Contaminant Parameters Selection of Parameters Model Outputs Leachate/Groundwater Maximum CoC Threshold Values Soil Maximum CoC Threshold Values Comparison of Leachate and Soil CoC concentrations ConSim Level 1 Assessment Comparison of Soil Threshold Values Summary Further Work ii

6 Appendices Appendix A Appendix B Vertase FLI Drawings Drawing D907_87 Surveyed Geological Section Drawing D907_154 Post Remediation Conceptual Site Model Drawing D907_134 - ConSim Graphical Input of Source Zones and Receptor, Type B and C model Drawing D907_169 ConSim Graphical Input of Source Zones and Receptor, Type A model Atkins Drawings Drawing /002, Conceptual Site Model for Proposed Site Development, July 2006 Drawing /Figure 5, Groundwater Contours (maod) April 29 th 2006 Drawing /Figure 6, Groundwater Contours (maod) May 11 to 16 th 2006 Drawing /Figure 7, Groundwater Contours (maod) 16 th December 2006 Appendix C Appendix D Appendix E Water Pumping Volumes Geotechnical Results Soil Source Parameter Supporting Data Fraction of Organic Carbon Moisture Content Appendix F Appendix G Appendix H Appendix I Contaminant of Concern Input Value Justifications Contaminants of Concern Literature Values ConSim Model Inputs Type A Material ConSim Model Inputs Type B and C Material Appendix J Relationship Between Soil and Leachate CoC iii

7 Concentrations Appendix K Data CD ConSim Model Outputs iv

8 1.0 Introduction VertaseFLI have been appointed by Harrow Estates Plc to undertake remedial works at the former Bayer Crop Science agrochemicals works in Hauxton, Cambridgeshire (the site). The site has been determined as a Special Site under Part IIa of the Environmental Protection Act (EPA) 1990 due to identified significant pollutant linkages being present with respect to groundwater and surface water resulting from the former use in the production and storage of agrochemicals. The majority of the buildings and structures at the site have been demolished, and at the time of writing, remedial works comprising the excavation of contaminated soil material, the formation of biopiles (including the addition of organic matter) and turning of the contaminated soil material were being undertaken. On completion the remediated soils will be reinstated at the site and the site will be developed for primarily residential use. In order for the remediated soil material to be reinstated, it must be demonstrated through the development of an appropriately detailed risk assessment, that the reinstated soils do not present a significant risk to local receptors such as groundwater and surface water. The initial risk assessment and remedial targets were based on site investigation data collected prior to remediation. As the remedial works have progressed, more data has been obtained on the volumes and properties of the different soil material present at the site so that a more detailed and representative post remedial conceptual site model can be developed. Therefore, in accordance with the remediation method statement (VertaseFLI, Apr 2010) this report reassesses and where necessary revises the risk assessment for the site in light of the additional data collected during the remedial works. 1.1 Limitations It is important to note that this document refers to the CSM with respect to the controlled waters risk assessment only. A human health risk assessment has been undertaken and presented in the report, Derivation of Pesticide Soil Screening Values & Evaluation of the Spatial Extent of Contamination (Atkins, July 2007). It is also discussed in the VertaseFLI Remediation Strategy Report (VertaseFLI, Nov 2008). 1

9 2.0 Remediation Strategy and Approach to Risk Assessment The main strategy for the remediation at the site was to excavate all materials at the site to ensure that all uncertainty regarding contaminants and geological conditions are removed. All excavated soil material was to be segregated, classified and treated as appropriate before being reinstated and validated. Any contaminated groundwater was to be separated, treated and disposed from the site under discharge consent. Following the remediation and reinstatement of soils, a clean cover system will be imported from off-site above the finished levels. Paragraphs 6.3 and 6.4 of the Remediation Strategy set out the approach to be used in developing the risk assessment with respect to environmental receptors as follows: 6.3 An important part of the approach of our remedial strategy will be to collect further information on the geology, hydrogeology, contamination, material parameters and characteristics during the remedial works. It is our intention that this information will be used to further develop the site model to reevaluate the remediation targets. This will be continually re-assessed as the remediation is continued and may ultimately result in the preparation of a numerical model that represents exact site conditions with a high degree of certainty to prove that materials present on site post remediation do not represent a significant risk of significant harm to the environment and that adequate remediation works have been completed to satisfy the requirements under Part IIa of the Environmental Protection Act This modelling approach will be calibrated by site based monitoring and the mode calibrated appropriately. It does mean that some material will be replaced at the site that does not meet the present generic criteria but through the remediation we will have detailed data and knowledge of this material which will allow clearer understanding of the site. This knowledge and understanding will be used to present a new conceptual model and appropriate risk assessment. Therefore, an iterative approach has been used to allow the groundwater risk assessment to be further developed as more data becomes available during the risk assessment, so that the post remediation site conditions and conceptual model, and therefore the site specific remedial targets, can be developed with as much accuracy as possible. The level 2

10 of data now available has enabled a robust model for all contaminants of concern to be developed with revised risk based remediation targets to work towards. As the remedial work continues and soil material is reinstated, the validation data for the reinstated soils will be incorporated into the risk assessment model as part of the validation process so that on completion of the work the final model will accurately represent the remediated conditions at the site. 3

11 3.0 Environmental Setting 3.1 Site Description The site is situated approximately 200 m northwest of the village of Hauxton (National Grid Ref TL ), and covers an area of approximately 9 hectares. It was previously occupied by Bayer CropScience and used for the production and storage of agrochemicals including pesticides, insecticides and herbicides. The site is bounded to the west by the A10 trunk road beyond which is agricultural land and the Waste Water Treatment Plant (WWTP) for the Site. The northern and eastern site boundaries are formed by the Riddy Brook, with Church Road forming the southern site boundary and the southeast of the site bounded by agricultural land. The site is generally level with a ground elevation of between 12 and 13 m AOD. 3.2 Pre Remediation Conditions Pre-Remediation Ground Conditions Based on the information provided by Enviros (2005) and Atkins (2006), the preremediation ground conditions at the site are presented in Table 1. Table 1: Ground Conditions Description Made Ground (consisting of reworked sand and gravel, chalk marl, alluvium, brick rubble and clinker), foundations, drainage features and voids Superficial Deposits Alluvium and River Terrace Gravels West Melbury Marly Chalk Formation (WMMCF) Marly chalk with thin limestone bands, typically described in available logs as a stiff light grey clay Gault Clay Thickness Typically up to 2 m bgl, with a maximum thickness of 5 m Generally < 3 m thick where present. Completely replaced by Made Ground in parts of the site Present in the south and northwest of the Site only. Typically less than 3m thick with a maximum thickness of 7m in some areas. Typically present at a depth of 5 m bgl underlying Made Ground/Superficial Deposits/WMMCF, the thickness is understood to be up to 50 m (based on historic borehole data presented in Atkins (2006) 4

12 Lower Greensand m Existing Remedial Measures Prior to the current remedial works at the site, the following measures had been undertaken at the site to control groundwater: A bentonite and cement cut-off wall was constructed along the Riddy Brook. It is understood to have been installed in 1974; A groundwater abstraction system was in use in the north of the site to prevent the migration of contaminated groundwater to the north of the bentonite wall. The system comprised several sumps which were pumped to the waste water treatment works (WWTW) to the north of the site; and A dewatering system was present in the south of the site associated with the warehousing in this area. The construction of the warehouse and associated loading areas is understood to have included the excavation of soil material such that they were constructed below the natural water level on the site. As a result, a dewatering system comprising a sump was constructed to artificially lower the groundwater level in this area with all waste water pumped to the adjacent WWTW Hydrogeology Geological Units Made Ground and Drift Deposits The natural drift deposits at the site comprise River Terrace Gravels and Alluvium and are classified by the Environment Agency as a Secondary A Aquifer which are described as: permeable layers capable of supporting water supplies at a local rather than strategic scale, and in some cases forming an important source of base flow to rivers. These are generally aquifers formerly classified as minor aquifers. The granular Made Ground was considered by Atkins to be part of the same hydraulic units for modelling purposes. The presence of cohesive Made Ground was considered to be associated with the presence of perched groundwater. 5

13 West Melbury Marly Chalk Formation The Lower Chalk (which includes the WMMCF) is classified by the Environment Agency as a Primary Aquifer. A Primary Aquifer is described as: These are layers of rock or drift deposits that have high intergranular and/or fracture permeability - meaning they usually provide a high level of water storage. They may support water supply and/or river base flow on a strategic scale. In most cases, principal aquifers are aquifers previously designated as major aquifer. However, the investigations undertaken by Enviros and Atkins indicated that the WMMCF was largely absent from the centre and north of the main site. The WMMCF had a high content (typically described in available borehole logs as a stiff light grey clay) and was considered by Atkins to have poor aquifer properties Gault Clay The underlying Gault Clay is considered to act as an aquiclude, preventing continuity between any shallow groundwater present in on the site and the Lower Greensand which underlies the Gault Groundwater Levels and Flow Direction Groundwater was typically present at depths between 0.69 and 2.42 m below ground level (bgl) with an average depth on the site of 1.3 m bgl. Based on the available site investigation data, pre remediation, groundwater flow was assumed to occur within the granular Made Ground and drift deposits, site infrastructure, and within the dis-continuous sand and gravel lenses within the underlying WMMCF. The local groundwater flow direction was generally from the south and west towards the Riddy Brook and the River Cam. However, groundwater flows on site were significantly altered due to the presence of a bentonite cut off wall along the northeast site boundary and the ongoing abstraction of groundwater in both the north and the south of the site. As can be seen from the 2006 Atkins groundwater contours presented in Appendix B, a groundwater low was present in the south of the site as a result of the dewatering/groundwater abstraction in this area which resulted in groundwater flow towards this area and a steeper hydraulic gradient over much of the site compared to off-site. Following remediation including the removal of the bentonite wall and cessation of groundwater abstraction, it is anticipated that groundwater flow across the site will generally be to the northeast, towards the Riddy Brook. 6

14 3.2.4 Hydrology The Riddy Brook and Hauxton Mill Race are the closest water bodies to the site, forming much of the northern and eastern site boundary. The Riddy Brook and Hauxton Mill race meet immediately to the north of the site where they enter the River Cam. Shallow groundwater at the site is considered to be in direct continuity with the Riddy Brook. Due to the existing bentonite wall and groundwater abstraction system, the site does not currently contribute significantly to the Riddy Brook base flow. 3.3 Observed Conditions During Remedial Works As the remediation has progressed, the excavation of soil material across the site has allowed a far more detailed understanding of the pre-remediation ground conditions including the extent of contamination, and the hydrogeological properties of the soil material to be developed. The following sections describe the additional observations made during the remediation of the site so far Ground Conditions The excavation of soil material as part of the remedial works has generally confirmed the distribution and thickness of the Made Ground, WMMCF and Gault Clay described by Enviros and Atkins. The presence of natural superficial deposits typically comprising sand and gravel was also confirmed. The excavations showed the deposits to have been discontinuous across the site, as described in the previous site investigations, and comprised several large shallow lenses of sand and gravel with a maximum thickness of 3m. Thin discontinuous lenses of sand and gravel were also identified in the WMMCF. Drawing 907_85 in Appendix 1 shows a surveyed section of the excavation with exposed isolated sand and gravel lenses present within the surrounding stiff grey clay material. It is important to note, that post remediation, the ground conditions and properties may be significantly different to the pre-remediation conditions due to the homogenisation of soil material during the remediation and the compaction on reinstatement Additional Contaminant Source The excavations generally confirmed the contaminant distribution identified in the previous reports with contaminant levels generally highest in the former process areas. However, during the excavations a discreet lens of sand and gravel in the top of the WMMCF was identified to the northeast of the site (surveyed on Drawing 907_85), adjacent to the Riddy 7

15 Brook which also contained between 20 and 30 corroded steel drums. The sand and gravel was associated with significantly elevated contaminant concentrations. The sand and gravel lens extended to the Riddy Brook and may have acted as a direct contaminant pathway until the bentonite wall was constructed, On discovery, the drums were appropriately disposed of and the associate sand and gravel moved to a treatment bed Hydrogeology Prior to remediation, groundwater flow to the Riddy Brook through the site was assumed to be through granular Made Ground and granular drift deposits with the majority of any flow through the discontinuous lenses of sand and gravel within the WMMCF as shown in the original Atkins CSM (Appendix B). However, as described in and 3.3.1, the WMMCF predominantly comprises stiff clay with thin isolated discontinuous lenses of sand and gravel. The full thickness of WMMCF has been exposed in the sides of the remediation excavations. Based on the exposed sections, groundwater flow within the in-situ WMMCF surrounding the site is very low with any flow generally occurring as seepages through the discontinuous sand and gravel lenses. These seepages through the exposed lenses typically decrease with time suggesting negligible recharge through natural strata as would be expected given the discontinuous nature of the sand and gravel lenses and the surrounding stiff clay/marl. As a result, the excavations which are to depths significantly below the natural water table over much of the site, have largely remained dry (with the exception of rainfall) for the duration of the remediation so far. In areas where excavations have not commenced groundwater flow appears to be largely associated with the presence of drainage features and other site infrastructure, and the presence of granular Made Ground following periods of rainfall. The pumping system in the north of the site is no longer in use. The remaining pumping system in the south of the site receives all water from the site drainage system. The sump for the pumping system is located adjacent to a lens of sand and gravel and this is likely to contribute to the total volume of water removed from the site. 8

16 4.0 Review of Previous Reports A number of investigations and risk assessments have been undertaken at the site since For clarity, a summary is provided in the following sections of some of the previous work carried out. The following reports relevant to the assessment of risks to groundwater and surface waters were made available to VertaseFLI for review: Enviros Consulting Ltd, Part IIA Site Investigation Report, Report for Bayer Crop Science, January 2005, Reference SH A; Atkins Environment, Remediation of Former Bayer Site, Hauxton, Preliminary Conceptual Model Report Prepared for Bridgemere UK Limited and Harrow Estates Plc, August 2006; Atkins Environment, Former Bayer Site, Hauxton, Groundwater Modelling Report, Prepared for Harrow Estates Plc, June 2007; and Vertase FLI, Former Bayer Crop Science Site, Hauxton Further Quantitative Risk Assessment for Risks to Groundwater and Surface Waters, February 2011,. In accordance with the Remediation Strategy, a review of the previous site investigations and risk assessments was undertaken. The principal findings of previous investigations and risk assessments at the site are detailed in the following sections. 4.1 Enviros Consulting Part IIA Site Investigation Report for Bayer Crop Science, January 2005 The report details the findings of the site investigation undertaken to satisfy the determination of the site as a Special Site under Part IIa of the Environmental Protection Act The report built on previous work at the site from 1991 onwards which had included installation and monitoring of 59 No. piezometers and 19 No. monitoring boreholes. Additional intrusive work comprised the drilling of 10 No. new boreholes and 41 window sample holes. The key findings of the report were: Identified soil contamination was largely restricted to localised hot spots within the site, typically in the immediate vicinity of the former production areas. Identified contaminants included a wide range of pesticides and VOCs; 9

17 Soil contamination was considered to make a small and localised contribution to the contaminant source with only small volumes of contaminated soil identified in the unsaturated zone. It was considered that greatest potential impact on controlled water receptors would be from the presence of contaminants within groundwater; The greatest concentration of contaminants in groundwater was identified in the centre of the site; Contaminant concentrations in groundwater were significantly lower outside of the identified contaminant source areas. The decrease in concentrations was much greater than would be anticipated through contaminant migration alone and it was therefore considered that biodegradation of contaminants was occurring. Additionally, one of the main solvent contaminants in groundwater at the site was trichloroethene (TCE) and the presence in groundwater of breakdown products which increased as TCE decreased away from the source was taken as further evidence of biodegradation occurring; The WMMCF was proven to be absent under much of the site and less than 4m thick downstream of the contaminant sources. The WMMCF was also of low permeability. Therefore, the WMMCF was not considered to be a significant receptor and the potential pollutant linkage between the site and the WMMCF was considered invalid; and A significant pollutant linkage was confirmed between contaminated shallow groundwater and the Riddy Brook and River Cam. 4.2 Atkins Environment, Remediation of Former Bayer Site, Hauxton, Preliminary Conceptual Model Report August 2006 Atkins Environmental (Atkins) prepared the report on behalf of Harrow Estates to further develop and refine the conceptual site model (CSM) for the site and to address uncertainties identified in the Enviros report. An additional 12 boreholes and 17 window sample holes were drilled over the site to further assess the ground conditions overlying the Gault Clay and to install new groundwater monitoring boreholes. Samples of soil and groundwater were analysed for contaminants including individual pesticides and herbicides, some geotechnical testing was also undertaken and, falling head tests were conducted between 1.5 m and 3.6 m bgl during drilling. The principal findings of the work were: 10

18 The investigations confirmed the highest contaminant concentrations were in the former production and storage areas of the site; Leachate analysis indicated that there was the potential for contaminants, including pesticides and herbicides to leach into groundwater at the site; Groundwater analysis identified high levels of pesticides and organic substances although there did not appear to be a consistent pattern of groundwater contamination, transport or migration across the site, with the presence of cohesive soil material appearing to limit migration; Concentrations of light non aqueous phase liquids (LNAPL) and dense non-aqueous phase liquids (DNAPL) were identified in concentrations that may have been indicative of free phase contaminants to be present; The report confirmed the Enviros findings that biodegradation of pesticides, herbicides and organic compounds was occurring; The report considered that both the WMMCF and surface water courses (Riddy Brook and the River Cam) should be considered as receptors; and The report recommended the use of the use of MODFLOW and the Environment Agency Remedial Targets Worksheet to derive suitable remedial targets for the site. 4.3 Atkins Environment, Former Bayer Site, Hauxton, Groundwater Modelling Report, June 2007 Based on the findings of the Preliminary CSM report (discussed in Section 4.2), a quantitative risk assessment (QRA) was conducted using MODFLOW and the Environment Agency Remedial Targets Worksheet (EA RTW). Additionally, further assessment of the presence of DNAPL was carried out and pumping tests were also undertaken to provide more information on the hydraulic conductivity in the soil material overlying the Gault Clay. The approach taken for the groundwater modelling for the QRA was as follows: Development of a detailed water balance for the site and surrounding catchment area; 11

19 The development of the MODFLOW model based on the local geography, geology and hydrogeology which was calibrated based on observed groundwater levels and hydraulic conductivities from the site investigation data; The calibrated MODFLOW model was used to plot travel pathways and the relative unretarded travel times between known contaminant sources and the controlled water receptor (the Riddy Brook) using MODPATH; Qualitative risk screening was conducted based on contaminant concentrations, distance and travel time to receptor and the retardation characteristics of individual contaminants to select a representative list of priority contaminants at the site; and Quantitative Risk Assessment of the priority contaminants was using the EA Remedial Targets Worksheet (EA RTW) which set the preliminary remedial targets MODFLOW The modelled catchment which included the site covered an area of ha. A water balance calculation was undertaken for the catchment area based upon the estimated groundwater base flow to the River Cam and predicted infiltration rates for grassland. This gave an infiltration rate of 1.45 x 10-4 m/day which was used to derive a total water balance for the catchment of 310 m 3 /day. A groundwater flow model for the site was developed using MODFLOW. An iterative approach was taken in the development of the model with input parameters being refined to reflect observed site conditions and data obtained from the site investigation such as the hydraulic conductivities obtained from the pumping tests. A total of 20 models were run to develop the final model of the site which included the modelling of the bentonite wall and groundwater abstraction which was ongoing at the time of writing. Two additional models were also run for the proposed redevelopment of the site with the groundwater abstraction and bentonite wall removed from the model although it was not clear if any other groundwater parameters were altered to reflect the likely changed in groundwater flow. Uniform infiltration rates of m/d for residential properties and m/d for commercial properties were assumed, the modelling conducted with a uniform distribution between the two values. It was considered that the models gave a reasonable representation of the likely future groundwater flux rates and therefore the hydraulic conductivity and hydraulic gradients developed for the models were considered appropriate to use in the QRA. 12

20 4.3.2 QRA The QRA used the EA RTW to model the potential risks. UK Drinking Water Standards were used as appropriate target criteria for the risk assessment due to the limited number of Environment Agency Fresh Water Environmental Quality Standards (EQS) available for organic compounds. The site was divided into two zones which were modelled separately. The first zone comprised the area within 20 m of the Riddy Brook (the receptor) with the second zone comprising the remainder of the site. Twenty three contaminants of concern (CoC) were identified and remedial targets were developed for all CoCs in both zones. However, there were recognised issues with assessing the cumulative impact on the Riddy Brook from two separate sources. As a result for the outer zone, remedial targets were derived based on 90% of the modelled remedial target assuming a distance of 60 m to the receptor. For the inner zone, the distance to receptor was assumed to be 1 m Aquifer Parameters The modelled aquifer was the Made Ground, and the inputs for bulk density and porosity were based on assumed values for cohesive and granular soils. The hydraulic conductivity and hydraulic gradient were determined through the MODFLOW analysis. Typically, for each parameter a range of values was obtained and a representative distribution (Probability Distribution Function (PDF)) selected so that the natural variability of the aquifer could be represented. The aquifer parameters used in the model are presented in Table 2. Table 2 Aquifer Properties Used in Atkins QRA Parameter Units PDF Minimum Most Likely Maximum Water filled soil porosity % Triangular Effective Aquifer Porosity % Triangular Air Filled Porosity % Uniform 1-2 Bulk Density of soil gcm -3 Uniform material in aquifer 2 Infiltration rate m/day Uniform 1x x 10-4 Hydraulic Conductivity m/day Log Triangular Hydraulic Gradient m/m Triangular

21 Contaminant Parameters Contaminant parameters (K d, Henrys Law Constant and half-life in groundwater) were obtained from literature values, primarily obtained from the following references: Handbook of Physical-Chemical Properties and Environmental Fate for Organic Chemicals Second Edition, Mackay et al; ToxNet: The United States Natural Library of Medicine, Hazardous Substances Data Bank EEC active substance reports and Relevant Environment Agency publications. A representative range of values and PDF was selected for each contaminant parameter. Values of partition coefficient K d were calculated based on literature values of the soil organic carbon partition Coefficient K oc and averaged site specific values for the fraction of organic carbon (FOC) using the equation K d = K oc x FOC. As an additional factor of safety, 10% of the calculated value of K d for each contaminant was used to develop the remedial targets. For several pesticides and herbicides, there were no published values for contaminant half life in water. In these cases, a range of half lives considered by Atkins to be conservative (relative to modern pesticides) were used in the model, typically 100 to 730 days Selection of Input Values The EA RTW requires single inputs for each aquifer and contaminant parameter. However, as detailed above, the aquifer and contaminant properties comprised a range of values and representative PDFs. Therefore, the predictive modelling software Crystal Ball TM was used with the parameter ranges and PDFs to derive a single value based on the 95 th percentile value for each parameter Remedial Targets Remedial targets were developed for soil and groundwater in both the inner and outer zones of the site. A number of the calculated remedial targets were below the commercially available limits of detection, and for these contaminants the remedial targets were set at the detection limit. 14

22 4.4 Vertase FLI, Further Quantitative Risk Assessment for Risks to Groundwater and Surface Waters, January 2011 The report reassessed the remedial targets for five priority contaminants of concern (dicamba, schradan, Bis(2-chloroethyl)ether, ethofumesate and 1,2-dichloroethane) using ConSim. ConSim was selected as a suitable risk assessment tool as it can assess the combined effects of different contaminant sources at a receptor and it allowed a range of input values (in the form of probability functions) for all parameters using Monte-Carlo analysis so that natural variations in inputs can be modelled to produce 95 th percentile probability. Due to the geometry of the site, for the modelling, the site was divided into four zones, Zone 1 (the 20 m buffer zone), Zone 2S and 2N (in the centre of the site) and Zone 3 in the southwest. For consistency, and where appropriate, inputs from the Atkins RTW model were used. Soil material was divided into three types, Type A (Granular Made Ground and sand and gravel), Type B (WMMCF) and Type C (Gault Clay). Environment Agency EQS values for freshwater were used for screening criteria at the Riddy Brook, or if not available UK drinking water standards. If neither was available either detection limits or screening values from other regulatory frameworks (such as United States Environmental Protection Agency) were used. Remedial targets were derived for each soil type in each zone with respect to the Riddy Brook for soil, leachate and groundwater. 4.5 Summary of Previous Works A CSM and initial remedial targets were developed by Atkins using EA RTW before remediation commenced for twenty three contaminants of concern. The initial CSM and derivation of remedial targets was largely based on the existing pre-remediation conditions, available Enviros and Atkins site investigation data and modelling of the groundwater regime at the site using MODFLOW. Subsequently five CoCs (dicamba, schradan, Bis(2-chloroethyl)ether, ethofumesate and 1,2-dichloroethane) were identified as priority CoCs by VertaseFLI and remedial targets for these were reassessed using ConSim to provide a more detailed probabilistic risk assessment. 15

23 5.0 Conceptual Site Model 5.1 Original CSM The original CSM for the site was developed by Atkins in 2006 to 2007 and is presented in Appendix B. The CSM presents a detailed model of the sub-surface contaminant pathways prior to remediation. The contaminant source is shown as granular Made Ground and cohesive Made Ground, much of which was located below the water table. The main environmental receptors were groundwater and surface water (Riddy Brook). The key groundwater contaminant pathways in the model are: Vertical migration through the unsaturated zone; Migration of contaminants through sand and gravel lenses within the cohesive Made Ground and WMMCF; and Migration through existing site infrastructure such as sumps and utility trenches. The original CSM and therefore the initial risk assessment and remedial targets were based on the available data at the time which comprised the findings of the site investigations and therefore reflected the pre-remediation site conditions (See sections 4.2 and 4.3) and it was assumed that the majority of groundwater flow was through the sand and gravel lenses associated with the WMMCF. Although significant amount of data had been collected, the investigations were still limited by the presence of buildings and site infrastructure. As described in Section 3.3.2, additional contaminant sources have been located and treated during the remediation process that were not identified during the site investigations. The presence of the bentonite cut off wall and the on-going groundwater abstraction are also likely to have affected groundwater levels and flow directions on the site and the presence of site infrastructure such as sumps, and trenches may also have impacted on the results of pumping tests. 5.2 Post Remediation Site Conditions Ground Conditions Post remediation, ground conditions at the site will generally comprise the following three remediated soil types (see Drawing D907_153, Appendix A): 16

24 Type A Sand and gravels, including granular Made Ground. The total volume is approximately 10,000 m 3 at present; Type B Cohesive soils largely comprising the West Melbury Marly Chalk Formation (WMMCF) including previously reworked material. The total volume is approximately 62,000 m 3 at present; and Type C Gault Clay. The total volume is approximately 12,000 m 3 at present. The soil material will be reinstated in layers replicating the distribution of undisturbed soils prior to development of the site, so that the Type A overlies Type B which will overlie Type C. As described in Section 2.1, prior to remediation the distribution of the natural granular deposits at the site were limited to several shallow discontinuous lenses of sand and gravel. As a result of this and the limited presence of granular Made Ground there is only a relatively small volume (10,000 m 3 at present) of the Type A material present which is insufficient to provide cover over the entire site. Given a thickness of 0.3 m the Type A material would cover approximately 3.5 ha, less than half the area of the site. Therefore, no Type A material will be placed in Zone 1 and the Type A material is also unlikely to be continuous over Zones 2S, 2N and 3 replicating the pre remediation distribution of sands and gravel. The anticipated shortfall in reinstated Type A material in will be made up with Type B material. Given the volumes of remediated material and the area of the site, typical thicknesses of the reinstated units are likely to be as follows: Type A Between 0.3 and 0.6 m (where present); Type B Between 3 and 5 m; and Type C Approximately 0.5 m. The Type C material (comprising remediated Gault Clay) will be placed directly over a significant thickness of undisturbed Gault Clay. It should also be noted the development proposals include the placement of imported low permeability cover material on top of the reinstated soil material. The cover material will be imported from an off-site source by the developer following the completion of the remedial works. 17

25 5.2.2 Groundwater Flow Through the Site Pre Remediation and Observed Groundwater Conditions The original CSM for the site assumed groundwater flow at the site was predominantly through the WMMCF and the associated lenses of sand and gravel. However, as discussed in Section 3, the lenses of sand and gravel within the WMMCF are relatively small and discontinuous with the WMMCF typically comprising a stiff clay. Site observations during the ongoing remediation have indicated that the majority of groundwater flow on site was through the granular Made Ground, site drainage system and site services result from periods of rainfall. The excavations undertaken for the remediation provide a complete cross section through the top and base of the in-situ WMMCF and there has been negligible flow observed in the excavation walls other than very slight seepages through the discontinuous lenses of sand and gravel. The seepages have generally decreased with time following exposure suggesting very limited recharge from the surrounding marl material as would be expected from a stiff clay. As a result, the excavations including those below the water table have also remained dry (with the exception of rainfall) for the duration of the remedial works so far. The groundwater contours presented in Appendix B represent the pre-remediation site conditions. The impact of the dewatering system in the south of the site can be seen with the presence of a groundwater low and the surrounding groundwater contours indicating groundwater flow towards the dewatering system. It is likely that the artificial lowering of groundwater in this area was driving groundwater flow through the sand and gravel lenses within the WMMCF on site. It is important to note that the sump for the dewatering system is situated adjacent to a sand and gravel lens so that the volume of groundwater removed is higher than may be anticipated if it had been installed in the stiff light grey clay marl material. Therefore, as a result of the groundwater flow induced by the dewatering, the observed flow in the WMMCF prior to remediation is not considered representative of the post remediation conditions. Without the dewatering, groundwater levels in the south of the site would return to natural levels (in the order of 1 m bgl) and the likely groundwater flow rate would be significantly reduced to rates more comparable with the observed low hydraulic conductivity and hydraulic gradient in the surrounding natural WMMCF. 18

26 Comparison of Waste Water Pumping and Rainfall Data Drainage at the site is designed to collect all surface water, including any groundwater that may flow into the excavations. Given the existing ground conditions and ground cover it is anticipated that the majority of rainfall will be collected by the drainage system. Over an 8 month period between September 2010 and April 2011, a total volume of 31,963 m 3 was pumped from the site to the waste water treatment plant (see Appendix C). Based on the average annual rainfall for the area of 586 mm/year and an approximate site area of 8.5 ha, over an 8 month period a total rainfall volume of 33,207 m 3 would be anticipated which is very similar to the volume of water pumped from the site. Recorded rainfall data for Cambridge gave a total rainfall for the same 8 month period of mm, equivalent to m 3 over the site. A significant proportion of the difference between pumped groundwater volume and total rainfall volume (approximately 10,000 m 3 ) is likely to result from the very low rainfall in March and April 2011 (a total of 4.7 mm over both months) and the subsequent use of large volumes of water on site for dust suppression. During this period, approximately 180 m 3 of water a day was used for dust suppression, equivalent to total of approximately 8,100 m 3. Based on the recorded pumped water volumes relative to local rainfall, and making allowance for loss of rainfall as evaporation etc there appears to be only a very low contribution to the pumped water volumes from groundwater ingress into the excavations. Considering the depth of dewatering achieved (approximately 1 m) this suggests that the volume of water present in the natural WMMCF including the sand and gravel lenses and the hydraulic conductivity are generally very low Reinstated Soil Material and Likely Impact on Local Groundwater Regime The reinstated Type B and Type C soil material will have been homogenised during the remediation and compacted. As a result of the sorting and homogenisation of the Type B material, the discontinuous sand and gravel lenses will no longer be present. Additionally, all historic site infrastructure and drainage will have been removed and the limited volume of granular material will be replaced in isolated lenses above the water table. These activities will have removed the majority of previously identified contaminant pathways and reduced the hydraulic conductivity/permeability of the reinstated material relative to the surrounding natural strata. Without the impact of the current dewatering system in the south of the site and based on the observed negligible flow through sides of excavations, groundwater flow through the 19

27 natural strata surrounding the site and therefore through the reinstated soil material is likely to be very low. Although the reinstatement of reduced permeability soil material may locally alter the groundwater regime, given the relatively low hydraulic gradient observed in the surrounding area, and the lack of significant groundwater flow through the natural WMMCF and associated sand and gravel lenses, any changes to groundwater levels in and surrounding the site are not likely to be significant Aquifer Parameters Groundwater Levels Monitoring of groundwater levels before and during remediation indicates that groundwater levels at the site are shallow, with groundwater typically being encountered between 0.8 and 2 m below ground level Hydraulic Gradient The presence of the bentonite cut-off wall and groundwater abstraction on site make accurately determining the post remediation hydraulic gradient and groundwater flow direction across the site very difficult. It should also be noted that the MODFLOW models previously developed by Atkins were based on the original CSM (discussed in Section 5.1) and site investigation data and reflect the ground conditions at the time including the presence of granular Made Ground, drainage channels and assumed flow through the WMMCF. Therefore the modelled groundwater parameters used in previous reports are unlikely to be fully representative of the remediated site conditions. Available Atkins groundwater monitoring data from the adjacent wastewater treatment plant (immediately to the northwest of the site) appears to be outside of the influence of both the bentonite wall and groundwater abstraction. It is therefore considered most representative of the local groundwater conditions and the likely post remediation groundwater conditions on site. The local groundwater flow is in a northeastern direction towards the Riddy Brook and the local hydraulic gradient is typically between and Hydraulic Conductivity and Permeability Testing As the soil material has been largely homogenised as part of the remediation process, the variability within the reinstated compacted soil material and therefore the variability in hydraulic conductivity is likely to be significantly reduced relative to ground conditions prior to remediation. The reinstated soil materials will also be compacted which will further reduce variability. 20

WEST LONDON PIPELINE AND STORAGE LIMITED AND UNITED KINGDOM OIL PIPELINES LIMITED

WEST LONDON PIPELINE AND STORAGE LIMITED AND UNITED KINGDOM OIL PIPELINES LIMITED WEST LONDON PIPELINE AND STORAGE LIMITED AND UNITED KINGDOM OIL PIPELINES LIMITED WLPS BUNCEFIELD REBUILD Flood Risk Assessment Green Lane Hemel Hempstead Hertfordshire HP2 7HZ September 2009 Prepared

More information

U. S. Army Corps of Engineers Ground Water Extraction System Subsurface Performance Checklist

U. S. Army Corps of Engineers Ground Water Extraction System Subsurface Performance Checklist U. S. Army Corps of Engineers Ground Water Extraction System Subsurface Performance Checklist Installation Name Site Name / I.D. Evaluation Team Site Visit Date This checklist is meant to aid in evaluating

More information

Alternate Concentration Limits/Groundwater Cleanup Levels. Title slide

Alternate Concentration Limits/Groundwater Cleanup Levels. Title slide Alternate Concentration Limits/Groundwater Cleanup Levels Title slide 1 Alternate Concentration Limits (ACL) Terms and Definitions 40 CFR 264 Subpart F Definitions Regulated Unit Ground Water Protection

More information

Soil Cleanup Goals. Minnesota Department of Agriculture Pesticide and Fertilizer Management Division. Guidance Document 19

Soil Cleanup Goals. Minnesota Department of Agriculture Pesticide and Fertilizer Management Division. Guidance Document 19 This document is made available electronically by the Minnesota Legislative Reference Library as part of an ongoing digital archiving project. http://www.leg.state.mn.us/lrl/lrl.asp Minnesota Department

More information

Site Assessment for the Proposed Coke Point Dredged Material Containment Facility at Sparrows Point

Site Assessment for the Proposed Coke Point Dredged Material Containment Facility at Sparrows Point Site Assessment for the Proposed Coke Point Dredged Material Containment Facility at Sparrows Point Prepared for Maryland Port Administration 2310 Broening Highway Baltimore, MD 21224 (410) 631-1022 Maryland

More information

State of Rhode Island Department of Environmental Management Division of Site Remediation. Policy Memo 95-01

State of Rhode Island Department of Environmental Management Division of Site Remediation. Policy Memo 95-01 State of Rhode Island Department of Environmental Management Division of Site Remediation Policy Memo 95-01 Guidelines for the Management of Investigation Derived Wastes 1.0 Purpose The purpose of this

More information

Information Request 14

Information Request 14 Information Request 14 Information Request 14 14-1 Responses to Information Request 14 Response to Information Request 14a Response to Information Request 14b Response to Information Request 14c Response

More information

CHAPTER 13 LAND DISPOSAL

CHAPTER 13 LAND DISPOSAL CHAPTER 13 LAND DISPOSAL Supplemental Questions: Which of Shakespeare's plays is the source of the opening quote? The Tempest [1611-1612],Act: I, Scene: i, Line: 70. 13-1. Cite four reasons landfills remain

More information

Lars-Göran Gustafsson, DHI Water and Environment, Box 3287, S-350 53 Växjö, Sweden

Lars-Göran Gustafsson, DHI Water and Environment, Box 3287, S-350 53 Växjö, Sweden Alternative Drainage Schemes for Reduction of Inflow/Infiltration - Prediction and Follow-Up of Effects with the Aid of an Integrated Sewer/Aquifer Model Introduction Lars-Göran Gustafsson, DHI Water and

More information

EARTHWORKS COMPLETION REPORT ELLEN STIRLING PARADE, ELLENBROOK. Ellenbrook, W.A. Georgiou Group Pty Ltd

EARTHWORKS COMPLETION REPORT ELLEN STIRLING PARADE, ELLENBROOK. Ellenbrook, W.A. Georgiou Group Pty Ltd EARTHWORKS COMPLETION REPORT ELLEN STIRLING PARADE, ELLENBROOK Ellenbrook, W.A. Georgiou Group Pty Ltd GEOTPERT08050AZ-AH 27 March 2013 EARTHWORKS COMPLETION REPORT ELLEN STIRLING PARADE, ELLENBROOK Ellenbrook,

More information

Groundwater Flooding: a UK Perspective

Groundwater Flooding: a UK Perspective Groundwater Flooding: a UK Perspective David Macdonald British Geological Survey Maclean Building Crowmarsh Gifford Wallingford OX10 8BB Tel 01491 838800 NERC All rights reserved Talk outline Definition

More information

3. Given the geographic extent of the area, amendments have been made to the following regional planning documents

3. Given the geographic extent of the area, amendments have been made to the following regional planning documents AMENDMENTS TO THE REGIONAL PLANS RELATING TO LAND REPAIR ON EARTHQUAKE DAMAGED RESIDENTIAL LAND UNDER s27 OF THE CANTERBURY EARTHQUAKE RECOVERY ACT 2011 1. This memorandum outlines the specific changes

More information

COST AND PERFORMANCE REPORT

COST AND PERFORMANCE REPORT COST AND PERFORMANCE REPORT Pump and Treat of Contaminated Groundwater at the United Chrome Superfund Site Corvallis, Oregon September 1998 Prepared by: SITE INFORMATION Identifying Information: United

More information

Risk Management Procedure For The Derivation and Use Of Soil Exposure Point Concentrations For Unrestricted Use Determinations

Risk Management Procedure For The Derivation and Use Of Soil Exposure Point Concentrations For Unrestricted Use Determinations Risk Management Procedure For The Derivation and Use Of Soil Exposure Point Concentrations For Unrestricted Use Determinations Hazardous Materials and Waste Management Division (303) 692-3300 First Edition

More information

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska APPENDIX B Geotechnical Engineering Report GEOTECHNICAL ENGINEERING REPORT Preliminary Geotechnical Study Upper Southeast Salt Creek Sanitary Trunk Sewer Lincoln Wastewater System Lincoln, Nebraska PREPARED

More information

Defence College of Technical Training. Former RAF Lyneham Geo-Environmental Report 32655 Appendix D: Preliminary Qualitative Risk Assessment

Defence College of Technical Training. Former RAF Lyneham Geo-Environmental Report 32655 Appendix D: Preliminary Qualitative Risk Assessment Item No. Area/ Building Pathway to 1 Identified areas of / (redevelopment Ingestion Inhalation Severe Likely High SKM Enviros desk study highlights several known areas of significant historical. Areas

More information

WILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10

WILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10 WILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10 SUMMARY 2009-10 The Willochra Basin is situated in the southern Flinders Ranges in the Mid-North of South Australia, approximately 50 km east of Port Augusta

More information

Vital Earth Composting Facility Flood Risk and Drainage Statement

Vital Earth Composting Facility Flood Risk and Drainage Statement Vital Earth Flood Risk and Drainage Statement Final December 2011 Prepared for Vital Earth Ltd Revision Schedule Flood Risk and Drainage Statement December 2011 Rev Date Details Prepared by Reviewed by

More information

Ground Water Surveys and Investigation

Ground Water Surveys and Investigation Ground Water Surveys and Investigation By Gautam Mahajan ASHISH PUBLISHING HOUSE 8/81, PUNJABI BAGH, NEW DELHI-110 026 - Contents Preface List of Abbrivations (v) (vii) 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.7.1

More information

Environmental Remediation Examples and Remediation Strategic Planning

Environmental Remediation Examples and Remediation Strategic Planning Environmental Remediation Examples and Remediation Strategic Planning Yasuo Onishi (yasuo.onishi@pnnl.gov) October 16, 2011 Pacific Northwest National Laboratory, and Washington State University, Civil

More information

1.2 This technical note provides a preliminary investigation into the Flood Risk and provides outline drainage strategies.

1.2 This technical note provides a preliminary investigation into the Flood Risk and provides outline drainage strategies. ODYSSEY MARKIDES TECHNICAL NOTE PROJECT : CHAILEY HOUSE, BLEWBURY JOB NO. : 14-216 NOTE TITLE : PRELIMINARY FLOODING AND DRAIANGE AUTHOR : STEVEN ROOTH APPROVED : ANDREAS MARKIDES DATE : 02/09/2014 1.0

More information

Groundwater Training Course SOPAC, April 2005. Electromagnetic (EM) Induction method for Groundwater Investigations

Groundwater Training Course SOPAC, April 2005. Electromagnetic (EM) Induction method for Groundwater Investigations Groundwater Training Course SOPAC, April 2005 Electromagnetic (EM) Induction method for Groundwater Investigations Electromagnetic (EM) Induction Method Basic principle: An AC electric current is applied

More information

Inventory of Performance Monitoring Tools for Subsurface Monitoring of Radionuclide Contamination

Inventory of Performance Monitoring Tools for Subsurface Monitoring of Radionuclide Contamination Inventory of Performance Monitoring Tools for Subsurface Monitoring of Radionuclide Contamination H. Keith Moo-Young, Professor, Villanova University Ronald Wilhelm, Senior Scientist, U.S. EPA, Office

More information

Guidelines For Sealing Groundwater Wells

Guidelines For Sealing Groundwater Wells Guidelines For Sealing Groundwater Wells Government of Newfoundland and Labrador Department of Environment and Conservation Water Resources Management Division Government of Newfoundland and Labrador Department

More information

STATE OF TENNESSEE DEPARTMENT OF ENVIRONMENT AND CONSERVATION DIVISION OF UNDERGROUND STORAGE TANKS TECHNICAL GUIDANCE DOCUMENT - 008

STATE OF TENNESSEE DEPARTMENT OF ENVIRONMENT AND CONSERVATION DIVISION OF UNDERGROUND STORAGE TANKS TECHNICAL GUIDANCE DOCUMENT - 008 STATE OF TENNESSEE DEPARTMENT OF ENVIRONMENT AND CONSERVATION DIVISION OF UNDERGROUND STORAGE TANKS TECHNICAL GUIDANCE DOCUMENT - 008 Effective Date - January 13, 1992 Revised Date - November 19, 1993

More information

1.72, Groundwater Hydrology Prof. Charles Harvey Lecture Packet #2: Aquifers, Porosity, and Darcy s Law. Lake (Exposed Water Table)

1.72, Groundwater Hydrology Prof. Charles Harvey Lecture Packet #2: Aquifers, Porosity, and Darcy s Law. Lake (Exposed Water Table) 1.72, Groundwater Hydrology Prof. Charles Harvey Lecture Packet #2: Aquifers, Porosity, and Darcy s Law Precipitation Infiltration Lake (Exposed Water Table) River Water table Saturated zone - Aquifer

More information

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT 1.0 SOIL IMPROVEMENT 1.1 General Soil Investigation Information are provided in Part B1 annex as a guide to the Contractor for his consideration

More information

Evaluation of Site-Specific Criteria for Determining Potability

Evaluation of Site-Specific Criteria for Determining Potability Evaluation of Site-Specific Criteria for Determining Potability and Cleanup Goals for Impacted Groundwater This paper presents considerations used to evaluate site-specific criteria for determining groundwater

More information

Review of Groundwater Vulnerability Assessment Methods Unsaturated Zone. Dept. of Earth Sciences University of the Western Cape

Review of Groundwater Vulnerability Assessment Methods Unsaturated Zone. Dept. of Earth Sciences University of the Western Cape Review of Groundwater Vulnerability Assessment Methods Unsaturated Zone Dept. of Earth Sciences University of the Western Cape Background Sililo et al. (2001) Groundwater contamination depends on: Intrinsic

More information

Matt Harris, Golder Associates (NZ) Ltd. The value of geophysics as a non-intrusive method for site characterisation

Matt Harris, Golder Associates (NZ) Ltd. The value of geophysics as a non-intrusive method for site characterisation Matt Harris, Golder Associates (NZ) Ltd. The value of geophysics as a non-intrusive method for site characterisation Presentation Outline What is geophysics and how can it help me? Electrical Resistivity

More information

9.00 THE USE OF HUNTER LAND DRAINAGE PERFORATED PIPES. Hunter Underground Systems

9.00 THE USE OF HUNTER LAND DRAINAGE PERFORATED PIPES. Hunter Underground Systems 9.00 THE USE OF HUNTER LAND DRAINAGE PERFORATED PIPES Hunter Underground Systems 9.01 General 9.02 Surface water Drainage 9.03 Groundwater Drainage 9.04 Dispersal of Septic Tank Effluent 9.01 The use of

More information

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No. 2009-8M (Supersedes Report No.

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No. 2009-8M (Supersedes Report No. GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES Materials Engineering Report No. 2009-8M (Supersedes Report No. 21) F CHOWDHURY GEOMECHANICS AND STRUCTURAL MATERIALS ENGINEER S REHMAN GEOTECHNICAL

More information

GROUNDWATER INVESTIGATION IN SITE ASSESSMENT. Technical Guidance for Contaminated Sites

GROUNDWATER INVESTIGATION IN SITE ASSESSMENT. Technical Guidance for Contaminated Sites GROUNDWATER INVESTIGATION IN SITE ASSESSMENT Technical Guidance for Contaminated Sites Submitted to: Land Remediation Section 10470 152nd Street Surrey, BC, Canada V3R 0Y3 REPORT Report Number: 07-1412-0162

More information

1.34 WASTE CONTAINMENT AND SITE REMEDIATION TECHNOLOGY TAKE-HOME FINAL EXAM DUE FRIDAY MAY 7, 2004 AT 9:30 AM

1.34 WASTE CONTAINMENT AND SITE REMEDIATION TECHNOLOGY TAKE-HOME FINAL EXAM DUE FRIDAY MAY 7, 2004 AT 9:30 AM 1.34 WASTE CONTAINMENT AND SITE REMEDIATION TECHNOLOGY TAKE-HOME FINAL EXAM DUE FRIDAY MAY 7, 2004 AT 9:30 AM This is an open-book exam, but the work should be yours alone. Please do not work with others

More information

Appendix C - Risk Assessment: Technical Details. Appendix C - Risk Assessment: Technical Details

Appendix C - Risk Assessment: Technical Details. Appendix C - Risk Assessment: Technical Details Appendix C - Risk Assessment: Technical Details Page C1 C1 Surface Water Modelling 1. Introduction 1.1 BACKGROUND URS Scott Wilson has constructed 13 TUFLOW hydraulic models across the London Boroughs

More information

Proposed Construction of Basement Flood Risk Assessment. 35 Edwardes Square London W8 6HH

Proposed Construction of Basement Flood Risk Assessment. 35 Edwardes Square London W8 6HH Proposed Construction of Basement Flood Risk Assessment 35 Edwardes Square London W8 6HH 1 Introduction This FRA has been carried out in accordance with the National Planning Policy Statement (NPPF), the

More information

Queenborough Bar Mill, Rushenden Road, Queenborough, Kent, ME11 5HS.

Queenborough Bar Mill, Rushenden Road, Queenborough, Kent, ME11 5HS. Application SCR evaluation template Name of activity, address and NGR Invicta Merchant Bar Limited. Queenborough Bar Mill, Rushenden Road, Queenborough, Kent, ME11 5HS. National Grid Reference (NGR) of

More information

PREDICTIVE MODELLING AND MONITORING NATURAL ATTENUATION TO SAVE REMEDIAL COSTS

PREDICTIVE MODELLING AND MONITORING NATURAL ATTENUATION TO SAVE REMEDIAL COSTS PREDICTIVE MODELLING AND MONITORING NATURAL ATTENUATION TO SAVE REMEDIAL COSTS A.Aziz Shaikh, Brian Tsang, Greg Sutor and Thomas Dance Abstract This paper describes the multidisciplinary components of

More information

SOIL GAS MODELLING SENSITIVITY ANALYSIS USING DIMENSIONLESS PARAMETERS FOR J&E EQUATION

SOIL GAS MODELLING SENSITIVITY ANALYSIS USING DIMENSIONLESS PARAMETERS FOR J&E EQUATION 1 SOIL GAS MODELLING SENSITIVITY ANALYSIS USING DIMENSIONLESS PARAMETERS FOR J&E EQUATION Introduction Chris Bailey, Tonkin & Taylor Ltd, PO Box 5271, Wellesley Street, Auckland 1036 Phone (64-9)355-6005

More information

FINAL PLAN OF REMEDIAL ACTION

FINAL PLAN OF REMEDIAL ACTION FINAL PLAN OF REMEDIAL ACTION 1000 FRENCH STREET SITE Wilmington, Delaware DE 1115 June 1999 Department of Natural Resources and Environmental Control Division of Air and Waste Management Site Investigation

More information

Hydrogeological Desk Study Appraisal

Hydrogeological Desk Study Appraisal Site Reference Client Name Hydrogeological Desk Study Appraisal Application for the Development of Houghton Main Renewable Energy Park (REP) comprising a Timber Resource Recovery Centre and an Anaerobic

More information

3D-Groundwater Modeling with PMWIN

3D-Groundwater Modeling with PMWIN Wen-Hsing Chiang 3D-Groundwater Modeling with PMWIN A Simulation System for Modeling Groundwater Flow and Transport Processes Second Edition With 242 Figures and 23 Tables 4y Springer Contents 1 Introduction

More information

Utilizing an Innovative, Effective Site Assessment and Monitoring Tool

Utilizing an Innovative, Effective Site Assessment and Monitoring Tool Utilizing an Innovative, Effective Site Assessment and Monitoring Tool Jay W. Hodny, Ph.D. W. L. Gore & Associates, Inc., Elkton, MD, USA Laurie LaPlante, P.E. Kleinfelder, Inc., Salt Lake City, UT, USA

More information

Alberta Tier 2 Soil and Groundwater Remediation Guidelines

Alberta Tier 2 Soil and Groundwater Remediation Guidelines Alberta Tier 2 Soil and Groundwater Remediation Guidelines May 21, 2014 ALBERTA TIER 2 SOIL AND GROUNDWATER REMEDIATION GUIDELINES 2014 and updates Final Draft May 21, 2014 ISBN: 978-1-4601-1701-9 (Printed

More information

(http://www.molevalley.gov.uk/media/pdf/c/r/srfa_-_updated_jnauary_2012.pdf

(http://www.molevalley.gov.uk/media/pdf/c/r/srfa_-_updated_jnauary_2012.pdf Possible Submission about Water and Flooding (See maps 3a and 3b) From Mole Valley Local Development Framework: Strategic Flood Risk Assessment Update 2012 (http://www.molevalley.gov.uk/media/pdf/c/r/srfa_-_updated_jnauary_2012.pdf

More information

GUIDANCE DOCUMENT FOR DEVELOPMENTS AND SUBDIVISIONS WHERE ONSITE WASTEWATER TREATMENT SYSTEMS ARE PROPOSED

GUIDANCE DOCUMENT FOR DEVELOPMENTS AND SUBDIVISIONS WHERE ONSITE WASTEWATER TREATMENT SYSTEMS ARE PROPOSED February 2012 July 2012 GUIDANCE DOCUMENT FOR DEVELOPMENTS AND SUBDIVISIONS WHERE ONSITE WASTEWATER TREATMENT SYSTEMS ARE PROPOSED i Table of Contents List of Tables...iii List of Figures...iii 1 Introduction...

More information

Emergency Spillways (Sediment basins)

Emergency Spillways (Sediment basins) Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]

More information

CIVL451. Soil Exploration and Characterization

CIVL451. Soil Exploration and Characterization CIVL451 Soil Exploration and Characterization 1 Definition The process of determining the layers of natural soil deposits that will underlie a proposed structure and their physical properties is generally

More information

Case Study 3 Conservation Chemical Company, Kansas City, Missouri, EPA Region 7

Case Study 3 Conservation Chemical Company, Kansas City, Missouri, EPA Region 7 29 technologies. The large amount of waste at the site poses a difficult problem for which some innovative cleanup technologies, including in situ techniques to avoid excavation, could have been considered

More information

FLOOD RISK AND SURFACE WATER DRAINAGE ASSESSMENT HILLHOUSE RESTORATION SITE, OFF JAMESON ROAD, THORNTON CLEVELEYS ON BEHALF OF NPL ESTATES

FLOOD RISK AND SURFACE WATER DRAINAGE ASSESSMENT HILLHOUSE RESTORATION SITE, OFF JAMESON ROAD, THORNTON CLEVELEYS ON BEHALF OF NPL ESTATES FLOOD RISK AND SURFACE WATER DRAINAGE ASSESSMENT HILLHOUSE RESTORATION SITE, OFF JAMESON ROAD, THORNTON CLEVELEYS ON BEHALF OF NPL ESTATES Integra Consulting Engineers Limited NS / 2543 Fountain House

More information

Chippenham Surface Water Management Plan Intermediate Assessment of Groundwater Flooding Susceptibility

Chippenham Surface Water Management Plan Intermediate Assessment of Groundwater Flooding Susceptibility Chippenham Surface Water Management Plan Intermediate Assessment of Groundwater Flooding Susceptibility Phase 1 & 2 November 2011 Prepared for Revision Schedule Surface Water Management Plan Intermediate

More information

DRAINAGE MANAGEMENT PLAN. HERTFORDSHIRE RESIDUAL WASTE TREATMENT PLANT Hertfordshire County Council

DRAINAGE MANAGEMENT PLAN. HERTFORDSHIRE RESIDUAL WASTE TREATMENT PLANT Hertfordshire County Council DRAINAGE MANAGEMENT PLAN HERTFORDSHIRE RESIDUAL WASTE TREATMENT PLANT Hertfordshire County Council EMPLOYER: Veolia Environmental Services (UK) Plc Veolia House 154A Pentonville Road London N1 9PE Copy

More information

FINAL GUIDANCE FOR CONDUCTING BENEFICIAL WATER USE DETERMINATIONS AT ENVIRONMENTAL CLEANUP SITES

FINAL GUIDANCE FOR CONDUCTING BENEFICIAL WATER USE DETERMINATIONS AT ENVIRONMENTAL CLEANUP SITES FINAL GUIDANCE FOR CONDUCTING BENEFICIAL WATER USE DETERMINATIONS AT ENVIRONMENTAL CLEANUP SITES Oregon Department of Environmental Quality Waste Management and Cleanup Division 811 SW Sixth Avenue Portland,

More information

DRAFT. GROUNDWATER REMEDY COMPLETION STRATEGY: Moving Forward with Completion in Mind

DRAFT. GROUNDWATER REMEDY COMPLETION STRATEGY: Moving Forward with Completion in Mind GROUNDWATER REMEDY COMPLETION STRATEGY: Moving Forward with Completion in Mind Table of Contents 1. Introduction...2 1.1 Purpose and Scope...2 1.2 Background...3 2. Elements of a Groundwater Remedy Completion

More information

The tools will also help to predict the impacts of the options on groundwater within the many ecologically sensitive sites in the floodplain.

The tools will also help to predict the impacts of the options on groundwater within the many ecologically sensitive sites in the floodplain. INVESTIGATING THE INTERDEPENDENCIES BETWEEN SURFACE AND GROUNDWATER IN THE OXFORD AREA TO HELP PREDICT THE TIMING AND LOCATION OF GROUNDWATER FLOODING AND TO OPTIMISE FLOOD MITIGATION MEASURES David Macdonald,

More information

Liquid Effluent Treatment Plant (LETP) Land Clean-Up

Liquid Effluent Treatment Plant (LETP) Land Clean-Up Liquid Effluent Treatment Plant (LETP) Land Clean-Up Frequently Asked Questions What is proposed? Magnox Ltd is proposing to remove the redundant Liquid Effluent Treatment Plant (LETP) at Harwell and to

More information

GEOLOGY, GROUNDWATER AND LAND CONTAMINATION MANAGEMENT PLAN

GEOLOGY, GROUNDWATER AND LAND CONTAMINATION MANAGEMENT PLAN Intended for FORTH CROSSING BRIDGE CONTRUCTORS () Document type Report (REP) Date 5/3/13 FORTH REPLACEMENT CROSSING GEOLOGY, GROUNDWATER AND LAND CONTAMINATION MANAGEMENT PLAN FORTH REPLACEMENT CROSSING

More information

Asbestos Disposal in the Northern Territory

Asbestos Disposal in the Northern Territory Information on the requirements for the disposal of Asbestos in the Northern Territory Scope These guidance notes have been developed to assist industry, local government, consultants and other relevant

More information

Environmental Guidelines for Preparation of an Environmental Management Plan

Environmental Guidelines for Preparation of an Environmental Management Plan 2013 Environmental Guidelines for Preparation of an Environmental Management Plan Environmental Management Division Environmental Protection Agency 3/13/2013 ENVIRONMENTAL GUIDELINES FOR PREPARATION OF

More information

Frequently Asked Questions on the Alberta Tier 1 and Tier 2 Soil and Groundwater Remediation Guidelines. February 2008

Frequently Asked Questions on the Alberta Tier 1 and Tier 2 Soil and Groundwater Remediation Guidelines. February 2008 Frequently Asked Questions on the Alberta Tier 1 and Tier 2 Soil and Groundwater Remediation Guidelines February 2008 Frequently Asked Questions on the Alberta Tier 1 and Tier 2 Soil and Groundwater Remediation

More information

COMPREHENSIVE PLAN SECTION B, ELEMENT 4 WATER RESOURCES. April 20, 2010 EXHIBIT 1

COMPREHENSIVE PLAN SECTION B, ELEMENT 4 WATER RESOURCES. April 20, 2010 EXHIBIT 1 COMPREHENSIVE PLAN SECTION B, ELEMENT 4 WATER RESOURCES April 20, 2010 EXHIBIT 1 ELEMENT 4 WATER RESOURCES TABLE OF CONTENTS 4.1 INTRODUCTION 4.2 GOALS AND POLICIES 4.2.A General Goals and Policies 1 4.2.B

More information

Trevor Lloyd Director

Trevor Lloyd Director Trevor Lloyd Director Qualifications Environmental Toxicology and Health Risk Assessment Course - Qld Centre for Public Health (1998) Quality Assurance Auditing Training Course - Bywater plc (1994) University

More information

SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT RESOURCE REGULATION TRAINING MEMORANDUM

SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT RESOURCE REGULATION TRAINING MEMORANDUM SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT RESOURCE REGULATION TRAINING MEMORANDUM DATE: December 04, 1996 This document is subject to change. If in doubt, verify current status with Technical Services

More information

SUCCESSFUL FIELD-SCALE IN SITU THERMAL NAPL REMEDIATION AT THE YOUNG-RAINEY STAR CENTER

SUCCESSFUL FIELD-SCALE IN SITU THERMAL NAPL REMEDIATION AT THE YOUNG-RAINEY STAR CENTER Paper 2B-01, in: A.R. Gavaskar and A.S.C. Chen (Eds.), Remediation of Chlorinated and Recalcitrant Compounds 2004. Proceedings of the Fourth International Conference on Remediation of Chlorinated and Recalcitrant

More information

NUMERICAL ANALYSIS OF SEEPAGE THROUGH EMBANKMENT DAMS (CASE STUDY: KOCHARY DAM, GOLPAYEGAN)

NUMERICAL ANALYSIS OF SEEPAGE THROUGH EMBANKMENT DAMS (CASE STUDY: KOCHARY DAM, GOLPAYEGAN) NUMERICAL ANALYSIS OF SEEPAGE THROUGH EMBANKMENT DAMS (CASE STUDY: KOCHARY DAM, GOLPAYEGAN) *Reza Naghmehkhan Dahande 1 and Ahmad Taheri 2 1 Department of Civil Engineering-Water Management, Islamic Azad

More information

How To Map A Lake In The North Of The Holland (Fiji)

How To Map A Lake In The North Of The Holland (Fiji) 1. Hydrogelogical mapping Jiri Sima Aim of HG map Groundwater and rocks qualitative permeability and quantitative potential of rock units aquifers / aquitards / aquiclides Water points (spatial distribution

More information

National Planning Policy for Waste

National Planning Policy for Waste National Planning Policy for Waste October 2014 Department for Communities and Local Government Crown copyright, 2014 Copyright in the typographical arrangement rests with the Crown. You may re-use this

More information

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Brussels, 18-20 February 2008 Dissemination of information workshop 1 Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Dr.-Ing. Bernd Schuppener, Federal Waterways Engineering

More information

Vulnerability Assessment

Vulnerability Assessment Vulnerability Assessment VULNERABILITY As used in this report, vulnerability refers to the sensitivity of groundwater to contamination, and is determined by intrinsic characteristics of the aquifer. It

More information

Proposed Terms of Reference for EIA studies

Proposed Terms of Reference for EIA studies 1 Proposed Terms of Reference for EIA studies Base line data collection will be collected for the Post-Monsoon season 2016 (September to November 2016) in study area and 10 kms radius from project site.

More information

GUIDELINES FOR SOIL FILTER MEDIA IN BIORETENTION SYSTEMS (Version 2.01) March 2008

GUIDELINES FOR SOIL FILTER MEDIA IN BIORETENTION SYSTEMS (Version 2.01) March 2008 GUIDELINES FOR SOIL FILTER MEDIA IN BIORETENTION SYSTEMS (Version 2.01) March 2008 The following guidelines for soil filter media in bioretention systems have been prepared on behalf of the Facility for

More information

Use of Alternate Concentration Limits (ACLs) to Determine Cleanup or Regulatory Levels Under RCRA and CERCLA

Use of Alternate Concentration Limits (ACLs) to Determine Cleanup or Regulatory Levels Under RCRA and CERCLA U.S. Department of Energy Office of Environmental Policy and Assistance ACL Information Brief DOE/EH-413-9912 (December 1999) DEPARTMENT OF ENERGY UN ITED STATES OF AMERICA Use of Alternate Concentration

More information

V. ENVIRONMENTAL IMPACT ANALYSIS E. Hazardous Materials

V. ENVIRONMENTAL IMPACT ANALYSIS E. Hazardous Materials E. HAZARDOUS MATERIALS An Environmental Site Assessment Phase I Update was performed on the subject properties by California Environmental Inc. in March 2000 1. This report is included in Appendix E of

More information

4. Environmental Impacts Assessment and Remediation Targets

4. Environmental Impacts Assessment and Remediation Targets 4. Environmental Impacts Assessment and Remediation Targets 4.1 Environmental Impacts Significant additional development in the Alder Creek watershed is not anticipated at this time; however, there are

More information

720 Contour Grading. General. References. Resources. Definitions

720 Contour Grading. General. References. Resources. Definitions 720 Contour Grading General Contour grading directs water to a desired point, prevents erosion, provides noise deflection, provides visual fit of the facility into the landscape, and protects desirable

More information

STATE OF VERMONT AGENCY OF NATURAL RESOURCES DEPARTMENT OF ENVIRONMENTAL CONSERVATION WASTE MANAGEMENT DIVISION SOLID WASTE MANAGEMENT PROGRAM

STATE OF VERMONT AGENCY OF NATURAL RESOURCES DEPARTMENT OF ENVIRONMENTAL CONSERVATION WASTE MANAGEMENT DIVISION SOLID WASTE MANAGEMENT PROGRAM STATE OF VERMONT AGENCY OF NATURAL RESOURCES DEPARTMENT OF ENVIRONMENTAL CONSERVATION WASTE MANAGEMENT DIVISION SOLID WASTE MANAGEMENT PROGRAM Solid Waste Management Program Waste Management Division 103

More information

Catchment Scale Processes and River Restoration. Dr Jenny Mant Jenny@therrc.co.uk. The River Restoration Centre therrc.co.uk

Catchment Scale Processes and River Restoration. Dr Jenny Mant Jenny@therrc.co.uk. The River Restoration Centre therrc.co.uk Catchment Scale Processes and River Restoration Dr Jenny Mant Jenny@therrc.co.uk The River Restoration Centre therrc.co.uk 3 Main Catchment Elements Hydrology Energy associated with the flow of water affects

More information

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development 7 SPECIFICATIONS There is currently no Irish specification for construction of drainage works, or water supply works. There are several publications that give guidance on drainage works, such as the Building

More information

UNDER DRAINAGE AND FILTER DESIGN

UNDER DRAINAGE AND FILTER DESIGN UNDER DRAINAGE AND FILTER DESIGN Tailings and HLP Workshop 28 April to 1 May 2010 INTRODUCTION The internal drainage is of crucial importance to the reliability and safety of a tailings dam throughout

More information

ALL GROUND-WATER HYDROLOGY WORK IS MODELING. A Model is a representation of a system.

ALL GROUND-WATER HYDROLOGY WORK IS MODELING. A Model is a representation of a system. ALL GROUND-WATER HYDROLOGY WORK IS MODELING A Model is a representation of a system. Modeling begins when one formulates a concept of a hydrologic system, continues with application of, for example, Darcy's

More information

Well gauging results LNAPL in Benzol Processing Area

Well gauging results LNAPL in Benzol Processing Area Well gauging results LNAPL in Benzol Processing Area 3.59 ft 0.62 ft 4.64 ft Context Scope & Methods Onshore Results Offshore Results Summary & Conclusions 13 Page 1 of 4 Underground Storage Tanks Last

More information

Flash Flood Science. Chapter 2. What Is in This Chapter? Flash Flood Processes

Flash Flood Science. Chapter 2. What Is in This Chapter? Flash Flood Processes Chapter 2 Flash Flood Science A flash flood is generally defined as a rapid onset flood of short duration with a relatively high peak discharge (World Meteorological Organization). The American Meteorological

More information

ALBERTA TIER 2 SOIL AND GROUNDWATER REMEDIATION GUIDELINES

ALBERTA TIER 2 SOIL AND GROUNDWATER REMEDIATION GUIDELINES ALBERTA TIER 2 SOIL AND GROUNDWATER REMEDIATION GUIDELINES December 2010 ALBERTA TIER 2 SOIL AND GROUNDWATER REMEDIATION GUIDELINES Alberta Environment December 2010 ISBN: 978-0-7785-9948-7 (Printed Edition)

More information

Could your house sale or purchase be affected by Contaminated Land?

Could your house sale or purchase be affected by Contaminated Land? Could your house sale or purchase be affected by Contaminated Land? What is Contaminated Land? The legal definition of Contaminated Land, as provided by Part IIA of the Environmental Protection Act 1990,

More information

Case Study: Habitat Restoration

Case Study: Habitat Restoration Case Study: Habitat Restoration RCRA Corrective Action Site Oil Refinery E-Pond SWMU Lima, Ohio B-1 Introduction: In January 2001, the U.S. EPA issued additional RCRA Cleanup Reforms to accelerate the

More information

On Site Sewage System Maintenance Inspections. March 2011. Building and Development Branch Ministry of Municipal Affairs and Housing

On Site Sewage System Maintenance Inspections. March 2011. Building and Development Branch Ministry of Municipal Affairs and Housing On Site Sewage System Maintenance Inspections March 2011 Building and Development Branch Ministry of Municipal Affairs and Housing Introduction The Building Code Act, 1992 and Building Code (Ontario Regulation

More information

Chapter 9: Water, Hydrology and Drainage Land West of Uttoxeter

Chapter 9: Water, Hydrology and Drainage Land West of Uttoxeter Chapter 9: Water, Hydrology and Drainage Land West of Uttoxeter ENVIRONMENTAL STATEMENT: VOLUME 1 9.1 INTRODUCTION 9.1.1 This Chapter considers the effects of the Project on surface water and groundwater

More information

NuGeneration Ltd Site Investigations

NuGeneration Ltd Site Investigations NuGeneration Ltd Site Investigations Introducing the site assessment and radiological characterisation project NuGen has commissioned an engineering consortium - which is a joint venture of IBERDROLA Ingeniería

More information

Preliminary Assessment

Preliminary Assessment Preliminary Assessment Bonebrake Theological Seminary Site Dayton Unit III Dayton, Ohio Prepared by: U.S. Army Corps of Engineers Buffalo District 1776 Niagara Street Buffalo, NY 14207-3199 September 5,

More information

REPORT. Earthquake Commission. Christchurch Earthquake Recovery Geotechnical Factual Report Merivale

REPORT. Earthquake Commission. Christchurch Earthquake Recovery Geotechnical Factual Report Merivale REPORT Earthquake Commission Christchurch Earthquake Recovery Geotechnical Factual Report Merivale REPORT Earthquake Commission Christchurch Earthquake Recovery Geotechnical Factual Report Merivale Report

More information

ENVIRONMENTAL STATEMENT: VOLUME 2 APPENDICES 11.1 TO 11.3

ENVIRONMENTAL STATEMENT: VOLUME 2 APPENDICES 11.1 TO 11.3 NORTH LONDON WASTE AUTHORITY NORTH LONDON HEAT AND POWER PROJECT ENVIRONMENTAL STATEMENT: VOLUME 2 APPENDICES 11.1 TO 11.3 AD06.02 NORTH LONDON WASTE AUTHORITY NORTH LONDON HEAT AND POWER PROJECT ENVIRONMENTAL

More information

Assessment. Ian Uglow Technical Director, SLR Consulting iuglow@slrconsulting.com. 7 th October 2010

Assessment. Ian Uglow Technical Director, SLR Consulting iuglow@slrconsulting.com. 7 th October 2010 Peat Stability Risk and Hazard Assessment Ian Uglow Technical Director, SLR Consulting iuglow@slrconsulting.com 7 th October 2010 What goes into a Peat Stability Risk Assessment? You will need: An understanding

More information

Sutton Harbour Holdings PLC. March 2007

Sutton Harbour Holdings PLC. March 2007 Sutton Harbour Holdings PLC March 2007 Contents!! " # # $ % % &'(&'' ) ) ( * + ', *!$ -,!'! #. / $$ #% 00& ' 00&1 $ Executive Summary!! " WSP Development and Transportation has been engaged by Sutton

More information

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:! In-situ Testing! Insitu Testing! Insitu testing is used for two reasons:! To allow the determination of shear strength or penetration resistance or permeability of soils that would be difficult or impossible

More information

A Federal Approach to Contaminated Sites

A Federal Approach to Contaminated Sites Government Gouvernement of Canada du Canada By: Dillon Consulting Limited Ottawa, Ontario November 1999 A Publication of the CSMWG Printed November 2000 The (CSMWG) established under the auspices of the

More information

FREQUENTLY ASKED QUESTIONS. New Subsurface Sewage Treatment System (SSTS) Ordinance

FREQUENTLY ASKED QUESTIONS. New Subsurface Sewage Treatment System (SSTS) Ordinance FREQUENTLY ASKED QUESTIONS New Subsurface Sewage Treatment System (SSTS) Ordinance General SSTS and Ordinance Questions: 1. How do SSTS treat wastewater? The best website to review SSTS system components

More information

APPENDIX G SETTLEMENT

APPENDIX G SETTLEMENT APPENDIX G SETTLEMENT TABLE OF CONTENTS G.1 IN T R O D U C T IO N... 1 G.2 MATERIAL PLACEMENT AND COMPACTION... 1 G.2.1 Incom pressible M aterials... 1 G.2.2 Compressible Materials... 2 G.2.3 Soil P lacem

More information

Works Approval Conditions 1 General

Works Approval Conditions 1 General Works Approval Conditions 1 General 1.1 Interpretation 1.1.1 In the Works Approval, definitions from the Environmental Protection Act 1986 apply unless the contrary intention appears. 1.1.2 In the Works

More information

6 Chemicals from human settlements

6 Chemicals from human settlements 6 Chemicals from human settlements 6.1 Introduction The world is becoming increasingly urban, particularly in developing countries. The transition of people from rural areas to cities represents a major,

More information