Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:



Similar documents
An introduction to Earned Value Analysis

Accounting System. Page 1 of 9

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Tracking Budgets and Schedules

Appendix D Glossary Of Terms

Basic Concepts of Earned Value Management (EVM)

Introduction to earn value management in Civil Engineering

Application of Earned Value Management System on an Infrastructure Project: A Malaysian Case Study

Using Earned Value Management for Improving Processes. By Cynthia K. West

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:

Government Contracting and Earned Value Management (EVM)

Earned Value Management Guidelines

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS

Earned Value Management and Professional Services Automation

Agile Project Management Controls

Training Seminars. Description. Core Courses: The core courses consist of the following:

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction

FOREWORD. Page 2 of 88

Program and Project Management Practices in the Federal Civilian Agencies

Earned Value Management System Description

THE PROJECT MANAGEMENT KNOWLEDGE AREAS

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

Chapter 7. (PMBOK Guide)

USFWC Project Management Workshop May 31 st, 2014

How To Manage A Project

Basics of Cost and Schedule Control

IT Baseline Management Policy. Table of Contents

Using Earned Value Management Concepts to Improve Commercial Project Performance

The Program Managers Guide to the Integrated Baseline Review Process

AACE International Recommended Practice No. 86R 14

PROJECTS SCHEDULING AND COST CONTROLS

Module 5 Cost Management PMP Exam Questions

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

July 6, (1) CHAPTER 11

Estimating Cost at Completion - Judgment & EV Information

INSE 6230 Total Quality Project Management

Chapter 7: Project Cost Management. Munawar

SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT

The Two Most Useful Earned Value Metrics: the CPI and the TCPI

L10: Budgeting and Cost Control. Olivier de Weck

Expert Reference Series of White Papers. Importance of Schedule and Cost Control

What is the Health of my Project?

Project Management System Description (PMSD)

700 Analysis and Reporting

Young Hoon Kwak Associate Professor School of Business The George Washington University

Brainstorm. What is Cost and Project Cost Management?

Earned Value Management Systems Application Guide

Project Cost Management

Developing Work Breakdown Structures

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

Services Contracts and Earned Value Management (EVM)

Since 1985, the Test Program Set (TPS) development

A collection of Safran Project report samples for project professionals

PROJECT COST MANAGEMENT

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP

Earned Value and Agile Reporting

Earned Value Management Best Practices

IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN?

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2007 management for development series The Project Management Processes PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

Agile and Earned Value. A white paper. October Author Stephen Jones, Sellafield Ltd

PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP

QUALITY AND PERFORMANCE IN PROJECTS. Project Management and Leadership 2015D, PhD, PMP

What is Costrac? Approval of Budget against WBS. Feasibility Study Completed. Define & Map WBS. Approval of WBS. Estimate

Earned Schedule Leads to Improved Forecasting

Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. wit.vaishnavi@gmail.com

How To Write Ansi/Eia Evm System Acceptanceance Guide

Project Management Guidebook

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

Earned Value Management Systems Application Guide

Interpreting the Management Process in IEEE/EIA with the Help of PMBOK

Office of Budget and Financial Planning

A Framework for Project Metrics

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

PROJECT COST MANAGEMENT

Assessing Schedule Performance with Earned Value

BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant

Chapter 5: Project Cost Management

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH

Schedule Adherence a useful measure for project management

LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION

Schedule Analysis Using Earned Value Concepts ABSTRACT

Predicting progress on your project

How to successfully manage your mega-project

Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria

Project Management. Training Courses

This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.

Certification Exam Objectives: PK0-003

300 Scheduling and Budgeting

ITRM Guideline CPM Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

PMO Metrics Recommendations

Transcription:

Earned Value Management Tutorial Module 1: Introduction to Earned Value Management Prepared by:

Module1: Introduction to Earned Value Welcome to Module 1. The objective of this module is to introduce you to Earned Value and lay the blueprint for the succeeding modules. This module will include the following topics: Earned Value Management defined The differences between Traditional Management and Earned Value Management How Earned Value Management fits into a Program and Project environment The framework necessary for proper Earned Value implementation Module 1 - Introduction 1

What is Earned Value Management? Earned Value Management (EVM) is a systematic approach to the integration and measurement of cost, schedule, and technical (scope) accomplishments on a project or task. It provides both the government and contractors the ability to examine detailed schedule information, critical program and technical milestones, and cost data. Earned Value Management is intended to provide data from a contractor s management system to the government in standard data elements that Relate time-phased budgets to contract tasks Integrate cost, schedule, and technical performance Indicate work progress objectively Are valid, timely and auditable Are from the internal system the contractor uses to manage Are at a practical level of summarization Module 1 - Introduction 2

Why use Earned Value Management? By using Earned Value and implementing an Earned Value Management System (EVMS), the following questions can be answered objectively: Where have we been? Where are we now? Where are we going? Why use Earned Value? For one, it is mandated by some key DOE directives and guidance that Earned Value will be implemented. The following pages will discuss these. Module 1 - Introduction 3

DOE guidance for Earned Value A memorandum from the Deputy Secretary of Energy, dated September 19, 2001. I intend to continue the direction contained in DOE Order 413.3. The responsibilities contained in the Order require that you know what is going on with your projects and that you assist your program managers and project managers in resolving issues and problems. The quarterly performance reviews, monthly status updates utilizing the Earned Value Management System as a metric, and periodic independent reviews are all sources for project information that allow us the opportunity to intercede before projects get off track. Now let s look at the DOE Order 413.3 Module 1 - Introduction 4

DOE guidance for Earned Value Current Department of Energy policy, DOE Order 413.3, Program and Project Management for the Acquisition of Capital Assets, states the requirements for contractor s project management system The industry standard for project control systems described in American National Standards Institute (ANSI) EIA-748, Earned Value Management Systems, must be implemented on all projects with a total project cost (TPC) greater than $20M for control of project performance during the project execution phase. Finally, below let s look at some Best Practice guidance currently in the DOE. The Office of Field Management has issued a series of 33 Good Practice Guides. Though they are not official guidance, each guide describes the good practices used throughout DOE and industry for specific topic including Earned Value Management, and provides examples of performance objectives, criteria, and measures. Module 1 - Introduction 5

Earned Value Management History With the understanding of what Earned Value is and why it used, let s take a brief look at the history of Earned Value. 1960s - Earned value-based performance management began in the 60s, based initially on Department of Defense (DOD) Cost/Schedule Control Systems Criteria (C/SCSC). Earned Value was used as an objective measure for progress, i.e., physical accomplishment 1970s-80s The DOD continued the use of Earned Value in response to bearing cost and schedule risk in cost-plus contracting. Contractors pushing high tech, newly developed weaponry Military having critical schedule needs ( Arms Race ) 1990s Policy moved Earned Value into all Federal agencies OMB Circular: A-11, NASA Policy Directive 9501.3, DOD 5000.2R, and DOE Order 413.3 to name a few Module 1 - Introduction 6

Traditional Management vs. Earned Value Management To better understand Earned Value Management, let s take a look at how earned value management compares with traditional management. There is an important and fundamental difference between the data available for analysis in a traditional management environment as compared to an environment using earned value. Following pages will discuss and contrast the difference between the two management approaches. Module 1 - Introduction 7

Traditional Management In Traditional management, there are two data sources, the budget (or planned) expenditures and the actual expenditures. The comparison of budget versus actual expenditures merely indicates what was planned to be spent versus what was actually spent at any given time. But how much has been produced? As you can see, with this approach there in no way to determine the physical amount of work performed. It does not indicate anything about what has actually been produced for the amount of money spent nor whether it is being produced at the rate, or according to the schedule, originally planned. In other words, it does not relate the true cost performance of the project. As the graph shows, this comparison only represents the relationship of what was budgeted (planned) versus what was actually spent. 70 60 50 40 30 20 10 0 J F M A M J J A S O N D Budget 5 10 15 20 25 30 35 40 45 50 55 60 Actuals 10 20 30 40 50 60 Time Now Module 1 - Introduction 8

Earned Value Management In Earned Value Management, unlike in traditional management, there are three data sources: the budget (or planned) value of work scheduled the actual value of work completed the earned value of the physical work completed Earned Value takes these three data sources and is able to compare the budgeted value of work scheduled with the earned value of physical work completed and the actual value of work completed. Let s take a closer look at how earned value appears in a graph. Module 1 - Introduction 9

Earned Value Management Notice the three lines on the graph below. These lines correspond to the three components of earned value: budget (in red), actual expenditures (in blue), and the earned value of the production (in black). Note how the budget line is below both the actual expenditures and the earned value lines. What does this indicate? First, it is obvious that the project is expending more (blue line) than it was budgeted to spend, to date 150 (red line). Given the progression of each line, it is also apparent that this trend has occurred since the beginning of the 125 100 75 50 25 Time Now 0 project. J F M A M J J A S O N D Budget 5 10 15 20 25 30 35 40 45 50 55 60 But what else can be Actuals 10 20 30 40 50 60 interpreted from the Earned 8 15 25 30 35 45 Forecast 70 80 90 100 110 120 graph? Let s take a closer look on the next page. Module 1 - Introduction 10

Earned Value Management In addition to tracking budget and actual expenditures, the graph indicates what has been completed or earned. By comparing the budget line (in red) to the earned value line (in black), it is immediately apparent that the project is producing more than it was budgeted to produce to date. Additionally, by comparing the actual expenditures (in blue) to the earned value line (in black), it is immediately apparent that the project is spending more then it was budget to date. So while the project is expending more (blue line) than budgeted (red line), it is also producing more (black line) than budgeted. So what conclusions can be drawn from this graph? Let s find out on the next 150 page. 125 100 75 50 25 Time Now 0 J F M A M J J A S O N D Budget 5 10 15 20 25 30 35 40 45 50 55 60 Actuals 10 20 30 40 50 60 Earned 8 15 25 30 35 45 Forecast 70 80 90 100 110 120 Module 1 - Introduction 11

Earned Value Management There are two conclusions the earned value data will immediately let you make; they deal with schedule and cost variances. Schedule Variance - the project is experiencing a schedule variance of 15. This is derived from comparing the Earned (45) to the Budget (30). Another way of stating this is that the project is ahead of schedule in comparison to what was supposed to be done in the frame time measured. 150 125 100 75 50 25 Time Now 0 J F M A M J J A S O N D Budget 5 10 15 20 25 30 35 40 45 50 55 60 Actuals 10 20 30 40 50 60 Earned 8 15 25 30 35 45 Forecast 70 80 90 100 110 120 Module 1 - Introduction 12

Earned Value Management Cost Variance - the project is experiencing a cost variance of -15. This is derived from comparing the Earned (45) to the Actual expenditures (60). Another way of stating is that the project is experiencing an overrun of 15. This cost variance is very important because history tells us that overruns in cost do not correct themselves and need management intervention. Along with the schedule and cost results discussed, earned value management enables you to forecast the final results of the project (blue dashed line). 150 125 100 75 50 25 Time Now 0 J F M A M J J A S O N D Budget 5 10 15 20 25 30 35 40 45 50 55 60 Actuals 10 20 30 40 50 60 Earned 8 15 25 30 35 45 Forecast 70 80 90 100 110 120 Module 1 - Introduction 13

Summarizing Traditional Management vs. Earned Value Management In summarizing, Traditional management provides you with How much money and time a particular job is likely to require prior to starting and once started, how much money was spent at any given time. While Earned Value Management provides you with How much money and time a particular job is likely to require prior to starting and once started, how much money was spent at any given time. Plus Once started, what work has been accomplished to date for the funds expended (what you got for what you spent) Once started, what the total job will cost at completion, and how long it will take to complete Module 1 - Introduction 14

Earned Value in a Management Environment Understanding how Earned Value fits into the program and project management environment is also essential. On the following page we will discuss and define items such as project vs. program, project management, program management and the relationship between them. Module 1 - Introduction 15

What is Program/Project Management? Program/Project Management is the application of knowledge, skills, tools, and techniques to meet or exceed stakeholder needs and expectations. Program/Project Management requires the ability to get the job done: On Time! Within Budget! According to Specifications! With a High Level of Customer Satisfaction Scope The first three (3) requirements are known as the Triple Constraint So how do projects and programs differ? Take a look on the next page. Quality Time Cost/Resources Module 1 - Introduction 16

What is a Project vs. Program The Characteristics of a Project are: Temporary endeavor undertaken to create a unique product or service Having a definite beginning and a definite end The Characteristics of a Program are: A group of projects Managed in a corresponding way To obtain benefits not available from managing them individually Module 1 - Introduction 17

Earned Value Management vs Program/Project Management Earned Value is a Program/Project management technique used to objectively evaluate cost and schedule efficiency, thereby facilitating better management of customer needs and expectations. Earned Value Management is a subset of Program/Project Management. As this hierarchy indicates, Earned Value Management is a component of Project Management, which in turn is a component of Program Management. While many components comprise Program and Project Management, this tutorial focuses on the Earned Value Management component. Program Management Project Management Budgeting Cost Proposals/Negotiations Cost Collection Change Control Earned Value Management Forecasting Funding Resource Management Reporting Risk Management Scheduling Module 1 - Introduction 18

Framework for an Earned Value Management System (EVMS) So far, we have discussed what Earned Value is, why to use it, and how it fits into a program and project management environment. Next, we need to discuss the framework needed to implement earned value. The EVMS framework can be divided into three phases: 1. Inputs - what is needed to implement Earned Value 2. Earned Value Methods formulas, metrics and performance measurements used 3. Outputs reporting requirements (structure, time-phases, details) On the following pages these three phases for developing an Earned Value Management System (EVMS) will be discussed in more detail. Module 1 - Introduction 19

Inputs needed for Earned Value Management System (EVMS) As you recall, the first phase of Earned Value is inputs. The inputs required for an EVMS include: Work Breakdown Structure (WBS) Organizational Breakdown Structure (OBS) Project Schedule Time-phased Baseline Budget Cost/Resource Control Plan Change Control Plan These Items are covered in Modules 2 through 4 and Module 8 WBS/OBS Project Schedule Resource Planning Define/Assign Schedule/Budget Establish Baseline Accounting System Earned Value Management System If any of these items are not completed or are not completed appropriately, the use of Earned Value will be compromised and your outputs will not properly represent the program/project current and future status. Plan Actuals $$$ Funding Performance Measurement Early Warning & Detection Informed Management Decisions Corrective Actions Recovering Planning Module 1 - Introduction 20

Earned Value Method needed for Earned Value Management System (EVMS) The second phase of Earned Value is the earned value method. The Earned Value method required for an EVMS include: Planned Value (PV), Earned Value (EV) Actual Cost (AC) Metrics and Performance Measurements Forecasting Integrated Baseline Review These Items are covered in Modules 5 through 7 WBS/OBS Project Schedule Resource Planning Define/Assign Schedule/Budget Establish Baseline Accounting System Earned Value Management System Once again, if any of these items are not completed or are not completed appropriately, the use of Earned Value will be compromised and your outputs will not properly represent the program/project current and future status. Plan Actuals $$$ Funding Performance Measurement Early Warning & Detection Informed Management Decisions Corrective Actions Recovering Planning Module 1 - Introduction 21

Outputs needed for Earned Value Management System (EVMS) The last phase of Earned Value is the outputs. The outputs required for an EVMS include: Reporting requirements Proper Analysis of Reports Correct Action taken These Items are covered in Modules 7 & 8. WBS/OBS Project Schedule Resource Planning Define/Assign Schedule/Budget Establish Baseline Accounting System Earned Value Management System Even if the first two phases are completed appropriately, improper analysis of the outputs could cause inappropriate or inadequate actions to be taken against the program/project and could either create problems that otherwise would not exist or fail to fix the real problem that does exist. Plan Actuals $$$ Funding Performance Measurement Early Warning & Detection Informed Management Decisions Corrective Actions Recovering Planning Module 1 - Introduction 22

Review of Module 1 You cannot manage what you cannot measure and what gets measured gets done. --- Bill Hewlett, Hewlett Packard Reviewing the major items of this module: Earned Value Management (EVM) is a systematic approach to the integration and measurement of cost, schedule, and technical (scope) accomplishments on a project or task DOE Order 413.3 is the approved policy In comparing Earned Value Management to Traditional Management, Traditional Management does not allow for analysis of the physical amount of work performed. Earned Value Management allows for both schedule and cost analysis against physical amount of work performed Earned Value Management is a subset of Program/Project Management EVMS can be divided into three phases (Inputs, Earned Value method, outputs) and all three must be completed appropriately for proper management of the program/project Module 1 - Introduction 23

Summary of Module 1 At this point, we have examined the basics of earned value. As explored previously, the following modules address in depth the components that comprise earned value to help you incorporate earned value into your projects. If you have a firm grasp of the concepts covered in this module, you are ready to progress to the next modules. Otherwise, review this module again to ensure you have a solid understanding of the basics of the Earned Value Management System. This concludes Module 1. Module 1 - Introduction 24