Subcontractor Involvement Project Tracking Progress Curves. CSTM 462 Fall 2012



Similar documents
Resource Planning and Scheduling. CSTM 462 Resource Loading Fall 2012

Estimating Activity Durations CSTM 462

SCHEDULE AND BUDGETING

1.040 Project Management

SECTION COST LOADED CRITICAL PATH SCHEDULE

Spec. Standard: 11/27/ Revision: 11/27/06

SECTION PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

Contract / Construction Management. November 2006

PROJECT CONTROL PROCEDURE (PROJECT STANDARDS AND SPECIFICATIONS)

CONSTRUCTION CONTRACT TERMINOLOGY

EXHIBIT 2-2-C PROGRESS SCHEDULES

LONG INTERNATIONAL. Long International, Inc Whistling Elk Drive Littleton, CO (303) Fax: (303)

ATTACHMENT 1: CONTRACTOR PAST PERFORMANCE REPORT CONSULTING SERVICES Note: Continuation sheets may be used if more space is required.

Should I Resource Load My Schedule?

LONG INTERNATIONAL. Long International, Inc Whistling Elk Drive Littleton, CO (303) Fax: (303)

Factors Affecting Progress Payments in Oil and Gas Industry Projects: Progress Measurement Method and Project Cash Flow

LECTURE 10. Resource Allocation and Resource Leveling

Cash flow is the life line of a business. Many start-up

// Benchmarking Project Schedules

How to Plan, Design & Implement A Bad Schedule Lessons Learned: The Scheduler as Generalist

CHAPTER 8 PROJECT TIME-COST TRADE-OFF

Project Time Management an essential element to project success

Productivity: Measurement, Improvement and its Role in Mitigating the Risks of Dispute in Construction Projects

Planning & Scheduling CSTM 462. Managing a project through time and resources. The need for proper planning and scheduling.

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule

Considerations. Change your viewpoint. Understand and pursue The Primary Metrics

Scheduling 101 CPM Basics. Phoenix Project Management Systems, LLC

King Fahd University of Petroleum and Minerals

Project Management Using Earned Value

This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.

UNIFIED FACILITIES GUIDE SPECIFICATIONS

Pricing Your Work (Overhead Recovery Review)

Panama Canal - Third Set of Locks Expansion Project Project Controls in a multi-cultural environment

A Framework for Project Metrics

JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013

Accounting System. Page 1 of 9

Construction Surety Bonds

For illustrative purposes only, we will look at the logical flow of the Data Pro Job Cost package as a general contractor might use it.

MODEL SCHEDULING SPECIFICATION

Developing Critical Path Method Scheduling (CPM)

Pre Construction Services

SCHEDULING AND PROJECT MANAGEMENT

Practical Aspects of Construction Scheduling

SOUTH FLORIDA WATER MANAGEMENT DISTRICT CONTRACTOR CPM SCHEDULE SUBMITTAL - DISTRICT REVIEW General Contractor CPM Schedule

NE-50413B Mastering Microsoft Project 2010

MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software.

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016

SE351a: Software Project & Process Management

RFQ NORTHSTAR AUDITING SERVICES ADDENDUM NO. 1 REF. LOCATION DESCRIPTION OF CHANGE. Revised Scope of Work. Work tasks have been revised.

Activity Schedules in the NEC3 Engineering and Construction Contract

How to best position your construction company to a surety in 2013

Baseline Schedule Metrics. Donald R. McNatty, PSP FAACE November 18, 2015

Enterprise Resource Planning. Dr. Chawalit Jeenanunta

Scheduling Best Practices

300 Scheduling and Budgeting

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Business Success through Excellence in Project Management (Better, Cheaper, Faster and Safer Projects)

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.

How project management software can smooth the way

SYLLABUS 12/14/2012 CONE 425 Construction Planning, Scheduling, & Control Spring, 2013 Rev. 0. Syllabus Spring, 2013

CHAPTER 6 PROJECT CASH FLOW

Alexandria National Cemetery SECTION NETWORK ANALYSIS SCHEDULE

Step by Step Project Planning

PS.12. 4D Scheduling A Case Study

Implementing a Purchase Order System

Construction Economics & Finance. Module 6. Lecture-1

Assistant Project Management - Training Program A 3-year Program Beginning strategy places the new employee into a three-year program that provides

Review of Schedule Specification Requirements District SAP/WBS breakdown Asset template Cost & Resource Loading Stored Material Costs

The Past and Future of CPM Project Scheduling. Dr. Dan Patterson PMP Pertmaster, Acumen, PMFocus Founder

Programmes. Unit 3: P lanning construction work processes and efficient use of resources in construction and the built environment.

CPM-200: Principles of Schedule Management

SECTION CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS

PROJECT COST MANAGEMENT

Design Consultant Project Management Requirements

SECTION a - CONSTRUCTION PROGRESS DOCUMENTATION

Linear Schedules for Tunnel Projects

PN /16/ CRITICAL PATH METHOD PROGRESS SCHEDULE

No. 6: Purchase Orders / Subcontract Management - A Line Drive! BY MIKE ODE

How to successfully manage your mega-project

Prof. A. Ray Chaudhuri Department of Civil Engineering Adama Science and Technology University (ASTU), Adama, Ethiopia. I.D:

ITEM DOCUMENT CONTROL MANAGEMENT DESCRIPTION:

U.S. Department of Veterans Affairs. Facilities Management. Critical Path Method. Guidelines for Preparation of CPM Schedule Volume I

QUESTIONS & ANSWERS LOG

Mastering Microsoft Project 2013

Construction Project Scheduling

Project Time Management

Scheduling Glossary Activity. A component of work performed during the course of a project.

Project Time Management

Vendor Managed Services: Question and Answer

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False

Transcription:

Subcontractor Involvement Project Tracking Progress Curves CSTM 462 Fall 2012

Subcontractor Involvement into the Critical Path Many building contractors get very little input into the schedule from their subcontractors. Difficult to get the required information. Relationship between General Contractor and Subcontractor Adverse Teamwork Force them to meet dates in schedule

Required in Specifications Examples The Contractor shall utilize the CPM Progress Schedule in planning, scheduling, coordinating and performing the work under the contract including all activities of trade contractors, equipment vendors, and suppliers. All procurement, manufacture, and delivery activities for all major materials and equipment shall be identified; major means: either a specification section is dedicated to the material or equipment or a dollar value greater than $5,000.00 is associated with an item which is a component of a specification section

Required in Specifications Examples Assignment and coding of all activities by the performing entity such as Subcontractors, Vendors, and the Owner, shall be included. Certification: Submit certification that identifies each subcontractor and major equipment supplier and which confirms that each has participated in, reviewed, and concurs with the CPM Progress Schedule and the associated cost data as it relates to their work. Submit these certifications at the same time that the CPM Progress Schedule is initially submitted.

RACS Schedule Advantages Measures Necessary Manpower Request more detail to understand subcontractors work scope and schedule Measures Required Work in Place WIP Both Items are more easily tracked and measured 5

RACS Example Electrical Subcontract Total: = $1,000,000 ** Determined from Bill or from Labor % Hourly Rate for a Worker: = $ 40/hr Value of Labor in the Contract**: = $ 400,000 Length of Project: = 2 months (or 40 WD) Based What is the number of workers that are needed on the job every day to maintain schedule?? Advanced Scheduling and Measuring Productivity Workshop 6

RACS Example $400,000 (Labor) / $ 40/hr = 10,000 hours to complete job 10,000 hours / 8 hours per day = 1250 man-days 1250 man-days / 40 work days = 31.25 Workers So..if you do not have a commitment from the sub to have at least workers on the job, or if the sub doesn t deliver 31 workers every day, you will fall behind. Better to know this before you award, or you will have a problem!! 7

To get paid monthly Percent Complete Tracking Progress on a Job Why? Know completion date Compare Planned vs. Actual Check productivity- Earned Value

Earned Value A common question- What is the stage of completion of the project? Or What is the physical percent complete of the project?

Understanding Earned Value Integration of Cost and Schedule Cost Loading From End Loading for Payment What is the stage of completion of the project? What is the basis of that assessment? Some say cost I say no way, WHY? Earning whatever was budgeted

Earned Value It is critical to have an appropriate way to physically progress the work activity. Installed quantity report. On specific work activities which relate to overall project completion. Will it require two systems? Yes- Time & Money Proper tracking of the system for progress reporting.

The Concept of Earned Value Actual Percent Complete times Total Project Revenue. What Owners want to know. Actual percent complete is the key. Earned man-hours not actual man-hours. How do you properly progress the job. Getting percent complete from your schedule.

Work-in-Place How do I know what percent complete I am? Activity with ten days duration At 50 percent complete? Answer A. Five Days B. Not enough information

Example Pour Concrete Walls- 10 Days Pour concrete walls- 100 cubic yards Total budget 1000 man-hours Actual hours to date 500 man-hours Actual poured 40 cubic yards 40% complete 50% of man hours used

What is the common denominator? Days Man-hours Dollars Quantities

Work-in-Place Installed Quantities The difference between earning and burning I need to find the actual percent complete. How do I do that? Many owners think cost. It comes from work-in-place.

Earned Value How do I know what percent complete is the activity- cable tray? Quantities for each activity lead to man-hours earned. Man-hours common among all activities This is a minor issue not very well understood in the industry.

The Field System for Tracking Estimate Quantity Take-Offs Budget Conversion/Control Budget Quantity Tracking- Installed Quantities Earned Value Determine Progress Calculate Productivity Forecast Man-hours and Completion

Difficulties in assessing progress Work in Place Based on Cost Issues with what part of cost Actual Percent Complete Thumb nail Visual Actual Work in Place

Project Monitoring & Control Establishing a Baseline Difficulties in assessing progress Understanding Earned Value Updating the Schedule Time in Contract Provisions

Plan vs. Actual Master Baseline Schedule In order to be meaningful, there has to be a baseline schedule to compare against in order to determine the status of the project. Baseline normally cannot change without approval Nothing says you can have different baselines for review but may not be approved by Owner Purpose of Updating the master schedule Evaluate Project Status Predict Completion Date Create a historical record Evaluate Change

% Complete Float is his life A line from a professional scheduler. Working with items with float Free Float- The amount of time an activity can be delayed without delaying the start of another activity. The use of Early and Late Start Curves and Schedules 100 90 80 70 60 50 40 30 20 10 0 Project Progress Curve 1 2 3 4 5 6 7 8 9 10 11 12 Time

Free Float Free float is the amount of time an activity can be delayed without taking away float from later activities. Used in the evaluation of float ownership amongst activities. It is a analysis provided in schedule analysis beyond the scope of calculating the Critical Path.

Float : Early & Late Schedules Early Schedule A C D Float B E Float A C D Late Schedule E B SK.04-53 Copyright 2001 - AACE International

% Complete Float : Early & Late Schedules Project Progress Curve 100 90 80 70 60 50 40 30 20 10 0 Early Schedule Late Schedule 1 2 3 4 5 6 7 8 9 10 11 12 Time SK.04-54 Copyright 2001 - AACE International

Progress Curves In management reporting the most looked at document is the percent complete curve. Comparison of planned versus actual. Percent Complete Planned vs. Actual Man-hours Dollars

Progress curve From the baseline schedule a planned curve can be drawn based on percent complete and calendar time. Tracking actual progress against plan can identify trends, issues and opportunities The steepness of the curve, the evaluation of actual work in place for each work evaluating trends. Front end loading, normal loading and back loaded schedules. Early Finish or late finish curve.

Planned Vs. Actual

Baseline and Updating Planned vs. Actual Develop baseline schedule Contract requirements Lock and load and start construction Each actual start, finish and percent complete at that reporting period. Changing the baseline Playing with the curves

Early and Late Start Curves

Tracking planned Vs. Actual

To 100 Percent Complete

What does this mean?

Playing with the numbers

Use of Project Cost/Value Information in Relation to the Project Schedule Cash Flow Projections Progress Payment Schedule Working Capital Projection Progress Measurement Can utilize the progress measurement overall to tie-in work in place.

Cost Planning/Scheduling Cost is the common yardstick that is used to measure the expenditure of resources on a project. Assigning costs to individual activities in a network schedule is commonly referred as cost loading, value loading or dollar loading. Activity cost vs. value (revenue). Difficult to tie the estimate, cost code structure and schedule activity structure. One main reason is the different level of detail and the ability to track costs accurately.